Documente Academic
Documente Profesional
Documente Cultură
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
0001 00
A2
Sh. 1 of 12
WAFA PLANT
SPARING AND STAND BY
PHILOSOPHY REPORT
A2
03/07/00
A1
19/06/00
P1
28/12/1999
REV.
DATE (DD/MM/YY)
T. MILETIC
M. RICCI
COLANERI/E. BARONE
KASHIM
T. MILETIC
M. RICCI
COLANERI/E. BARONE
KASHIM
L. CONA
M. RICCI
COLANERI/E. BARONE
WRITTEN BY
VERIFIED BY
APPR./AUTH. BY
STATUS
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
0001 00
Sh. 2 of 12
INDEX
1.
SCOPE
2.
3.
GENERAL CRITERIA
4.
4.1.
4.2.
4.3.
4.4.
4.5.
Unit 350 : Gas demercurization (space allocation for possible future installation).
4.6.
4.7.
4.8.
4.9.
4.10.
4.11.
4.12.
4.13.
5.
5.1.
5.2.
5.3.
5.4.
5.5.
5.6.
5.7.
5.8.
5.9.
5.10.
5.11.
5.12.
5.13.
A2
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
5.14.
5.15.
0001 00
A2
Sh. 3 of 12
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
1.
0001 00
A2
Sh. 4 of 12
SCOPE
The scope of this report is to outline the sparing and stand by philosophy which will be
followed during the development of the basic design of the WAFA Desert Plant &
Utilities.
2.
Maximum allowed yearly downtime for WAFA Desert Plant, equal to 28 days at
50 % gas production rate.
It includes unexpected downtime period and scheduled downtime period (for
routine maintenance and major overhaul). Said target is to be considered a
maximum figure and it is not expected every year.
Allowed total yearly shutdown equal to 0.5 %; it means that the total gas
production at Wafa desert can be zero (due to a unscheduled shut-down) only for
less than 0.5 % of the yearly time (i.e. 43.8 hours);
To reach the abovesaid target the basic philosophy that will be applied is to split the oil
separation/treatment plant and the gas separation/treatment plant into two parallel
trains sized at 50% capacity each.
Exceptions to this philosophy will be taken in some places where single equipment will
be spared (see paragraph 4), but keeping the general concept that 50 % of production
has to be maintained.
This is considered to satisfy the max yearly shutdown target because:
a)
b)
the probability of two parallel lines shut down at the same time for accidental
reasons is extremely low;
in case one line is in major overhaul, the other line could be affected only by
small emergency situations which can be solved in short time, enabling said line
to restart well before the period of 43.8 h. In fact all items more likely subject of
failures, such as rotary equipment, will be spared adequately. Failure of static
equipment is not considered.
The target of max total yearly downtime at 50 % capacity is considered reached since
it is possible to operate maintenance on one train keeping half of the plant production.
For sure this will require a careful planning of the maintenance.
The consequence of the required availability target on utilities units is that:
the global availability for all utility facilities directly linked to plant production, such
as Flare, Fuel Gas, Power Generation, Instrument Air, Cooling Water, Steam &
Condensate and Fresh Water Treatment Systems shall be at least as high as
that of process units (>99.5%);
some utilities (HP flare) shall be split into two systems, each one dedicated to
one Process train;
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
3.
0001 00
A2
Sh. 5 of 12
GENERAL CRITERIA
Within each line, stand-by equipment will be provided for items which need frequent
maintenance or load sharing (e.g. filters, pumps), whenever necesary to ensure the
required quality and continuity.
Availability of spare parts, or of a complete equipment, in maintenance warehouse has
been considered, case by case.
Here below is the general sparing philosophy per type of equipment for WAFA Desert
Plant (Process & Utilities Units). Exceptions and particularities to the above sparing
philosophy for units, machines and packages are indicated in the following paragraphs
PROCESS UNITS and UTILITY UNITS.
Filters
2 x 100%
Storage tanks
2 x 50%
Chemicals tanks
1 x 100%
1 x 100%
Compressors
See 4
Pumps:
- Continuous service
2 x 100%
- Intermittent service
3 x 50%
1 x 100%
Air coolers:
- Number
- Number of fans
1 x 100%
2 per bay min
Safety Valves
N+1
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
4.
0001 00
A2
Sh. 6 of 12
4.1.
4.2.
4.3.
4.4.
4.5.
Unit 350 : Gas demercurization (space allocation for possible future installation).
The section is based on two parallel lines at 50 % capacity.
4.6.
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
4.7.
0001 00
A2
Sh. 7 of 12
4.8.
4.9.
4.10.
4.11.
4.12.
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
4.13.
0001 00
A2
Sh. 8 of 12
5.
5.1.
5.2.
5.3.
1 x 100%
1 x 100%
1 x 100% + one in warehouse.
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
0001 00
A2
Sh. 9 of 12
5.4.
1 x 100%
1 x 100%
1 x 100% + 1 in maintenance warehouse
1 x 100%
1 x 100%
1 x 100%
3 x 50%
2 x 100% per heater
1 x 100%
3 x 100%
2 x 100% per WHRU.
5.5.
2 x 100%
1 x 100% per package
1 x 100% per package
1 electric (start-up) per package
1 Hot Oil per package
2 x 100% per package
1 x 100%
1 x 100%
2 x 100%
1 x 100%
2 x 100%
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
5.6.
0001 00
A2
Sh. 10 of 12
5.7.
4 x 33%
2 x 50%
2 x 100%
1 x 100%
2 x 50%
The type of turbines is homogeneous with the ones used for turbo-compressors
(FRAME 5), in order to standardise spare pieces of equipment and maintenance
procedures.
The number of turbo-generators in normal operation allows that if one turbogenerator trips, the remaining one could take the whole electric power and waste
heat recovery duties instantly.
There is always one turbo-generator in stand-by for eventual maintenance
purposes (turbines, electric generators or waste heat recovery units).
5.9.
3 x 100%
1 per Turbo-generator
1 for all Turbo-generators
2 x 100%
1 per EDG (sized for 12 hours min)
1 x 100%
1 + 1 (allows maintenance and cleaning)
3 x 50%
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
5.10.
0001 00
A2
Sh. 11 of 12
These storage capacities are essential for pumping in series operation and represent
safety hold-ups in order to cope with exceptional events and give higher reliability and
flexibility of operation of the whole water treatment chain. Each storage capacity is split
into two tanks in order to allow an intervention on tanks for cleaning or leak repairing,
without need of water treatment shut down, and consequently production shut down.
Sparing philosophy is the following:
Winning Water Well Pumps
Winning Water Sand Filters
Storage Tanks
Pumps
Chemical Storage Tanks
Chemical Injection Pumps
Water Desalination packages
Water Demineralisation packages
Mixed Bed Exchangers
Potable Water Pressure Vessel
Potable Water Active Carbon filters
5.11.
5.12.
Company responsibility
2 x 100%
2 x 100%
2 x 100%
1 x 100%
2 x 100%
2 x 100%
1 x 100%
2 x 100%
1 x 100%
2 x 100%
1 x 100%
1 x 100% + one in maintenance warehouse
one per Area A1, B1, C1, D1, E1, L1, F1, N1
1 x 100% par each Closed Drain drum + one in
maintenance warehouse
Originator
Module
53
Type
Discipline
Identification N
Rev.
LIBYAN BRANCH
Contract N 0001GP99
5.13.
0001 00
A2
Sh. 12 of 12
5.14.
2 x 100%
2 x 100%
1 x 100%
2 x100%
2 x 50% or 3 x 33%
N+1
2 x 100%
5.15.
2 x 100%
2 x 100%
1 per Diesel Fire Water pump (sized for 12 hours min.)
1 x 100%