Documente Academic
Documente Profesional
Documente Cultură
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
Controlling
Document
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
Acceptance
Criteria
Frequency
QC Approval
ADPC submittal
review code 1 or
code 2
Prior to start
the work on
site
Approved ADPC
review sheet
with code 1 or
code 2
QC Approval
ADPC submittal
review code 1 or
code 2
Prior to start
the work on
site
Approved shop
drawing
QC Approval
Prior to start
the work on
site
IFC drawing
QC Approval
ADPC submittal
review code 1 or
code 2
Prior to start
the work on
site
Approved Material
Inspection
Request
Approved test
report
Method Statement
1.02
Shop Drawing
1.03
Notice of operation
1.04
Exhibit D part
1 Appendix
1 Specific
Constructio
n
Requiremen
ts, rev E
ADM
Standards,
section 11
clause
200.06h
ADM
standards
section 1-2,
clause
102.08
Exhibit D
Scope of
works
Technical
Specificatio
n Clause
2.1.3
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
S - Surveillance
R Record Review
Ite
m
No.
1.05
Prior to start
the activity
1.06
ADM
Visual Inspection
Standards
Section II-5
clause
205.04
Every
excavation of
existing
utilities
2.01
2.01.
1
2.01.
2
Controlling
Document
ITP No.
Rev. No
Date:
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
Acceptance
Criteria
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
Frequency
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
Field Survey Data
and Report
(FM-260-ATTACH
01)
(FM-260-ATTACH
02)
(FM-260-ATTACH
03)
(FM-260-ATTACH
04)
FM-260-V8-003
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
R/S
R/S
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
2.01.
3
2.01.
4
2.01.
5
2.01.
6
2.01.
7
Liquid Limit
2.01.
8
2.01.
9
Chloride content
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Controlling
Document
Acceptance
Criteria
earthworks
and filling
clause 4.2
AASHTO T-89 Max 40%
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
1 sample every
3000m3
1 sample every
3000m3
1 sample every
3000m3
1 sample every
3000m3
1 sample every
3000m3
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
test
test
Test
Test
Test
Less than 5%
Less than 5%
Frequency
1001-260-V8-0000-00136
006
As determined by
testing
Minimum 15%
Less than 2%
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
Approved
Report
Approved
Report
Approved
report
Approved
report
Approved
report
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
2.01.
10
Fabric Weight
Tensile Strength
Elongation
Puncture Strength
Burst Strength
Tear Strength
Permeability
Flow Rate
Strength Retention
Controlling
Document
ITP No.
Rev. No
Date:
Specificatio
n Clause 4.2
ADM
Standards
Section II-7
clause
207.05
TYPE 1
TYPE 2
100gm/m2 /
ASTM D 1910
135gm/m2
ASTM D 1682 560N
900N
ASTM D 1682
20%
ASTM D 751
20%
ASTM D 3786 200N
600N
ASTM D 1117
AASHTO M
288
AASHTO M
288
ASTM D 1682
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
Approved Test
report
Approved Test
report
S - Surveillance
R Record Review
Acceptance
Criteria
860KPA /
2200KPA
80N
225N
0.01cm/sec / .
01cm/sec
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
1001-260-V8-0000-00136
006
Frequency
First delivery of
each supplier
First delivery of
each supplier
First delivery of
each supplier
First delivery of
each supplier
First delivery of
each supplier
First delivery of
each supplier
First delivery of
each supplier
Approved Test
report
Approved Test
report
Approved Test
report
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Controlling
Document
Acceptance
Criteria
Frequency
2.01.
11
Check suitability of
Capillary break material
Soundness (Sodium)
Soundness (Magnesium)
Sand Equivalent
Liquid Limit
Plasticity Index
Sulphate Content
Chloride Content
Flakiness Index
Elongation
ADM
Standards
section III-2
clause
302.02
AASHTO T96
(ASTM
C131)
AASHTO
T104
AASHTO
T140 (ASTM
C88)
AASHTO
T176 (ASTM
D-2419)
AASHTO T89
(ASTM
D4318)
AASHTO T90
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
12% MAX
15% MAX
25% MINI.
35% MAX.
6.0% MAX.
0.50% MAX
1.0% MAX
35% MAX.
35% MAX.
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
Approved Test
report
40 MAX
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
Approved Test
report
25l/s/m2. /
25l/s/m2.
560N
900N
1001-260-V8-0000-00136
006
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
Approved test
report
Approved test
report
Approved test
report
Approved test
report
Approved test
report
Approved test
report
Approved test
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
Specific Gravity
S - Surveillance
R Record Review
Controlling
Document
Acceptance
Criteria
2.20 MIN.
(ASTM D
4318)
B.S 1377
B.S 812
65% Min.
B.S 812
Sieve size analysis
100mm
75mm
50mm (2)
25mm (1)
12.5mm (1/2)
9.5mm (3/8)
% Passing
B.S 812
100
AASHTO
T100 & T85
AASHTO
T180D
AASHTO
T193 (ASTM
D1883)
75 to 100
As per CTI
1001-260V9-000000010
ITP No.
Rev. No
Date:
25 to 75
10 to 50
5 to 20
0 to 3
Frequency
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1 test every
1000m3
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
report
Approved test
report
Approved test
report
Approved test
report
Approved test
report
Approved test
report
Approved test
report
Approved test
report
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
Approved test
report
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
Controlling
Document
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Acceptance
Criteria
Frequency
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
Approved test
report
Approved test
report
Approved test
report
Approved test
report
Construction Phase
ADM
Removal of all dead Prior to start
Inspection
standards
trees, brush or other
next activity
checklist
section II-3
objectionable
of each area. (FM-260-V8-001)
clause
vegetation.
(FM-260-V8-002)
All stumps roots or
203.05
(FM-260-V8-003)
AASHTO Tmats shall be
193
removed to a depth
not less than 90cm
below Subgrade.
All depressions
formed by removal
of stump roots shall
be refilled with
approved borrow
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
Controlling
Document
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Acceptance
Criteria
Frequency
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
material.
3.01. Check existing Subgrade material
2
and removal of unsuitable
ADM
material
standards
CBR @ 95% MDD
Section II,
clause
206.05
ADM
Standards
Section II
clause
207.04
W/
R
W/R
S/R
ADM
The level and
From the start Field survey
standards
alignment shall be
of the
request data.
section II-3
in accordance to IFC
activity
(FM-260-ATTACH
clause
drawing.
01)
203.03
(FM-260-ATTACH
02)
(FM-260-ATTACH
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
Layer Thickness
Controlling
Document
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Acceptance
Criteria
Frequency
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
03)
(FM-260-ATTACH
04)
ADM
Minimum of 95% MDD First layer of fill Approved test
standards
before
report
section II-6
commencem
clause
ent of main
206.02d.
filling works
ADM
standards
section II-6
clause
206.02b
ADM
standards
section II-6
clause
206.02c.
To be cut and
Prior to filling Approved test
scarified according
of first layer
report
FM-260-V8-003
to IFC drawing
Maximum15cm of
Every layer of
Survey report
compacted depth
filling
(FM-260-ATTACH
(10cm max depth
01)
in inaccessible
(FM-260-ATTACH
areas.)
02)
(FM-260-ATTACH
03)
1 per 1500m2
(FM-260-ATTACH
Minimum 95%
04)
FM-260-V8-003
Approved test
Exhibit D, part
report
2 att.C
FM-260-V8-003
particular
specs
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
1 per 750m2
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
W/
R
W/R
W/
R
W/R
S/R
W/
R
W/R
W/
W/R
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
3.01.
6
Controlling
Document
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Acceptance
Criteria
Frequency
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
1 test every
Approved test
100 LM run
report
or 1000m2
FM-260-V8-003
whichever is
less
W/
R
Approved test
report
FM-260-V8-003
H
Inspection
Free from cuts and
Every laying
Checklist
damage
for Geotextile
(FM-260-V8 Shall be laid loosely
020)
parallel to the
centerline with a
minimum of 300mm
Every laying
overlap.
Laying of Geogrid material (S30 or
for Geogrid
Free
from
cuts
and
similar equivalent)
Inspection
damage
CTI no.: 1001Checklist
Shall
be
laid
on
the
260-V9(FM-260-V8top
of
capillary
0000-00005
ADM
Standards
Section II
clause
207.05
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
S/R
W/
R
S/R
W/
R
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
Layer Thickness
Compaction Degree
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Controlling
Document
Acceptance
Criteria
Frequency
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
Approved survey
report
(FM-260-ATTACH
01)
(FM-260-ATTACH
02)
(FM-260-ATTACH
03)
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
W/
R
S/R
W/
R
W/R
W/
R
S/R
R Review
Record/ Documents review
Khalifa Port
Abu Dhabi Ports Co. ADPC
1001-260
Nature of Inspection
H Hold Point
W Witness Point
Ite
m
No.
ITP No.
Rev. No
Date:
S - Surveillance
R Record Review
Controlling
Document
Acceptance
Criteria
cross-sections of the
road
shall
not
exceed 0.4 percent.
Frequency
1001-260-V8-0000-00136
006
Inspection Authority
1 Supervisor
2 QC /QA
Form of
Record /
1
Verification
Document
3 - PMC
4 Third Party
Inspection
Remarks
2
3
4
(FM-260-ATTACH
04)
Levels
of
the
finished
surface
shall not vary by
more than 2cm.
4.01
4.02
ADM
According to all IFC
specification
drawing
section 1-1
clause
101.03
As per
According to all ITP
required
test required
according to
the test on
ITP
H Hold Point
Written notification required. Contractor may not
proceed beyond this point without written confirmation
of the Employer
W Witness Point
Written notification required but
contractor may proceed if Employers
representatives do not attend.
S Surveillance
No notification required but activity may
be subjected to Employer surveillance/
monitoring
R Review
Record/ Documents review