FACULTY OF CIVIL ENGINEERING

ECM442:CIVIL ENGINEERING QUANTITIES


LECTURER : PUAN SAFARINA HASLIMAWATY
PREPARED BY:
1
2
3
3
4

MMOHD SYAFIQ FIRDAUS BIN ZOLKEFLI


MUHAMMAD ZULFAQUR BIN ABD MANAB
MOHD NOR AIZAT BIN NOR AZIZI
MUHAMAD ASYRAF BIN ROSLAN
MOHD FAWWAZ BIN MD ISA

GROUP : EC 220 6G
DATE SUBMISSION : 20TH DECEMBER 2013

2012848708
2012830462
2012629288
2012237356
2012417714

CADANGAN MENDIRIKAN 5 UNIT RUMAH TERES SETINGKAT DIATAS


TANAH LOT NO.
5237 (GM 2668), 8439(GM4204) & 8440(GM4205)
TEMPAT : GUAR GAJAH , MUKIM ARAU, PERLIS INDERA KAYANGAN

COMPANYS NAME :

PUNCAK BINA SDN. BHD

NO. 1, LORONG LIMA, TAMAN UTARA JAYA KUALA PERLIS,


02000 KUALA PERLIS, PERLIS

OWNERSS NAME : MAJU MERCU SDN. BHD


433569-D, LANGRAJAWALI 4, TAMAN DATO JAAFAR, 01000
KANGAR, PERLIS

TABLE OF CONTENT

TITLE
INTRODUCTION
OBJECTIVE
WORK PROGRESS
TAKING OFF
BILL OF QUANTITY
CONCLUSION
APPENDICES
BUKU KADAR HARGA JKR

INTRODUCTION
Civil Engineering Quantities (ECM442) is one of the main subjects in civil
engineering courses. We need to look for architectural and engineering (detailing)
drawings for a single storey building. Therefore, we have chosen a single storey
terrace house in Perlis as our project plan. There are two main aspects need to be
prepared for this project, that is taking off and bill of quantities.

The works that need to be undertaken are excavation, filling, lean concrete,
concrete, reinforcement and formwork. Besides, we also must calculate the works
for basic structure of this project such as foundation, beam, slab and column.
Taking off must be prepared as measuring from drawings and recording all
dimensions in recognized form. After that, preparation bill of quantities need to be
prepared according to the items by stating the quantities and brief descriptions of
work to be carried out with it respective quantities and unit cost of the building.
Objectives of Bill of Quantities
The objectives of Bill of Quantities are to:
a)

Provide sufficient information on the quantities of Works to be

performed to enable
bids to be prepared efficiently and accurately.
b)

Facilitate the comparison of rates and prices between bidders.

c)

Provide priced Bill of quantities for use in the periodic variation of

Works executed.
d)

Provide rates and prices which can be used in the variation of

additional works
instructed by the Clients.
e)

Enable the Clients to assemble actual tendered rates and prices to

prepare for future


estimating and budgeting.

TASK
For this session, each group will discuss about:

A Client has appointed your company to estimate and evaluate the


total cost of construction project. As a civil engineer, you requested
to prepare a complete set of "bill of quantities for civil work
according to Standard Building Method of Measurement. The works
are listed below:

Excavation
Filling
Lean concrete ( thickness of lean concrete at 50mm)
Concrete
Reinforcement
Formwork

You are required to calculate the works for basic structure of this
showroom such as:

Foundation
Beam
Slab
Column

SECTION A: LIST OF PRINCIPLE QUANTITIES

The list of principal quantities being the main components of the works, with their
approximate estimated quantities, so that tenderers obtain an overall picture of the
general scale and character of the proposed works at the outset.
A list of principal quantities relating to a reservoir as follows:
NO.
1

TASK
GENERAL ITEMS
Provisional Sums
Prime Cost Items

FOUNDATION
Excavation
Concrete
Formwork
Steel Reinforcement

COLUMN
Concrete
Formwork
Steel Reinforcement

BEAM
Concrete
Formwork
Steel Reinforcement

SLAB
Concrete
Steel Reinforcement

COST

SECTION B: PREAMBLES
The preamble in a civil engineering bill of quantities is to indicate to tendering
contractors whether methods measurement other than the CESMM have been used
for any part of works and whether any modification have been made in applying the
CESMM to meet special needs where there are important practical reasons for
adopting a different procedure
a)

Taking Off
a list of materials with quantities and types (such as specific grades of steel) that are
required to build a designed structure or item. This list is generated by analysis of
a blueprint or other design document. The list of required material of construction is
sometimes referred to as the Material Take off List (MTOL).

b)

Bill of Quantities
Is a document used in tendering in the construction industry in which materials, parts,
and labour (and their costs) are itemized. It also (ideally) details the terms and conditions
of the construction or repair contract and itemises all work to enable a contractor to price
the work for which he or she is bidding.

c)

Foundation
The lowest and support layer of a structure. Foundations are generally divided into two
categories: shallow foundations and deep foundations

d)

Beam
A structural element that is capable of withstanding load primarily by resisting bending.
The bending force induced into the material of the beam as a result of the external loads,
own weight, span and external reactions to these loads is called a bending moment.

e)

Slab
A common structural element of modern buildings. Horizontal slabs of steel reinforced
concrete, typically between 100 and 500 millimeters thick, are most often used to
construct floors and ceilings, while thinner slabs are also used for exterior paving.

f)

Column
Is a structural element that transmits, through compression, the weight of the structure
above to other structural elements below. In other words, a column is a compression
member. The term column applies especially to a large round support with a capital and
base

g)

Excavation
Common excavation is the excavation of soil materials from within the
contract limits; however, this excavation is not limited to soil materials
and may include existing HMA pavement. This HMA pavement includes
HMA mixtures, crushed stone, bricks, cinders, etc. If the material is
indicated on the plans and is not a concrete pavement or another defined
excavation, then the material is considered common excavation.

h)

Concrete
Concrete is a composite material composed of coarse granular material
(the aggregate or filler) embedded in a hard matrix of material (the cement or binder)
that fills the space among the aggregate particles and glues them together.

i)

Lean Concrete
Lean concrete does not contain many of the high-density rock materials that regular
concrete does. Lean concrete often consists of reclaimed concrete materials, ash, and
discarded sand. It's a cheaper alternative to regular concrete.

j)

Formwork
Formwork is the term given to either temporary or permanent molds into which concrete or similar
materials are poured. In the context of concrete construction the falsework supports

NO

ELEMENT

UNIT

1.

Work
Excavation
Formwork
Concrete work
Reinforcement
Filling
Cost , Rate

m3
m2
m3
kg
m3
Ringgit Malaysia

Material
Cement
Aggregate
Water
Nails
Timber
Lean concrete

m3
m3
m3
kg
m2
m3

General
Density
Labour
Machinery
Site
Prime cost
Provisional sum

Kg/m3
No.
Per day
No.
Ringgit Malaysia
Ringgit Malaysia

2.

3.

UNIT OF MEASUREMENT

SECTION C: DAY WORK SCHDULE


General
The Daily Works Schedule shall be administered strictly in accordance with the
Conditions of Contract.
The Daily Works Schedule shall only be for labor, materials, and plant outside of or
in addition to the scope of the Works as required or reasonably implied by all
Contract Documents and will be as approved by the Department and the Engineer.
The Contractor will be paid for Daily Works Schedule Items carried out during the
course of the Contract at the rates tendered in this Schedule. Profit and overheads
are not to be included in the actual rates but stated as a percentage to be added at
the end of the Labour, Materials, and Plant Sections of this Schedule of Rates. Daily
Works Schedule Rates tendered by the Contractor will be carefully taken into
account at the time Tenders are being considered. The time engaged in the
authorized works will be certified and paid. In the event of labour or plant having to
be brought to the Site specially for an item of the Daily Works Schedule, then a
reasonable allowance will be made for travelling time. The allowance for travelling
time is to be agreed before the Daily Works Schedule Item is executed.
It is necessary to make provision for a daywork evaluation of work which cannot be
assessed at bill rates. CESMM provides three alternative procedures :

A list of the various classes of labor, material and plant for which daywork
rates or prices are to be inserted by the tenderer.

Provision for payment at the rates and prices and prices and percentage
variations contained in the current federation schedules of daywork.

The insertion of provisional sums in the bill of quantities for work executed on
a daywork basis comprising separate items for labor, materials, plants etc.

METHODOLOGY/PROCESS
ELEMENT
Foundations
Columns

Person in Charge
Mohd Fawwaz bin Md Isa
Muhammad Zulfaqur bin Abd

Beams

Manab
Muhammad Asyraf bin Roslan

Slabs

Mohd Syafiq Firdaus bin Zolkefli


Mohd Nor Aizat bin Nor Azizi

STANDARD

1. Civil Engineering Standard Method of Measurement (CESMM)

Used in conjunction with civil engineering works such as earthworks, roads,


bridges, structures, culverts, sewage etc. In addition, the quantities are
prepared by the civil engineers.

2. Standard Method of Measurement (SMM)

Used in conjunction with building work and quantities are prepared by


Quantity Surveyors.

3. Buku Kadar Harga JKR

DETAILS OF THE PROJECT


1. TITLE
5 units of single-storey terrace house
2. LOCATION
The proposed project is located Guar Gajah Arau, Perlis
3. LAND AREA
The land area of the project is in Arau, Perlis
4. ESTIMATED COST
The estimation cost for this project is RM55,000.00
5.

Authority Cooperated:

JABATAN KERJA RAYA


JABATAN PERANCANGAN BANGUNAN
JABATAN PENGALIRAN DAN SALIRAN

SCOPE OF WORKS
In this project, we only do the taking off and estimation cost for a single
house only. To accomplish this project, we have divided the works equally to the
team members so that the works can be done easily and efficiently without any
problems occurred. The team members and their division of works are :
Name
Muhammad Asyraf bin Roslan
Mohd Fawwaz bin Md Isa
Mohd Syafiq Firdaus bin Zolkefli
Muhammad Zulfaqur bin Abd Manab
Mohd Nor Aizat bin Nor Azizi

Scope of Work
Ground Beam & Estimation
Foundation and Estimation
Roof Beam and Estimation
Colum and Estimation
Slam and Estimation

SECTION D: WORK ITEMS

Taking off

FOUNDATION
No.

Dimension

Quantit

Description

Unit

y
Footing 1 (F1)
EXCAVATION WORK

15

15

15

15

15

0.60
0.60
0.75

a) Footing excavation
thickness = 1200 450 = 750
4.05

0.3
0.95

3.90

0.6
0.6

5.4

0.6
0.6
0.25
0.25
0.25
0.8

M3

b) Backfilling of soil
( 0.6 x 0.6 ) (0.25 x 0.25) = 0.30m2

M2

c) Lean concrete with thickness 50mm


M2

d) Concrete
i) concrete to pad footing
1.35
+
ii) concrete to column stump
0.75
2.10

M3

Footing 2 (F2)
EXCAVATION WORK

0.90
0.90
0.75

0.72
0.90

a) Footing excavation
thickness = 1200 450 = 750
4.86

M3
b) Backfilling of soil
( 0.9 x 0.9 ) (0.3 x 0.3) = 0.72m2

5.18

M3

c) Lean concrete with thickness 50mm


8

0.9
0.9

0.9
0.9
0.30
0.3
0.3
0.8

6.48

M2
d) Concrete
i) concrete to pad footing

1.94
+
ii) concrete to column stump
0.58
2.52

M3

Excavation of 150 mm top soil


from existing level

15

0.6
0.6

5.4

0.9
0.9

6.48

M2

11.88

M2

Excavation of trench depth


Not exceeding 1.5m
15

0.6
0.6
0.75

4.05

0.9
0.9
0.75

1200
0.150 - topsoil
1.05
0.05 + hardcore
1.10

4.86

8.91

M3

Excavation of trench depth


Exceeding 1.5m but not exceeding 3.0m
15

15

0.6
0.6
0.45

2.43

0.9
0.9
0.45

2.92

5.34

M3

CONCRETE WORK
Concrete grade 1:1.5:3 (G30)
-20 mm aggregate for footings

0.6
0.6
0.25

1.35

0.9
0.9
0.3

1.94

M3

3.29

M3
Concrete grade 1:1.5:3(G30)
-20 mm aggregate for stumps

15

0.15
0.15
0.5

0.17

Footing 1 (F1)
1.200
0.450 ground beam
0.750
0.250 footing
0.500

Footing 2 (F2)
1.200

M3

0.3
0.3
0.45

0.450 ground beam


0.750
0.300 footing
0.450
0.32
0.49

M3

FORMWORK
Rough surface for footings
15/
4

0.6
0.25

8/4

0.9
0.3

8.64

17.64

M2
Rough surface formwork
for side of stump

15/
4

0.75
0.15

6.75

0.75
0.3

7.2

13.95

M2

8/4

REINFORCEMENT
Reinforcement For Footing
Footing 600 x 600 x 250
Length of one steel bar

0.600
0.100 cover
0.500
0.066 + bends 5.5d @ 5.5/0.012
0.566 ~ 0.57
0.57

42.75

MR of T12 steel bar

15/
5

REINFORCEMENT
Reinforcement For Footing
Footing 900 x 900 x 300
Length of one steel bar
0.900
0.100 cover
0.800
0.066 + bends 5.5d @ 5.5/0.012
0.866 ~ 0.87
0.87

8/7

48.72

MR of T12 steel bar

Reinforcement for Stump


Stump 150 x 150
Length of one bar
1.250
0.050 cover
1.200
0.048 Less 4T12
1.152

0.066 + bend 5.5d (4T12)


1.218
0.48 + lapping 40d
1.698 ~ 1.700
1.700

102

MR of T12 steel bar

15/
4

Mild steel link for stump 150 x 150


Length of one link
0.150
0.100 cover 2/0.050
0.050
4/0.050 = 0.200
0.144 + hook 24d
0.344
Distance that require link
1.152
0.450 ground beam
0.702
No.of links = 0.702/0.125 + 1
= 6.62, say 7
0.34

35.7

MR of M6 link

Reinforcement for Stump


Stump 300 x 300

15/
7

Length of one bar


1.250
0.050 cover
1.200
0.048 Less 8T12
1.152
0.066 + bend 5.5d (8T12)
1.218
0.48 + lapping 40d
1.698 ~ 1.700
1.7

27.2

MR of T12 steel bar

2/8

Mild steel link for stump 300 x 300


Length of one link
0.300
0.100 cover 2/0.050
0.200
4/0.200 = 0.800
0.144 + hook 24d
0.944
Distance that require link
1.152
0.450 ground beam
0.702
No.of links = 0.702/0.125 + 1
= 6.62, say 7

0.944

52.86

MR of M6 link

8/7

COLUMN

No.

Dimension

Quantit
y

Description

Unit

COLUMN

CONCRETE WORK
Concrete grade 1:1.5:3

5/

1.50
1.50

-20mm aggregate for column


For column 150 x 150 (C1)

2.60

29.25

For column 300 x 300(C2)


13/

3.00
3.00
2.60

304.2
For column 225 x 225(C3)

6/

2.25
2.25
2.60

79.0
412.45 m3
M3

FORMWORK
Rough surface
Formwork for column 150 x 150

5/4

1.5
2.6

78.0

13/4

3.0

405.6

Rough surface
Formwork for column 150 x 150

Rough surface
Formwork for column 150 x 150

2.6
624 m2
6/4

2.25
2.60

104.4

M2
REINFORCEMENT FOR COLUMN

REINFORCEMENT FOR COLUMN


225x225
Length of one bar
3.060
0.038-cover
3.022
0.032- less 2T16
2.990 (i)
0.088 + bend 5.5d (4T16)
3.087 say 3.09
MR of T16 steel bar
6/4

3.09

74.16

M
Mild steel link for column 225x225
Length of one link
0.175
0.076 - cover 2/0.038
0.099
4/0.099= 0.396
0.300 + hook 30d
0.696

Distance that require link


2.998 (length of steel bar)
No. Of links = 2.990/0.099+1
=31
MR of M10 link
6/31

0.696

129.5

REINFORCEMENT FOR COLUMN 150 X


150
Length of one bar
3.060
0.038-cover
3.022
0.024- less 2T12
2.998 (i)
0.066 + bend 5.5d (4T12)
3.064 say 3.07
5/4

3.07

61.4

MR of T12 steel bar

Mild steel link for column 150x150


Length of one link
0.125
0.076 - cover 2/0.038
0.049
4/0.049= 0.196
0.144 + hook 24d
0.340
Distance that require link
2.998 (length of steel bar)
No. Of links = 2.998/0.049+1
=62
5/62

0.304

105.4

MR of M6 link

GROUND BEAM

No.

Dimension

Quantit
y

Description

Unit

CONCRETE WORK

GB2
Length
add(+)column
add(+)column
1/

0.15/
0.45/
3.65/

0.246

0.25m concrete G30(1:1:2)


GB33
Length
less(-)column
less(-)column

1/

0.15/
0.45/
1.61/

0.109

1/

0.15/
0.45/
1.64/

0.15/
0.45/
3.2/

0.443

0.216

M3

=1830
=75
=112.5
1642.5

0.44m concrete G30(1:1:2)


GB9
Length
less(-)column
less(-)column

M3

= 1830
=75
=150
1605

0.11 m concrete G30(1:1:2)


GB4
Length
less(-)column
less(-)column

1/

= 3350
=150
=150
3650

M3

= 3350
=75
=75
3125

0.22m concrete G30(1:1:2)

M3
M3

GB19
Length
add(+)column
add(+)column
1/

1/

1/

1/

1/

1/

0.15/
0.45/
6.96/

0.15/
0.45/
6.10/

0.15/
0.45/
4.70/

0.15/
0.45/
3.09/

0.15/
0.45/
4.96/

0.15/
0.35/

0.47

0.47 m concrete G30(1:1:2)


GB34
Length
add(+)column
add(+)column

0.412

0.209

0.335

M3

= 5180
=75
=150
4955

0.34 m concrete G30(1:1:2)


RB10
Length
less(-)column
less(-)column

M3

= 3350
=150
=112.5
3087.5

0.21m concrete G30(1:1:2)

GB14
Length
less(-)column
less(-)column

M3

= 4870
=75
=75
4720

0.32m concrete G30(1:1:2)

GB10
Length
less(-)column
less(-)column

M3

= 5800
=150
=150
6100

0.41 m concrete G30(1:1:2)

GB6
Length
less(-)column
less(-)column
0.319

= 6700
=112.5
=150
6962.5

= 3350
=75
=150
3125

M3

1.64/

1/

1/

1/

0.15/
0.45/
13.41/

0.15/
0.45/
17.1/

0.15/
0.45/
1.97/

0.164

0.16 m concrete G30(1:1:2)

GB28
Length
add(+)column
less(-)column
0.906

1.15

=13410
=112.5
=112.5
13410

0.91m concrete G30(1:1:2)

GB23
Length
less(-)column
less(-)column

M3

= 17400
=150
=150
17100

1.15m concrete G30(1:1:2)


RB21
Length
add(+)column
add(+)column

0.133

M3

M3

= 1820
=75
=75
1970

0.13m concrete G30(1:1:2

M3

FORMWORK
Vertical inner side:
Gb34, GB29
Side length
add(+)column
less(-)column
2/

0.45/
5.65/

5.09

= 5800
=75
=75
5800
5.09 m sawn timber
GB23
Side length
less(-)column
less(-)column
less(-)column

=17380
=75
=3/150
=75

M2

2/

0.45/
16.78

15.1

16780
15.1 m sawn timber

Side length
less(-)column
less(-)column
less(-)column
1/

0.45/
16.63/

7.48

=17380
=75
=4/150
=75
16630
7.48 m sawn timber

M2

M2

GB21
Side length
add(+)column
less(-)column
1/

0.45/
1.22/

0.55

= 1220
=75
=75
1220
0.55 m sawn timber
Side length
less(-)column
less(-)column

1/

0.45/
1.67/

0.75

= 1820
=75
=75
1670
0.75 m sawn timber

M2

M2

GB22
Side length
add(+)column
less(-)column
1/

0.45/
2.45/

1.10

= 2450
=75
=75
2450
1.10 m sawn timber
Side length
less(-)column
less(-)column
less(-)column

1/

0.45/
2.15/

0.97

= 2450
=75
=1/150
=75
2150
0.97 m sawn timber

M2

Vertical inner side:

M2

GB28
Side length
less(-)column
less(-)column
less(-)column
2/

0.45/
12.36/

11.12

= 13410
=75
=4/225
=75
12360
11.12 m sawn timber

M2

vertical base:
GB23
Base length
less(-)column
less(-)column
less(-)column
1/

1/

0.15/
2.15/

0.15/
1.67/

0.32

= 2450
=75
=150
=75
2150
0.32 m sawn timber

M2

GB22
Base length
less(-)column
less(-)column
0.25

= 1820
=75
=75
1670
0.25 m sawn timber

M2

GB29
Base length
less(-)column
1/

1/

0.15/
12.06/

0.45/
1.68/

1.81

= 13410
=6/225
12060
1.81m sawn timber

M2

1.51

Horizontal inner side:


GB33,GB14
Side length
=1830
less(-)column
=75
less(-)column
=75
1680
1.51 m sawn timber

M2

Inner side GB2, GB8, GB9, GB14, inner


GB19

8/

3/

Side length
less(-)column
less(-)column

0.45/
3.20/

12.6

0.45/
1.37/

1.85

=3350
=75
=75
3200
12.6 m sawn timber
GB6, inner GB19
Side length
= 1520
add(+)column
=75
less(-)column
=75
1370

M2

M2
1.85 m sawn timber

2/

8/

0.45/
3.16/

0.45/
1.64/

GB10
Side length
less(-)column
less(-)column
2.84

5.9

= 1820
=112.5
=75
3162.5
2.84 m sawn timber
7/GB4, inner GB19
Side length
= 1830
less(-)column
=112.5
less(-)column
=75
1642.5
5.9 m sawn timber

REINFORCEMENT
RB 2 (F-G)
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 3.35

Add (+) column


2/0.075
=0.15

M2

M2

Less(-) cover
2/0.038

Add (+)bend
2/5d
2/2

3.54

14.16

= 0.076

=0.12
3.54

14.16m T12

Stirrup:
150

450

Length
Less(-) cover

Width
Less(-) cover

=0.450
2/0.038
0.374

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup

Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1/4/

1.05

4.2

M
4.2m-R6

RB 6 (F-G)
Reinforcement bar:
Top
2T12
bottom
2T16
Length

= 3.35

Add (+) column


=0.15
Less(-) cover
2/0.038

Add (+)bend
2/5d
2

3.54

7.08

= 0.076

=0.12
3.54

=0.16
3.58

7.08m T12
Add (+) bend
2/5d
2

3.58

7.08
7.08m T16
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1/31
/

1.14

4.2

M
4.2m-R6

RB 9 (F-G)
Reinforcement bar:
Top
2T12
bottom
2T16
Length

= 3.35

Add (+) column


2/0.075
=0.15
Less(-) cover
2/0.038
Add (+)bend

= 0.076

2/5d
3.54

7.08

=0.12
3.54

=0.16
3.584

7.08m T12
Add (+) bend
2/5d
3.58

7.16

7.16m T16
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05

No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1.05
1/4/

4.2

M
4.2m-R6

RB 14(F-G)

Reinforcement bar:
Top
2T12
bottom
2T16
Length

= 3.35

Add (+) column


=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
3.54

7.08

=0.12
3.54

=0.16
3.584

7.08m T12
Add (+) bend
2/5d
3.58

= 0.076

7.16
7.16m T16

Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1.05
1/4

4.2

M
4.2m-R6

RB 14 (G-H)
Reinforcement bar:
Top
2T12
bottom
2T16
Length

= 1.83

Add (+) column


2/0.075
=0.15
Less(-) cover
2/0.038

= 0.076

Add (+)bend
2/5d

=0.12

2.03

4.06

2.024

=0.16
2.184

4.06m T12
Add (+) bend
2/5d
2.18

4.36

4.36m T16
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=1.83
Less(-)column =0.150
Total length
=1.68
(1.68/1.05)+ 1
=3 nos
1.05
1/3

3.2

M
3.2m-R6

RB 19(F-G)
Reinforcement bar:
Top
2T12
bottom
2T16
Length

= 3.35

Add (+) column


=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
3.54
2/2

14.16

= 0.076

=0.12
3.54

14.16m T12

Stirrup:
150

450

Length
Less(-) cover

Width
Less(-) cover

=0.450
2/0.038
0.374

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05

No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1.05

4.2

1/4

M
4.2m-R6

RB 33 (G-H)
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 1.83

Add (+) column


2/0.075
=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
2.03
2/2

8.12

= 0.076

=0.12
2.024

8.12m T12

Stirrup:
150

450

Length

=0.450

Less(-) cover

2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=1.83
Less(-)column =0.150
Total length
=1.68
(1.68/1.05)+ 1
=3 nos
1.05

3.2

1/3

M
3.2m-R6

RB 23 (1-2)
Reinforcement bar:
Top
2T12/T20
bottom
2T20
TOP
Length

= 3.78

Add (+) 0.5column


0.075
=0.075
Less(-) cover
0.038
Add (+)bend
5d
3.88

7.76

= 0.038

=0.06
3.877

7.76m T12

2.58

2T20
Length = 1.29 +1.29
= 2.58m

2.58m T20
Add (+) bend
2/5d

BOTTOM
Length

=0.16
2.184

= 4.57

Add (+) 0.5column


0.075
=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
4.45
2

8.9

= 0.076

=0.2
4.444

8.9m T20
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length

=17.38

Less(-)column =0.150
Total length
=17.23
(17.23/1.05)+ 1
=18 nos
1.05

18.9

1/18

M
18.9m-R6

RB 23 (2-4A)
Reinforcement bar:
Top
2T12/T20
bottom
2T16
TOP
Length
3.30

= 3.30

6.60

M
6.60m T12
Length

2.58

= 2.58

5.16

M
5.16m T20
BOTTOM
Length

= 5.49

Add (+) 0.5column


0.075
=0.075
Less(-) cover
0.038
Add (+)bend
5d
5.53
2

11.06
11.06m T16

= 0.038

=0.08
5.53

2.58

2T20
Length = 1.29 +1.29
= 2.58m
2.58m T20
Add (+) bend
2/5d

BOTTOM
Length

=0.16
2.184

= 4.57

Add (+) 0.5column


0.075
=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
4.45
2

8.9

= 0.076

=0.2
4.444

8.9m T20

Stirrup:
150

450

Length
Less(-) cover

Width
Less(-) cover

=0.450
2/0.038
0.374

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45

Total length
Add(+) anchor

=2/0.45
24d
1.05

No of stirrup
Length
=17.38
Less(-)column =0.150
Total length
=17.23
(17.23/1.05)+ 1
=18 nos
1.05

35.34

1/18

M
18.9m-R6
RB 23 (4A-4B)
Reinforcement bar:
Top
2T16
bottom
2T12
TOP
Length

1.675

= 1.675

3.35

M
3.35m T16

BOTTOM
Length

= 1.20

Add (+) column


=0.15
Less(-) cover
2/0.038

= 0.076

Add (+)bend
2/5d
1.394
2

2.79

=0.12
1.394
M

2.79m T12
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=1.2
Less(-)column =0.15
Total length
=1.05
(1.68/1.05)+ 1
=2 nos
1.05

2.1

1/2

M
2.1m-R6

RB 23(4B-6)
Reinforcement bar:
Top
2T12/T20
bottom
2T12
TOP
Length
= 2.70
2.70

5.40

M
5.40m T12
Length

2.0
2

= 2.0

4.0

M
4.0m T20
BOTTOM
Length

= 3.70

Add (+) column


=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
3.90

7.80

= 0.076

=0.12
3.90

7.80m T12
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374
Width
=0.15
Less(-) cover
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.70
Less(-)column =0.150
Total length
=3.55
(3.55/1.05)+ 1
=5nos
1.05
1/5

5.25

M
5.25m-R6

RB 23 (6-7)
Reinforcement bar:
Top
2T12
bottom
2T12

TOP
Length

= 2.55

Add (+) 0.5 column


=0.075
Less(-) cover
= 0.038
Add (+)bend
5d
2.647

5.3

=0.06
2.647

5.30m T12
BOTTOM
Length

= 3.05

Add (+) column


=0.15
Less(-) cover
= 0.076
Add (+)bend
5d
3.244
2

6.49

=0.12
3.244

6.49m T12

Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374
Width
=0.15
Less(-) cover
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.05
Less(-)column =0.150
Total length
=2.90
(2.90/1.05)+ 1
=4nos
1.05

4.2

1/4

4.2m-R6
RB 23 (1-2)
Reinforcement bar:
Top
2T12/T20
bottom
2T20
TOP
Length

= 3.78

Add (+) 0.5column


0.075
=0.075
Less(-) cover
0.038
Add (+)bend
5d
3.88

7.76

= 0.038

=0.06
3.877

7.76m T12

2.58

5.16

2T20
Length = 1.29 +1.29
= 2.58m

5.16m T20
Add (+) bend
2/5d

BOTTOM
Length

=0.16
2.184

= 4.57

Add (+) 0.5column


0.075
=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
4.45
2

8.9

= 0.076

=0.2
4.444

8.9m T20
Stirrup:
150

450

Length
Less(-) cover

Width
Less(-) cover

=0.450
2/0.038
0.374

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05

No of stirrup
Length
=4.57
Less(-)column =0.150
Total length
=4.42
(4.42/1.05)+ 1
=6 nos
1.05

6.3

1/6

M
6.3m-R6
RB 23 (2-4)
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 4.88

Add (+)column
=0.15
Less(-) cover
= (2)0.038
Add (+)bend
2/5d
5.074
2/2

20.30

=0.12
5.074

20.30m T12
Stirrup:
150

450

Length
Less(-) cover

Width
Less(-) cover

=0.450
=2/0.038
0.374

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45

Total length
Add(+) anchor

=2/0.45
24d
1.05

No of stirrup
Length
=4.88
Less(-)column =0.150
Total length
=4.73
(4.73/1.05)+ 1
=6 nos
1.05

6.3

1/6

M
6.3m-R6
RB 23(4B-6)
Reinforcement bar:
Top
2T12/T20
bottom
2T12
TOP
Length
= 2.70

2.70

5.40

M
5.40m T12
Length

2.0

= 2.0

4.0

M
4.0m T20
BOTTOM
Length

= 3.70

Add (+) column


=0.15
Less(-) cover
2/0.038
Add (+)bend
2/5d
3.90
2

7.80

= 0.076

=0.12
3.90

7.80m T12
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374

Width
Less(-) cover

=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.70
Less(-)column =0.150
Total length
=3.55
(3.55/1.05)+ 1
=5nos
1.05

5.25

1/5

M
5.25m-R6
RB 23 (6-7)
Reinforcement bar:
Top
2T12
bottom
2T12
TOP
Length

= 2.55

Add (+) 0.5 column


=0.075
Less(-) cover
= 0.038
Add (+)bend
5d
2.647
2

5.3
5.30m T12

=0.06
2.647

BOTTOM
Length

= 3.05

Add (+) column


=0.15
Less(-) cover
= 0.076

Add (+)bend
5d
3.244
2

6.49

=0.12
3.244

6.49m T12
Stirrup:
150

450

Length
Less(-) cover

=0.450
2/0.038
0.374
Width
=0.15
Less(-) cover
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.05
Less(-)column =0.150
Total length
=2.90
(2.90/1.05)+ 1
=4nos

1.05

4.2

1/4

M
4.2m-R6

SLAB

No.

Dimension

Quantit
y

Description

Unit

SLAB
CONCRETE WORK
Mass Concrete
1/

1/

5.80
1.83
0.125

6.06
3.35
0.100

4-6 / G-H
1.33

1.33 m

1-2 / F-G
2.03
2.03 m

1/

4.56
3.05
0.125

M3

M3

2-4B / F-G
1.74

M3

1.74 m
1/

1/

1/

3.70
3.35
0.125

3.05
3.35
0.125

1.52
1.22
0.125

4B-6 / F-G

1.55

1.55 m

1.28

6-7 / F-G

1.28 m

M3

M3

0.23

M3
2-3 / E1-F

0.23 m
1/

1.82
1.83
0.125

M3
1A-3 / E-E1

1/
3.64
3.35
0.125

0.42 m

1.52

M3

1/
5.50
3.35
0.125

3-4A / E-F

2.30

1.52 m

M3

1/
2.45
1.52

4A-6A / E-F

0.125

0.47

M3
2.30 m

1/
1.55
1.83
0.125

6A-7 / E1-F
0.35

M3
0.47 m

1/
0.90
1.83
0.125

6A-6B / E-E1

0.21

0.35 m

M3

6B-7 / E-E1

0.21m3

2/

2/

5.80
0.125

1.45

1.83
0.125

0.46

M2
FORMWORK

2/

2/

6.06
0.100

1.21

3.35
0.100

0.67

Sawn timber of 38mm thickness for side


of slab

M2

2/

4.56
0.125

1.14

2/

3.05
0.125

0.76

2/

3.70
0.125

0.93

2/

3.35
0.125

0.84

2/

3.05
0.125

0.76

2/

3.35
0.125

1.91 m

M2

1.88 m2

M2

1.90 m

0.84

M2

1.77 m2
2/

2/

2/

2/

1.52
0.125

0.38

1.22
0.125

0.31

1.82
0.125

0.46

1.83
0.125

0.46

M2

1.60 m

M2

2/

2/

2/

2/

2/

2/

3.64
0.125

0.91

3.35
0.125

0.84

5.50
0.125

1.38

3.35
0.125

0.84

2.45
0.125

0.61

1.52
0.125

0.38

0.69 m

0.92 m

2/

1.55
0.125

0.39

1.83
0.125

0.46

2/

0.90
0.125

0.23

1.83
0.125

0.46

M2
2.22 m

2/

M2

M2
1.75 m

2/

M2

M2

1.00 m

10/

5.856

0.85 m

0.69 m

58.56

REINFORCEMENT
4-6 / G-H
y-direction
R8-200

29/

1.886

54.69

5.800
- 0.024 (- 2cover)
5.776
+ 0.080 (+ 2bends)
5.856

2/0.012
2/5d

Total length required steel


( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
58.56m, R8
x-direction
R8-200
1.830
- 0.024 (- 2cover)
1.806

2/0.012

+ 0.080 (+ 2bends)
1.886

2/5d

Total length required steel


(5800 12 - 12 ) = 5776
No of steel
5776/200 =28.88
29
54.69m R8

17/

6.116

103.97

1-2 / F-G
y-direction
R8-200
6.060
- 0.024 (- 2cover)
6.036
+ 0.080 (+ 2bends)
6.116
31/

3.406

105.59

Total length required steel


( 3350 -12 -12 ) = 3326

No of steel
3326/200 = 16.63
17
103.97m R8

x-direction
R8-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406

Total length required steel


( 6060 -12 -12 ) = 6036
No of steel
6036/200 = 30.18
31
105.59m, R8

31/

4.616

73.86

2-4B / F-G
y-direction
R8-200

16/

3.106

71.44

4.560
- 0.024 (- 2cover)
4.536
+ 0.080 (+ 2bends)
4.616
Total length required steel
( 3050 -12 -12 ) = 3026
No of steel
3026/200 = 15.13
16
73.86m R8

x-direction
R8-200
3.050
- 0.024 (- 2cover)

3.026
+ 0.080 (+ 2bends)
3.106
17/

3.756

63.85

Total length required steel


( 4560 -12 -12 ) = 4536
No of steel
4536/200 = 22.68
23
71.44m R8

4B-6 / F-G
y-direction
R8-200

19/

3.386

64.33

3.700
- 0.024 (- 2cover)
3.676
+ 0.080 (+ 2bends)
3.756

Total length required steel


( 3350 -12 -12 ) = 3326
No of steel
3326/200 = 16.63
17
63.85m R8

x-direction
R6-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.060 (+ 2bends)
3.386

16/

3.406

54.50

Total length required steel


( 3700 -12 -12 ) = 3676
No of steel
3676/200 = 18.38
19
64.33m R6

6-7 / F-G
y-direction
R8-200

17/

3.106

52.80

3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406

Total length required steel


( 3050 -12 -12 ) = 3026
No of steel
3026/200 = 15.13
16
54.50m R8

x-direction
R8-200
3.050
- 0.024 (- 2cover)
3.026
+ 0.080 (+ 2bends)
3.106

6/

1.556

9.34

Total length required steel


( 3350 -12 -12 ) = 3326
No of steel
3326/200 = 16.63
17
52.80m R8

2-3 / E1-F
y-direction
R8-200
1.500
- 0.024 (- 2cover)

8/

1.276

10.21

1.476
+ 0.080 (+ 2bends)
1.556

Total length required steel


( 1220 -12 -12 ) = 1196
No of steel
1196/200 = 5.98
6
9.34m R8

x-direction
R8-200
1.220
- 0.024 (- 2cover)
1.196
+ 0.080 (+ 2bends)
1.276
Total length required steel
( 1520 -12 -12 ) = 1496
No of steel
1496/200 = 7.48
8
10.21m R8
9/

1.886

16.97

1A-3 / E-E1
y-direction
R8-200

10/

1.876

18.76

1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886

Total length required steel


( 1820 -12 -12 ) = 1796
No of steel
1796/200 = 8.98
9
16.97m R8

x-direction
R8-200
1.820
- 0.024 (- 2cover)
1.796
+ 0.080 (+ 2bends)
1.876

0.57

Total length required steel


( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
18.76m R8

17/

3.696

62.83

3-4A / E-F
y-direction
R8-200
3.640
- 0.024 (- 2cover)

19/

3.406

64.71

3.616
+ 0.080 (+ 2bends)
3.696

Total length required steel


( 3350 -12 -12 ) = 3326
No of steel
3326/200 = 16.63
17
62.83m R8

x-direction
R8-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406
Total length required steel
( 3640 -12 -12 ) = 3616
No of steel
3616/200 = 18.08
19
64.71m R8

17/

5.556

94.45

4A-6A / E-F
y-direction

R8-200

28/

3.406

95.37

5.500
- 0.024 (- 2cover)
5.476
+ 0.080 (+ 2bends)
5.556

Total length required steel


( 3350 -12 -12 ) = 3326
No of steel
3326/200 = 16.63
17
94.45m R8

x-direction
R8-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406
Total length required steel
( 5500 -12 -12 ) = 5476
No of steel
5476/200 = 27.38
28
95.37m R8

8/

2.506

20.05

6A-7 / E1-F
y-direction
R8-200

13/

1.576

20.49

2.450
- 0.024 (- 2cover)
2.426
+ 0.080 (+ 2bends)
2.506

Total length required steel


( 1520 -12 -12 ) = 1496
No of steel
1496/200 = 7.48
8
20.05m R8

x-direction
R8-200
1.520
- 0.024 (- 2cover)
1.496
+ 0.080 (+ 2bends)
1.576
Total length required steel
( 2450 -12 -12 ) = 2426
No of steel
2426/200 = 12.13
13
20.49m R8

8/

1.886

15.09

6A-6B / E-E1
y-direction
R8-200

10/

1.606

16.06

1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886
Total length required steel
( 1550 -12 -12 ) = 1526
No of steel
1526/200 = 7.63
8
15.09m R8

x-direction
R8-200
1.550
- 0.024 (- 2cover)
1.526
+ 0.080 (+ 2bends)
1.606
Total length required steel
( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
16.06m R8

15/
4
1.700
8/4

15/
4

2.43

M
8/4

2.92

1.35

6A-6B / E-E1
y-direction
R8-200

1.94

0.17
15/
5

1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886

Total length required steel


( 1550 -12 -12 ) = 1526
No of steel
1526/200 = 7.63
8
15.09m R8

0.34
x-direction
R8-200

0.32

1.886

5/

9.43

1.550
- 0.024 (- 2cover)
1.526
+ 0.080 (+ 2bends)
1.606
Total length required steel
( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
16.06m R8

6B-7 / E-E1
y-direction
R8-200

0.956

10/

9.56

1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886
Total length required steel
( 900 -12 -12 ) = 876
No of steel
876/200 = 4.38
5
9.43m R8

x-direction
R8-200
0.900
- 0.024 (- 2cover)
0.876
+ 0.080 (+ 2bends)
0.956
Total length required steel
( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
9.56m R8

ROOF BEAM

No.

Dimension

Quantit
y

Description

Unit
CONCRETE WORK

RB15
Length
less(-)column
less(-)column
1/

0.15/
0.35/
4.96/

0.26

0.26m concrete G30(1:1:2)


RB29
Length
add(+)column
less(-)column

1/

0.23/
0.35/
13.41/

1.08

0.15/
0.35/
3.39/

0.178

1/

0.15/
0.35/
17.16/

0.901

M3

= 3350
=112.5
=75
3387.5

0.178m concrete G30(1:1:2)


RB33
Length
less(-)column
less(-)column

M3

= 13410
=112.5
=112.5
13410

1.08 m concrete G30(1:1:2)


RB11
Length
add(+)column
less(-)column

1/

= 5180
=75
=150
4955

M3

= 17380
=75
=150
17155

0.90m concrete G30(1:1:2)

M3

RB6
Length
less(-)column
less(-)column

1/

0.15/
0.35/
4.75/

0.248

0.25 m concrete G30(1:1:2)

RB20
Length
add(+)column
add(+)column
1/

0.15/
0.35/
6.96

0.37

4/

1/

0.15/
0.35/
3.65/

0.15/
0.35/
1.64/

0.15/

0.184

0.344

M3

= 1830
=75
=112.5
1642.5

0.34 m concrete G30(1:1:2)


RB10
Length
less(-)column
less(-)column

M3

= 3350
=150
=150
3500

0.18 m concrete G30(1:1:2)


RB4
Length
less(-)column
less(-)column

M3

= 6700
=112.5
=150
6962.5

0.37 m concrete G30(1:1:2)

RB2
Length
add(+)column
add(+)column
1/

= 4870
=75
=75
4720

= 3350
=75
=150

M3

0.35/
3.13/

1/

1/

0.15/
0.35/
1.97/

3125
0.164

RB22
Length
add(+)column
add(+)column
0.103

0.15/
0.35/
2.05/

1/

0.15/
0.35/
17.16/

0.15/
0.35/
6.1/

0.90

0.32

M3

= 5800
=150
=150
6100

0.32m concrete G30(1:1:2)

RB10
Length

M3

= 17380
=75
=150
17155

0.90m concrete G30(1:1:2)

RB34
Length
add(+)column
add(+)column

M3

=2050
=75
=75
2050

0.11m concrete G30(1:1:2)

RB24
Length
less(-)column
less(-)column

M3

= 1820
=75
=75
1970

0.10 m concrete G30(1:1:2)

RB23
Length
add(+)column
less(-)column
0.11

1/

0.16 m concrete G30(1:1:2)

= 3350

M3

1/

1/

0.15/
0.35/
1.64/

0.15/
0.45/
1.97/

less(-)column
less(-)column
0.164

0.16 m concrete G30(1:1:2)

RB21
Length
add(+)column
add(+)column
0.133

=75
=150
3125
M3

= 1820
=75
=75
1970

0.13m concrete G30(1:1:2)

M3

FORMWORK

1/

0.35/
2.45/

0.86

Vertical inner side:


RB23
Side length
= 2450
add(+)column
=75
less(-)column
=75
2450
0.86 m sawn timber
Side length
less(-)column
less(-)column

1/

0.35/
0.75/

0.26

= 900
=75
=75
750
0.26 m sawn timber

M2

Side length
less(-)column
less(-)column
1/

0.35/
1.44/

0.49

= 1550
=75
=75
1440
0.49 m sawn timber

M2

RB29

M2

Side length
add(+)column
less(-)column
1/

0.35/
1.22/

0.43

= 1220
=75
=75
1220
0.43 m sawn timber
Side length
add(+)column
less(-)column

1/

0.35/
1.82/

0.64

= 1820
=75
=75
1820
0.64 m sawn timber

M2

M2

RB29
Side length
less(-)column
less(-)column
1/

0.35/
1.6/

0.56

= 1820
=112.5
=112.5
1595
0.56 m sawn timber

Side length
less(-)column
less(-)column
1/

1/

0.35/
2.42/

0.85

= 3640
=112.5
=112.5
2415
0.85 m sawn timber

M2

Side length
less(-)column
less(-)column

0.35/
5.28/
1.85

= 5500
=112.5
=112.5
5275
1.85 m sawn timber

M2

Side length
less(-)column
less(-)column
1/

0.35/
1.33/

0.47

= 1500
=112.5
=112.5
1325
0.47 m sawn timber

M2

M2

Side length
less(-)column
less(-)column
1/

0.35/
0.68/

0.24

= 900
=112.5
=112.5
675
0.24 m sawn timber

M2

RB34,RB33
Side length
less(-)column
less(-)column
2/

0.35/
5.65/

3.96

= 5800
=75
=75
5650
3.96 m sawn timber

M2

RB34,RB33
Side length
less(-)column
less(-)column
2/

0.35/
2.90/

2.03

= 3050
=75
=75
2900
2.03 m sawn timber
Side length
less(-)column
less(-)column

2/

0.35/
3.55/

2.49

= 3700
=75
=75
3550
2.49 m sawn timber

M2

Side length
less(-)column
less(-)column
2/

0.35/
5.91/

4.14

= 6060
=75
=75
5910
4.14 m sawn timber

M2

Side length
less(-)column
less(-)column
2/

0.35/
4.35/

3.05

= 4570
=75
=150
4345
3.05 m sawn timber

M2

RB24
Side length
less(-)column
less(-)column
1/

0.45/

= 7050
=75
=75
7800

M2

3.65/

2.73

2.73 m sawn timber

M2

RB24
Side length
less(-)column
less(-)column
1/

0.35/
4.71/

1.65

= 4860
=75
=75
4710
1.65 m sawn timber

M2

Horizontal inner side:

5/2/

3/2/

1/2/

0.35/
1.68/

0.35/
1.68/

0.35/
1.83/

11.48

Inner RB2, RB6, RB10,RB15, inner RB20,


RB11
Side length
= 3350
less(-)column
=75
less(-)column
=75
3270
11.48 m sawn timber

M2

RB4
Side length
less(-)column
less(-)column
3.53

1.28

= 1830
=75
=75
1680
3.53 m sawn timber

Side length
add(+)column
=75

M2

= 1830
=75 less(-)column
M2

1830
1.28 m sawn timber

3/

0.35/
1.37/

1.44

RB6
Side length
less(-)column
less(-)column

= 152
=75
=75
1370

M2

1.44 m sawn timber

2/

0.35
1.68/

1.18

RB9
Side length
less(-)column
less(-)column

= 1830
=75
=75
1680
1.18 m sawn timber

M2

Horizontal base:

1/

5/

2/

5/

0.15/
1.68/

0.15/
3.2/

0.15/
1.37/

0.15/
1.64/

0.25

2.4

RB9,RB15
Base length
less(-)column
less(-)column

= 1830
=75
=150
1680
0.25 m sawn timber
RB20,RB15,RB10,RB6,RB2
Base length
= 3350
less(-)column
=75
less(-)column
=75
3200
2.4 m sawn timber

0.41

RB20,RB6
Base length
less(-)column
less(-)column

1.23

RB20,4/RB4
Base length
less(-)column
less(-)column

= 1520
=75
=75
1370
0.41m sawn timber

= 1830
=112.5
=75
1642.5
1.23m sawn timber

M2

M2

M2

M2

1/

0.15/
3.16/

0.47

RB11
Base length
less(-)column
less(-)column

= 3350
=112.5
=75
3162.5
0.47m sawn timber

M2

vertical base:

1/

2/

2/

2/

0.15/
5.65/

0.15/
2.9/

0.15/
3.55/

0.15/
4.42/

0.85

RB35
Base length
less(-)column
less(-)column

0.87

RB33,RB24
Base length
less(-)column
less(-)column

1.07

Base length
less(-)column
less(-)column

M2

1.32

Base length
less(-)column
less(-)column

M2

= 5800
=75
=75
5650
0.85 m sawn timber

= 3050
=75
=75
2900
0.87 m sawn timber

= 3700
=75
=75
1370
1.07m sawn timber

= 4570
=75
=75
4420
1.32m sawn timber

RB33
Base length

= 3960

M2

M2

1/

1/

1/

1/

0.15/
3.81/

0.15/
1.95/

0.15/
1.05/

0.15/
4.71/

0.57

less(-)column
less(-)column

=75
=75
3810
0.57m sawn timber

M2

0.29

Base length
less(-)column
less(-)column

M2

0.16

RB24
Base length
less(-)column
less(-)column

M2

0.71

Base length
less(-)column
less(-)column

M2

= 2100
=75
=75
1950
0.29m sawn timber

= 1200
=75
=75
1050
0.16m sawn timber
= 4860
=75
=75
4710
0.71m sawn timber
Horizontal outer side:

4/

1/

0.35/
1.98/

0.35/
3.65/

2.77

RB9, RB15
Side length
add(+)column

M2

1.28

RB2
Side length
add(+)column
add(+)column

M2

= 1830
=150
1980
2.77 m sawn timber

= 3350
=150
=150
3650
1.28 m sawn timber

1/

1/

1/

0.35/
1.37/

0.35/
2.02/

0.35/
6.89/

0.48

0.71

2.41

RB6
Side length
less(-)column
less(-)column

M2

RB4
Side length
add(+)column
add(+)column

M2

RB20
Side length
add(+)column
add(+)column

M2

= 1520
=75
=75
1370
0.48 m sawn timber

= 1830
=75
=112.5
2017.5
0.71 m sawn timber

= 6700
=75
=112.5
6887.5
2.41 m sawn timber

Vertical outer side:

1/

1/

1/

0.35/
5.95/

0.35/
3.05/

0.35/
8.53/

2.08

RB34
Side length
add(+)column
add(+)column

1.07

RB33
Side length
add(+)column
less(-)column

2.99

Side length
add(+)column
less(-)column

= 5800
=75
=75
5950
2.08 m sawn timber

= 3050
=75
=75
3050
1.07 m sawn timber
= 8530
=75
=75

M2

M2

M2

8530
2.99 m sawn timber

1/

0.35/
16.71/

5.85

RB29
Side length
add(+)column
less(-)column
add(+)column

= 17380
=112.5
=4/225
=112.5
2017.5
5.85 m sawn timber

M2

REINFORCEMENT

RB 23
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 2.450

Add (+) column


2/0.075
=0.15
Less(-) cover
2/0.025
Add (+)bend
2/5d
2/2/

2.67

10.68

= 0.05

=0.12
2.67

10.68m T12

Stirrup:
150

350

Length

=0.350

Less(-) cover

2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup
Length
Less(-)column
Less(-)column

1/12/

1.14

13.68

=2/0.5
24d
1.144

=2450
150
2/75
2150

(2150/200)+ 1
=11.7512nos

13.68m-R6

RB 20
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 6.70

Add (+) column


=0.15
=0.11
Less(-) cover
0.025
Add (+)bend
5d
2/2/

7.0

28.0
28.0m T12

= 0.025

=0.12
6.995

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup
Length
Less(-)column
Less(-)column
Less(-)column

1/31/

1.14

35.34

=2/0.5
24d
1.144

=6700
2/150
112.5
150
6137.5

(6137.5/200)+ 1
=30.6831nos
35.34m-R6

RB 34
Reinforcement bar:

Top
bottom

2T12
2T12

Length

= 5.800

Add (+) column


2/0.15
=0.3
Less(-) cover
2/0.025
Add (+)bend
2/5d
2/2/

6.17

24.68

= 0.05

=0.12
6.17

24.68m T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

=2/0.5
24d
1.144

No of stirrup
Length
Less(-)column

1/29/

1.14

33.06

=5800
2/75
5500

(5500/200)+ 1
=28.529nos

33.06m-R6

RB 15
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 5.180

Add (+) column


0.15
=0.15
0.075
=0.075
Less(-) cover
2/0.025
= 0.05
Add (+)bend
2/5d
2/2/

5.48

21.92

=0.12
5.48

21.92m T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup
Length
Less(-)column
Less(-)column
Less(-)column

1/25/

1.14

28.5

(4805/200)+ 1
=25.025nos
28.5m-R6

RB 11

=2/0.5
24d
1.144

=5180
75
150
150
4805

Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 3.350

Add (+) column


0.075
=0.075
0.11
=0.11
Less(-) cover
2/0.025
= 0.05
Add (+)bend
2/5d
2/2/

3.61

14.44

=0.12
3.61

14.44m T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup

=2/0.5
24d
1.144

Length
Less(-)column
Less(-)column

1/17/

1.14

19.38

=3350
112.5
75
3162.5

(3162.5/200)+ 1
=16.817nos

19.38m-R6

RB 6
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 4.870

Add (+) column


2/0.075

=0.15

Less(-) cover
2/0.025
Add (+)bend
2/5d
2/2/

5.09

20.36

= 0.05

=0.12
5.09

20.36m T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

=2/0.5
24d
1.144

No of stirrup
Length
Less(-)column

1/25/

1.14

28.5

=4870
2/75
4805

(4870/200)+ 1
=24.625nos

28.5m-R6

RB 2
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 3.3500

Add (+) column


2/0.15
=0.3
Less(-) cover
2/0.025
Add (+)bend
2/5d
2/2/

3.75

14.88

= 0.05

=0.12
3.75

14.88m T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup
Length
Less(-)column

1/18/

1.14

20.52

(3345/200)+ 1
=17.718nos
20.52m-R6

=2/0.5
24d
1.144

=3350
2/75
3345

RB 4
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 1.83

Add (+) column


=0.075
=0.113
Less(-) cover
0.025
Add (+)bend
5d
2/2/

2.023

32.32

= 0.025

=0.12
2.023

32.32m T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup

=2/0.5
24d
1.144

Length
Less(-)column
Less(-)column

1/9/

1.14

41.04

=1830
112.5
75
1643

(1643/200)+ 1
=9.219nos

M
41.40m-R6

RB 10
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 3.350

Add (+) column


0.075
=0.075
0.11
=0.15
Less(-) cover
2/0.025
= 0.05
Add (+)bend
2/5d
2/2/

3.645

14.58

=0.12
3.645

14.58m T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025

0.4
Width
Less(-) cover

Total length
Add(+) anchor

No of stirrup
Length
Less(-)column
Less(-)column

1/13/

1.14

14.87

=0.15
2/0.025
0.1
=2/0.5
24d
1.144

=3350
150
75
2450

(2450/200)+ 1
=13.313nos

14.87m-R6

RB 22
Reinforcement bar:
Top
2T12
bottom
2T12
Length

= 1.820

Add (+) column


2/0.075

=0.15

Less(-) cover
2/0.025
Add (+)bend
2/5d
2/2/

1.98

7.92
7.92m T12

Stirrup:
150

= 0.05

=0.12
1.98

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

=2/0.5
24d
1.144

No of stirrup
Length
Less(-)column

1/25/

1.14

10.3

=18200
2/75
1670

(1670/200)+ 1
=9.359nos

10.3m-R6

RB 24
Reinforcement bar:
Top
2T12
Length (1-2)
less(-)t16
Add (+) col
Less(-) cover

= 4.57
=1.29
=0.15
= 0.025

1/2/

3.965

7.93

Add(+)lapping
Add (+)bend

= 0.5
=5d
3.965

7.93m-T12

1/2/

6.21

12.42

Length (2-4b)
= 7.0
Less(-) t12
=1.29
Add(+)lapping =0.5
6.21
12.42m T12

Length (7-4b)
Less(-) t12
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend
1/2/

6.37

12.74

=6.76
=1.0
=0.075
=0.025
=0.5
=5d
6.37

12.74m-T12
1/2/

2.58

5.16

M
Length of T16 bar =2.58
5.16m-T16
bottom

1/2/

11.34

22.68

Length (1-4b)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend

2T12
=10.65
=0.15
=0.025
=0.5
=5d
11.34

22.68m-T12
Length (7-4b)
Less(-) t12

=6.76
=0.81

1/2/

6.06

12.12

Add(+)col
Less(-)cover
Add(+)bend

=0.075
=0.025
=5d
6.06

12.12m-T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup
Length
Less(-)column
4/150
Less(-)column

1/84

1.14

95.76

(16555/200)+ 1
=83.7784nos
95.75m-R6

=2/0.5
24d
1.144

=17380
150 Less(-)column
75
16555

RB 29
Reinforcement bar:
Top

1/2/

3.05

6.1

Length (1a-3)
Add (+) col
Less(-) cover
Add (+)bend

= 2.85
=0.113
= 0.025
=5d
3.05

6.1m-T12

1/2/

7.46

14.92

Length (4a-6a)
=3.5
Less(-) t16
=2/1.48
Add(+)lapping =2/0.5
7.46

14.92m T12

1/2/

1.55

3.1

1/2/

2.96

5.16

Length (7-6b)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend

=0.9
=0.113
=0.025
=0.5
=5d
1.55

3.1m-T12

Length of T16 bar =2.96


5.16m-T16
1/2/

4.8

9.6

Length of T16
Less(-)T12
Add(+)lapping
9.6m-T16

= 5.12
=1
=0.675
4.8

bottom

1/2/

9.61

19.22

Length (1a-6a)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend

2T12
=8.96
=0.113
=0.025
=0.5
=5d
9.61

19.22m-T12

1/2/

1.94

3.88

Length (7-6a)
Less(-) t12
Add(+)col
Less(-)cover
Add(+)bend

=2.45
=0.66
=0.113
=0.025
=5d
1.94

3.88m-T12
Stirrup:
225

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.225
2/0.025
0.175

Total length
Add(+) anchor

=2/0.575
24d
1.294

No of stirrup
Length
Less(-)column
Less(-)column

=17380
4/225
2/112.5

16255
1/13
1/

1.294

169.51

(16255/125)+ 1
=131.04131nos

169.51m-R6
RB 33
Reinforcement bar:
Top

4.04

8.08

Length (1a-2)
Add(+)col
Less(-)t16
Less(-)cover
Add(+)lapping
Add(+)bend

1/2/

=4.57
=0.15
=1.22
=0.025
=0.5
=5d
4.04

8.08m-T12

6.34

12.68

1/2/

Length (2-4b)
=7.06
Less(-) t16
=1.22
Add(+)lapping =0.5
6.34

12.68m T12

6.36
1/2/

12.72

Length (7-4b)
Add(+)col
Less(-)cover
Less(-)t12
Add(+)lapping
Add(+)bend

=6.75
=0.075
=0.025
=1.0
=0.5
=5d
6.36

2.44

4.88

12.72m-T12

1/2/
Length of T16 bar =2.4
4.88m-T16

bottom

12.01

24,02

1/2

Length (1a-4b)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend

=11.44
=0.15
=0.025
=0.5
=5d
12.01

24.02m-T12

6.05
1/2/

12.1

Length (7-4b)
Less(-) t12
Add(+)col
Less(-)cover
Add(+)bend

=6.75
=0.81
=0.075
=0.025
=5d
6.05
12.1m-T12

Stirrup:
150

350

Length
Less(-) cover

=0.350
2/0.025
0.4

Width
Less(-) cover

=0.15
2/0.025
0.1

Total length
Add(+) anchor

No of stirrup
Length
Less(-)column
4/150
Less(-)column

=2/0.5
24d
1.144

=17380
150 Less(-)column
75
16555
M

(16555/200)+ 1
=83.7784nos
96.75m-R6

BILLS OF QUANTITIES

Ite
m
no.

Description

Quanti
ty

Uni
t

Rat
e

RM

1.

2.
2.1

2.2
2.3
2.4
2.5

3.

4.
4.1

4.2

EXCAVATION WORK
Excavation of top soil , 150mm
Excavation of trench depth not exceeding 1.5m
Backfilling
Excavation for ground beam, (GB1, GB2, GB3,
GB4)

CONCRETE WORK
Footing
Concrete grade of C30 20mm aggregate for
footings
Concrete grade of C10- crusher run for lean
concrete
Concrete grade of C30 - 20mm aggregate for
stump
Column
Concrete grade of C30 for column
Ground Beam
Concrete grade of C30
Roof Beam
Concrete grade of C30
Slab
Concrete grade C30

FORMWORK
Rough surface
Rough surface
Rough surface
Rough surface
Rough surface
Rough surface

formwork
formwork
formwork
formwork
formwork
formwork

for
for
for
for
for
for

footing
stump
column
ground beam
roof beam
slab

REINFORCEMENT
Stump and Footing
Y12, 91.70
(3.142 x 0.0122 x 91.70 x 7850)
R6, 88.56
(3.142 x 0.0062 x 88.56 x 7850)
Column

11.88
8.91
9.08
10.149

m2
m3
m3

3.29
11.88
0.49

m3
m3
m3

412.45

m3

3.22

m3

7.05

m3

13.43

17.64
13.95
624
69.24
50.8
15.27

m2
m2
m2
m2
m2
m2

325.69

kg

78.56

kg

1468

kg

468.26

kg

4.5
35.6
0
17.5
0

326.
6
437.
5
326.
6

53.46
317.20
158.90

1074.5
5197.5
160.00
92801.
00
724.50

225.
0

5101.3
8

225.
0

3021.7
5

225.
0
225.
0

56.1
0
21.5
0
21.5
0
21.5
0
20.4
5
82.8

989.60
300.00
13416
1488.6
6
1038.8
6
1264.3
6

1270.2
0

T12, 380.68 = 380.68m


(3.142 x 0.0122 x 380.68 x 7850)
T16, 74.16 = 74.16m
(3.142 x 0.0162 x 74.16 x 7850

0
306.40
1306
665.5

4.3

kg
5726.2
0

kg

Link,
R10, 529.5
(3.142 x 0.012 x 529.5 x 7850)
R16, 105.4
(3.142 x 0.0162 x 105.4 x 7850)

3.90
3.90
530

kg
3.90

4.4

4.5

Ground Beam
T12, 149.13 = 149.13m
(3.142 x 0.0122 x 149.13 x 7850)
T16, 40.17 = 40.17
(3.142 x 0.0162 x 40.17 x 7850)
T20, 50.18 = 50.18m
(3.142 x 0.0202 x 50.18 x 7850)
R6 for stirrups, 94.6 = 94.6m
(3.142 x 0.0042 x 954.8 x 7850)
Roof Beam
T12, = 374.49m
(3.142 x 0.0122 x 374.49 x 7850)
T16, = 24.8m
(3.142 x 0.0162 x 24.8 x 7850)
R6 for stirrups = 607.56m
(3.142 x 0.0082 x 607.56 x 7850)
Slab
R8 for y-direction, 582.9m
(3.142 x 0.0062 x 582.9 x 7850)
R8 for x-direction, 584.01m
(3.142 x 0.0052 x 584.0 x 7850)

1826.2
1

253.64

kg

495.06

kg

84

kg

5093.4
0

3.90
2595.5
0
3.90
1330

kg

156.6

kg

3.90

539.5

2012.7
0

kg

963.83
3.80
230
230

kg
3.80

1881.3
0

3.80

319.20

3.80

5054.3
0

kg

3.80
595.00
3.80
3.80

2050.0
0

3.80

874.00

3.80

874.00

TOTAL ESTIMATED COST = RM 158,548.33

ESTIMATING
LABOUR &EQUIPMENT COST

EXCAVATION BY MANUAL
(a)

Labour time involved in excavating 1 m3 of soft soil

1 1/3 hr

Labour time involved in carting-away 1 m3 of soft soil

1 1/3 hr

Total labour time involved

2 2/3 hr

RM 9.17

RM 10.55

The labour time costs RM55 /8 hr (8 hr per day)

Labour cost for excavation 1 m3 of soft soil


= RM55/8 x 2 2/3

Labour cost for excavation 1 m3 of soft soil including 15% profit


= RM55/8 x 2 2/3 x 1.15
Total excavation = 40.02m3 x RM 10.55

RM 422.20

EQUIPMENT COST
Cost Of Renting Excavator
Cost of excavator

RM

805.00

Repair and maintenance -RM 805.00 x [1/10]

RM

80.50

Transportation to site

RM

40.23

RM

925.73

RM

0.57

- RM 805.00x [1/20]

Cost of renting excavator for 1 years


Cost of owning excavator for one hour
= RM 805.00/[1 x 200 x 8]

Cost Of Operating Excavator

Driver

RM 95.00

Unskilled labour

RM 55.00

36 liters of diesel - 2 x 36

RM 72.00

2 liters of lubricating oils - 45 x 2

RM 90.00

Cost of operating excavator per day

RM 312.00

Cost of operating excavator per hour - RM 312.00/8

RM 39.00

RM 39.57

Cost of owning and operating excavator per hour


= RM0.57+ RM 39.00
Output of excavator per hour is 8 m3

Cost of excavating 1 m3 of soft soil per hour including 15% profit


=

RM [39.57/8] x 1.15

Total excavation = 40.02 m3 x RM 5.68


Period of usage ; 1weeks = 56 hrs
MANUAL EXCAVATION = RM 422.20
MACHINERY EXCAVATION = RM 227.31
TOTAL = 649.50

=
=

RM 5.68
RM 227.31

LABOUR REQUIREMENT ration 1:2


Skilled workers

Unskilled workers

Formwork

Concrete work

Reinforcement

Formwork

Concrete work

Reinforcement

Formwork

Concrete work

Reinforcement

Formwork

Concrete work

Reinforcement

Foundations

Columns

Beams

Slabs

MATERIAL COST FOR FORMWORK


Material cost:
2. Cement;
a) vol. of cement

= 0.3 x 0.3 x 0.2


= 0.0018m3

Total vol. of cement

= 451.81 x 0.0018
= 0.81m3

Cost of cement

= (0.81 x 1000bag) x rm19.00


= RM 15,451.90

Cost of cement for fixing 1 piece heavy duty tile

= RM15451.90/ 451.81
= RM 34.20

Operating cost:
1. Workers;
a) Skilled workers

= 2 x RM85.00
= RM170.00

b) Unskilled workers

= 4 x RM 55.00
= RM 220.00

Operating cost for fixing 1 pieces heavy duty tile

= (180 days x RM390) / 451.81


= RM 155.40

Total cost of proposed project and 15% profit


= (RM 422.20) x1.15
= RM485.53 + RM15451.90
TOTAL: RM15937.43 (mixer + labour
for all elements)

MATERIAL COST FOR REINFORCEMENT


Material cost
Operating cost:
1. Workers;
a) Skilled workers

= 2 x rm85.00
= rm170.00

b) Unskilled workers

= 4 x rm 55.00
= rm 220.00

Operating cost for fixing 1 pieces heavy duty tile

=(250 days x rm390) / 14452.382


= rm 6.74

Total cost of proposed project and 15% profit


= (RM 31442.21) x1.15
= RM 36158.58 (mixer + labour for all
elements)
ESTIMATING OF CONCRETE WORKS
EQUIPMENT COST
Cost of renting mixer 10/7
Cost of renting mixer = 220.00
Cost of transportation to site = 1/20 220.00 = 11.00
Cost owning per day =231.00/ (5200) =0.23
=2,014.80

OPERATING COST
1. Workers;
a) Skilled workers

= 2 x rm85.00
= rm170.00

b) Unskilled workers

= 4 x rm 55.00
= rm 220.00

Operating cost for fixing 1 pieces heavy duty tile

= (365 days x rm390) / 461.69


= rm 308.00

Total cost of proposed project and 15% profit


= (RM 108080) x1.15
= RM 2014.80 + 124291.70
TOTAL: RM 126306.50 (mixer + labour for all elements)

TOTAL COST
NO ITEMS

DESCRIPTION

TOTAL BILL
(RM)

EXCAVATION COST
1.

By manual (hand)

422.20

2.

By machine

227.31

MATERIALS COST
3.

TOTAL BILL FOR FOUNDATIONS

4.

TOTAL BILL FOR COLUMNS

5.

TOTAL BILL FOR BEAMS

5825.88

6.

TOTAL BILL FOR SLABS

1748.00

6429.00
92801.00

LABOUR COST
7.

Formwork

8.

Concrete work

126306.50

9.

Reinforcement

31442.24

15937.43

TOTAL COST OF THE PROJECT


(RM)

281,139.55

SIMPLE DISCUSSION/ OVERVIEW


The total cost of the project is RM 281139.55.
Then, the construction of column we used Concrete grade 30 20mm coarse
aggregate for concrete work. For the reinforcement , the are many type that we
used as below:

T12, Tensile bar with diameter of 12mm


T16, Tensile bar with diameter of 16mm
T20, Tensile bar with diameter of 20mm
R10, mild steel bar with diameter of 10mm
R6, mild steel bar with diameter of 6mm
R8, mild steel bar with diameter of 8mm

CONCLUSION
As a conclusion, the overall cost of the project is about RM 281139.55 for a single
unit of terrace house.

REFERENCES
1.

Buku Kadar Harga JKR

2.

Lecturers Slide Presentation Notes

3.

http://bceqjan2010.blogspot.com

4.

http://www.designingbuildings.co.uk/wiki/Bill_of_quantities

5.