Documente Academic
Documente Profesional
Documente Cultură
/ "/,o3z,_
"_
_-
__-
=_
[r
- CONTENTS
""
-_
" )i.0
I"-
INTRODUCTION
1.1
Introduction
1.2
Objectives
1.3
Study
Groundrules
1.4
Study
Approach
[_
|
"
SECTION
CONCLUSIONS
:_
2.0
SIGNIFICANT
[i
3.0
PROGR/_IN/_AGENNNT
'I I
3.1
Manufacturing
3.2
Improved
_
8
SECTION
-F_
III
Documentation
Configuration
and
t_,
Government/Contractor
3.4
3.5
_stronaut
3.6
Business
3.7
Organization
r
[_
and
,
4.0
Management
Option
Management
Reports
17
-"
Manpower
32
42
Item
Control
System
SECTION
-_
Management/Control
3.3
Field
11
Control
Methods
[i"
48
55
Summary
66
IV
;_
&._
i
ENGTNEERING
71
.&
4.1
Interface
Control
4.2
Contract
4.3
Field
4.4
Organization
End
Documentation
72
Item=Bpecifications
88
98
Operations
and
Manpower
Summary
105
%
SECTION
5.0
i.._.
QUALITY
5.1
Traceability
[i
5.2
5.3
Inspection
Organization
128
andandIn-Process
Manpower
--
129
Verification
Summary
135
162
_ ;
_.
:o
C
;
s.s
074
i01
I_
L
FORE_qARD
Apollo/Skylab
Study
Duration
Study
Team
Suit
Program
December
Management
17,
1973
Systems
through
Study
April
30
1974
Members:
!
I.
C
[j
Program
Control
Configuration
Engineering
M.
Management
{ _
J. D' Andrade
G. Amey
Control
Quality
Prepared
by:
i_
T. Pribanic
J. McMullen
[._
Resources
McNiff
R.
K. McGahey
Deamer
z-\
f-
_.
([
--u-
;"
Michael
McNiff_
Program
Control
[.i
Approved
_ohn McMullen
_:anager, Space
W
Manager
by:
& Environmental
Systems
[_
"<
Prepared
for
the National
Contrac_
NAS
9-6100
Aeronautics
Space
Agency
-iii-
_ !
.|
I_
I,
SEC?ION
INTRODUCTION
"
Jr
B,
_J
1.0
'_
_
.-
_[
INTRODUCTION:
A management
programs
was
_!
Industries,
through
April
contract
NAS
r_
i
syst_ns
conducted
Inc.,
by
during
30,
study
9-6100,
ILC Dover,
the
1974,
for
in
calendar
by
spacesuit
a division
period
response
issued
future
to
NASA
SA
of
of
606S
Johnson
ILC
December
17,
(Schedule
IV)
1973,
Spacecraft
S
I__.
Center
(JSC).
study
included
past
suit
programThisrequirements
and
_[_
addition
to
[_
-the most
cost
spacesuit
-its
new
modified
effective
programs.
systems
methods
This
in
for
report
order
use
to
during
highlights
ofin
identify
future
the
effort
and
findings.
Past
to
and
the investigation
management
systems
comply
NPC
space
with
200-2,
the
NPC
encompassed
suit
programs
overall
250-1,
NASA
and
development
have
NPC
and
required
program
500-I_
the
contractor
requirements
These
production
of
of
requirements
all
hardware
%.
r_
ranging
i_
yet
each
crew
class
protective
of
manufacturing
of
requirements
these
for
gear
hardware
testing
staffs
i_
from
program
was
and
to
total
unique
in
inspection
necessitated
compliance.
launch
vehicles,
design,
development,
criteria.
The
significant
Inevitably,
complexity
contractor
extraneous
redundant_
areas
of documentation,
data and
control
were
generated.
The identification
_
and
program
management
of a set of
r -
requirements
specifically
considered
!:
essential
It
is
set
associated
systems
of
of
As
approaches
in
control,
to
achieve
recognized,
a complete
expensive.
tailored
for
a result,
both
to
from
that
program
future
this
space
suit
cost
the
establishment
requirements
study
investigated
the
least
implementation
would
costly
and
of
and
programs
has
is
reductions.
spacesuit
determine
an
the
significant
however,
specialized
order
to
be
alernate
method
operational
standpoint.
Past
"
with
the
were
increasingly
and
and
emphasis
maintain
programs
_.
spacesuit
will
balances.
with
have
concentrated
on
more
and
the
require
To
programs
fully
complex
advent
fewer
of
mission
extremely
each
the
dynamic
assurance.
expensive
controls
realize
been
to
Systems
develop
new
program.
Future
and
redundant
checks
inherent
reduction
of
-2........
'_
L_
Ib_
2_
("
overall
the
program
management
structured
major
_
'
[.
systems
a.
systems
Significant
section
and
_-
investigated
used
during
the
Topics
to
in
I"
(:
the
past
be
important
of
applicable
be
several
Apollo,
II:
Skylab,
_ithin
"-
This
conclusions
from
these
integrity,
must
discussed
Section
resultii_g
the
study.
conclusions
portion
of
is
i _i
Sections
VI.
Management
Sections
the
the
item
programs
report
explanation
through
Program
future
end
This
recommendations
III
I_
III
various
Engineerina.
through
V:
difficulties
This
and
Quality
section
experienced
discusses
with
the
systems
and procedures
that controlled
the
inter-relation
of these
groups.
Recommendations
or
'
guidelines
also
c.
for
future
spacesuit
programs
are
included
Organization
section
future
_
i2
these
Conclusions
contained
b.
[_
compromising
summarizes
detailed
["
_i
_
for
accordingly.
management
I_
_
without
and ASTP
spacesuit
programs.
this report
include:
(-,
I
I_
costs,
forecasts
and
Cost
discusses
the
space
the
suit
Cost
Summary
Section
recommendations
program
organization
VI:
for
This
and
savings.
:'
v,
r
2-
'
_1
I
i. 3
STUDY
used
The following
items include the basic ground
to establish
the guidel_aes
or recommendations
(i_
a.
GROUNDRULES
The
ILC Management
Systems
in effect
rules
discussed
during
the
I h
man months
(by skills)
on future programs_
_,
,_
c.
Recommendations
future programs.
d.
Proposed
I_
e.
efforts
as guidelines
are based
in suit
similar
are presente_
guidelines
advancements
to perform
designs
used
The
on future programs.
rate is assumed
delivery
suit every 20 working day@.
for
"
on state-of-the-art
expected
be
to
to be
one
(i) space
i
[_
_
[[
f.-
projected
g.
I""_
The
to
h.
On future programs,
only one (I) cycle Qual is
assumed
to be performed
using the worst case
mission(s)
requirements
future
of NHB
program
Minimal
change
support
will
through
5300.4
quality
activity
be required
the
life
will
be
of
the CEI.
applicable
systems.
and minimal
for
future
depot
flight
suit
programS.
"
'
I. 4
STUDY
,J
At
_ ("
Suit
_-_
major
I [.
APPROACH
the
groups.
with
the
i ["
respective
around
{ _
I_
Apollo,
key
personnel
were
formed
representatives
Quality
Each of
history
the
and
groups.
priorities
i
'_ "
_i
of
the
and
from
the
problem
list
of
areas
each
of
th_
a study
team.
Program
Management,
Business
The
Management
thoroughly
familiar
utilized
by his
specific
were
a',d ASTP
from
as
participants
was
scope
of systems
A
Skylab
study
identified
tasks
as
were
areas
within
list.
The
among
the
each
list
five
Program
I"
established
and
to
descipline
was
to
the
starting
least
two
selected
for
the
final
specific
tasks
!includes
divided
follows:
CMO,
Documentation
I_(
Improved
[_
Government/Contractor
Configuration
Program
Phasing
Astronaut
Field
Business
[!
at
as
that
in
level
Business
Management
Control).
Manufacturing
{
_ I_
13
1 areas
Management
Program
were
reduced
function.
insure
centered
base.
Items
within
this list were
assigned
priorities
accordance
with
theil
potential
dollar
savinus.
Second
9-6100,
CMO,
known
of
groups
consisted
i i_
I
"
NAS
functional
Engineering,
i
conclusion
Contract,
team
and
Systems
Management/Control
Management
Philosophy
Option
Item
Management
Control
Methods
Reports
Control
System
Engineering
Interface
Control
Contract
End Item
Field
Operational
Iii
Inspection
Organization
The
the
initial
baseline
identifying
"
Specifications
Documentation
Traceability
Quality
II:
Documentation
baseline
any
organization
effort
system
system.
and
In-Process
of
each
(Apollo/Skylab
cost
related
Flowcharts,
charts,
and
other
Verification
task
A7LB
problems
standard
pertinent
consisted
Mc4ei
of
defining
Suit)
associated
operating
with
and
the
procedures,
documentation
were
_
_4
li
{
r
_,
_""
used
to
then
analyzed
Advantages
were
team
,
I_
-
support
to
and
made
to
meetings
Guidelines
identified
this
phase.
comply
alternate
disadvantages
of
that
some
NASA
ILC
means
each
measure
effectiveness
were
used
to
resolve
for futur_
programs
problem
area.
When
with
individual
identify
proposed
guidelines
were
requirements,
these
were
deviations
were presented.
revealed
Each
problem
of
were
was
optimization.
identified,
surveys
of each alternate,
final
selections.
were presented
implementation
for
of
and
each
in violation
of known
NASA
program
identified,
and proposed
requirements
In several
cases,
the study
baseline
program
systems
requirer
nts.
did
not
These
completely
were
_
}_
_S
also
:2
identified
evidence
I_
group
and
of
where
their
their
advantages
Cost
effectiveness
was
by comparing
a baseline
proposed
future
organization
guidelines.
The individual
_.
were
retention
then
combined
into
were
was
proposed,
given.
measured
in
organization
_
each functional
(A7LB)
to a
having.implemented
proposed
functional
a total
supporting
program
,i
the suggested
organizations
organization.
E
?&
I"
'
Z_
-i
I)
- SECTION
SIGNIFICANT
II CONCLUSIONS
._,
2,
2.0
SIGNIFICANT
CONCLUSIONS:
,4
NiDe
the
completion
also
:
_
(9) major
These
programs
will
The major
i ii
within
study.
each
result
} [_
resulting
--
|'
this
this
of
spacesuit
savings.
study
include:
c.
Qualify
d.
the first
Reduce
the time.
drawing
to the
CEI worst
item
f.
Allocatesufficient
case
by
requirements
using
for configuration
and
100%
subassembly
in-process
time
early
efficient
systems
g.
Perform
astronaut
fit checks
h,
Streamline
the
data
reporting
centralize
the
data
collection
program
management
the new
mission
requirements
develop
with
ttlan t_e
Increase component
testing to reduce
of reduced
rather
instructions
e.
this
the ATLB
program.
1565
months.
['
j
"
in program
to
and procedures.
savings
in each
manpower
required
guidelines
acceptance
inspection,
at user's
s_te.
requirements
and
system.
control functions.
study area were reflected
to
operate
implemented.
th_
These
respective
individual
new
man
organization
with
This
the
total
one
in effect
potential
at
saving
_
<
ILC during
amounted
to
In retrospect,
this study stresses
the importance
of allotting
sufficient
time e_rly in a program to develop
[i
and verify
_
[_
[
k
from
cost
sections
program
are
b.
in terms
areas
on future
at
Place
the qualification
of subassemblies
rather emphasis
than the onentire
spacesuit
assembly.
i.
Consolidate
Potential
cost
auidelines
subsequent
if used
resulted
a.
i L
i
Additional
in a major
manufacturing
control.
or guidelines
of the
guidelines,
guidelines
__,
,
of this
discussed
report.
conclusions
efficient
and compatibiemanagement
systems.
_
i
: ["
[ _"
fact that
the
bears
tribute
I,
-
during
[_
![:
that
had
Several
!i
_
k:
_i_
[_
of
_f: the
i'_:l
co_it_ent
in
management
to
in
proven
early
il :I _
NASA
for
being
conditions
an_
ILC
made
became
more
discussed
in
aware
cost
this
when
_odify
a more
qualified
_ -exis_.ng
program
systems
m_npower
areas
effective.
report
program
systems.
and
must
was
manageme:_'-syst
costly
operational
the
of
are
in
In the early
phases
of the program,
the
of perso**.lel that were
technica].ly
qualified
program,
resulted
the
_"
both
potential
the
ended
inderrun"
condition
and
II.Cin
cost an saving
efforts.
However,
to analyze
and modify
the systems
were
deeply
technical
and
production
activities.
In the
_.
_ _
program,
this category.
limited
nmnber
:
";
the
contract
to NASA
impact
On
existing,
be
analyzed
proven
for
available,
_an
future
involved
in
later
phases
to
woult_
continue
programs,
systems
cost
must
li
have
il
with
new
i[_
be
effectf>eness
"
1
.
2.c
:
.
'
)
f.
[2
2-
_j
D
3.1
[,
'-
"
_LANUFACTURING/PROGR2hM
DOCUMENTATION
CONTROL
OBJECTIVE:
k_,
To
evaluate
documentation
the possibi]$ty
related
to the
fabrication
Contract
End Item_
(CEI).
by elimination
of unnecessary
LL
of reducing
drawings
program
costs
and control
of
and redundant
Identify
documentation
utilized
fabricating
the all
A7LBdrawings
Spacesuitand Assembly.
Eval'Jate
the
r
" redundancies
L
s
the
requirement
data.
future
could
PROBLEM :
P
!
per
cases
BACKGROUND:
be
possible
documentation
consolidation
and
of the
investigate
remaining
I_
on
.
NAS
was
9-6100
required
MIL-D-1000,
superfluous
li
:
["
to the
|
generation
Type
E, Form
table-of
of drawings
B, which
operations
in many
(TO's).
.....
Federal
Sepcification
"Engineering
MIL-D-1000,
drawings
in this
Type
E, Form
category
shall
B,
provide
original
drawings
_
['
parts
generation
i
.
design."
of all
of the
CEI were
i
' [_
_
_
of
this
sub-assemblies
prepared.
This
requirement,
and
comPonent
stipulation
caused
the
185
drawings
were actually
required drawings
to fabricate
an A7LB
suit
assembly.
The remaining
were utilized
space
only
and
prepared
It was
manufacturing
q
a result
_!
drawings.
were
li
As
assemblies,
st_bsequent
as a *configuration
_
'_
procurement,
without additional
design activity
of an item
that duplicates
the physical
and performance
characteristics
Of the
Ii
[<
Ix
the necessary
design,
engineering,
manufacturing
and quality
support information
directly
or by reference
to enable the
_*
existing
realized.
specification
states,
i.
for
Contract
[ "
the
which
_:
within
in
control
to meet
determined
personnel
the
updating
vehicle
of
5,2_0
(See Appendix
requirements
_
"A")
and
of MIL-D-IO00.
U"
drawings
to manufacture
softgoods
items.
Drawings
which
contained
all the detail needed for engineering
definition
i?
-12-
_
were
L_
so
.
complex
not
and
unwieldly
understand
Table
of
or
use
Operations
necessary
for
requirements
operational
them.
To
(TO's)
the
of
that
was
fabrication,
the
CEI.
personnel
resolve
this
prepared
for
inspection
The
TO
problem,
each
and
consisted
could
a
major
sub-
traceability
of
manufacturing
7
?
assembly
and
instructions
_he
L_
Manufacturing
area
.
"
and
did
numbers,
The
was
assembly.
The TO contained
and Fabrication
Inspection
instructionsoremained
not
sizing
reference
any
information,
FIRS package,
which
the portion
of the
in
the
information
inspection
Production
such
as
part
requirements,
etc.
consisted
of approximately
800 pages,
TO which
contained
this
information.
.
.
[i_-
-,
Early
in the program
_,e TO's and drawings
released
for the first
CEI
(FACI baseline).
A
were
dynamic
_
i
program
was encountered
concerned,
and a dual
changes
were
was required
-
one
for
Any
Class
the
other.
used
for
the
by
TO's
I and
II
Since
each
new
and
was developed
to the system
or
increasingly'redundant
system
f_
not
situation
was
_i
trade-off
study
drawings
maintain
two
the
to
changes
and
field
the
TO's
sites
allowed
of
to
which
paper
system.
were
in
existence
by
other
indicated
in
prepared
The
TO
system
These
improvements
to become
and
a result
be
than
were
However,
would
rather
be
the
being
contractors.
as
it
a change
designs.
TO
inefficiencies
to
iterations.
the drawings
continue
3.1.i).
procedures
had
existing
Figure
caused
the
but
to
system
(see
documentation
sets
to
drawings
one
through
several
gradually
caused
!-_
at
for
different
I_
only
one
changes
system,
designs
as far as configuration
change
control
procedure
of
less
toal
utilized
:
%
This
a cost
costly
implementing
to
a new
system.
_
Upon
design
:
_
receipt
resolution
achieved
and
released
to
classified
require
Suit
of
between
a Change
authorize
as
the
a Contract
Type
Action
to
and
III
make
of
Authority
the
Request.
revision
customer's
Contractor
NASA
Change
documentation
approval.
ohan_es
TO's.
and
This
to
contractor
Notice
the
the
(CCA),
as
system
TO's
was
(CARN)
TO's
such
was
>
were
did
not
permi%ted
without
!_
the
awaiting
NASA
i_
,_'|
process
[ ....
of
-i
_.
formal
_:pp_-oval of
allowed
the
the
design
the
associated
contractor
change
on
to
items
in
practical
preclude Co1_current
progra_n
or
retrofit to costs.
:"
Engineering
the
by
Change
drawings.
Ord
The
approximate.ly
formal
three
ECO
weeks
p]:oce_'d with
production
delays
with
(ECO)
ECO/drawing.
was
soon
generated
generally
to
followed
of
as
was
additional a formal
rework
effort,
being
because
incol-poration
as
and
t_is
This
the
the
revise
eARN
'
document-ation
' r-:
and
approval
RECOMMENDED
"_
is
E,
Form
Type
'_'"
reference
3 be
drawings
sub-assembly
_
prepare
assemble
:?
:[:
!
used)
_
_
are
of
I_
t
This
cannot
goods
approach
(TO's)
government
drawing
indicates
which
savings
_,
as
for
follows
the
drawings
by
as
of
major
for
the
that
Type
suit
soft
goods
need
c0uld
these
and
in
Space
the
to
and
TO's
of
Suit
Con'tractor's
changes.
Section
Suit
be
to
I documentation
revisions
A7LB
the
requirements
discussed
size
preparation
the
require
of
Contracts
to manufacture
(patterns
and
satisfy
used
MIL-D-1000,
3.2
(Appendix
deleted.
drawings
of
"A")
The
would
be
Hours
--
Drafting
:_
_:
This
spent
in
._.:_
L_
{'_
210
EC0|s
K_
50%
of
Support
7,090
28,364
total
the
During
deleted,
were
savings
updating
the
these
21,274
TOTAL
eliminate
the
Mission
_I".
will
are
_I.
requirement
be
for
on
the
approval
list
Suit
(TO's)
will
500-1.
of
Space
be used
equipment
to
NPC
requirements
future
delete
needed
Operations
The
only
in
Additional
recommendations
this report.
f_
and
This
requiring
the
and
PROGRAMS:
Operations
draftings.
MIL-D-1000.
-'
of
drawings
which
the suit
soft
and
Table
that
revised
Table
MIL-D-1000
__'OR FUTURE
recorr_nended
the
"assembly
of
GUIDELINES
It
._t_
.-_
requirements
period
processed
of
the
of
affected
of
not
reflect
4,192
the
unnecessary
September
to
changes
savings
does
blan flours
revise
drawings
man
hours
l_ours
drawings.
1969
525
man
to-September
draftings
wl_ich
cou._d
could
1970,
Assuming
De
result.
"-I4-
F
L
PROBLEM:
i" [ '-.._'
_ ["
configuration
Various
"
subsequent
several
[
[
consolidation
Tilis was
individuals
of
and
duplicated
was
performed
not
by
reviewed
for
possible
for
various
early
data.
controlling
of
program
the
were
Apollo
Program.
generated
FACI
Program,
with
and
baseline
space
the
formats
traceability
suit
additional
and
being
generated
developed,
it
the
end
of
'
etc.
)
'_ _
assembly.
by
or
by other
continued
the
for
requirements
perpetuated
utiiizing
various
modifying
existing
departments.
through
the
Apollo/Skylah
Program,
50
different
CMO
. . .
'
In
of
[i
associated
shop
addition,
orders
this
and
sheets
documentation,
release,
IL
revision
been
documents
system
compiling
that
of
TO's.
the
,,,
RECOMMENDED
and
of
of
were
being
the
,,,
gone
inspection
,
FOR
early
with
not,
assembled
equipment
as
Even
FUTUR_
in
and
the
this
other
was
_ result,
error
initiation
traceability
operator
As
required
mass
than
using
the
equipment
from
obsolete
undetected
per
at
th e
of
i
:
original
latest
have
manufacturing
the
FIRS.
<
_
,ROGRAMS:
program
of
_ould
until
the
inspection
did
the
and
GUIDELINE
Determine
also
paper..
system
verify
manufactured
completion
[i
of
the
instructions
additional
. .
records
on various
form_ts.
processing
, duplication
and
[i
over
prepared.
emphasis
as:
retrofit
status
reports,
charts,
retrofit
kit deliveries,
considering
At
Apollo
configuration
generated
without
the
operational,
encountered;
such
number
progression
documents
of
were
the
became
reportsthiswhich
were
Once
situation
[i:
stages
documentation
departments
-.
_.
the
manufacture
New
E
on
the
were
dash
I [ii
_
During
As
changes.
BACKGROUND:
the
;
4
engineering
different
. placed
,.
of
the Contract wasEndgenerated
Item and toto verify
control the
documentation
as
is
practical
operational.
information
should
funneled
a group
which
informationThis will
be required
when be the
program to becomes
which
has been delegated
authority
for all the data
r_
r':
i
designed
collection taking
and
In
addition,
all control
dissemination.
all
requirements,
i
. I-
should
requested
of
data bedissemination.
i I"
discussed
in
Section
infoz]nation
A system
for
through
this
Additional
3.2
of
this
into consideration.
could
then be
additional
information
group
to insure
recommendations
optimization
are
,"
report.
J"
" [i
-16-
3.2
I["._-._
OBJECTIVE:
IMPROVED
CONFIGURATION
MANAGEMENT/CONTROL
Propose
an
Configuration
which
would
["
System
Assurance,
Program
APPROACH:
A review
departments
consolidate
! i..
[_
Authorized
of
was
the
manufacturing,
Control
CMO
the
data
Traceability
Product
data.
:_
requirements
performed.
following
. formats:
As-designed
and
consolidate
and
SYSTEMS
of
each
of
A goal
established
data
on a was
minimum
number
the
to
of
_
vs.
As-built
Authorized
Configuration
Classification
Qualification
_
I].
Status
Interchangeability
Bills
of Materials
. .
).
.
Softgoods
Sub-Assembly
Modification
Kit Status Drawings
_.
Traceability
[]
Delivery
INTRODUCTION
At
_
}
the
outset
controls
established
Assembly
concept,
of
the
were
that
based
an
on
a total
ITLSA,
EV
from
i !_
'
the
top
[-
the
tested
separable
300
(PGA)
comprise
and
component
removal
of some details
:_effectiveness
was proven
it
easier
to
series
did
Glcves,
IV
drawing
use.
_ach
a PGA:
and
as
control
created
of
the
Garment
together
make
the
control
at
existing
list.
certainitems
components
asof those
they
a separate
more
could
unit.
paperwork,
top assembly
of shipment
components
Gloves,
components
however,
shipped
from the
at time
Helmet
simplify
change
caused were
the defined
removal
components
collectively
functionally
'
A7LB
assembly
methods.Separable
This
Ii_
of
and
configuration
Pressure
formed
a space
suit assembly.
The decision
to
transition
to separable
component
configuration
beginning
Boots,
the
;_ [i
_
the
Lunar
program,
Suit
i_
Instrumentation,
is
Apollo
_ _"
which
Schedule
were
be
Although
its
drawing
making
and it caused
individually
_-
controlled
by
part
number
and
corresponding
assen_._ly drawing.
_ ["
L
The
ITLSA
top
d._s<.m:._.]y
d1-n,...,ing
fo_- example
did
not
reflect
%k
serial
"
numbered
effectivities;
therefore,
a components
[..
_'
:
to compliment
the drawing and Table of Operations
(TO's)
system.
Tlle components
list defined
the dash number which
-.
t :
'
_"
!
_--
applied
r_
Other
to a given
separable
serial
numbered
component
suit
for
configurations
each
(i.e.,
of the
ITLSA's.
helmet,
,)
the components
|!
condition
Change
"
['
[_
authorized
along
Order.
This
Quality
Assurance,
time
initial
of
contractor
had
,
.
required
and NASA
a mixture
ILC
"as built"
each
verification
and
inspection
words,
categories
of
:_
applicable
to the Apollo
'
Both
series
A7LB
suit
different
ITLSA's;
of suit
program,
the A7LB
were
of
cont_.-olling
each had
configuration
two distinct
600
programs
respectively.
were
based
;/
suit
and A7LB
and Skylab
configurations
at the
types
data
there
300
Engineering
the space
engineering
management,
the configurations
of various
components
of which
its own unique rules.
Also to further define the
of the
_.__/_
applicable
configuration
In other
configuration
and
of
of several
complexity
.
number
a description
shipment.
authoritative
I"
[
with
part
series
on the
same
o,
con%men top
period,
dash
(
assembly
twenty-three
01 through
(76) Class
dash
of
I!
[
_.
[.
_
;
I:
of
Integrated
by this
dash
modifying
Torso
drawing
sixty-seven
(671.
This
problem
Apollo
A7L
different
than
the
PGA
L_mb
during
by
existing
o_]es
Suit
suit
ranging
approximately
In each
affected
the
Apollo/Skylab
the
creating
The
Assen_blies
seventy-six
case,
either
from
total
(ITLSA's)
programs
same
-':
a _ew
?.
number
'i
controlled
was
_:
"
is further
phase
number
were
-:
demonstrated
configurations
total
from
changes.
was
this A7LB
configurations
23 evolved
drawing
number
Throughout
(23) unique
I engineering
top assembly
I _
drawing.
created
by
and
on
the
earlier
fifteen
(i15)
_.
drawing.
manufact_,red.
_
_
the same
of P<,,..]
_._' (96) actually
"
The
statistics
referenced
reflect
_-
assembly
drawing
The
many
variations
L.
not
only
made
["
but
als_
became
[_
"_
!-
large
one
was
different
the
ITLSA
supplemented
revised
and
upon
an
on
user
when
from
the
study
engineering
drawing
task
configuration
hundred
effects
the
configuratons
for
for
of
multiple
a time-consuming
drawing
portion
pyramid
_rom
difficult
drawings
describing
drawing
of
this
and
resultin%
one
assembly
_'J" sized
volume
it
differentiate
- top
L.
the
in
of
(122)
approximately
of
to
four
(4)
materials
items.
fifty-wo
Atypical
consisted
twenty-two
drawing
interpret,
had
another.
a list
one
to
one
with
changes.
This
times
same
which
L
["
" [_
,. _"
included
at
listings
and
change.
Reports
Section).
_were
_I [
_J [/
the
one
and
These
the
as
same
redraw.
evolved
Ntunerous
with
each
status
same
listings
with
in
abstracts.
each
change
engineering
:_
engineering
Government-Contractor
drawing
complicated
separable
was
generation
of
component
proven
more
Manufacturing
,
also
(Reference
serve
This
"
:
complete
Management
most
The
cases
end
results
. . . a mountain
drawings.
of
Throughout
program
the contractor
was constintly
trying
to create
piece
of paper
that provided
a complete
description
of
each
_!
to
always
paper
one
matrices
drawing
attempted
:, _
least
additional
configuration.
to
be
an
than
50
different
and
Product
documentation
for
impossible
task
CMO
after
reports,
Assurance
the
matrices,
originated
traceability
and
accountability
I_
requirements.
PROBLEM:
'
o . 0
Configuration
_q
levels
[_
identification
I
'
time
of
occurring
consuming
paper
configuration
block
conf_/ration
included
component
searches
when
was
or
lowe)
the
required.
ror m,
oorm
control
existed
where
ohar_s
were made
to "like"
its top assembly
or (part number)
this
at
differences
0urn
I.
_
-
created
changes
(9)
ITLSA's
(serial
but
only
to
items
without
identity.
An
numbers
00!
the
extent
affecting
example
of
009)
which
/
i
1
**
were
['
Ii
'" 1 _"
configured
to
an
Change
Order
prescribes
change
occurs
A7LB-100000-01.
a change
A Class
for
all
I Engineering
nine
suits
and
the
k-
\
'i
The
top
changes
lower
a lower
level
assembly
remains
an
(or dash
01
level
shipment
to
at
of
the
(ITLSA
dash
a dash
" list
01
was
i_
_,
this
were
were
versus
of
a major
at
drawing
This
!0
because
it created
a Class
II
_hich
considered
good
problems
change
was
not
At
at
time
were
not.
any
comDcncnt
modifications
all
would
The
of
indicate
the
_xact
the
suit.
and
should
have
a part
number
change
of
tracking
required
to
been
Furthermore,
these
but
items,
recorded
There
reflected
management
be
components
with Class
I changes
II engineering
changes
configuration
the
of
five
indicated
condition
I nature
by
sort
records
was
itself
Class
level
assemb]y).
incorporated,
it
as-built
a Class
r [-
is not
were
theoretically
this
there
traceability
document
top
however,
drawing.
if
four
list only
concerned
cases
of significant
which
example),
and
only
of
assembly
only
data
the
as-authorized
_:_
and
when
top
than
A7LB-100000-01;
modifications)
for
01
configuration
r-
the
(other
on
was
not.
practice
since
any
configuration
some
Class
and/or
II
reports
ECO's
Using
I change
1
L
exist,
many
by
was
with
76
_equired
nine
ITLSA's
01 and
dash
Class
I ECO's
of dash numbers.
PROBLEM:
be
records
shown
on
as an example,
only
and
yet
various
if a Class
a portion
of the
level
II ECO's
identify
data
to
affecting
lower
Assurance
were
implemented
a dash
inherent
23
the
Quality
02 with
changes
and
the
possibility
Multiply
several
this
significant
of
condition
Class
No defined
policy existed
using causing
acceptable
alternate
(interchangeable)
parts for
without
a configuration
_;
change.
J_
BACKGROUND
The
_ C
and
definition
Skylab
of
program
as
stated
_ _
had
to
be
designed
components
[-
interchangeable
component,
F.
assembly
I_
This
and
_-
[-
involve
was
be
_ I_
implemented
, |_
improvements)
to
used
an d
practices
:
Apollo/Soyuz
classified
A7LB
arm
["
not
for
an
acceptable
without
FUTURE
Consolidate
the
thus
new
any
not
implementation.
occur
drawings
due
if
to
(with
was
arm
part
configuration
hardware
was
latest
to
the
that
program
philosophy
A7L
design
used
on
bearing
for
the
was
the
optimum
impact.
PROGRAMS:
information
reducing
contained
the
manpower
on
various
required
and
_L
)
i [
_
associated
visibility.
costs
and
still
provide
sufficient
controls
and
;
%
_be
I_
[_
generated.
Ii
report.
be
"
The
which
subassembly
in the Table
of
should
be
drawings
Operations.
similar
The
identified
A7LB,
etc.
identified
contractor
to
remaining
by
Those
by the
the
that
would
would
The
shown
items
and
d&termine
be redundant
to
results
of this
on
which
appropriate
review
information
review
Appendix
"A"
required
drawings
model
prefix,
items
not requiring
drawings
contractor's
numbering
system
of
this
,_
R
would
i.e.,
A6L,
would
be
'
(
!
prescribed
'
hardware
used
deviations
alternate
to
qualified
austerity
the
complete
difficulties
hardware
where
affected
would
an
This
Project
was
that
available,
Test
FOR
flight
:_
(or top
prior
major
potentially
to
change
and
Garment
other
subassembly
of
As
all
Each
the
that
Apollo
changeout
only
for
number.
Each
component
with
the
the
Pressure
changc
category
funding
bearing
documentation
fact
accepted.
as
GUIDELINES
One
a suit.
was
were
to
changes
in
A7LB
nun_er.
was
ECO
the
a spares
configuration
part
for
re-identification)
data.
costly
_J
replaceable
same
an
was
in
the
a configuration
number
configuration
remained
in
prescribed
same part
which
required
occurred
be
the
part
part
would
that
to
having
PROGRAM:
interchangeabili_y
Assembly
CEI specification
those
components
with
the
SUIT
_ [
_
'
APOLLO/SKYLAg
-21-
Ir
i
i
A follower
Ii
document
i.
_"
r_
tag would
is two-fold:
Replace drawings,
inspection
L.
2.
Provide
TO
one
for
vehicle
" An
The
authority;
C.
Description
the
_i
the
to use,
- each
assembly
would
D.
Operation
Number:
assigned
I
arms
the
I'
I L,
revision
item
to
<
number,
go-ahead,
"
etc.
to complete
i.e.,
for
!
_
<
charge
be noted,
cure,
of
3 2.1
of this
required
detail,
required
in Figure
join
install
arms
wrist
an operation
to each
and
an organized
order
detail
this
the components
and
production
time
which
"
number
example
etc.
would
005 - join
and would
manufacturing
be
or inspection
I.
is a manufacturing
function
i I
completing
of inspection,
column
accept
DR, MRB, etc.
F.
!
! f-_
!-
G.
" :_- H.
note
or
quality
Bill
the
scheduled
task
would
item
and
being
would
the
stamp
be
the
where
time
authority,
applicable
representative
lapse
of Materials:
pa_ts
In the case
dispositioning
government
inspection.
Hours:
individual
initial.
inspector
Acceptance_
piece
[i
the
- the
would
Government
the
the detail
_,
identify
instruction
to use
Accept/Reject/Rework
S.
i i
1
subassembly,
nomenclature,
order,
of
of materials.
to indicate
fabrication
purpose
traceability
manufacturing
flow.
sample of a format is illustrated
spares
F
orders,
explanation
of the form is as follows:
A.
The part number and serial number
be fabricated.
B.
the
for
The
and bills
the operation
required
shop
records
to fabricate
be generated.
would
in hours
!
,_
the
verify
-
to compl_te
noted.
all
assemblies,
raw materials
fabricated
_,ubassemblies,
required
would
to complete
be listed,
i_
(
i
r_
,. .
I.
,
i
_<
C
J.
K.
i L
L,
,
The
maiDtain
The
part
number
and
amount
and
of each
nomenclature.
line
item
required.
Quantity
per unit,
quantity
pen lot - traceability
the number
Lot
and Serial
Numb e_:
the material
either by serial number
verified
and noted.
or
Operation
numbers
operation
where
line
item
Tag:
could
the
"Follower
a fast
release
- the
lot number
is utilized
be
system
should
number
would
a Type
would
be
or nmbers
listed.
III document
the program
be
_o
dynamics
["
dictate
it.
documentation
;
However,
this
should
should
be changed
be
by
the
the
exception.
Procedures
of
the
Engineering
Change Order and the class established
accordingly.
A control
and verification
document would also be
L
L_
required.
could
be an The
"Au]_orized
and
Delivery A sample
Schedule"
(ACDS).
purpose
would be two-fold:
The
replacement
Components
[k
of the
following
C,_,figuration
of
this form
documentation:
List
Authorized
Change List
Supplemental
Change List
[_
"
.C?mponent
Li_t Progression
Chart
configuration
Identification
index
_
_-.
Configurati0n
Status
Open Engineering
and
2.
Listing
Retrofit
Provide a configuration
status for NASA as well
for
all
contractor
Report
mechanism
and qualification
as an active document
departments.
I_
L
require follower
tags
on drawings
should be
of information
)
_
All
,
_
with
family tree.
All
prefixed
and would
and drawings.
However,
the details
kept to a minimum
to avoid duplication
the T0's.
Ideally,
they
could
_
?
be
outline drawings
since the configuration
of the components
comprising
tile assembly wou_d be controlled
by the ACDS.
r:}____.
"
23
:;
$-
" -"
"
r.,
A samole
[._
_
An
of
this
format
is illustrated
in Figure
3.2 2
explanation
of the form is as follows:
A.
Dawing n_mber and name.
[..
B.
Custom - identification
of
article is custom sized.
! i [',
C.
Class
I ["
" ! ["
D.
{
I
List
-.,_
I:_
...._.......
--4_.
_ .
- indication
of Materials
the astronaut
of classification
-. the
I, II or III.
assemblies,
subasse/_blie_
"w..n',_.sC-'
_, I _i
L -xZ,_:_._.___eI,T.%;-_<
would
be identified
by part
and piece
parts required
to number&"
assembly
As-authorized/as-built
F.
show
[-:":
_-_'_w_
__
any
incorporated
authorized
given
"
Delivery
each C_I
ACDS
would
Schedule - the
or modification
be released
- this
would
the present
could
be relative
receipt
A CCA
is received
i_
CEI's
The
authorized.
a change
3.2.3.)
:_
of a production
"
operate,
i
!
scheduled
ship date for
kit would be indicated.
how
(See Figure
would be compiled
from the follower
and scheduling
section.
To indicate
simulated.
I'
to
information
requireu
tags and theplanning
would
i
,
configuration._
[.
_
the system
those
article
order
("
for only
upon
the
go-ahead
and
change
aCEI.
H.
_-.'-"
latest
situations
A_F__%_
]i*_
the
if the
cycle
will
be
for an arm
assembly.
Nine
units
i"
_
_ ! C
"
I _
and
Qualification
_i
retrofit
go-ahead
Ul
has
contractor
(see Figure
,
e"
S/N
status
been
chaP4es
3 2.4)
is not
received
the
"in-line"
effected
for
lower
and
incorporation.
production
21 arm assemblies.
arm
The notation
assembly
AR01
humber
is placed
under
005 and
listed.
the modification
these CEI's are
|_
as a -02 configuration,
that the present
configuration
_01 and the proper delivery date for the modification
...
The
I_
_
t_
part
order
_.
SN001,
is
authorized
is
kit.
-24-
[
_
L_/'"
k. :
When
the
the
Symbol
changed
006
if
to
future
kit
the
-02
is noted
under
NA01
008
indicating
program
S/I_'s
010
Concurrent
"
incorporated
AD0!" and
the
requirements
necessary
for any of
without
qualification
is
A replaces
through
under
modification
the CEI's
testing
through
with
"
002,
003,
configuration
dictate
that
this
004
is
and
and
change
i
is
015.
3.2._)
This
the
and
would
015A
d to
be
above,
the
manufacturing
be
changed
change
the
the
addition
is
I04002-01
would
be
the
part
of
arm
number
the
and/or
explanation
shown
by
is
as
changing
follows-
the
numbers
from
revision
of the
block
piece
would
affected,
104002-02Land
only
drawing
the
which
to 010B
show the
021.
an
Figure
the change
may be incorporated
The Symbol
A remains
(see
010A and
be change
S/N'S
5)
the
production
CEI'sas would
be revised
would
be modified
necessary
and
in
this valve
case
relief
3.2
configuration
present
as-built
figure
the
"follower instructiOnSg
ta " for
inspection
and
-
(see
and
new
assembly
and
015B.
The
part number
changes
added.
to
The
and
revision
pressure'relief
_.
this
revision-may
block
and
pressure
would
_"_
_"
only
illustrate
valve.
"j"
f
)
_O1:Tr,.
_'_
-_
d,,
"
;
k...
I"
_(:
[-
AUTI-IO;I,U].'*,,."
T". O.
LOT SIZE
START
I,O.
P':_
o3o
n,.'scon.ec-f
O35A
i-
'
I ..
[:
1- $,q,-
i:
-juJ
- 1- -]> _i
._
I_)ART NAME
--_
J.
............
,,
_.-
(...
I"--, I-
. ...i
......
.,
,-
"
r-
.....
72;o
!.
.... -045A
-.
_'
_"
'l
....__m --I
..ors:,
]
Store
..,i.
Ab':_!. !.h'.-._-T
III_C,.ICZ,:XI
...o.,.,-_.
....
InslallWrist
.:.
!l.}-':
__ ...L,_.._._
_]
ACO':-r_
]qUh.ID?-_E.ATLL_-I'.u:_."..:-:,:
-_
NO.klEIqC].ATU
SIN
O01
CO_.IPL_TE
D:'ZO:ZPTTO':
--
REV
PART
OXm t
""
FOT_,I..Ov<E.'.
r, "I'AC
l0
IUN IT
_N
_ - F
J _
i
_
OPERATION hL".,,B!.,_q
It
t,
i_
Ill
[_
&
%
'>
-t
1'i
Up.p=e,
lrl
Arm Assy.
_'T-190043-04
Adhesive
_TII_T0'_'0'
(-
.=
302-104003201
""
_'_,r_-_d
'
302-I040910-0 :;rl
st Di_connect
---
014
020
AIR
---
N/A
010,
020,
A/R
''"
O'
020
.....
---
vzCUii:
/
026
O.
035
035
'I
_.l'.lll'_'
Illih ram,Ill
HI. I_o,],.(Lqlll_iP,:l
2:
[-
3.3
_ ,
GOVERNMENT
TO
REPORTS
consolidate
Reports
_NAGEMENT
OBJECTIVE:
_ L
- CONTRACTOR
as
as
possible
repetitious
APPROACH
:
many
Government
under
activities
one
and
- Contractor
control
data
in
order
to
eliminate
files
%
/
!"
Methods
of
Contractor
r-
"
management
Apollo,
Skylab
tion
new
to
controlling
and
the
quantity
documentation
ASTP
concepts
programs
of
of
used
were
control
./
Government
to
support
examined
These
in
concepts
_i
the
addi-
were
evaluated
_.
for
necessity
-_
Cost
savings
Skylab
and ASTP
!:
centralization
,_
GROUNDRULES
i.
The
cost
effectiveness
Apollo,
data
techniques.
USED
space
1973
and
FOR
suit
was
used
STUDY:
program
as
I_
_
i '_
for
the
study
the
period
of
1970
through
baseline.
INTRODUCTION:
Large
quantities
tation
were
prepared
;:
programs
'i_
the
As
suit
;:
_.
;.
,
,
a result,
program
preparation
of configuration
management
during
the Apollo,
Skylab
of
the
office
organizational
similar
different
functional
have
been
examined
for
future
suit
duplication
reports
groups
in
this
programs
and
which
files
and
documentation
These
with
will
the
problems
in
a cost
! _.
14
reduction.
PROBLEM:
I_
Duplication
of
files
within
the
Program
Office
structure.
I_
ii
During
.
_roups
prepared,
Similar,
the
wiehin
Apollo
the
approved
and
in
and
program
and
some
Skylab
suit
office
organizational
functioned
cases,
the
in
same
programs,
a_cordance
several
structure
with
documentation.
-32L2
I
1
:_
by
recommendations
result
:_
?
within
structure
occurred.
report
of
documenand ASTP
I,
I!
_'
"_
As
:
-:
_.I(.....
,
own
r"
a result,
created
and
maintained
and
produced
sepa_'ate
identified.
{_
of
files
the
in
each
systems
of
study,
the
only
files
at
similarly
the suit
related
contractor's
data.
For
"data files,
additional
requiring
a large
work
deals
This
I_
[}
status
)_
Some of the
listings,
listed
in
Many
separate
typical
management
etc.,
investigated
Figures
3.3.2.
factors
contributed
files
at
reorganization
functions
maintain
the
and
suit
the
contractor's
relocation
(ii)
_
_
working
evolved,
thereby
all the data.
reports,
included
towards
with
facility
containing
each of the separate
clerical
force
to
similar
configuration
management
customer/col_tractor
reports.
It is estimated
that there
were at least
eleven
[_
,
_
blocks
however,
";
their
set of files
to perform
their
duties.
This group
organizational
structul:e
section
group
" "
i_
!
"_
each
various
is
considered
matricies,
those
items
generation
facility.
of
i!
of
The
interdepartmental
:,
._
i I {
'
'
groups
throughout
the
program
of the
larger
generation
departments
of separate
within
the
the
files.
When
Apollo/Skylab
prime
some of
program
cause
!,
the
structue
i
'_
.,%
_:'
[i
-
were
dividedadopted
into
new areas
I'
reorganizaticn or
department
_
If
.....
_..t_,"
/
_ _2-J' i
i__._._._
_"
_.
'' _
_J'"
__
_:
with
the
[,
(.i
"}
for
When
this
department
their
own
occurred,
head
and
reference
the
the
whencontractor's
the DCASR
the
files
Another
was
all
report
originator
of
the
personnel
facility,
This
data
a
area
:.
of
remained
activity
would
to
the
at
, :
,
file.
were
another
a newrelocated
file was to
established.
method
establish
techniques
to the duplication
used
for
resulted
his
own
in
the
distribution
-3:3-
,:-
_i .i
records
kept
the contractor's
resident
engineer's
the same data file;
factor
the random
which distribution
contributed
various
files
these
file.
duplication
was
agencies
located
dissemination.
of
existing
relocated
, facility;
the DCASR
and the NASA
; At one time,
both agencies
shared
of
--
the supervision
keeping.
Often
portion
involved of the
thatphysical
department
re-location
to anotherof
One example
of file
the two governmental
_however,
part of
i_i
..
,"_
_
plant.
generate
[
1
the
smaller
their
owngroups,
file
requirements.
i
[I
used
t
with
technical
and
[-
Since
r-
engineering
_.
internal
EM's
were
each
distribution.
control
board
for
was
a PD during
approximately
!i
instances,
severa!
copies.
This was
[i
of
Thispersonnel
desire
served
program
governed
of the Apollo
(30) in-house
resulting
for
copies
in
of
the
part
the
customer.
and
his
own
mangement
contained
by
The
people
from the
partially
due to
to
which
established
They
(CCBD's).
the peak
thirty
by
management
as
were
Project
conveyed
originator
not
directives
was
departments.
instructions
and
documentation
different
PD's
tovarious
program
the
by
techniques
(EM's)
daa
generated
personnel,
directives
suit
EM's
contractural
were
distribution
Memorandums
(PD's).
I-
[,
random
Engineering
Directives
Typical
normal
average
pertinent
change
distribution
and Skylab
programs
copies.
In some
same department
received
the constant
change-over
new
oncoming
needs. in
separate
filespe_sonnel
is prevalent
any
industry_
During
latter
of
the
A7LB
suit
program,
_,
review
l
! !
was
As
of
all
conducted
a
a
were
only
the
an
GUIDELINES
FOR
during
is
reduce
was
reproduction
employed.
sending
copies
department.
of
SUIT
and
Apollo
and
Skylab
programs.
control
and will
result
in a considerable
A detailed
discussion
of the reco_nended
Similar
suit
_
did
ease
stop
data
(EDP)
be
list
As
centralization
used
to
and
data
cost-savings.
electronic
data
presented
in
this
prepared
by
the
enhance
guideline.
PROBLEM:
{
[
be
not
distribution
that
processing
will
did
data
electronic
(EDP)
reports
effort
processing
costs.
distribution
PROGRAMS:
files
reconmlended
data
This
result
data
Data
somewhat;
however,
it
of the routed
copies.
of
the
distributions
it
by
each
FUTURE
Proliferation
to
system
of
costs
copying
respective
effort
reduced
head
reproduction
additional
occurred
their
router
I
_.
in
result,
listings
to
data'and
contractor
reports
and
were
even
by
different
government
and
the
inter-departmental
_
,
groups,
i[
1
'
-34g
I!4
.
'
;
_ i
_
\.
'
BACKGROUND:
A problem
duplicagion
of
and
key
inherent
to the aeros_ace
efforts
of data
management
dissemination
factors
were
I"
_
I.
2.
by
the
Ill
review
These
'!
_
i
documents
lack
of
a
reports.
Examples
occurrence
since
understood
each
Some
existed
I'
in
existence
of
3.
QA
The
"
similar
Action
Profile
These
the
!
similar
requirements
(
reports.
few
reports
central
and
data
Card
data
of
and
the
CMO personnel
a normal
difficulty
generation
to
which
commonality)
include:
Components
List,
Log.
Open
Engineering
Flight
Readiness
Status
Engineering
and
Drawing
over
pro_eriy
the
contract
Status
cases
of
a period
by
data
providing
::
Log,
administered
same
and
Review
Report.
Change
illustrate
meet
& R personnel
Serialization
Retrofit
evolved
control
duplicated
Check
List and contents,
ARD-001,
Matrix,
Configuration
Status
File,
that
or
many
QA
had
Report,
Status,
Schedule,
examples
validity.
operations.
report
due
its
counterparts
and
other
& R Component
ARD-004,
Index
of
combination
Package,
related
caused
contractor
operations
Listing,
Waiver
Incorporation
_.I"
:'
and
to
explanatory
customer's
Historical
Program
Mission
."
t
_v
other's
Component
2.
as
fostered
the
formal
disseminated.
distribution.
data
source
customer
examples
and
i_
after
central
being
no
questionable
usually
include
the
(shown
1.
I'
_--
is
to
has
the contractor
reports
and customer
their
countezparts
data.
This was
understanding
which
prior
data
corrective
The
data
itself
uncontrolled
favoring
favoring
data
|%..,
is
concurrence
the
Two
paper
data source
paper
and/or
Therefore,
I
the customer
and contractor.
cause
of this problem;
Uncontrolled
No central
Uncontrolled
industry
is the
report
generation
Drawing
Listing.
multiple
of
several
could
!
years.
combine
management
fewer
consolidated
t "
, ;-_
'._(,
,
GUJDELINES
It
FOR
FUTURE
SUIT
is recommended
to reduce
and
be
used
of
similar
data
and
as
PROGRAMS:
that a data
centralization
system
a goal eliminate
the preparation
reports
by
different
contractor
and
customer
groups.
f-
[.
follows
I"
The
:
objectives
of
A.
To
and
monitor
a central
data
control
all
source
data
would
be
as
distribution
!.
,_
i_
relative
to
contract
needs.
the data
requirements
established,
the data
I_
L.
_
[-
the
number
of
[:
Also
any
requests
["
have
To
copies
to
organize
._
encompass
service
i '_
data
L_
be
C.
To
the
control
monitor
and
surveillance
discourage
D.
TO
data.
--
t._l
(iii'
_
T
during
the
Since
files
and
files
became
of
any
data
data
was
for
toward
the
A7LB
complete
minimal.
cost
savings
in
Elimination
of
!and instituting
copy
counts
separate
should
file
keeping
the
central
point
for
the
central
data
source
and/or
generates
requested
- ELECTRONIC
documentation
Apollo,
of
as
to
department
policies
Xerox
order
all
from
data,
this
source
current.
manufacture,
quantity
area
RECOMMENDATIONS
Manual
material,
be
of
be
cases,
administers
status
will
SUPPLEMENTAL
many
current
the
CMO
material
of
one
either
!_
data
and administrative
efforts
reproduction
in
the
reproduction.
designate
all
I''
data
in
liaison
would
effect
daily
__
of
CMO
door"
'
area
by
"open
would
central
source
source
transition
il
distributed.
copies
the
data
centra?
|*_
by
Since
the
the
_-
approved
functions.
and
additional
central
reproduced
CMO, engineering
program,
i I
_:
once
and distributions
are
control
group
would
control
for
the
essentially
that
office.
B.
means
first
_
This
Skylab
documentation
continuous
a major
control
ship
and
and
was
trace
ASTP
activity.
and
As
used
each
PROCESSING'
to
receive
Contract
programs.
previously
updating
DATA
Due
discussed,
referral
a
result,
End
to
Item
the
la_'ge data
back
the
to
these
methods
.of
<
Electronic
|_,
: I "
;
_
this
study.
raw
material
shipment,
'
;
Data
The
t"
An
EDP
throuqh
subsequent
common
A colmnon
(EDP)
Sy.;teln is
receipt
and
Processing
data
base
base
investigated
recommended
the
QA
data
was
R and
approach
approach
is
f_om
fabricat.ion
and
during
tile tJ.m_ of
phases,
f_nal
CHO monitoz-ing.
for
EDP
a computer
is
recommended.
_,rien_-ed
central
information
for
:
use
system
by
all
available
in
["
a time3y
planning
of
and
accurate
rather
than
o_
programs
matrix,
,,
by
the
need
yet
flexible
only
for
I
ECO
_.,
!..
at
which
both
It
are
its
by
is
a data
makes
useable
and
for
the
processing
of inter-related
data,
direct
access
methods,
methods
to
to
be
meet
components
to
update
source
other
current,
the
and
of
the
system
does
not
which
Through
was
used
utilization
data
basis
of
the
reconunended
the
computerized
The
system.
proper
data
inputs
reports.
satisfies
maintainable
mu] c"ple
is
how
the
on
CCA
management
system
users.
requires
base
as
information
used
capturing
req_]...._'e
re-entry
3 3 3 illustrates
pertinent
:.
._
for
areas.
a conunon
Figure
of
was
list,
easily
needs
operating
as
the
it
,'se of
was
support
various
data generated
during
the the
Apollo
programs.
As illustrated
in this
table,
ECO
ii I
files
oper,_tional
ARD-004
and COMPHIST
data
this structured
information
example
system.
data
':
_,
data
contractor.
sequential
information
uses
which
generated
needed
One
for
together
files
information
by
enough
once,
various
_
the
files
manner
traditional
ARD-001,
The use of
Information
}
of
non-duplicated
technique,
,"
{.
I
structured
purposes.
technique
of yping
is used tc retrieve
the
areas
set
[i.
.'
integrates
operating
A chaining
_.
which
for
ECO
of
numerous
EDP
would
part
be
used
to
,,
and Skylab
contained
other
documentation.
methods,
' :_
;?
! "
the
provided
number,
the
the
serial
number,
;'
' I
effectivity,
authorizing
each
referral
back
:.
I. .
If
exisgs
'_
(-
r,
;:
doubt
easily
!.
cross-referenced
checked
through
with
with
to
the
the
the
CCA,
and
the
other
data
EDP
master
and
other
pertinent
will
enable
provide
information,
record
files
data,
easy
quick
it
information.
could-then
since
the
be
ru_-off
)
could
_ i
....
L
\_
reference
output.
Additional
{"
for future
_-
program
r-
suit
{_
a structured
!,
CEI separable
2.
considered
the
final
_ _
to be desirable
and O_tainable
Component
from
Listing
component
list
component
this
EDP
generated
expanded
by
for
in the assembly
each
sequence,
authorized
configuration
to that
which
was
i _
1
built.
configuration
reference
3.
r_
Additional
manner:
[-
a.
The
ACL
Report
[_
its
_-
[-(
....
generated
any
!
CCA
by
c.
Vendor
could
f,
h.
master
respect
to
listing
to
and
the use of
reduction
of
or the
show
are
included
the
expansion
end
item
techniques
i_
provide
a comprehensive
management
..
reporting
vehicle
when
pertinent
into
the
to serve
information
for
the
timely
customer
vendor
common
system
_-
concept
'
I-
is to first
of EDP
_"
secondly
to centralize
I"
accurate
reports
critical
times
f "
flight
!.
An a major
reduce
the
control
number
applications,
flight
and
savings.
for
and
data
accurate
as well
future
of reports
the data
in a timely
(i.e.
! _
I
iI _
I
data
as the
-.
cost
I '
will
contracuor's_needs.
The
i
!
base.
The
t
i _
rating
implemented
i_
I _'
o_ effectivity,
be
files
follo_ing
and ECP's
traceability
also
noted.
inquiring
with
to its components
used
be
in the
provided
of each
component
structure
!i
_ .
will
is possible
ECO's
assembly
of any
recognized,
records
kcan be
status
are
-_
i_
I
_"
CCA
traceability
as to the
b.
differences
to existing
,-_
*,
to provide
The Fabrication
List (trace data) is a structured_
list of components
(as built) which compares
the _
programs
used
_ -
As
,_
information
An Authorized
[
,
documentation
are:
I.
"i.;_
_ _,
_
all
source.
fashion,
readiness
formal
The
The
and
production
reviews,
will
application
and matrices
especially
design
goal
suit
reviews)
of
during
actual
will
be to service
result
material
-38-
:,
., _ -_
. _#_._,_
...._ .....
,_
_-_
.....
. ....
-_ ....... ..= _ _
_-_++
........
.......
_.........
...........
_.-,,._i_,_-_--__'_
_.
I:
inventory
production
i |. C,
managem,_nt,
-"
_-
control,
configuration
control
and status
listings,
and delivery
scheduling,
traceability,
cost
and
retrofit
requirements
all
rom
one
data
_
_
.
source.
t_
In
F:
I_
F:
L
conclusion,
this
recommendation
for
processing
the system
is the result
of an investigation
feasibility
for future
space
suit
a_ditional
detailed
and
"is recommended
to
of
all
necessary
study
involving
a programmer.
completely
a systems
(approximately
create
and
EDP
control
and
to determine
programs.
An
teasn,
nine
implement
consisting
months)
the
control
data.
._
-._
?:
-g
5
"
_,'
-39-
I.
[_
DOCUMENT
Component
CCA
{'_"
TITLE
lli_torical
STA_DAP_12" DT_TRI_UTION
Report
Matrix
-16
Components
List
(CL}
15
ARD-001
!"
_RD-004
i ['"
3"
Program
_'
Action
"23
Review
Status
[_
Formal
Reiv_w
Chit
Change
Co_ponents
List
Engineering
23
Formal
Engineering
23
Open
r_
:
Section
Open
Engineering
A_-licable
Mission
Close
In Flight
!%
23
Checklist
Documentation
ti.
.17
23
or
RID
Status
23
Log
23
Progression
Chart
15
(,
Co_figuration
""
Mission
_.
Au_,orized
._.
in
_/
[_
"'"
Mission
ConfigurationMatrlx
J
!'"
"
t',
Change
List
Authorized
Change
Change
Order
Waiver
Field
Deviations
Operations
I.
Systems
Safety
Field
Optional
'
_.
"
J
i ,_]
-,
Drawing
Index
Status
Retrofit
Status
ECO Review
EC0
(SACL)
-.
_:
10
(ECP)
11
As
30
Schedule
Package
(FOB}
Hotice
Item List
Lis_
,.
"V
Required
Min.
<
--
14
12
't
lO
12
':_'
"12
I0
(FOIL}
"
lO
FOIL
Card
'_
ii
12 Min.
Record
Bulletins
:__
11
Incorporation
Matrix
Review
8
10
(PECP}
(EM's}
.i,torioal tatu
.Drawing
List
(CCR)
Magnitude
_. Stetus
Supplementary
._
Change
Record
Proposals
of
_"
.'
! 1;.
9
Ii
(ACL}
Supplementary
Readiness
10
Notice
Flight
li
(CII}
10
Status
Open
Engineering
and
Equipment
Allocation
t._, ,
Index
PGA TLSA
Sizing
Adjustment
Pro_ect
Directives
-6
Waiver
Prel_inary
ECP's
Engineering
Memorandums
"
)
'_:
waiver
status
Log
Rough
("
21
Classification
Status
Engineerin_
..
20
Status
List
(CSL)
Progression
Chart
Configuration
(AMCI)
Board
Identification
Authorized
Control
Conflguration
:_ ' I'(
6
13
Component
Flight
I, II &III
Gear}
Configuration
Dash Number
Status
CEI/Separable
List
(Class
Waiver
i.
Account
Matrix
Minutes
& Agenda
Change
Directives
(CCBD)
:_
-_
Change
Profile
File
(CMO)
AS
& ERRC
i:
Required
}o_
6
8
5
Report
21
Di_rlbu_ion
FIGURE
3 3.2
I:
-40-.
R_
....
t
CO._.ION DATA
SOURCE
%
_
_
\'"
- ENGINEERING
t.
The
ECO
provided
data
'_
Component
CCA
Components
_ {-
CHANGE
ORDER
(ECO)
for:
Historical
Report
Matrix
List
ARD-001
ARD-004
Program
Action
Engineering
i"
CL
Check
Changa
Progression
List
Log
Chart
AMCI
;:
_,
!"
CII
r-
Dash
t._
ACL/SACL
i'(
t
("
_:
_-
Number
Progression
CCR
=
ECP
Drawing
Index
Drawing
Status
Retrofit
List
Status
|_
Report
t j
I-
I-
I{ _,
Figure
3.3.3
?-
-41-
._
e,
t.:
"
3.4
TITLE
f-
Proglam
_ (-
Phasing
Philosophy
OBJECTIVE:
\L
I"
TO
program
%_.
overall
impact
Design
i
reduce
of
program
engineering
Verification
Testing
costs
by
changes
and
minimizing
occurring
the
during
Qualification
Testing.
BACKGROUND:
Durin_
_
t
Suit
the
program,
Apollo
and
schedules
Sk_ab
were
phases
very
of
tight.
the
The
Space
program
would
it.
not
allo_
enough
time
for
the
start
the
completion
of
Qualification
i [-
" Testing
i"
prior
Changing
"
mission
additional
_'j
with
_ ._.
the
_ '
to
to
profiles
requirements
the
redesigns
of
manufacturing
were
constantly
of
to
meet
the
suit,
the
enlarged
space
suits.
demanding
which
in
conjunction
requirements,
caused
qualification
15 months
testing
on
the
phase
A7LB
to
space
extend
from
four
months
suit.
PROBLEM:
I_
Design
the
Verification
fabrication
!"(
Qualification
L.
production
of
Testing
space
The
the
DVT
Testing
(DVT)
qualification
was
was
space
parallel
to
concurrent
suit
the
with
and
fabrication
of
suits.
and
Qualification
[_
mission
requirements
than
comFonents.
!._
BACKGROUND:
of
an
Programs
entire
space
were
suit
based
on
assembly
the
rather
_4
by
This
[L
.
especially
Testing.
&
not
only
formulated,
but
until
was
significant
cost
now
retrofit.
reached.
The
[
on
_
,_i,-'
the
impact
DVT
and
FOR
problem,
items
Qua!_fication
level
contractor,
as
the
and Qua]ificatic_
space
suit was
with
the
could
the
delay
produced
be
government
had
that
a
would
PROGRAMS:
programs
depicted
in
being
FUTURE
delays
resolution
concurrence
the
on
program
of the DVT
the entire
a design
design
GUIDELINES
a component
enable
significant
until
Compounding
require
RECO_4ENDED
caused
in the initial
phases
If a failure
occurred,
"impounded"
>
situation
in
event
should
Figure
of
3.4.1.
a failure,
be
based
This
to
would
proceed
to
Qualification
subject
_
the
required
should
be
etc.
!.
DVT
this
["
!__
PROBLEM
and
Qualification
:
The
proiect,
and
[-
engineering
project,
of
units
programs
to
situation
excess
am.ount
rather
than
exerts
a considerable
of
DVT
and
provide
the
'"
tuning"
changes
often
_"
formal
very
to
change
time
that
the
to
and
permit
time
to
the
allotted
These
to
unit,
caused
at
to
engineer
goal
time,
fabrication
is
to
"fine
could
process
the
very
the
redesign
schedule
Pre-delivery
factor
an
the
changes
coordinate
often
design
his
but
results
spend
during
Since
for
problems
The
units.
DVT
design
The
engineer
influence
one
the
delays.
Acceptance
contributed
to
was
significantly
problem.
The
management
'_
any
this
that
studies.
engineers.
incorporated.
configuration
consuming,
insure
in
to
tasks.
of
within
schedules
insure
train
manufacturing
design
in
legs,
training
design
amount
paperwork
the
RECO_IENDED
!
are
to
trade-off"
designed
quality
the
design
to
adequately
"cost
supporting
incorporated
Verifying
best
release.
arms,
program
written
sufficient
known
design
incorporated
be
qualification
production
time
solving
!
I
be
of
with
suit.
should
cause
design
engineers:_rior
were
and
for
the
not
without
allocate
the
space
allow
approved
quality
changes
manufacturing
this
meet
DVT
also
component,
are
and
would
than
unanticipated
ready
in
rather
commence
each
could
and
tuning"
Future
the
qualification
of
early
engineers
of
is
reflected
manufacturing
fabrication
item
life
of
could
procedures
is
design
"Fine
|
{
cycle
It
event
testing
the
component
del_ys.
the
established
flexibility
another
undue
in
until
The
to
Qualification
component
[_
of
_lexibility
problems.
program
significant
slave
Testing
GUIDELINES
appropriate
should
end
items.
and
sufficient
This
FOR
time
PROGRAMS:
engineering
control
can
FUTURE
only
the
occur
allocated
disciplies
fabricati0n
if
prior
these
to
of
and
program
all
contract
groups
any
are
available
fabrication.
-43-
L/
PROBI,EM:
!"
Significant
t ("
testing
[_
of
BACK_ ROIIND :
awaiting
design
'
contract
encountered
changes
during
authorizing
Qualification
incorporation
"_
was
suit.
This
of
drawings.
the
are
changes.
FACI
_
delays
performed
signified
on
that
However,
the
first
the
CEI
one
of
qualification
met
the
the
main
space
design
requirements
problems
was
the
( -
i..
time delay
from
submittal
ECP baseline
for changes
<
_f
f'"
_"
/
_:
:
"delay
caused
in
I_
GUIDELINES
_!.
!/"
i
._
program
qualification
delays
and
of CCA.
The
FACI.
Thus,
this
of the PGA's.
This
associated
increases
costs.
FOR
Qualification
final
emphasis
FUTURE
assure
and
component.
on
;.
_=7_
PROGRAbIS:
/_
Depending
on the
/
,
contractor
could
commit
i,i
"i
occurred
during
the
significant
program
(a
[i.;
of ROM. to receipt
is established
at
the
FACI
agreement
contractor
successful
a FACI
a summary
This
_<
circumstances
to
and
after
upon
would
during
completion
of
the
negotiations,
completion
design
the
:
<
of
availability
place
._
of
the
<
additional
phase
Qualification.
to
However,
""
_
2
k_'development
such
areas
as
NASA
phase,
approval
etc.
would
of
changes,
require
duration
of
,_
the
re-evaluation
_
";
C.
.)
["
.
I L.)
''
_.
q
,?
_
_.____
_t,m,am_..w.J_.JtJ.all:tlllliROJmhl_eJ.'tL_l,_p'._lIlv_.__
-,
>
r I
'
{ "
_I
_---I-Z.]__j.
J i ;--12[-,
'i,
.
"
_-". -
,'
'
_--_-:,
___._
i I- I i - ,
----l--
--"
,._
_:,
_"
---:,_.T._._---Z::_.
e..
--..---._
i-
"
;-.
L.
.-. le
B
m
,_
l:::::1N
.__j
--
, :1
..
I !
---
, _ i
"
....--_--_---....
----- ,I
:___i__J --____:_
..........
i--I
---J---:--
' "-o
_
--_
_.__:______L_G_
"
......
!....
".
.._:_i' ,
!__J--_-4--, ....
_
i-:'l
,_
_,"
--
.....-..=.... ,,,
I-
It
"......
l__.z',"_-."
: :_
..... "--']'---
j i
,-,---,I _J
....
..,.-..,..=..._
_-_' ---_---'I--"_,_.,
''"1
i
......
-_"
,I l_l._J
.....
L_.'__..___.,'
I
!: t ,
I L_.L_--'._.__I__J_-__.L_._.-_: --1
-
-,_
.:
i_.
'".
_,
I.:.
,S _
::::E..i_i
::
i
O"
I_
_
u_
, _
-:
i:
i-_
__,
'
>
_.._ _
_
.,--lid
'
, _:
_t 1-1
'
'_:_._
_
--,
, O_
, ,
f_,
B
,-
_o
[
-45-
' [i
'
1
_oJtl
_ell:tlUlillmO]all.ll.O];4n._l_zr._i.-,_II,,l_,o..i_
f I
-46-
.... 6
[: r
3.5
TITI.E:
:"
['
(
Astronaut
:.
[) [_
_
TO
control
Field
mechanisms,
I[
BACKGROt]ND
Many
plus
field
modifications
[
[..
of the following
discomfort
caused
value,
fit
field
saving
optional
for
future
item
suit
to
his
suit
fit
and
department
separable
['"
suit
i_
,..
no
real
of
FOI's.
as
crew
of
components
During
the
controls
The
various
as
required".
tO
properly
revised
'
a unique
request
shipping
Each
the
It was
_t
system
to
NASA
papers,
of
the
would
that
asually
request
for
etc.
some
were
by
initiated
the
thirty
FOI's
each
GloVes,
This
of
program,
there
creation
FOI's
and
pads
in
usually
controls
. 0
suit,
prior
to
DD250.
the
indicated
(in detail)
all
expressed
to
notation
"install
established
new
and/or
a..desire,
request
was
for
first
incorporation.
r_sponsibility
on
that
then
this
were
referred
was
o ,
implementation
(originally
an_J.guous
the
.helmet,
of
the
at
CMO
(30).
for
I_/EV
The
Garment.
a crewman
notation
doffing,
of
his
Form
the
FOI's
Cooling
FOI
contractor's
via
check
was
control
to
The
Liquid
were
time
customer
the
of
and
during
component
ITLSA,
the
comfo_'t
modification
to
part
items)
identify
items.
exposed
CEI
"/efinition
or
and
program
governing
FOI's
fit
monitored
a PGA;
earlier
files.
evolved
9-6100.
FOI's
and
and
perference
NAS
listings
of
instrumentation,
(FO!'s)
donning
suit
separate
historica]
separable
defined
the
tracking
physical
abnormalities,
personal
points
on the suit,
cosmetic
controlled
during
includes
of
configuration
additional
initial
or
reasons;
by hard
nun_,er
checks,
items
at
impact
PROGP_:!S:
contract
a cre_cman
approximate
for
of
which
massive
SU_T
simplification
count
of
optional
checks
when
_'
cost
revisions,
APOLLO/SKYLAB
[.-
i.
for
modifications
generation
resulted
:_
_:
and
!.
in
drawing
200
guidelines
result
optional
'"
sound
will
multiple
'
i :"
estab).ish
which
change,
Control
program.
PROBLEM :
(_ _![_
Item
o JEc vE.
i _
.,
_
0ptional
Field
the
affected
After
the
to
relay
this
components
reque:._t for
the
or
new
FOr
I (
granted,
was
apl,roved
by
NASA,
and
contractural
authorization
the
i.
CMO
r,
i
2.
i
i .
to
causing
occurred:
configuration
change
specification
a Field
separable
Change
drawing
Optional
component.
configur&tion
liner
*_
creation
3.
[
at
the
CMO
updates
and
initiates
affected
a comfort
new
i
4.
I
_
"
PGA Contract
nature,
each
a formal
End Item
separate
configuration
suit
connectors
of
program.
the
addition
drawing,
part
Item
FOIL
number
scheduled
to
see
The
for
if
List
for
DD250'd.
crewman
him
when
in
for
FOI's
all
new
(FOIL)
suits
he
_.
FOI
retrofit
after
desires
the
the
had
the
exhaust
specification
the
from
option
most
of
in
required
the
Apollo
of
"orientation
gas
positioning
comfortable
This
the
and
orientation
lines.
as
in
and were
similar
suit configurations
be
orientation
and
described
differed
would
crewman
were
Incorporation
Skylab
example
02
CEI
of
Specification
category
of
the
attaching
the
list
FOI!s
where
"lock-locks"
in
be
and
Optional
requirements.
One
the
noted
example
package.
configuration
drawing
The insertion
and verificatioi_
of the new FOI
requirement
in applicable
component
accepLance
data
unique
the
be
typical
item
change.
Although
i
_
been
would
end
assembly.
Field
have
an
assembly
a supplementary
that
consulting
pad
ITLSA
master
requirement
I
top
to
adding
the torso
limb
only.
This would
involve
of
by
could
i_
the
Order.
affected
and
change
pad on
Skylab
to
notice,
One
of a new unique
comfort
suit liner
assen_ly
for
a change
control
change
Item
change
;f
of
events
Engineering
applicable
revising
and/or
<
of
directive,
subsequent
Revision
or
chain
initiation
board
"
following
to
item
of
was
gas
,,
connector
particular
I
-_
for
the
locks
FOI
Command
for
all
required
Module
Apollo,
different
Pilot
as
Skylab
and
clocking
compared
ASTP
suits.
This
configurations
to
clocking
for
th_
'2
v
-49-
EV
crewman's
_ (. .
PGA's
I_
The specific
a forthcoming
fit
['-
was
were
suits
since
the
gas
connector
locations
on
the
different.
tasks
check
involved
in the preparation
for
and subsequent
fit check
action
/
as
follows:
Crewman
i_
i.
I_
Ii
Initial
(First
Preparation
of
the
various
options
and
CEI's
submitted
Suit)
_o
be
to
the
total
Fit
FOI
fo_
Check.
package
the
fitchecked.
Fit
sho_ing
separable
This
Check
all
components
package
Engineer
the
is
day
,_
before
2.
,
[_
"
3.
4.
fit
check.
The
Fit
Check
optional
items
using
the
as
FOIL
The
crewman's
FOIL
package
CMO
generates
of
and
the
is
5.
After
submits
L.
If
I-
the
are
then
or
on
ACL
the
CMO.
selected
to
fit
check
:_
on
the
_
_
Directive
and
which
S
j_
incorporation
options.
the
"
This
shipment
of
the
'_
affected.
FOIL
to
the
does
not
_
Quality
CMO
get
annotates
separable
which
noted
incorporated,
CMO
the
at
are
fabrication
prior
FOI
crewman
Project
components
a requested
list
for
a verified
depo,
to
Check
crewman
FOI's
difference
,
returned
conducted
the
various
,_
selections
details
CEI/separable
the
the
guidelines.
a Fit
various
discusses
with
FOI
the
action
I
Engineer
field
directs
for
Assurance
close
out.
incorporated
this
at
i_
configuration
components/CEI's
ever
is
applicable.
a FOI
is
made
parts
!.
6.
If
a request
in
the
CEI
specification,
CMO
that
was
would
not
then
to advise
the customer
of this new request
for
Approval
back
to
the
chain
of
of
a FOI
events
defined
initiate
a new
paperwork
revert
for
request.
would
described
in
i
the
Crewman
i.
(
previously
mentioned
Items
S_bsequent
Fit
(Second
About
fit
4-5
check,
(with
QA
_eeks
Fit
& R,
CMO
Check
and
Check
prior
would
to
the
initiate
Engineering,
Manufacturing
1 -
next
4.
and
Suits)
forthcoming
a FOIL
Program
review)
_ub
to
package
Control,
_;
CM0,
manufacturing
_
_
q _k
!
i
['"
{
"
;'_
for
incorporation
requested
i
by
have
the
identical
.
2.
After
[-,
the
"
was
prescribed
efforts.
If
to
FOI's,
CMO as
advise
done
to
the
a FOI
Quality
results
did
not
of
gct
I-
Engineering
3.
The
of
Fit
ChecJ-."
the
options
any
discrepancies.
Eng;neer
would
I;
of
duril_g
the
suit's
I'
point,
the
crewman
I.'
his
{L
suit
and
not
want
some
during
the
advise
initial
phase.
some
suit
usually
of
crewman
At
;'
this
experience
as was
the
Fit
the
incorporated
fabrication
first
would
incorporatednot
had
to
be
incorporated
by manufacturing
due to schedule
problems,
then the'CMO
_.ould advise
Fit Check
_:
-i.
This
i.
i_
crewman.
of
would
FO]'_., previously
l_ext production
suit
previousb,..., shipped.
incorporation
manuf_.cturing's
,_
:
all
same
crewman's'
to that
Assurance
of
the
options
Check.
on
case,
he
reque_;ted
The
next
,.
step
would
L
be
to
I ,
_Ii
Therefore,
varied
with
Results
of
by
the
4.
A
,_
"
new
numerous
The
"
of
cerain
_.
as
a typical
POl's,
To
depot
1
i
ID
problem
the
optional
counteract
review
each
prior
each
the
any
desired
of
his
second
for
suit
fit
appropriate
instances
each
would
action
steps
suits
were
the
depot
and
arm
Checks
crewm_;;
the
and
be
taken
one
when
caused
the
Fit
reflect
suits.
mentioned
at
and
subsequent
baseline
surfaced
citing
not
received
'
to
repeat
_J
six.
through
undcrgoinfield
sites.
alteration
leg
or
adjustment
removal
, :
changes
example.
discomfort,
some
crewman
field
FOI
operations
wore
the
the
CMO and
crewman
_{
FOI's
on
previously
in
This
i
the
these
desires
problem
rework
'_
new
rework
_-
remove
this
wouldn't
_it.
but
This
until
condition
caused
loss
item
configuration
type
of
CEI/separable
to
show
rework.
the
next
time
not
only
produced
of
and
quality
controls.
CMO
component
ADP
upon
the
"
over
the
compared
*:
confidence
problem,
CMO
the
was
tasked
receipt
original
to
at
the
baseline
!T
F"
_
FOIL
'_
to
unique
Test
identify
f"
gas
of
verified
changes
r_
> [, i..
the
FOIL
derived
Preparation
the
It
;
_
/
_
Assurance
rt
was
_[.
requirements,
Department,
restored
tu
all
field
incorporated
r&views
same
i
{ _
on
CMO
the
wiLh
dfferences
noted
and
on
a FOI
responsibility
to
pad
requiren_ents,
TPb.
the
is then logged
There
were many
the
cre%_an
FOI
shipments
_ i
The
addJtiona!
i _
each
i.e.,
UpoD
aid
of
'
completion
the
Quality
comfort
pad,
pads,
The
This
induced
_-
the
component
across
}iii
the
Drawing
One
I!
"
|_
for
of
each
for
of
the
his
meant
that if
a dash number
[..
built"
dash
re-shipment.
fit
checks.
amounted
were
'_
,
for incorporation
this
incorporated
there
problem
were
pads,
each
component
Assurance
changing
of
proposed
whether
FOI's
or
suit.
produced
controls.
standard
For
FOI' s,
wristlets,
glove
or
due
or
to
not
progrm_
o .
to
add
the
the
rule,
dynamics.
re-identify
change
suits.
was
applicable
number
part
usually
generated
Specification
Changes
to
FOI
by
to
install/not
he did
change
not want
and was
and
ACL's,
install
ECO's,
etc.
of
list to agree
a crewman
the
FOI that
the FOIL,
indicating
"
revision,
r.e-identification
a certain
noted
on
progressed
new
FOL
on a components
number
was when
option
was
with
;
_
etc.
were
all
shipped
Quality
pape_orkwere
hu,_er
suit
who
in turn
The change
is authorized
Verification.of
device,
new
the "as-built"
part
with the "authorized"
to
they
CEI/separable
preference
rules
the
consecutive
this
period
to the CMO,
engineering.
comfort
FOI's
for
that
prior
before
were
and
liner
anoher
Changes,
exercised
(i
suit
latter
"mountains"
FOI's
component,
board
The
with
valsalva
rules
status
periods
CMO duringof
same,
configuratiop
chin
fact
in and monitored
by the CMO.
FOI's
that,
regardless
of whether
desired
CEI/separable
L, :
..
during
by the
the
FOI
concurrence
and
field
site.
not
original
chenge
}i
its
Lad to be reported
with deput
project
_- [
were
comfort
incorporated
receives
depot
by the
applicable
! .=
i
CMO's
re-verified
to
full-timeinvolved
task
The a efforts
Also
_ i _"
"-_ ,
wa{
All
....
, L;
_ i
ADP
etc.,
ADP.
the
dimensions,
clocking,
retrofit
the
from
Sheet.
exact
connector
in
FOI.
:
'_
This
affected
the "as-
incorporation.
..
!_ ,
,i
! .)_
.-
that
*
_
! :
crewman
It was
exercised
obvious
Optional
due
or negative
o this
colaplex system
accountability
that a more practical
and economical
system
could be devised.
Belovz are some recolamendations
for
o ,
follow
_-_ i
these
_I.
I"
"
"_
prev'ious FO!
metilods add
2.
and
continuous
controls.
L:
PROGP_t4 METHOD:
for future, program
FOI
control
should
guidelines:
i
[
control,
of
i _
_ }
_ _.
identification,
option.
Field
enhancing
Item
that
a positive
_:, ":
_;
the
completion
of FOI
installation.
of the
FOI.
f
_ , ;
lation
by the
":-_
i
and
3.
In most
Quality
Do not
cases,
Assurance
change
or revised
evaluate
action would
as well as
....
the
the
effects
temporary
instal-
!:
'_
_
hours.
configurations
FOi's.
as a result
If a crewman's
of new
desire
for change
4
affects
the qualification
separable
_
as
"
4.
"
p:-oposed
Type
internal
change
;
}
_'
II document
level
detail
1'*
I_"
which
of acceptable
component
would
be
It would
controls;
of ch_n%,e.
each
be
or
classified
requires
:.
authorization.
"cookbook"
_CO
of a CEI
it should
I engim.ering
a "cookbook"
;_
Create
then
at the CEI/Separable
a Class
contractural
'
2
component,
status
This
c_:ange, all
FACI.
as defined
This
classified
as a
be subjected
to
however,
same
FOI's
book
necessary
at the Class
wculd
define
II
in
manufacturing
i
and fabrication
instructions
for installation,
methods of tracking,
and the procedures
involved
.:
*
;:
i
I
eliminate
the
listing,
I
and
CMO.
the
I
_i
Provide
It
a part
FOI's
the
activities
of
of
the
only
CEI
FOI
end
when
specification
.
conducted
installation
item
FOI
by
the
should
ADP.
specifically
requested
by
crewinan
is
estimated
CMO
check.relative The
under forthe each
new fit
method
[
F"
expended
experienced
by
would
approximately
be
for
numerous
Verification
remain
5.
need
that
36
a minimum
hours/fit
of
40
hours
was
cost
to
thesavings
CMO effort
check.
_c
:|c
&
,_,
; '
"54--
i [
3.6
TITLE:
' _
Business
Menagement
System
PROBI,_I:
_ _
During
significant
business
the
performance
problems
I.
The
I !
system
533
NAS
encountered
management
of
to
in
the
two
the
operation
was
not
most
of
the
%;ere:
reporting
relatable
9-6100
format
ILC
internal
cost
directly
control
methods.
t
_
This
q_
_
_
:
as
in
the
533
significantly
an internal
management
the construction
and
.,"
redundant
of
2.
as
533
cost
The
cost
the
with
rendered
non-utilitarian
the
and
'
through
of
Breakdown
of
WBS's
employed
did
of
to
-
BREAXDOWN
At
WBS
was
WBS
found
shown
to
meet
it
was
"
internal
i
i _
each
change,
for
to
served
(533
data
various
went
stages
implementation
inefficiencies
a
loss
as
in
and
continuous
important,
provide
the
1
various
significant
establish
meaningful
management-information
planning
report)
relative
efforts.
WBS
has
STRUCTURE:
the
outset
employed
is
_
at
not
which
BACKGROUND:
WORK
future
changes
as
data
[WBS)
collection
Equally
relationship
'
well
data.
reporting
produced
data.
segregation
for
At
re-education
management
monitoring
cost
contract.
track
ILC
Structure
developing
as
non-reflective
provide
skeleton
inaccuracies
-
to
significant
the
system,
manpower
basic
for
and
report,
and
Work
control
tool.
This-resulted
administration
of a
in
in
of
which
program
3.6
The
management
blended
in
Schedules
'
approx_ma.ed
applications.
1
reporting
applied.
9-6100,
closely
textbook
Figure
NAS
This
quite
WBS
The
however,
data
satisfactorily
the
of
the
never
served
with
a
type
the
WBS
information
during
available
II,
classic
facsimile
provided
requirements
reports,
tool.
I and
period
from
the
adeauate
as
an
this..'!
general
-55-
terms
_ I
established
analysis.
must
The
be
in
the
previous
failings
sufficiently
in
this
section's
_S
computerized
are
and
historical
cost
th,it a Contractor
oriente_
towards
# -
government
cost
systems
as
well
as
being
of
thic
propcr!y
organized
to
:
J
attain
the
cross-matrJxing
becomes
is
|.
[
at
to
all engineering
Item
(CEI) and
5:
Development,
Field
by
that
_L
functions.
1 Task.
never
used
In
in
The
any
data
use
of
At
to
_
was
the
was
to
significant
now,
!_
and
into
the
in
been
the
operation
was
day-to-day
is
occurring
of
SA
for
I Tasks
relate
on
433
July
proposal
and
retained
repo_ting
I,
the
framework
essentially
were
WBS
be
have
not
the
had
useful
program.
_t
be
and
was
This
of
manpower
attempted
The
primary
close
as
ILC.
_nd
internal
was
felt
This
the
This
was
budgets
then,
and
early
negotiation
program
through
instituted.
WBS
established
_hrough
the
WBS
of
as
alignment
of
was
to
1971
IVB.
continuity.
phase
form
the
and
for
should
and
WBS
_
C
completion
of
;_
management
revised
organizationally.
framework
was
known.
Schedule
negotiated
_"
segmented
time
within
operation
not
further
this
of
studies
of
Management
determined
formation
organizational
from
were
cost
NASA
date
that
a basic
retained
of
in
meaningful
which
time
by
to
arranged
that
concept
data
Level
however,
possible
had
in
start
the
produce
in
separation
this
a CEI
data
Contract
End
Component
at
to
shown
were
philosophy
data
abandoned
provide
Program
Costs
the
historical
ILC
this
to
negotiations
retain
aim,
the
a milestone
following
This
in
to
to
WBS
and
was
the
etc.
identified
functions
at
value
concept
constructed
rerospect,
The
way
be
timely
o_ientation
unde2
exceptions.
compiled
information.
limited
was
manageluenh
should
or
WBS
Soares,
were
The
costs
essential
I_S
Production,
Level
correct
This
The
information
useful
and manufacturing
costs
by
Level
1 Task_;
i.e.,
Design,
Support
all
without
-'_.....
resource
and
Schedule
IV.
was performed
This
i_
_
J
of
IVA
_"
app_lc_t
and
handle
system_.
inception
Schedule
3.6.2.
to
derive
computer
the
and
organizational
cumbersome
difficulg
Figure
of
quite
adequate
full
h_,_f4_
...........
-56-
the
program,
one
establishzhenh
Janua_;y
i
i,
of
continued
i
.
ground
Schedule
WBS
{
and
rules
the
wes
bccn
all
D_BS, the
_gBS's
in
throughout
is
resources
vari_,us
adhering
Level
and
In
l Tasks.
the
which
form
under
the
varied
performance
_'ere
the
addition
that
applied,
at
to
during
found
noted
1 Tash
the
Previously
program.
also
was
closer
en,ployed
same
occur
a Level
in
are
the
the
it
did
infor;_ntion.
fe,,: items
retained
varying
as
j nc]udc.d
the
very
that
a_,othc:r step
budgeted
had
IV,
levels
to
Support
and
Reviewing
'
"","
Ai_..ion
This
Support
_-
change
]973.
to negotiatcd
Mission
of
notable
to
other
in
same
the
axis
its
format
/
and
!
:_
-
content
labor
_,
through
categories
Schedule
these,
data
produce
previous
IV,
in
for
to
useful
h_S's
provide
the
WBS.
ease
such
that
533
REPORT
data
It
in
and
burdens
fol" the
historical
cost
were
not
and
rules
In
Neither
of
workable
management
did
readily
they
analysis
sufficiently
applying.
seemed
in
<
the
was
resulted
from
be
clearly
cannot
exist.
detailed
WBS
continually
undoubtedly
should
of
report
the
and
lack
on
data
via
to
internal
data
information
to
reorient
of
of
take
by
"gray
area"
defined
element
to
caused
data
be
533
Report
Very
few
management
being
it
and
data
need
the
instabilit_
in
be
each
aligned
for
from
of
program.
the
facilities
Both
parties,
better
served
placed
the
I_
533 _
from
the
reconstruction.
departments
in
the
report
volume
of
inputs
_
Z
significant
government
the
the
fallout
the
the
an
of
inclusion
with
strictly
facets
a once-a-month
data
coupled
was
a natural
was
input
the
computer
manpower
would
the
preparation.
report
necessary
contractor,
provided
nor
areas"
reorientin_
the
_BS.
level.
monitoring
equally
relevant
involved
This
ILC,
the
II
business
was
of
I and
than
daily
level
detail
interpreting
WBS's
"gray
were
Rather
Schedule
program
"his
but
Future
exercise
at
ground
Reporting
_k
in
and
WBS's
the
themselves
reclarification.
in
were
In
section.
descriptions
{t
detail
application
day-to-day
data
program.
%.;ere the
functions
the
The
_'
the
and
the
i_
organizational
-57-
alignment
and
the
cost
systems
in
place
at
the
contr_.ctor's
facility
were
governing
factors
in
the
e:;tabJishment
of
533
reporting
i_
the
_"
correct
reporting
formats.
formation
WDS
of
should
This
the
problem,
correct
also
however,
_;ifS.
produce
The
the
is
relatable
solution
solution
to
of
the
te
the
533
problems.
i :
:
0
1
[-a
i
i-
.)
2
!' ,l
,r
L.
9
, ,
-k
"]
{_
_:
{.,
t
-58.................
GUTD]/;LINE:-_ - FUTURE
r
PROGRA;.I RECO'.:!dENDATION._;:
At
cost
,
the
studies
Prior
program
Development,
Spares,
as
existent
1-ypicai
in
be
the
fer
constructed
'
described
be
to
all
suit
the
each
costs
segments
of
and
',
Engineering
Development
i
support
the
design
at
concepts.
Level
of
2 to
formal
Design
also
prcgrams
c0st
into
function
1 task
with
1 tasks
would
which
the
major
and
the
Program
activities
functions.
recommended
Management
performed
by
organization.
Design,
combine
include
as
all
quality
to
Component
encempass
segregate
Development
Verification
models
cost
costs
engineering
assurance
engineering
Indi%idual
Component
functions
Development
the
total
..-
such
fabrication
major
be
and
Level
- would
effort
should
suit
- Level
function.
Design
the
the
would
office
Tasks
suit
_'_3S which
program
Development-
sl_ould
a recommended
major
associated
the
syste_n,
l,e
follows:
:._anage_ent
include
wou!_:
(_qES), being
on
of
each
Management,
which
future
Structure
i is
of
functions
manage_,:.ent of
management
to
_h_.pport were
These
space
as
Program
program:.
segregation
are
Field
criter:"
functions
Support,
information
of
majol:
the
%.:el'e
significant
The
and
9-6100,
sections
criteria
for
typical
NAS
meaningful
Exhibit
to
Program
would
the
description
of
the
business
above.
contents
study,
Repair,
produce
provide
A brief
previous
"" -_-Brea]:down
applicable
would
the
blission
basis
the
Program,
determined.
being
The
skeleton
the
and
establishcrl
Apollo
in
to
were
Retrofit
therefore
the
Production,
programs.
of
presented
performed.
a suit
close
of
reliability
could
design
include
prototypes
other
verification
accounts
- would
Test
and
for
each
and
and
of
be
established
activity.
fabrication
and
of
Qualification
Test
units.
Qualification
within
this
Formal
Testing
1-
Verification
would
also
be
Testing
Level
and
2 activities
task.
E_n_inee_ing
Engineering
Design
Design
Tasks
- would
tasks
authorized
accumulate
by
Work
costs
Request
on
all
Forms
(WRF's).
-59-
I
I
t
L
Individual
cost
accounts
PRODUCTION
under
the
would
- All
Level
be
assigned
l_roduction
1 task
costs
Production.
to
e;_ch _'IRF.
would
be
Production
included
would
be
l-
defined
as
including
labor_- directly
End
as
Items.
associated
[.:anufacturin
a production
segregated
be
cost.
at
].evel
separately
_.
.manufacturinc
7 and
with
fabrication
of
9 Engineeri,,g
Level
3 into
SUPPORT
performed
by
personnel
shall
would
that
perform
the
CEI's
CEI's
as
quality
Contract
be
be
considered
further
determined
space
to
suit.
with
mission
Mission
engineering,
also
associated
designated
inspection
the
would
future
costs
included.
would
various
on
- All
personnel
be
2 task
the
identifiable
MISSION
only
effort
support
support
personnel
assurance
and
reliability
activities.
RETROFIT
at
Level
Depot
the
following:
Retrofit
articles
already
returned
to
_,
depot
the
under
,
;
this
Level
the
single
and
inspection
of
_ _
Level
be
will
segregate
performed
customer
depot
would
could
but
be
be
on
retained
or
considered
assigned
as
for
each
totally
spares
labor
individual
by
- all
WRF's
costs
would
associated
be
accumulated
task.
1 task
an
FIELD
work
the
tasks
authorized
- all
orders
retrofit
}'it Fabrication
spares
have
1 task
task.
SPARES
_
Level
to
Individual
& R effort
- all
contractor's
Modification
M
- This
delivered
retrofit.
with
REPAIR
2 into
retrofit
_
AND
would
included
Spares.
All
materials
be
cost
synomomous
woul_be
entitled
and
SUPPORT
costs
utilized
included.
Each
collection
- the
Level
with
the
within
manufacturing
in
the
Spares
completion
Order
would
code.
1 task
function
Field
Support
would
Field
Support.
:
>
_
All
9
costs
associated
field
would
site
_
of
with
field
be
Level
support
with
the
included.
3 if
support
Level
desired
activity,
of
the
space
2 segregatior
further
segregaling
suits
could
the
in
be
the
by
types
i_
i '
L.
In
.; ,
program
as
internal
:
space
fur_he_
"_:ek,
ie_ of
well
as
the
meaningful
rc:vJ.-.i:tg,the
management
of
_;u''_. co_;Lracto_:
to
n,,(.l_,,,:,of _:,contractor
cos.',:s,it
would
criteria
was
decidec]
that
"_,.:
- o-.,.:._i.
. _ ] into
for
the
the
typical
following
primary
!
should
L_
provide
[--
"a typical
_.
be
the
Brief
i i
Program
(_fice
WBS
and
activity
EngJ.neering
time
of
by
of
].abet
level
coding
Exhibit
would
the
be
detail
to
1 portrays
used
level
in
of
the
_
the
organization
individual
these
as
as
seen
would
represent
be
by
the
i_'
sum
of
organization.
further
Engineering,
fit
the
The
Management
could
Systems
under
coding.
codes
Program
- Engineering
or
detail
follow:
have
alignments
segmented
Design
Engineeri_g,
organization
at
the
performance.
segregate
the
as
through
Engineering
would
su_'ve
which
an
total
and
established.
sun,mary
Manufacturing
;
be
Reliability,
O1-ganization
would
the
Test
case,
- Each
accumulated
such
the
Management
data
into
and
accordingly.
could
the
bei._g
definitions
Program
,-
data
1.]anacAcment , Engineering,
Assurance
organizatien
to
This
summarized
this
adjunct
WBS.
Program
Quality
Support.
_'
,.
_
divisiohs:
Manufacturing,
Field
labo_:
- The
and
fabrication
Manufactul-ing
identify
group;
organization
at. a minimum
all
inspectien
group
the
activity
and
performed
manufacturing
engineering.
Quality
organization
Engineering,
-
and
could
more
be
and
Reliability-
The
QA
& R
;_
would
include
such groupings
as Qua]ity
Reliability
Engineering,
Technician
Support
Documentation
deemed
""
Assurance
Support.
satisfactory
inserted
here
Other
at
as
the
well
organizational
time
as
of
in
alignments
contract
all
other
performance
primary
labor
,.
divisions.
Field
for
Operations
segregation
ope._:ations.
of
The
- Each
Field
organizational
above
Site
would
information
reco_endations
are
be
for
directed
the
basis
field
towards
specific
i,-
suit
a_'eas
program.
needing
In
attention
addition
to
at
the
which
the
above,
should
outset
of
however,
definitely
the
next
there
are
be
-6_ -
,!
i"
[
inc.luded
,
in
i.
the
planning
for
the
a WBS,
prefcrrably
described
above,
early
in
all
needs
of
the
that
it
will
it
will
meet
management
system;
or
adaptable
accounting
through
2.
readily
Make
{
-
3.
!
pogram;
be
business
be
in
contractor's
retain
the
_o..cu__._n__
internal
same
WBS
system
a useful
tool
to
NASA.
Do
tracks
that
data
or
not
are
have
_:equire
not
no
both
establishment
readily
use
to
drawn
the
management
system.
k_,en the
is
solidified,
establish
application
. . . allow
clear
WBS
finally
guidelines
gray
to
areas.
Do
the
not
change
ground
rules
in
mid-program.
The
in
nature
however,
above
and
we
establishment,
programs.
i
Q
lines
contractor's
no
I
the
the
are:
program.
and
contractor
They
along
the
tAen
reporting
information
from
to
entire
contractor
of
and
system;
the
the
the
I.
prog_-am.
Establish
sure
next
recommendations
in
feel
others,
that
operation
are
more
they
specific.
will
and
in
be
of
analysis
some
In
cases
either
benefit
of
future
in
genera].
case,
the
space
suit
'
Apollo
NAS
9-6].00 Schedules
I & II
lqork Brc.,hdo,..-._
Structure
l
%
L
.[
[-
Level
0
__
I
Schedule
_
-
i[..
I
'
Contract
PGA End
Items
I
,
LCG
_;. i
TMG
ft
'
, it
_ "
EV
Visor
Garment
Accessories
Program
Manager.,ent
Project
Engineering
Systems
Integration
--
Manufacturing
}I
1
Quality
'
_'
Schedule
Assur.%nce
and
Reliability
II
Sustaining
"
Engineering
Field
Engineering
Support
I.
Off
On
Site
Site
Spares
(-
i "
Spares
Program
Spares
Orders
Management
(
,
FIGURE
!.
3.6.1
-63-
dl/dtOJliligll_dillnaOJal',l_uJ,'qLell_r:
_,:_
N'OiJO
;
:,
_'I_'[J'-fi_Ptt'_,'_
,rz?A[-_ZrlJ: IV
_].
i
I
_21-.I----_----O7-_?;,.wI
_ iz,':.:,:fh:':._..w! ', UjAIA'FIW_T]C_:
872-_- --_=---p!'.,'_L;l'Ir,,'l
(:,'JJ':_
& ;:CIUIJ_.'L
L;JJI[I-2.?:I')
823-_-------P.
_-i :;:I:;:
':
]!:I::';
T;,"
"_Lq0]'_')
" '
tJ24--[
.... L---m-_Uc,':' n':':_:'n'
'
INll'-'t',,ll_lkg,J,lll_
f_-I
_.
826_----4-/
_-'v"
D',r_
O..'a::_'.':;R
!,
]'.,_/_
-........
_,"
P,29-,-
L. -._,.;.I
......
" ._l,
(_,...,liI
....
[II,)
.................................................
_"
",
. __L_- __ .......
-420._ t, :.,\:,';\_..,_R
---1.........
"
......
X04-1
::_
:-
:.
r ......
["
'
"-(?'.C':,
:
,
{
[.
.1.,
_)
A'_:.T,YSIS
.t_aZ-_
"
10:a
:'
x09-b---4-......'.... s_..-:.:._,'_
;,cr_'o_:'_
----' ....
---7-- I_Vl'a;_
.... O,_.........
La.AiJt,',. s
_34.7___
FILYD
F '.Ii_
-_c
OPEP.:,T]O::S
OP_r'iTIOXS
_
..
:
?
t ---I;,,NC-12dY SUPPC.,tT
-4----____
....
X54 ....
X58x59 ....
x60 ....
'
:
,i
IX31@------F--!-'e._C
IXn--_---t-;
"_
?W,/.':_:7::;['
Ix30"4"-"_
,)i:k:".'.l
:-7"b'.7;2" 22"
Ii :.;A
_,
:-= -"
_---_--- -l.'tS -
].
-l-_.
_ _I'S
:"-
_- _ "----_,
_.(I"JX.CI
PdC,:_
-,, _JP,__&v%v[_
i:.___:_p
}_vcrr:_o.b
}t.',_:F,SS
x61--2_-L--_---dm t_'_;-rr.a
Z52"_'.-"--_---'.:::Lg'g_NI[L
D!_s:'_ ff:!_:!,_ .s'._)
s[:p;,p:d,r.,_
co:,:.:
v,:__wrs
,
:.
.............
x71-if---i------.'
---rr_s,_-hv
xn-t-----_---ff--rv
i
,
_;,_
rs
__.._=-:-_--.--.-.m:o-_i..m:,,..ss .._
I
--
x-5.-GV--';b,L-.:L
,.&-u...,:,_,
{P_b.,_
L,...:::._
/_2+'-......
"....... :.2 .::"':.
' ..... 7 .7
W"_':"
it
""
pI%iLX_[c S:JPi:OP,._
"_
XlX-_---t Feb\.GFS_'
i,
t
:
"
'
X3X------SPt_J_E
& /.$.YI_RTAL
IDEh'TLPIC?_IO:_
XPX'- ....
FI!:_D PN_q'S
:.L2rA_'IC_\TIO:I,,%'AI2,'TE2.D::C/_..
& RF.P_R & AL\.'f'AZ,_2N_]ITfY
XIX-----CP4_'I
MISSICtl SUP.-PO_'ZI?
X5X-r"_ -_ ;GF,'_I;_LR/:
:G SUPPO!_
l
I
l
XTX-,----ZE_9 '!G"AIlF/SLq_FCICf
.........................
XSX------ADV_.qC_IDPR.'I,RP_',.'.Ib',._)IDI_
X9X .... AT_'_IJ,9 ,\PPl,tCr:Tl"?:S
Sb?F_aRT
_X "2-._'--i
6 ii:};d'"I.':;._"
"'D
''t_.
.... i, ,'Ia
,'J,,.,
'_'f"
,i
'1
i:"'
,I
'-
, ,
XXfl-_---_L_OLINC;
!.
[
I
XXg-P ....
F'I 17.,D ::tl IT 'I'}_IHICIN_
'XO+-- - I'J:I,bV; I L['I%'
X_l-i- ---t,I'YH :tLIN,
}.
_..4-h---!::Sl'il21'rc21
XX5-F.-u-F:\:'ILFC,%TIO;!
XX6-F ....t.-%,:!:' __1,
X:FI-P---TI;
;i":;G
'
,.
"_
"*......................................
FIGURE
3,6.2--
R.\'I'-I ....TI_',VI
:h
_----O11,':11
DIItlX'['
.
"6 4 -"_
GLOSSARY
COST
ELI_;HENT - the
'-
Burden,
etc.
FUNCTION
- a
type
of
cost,
e.g.,
Labor,
costs
into
Materia],
MAJOR
_
generic
functions
tasks
Support,
;
separation
of
typical
of
suit
are:
Production,
Prog_.-am
Management,
Maintenance
and
Repair,
pr, jram-_.
The
Dcve].opl.ient,
Field
and
meaningfu]
Mission
Support,
Spare..s.
"
_ !"
PIIA___IE
- - refers
-_
divisions
_ !"
to
of
through
,'
'
[
PRIMARY
LABOR
the
14,
various
the
total
Apollo
DIVISION
applications
contract
th1"ough
- a separation
components,
i e.,
Managen_ent,
Quality
Field
15
suit
relative
17,
of
Manufacturing,
Assurance,
Skyiab
labor
and
time
to
Apu]lo
an_
into
Engineering,
and
Reliability
AS_i'P.
organizational
Program
and
Support.
!-
"
-65-
3.7
TITLe: :
f-
_-
Frogram
14anagement
Organization
and
Manpower
Su_.,_ary
OBJ I._'CT
!VE :
Evaluate
l
existed
Deter,_ine
'
implementation
f!
L_
presented
the
The
the
comparative
maPgement
'
_ }
required
summary
this
of
these
The
_
DISCUSSION
.
[.i
.-
k .
I
of
programs.
the
progrmus
as
this
section.
which
was
suit
was
supported
used
as
then
1973
Emphasis
required
was
was
management
section
3.4
organization
management
to
1973
197_
to
1973
organizations,
estimated
the
figure
(See
rate.
In
the
program
The
of
the
period
study
reducing
the
to
schedule
for
future
of
management
on
of the
d_ ring
rate
factored
required
for
as
this
program
the period
of
average
compare
was
of
manloading
an
section
structure
level
p_'ograms
this
properly
manpower
was
The
_.,as based
order
the
program
manpower
3.7.3).
:ion
for
on
compared
to the level
that existed
at ILC
production
levels
as
paragraphs
3.7.2
Figure
organiz;
a comparison
organization
guidelines
preceeding
was then
organization
1970
production
of
recommended
in
by
manpower.
program
in
the
used
placed
presented
:
in
the
1/5
these
to
a
reflect
1/20
-66-
................................
nmn._
--,m
resulting
determin,:d
organization
the
the
manpower
STUDY:
support
in
The
organiza'Lions.
through
of
ree_u_nended
program.
management
proposed
hbe
to
illustrated
the
programs
manloaded
discussed
resulted
_Y
1970
Implementation
as
L_
THE
program
Th_
::
FOR
level
i "
3,6
formulate
savings
baseline.
I {_
to
management
USED
of
future
whi._h
from
o_ganization
suit
a future
manpower
_' !
! ;
suit
resulting
through
ASTP
used
program
I.
ASTP
for
management
and
support
of
savings
3.1
program
were
to
GROUNDRULES
and
guidelines
paragraphs
section
, L
the
organization
hsseline.
Guidelines
identified
as program
manpower
savings
in paragrephs
3 ] through
3 6 of
2.
[
_'
Skylab
manpower
Sk_,lab
of
ILC
Apollo,
:_
._
"manage_ent
Apollo,
total
in
the
program
APPROACII:
f....
i_
d_ring
(-
the
_ [- __ [_ _ .
production
rate
a total
manpower
Comparison
savings
of
of
480
these
two programs
man montJls.
revealed
--,
,t-
.
--
r/
_"
I '
l.!
l
_"
2":
t;
i, i
e O
'_
a,
,,.lllalllhmo]|Tn.lL.U,j..L,..
'
"J"."
f.
"_"'ml_'
lib ii
" V_
!]
!"
4) 4J
ii t,
---
__
f_
-,_" I_
"
_.._.____.
-o
0 rj
"
4J-lJ
U_
rJ
I,,I
"
r_,-
1_
r,-
&
O_
r_,)
U "_..
"_rO,,P
"_
Oi_
,_
:_
04J
["
0
Id
_
l.q
IO
_ "
t
.
C
.IJ
-*.I--
_.,..
"
_,0_
_.'4.r4
_9 4,.,P
},,o_
:
J
;.
;:
-_o-
p
!
i.
.
SECT I0:_ IV
ENGINEERING
[_
4.0
ENGINEERING
4.1
TITL_
"
Interface
port
of
OBJECTIVE:
control
future
docu.n-.._icn,_"_
"
space
Establish
the
suit
most
(ICD)
for
_up-
program.
efficient
and
least
costly
method
of
controlling
government
!
APPROACH
and
the
to
new
of
future
furnished
space
and
cost
Cost
space
suits
with
equipment.
of
interface
programs
were
control
used
examined
in
on
ad-
control.
were
evaluated
for
efficiency
and
effectiveness.
savings
and
suit
ASTP
concepts
concepts
associated
Skylab
of
Skylab
These
contractor
methods
ApOllo,
dition
interfaces
The
_
the
ASTP
data
was
Programs
to
developed
the
by
comparing
recommended
new
Apollo,
interface
technique.
i
GROUND_
RULES
i.
The
It
FOR
space
1966
2.
USED
was
will
that
the
f_
tation
techniques
"
the
mentation
of
was
_lat
used
majority
not
for
used
a new
the
as
the
space
for
future
of
existing
be
Apollo,
period
study
suit
suit
of
baseline.
configura-
progra:z_
interface
and
documen-
useable.
interface
Skylab
of
interfaces.
performed
tiations
among
would
intervene
1_
additional
was
for
On
the
the
then
If
the
ASTP
were
programs,
used
by
both
identification
Apollo
practically
themselves.
to resolve
effort
and
control
contractors
I_
i
be
will
the
associate
contractors
1973
program
During
ICD
assumed
tion
INTRODUCTION
suit
through
STUDY:
all
program,
the
a stalemate
contractor
continued
among
various
NASA
and
and
docu-
the
associate
interface
nego-
occurred,
differences
NASA
and
contractors.
I
r
t"
'
-72-
During
\
_-
this
_
program,
contractors
maintain
and
NASA
acted
scheduled
a punctual
as
a med!,.to._
r "=
,- among
frequent
resolution
meetS
of
ngs
in
interface
_L,i_
_,
order
to
',
problems.
This
type
of
came
less
effective
"A"
ICD's
still
[
were
acted
without
program
_
!-
tion
during
suit
interfaces
existing
will
were
this
report,
the
of
This
on
Jn many
the
_
J
NASA
_
,
cases
contractor
The
ASTP
,_{
coordJna-
contractor
occurred
prior
Level
negotiated
equipment.
amount
existed
the
the
problems
Apollo,
'_'_Lh
recommendations
problem
a cost
study
of
be-
since
all
programs,
the
_:
therefore,
used.
during
in
assistance
program.
already
ICD's
result
and
as
program,
actively
centers
least
suit
program
this
also
manufactured
Each
The
areas
or
interfacing
Skylab
During
but
examined.
sented
the
NASA
the
the
experienced
were
and
involved
In
:
other
knov.'icdge
designed
contractor
during
mediator,
with
the
associate
introduced.
as
interfaces
who
clu_e
of
suit
Shylab
of
and
group
for
of
future
interfac'e
ASTP
is
programs
prr
which
reduction.
encompassed
'
pro_'_,,.,_
problems
suit
control
_-
investigation
of
the
following
a.
b.
Tl,e impact
of
and
end
item
The
use
of
flight
weight
Level
effectivities,
changes
"A"
ICD's
on
on
part
the
numbers
ICD' s.
advanced
"_
_
suit
pro-
_.
grams.
c.
The
duplication
quired
"
d.
e.
on
many
The
difficulties
due
to
Cost
and
Apollo,
in
the
Skylab
information
and
handling
ASTP
of
re-
ICD's.
some
ICD's
s_ze.
considerations
control
unnecessary
are
if
new
methods
of
_'-
interface
utilized.
-73-
i
PROBLEM
!;,"
Flight
_
weight
Document
ges.
provided
BACKGROUND:
life
being
!_
This
in
all
changes
support
vehicle
numerous
ASTP
Apollo
suit
were
on
to
Skylab
during
4-1-3
4-1-2
ILC,
Grumman,
and
and
Rockwell
by
which
ICD
total
the
chan-
previously
NASA
suit
and
31
ASTP
mission
and
nearly
"effectlvity"
alone.
examples
International
ve-
resulted
program
illustrate
and
and
what
changes,
of
as
Skylab
reassignments
suit
A
processed
4-1-1,
identify
mission
been
Apollo,
ICD.
chan_es.
gures
all
on
and
Control
(IRN)
required
configuration
the
item
document.
system
and
ICD
control
done
illustrated
Flight
r_
was
had
another
were
end
Notice
information
notes
and
Interface
Revision
in
configuration
ICD's.
was
this
effectivity
numbers,
numerous
cases,
Flight
or
in
Interface
_ contractor
of
hi_le
most
part
end
to
method
[
I
_esulted
(ICD)
In
ASTP
effectivities,
changes
I
%
ICD
of
Fitypical
effectivity
changes
In
(
effect
the
:-
all
any
costs
Notices
more
were
one.
the
of
to
for
much
and
time
changes
most
cases,
part
number
callouts
part
number
was
tion.
hardware
Since
number
of
since
the
the
part
vehicle
appeared
the
on
to
reduce
shill
actually
Revision
in
to
groups
expended
meetings
changes,
many
dimensions
suit
In most cases,
these
changes
sub-system
changes
which
did
signature
ICD's
were
neces_ay
numbers
or
not
Interface
was
effectivity
number
some
did
of
in
complete
were
and
required.
for
the
noted,
nu_er,
IRN's.
not
were
changed,
part
the
ICD
In
Identi-
interface
proprietary
each
and
time
had
of
informa-
the
dash
to
change.
resulted
from component
not effect
the interface.
and
:
changes.
dash
by
effort
attending
"effectivity"
flight
an
changes,
transmitted
However,
changes
In
these
memorandums
approval
effectivity
interface.
transmitting
(
I
suit
(IRN's)
fication
'
these
processing
Similar
:
_
real
of
than
_.
(
i
t
cases,
-74-
/,
_)&
c"
P
I
u o EI_
.-t
_I-+,
'nO
I C.'
fa
_1.5__
_
'
("_
'----_'"
,--_
I
I)
,_
"_
(.
o
.p.
+ I?
"-"
'
(_
I+
++., _
"0
++ +
,-
"+
C,|,v
P +I_<
_.<__ _
+ i
o,-,
: _+
'+
(_
lIiO]t(Ll11+.r.
JRl:JIIIIInOJIIl,
I ++_,_
.+__.,,., =
III._
L:
.,,:k
,_
"_
_!
t+
-,
IJ
,,
: P
t-<
t,_
..
_+,
I 1
'-
..., .....m,
"-it?<..
_,,+_'
t_
t/_
:+ I_ ."-,
:._
.-_ . _ +
,
_-_
o'
+.. _
_ _
,_
I,_
_
r_
_
_o _
coo
,,_
......
....
P.!
ra
C:
"_
++
....
"--
"
i+.
J
.-_
'_' _I
_,
i
_I
,,,,-, ; 01.."
-,,
'"'
i,-
+, -.,
C *, -'
..
"_":.;-L
r,2
I_
._
S C
.r,+
<>
=. + .+
i+,
+.,,.
....
-_
.,
:;5 ....
_ +
i"
,+
.................................
++<_
Unlihe
. !
numbers
Since
flight
provide
the
effectivity
absolutely
interface
no
notes,
useful
dimensiol_s
and
configuratiol-
inforlaation
other
dash
on
necessary
the
ICD.
info]-mation
!,
i%
2rovided,
associc'_te
- _
and
the
contractor"
r_ur_er
does
nothing
unfamiliar
with
of
on
but
the
confuse
suit
an
sub-systei,_
components.
The
,;
dash
the
itemizing
interfacing
weights
contractor
of
the
tDe
ICD
!a_est
served
suit
to
and
advi_,e
suit
equipment
f-
-in the
(LEVA,
SEVA,
structural
gloves,
design
helmet,
of
the
changing
of
for
flight
etc.)
vehicle
or
weights
the
for
use
o.'eration
of
maneuvering
unit.
The
_.
abnormal
have
frequent
occurrence
occurred
has
due
most
hardware.
may
be
an
However,
! i
weight
design
changes.
changes
An
_ ' ,
i
suit
design
change
eight
hour
mission.
b.
Nume_.-ous
ii
crew
continually
being
On
device,
and
others
the
Skylab
were
documented
stowage
list
was
'
weight
In
c1_ange
addition,
perform
_
the
formal
The
flow
,"
suit
weight
il
released.
review
chart
change
as
authorized
suit
on
or
this
on
the
illustrates
the
some
Skylab
suit
Skylab
each
contractor
ot
of
suit
Lunar
EVA
the
crew
program
an
were
basic
quantity
of
and
equipment
suit
suit
This
CEI
to
gloves,
pockets
List
change
required
what
the
comfort
ccjntractor
stowage
suit
to
optional
pads,
a contract
was
numerous
Apollo
to
Stowage
changes
the
on
added
comfort
the
the
hour
used
wristlets,
on
updated
was
a four
revised
program,
weights
J.ncluded
items
special
valsalva
many
from
Examples
included
necessitated
example
optional
configul'ation.
items
to:
substantial
weights
not a.beenChanges
the cc._e
pres_ure
suits.
Frequent
dn with
missionthe requirements
resulting
in
:i I
hardware
specification
authorization.
periodic_%lly
list
happened
to
after
the
an
CCA
approved
was
-78-
3
r
I
t4As/.x
(i
Ce>-,
'
i
_Y'Ec_
"
"
_F'_ f"l
--
_11
Or
ki.1,tl T"
I [
r,., ,.,.._,,......._,
i
'
:
The
_-
the
OWS
design
document
! "
;
_ "
<.
the
Thi_
with
stowage
the
list
suit
weight
system
was
a contract
change
the
ICD
GUIDELINES
i.
"
I
FUTURE
Although
the
the
the
by
be
the
part
each
of
the
the
Apollo
to
prog_.-an_ or
Skylab
suit
and
_e_
contractor
changed
the
to
suit
Configuration
they
flight
received
sui
'
weight,
intended
for
programs
of
it
the
p'_rsunnel
did
serv_
could
on
ICD's
prepared
list._ng
report
no._ directly
to
recommended
be
be
use
is
Tl-is
status
which
ICb's
individual
contractor.
a monthly
the
mission(s)
effectivities
documentation
used
or
and
.
other
as
as:_ociated
proc-ram.
part
various
system,
hardware,
should
required.
_'
was
listing
_
Y
n_,ed
notation'_-; on
t_e
respectiw,
information
2.
no
ICD.
,_ctivity,
futare
separate
similar
of
equipm-cnt
for
their
could
with
which
change
reader
maintained
,;
the
effectivity
advise
and
time
was
to
:?]_OC.R2_,iS:
numerous
that
on
requirements
there
the
during
contractor
caused
which
result,
used
each
design
a change.
Therefore,
not
as
on
authorization
required
FOR
As
changes
Con_r_dnd Module
A.'-a result,
served
contractor.
programs
"
also
numbers
sub-system
be omitted
and
dash
number's
of
the
and component
suit
from the ICD's
when
net
7I "
_ "
-79-
'
3.
progr_:m
used
stowage
list
effectively,
method
of
is
or
other
the
provic_ing
similar
qu].c,.co_
" '..... anu
a suit
weight
document,
ea'_:icst
change
to a
vehicle
:
contractor.
a contractu.'-al
it
will
an
ICD
the
change
PROBLEM
ICD
if
long
requirement
eliminate
approved.
As
the
each
as
tile stowage
for
need
the
to
The
suit
v,,ights
the
stowage
vehicle
process
tlr,.=
" ,_ a suit
is
transmit
change
not
is
contractor,
and
weJ.ght
should
list
list
bu
is
.'oted
on
used.
:"
Interfaces
negotiated
identifie_
between
kno:.ledgc
or
BACi:GROUND
NASA
on
Level
centers
assista._,,:e of
"A"
-.n_ in
:he suit
ICD's
many
were
cases
activel
witl'3ut
l"
the
cont,:actor.
:_
i
_
_>
Le,,-"
Apollo
equipment
anc_ Skylab
Center
to
b.
Su-.t and
c.
Juit
to
Rover
T020
suit
F3ot
_.
Suit
PGA
Restraint
The
ICD's
were
approved
NASA
center.
each
of
these
NASA
center
It
to
was
the
then
(b),
directly
the
betweer,
manufacture._-
-_t the
coordinate,_
(Preliminary
the
suit
dnd
defined.
Interface
were
not
by
NASA
ICD's
JSC
were
JSC
to
from
and
and
the
the
the
the
interfacing
ICD.
In
was
9WS
one
of
performed
vehicle
This
changes
Notices)
were
initiated
with
suit
contractor
the
suit
interfacing
program.
later
the
initiate_,
coordination
However,
Revision
coordinated
of
Unit
- Skvlab
commencement
- Apo.!lo
- Skylab
(MSFC)
transmitted
contractor
Johnson
M_neuvering
JASA
interface
the
3ky]:-tb
"A"
from
contractor
the._e interfaces
only
Level
%'as trahsmitted
center.
which
Foot
(MSFC)
the
inclu_;ed:
(MSFC)
Controlled
Center
to
than
inter_aces
to _,,"
_.S
on
l**_e_
f_ce._ with
" ".....
suit
other
Veh._cle
c m_t?ment
-..
utilized
the
c_nter
These
Lunar
were
define
Reseaxci_
NASA
NASA
to
/_angley
Whe,
well
ICD's
a NASA
(JSC).
Suit
information
to
a.
interfacing
:'
Intercenter
programs
supFlied
_.pzceci'aft
"A _ or
ICD
or
was
PIRN's
by
until
k
fter
N,_SA approval
had
been
made.
-80-
In
were
.
of
never
the
All
p-._rson_el
of
en
a.
th_s
bei::g
;
b.
the
Love]
suit
docum_nt.
fo-; a ].evel
details
approved
other
"A"
"A"
ICD's
coi_tractc-r
(ite_,s a and
until
It, addition,
ICD
in
some
after
the
cases
receipt
approval
rcqui',-ed
d)
ti::_e
several
months.
two
revie_:,ed by
NASA
requi,-e_
!
addition,
less
the
ICD.
The
suit
the
ICD.
Even
re_:1_'ited in
concerned
This
when
resulted
the
Many
PIR_'s
the
the
of
suit
.because:
-its
they
ICD
accuracy
stair contractor
memoranduu,
without
contractor
into,of ace
discrepan
NASA
suit
ebout
contractor
engineering
by
the
were
on
-n
personnel
did
attempted
to
Level
most
reco_endcd
"A"
not
sigr,
itemize
ICD's
cases
signed
by
corrections.
e.
_
?
:
;
In
were
review
since
on
suit.
the
sunlmary,
approved
NASA
NASA
without
cc.nsidered
assumed
the
the
them
to
s11it ccntractor's
have
responsibility
no
for
ip_pact
insuring
proper
well
an
as
the
Apollo
and
i
inte._:fac_s
the
vehicle
designed
:
i-
to
Based
on
Level
"A"
is
un_e_iroble
an
ICD's
If
it
is
directly
agreement
use
of
this
these
or
suit,
and
other
the
suit.
approval
Love].
th_
"A"
S_ylab
hardware
ICD's
as
program
were
easily
was
generally
used
defined
DD_r'_'c.
on
the
method
of
it
Skylab
ICD's
the
and
the
affected
sheet
to
be
interface
ICD
an
suit
are
_ubse_uent
believed
for
is
help
that
for
suit
future
used
PIRN's
expedite
interfaces
programs
in
future
coordination
sheet.
the
used.
contractors,
approval
to
is
program
control
designed
that
signing
the
interfaces
Shylab
used
"A"
by
the
experience,
Level
between
Since
past
a newly
basic
on
(PIP_N's).
if
recon_ended
initial
,I
(
fit
provided
FOP. FUTURE
espec%ally
changes
configured
GUIDE!,INES
were
be
with
NASA
later
programs,
for
the
coordinated
each
indicating
centers
can
then
NASA
approval
ICD's.
I
I
-81-
PI_OBLE_-i:
"-
During
interfaces
This
were
rcnultcd
Apollo,
S):y]._:band
ASTP
documen-_ed
separite]y
in
in
information
the
and
dupl_cation
of
inL_
difficult
handling
ICD's
the
programs,
lieu
of
individual
groul._.
_'z_c_'s,unnecessary
due
to
the
quantity
of
the
[
"_
ICD 's.
BACKGROU:'D
The
used
J
the
separo
philosophy
This
resulted
suit
";elated
internal
ICD's
..
each
Skylab
individual
and
ASTP
interface
in
total
ICD's.
memos
to
the
add unnecessary
paper.
by
98
duplication
programs
be
documented
of
in
suit
different
ICD
order
size
fo1_nat.
Sky!ab
ASTP
large
tc
interfaces
_:
a "C" to roll
specification
and
31
amounts
status
interfaces
associate
traditionally
massive
these
of
information
57
requiring
release),
were
from
in
Apollo,
memoraP, iums,
ICD
Duplication
prepamed
of
Besides
for
interfaces
which
ranged
were documented
(engineering
led
A:_ollo,
,._echanical
documented
on a drawing
while
functional
ICD's
that
addition,
paper%::ork
_
for
rely.."
In
..
suit
of
reports,
quantities
and
fill
the
the
occu,-red
contractors
of
need
to
drawing
between
and
the
ICD's
_"
su_t
contractor.
" '
This
illustrating
hardware
of
the
with
identical
,
occurred
when
one
interface
of
the
view
of
suit
the
while
suit
contractor
prepared
a specialized
a second
piece
contractor
interface
_:'ith his
an
ICD
of
his
preen, red
an
specialized
.piece
hardware.
"
Prior
to
ICD
preparation
by
an
associate
contractor,
'_
i
[
the
suit
contractor
illustration
:
which
uf
occurred
the
was
required
various
during
the
suit
phases
_o prepare
and
transmit
configurations
of
each
and
program.
an
changes
As
result,
was
the
further
_
:
_
!
illustrations
'_
contractor
duplication
compounded
which
responsible
of
by
were
effort
the
then
for
between
different
preparation
copied
preparation
or
of
traced
of
the
the
contractors
initial
by
the
associate
ICD.
t"
"
!
-82-
"
"
If
One
cau3e
"py. amid"
;--
$'.._enan
NASA
or
cases,
placed
or
this
traced
"each
li:_tcd
official
on
proaram.
such
Skylab
as
Level
connectors,
requirements
between
suit
documented
on
contractor
and
sketches
and
a Level
"A"
t_e
vicws
NASA
the
NASA
his
"A"
from
then
copied
on
twice
was
system
occurred
the
with
suit
JSC).
existing
interfaces
doc_unented
contractors
the
primarily
functional
previously
between
-_
the
used
on
area_,
vehicle
already
the
most
contractor
duplication
(NASA
on
effort.
interfaces
contractor
this
listed
was
perforned
interface
ICD
_"
In
higher
higher
mounting
JSC
pyramid.
which
:_,o,-kwas
for
point
Level
suit
the
ICD's.
preparation
the
shetch
the
contractor_,
ICD
the
of
Apollo
more
on
Duplication
_ince
and
by
interface
"I"
hard
etc.,
the
NASA
of
or
or
below
or
s_ae
use
the
of
highest
ICD
the
source
"Intercentcx'"
the
two
a drawing
charging
Another
with
t"'
....contractor
a result,
contractor
i
:
As
an
the
responsibility
prepare
onto
was
used
betwqgn
the
required
to
pyramid.
".
system
contractor
contractor
[
pcc_.ing
situatJ_en
_.... required
system
associat_
th_s
.'4 r
ICD
of
were
NASA
As
ICD's
:"
again
MSFC
vehicle
i"
a result,
were
copied
onto
ICD.
"t
ICD's
IDA02-1004-11,
IDA04-1031-11,
HDA02-715618-11,
t
HDA02-729670-11,
MH01-21021-136,
illustrate
an
illustrate
how
occurred
Skylab
on
and
was
to
past
duplication.
of
the
p_ogram
suit
views,
in
examples
dimensions
describe
ICD
suit
and
These
connector
was
carried
and
13M13524
examples
inte_face
over
to
the
programs-.
ne"-essary
Two
views,
Apollo
ASTP
contained
not
of
duplication
the
During
which
example
MII01-2i048-136,
the
p;:ograms,
numerous
dimensions
defining
of
and
the
ICD's
of
other
were
prepared
information
which
interface.
which
notes
interface
and
ICD's
contained
equipment
numerous
which
was
detailed
not
required
included:
1
a.
IDA02-1022-Ii
b.
HDA02-729629-!I
Buddy
Many
available
document
other
at
the
reveals
SLSS
'!A7LB
to
ICD's
writing
the
PGA
"Mechanical
A7LB
PGA
existed&
of
this
and
but
and
A6L
these
report.
Accessories
Functional
Interface"
ICD
LCG"
two
were
Inspection
readily
of
each
following:
-83-
a.
IDA02-I022-II
feet
long).
This
ICD
on
..
the
ATLB-hV
the
list,
and
case
have
pen,
dimensions
[erso;_.al
to
of
show
items
As
_espcnsibility
of
the
the
dimensioned
envelope
dimc:'sions
the
responsibil_ty
NASA
th_.t pocket
properly
2 of
in
this
iCD
words
should
by
be
added
by
profits
were
All
could
that
this
ICD
the
suit
contractor
since
all
the
in
separate
contract
a_ded
Revision
"A"
change
wos!d
the
be
the
the
to
insure
e_:ch
particular"
internal
3.CD, it
items
woa]d
placed
be
in
been
the
others
like
"level
to
Sheet
were
the
of
It
information
it
was
not
additional
suit
contracto;"
effort
2 and
directed
Sheet
an.;. discusse(
drawing.
ho obtain
by
on
deleted
add3 tional
efforts
under
details
itemized
and
ICD
illustrating
i]].ustl_ated
the
in
accomplished
of
to
all
been
fit.
all
notes
interface
the
items
have
adding
notc_d
contained
the
have
Lhat
n[:m]_;:v
pocket.
_.:ithin each
on
each
requiring
con_nactor
the
each
sunglasses
could
fit
listed
Additie.,ally,
part
individual
it
suit
with
would
ui:der
without
without
items
Likewise,
only
chec].l ....
_,
penlight,
result,
pocket.
out
n:me,
detailed
v.'o_._n
poc._ets
sc;_sor:_
the
the
these
the
called
dosimet._r
pockets.
of
of
dimensions
the
The
by
views
and
any
listed
Separate
of
each
conf_c_u:-ations,
been
envelope
of
3 1/2
of
suit
..h_,;_J - each
PCA's.
the
illustration
"
of
detailed
illustrated
'"
CMP
for
an._ utility
inside
A7L!_
dir]-unsions
the
could
pouch
and
envelope
in
szzed
illustrated
detail,
daha
roll
co.'.[:ail,
s illu._:tratior's
dimensions
are
;.
(two
prog_-am".
all
by
changes
four
authorizations.
?
-84-
I
!
b.
III)A02-7296::9-]I
feet
long)
This
ICD
(one
ro!]
sized
sheet,
sex-cn
,.'_
Buddy
.
seconOary
and
the
:
:
bag
flat
and
on
another
in
effect
two
ICD's
The
use
of
location
and
design
PDR
or
ICD
and
contractor
of
leverage
for
only
In
such
as
no
was
An
and
ICD's
water
illustrated
was
ICD's
has
for
shown
several
ICD
necessary
The
for
the
bags)
In
method
was
dimensional
in
which
contained
dimensions.
functional
stowage
cases,
the
softgoods
accepted
on
information
interfacing
::....
the
ocu_red
interface
these
both
occurred
interface
or
ICD
as
document
ICD's
of
NASA
required.
This
this
dimensions
illustrated.
if
contained
to
formal
an
used
later
ICD.
Rockwell
noted.
was
always
were
through
were
to
expedite
early
increase
the
to
before
rushing
cost
a technical
order
obnain
contractor's
envelope
duffle
to
the
on
only
as
mounting
in
exception
were
not
by
American
system,
the
was
dimensions
responsibility
(foam
multiple
which
contractor
p_'ocedure
associate
requirements
bag
to
changes
interface
North
this
In
related
hard,;are
object
hardware
an
the
flight
a program
illustration.
several
suit
information
approval,
accepted
when
dimensions
already
dimensions,
approval
After
location
the
the
the
The
change.
even
PG_
Expe:'ience
added
by
other
CDR.
of
typical
was
freeze
the
It was
was
information.
the
to
sides
or
the
include:
document
or
b.
which
of
time.
information
of
detailed
HDA02-71390_-I3
represent
unnecessary
]ocation
unnecessary.
suit
marks
ICD,
that
was
"of the
the
detailed
crewmen,
hocks
alignment
Apollo
at
thi[: ICD,
BSLSS
connector
two
"
GFE
b(:iween
syste'.n (BSLSS)
suited
on
t]-e views
unnqocessary
a.
NASA
In
the
addition,
contain
reasons,
stowage
i.utc:rface
sui_port
PCA.
BSLSS
These
which
Apol]o
of
the
the
life
illustrations
of
illustrateu
by
North
stowage
American.
85- "
Another
'
difficulty
documentation
used
on
experienced
past
_:ith
prcgram_
was
the
the
handling
roll nized
d_'awings
as well as all interface
general.
Some of these
problems
included:
i"
a.
ICD
"
b.
Reproducible
copying
delays
due
to
the
interface
of
dz-awings
size
of
large
i.
the
drawing.
;-
were
kept
c.
ICD's
for
_.
This
to
prevent
files.
mylar
mailing
'
contractors
I.
special
of
preclude
GUIDELINES
I.
and
FOR
It
tc
ICD's
special
storage
damage.
cont,'actor
associate
required
prepared
contractors
the
prenaration
of
drawings.
originals
fol" signature
dra':ing
mailing.
to
associate
required
the
tubes
protect
to
Mailing
d_livery
_i
was
by
use
of
>
the
registered
frequently
done
_o
loss.
_:UTURE
is
"of suit
drawing
special
related
required
reproducible
dra_,:ing during
mail
suit
drawing
This
cardboard
all
transmitted
their
The
co oies
were
special
d.
file.
Reproducible
:
r-
of
en
facilities
[
copies
_.
PROGI_H_:
reconam,ended
th_i
all
suit
interfaces
on
future
.
'
programs
be
documented
prepared
on
standard
paper.
This
ICD
in
a single
8 1/2
document
ii
ICD
inch
would
be
which
is
specification
similar
to
suit
I_
;.
include
'
"
systems
(SEVA,
"
all
would
interfaces
'
!-
and
suit
would
of
the
be
part
the
to
the
with
an
An
ICD
all
could
be
similar
and
equipment
etc.)
suit
be
sheet
signed
and
the
by
add
used
the
suit.
the
NASA
current
side
would
all affected
NASA
by
NASA,
suit
which
de_.ining
initiated
This
contractor
describe
approval
and
to
related
FCS,
the
and
contractors
would
document
IRN
LCG,
illustrate
contractors
ICD
suit
associa
interface.
of
_ specification
other
Kit,
all
only
associate
and
include
to
_ontractural
I
interfac
Maintenance
document
level
as
or
the
Changes
a contractor
'
procedures
similar
Aircraft
systems
for
the
level
Lunar
ICD
Roving
was
prepured
Vehicle
by
Boeing
(LRV)
during
{
,,
!
-86-
V
!
Apo]!o
prog_:am.
hardware
with
document
for
should
r
2.
_-ork
LRV
n_merous
the
noted
_n
on
8 1/2
X ii
inch
standard
of
co_,plex
A
is
piecc
of
similar
possible
c_nd
program_..
the
ICD
should
be
to
reduce
expel,ses
pa]_er
reproduction
convenience
il_terfaces
futu_-e
.item I,
was
Jnte_-fau.s.
su_.t
for
As
mailinc,
The
and
carrying
storage
the
prepared
and
in
permit
the
e_._..:en.lr
_',_ _'_ within
briefcase..
'
<
COST
CO'/SIDERATIONS
By
implementing
estimated
ICD
that
programs
support"
'
for
savings
of
the
duration
later
used
would
one
associate
'
cost
savings
mailing,
estil,_ated
and
of
at
be
test
or
(I) man
a one
the
the
from
from
an_
NASA
the
"level
decrease
changes
provide
of
effort
represents
one
man
program.
during
that
Additional
specification
of
excessive
required
the
suit
utilized
systems
is
at
storage
definitely
and
]?eriods
tl-ave!
or
were
is
future
This
Skylab
the
during
contractor
that
p_-ogram
it
support
program.
men
of
interface
would
to
Apollo
engineers
resulting
to
two
start
guidelines,
required
of
available
when
but
the
the
reproductioiA
schedule
reduced
approximately
was
activity
recommended
manpower
be
phases
systc:ms
the
can
early
or
the
the
support
to
more
s_me
time.
in
drafting
could
a savings
than
The
not
in
effort,
be
cost
time.
&
-87-
4.2
TITL_ '"
Contract
E'_.d Itc_m
Dcterm.ine
End
Item
future
and
i
(CEI)
Specifications
optimization.
T_ 7%_
rb "rr,_1
improver_ents
specifications
space
least
and
_;'hJ.chcan
method
made
to
Contract
as._5ociz:ted maintenance
costly
be
_,{13
of
control.
Specifications
used
provide
systems
the
most
for
efficient
App}_,OACH :
The
CEi
["
ASTP
suit
p_o,j.._u._-_'.,
'nave becn
'
have
been
examined
can
_;
frequent
change
time
expense
deletio.1
be
to
deleted.
Apollo,
These
which
items
resulting
Sky!nb
in
and
snecif[cations
requirements
specification
activity
the
stuCind_
determine
Those
on
or
which
excessive
information
experienced
:'!
maintenance
and
or
An
proposed
L
%_ere
identified
as
prime
candidates
for
possible
change.
estimate
of
the
manpower
deletions
or
revisions
saved
in
by
future
implementing
suit
the
specificatSons
is
i
'
i
provided.
GROUND
RULES
i.
USED
The
FOR
CEI
spec'tfications
through
some
to
2.
,
:
INTRODUCT
1973
cases,
new
end
item
was
this
space
_sed
used
earlier
support
Any
as
the
periods
fo_- the
period
study
baseline.
of
activity
1970
In
were
used
study.
suit
programs
will
require
new
contract
specifications.
7_ON:
Duri:_g
I
t
STUDY:
Item
(CEI)
NASA
"Apollo
past
space
suit
specifications
w._ , preFared
Configuration
requirements
for
were
on
the
programs,
Management
format,
the
Contract
in
accordance
Manua].,"
contents
and
NPC
change
En_
with
500--1.
the
All
procedures
imposed
flexibility
I
I
during
and
(,i
was
study
the
Apollo,
reconm_endations
is
suit
contractor
by
this
manual
and
little
permitted.
This
maintenance
programs
the
considered
of
for
Skylab
these
several
and
ASTP
rigidly
improvement
problems
suit
programs
controlled
during
experienced
future
in
the
preparation
specifications,
space
suit
provided
-88.
_ _-_
.......
"I
i
L:
,'
PROBLEM
:
Frc_q_._._:ut
chan_;e_
Interface
:
[.
Control
specification
BACKGROUND
to
Docunien[-o
a-] ,,cl"
spec:_ _'
;.lc,,. -_.....c,n
:weigl,ts
suit
(ICD)
resulted
in
nume2:ous
CEI
changes.
:
Frequent
changes
to the p_-ez_urc
.qa_cellt asseJ_,bly
separablc
comj_onent
specification
_,,_igh_s have occur_-ed
'. "
because
..
_:
:
a.
Changes
in
resulting
mission
in
numerous
:_
Apollo
suit
mission
to
b.
design
an
crew
configuration.
}
{
items
val,_alva
device,
and
others.
weight
the
weight
the
to
should
Apollo,
profit
contractcr
actual
component
specification
of
generally
the
I
|
ILC
by
change
new
NASA
greater
Contract
than
cases
weights
when
and
one
factor
in
in
an
This
maximum
the
agreed
were
system
weight
not
the
upon
add
cases,
during
include
a result,
safety
the
some
As
maximum
factors
suit
actual
system
weight
:,ieJght were
This
appJ:oxim_tely
provided
weight.
was
instituted
reduce
this
initiated
maximum
of
specification
requirement
,r.ade resulting
not
contractor.
control
was
In
weighc_;
establishi_.._
to
in
of
did
pockets
cent:col
maximum
effort
of
t._e addition
progr6uns
basic
coT:]fo_t gloves
.
change.
did
the
optional
re._u_t_d
specification
weight
crew
to
a pound.
suit
EVA
suit
of
a pound.
of
1972
changes
the
lunar
tenth
a result,
the
half
on
method
activity.
specification
:
suit
within
safety
in most
As
from
the
the
added
qua_-tity
.as a
suit
for
weight.
largest
plan
of
the
comfc'i't pads,
weight
that
ASTP
or
requirement
little
noted
and
inceutative
suit
a I%
be
as
hour
the
mission.
reviewed
resul_ing
nece_s':;.tated
included
u_:cd on
wristlets,
design
by
EVA
Examples
specification
Skylab
'
'
CEI
changed
It
the
or
changes
example
items
special
change
item
corr,:spending
'
incl_.dc'd
requirements
f'?om a four
hour
being
many
An
optional
suit
der;ign
design
change
eight
continually
optional
symptom
substantial
were
Each
and
',..'eight
changes.
Numerous
crew
and
by
to
specification
incl-easing
one
half
specification
in
minor
through
weight
the
;_ pound
(1%)
value.
inc._'eases
i
-89-
'"
to
the
system
, ,
file
exceeded.
[.
approved
to
one
pound.
until
the
At
half
change
In
this
shall:
its
the
the
half
were
pound
V_-_.ue an
reduced
NPC
the
February
physical
of
design
";as
altd
additional
of
As
Exhibit
the
or
of
the
procedural
equipment/facilities".
requested
number
19 67,
d_rectly
and
o_:
weight
"ApollolConfiguratior,
P_ragraph.3.2.1
the
kept
significa,_tly.
500-1,
either
and
specification,
specification
dated
on
the
in
w_s
with
imposed
rucorded
authorization
system
. . specify,
functional,
pounds)
specifications
states
".
other
time,
Manual",
requirements
one
This
to
Requzrement3
less
excess
accordance
Management
c.
or
increase
SCN's
"
(0.i
If,
CEI
"Interface
specification
by
reference,
CEI
because
of
relationships
a result
of
this
to
requirement,
all
Interface
item
:.
were
Since
(by
or
were
tabulated
by
the
or
revision
letter)
correspchding
(SCN)
of
of
an
approval
or
during
reduced
the
GUIDELINES
I.
was
was
th(
Skylab
paperwork
FUTURE
Two
percent
were
the
The
above
the
agreed
weight
value
should
the
This
excessive
the
CEI
NASA
formal
changes
individual
to
conform
deleted
it
since
during
is
to
will
the
ICD's
that
approval
in
decrease
change
changes.
Paragraph
Exhibit
maximum
permitted
weight
approval.
and
be
in
reconunended
letter
upon
specification
by
Reguirement"
revision
itemized.
the
eventual
of
increase
contractor
possible,
CEI
the
other
Program.
th_
"Interface
the
the
formal
the
caused
be
since
during
requirement
should
and
the
changed
either
confining
specification.
drastically
2.
to
and
PROGRAMS:
system
activity
end
specification.
date
required
with
the
document
requiring
This
CEI
change
colrd_ined
Program.
specification
.
ICD
t{uthorization
somewhat
FOR
an
Proposal
I Document
changes
each
to
approval
This
Change
Change
a Type
these
time
necessary.
Engineering
a Contract
specification
('.
noting
each
receipt
within
letter,
initiation
"referenced"
pertaining
revision
Specification
'
(ICD's)
ICD
IRN
ECP's
Documents
tabulated
these
l&test
Control
II
are
<
3.2.1
to
NPC
500-1
signed
Zf
this
as
a minimum,
dates
is
by
not
not
:_
be
,'
f
:,
-_0a
I
f
i
_,
..
PROB] oEM :
,i
During
the
specig_-_c'-,_
[_
i
This
"boiler
plate"
BAC]_G;<CUIgD-:
''
[ [
'
,?
i
CEI
resulted
type
"Boi].ec
Skylal._ and
ASTP
suit
end
item
equi_ment).. .
._
Apollo,
the
constant
._ep,'_ating of
information
in
was
accorda**ce
with
contained
the
500-1.
Sections
such
environments)
induced
materials,
processes
parts,
safety
"boiler
provisions
plate"
and
selection,
and
many
in
each
par_:,
.
r.apbs
.
(prime
information.
plate"
sp e_'''c_t
-tl _. ion
in
programs,
E_._].blt
"'"" "
a_ natural
environments
standard
other
of
_fl_..gnt)
_
and
paragraphs
commercial
cons;:ituted
information,
"Boiler
plate"
information
represents
approximately
60%
of
a typical
ranged
from
figures)
19
CEI
to
depending
Separate
individual
,
NPC
500-1.
water
to
connector
were
for
boiler
in
this
the
was
of
assembly
a
the
tables
end
were
prepared
pl-cpared
in
requirement,
Apollo
numerous
items
total
of
program,
for
each
accordance
as
CEI
seven
with
the
._.separate
12
and
item.
such
r_quire6
specifications
ir_formaticu
some
cases
Specifications
were
and
to
compliance
changes
_.n each,
of
the
MSCM
in
one
8080
all
the
hanges
change
changes
and
LCG
CEI
Specifications
for
the
changes
required
repeatability
required
Skylab
and
to
design
use
effecting
to
two
all
tabulation
standard
specifications
the
same
one
others.
throughout
the
of
An
example
the
of
CEI
applicability
requrements
which
se:,,,_,_:al
times
during
program.
To
to
plate
document
the
each
specifications
(excluding
complexity
a result,
for
length
the
ASTP.
Due
of
and
this
As
p_epared
I
-
the
adapter
specification.
in
where
specifications
item
Due
pages
on
CEI
end
specification
70
compound
contract
end
Proposal
(ECP)
different
item
CEI's.
this
problem
required
even
As
if
Ii
the
further,
a se,._arate
the
individual
En'jineering
saw_e change
a result,
each
MSC:4
effected
8080
Change
several
boiler
plate
-91-
specification
to
NASA
changcs
for
approval
Therefore,
resulted
some
,
:_
'
in
extensive
manpower
to
manpower
was
and
Board
type
the
<
approval,
even
_-
or
can
CEI
so
cal,lcd
"level
of
required
the
ECP
be
transmitted
changed.
"no
st"
changes
effort"
man]_cn_rs
Be_idcs
_
re=_uJt'ing
the
to
chan_e
original,
review
achu_lly
to
complete
addJ_Jonal
_ .
each
propos_Is
separate
(ECP_s)
Contractor's
in
the
have
diagrams
activities
_ small
for
uhe
of
CEI
in
to
c,_,-,",ge,
NASA,
Configuration
initial
order
duri_g
to
process
Control
that
that
and
were
number
It
of
the
illustrat,
can
in
be
d_iring
maldlo'u_s
of
the
seen
specification
produce_
on
4-2-2
involved
Specifications.
the
that
chanc e.,_
the
program
s_pport
a program,
PkOGP_AMS:
reduce
preparation
reconm_.ended
ILC
effect
I,'OR FUTURE
In
",?igures 4-2-1
specifications
a sioni[icant
required
ia
within
reduction
nuni_er
GUIDELINES
is
flow
route
manpower
. "I
also
s" )arate
(CCB)
various
each
an(_ process
_=upport
The
i"
s.._.plu
__, changes,
engineering
sCN's
'
for
these
extremely
submit
required
r(.qu_zed
"_ ,_ "
_,.... manpower
and
maintenance
one
CEI
of
CEI
specification
to
support
the
specifJ.catio_:s,
be
prepared
it
to
.'"
describe
reduce
all
the
t,,
_
. ',_'
It
should
of
NASA
change
future
f_ture
of
suit
suit
required
the
noted
Document
requirements
on
and
be
on
space
manpower
preparation
!
!.
the
later
that
NPC
space
NASA
end
J.tem ].equiremcnts.
i:o support
maintensnce
this
500-1.
suit
Document
both
o_
the
re:onm_endation
if
the
programs
NPC
the
This
Jnitia]
documentation.
is
in
violation
implementation
J.s desired,
500-1
would
should
of
the
not
be
this
applicab]._
imposed
contractors.
-92-
t_
PROBLEM:
[
L.
Tile confiquration
/ "
_=
specification
approval
incorporating
equipment
_:
BACKGROUND:
"_
During
program,
r{
I
to
Per
an
approval
extended
necessary
"
complexity
of
the
time
of
SCN
the
this
standards
Each
<
SCN
'
on
(ECP)
separate
In
to
NPC
500-1,
As
recommended
a result,
same
SCN
referred
to
the
these
SCN's
Of
ECP's
longer
the
and
the
and
the
item
specs
ECP
SCN's
the
of
state
and
and
would
This
issued
Exhibit
VII
original
from")
("changed
and
to").
against
different
latest
others.
change
the
prepared
approved
one
were
("changed
were
to
list,
(CCA's)
6.1.1.5
to
of
!
table)
changes
CCA's,
the
each
specification
SCN
was
be
occurred
approved
rejected
"changed
control
engineering
paragraph
latest
requirements
Examples
interface
changed
due
specification.
ILC
from'the
optional
SCN's
stated
the
affected
required
and
of
the
each
Paragraph
once
to
authorizations
being
due
NASA
design
same
by
500-1.)
requiring
several
different
paragraph
the
(ECP)
(process
several
remaining
no
to
replacement
Therefore,
NASA_
paragraph
;,
when
specification
paragraph.
new
was
specification.
field
was
(SCN)
when
separate
paragraph
to
occurred
SCN
with
submittal
submittal
resulted
to
same
on
with
each
specification
the
the
change
accordance
accordance
This
and
This
weights,
contract
prepared
system.
submitted
since
Skylab
were
changes
proposal
system.
documented
the
require
months.
also
manufacturing
was
proposal
I
of
six
chancj;:s made
listing,
of
in
many
approval
of
in
SCN's
in
problem
paragraph
in
Pare.
6.1,distribution
Exhibit
VII atof the
NPC
to their
change
NASA
approval
occurred
document
the
SC_;'s were
same
to
a CEI
delays
(SCN)
change
tile preparation
additional
different
{
for
up
part
notices
resulted
of
created
and
all
(Ref.
prior
engineering
An
500-1,
s_stem
time
i:
program
specification
NPC
required
changes.
change
depot.
agency
approval
program
which
design
Apollo
a CEI
contractor's
.the
procuring
i,
system
specification
500-1.
This
the
document
NPC
i_
management
by
since
from"
because
-95-
approval
of
affected
paragraph.
In
revised
the
an
effort
the
plan,
t,
by
to
revised
resolve
Exhibit
contains
upon
SCN
Skylab/Apol]o
881270043D.
,_
first
ILC
and
Engineer,
based
on
"
Technical
Monitor
SCN
Subsequent
in
I'_
by
an
the
V-A
and
approval
problem,
management
ILC
plan,
F of
the
system
agreed
_,
NASA
with
designee),
will
the
to
ECP
which
will
not
reflect
approval
be
made
Resident
NASA/JSC
approve
submittal/approval
officially
released
related
SCN
the
concurrence
(or his
additional
"
paperwork
implementation,
t econ
changes,
of
NASA/JSC:
by signature,
prior
to ECP
instances,
the SCN will
be
f
wording
configuration
following
expediency
this
].202, Paragraph
the
Dover
"For
the
In
and
will
part
the
of
SCN,
these
implemented.
be
implemented
the
original
I,
_.
"SCN's
ti_e
i
of
which
ECP
do
submittal
ECP
is
approved
for
obtaining
release
When
When
NASA
and
will
the
SCN
occurred
one
,
I
'"
approved
SCN
problems
experienced
this
five
the
disapproval
by
a procedure
was
Exhibit
modified,
release,
action
_,
the
this
the
one
approval
time
responsible
prior
to
with
this
received,
to
the
ECP
eliminating
It
should
the
in
ILC
CCBD
be
of
remote
Document
Engineer
will
be
risk
this
same
This
approximately
was
Recognizing
"
was
approval
drawback,
Resident
applicable
be
accordance
past.
incorporated
NASA
the
will
stating
the following:
event
an SCN is subsequently
after
until
SCN."
approval
in
NASA/JSC
CMO
in
submitted
contain
1202F
"In the
normal
then
at
subsequent
SCN's
changing
the
new
"changed
from"
paragraph.
Once
was
did
approved
any
the
days
sytem
since
the
approval
implemented
Engineer
of
was
be
occurs,
implementation
"
this
Resident
system,
it permitted
paragraph
to reflecL
to
not
signatory
the
the
noted
that
ECP
possibility,
881270043D,
disapproved/
approval
revised
to
and
offical
identy
required."
"SCN's
incorporating
will
never
be
modifications
revised.
or
Subsequent
retracting
,-
changes
a previous
SCN
-96-
i
t
f
_-
(in total)
will
retracting,
the
with
the
The
change
and
other
In
customer
_'%
I_
"'
.
: /
!"
f.' '
I F
(SCN)
SCN
added
log
will
nuri_er
be
updated
required
data."
actuality,
less
time
FOR
is
was
of
FUTURE
procedure
should
NASA
procedure
discussed
this
new
for
involved
in
schedule
savings
approval
time
to
,
!
CEI
SCN
new
be
re-activated
datu
changed.
latest
S_
approval
SCN's
due
and
to
ECP.
a specification
that
discussed
be
future
used
in
will
the
the
will
the
that
on
This
manpower
of
total
Release
reflect
prepara
the
to
utilized
procedure
the
of
PROGR;9._S:
similar
be
to
1%
cases
pages
and
to
than
used
recommended
system
881270043D
in
In
latest
disapproval
It
SCN.
superseded
GUIDELINES
C_
a new
previously
preparation
tT
require
space
in
NPC
result
lieu
in
SCN's.
of
notice
Document
programs.
the
>
recommended
Utilization
of
signification
review
In
ILC
suit
500-1.
preparation,
rewriting
in
change
and
addition,
cost
copying
savings
time
a definite
L .
six
a similar
is
suit
IL .
by
since
change
the
submithal
proposals
could
discussed
and
and
extend
CONSIDERATIONS:
implementing
rate
of
that
(i) man
of
function
the
change
specification
a savings
this
result
engineering
COST
estimated
one
also
months.
By
it
for
SPECIFICATION
!:
will
activity
as
manpower
required
maintenance
for
one
the
guidelines
the
man
during
activities
duration
over
the
most
of
in
of
level
the
past
programs,
to
can
Apollo
and
:.
support
be
a program.
required
assuming
performed
This
to
future
represents
perform
Skylab
programs.
-97-
4.3
_
TITLE:
Field
OBJECTIVE:
_
Ii
Contract
["
L_
Operating
_:
Operating
Procedures.
be employed
on future
effectively
_._
Procedures
Operating
reduce
To identify
guidelines
that might
space suit programs
that would
costs
for preparing
Procedures.
and
maintaining
Field
'
APPROACH:
l_,
Fiel_
Operating
contract
requirements,
use and effectiveness.
I"
Procedures
were
analyzed
in terms
of
format, methods
of change, ease of
Level of detail of these documents
?
was
_
I_
compared
determine
was
,
Procedures
_
iL
level
study
i:
,.
that
program
could
cou]_
areas
guidelines
are
(TO's)
to
be:implemented.
Emphasis
within
the Operational
to
cost
be modified
of effort
for
future
effect
recommended
savings.
in areas
of
potential
programs
employing
_le recommended
Field operational
documents
as referred
consisted
of the following
documents:
Maintenance
.
i
Illustrated
Parts
At the initiation
Manual
Breakdown
(No. 8819700713)
of this study, the Chamber
Pre-installation
I
[
Pre-installation
Test Procedure
were to be
analysis of field operational
procedures.
Acceptance
preliminary
survey
with
These
them.
Test_rQcedure
identified
documents
incorporate
to in this
(No. 8819700712)
:_
on identifying
of Operations
guidelines.
INTRODUCTION:
I.
i
Table
cost savings.
Potential
savings
are presented
by comparison
of level of effort required on NAS 9-6100 and projected
o
i
depot
if cross-utilization
placed
Future
to the
very
were
related
prior
problems
:_
to the
Skylab
through
several
(
I' _
these documents
expressed
overall
satisfaction
with the
format and adequacy.
On the basis of the results of this
I;
preliminary
these
two
use.
documents
had
I
[
of successful
that
evolved
Personnel
were
"4
in the
a
to
survey,
sequence
included
However,
cost
revised
th_ Fl_,ght
program
years
a test
few
and
_!
using
i _
deleted
-98-
from
the
k
: !
|
The
pages)
space
i I"
study.
Maintenance
technical
suit
Manual
publication
equipment
effectiv_
use
'i
and
inc_'_dJng
I
and
overhaul
The
I
Js a two
containing
systems
(1,0].3
descriptions
with
operational
volume
of
instructions
for
instructions,
maintenance
instructlons,
illustrated
309
illustrations
(_4)
and
_"
_ol_me,
pages,
Maintenance
Manual
assel_ly
Parts
Breakdown
parts
list
mod!:_ication
and
is
parts
lists
(IPB)
with
is
a single
supplements
instructions.
which
used
primarily
supporting
the
for
spare
parts
definition.
iI _
evolved
_!}"I
_
i
The MM and
from
four
included
many. _eviews
the
required
and
understandable
quality
_
CEI
indicated
its
of
I
: I
a);high
in
associated
basis,
I_
throughout
maintenance
is,
the
of
other
and
the
most
required
part
of
time
the
were
an
users
meeting
publications
were
to
prepare
and
operational
average
use
charged
program
to support
any
technical
publications
of
of
in
of
were
of
an
program.
personnel
current
document
suit
and
performance
expensive
space
activity
required
the
were
format
A survey
technical
such
documents
throughout
that
as
to
this
with
the
for
field.
These
and
relation
with
the
NAS 9-6100
activity
which
a complete,
necessary
satisfaction
objective.
to
Having
is
in
a technician
maintain
"
detail.
maintenance
Contract
support
modifications
document
These
engineers,
and
of
standard
documents.
to
level
general
intended
maintain
!
I
IPB resulting
from
years
of continued
illustrator
Labor
on
two
costs
a level-of-effort
maintained
tasks
associated
and their
time
with
was
not
PROBLEM:
charged
!
i
prepare
'
i
_,
to
contract
The Maintenance
and maintain
changes.
The
encompassing
I "'(
i
technical
'_
Manual
and
IPB were
expensive
to
throughout
the space
suit program.
_.
BACKGROUND:
Maintenance
document
detail
The
Manual
was
and contain
text
is
required
to
a very high
concise,
be an
level
comprehensive,
[:
all
of
,!
and
-99a
....
,........
!6..
SO
[
worded
as
to
school
graduate
theory
_nd
be
understandable
with
to
knowledge
technical
terms
of
used
a high
the
in
school
applicable
the
space
with
some practical
experience,
art
work
such
as
graphs,
photographs,
Illustration_
charts,
[.
drawings
used
in
text.
detail
on
["
drawings.
view,
["
At
of
required
are
not
of
current
readily
the
hours
of
use
contract,
time
had
to
be
the
of
a
An
to
full
three
average
and
of
and
front
quarter
from
_M
and
illustrations
normally
found
trans[errable
drawings.
IPB
contained
illustration
:i
->
prepare.
descriptions
all current
maintained.
usu_lly
field
consisting
diagrams,
The
than
required
illu_trations.
Technical
concerning
had to be
are
illustrations
185
30
i_
drawings
the
completion
a total
!
[
of
which
the
the
more
While
many
profile
torequired
support
service
general
suit
i"
used
theare manual
or
and
illustrated
details
Class
I and Class
II
All space
suit models
included.
At
one
configurations
that were
in
time
during
A7LB
Skylab,
the
P
program,
.
Command
(ASTP).
only
this
included
Module
Pilot
space
suits.
technical
the
A7LB
Apollo,
(CMP)
and
the
Since
the
Maintenance
publication
in
use
Apollo-Soyuz
by
Test
Manual
Project
is
field
personnel,
non-testing
technical
the
it
serves
"catch
directions.
I I
I
Notices
and Standard
into the document
as
i i"
for
all
Operations
Bulletins,
Repair
Procedures
part
of routine
System
general
section
complete
both
Cleaning
Although
I.
Class
I'
not permitted.
Notes
and warnings
had to be repeated
References
to other
existing
operational
procedures
throughout
the document
instead
of including
them
in the
showing
.(
incorporated
were
the
Safety
had to b_
maintenance.
and
referring
to
them
when
applicable
If design
and
did notchanges
obsoleteaffected
the current
one section
configuration,
of an
Field
all"
i [e
!
i:
_
as
not
redrawing
approved
instructions
complete
and
I documentation,
of
the
illustration,
configurations
on
same
were
contained
throughout
current
procedures
existed
reference
to
these
illustration
it required
rather
the
;_
than
illustration.
the
in
procedures
manual.
other
were
permitted.
:_
- 00-
1
,..
k
[r
Separate
used by
similar
manufacturing
starts
from
contained
I_
i
all
operating
space
new
zero
flow.
instructions
sequences,
materials
all
Disassembly
associated
TO's
were
tailored
are
normally
with
work
instructions
difficulty
are
are
assembly
operators
assembly.
of an end
that
instructions
and
not
do
not have
working
not prepared
on a
in
Maintenance
Manual
format because the sequence of work
not compatible
with maintenance
activities.
When CEI
was
"
[-_
''
modifications
were performed
at the depot, rework i_structions,
prepared
in the TO format, were used in lieu of the Maintenance
'
Manual
Additionally,
the pressures
specifications,
identifications
The
were
performed
many
step-by-step
fabrication
Production
the
suit
the
a suit.
of all
with
describing
and material
in TO's.
to contend
total
contain
to fabricate
use
!_
instructions
points
to the
k'
inspection
I"
They
required
different
item.
I.
and
of
the manufacturing
_,
schedules
never
permitted
sufficient
time
to insur_
that
.?
!
!
i '
I
rework
particular
_
I_i
i
instructions
was
useable
was
never
A.
_
_:
'
i"
t
in a format useable
for both depot
Less time was required
to address
job
in-flow.
at the
considered
Depot
I
t
rework
of
nearly
members
Manual
prevailed
the Maintenance
in some
because
that
instances,
the
i/
a TO
to fit
attempt
.
more
utilization
work
on
and
particular
to update
expeditious
the
reasons:
involved
the
Manual
complete
following
always
for
rework of structural
seams since it was
authorized
field maintenance
aztivity.
B.
,(
Although
depot
structural
Maintenance
to the conditions
and
the
existing
not
an
needed to perform
in existing TO's w
economical
rework
to change
problem
Maintenance
than
Manual
instructions.
CEI
design
changes
were
excessive
during
certain
-i01-
:
_,
i_
!.
L_
{
r
}
t,
1972,
Manual
a total
of
and IPB.
80 changes
were
processed
to the Maintenanc(
These
changes
required
modification
of
2,378
text
and
standards,
,
man
Maintenance
change
--
with
on
though
increased.
and
to
i.
maintaining
the
the
regard
for
created
a situation
Maintenance
Manual
associated
maintaining
the
the
experience
This
required
level
The
directed
Customer
established
initially
of
field
long-term
stand3rds,
technicians
extension
FOR
FUTURE
of
had
i
'
required
Future
PROGRAMS:
CEI
should
place
and
..i
appropriate
instructions
in
This guideline
will
probably
preparation
but
field
designs
maintainability.
all
repair
will
costs
to
should
_"
in
a minimum.
I.
2.
! -
to
of
TO's
assembly
I
3.
Use
of
consider
objective.
could
A
be
returning
at
and
(TO's)
the
the
be
overhaul
depot
costs
to
utilized
field
describing
to
CEI's
as
preparation
subsequent
provided
Maintenance
Initial
section
CEI
tooling
should
in
Manual.
initial
program
Major
practical.
use
as
*.
disassembly
supplement
TO
instructions.
references
Maintenance
Manual
which
is developed
perform
of
performed
instructions
should
procedures
be
Incorporate
less
cost
logistics
Operations
whenever
a major
'
to
maintenance
publications,
modification.
keep
assembly
the
should
the Maintenance
increase
the
considerably
to
programs
and
maintenance
compared
continue
Manual
of
in
emphasis
modification,
personnel
of
for
more
Future
of
field
cost
depot
order
Table
the
by
when
the
levels
result
/_
i
L
12,000
whereby
was
costs.
authorize
IPB
of
method
on
: ,
established
over
on
required
personnel.
GUIDELINES
!"
i
_
Bascd
changes
I:
Ha_ual
little
support
these
level-of-effort
direction
insisted
[
l
illustrations.
of
hours.
even
173
processing
The
I.
pages
other
should
be
permitted
when
practical.
and maintained
related
activities
within
the
Documentation
specifically
to
should
be
-i02-
#o
"
k.
referenced
in
the
verbage
actual
Notes,
lieu
of
incorporating
in
the
cautions,
etc.
section
'of the
Maintenance
should
be
Manual.
contained
in
I I
general
_"
repeated
I-"
When
simple
design
differences
assemblies
or sub-assemblies,
i.
one
['"
in
the
body
document,
illustration
when
to
4.
The
!,
working
I'_-"
L_
to
days
complied
the
Delays
of
exist
between
allow
the use
both
perform
of
authorized
a Customer
sh_ _id be
with,
release
necessary.
requirement
20
only
absolutely
depict
configurations.
and
allow
change
change
the
enforced
and
contractor
without
release
review
when
not
to
further
create
in
delay.
a pyramid
effect
r"
i.
_
and causes
maintaining
expensive
a current
Maintenance
handled
on
Manual
change
a CCA instead
basis.
_ ,,
before
['
5.
:
_-
of
changes
techniques
I'
!
will
requesting
necessary.
_
_
This
thing
proper
changes
that
would
caused
by
of
on
forethought
are
eliminate
personal
manner
delays
activity
should
be
of a level-of-effort
insure
This
or
in
b_cklogs
and
_ecument.
not
absolutel_,
a high
desires
percentage
when
presentation
is
the
only
of
Publications
question.
COSTING:
_'_ I_
Preparation
I
I'_
was
performed
NAS
9.6100.
on
I'
" _L
this
part
of
on
As
effort
preparation
information
and
a level-o'f-effort
many
the
initial
limited.
As
developed
in-house
When
the
seven
certain
the
design
ATLB
the
art
work
Company
program
and
model
and
people
were
phases
of
was
during
utilized
the
performed
capabilities
writers
full-time
program.
by
in
additional
bec_ne
associated
manufacturing
space
was
suit
Contract
Initial
very
little
technical
as groundwork.
A large
matured,
the
Technical
basis
costs
were
high since
was available
for use
since
suit
as
during
contracts
the
maintenance
outside
this
area
capability
more
introduced,
familiar
were
was
with
techniques.
the
publications
-103,_ i .__._.__------_
......
v_:'
:_,',':_
_'_---'
,'
.;_-'_,....... ......"_'-_7_:
.......
-_':. :,'
_ '_",,,"--'
........
i '",i ;'
-:_.... _::
_ :_:_i
_::::-:::
;;
,o
[
>
group
[ "_
technical
..
maintained
until
out.
Cost
data
the
contract
had
stabilized
to
writer
one
and
early
a level
of
illustrator.
1972
compiled
when
from
(September
two
the
July
1973)
engineers,
one
T_is
was
level
illustrator
1971
reveals
was
through
that
the
a total
phased
end
of
of
85
man
months
was
expended
on
to
slightly
over
equates
I.
["
" the
ASTP
required
were
preparation
of
hours
the
or
bulk
over
would
in
be
It
is
per
During
month.
required
qualification
savings
phases
an
of
that
of
of
design
ASTP
total
the
to
time
period,
used
in
result
one
full-time
publications
20
man
in
3,400
is
apparent
most
of
of
cost
have
after
would
months
per
illustrations
on
further
the
that
and
is
savings
with
reductions.
part-time
the
resulted
during
cost
guidelines
establishment
year
relatively
support
cost
technical
text
maintained
have
standards,
a program
person
This
and
new
that
would
could
pages
incorporating
changes,
this
spent
it
This
incorperated
change
for
approximately
Incorporation
baseline.
17
established
required
the
ext
Thirty-seven
On
illustrator
technical
of
new
models.
herein
I_
165
new
eliminated.
of
of
was
for
probable
support
basis
the
support
terms
recommended
i.
support.
pages.
change
90%
during
of
other
the
this
illustrations
stable
[ _
323
On
publications
men
approximately
to
required.
man
"
3.1
publication
period,
three
major
changes
were
processed
which
the CMP,
Skylab,
and ASTP
configured
suits.
The
modification
I"
technical
the
of
in
the
operational
program.
I
L_
f
'_ [ ,
/
-104-
I
LL
'
[_
4.4
TITLE:
!"
__
Engineeri_,g
[..
'
L.
["
and
OBJkCT'[VE :
Evaluate
the
engineering
during
and
ASTP
space
result
in
the
changes
still
I-
Orgmization
Summary
,
A7LB
that
Manpower
would
providing
an
org_,nization
suit
programs.
reduced
efficient
and
that
RecoI_end
overall
effective
existed
costs
while
engineering
-i
organization
in effect
programs
is used as a
operation.
APPROACH:
"
The
the
during
ILC functional
A7LB and ASTP
[_
comparative
baseline.
engineering
costs
toidentify
[
are
on
presented
[.
,
:
to
are
of
the
form
problem
proposed
that
contributed
identified.
for
means
in
each
Areas
reasons
made
engineering
space
suit
excessive
reducing
of
area
costs
chart
areas
and
associated
future
Cost
organization
These
excessive
are
reviewed
recon_T,endations
costs.
program
These
g_idelines
savings
are
that
compared
is
to
relative
reflected
in
to
are
a factored
-'
A7LB
,,.
organization
GROUND
i
RULES
i.
chart.
USED
The
FOR
engineering
through
1973
In
cases,
some
were
used
placed
The
-
2.
The
support
section
structure
I_'
of
for
the
the
study
of
level
supporting
was
period
of
periods
Emphasis
required
personnel
assumed
to
program
of
was
proportional
this
organization
schedule
report
(See
was
presented
Figure
manloaded
in
4.4.2).
,'
INTRODUCTION:
In
the
an
and
aerospace
program,
responsibilities
contractor.
concerning
'
engineers.
:'
engineering
3.4
(draftsmen,
be
4.4.1).
the
1970
baseline.
earlier
trade-cffs.
the
etc.)
proposed
to
{_
on
Figure
as
activities
reducing
effects
(See
used
support
technicians,
I.
organization
was
to
on
:,
STUDY:
..
'
'
engineering
Very
are
few
are
engineering
principally
specific
imposed
organizational
on
the
operational
the
Contractor
responsibility
requirements
Exceptions
-I05-
!
[-
are
requi1:e_,ents
ii .
imposed
the
d_rinc].
he
feels
will
is
In
to
be
In
this
an_
to
the
Project
the
costs
de_,ign
requi.-ements
qualification
problezs
been
identified
_:
J n the
Direction
of
of--
has
c:r,janiTe
form
hove
phase:
Manager
to
best.
several
excess
of
in
and
him
done
always
causes
the
allow
job
report,
of
and
cases,
the
nearly
causes
nature
most
get
drawings
devc]opment
flexibility
Customer
provide
the
program.
s_fficient
to
from
manner
the
r c_m,n
ations
e --'De d
_.
chat were
considered
identified.
problems
The
are
varied.
i
" Some
were
dynamics
i"
r"
efficient
a means
_,
;
i,
i
man
once
'
if
report,
based
the
the
on
that
existed
of
1/5
proposed
are
a measure
this
the
ILC
the
report.
BACKGROUND
OF
A7LB
the
be
of
during
1970-1973
be
on
the
of
this
and
the
savings
See
Figure
In
phase
that
will
be
is
organization
to
1973.
was
based
Manloading
differences
the
factored
associated
to
this
organization
1970
1/20th
::_y new
t/_e included
organization
rate.
_,
management
engineering
period
after
On
proposed
most
,_
IIowever,
development
is
solvers
lower.
force
based
department.
problem
required.
of
the
as
higher.
the
or
how
engineering
will
study
level
organization
of
of
will
all
level
production
the
of
of
reduced
a function
engineering
after
most
on
organization
manpower
to
at
loading
a large
In
as
realized
his
engineering
implementation
compared
average
of
of
the
more
give_
costs.
prim_.rJ ly
costs
develop
are
terms
because
savings
costs
performed
level
The
of
organize
trade-off
engineering
then
man
for
complete,
be
these
primarily
to
some
tim:,' to
Jn
amount
and
guidelines
reducing
complete,
need
must
an
case,
engineering
a manpower
guidelines.
use
is
is
determine
r
be
elects
to
feels
the
would
development
objectives
are
However,
elects
he
each
allow
identified
Manager
program,
"
In
didn't
savings
development
program
direction
or
program
he
contr<ct
eliminating
hours.
Project
If
the
oi
systems.
the
future
[
'
[
of
of
cases,
(
!
a result
with
the
The
on
an
between
organization
recon_nendations
4.4.3.
ENGINEERING
ORGANIZATION:
'
u.
_-
The
reported
Apollo,
directly
Skylaband
to
the
ASTP
Program
Engineering
Manager.
The
Organization
'
engineering
-106-
!_
sQ
organization
!.
total
tho
program
and
program.
directly
operated
as
was
"line"
involved
It w_,s managed
to
tl_e Program
for
the
Apollo
for
all
other
_unction
in
by
nearly_
He
total
had
and
personnel
the
aspect
engineer
group
engineering
every
a chief
Manag6r.
engineering
throughout
of
who
reported
responsibility
functional
responsibility
supporting
the
Apollo
group.
The
organization
consisted
of
personnel
assigned
[.
directly
to
.support
"
{?
Project
i
,.
major
Garment,
Each
.-
CEI's
of
thesa
company
by
of
CEI's
were
then
Contract
of
are
End
Item
made
the
project
(CEI)
,z
responsibilities
flight
'"
definition
support,
all
a prime
of
a project
engineers
;"
in
accordance
with
"
these
through
long
from
concept
people
responsibilities
'
development,
that
were
stage
of
a design
production
manufacturin
engineering
drawings,
and
instructions,
in
CEI
which
the
coordination,
requirements
to
project
engineers
expertiso.
were
their
involved
engineer
retrofit
tooling
Historically,
space
knowledge
the
CEI
Typical
were:
problem
design,
change
suit
with
production.
engineering
CEI's
support.
gained
through
every
a group
were:
assigned
and
engineers
responsibility
activity,
respective
experience
its
Sol,_e typical
engineer
change
had
by
on
effecting
contributor
analysis
their
the
gloves.
Since
decisions
or
EV
project
as
was
Meteoroid
emphasis
engineers.
engineer
was
failure
junior
major
associated_in
engineer
Themnal
and
sub-divided
were
through
assigned
engineering
and
Design
lead
was
project
engineer
were
the
engineer,
by
the
to
groupc.
was
that
associated
or
of four engineering
and documentation
Assembly
Additional
assigned
a project
Visor
engineers
non-Apollo
responsibility
_roups
requirements.
or
CEI's
"
other
engineering
Extravehicular
thermal
were
supplemented
some respect.
As an example,
one project
assigned
responsibility
for the Integrated
_'_
1
from
group
The organization
primarily
consisted
disciplines;
design_
project,
systems
into
"_
Apollo
personnel
_.
.
the
CE_
design
and
support,
fitcheck
activity,
support,
and
testing.
-i07-
;
j
for
It included
all manned testing,
final CEI acceptance
testing,
The system enqineering
group was primarily
rez_)nsJ.b!e
fitchecks,
qualification
testing,
interface
coordination
and
!.
system
level
!
_
of all
The documentation
non-system
level
engineering
group.
process
procurement
:_
"
q
all
activities
and
.operational
l.
i
t
Some
materials
!
planner
!
:
i
because
by all
system.
|
and
'
and a test
the
test
and
gzoup
directing
was
generation
of
trouble-shooting
consisted
whose
space
group
included:
testing,
costing
engineer
this
directly
the organization.
production
scheduling,
orders,
field
reported
from
this
and
change
instructions.
within
organizations
performed
coordinating
of
drafting,
group
sub-gro_pc
evaluation
remaining
who
spacesuit
engineering
support
responsibilities
was
of an engineering
and
activity
prime
suit
responsibility
test
activities
in
labs.
PROBLEM:
engineer
coordination,
included
engineering
specifications
The
total
and modification
selection,
material
the
specifications,
material
required
typical
with
This
documents
to the chief
dealt
documentation.
_ small
usually
that
Throughout
I
support
tasks
associated
functions
were
with
i
"
making
ILC
which
assigned
space
were
to the
these
the engineering
BACKGROUND:
the
suit
program,
primarily
several
performing
engineering
production
organization.
non-engineering
tasks
were
Costs
charged
to
department.
The
functions
and
test
The
glove
included
glove
modelmaking,
pattern
technicians.
model
maker's
major
responsibility
relative
.w
to the
I
I
,_
suit
manufacture
!
1
making
program
of custom
a master
it to make the
were developed
(_
consistent
exception
was
mold
development
gloves.
from
of molds
This
the
astronaut
custom manufacturing
early in the program
regardless
of a few
of the
design
task
size
used
for
consisted
of
hand
and
cast
the
using
mold.
Time standards
and were fairly
of the
improvements,
hand.
the
With
techniques
the
used
-lOS-
by
!
!
.
\
'
the
glove
tile program
which
primarily
The
glove
very
relatively
deve]op:_ent
early
in
a manufacturino
assigned
were
Following
occurred
been
modelmakers
making
modclmaking
function
the
molding
program,
tl_is was
supp0_'t
function
and
to
that
function
was
in
terms
department.
very
of
similar
to
enc;.neering
I"
_-
production
this
was
should
|
in
requirements
primarily
been
Test
technicians
of
for
the
assigned
a suit
program.
to
large
An
to
_:
Again
department.
of
make
_'
and
that
variety
attempt
necessary
function
organizationally
a
of
astronauts.
support
perform
phase
patterns
assigned
a manufactt_ring
have
support
develops
<
versus
program,
maker
th,: development
the
pattern
s.ho_nld h_ve
manufactu_-in,
the
During
technJcue:;,
3 support
of
throu_;hout
the
organizationally
pattern
unchange.]
functions
a realistic
eshimate
and
i
.
of
that
associated
since
it
However,
varied
several
readily
These
tasks
included
and
equipment
that
were
t
&
'.
primarily
'
the
of
the
of
be
identified
material
structure
of
and
responsibility
of
the
of
engineering
impractical,
production-associated.
of
adhesive
properties,
standard
a function
with
_.:ould be
as
testing
calibration
as
associated
to the dyna1_ics
of the progrsm.
performed
by the technician
daily
relatively
load
manufacturing
according
functions
could
testing
work
with
group
weekly
technician's
fitcheck
repair.
These
in
of
the
terms
organization,
were
in
routines
and
rate.
the_e
and
support
time
production
engineering
samples,
varied
Because
function-s
many
cases
were
couhs
IJ
associated
I
'
_.
with
example
manufacturing
these
functions
occurred
problem
were
charged
to
engineering.
when
idle time occurred
or when
job was difficult
to identify
during
when
the
detailed
trouble-shooting
direction
of
of
the
the
A
'
a
technician
,o
was
usually
charged
,
'
to
With
and
provided
by
engineering
the
coordination,
possible
an
engineer.
rather
than
exception
reassignment
of
This
time
was
normally
_/
:.,
manufacturing.
of
improved
functions
communication
:
%
:
identified
-109-
'
w ,
|-.
herein
would
However,
from
assignment
program
in
px-obably
the
would
costs,
smaller
costs".
GUIDELINES
not
result
standpoint
result
in
this
share
of
total
FOR
FUTURE
Personnel
of
in
and
in
a new
cost
a more
program
management,
realistic
situation
cost
saving:.
*
distribution
wou]d
being
proper
have
of
resulted
identified
as
"engineer__ng
PROGRam, S:
supporting
the
manufactuxing
process
should
be
assigned
department
{-
responsible
their
or
tile manufacturing
for
the
department
financial
mission
management
requirements
ii
qualificati,_n
activity
'
of
engineering
continuous
BACKGROUND
L
manufacturing
should
of
be
tasks
suppo_:ting
In
a period
Febxuary
1972,
prog_-ess
for
month
! _!
time
which
in
caused
turn
continuous
dictated
a high
level
support.
was
extending
active
29
period
cycle
months
(see
or
Table
utilized
in
from
February
qualification
approximahely
i).
1968
through
testing
was
70%
Approxin_tely
testing
to
meet
of
the
72%
new
or
of
in
49
the
redefined
test
mission
requirements.
The remaining
time was spent
for a combination
of equipment
failures
and
in qualifying
design
changes
such
disconnects.
as
Fifteen
_.
the
PROBLEM:
Changing
to
effort.
oxganizationally
adding
arm
months
were
remaining
noted
time
on
include
spent
4.4.6
_dditonal
and
and
expended
was
Table
procedures
bearings
on
final
wrist
on
the
A7LB
the
A7L
suit.
The
test
time
reflects
time
large
active
spent
in
reports.
suit
preparation
For
all
while
the
elapsed
and
of
times
does
test
practical
not
plans,
purposes,
it
can
be
progress
stated
throughout
that
qualification
the
total
test
activity
was
in
period.
{
Since
organization,
total
:
cost
A7L/A7LB
of
suit
this
task
no
attempt
the
deals
only
will
be
qualification
program.
The
with
made
the
herein
activity
objective
engineering
of
to
performed
this
_
i
develop
during
section
is
the
to
{
-IIO-
identify
engineering
costs
associated
with
quaiif_cation
\.
I
testing
and
recommend
costn.
Through
methods
a review
of
of
red'acing
program
these
engineering'
engineering
charges,
it
'
has
been
support
was
testing
support
regardless
consisted
of what
phase
of a con_ination
pattern
designers
and
does
I
that
required
nc,t include
_xpendc:d
:_
on
include
estimdt_d
to
the
the
CEI
ti'ne spent
four
r: n months
support
systems
in
of
of
the
start
failure
of
in.
This
hardgoods,
This
and
DVT
but
does
a:_d preparation
of qualification
documentation
such as plans,
procedures,
TRR's
and report's.
On this basis,
it is estimated
that
;
D
minimum
in
_
!
t
year period.
requirements
of
direct
196
man
support
months
of
If
had
of
engineering
qualification
time
test
complete
and correct
been
available
prior
support
_
_"
"
/
time
testing,
redesigns
engineer__ng
qualification
engineers.
development
to
qual
month
month
the program
was
of softgoods,
test
design,
prior
each
per
was
activity
expended
in
a four
mission
of
?
o_
testing,
it
M_ssion
can
test
be
assumed
programs
that
would
only
have
the
been
Mission
necessary.
and
These
:_
two
progran_s
required
seven
and
On
basis
of
nine
months
of
elapsed
time
_
respectively.
engineering
test
expended
I
,_
4 [
(7 + 9) +
The attainable
months
}"
'
preparation,
for
of
reflecting
show
month
these
two
attached
of
period.
flow
months/month
40%
increase
contingencies;
programs
would
have
to
total
of
cover
time
been
:'
man
by
preparation,
final
[7 X
0.4
chart
requirements
allowing
report
(7)
4-4-4),
a future
program
program
takes
in
total
a 40%
increase
in
39.2
man
months
seven
advantage
minimize
contingencies,
program,
a
to
and
] =
(Table
for
a qualification
subassemblies
Again,
loading
Th._s p_e_osed
time.
be
and
man
0.4
(7 + 9) ] = 89.6 man months
of effort.
savings
would
have been
196 - 90 or 106 man
performance
qualification
would
allowing
reports
engineering
and
four
engineering.
The
:
_
support
the
qualification
time
total
of
of
for
test
time
effort.
-iii-
"
It
I
:,
attained
I :
t
to
by
savings
similar
i
is
obvious
that
minimizing
of
savings
qualification
direct
test
qualification
engineering
of personnel
bench
tests.
considerable
savings
needed
to
test
%zill
perform
be
time.
DVT
addition
time,
by
and
be
In
_upport
realized
delta
can
the
reduction
component
GUIDELINES
FOR
i.
Cycle
I
_"
"
"
_
2.
,_t"
i ,','
L " '_
,.r
for
all
CEI
CEI
being
should
If
PROGRAMS:
requirements
must
possible
testing
"
(-'
FUTURE
the item
classified
missions
establish
failures
trade-off
thoroughly
that
occur
its
useful
during
should
be
the
utilize
the
no_ possible,
endurance
the
life.
qual
performed
defined
might
qualified.
_f this is
be subjected
to cycle
to
be
testing,
to
determine
if
/
1
t
that
(
3.
should
be redesigned
as a limited
life
cycle
testing
Subassembly
3.4
had
been
qualification
should
be
and
item
to
"
completed.
as
utilized
retested
or
to the extent
reflected
preclude
in
test
section
delays
?
if
a failure
failure
/
termination
i_.
analyzed
4.
!.
and
of
On
the
testing
past
CEI
until
corrective
programs,
required
the
action
on
the
such
was
CEI
as
complete
failure
defined
expensive
could
the
astronaut
and
have
Rocks"
resulted
been
In
precluded
mobility
A7L/A7LB
were
for
redesign.
allowable
._
made
and
CEI
prevented.
factors
"young's
the
be
during
safety
allowance
1"
should
occurred
initial
on
part
of
Overtesting
that
any
occur.
was
and
_-
implemented.
I
i
to
should
"i
set
g"
programs
were:
high,
versus
caused
i/6g
latter
no
effects
techniques
undue
a test
the
examples
too
mobility
in
Several
stresses
failure
case,
by,definition
and
redesign
of
techniques.
PROBLEM:
I
(
Astronaut
L.'
part
of
the
significant
fitchecks
pre-delivery
amount
of
'
#
were
performed
acceptance
engineering
..
test
at
which
the
depot
as
required
support.
I_
Ii
-112-
i["
i
BACKGROUND:
Because
'
_ _
space
at
the
depot.
_"
it
was
imperative
r
!
addition
could
the
suits,
of
to
cause
cables
(ITMG)
. necessary
_.
it
and
necessary
order
to
that
cable
premature
failures
correct
fitcheck
by
softgoods,
!
_
}
preparation
required
the
CEI,
In
lengths
mobility.
Since
Meteoroid
fittings,
of
Ccver
it was
established
integration
of
an
average
hardgoods,
engineers.
supporting
A7LB
and
the
ITMG
and
maDhours
of
testing.
Each
manufacturing
of
Thermal
be
and
performed
cable
permanent
to
be
restrict
lengths
prior
A7L
correct.
improper
and
with.
the
fit
were
Integrated
cable
installed
! {
f
the
attached
optimum
lengths
fit,
of
fitchecks
obtain
suit
were
design
that
affecting
acceptance
support
of
In
that
_ ;
II
was
integrated
wei:e beneath
permanently
final
the
systems,
This
supporting
support
hardware
personnel
and
of
the
52
project
and
consisted
and
of
facilities,
actual
pre-fitchecks,
coordination
fitcheck.
This
52
:I
hours
fitcheck
discrepancies.
_ _
procured
on
did
of
in
_
[
the
__
J
of
1
%
do
accomplish
'
adjustments
I
I
cables,
should
time
this
required
It
resulted
during
the
in
this
technicians,
training
FOR
not
FUTURE
a design
make
this,
should
which
are
be reduced
is
in
life
estimated
of
report
quality
200
10,400
the
in
correcting
PGA's
manhours
that
elimination
the
elimination
have
inspectors
equipment
with
more
one
of
contract.
would
of
Other
been
and
realized
program
to
support
efficient
utilization
time.
PROGKAMS:
requirement
fitcheck
that
initial
a requirement
a modularized
be
the
roughly
support.
have
required
basis,
cost
of facilities
and
and savings
associated
Impose
areas
GUIDELINES
On
reflected
astronauts'
i.e.,
not
personnel;
fitchecks;
of
would
engineer
savings
engineering
9-6100
fitcheck
fitchecks
full-time
include
NAS
engineering
not
considered.
suit
of
with
Use
of
fitchecks
PDA.
To
simplified
sizing
permanent
sizing
for depot
fitchecks,
With modularization,
-113-
slave
I_
L
selection.
be
sub-assemblies
could
Ideally,
preselected
on
the
be
used
only
the basis
for
pre-ma_ufacturing
sub-assemblies
of slave
that
units
size
would
could
be
not
the
[ii
gloves.
The
to the depot
few
times that
suit might
for rework
as a _result
of a require
fitcheck return
problem
[[.
would
less
be
commute
far
to
expensive
than
having
the
astronauts
the depot.
PROBLEM:
]"
.:
Limited
L L
the company
[_
required
In terms
company.
to speciality
[.
than
space
gear.
of
i
i
_J
and
resources
_utside
the
suit
program
was
not
of the
required
such
and
engineers
could
employed
by
products
protective
an average
pool
was
a large
the
and
non-suit
Company
the
need
engineering
quality
for design
hired
_
amount
and
specialists
of
in
are
not
taught
but
are
learned
In
1
|
-_ requiring
_"
through
large
support.
were
his
no
engineering
curriculum,
experience.'
necessary
longer
companies
required.
he
could
such
"
'_
design
engineering
the company
engineering
department
to the engineering
department
when
expertise,
Small
a classical
companies,
WOU_
be drawn from
needed and returned
services
of
reliability
i.
as part
Therefore,
were
unique
dictate
80%
the
supported.
The high
.i
o_ _ngineering
limited
not be
of
expertise.
otL_r
personnel
expressly
for working
on the space suit program.
A space suit program
requires
an extensive
engineering
limited
inflatable
The
that
been
shields,
program,
NASA.
was
a small
i_
[-
i
5
miscellaneons
line
has
face
with
product
line
helmets,
suit
within
to maintain
is considered
product
was
most
_
_
ILC
or company
space
groups
skills.
business
requirements
__"
the
group
Examples
were
other
engineering
su_t
ILC's
staff
_.
its
items.
During
company
[
of employees,
suits
structures
space
engineering
Historically,
of other
the
" minimum
of critical
BACKGROUND:
resources
In the
event
be recalled
as ILC,
not
talent
when
his
i_
_
:_;
of problems
for
having
short-term
the surplus
resources
available,
'
requirements
of
conditions,
the
must
the
hire
to meet
the
program_.
Under
these
individual
personnel
engineer
must
be
suppo_.ted
for which
they
were
almost
entirely
_'-
by the
program
committments
support
resolution
throuahout
!
[_
l_-.
-
f_
I_
require
the
retain
as many
costly
but
that
of
the
is the
FOR
i.
FUTURE
NASA
should
that
the
company
This
be made
can be
in order
to
leave
no
other
alternahives
supply
services
specialist
associated
skills.
An
with
example
certain
of
testing
probably
i
_
development
and change activity but in a progr_,
with limited change activity,
it could result in
_.,
2.
,6t_,'
I,
.
I.
t._,'
NASA
/_
and
result
could
contractor
by mission
organization
facilities
I
_
Another
responsibility
system
flow
time
failure
primarily
for
qualification
would
for
Excluding
requirement
personnel
option
must
engineering
activity
failure
changes,
be retained
all
resources
avaialable
of product
retrofits
levels
that
would
redesign
and nod
is completed
with
to handle
and
analysis
of
exist
(_
all
approval.
Qualified
iil
'
This
in increased
perform
it
specifications.
analysis
is probably
engineering
activity
! [
analysis whereby
NASA could
in the form of analysis,
savings.
caused
_ |
:'
occurring
"
must
to
Iii
a net
_.
prepared
as practical.
that
contractural
PROGRAMS:
engineering
problems
"experts"
[!
be
it is imperative
trade-off
When
OPTIONS
_i
contractor
any design
program,
of
the
hired.
kit
and
be
in the
failure.
at NASA
might
by
at
them
for NASA
use
the
fabrication
The
to retain
Contractor
once
|',
L
PROBLEM:
[_'._
Manufacturing
-_-
engineers
responsibility.
This
significant
amount
were
not
in
design
resulted
of
time
given
enough
engineers
supporting
spending
production
floor
problems.
):_;
In
_'_
few
t '
of
"
_
_
_:
the
early
personnei
were
the
[;_
_,
space
suit.
These
were
the
suit
well
as
and
making
This
were
delegated
I-i
they
gained
<
i..
Eventually,
_:
full-time
:,
consisting
_
was
_
_
!.
However,
additional
responsibilities.
design
engineer
_l'
_P
and
_ _ "_
}
I'
during
GUIDELINES
the
expensive
I.
_
t" '
_
I
%,
tl
_"
_,--
_"'l 4.,."
!
_'t
basis.
and
was
experience
reduce
caused
engineers
decisions.
engineer
by
quality
support
engineer
manufacturing
inefficient
matured,
the
manufacturing
were
delegated
required
was
not
only
lengthy,
allowing
training
should
manufacturing
the
committee
was
process
when
effective,
and
techniques
costs
to
transition
development
recommending
manufacturing
a design
and
was, then
detailed
design
until
program,
program
engineers
writing
the
area
Manufacturing
CEI
the
solve
technical
assign
of
PROGRAMS:
phase
for
_he
in
area.
the
This
to
for
supervisors
make
to
as
manufacturing
production
development
FOR
FUTURE
or
the
although
as
acquired
"as-needed"
4,
system,
the
resulted
decisions
to
fabrication
required
manufacturing
engineers
I-
modifications
design
production
and
_i
.i,
the
This
costly.
in
qua_:ter
a design,
to
developed
schedules
production
activities.
The
of
who
documentation
of
very
engineers
necessary
last
program,
and
experience
became
the
because
role
suit
design
technical
occurred
the
assigned
If
key
the
Through
all
program
enough
to
with
design
of
the
it
tile space
engrossed
Tight
problems.
I.
the
preparaLion
engineers
of
familiar
were
production.
I!
days
to
ol
on
an
inefficient
_dequate
time
personnel.
get
involved
the
extent
instructions
that
will
expedite
CEI
goes
into
during
of
and
flow
production.
-i16-
2.
Discrepant
must
be
clearly
caused
_
conditions
by
and
defined
generating
the
level
of criticality
te preclude
unnecessary
lost
time
discrepancy
reports.
3.
Manufacturing
[_
tooling
responsibility
requiremeDt
of manufacturing
Participation
should
be
|
|
the
engineers.
of manufacturing
engineers
_
during
U
I
(.
the development
process will reduce the number
of "one-time
only" tools made for the purpose
of
checking
I_
4.
out
design
phase
has
started.
They
an as-needed-basis
PROBLEM:
i
I
that
responsibility
by
other
Engineering
'
only
in the
engineering
change
orders
title
implies,
group
documentation
periods
Liaison
that
was
originally
CMO
of extensive
be given
on
"
!:
_
increased
of discrepancies.
the engineering
been performed
group
group
as
the
_5
the
program
change
As
their
between
office.
the
engineering
design
for engineering
functions
to process
for
within
responsible
liaison
and
formed
required
problems
specifications.
performed
drafting,
the
when
a small
and operational
they
be used
groups
was
organization
engineering,
was
program
as a support
production
only
disposition
Activities
were performed
by
were redundant
and could have
effectively
i $
and
should
5.
!
_.
Design engineers
should serve only
function
to manufacturing
once the
I_
concepts.
The
engineering
changes.
activity,
<
During
it was
the
determined
:_
,.
that.project
"
amount
of
The
requirements
and
their
majority
iI
" [""
suit.
as
to processing
of MIL-D-1000
A change
seven
time
engineers
of the workload
of assemblies,
_
design
levels
was
which
sub-assemblies
and
were
devoting
change
created
documentation.
by
necessitated
component
to a simple
piece
part
of drawings
in addition
an extensive
could
the
contractural
total
parts
documentation
of the
affect
to process,
i'
as many
procurement
-I17-
........
....
and
test
specifications.
_:_:
backlogs
occurred
and
were being overlooked.
identif_
all
that
changes
all
As the
workload
became
excessive,
changes
to second level documentation
Liaison
engineers
were tasked to
documents
affected
were
by
completely
a change
and
and
correctly
to insure
The necessity
of this group was justified
under the circumstances
that existed during the Apollo program_
However,
if drawing
F
_I
requirements
are reduced
(see Section 3.1) on future programs,
the need for an engineering
liaison group would be reduced.
" The
resPonsibilities
divided
between
the
Configuration
of
!
A
[;
Management
technical
would
$
performed
engineering
documents
remain
byorganization
this group
Organization
such
could
and thethen
(CMO).
as process
and
be
Preparation
test
specifications
the
responsibility
of engineering
while the
of
documentation
and
processing
coordinating
engineering
change
would be performed
by the CMO group.
This transfer of
responsibility
is considered
feasible
since
check-and-balance
and coordinating
activity
much of the
performed
by
the
to activities
Liaison
Engineering
performed
by
A flow
the CMO
process
of one
Group
was
redundant
group,
chart is presented
of the
savings
by
transferring
[i
from
could
as
rz
responsibility
that
4.4.5)
example
ECO
cost
(Figure
an
the
be realized
engineering
r_
savings
would
I;.
documentation.
flow chart
to perform
that
be
attainable
Additional
on other
savings
not
occurred
between
control
o_ changes
of specification
.i
review
board,
and
CMO
and
notices,
maintenance
and
on the
il
expensive
personnel
areas of duplication
Liaison
participation
were=
control
instructions,
control
of change
reflected
Engineering
to manufacturing
change
types
ii
_
il
Ill
'
documented.
I_
_.
on the
change
of component
lists.
-I18-
F"
Total
[ -k
transferred
the
responsibility
to
[
)
size
the
people
during
During
these
new
"
on
the
_.
_t
on
existing
[,
_,
_'.
estimated
groups
_!
level
;
!
man
:"
the
with
CMO.
further
of
of
the
one
During
reduced
was
changes
the
contract.
program.
remaining
in
to
40%
one
is
other
of
the
is,
could
in
of
CMO
the
CMO
manpower
the
be
phase,
person
to
to
five
reduced
engineering
operational
occurring
reduced
It
That
Program
five
generated
were
was
of
of
phases.
being
group
Apollo
the
varied
a level
The
reduction
A7LB
the
group
responsibilities
a net
during
people,
be
in
during
required
to
part
be
affecting
development
concurrent
models.
later
result
Skylab
while
or
reached
aocum_--ntatlon
a transfer
required
could
suits
liaison
group
and
new
operational
would
reporting
"r
model
that
three
Apollo
periods,
easily
group.
engineering
The
can
hindering
the.cnginc.cring
the
the
functions
without
program.
during
people
to
of
A7LB
these
group
of
during
" one
o CMO
effectiveness
The
;:
for
and
the
two
level
group.
[,
GUIDELINES
.,_
Expand
change
the
.,
FOR
the
activity
engineering
FUTURE
PROGRTW._S:
responsibility
functions
which
are
the
normally
group
to
performed
perform
by
group.
[
t.
//
_.
: _
-I19-
'
I'
:i
|1
-120-
...................
.
ill
nil
Ini
- ........
- i
i
',.
.,-I @
__
f,) _
4J-,-4
_.
0-,-t
t'-
g
_
..
f
;
i
f"
"
_"
- _
._
_-'_
l
I_
_
,.41J
_
14 1,4
_ _
-r"_,,-I
O_
_ _
-,-I _
I:_ _-I
..I.I _
_
-r-_-.-I
O_
_,_"
" -
__
._
_ _
._.a
__.,,_
_ -a
-H
4-)
_'_
_
!
_-
._ _
1o-,O
_r_
1.1o
:
(
- "
f .
m 14
0
U .a
k_
0
,a
__...
;
c_
'I-I
"'_%
un
I II
--
,
I
II
_
-121-
'
f
I -,2 I
; "_?_,
:"
_"
--_ r_
I -
'
_S
--
I-----
-c-
'
I._.
.
t -_
I*-'
_
--
-"
,_ _ _-'_
_'_
o .a',
"
"--_
_ , .:
......
>_
"_.
. ".-"_._'_"- ""
f_
el
"-, ,_ _'_._
+............
:.?.
"__
i. t`'-
i
:...............
(_
,_
-.
P_
(_
":_._--'-:._L_
:" ............
e _.....e
-4,
--- _"_ -.
L_
,1_.
--".......
.--
('
('J
_'_!
_'_
_'_f
_
---:- ....
_'_'
cJ_j
;___
.................
'
_ : ......
;_._,
"_
_'_-I-,
",.
_._L___ _ _'_ _ +
':_]
_"
;_,._;
"*i'
--. cq k_ "-. N
.I
_I--
J,
. _
.,j
'
--"-'
"... ..
{:,6.
'
.....
_ . -+'_'-
r_ I',. ,,. _
..
o 1,1 .I _.
__
...........
.....................
_I
".
'
"
'
'
'%---|
"
; "_I
"
-a ....
_:R,
"',"
_: -.. N'
_'
?
_..
_"
_,-
'
.
I .f "I
_v,,
;el.
"_
:,
I
I
.._=:.... _,-.._..,...:
-.t
r ..................
-4-- .............................
,J ,,|
, '
_ , _._.
I. ''/--
1"" t ............
.... _
.e,"....
_" _
i lJ"
_..-_,
,_:
"_"_,_"
_. -- | .....
.............
...... .............
.....
,_,._,
..........
I!
lllJa
;
,_
_- _P_ N' N
_ ** *, --A---,--
,_;-............................
_ ..............................
',
_I N
"i ......
" ,,.
,o
:,.q
.,..
--_--.*
,,_.--_--4,_._
..............................
I..' '.q
J
........
"_'--'---.....................................
,_.m
".
'
-.
G ......................
"J_
_'
_.
! :" ,<:>"J
....
; ..............
" ...._
.......................
_ "J'- -,,.
"6 .
t..._
".'------1--'-I
..,J
_.|
,'-
....
.t
_L_
_':_"
.
_:
.....
_-" "-
"'--N
--t
I
_.
--_
"
"
a:
:.
_=1
"%:
I_ _
t----T-H--. _...............
i"-;_
i" ''e_........
_ _
, -
Z_
...,
,_,
..............
..........
............
':..,..
.....
_ <>
'..--a
'. VI
"- .........................
o
o
;
,
_"
t lq , _' m
- _ o ,
;
"
--,-A....J
- - -
_,_
..............
........................
_.
Il
! "-
."'
-"
,,-_
..
T_,
_
<'>3
I:
li
.._,
:
; ............
'
uf
c_ ,: _
II
"
_ _I _I
-4
Iiiii
;
I ..I...L...J.
,..J.,..J
.. :
r"
FIGURE
4.4.6
.
%
J
"
QUALIFICATION
["
A7L
ITEM
PGA
REASON
FOR
QUALIFICATION
DATES
Mission
1/25/68
ELA2SED
TIN_
(_._O_T.IS)"'_
7.0
8/29/G8
|'"
Fluorel
Boot
Soles
Qual
new
material
8/1/68
1,5
9/19/68
) ..
,-
A7L'PGA
Mission
C Prime
10/15/68
0.25
10/22/68.
A7L
F
L_
A7L
PGA
Lunar
Surface
Mission
11/12/68
1.0
Mission
2/4/69
6/12/69
4.5
Requirements
3/13/69
3/17/69
0.25
Requirement
4/24/69
12/12/68
,'-"
L_rge
Wrist
(Apollo
ll)
r"
Disconnect
-
New
".
Arm
[
Bearing
(Apollo
Boot
I
|-
.New
i!)
0.24
4/29/69
Bladder
Flight
(Apollo
13)
Arm Assembly
and
EV Glove
(Apollo
14)
failur_
Redefinition
of
Cycle
requirements
1/9/70
0.25
1/14/70
9/22/70
10/14/70
0.75
I
I
Redesigned
Convolute
i"
Thigh
(Apollo
Qual
ATLB
PGA
(Apollo
15)
i
.
'
A7LB
PGA
(Apollo
16
Mission
& Skylab)
Total
Period-
Total
Time
Calendar
I
in
Time
Boots
1.5
9/21/70
6/25/71
9.0
9/3/71
2/21/72
5.75
SEVA
months
Qualification
in
and
12/3/70
1/14/71
Testing
Qualification
Testing
32
-
months
29 months
""
i
"
49
New Requirements
(Young's
Rocks)
SL
Failure
14)
--
.
'
-127-
',
-128-
B,
5 1
TITLE
Traceability
_
In
To
determine
i,
manpower
,.
Apollo/Skylab"
: I-
An
realized
in
through
traceability
evaluation
performed
can
be
by
an
Quality
and
evaluation
Reliability
of
the_
system.
flow
charts
reduce
described
It was
the
of
field
all
same
as
and
in
in-house
data,
Flow
was
also
determine
and
been
if
modifications
manpower
without
sites
discrepancy
in
center,
as
and
that
which
central
<
DR's,
and
contained
CEI
file.
maintaining
delivered
rework
reporting
the
center,
TPS's
for
a manual
Identification
requirements
of NPC-200-2
QI"
used
filing
generated
in-house
Chart
documentation
historical
field
to
has
capabilities.
is
trace
system
pape_ork
and
processed
I
traceability
The traceability
syste_
was
Data Retrieval
System
meeting
the
of
to
systcra
The
use
the
and
L
_
the
of
implemented
affecting
BACKGROUND:
[i
be
a reduction
[
J
can
if
APPROACH:
OBJECTIVE:
'
System
and
end
This
functioned
items
retrofit
systems.
copies
could
through
system
F
the
be
TPS
also
provided
L-.
trackin
9 of
Class
II
as
I
(
_
Documentation
documentation
Center
clerks,
I
["
documentation
technicians
engineer
and several
amount
10%
of
for
time
a CEI
well
as
Class
I changes.
The
utilized
full-time
traceability/
documentation
group
leader,
and
related
delivery
In addition,
23
quality
engineers
to
the
rate
of
every
,_
inspectors,
5
spent
a significant
traceability
one
system
three
(approximately
days).
PROBLEM_
i
3'
A
,
maintain
$1gnificant
the
amount
traceability
of
manpower
system.
was
required
to
--
,J,
'
129
I
?
BACKGROUND:
.-
i.
Tile system
developed
trace
system
and
r-_
L
(Ref.
NPC-250-i)
from
reliability
to
one
"
received
CEI
.
and
all
:
_
a total
capability.
field
data
historical
update
and
files.
and
provided
this
could
reduced
and
2.
>
be
store
data.
manpower
retrieving
if
data
task
could
be
requiredthe
many
& R department
manpower
of
of
treated
assigned
parts
and
equally
materials
with
An
Identification
of
must be completed
evaluation
critical
as early
to effectively
all
data
during
the reduce
production
"
However,
with
criticality
flow
(Ref.
evaluation
still
be
received
loop
A
_
This
non-critical
25%
system
Flow
in
has
Chart
such
decrease
significant
/_
parts
on
CEI's
to
material
of
past
trace
d_ta
has
also
revealed
the
described
respect
items
order
that
i
_
even
traceability
in
under
Flow
requirements
to
non-critical
phase
of the trace
contract.
Q1 ) structure
trace
.!
items
need
inspection.
a manual
improved.
The remaining
trace
would
still
require
a closed
as
in
were
and non-critical
as possible
in
definition,
.system
can not be
of parts/materials
categorized.
used
regards
i. "
[_ i
storing
to
shown
that approximately
25% of the
not have been
traced
past receiving
'
[
requirements
filing,
"_
requirements.
'_ I"
i _'-
j_
materials.
All
i_
several
receive,
Q & R would
data being
not
tracking
to
The
These
the
central
required
clerks
by the centr_l
department.
Parts
and materials
were
or
maintained
This
Central
Data Department.
responsible
for verifying
center
providing
traceability/documentation
file,
quality
data
of
historical/verification
a standard
time
Chart
will
required
QI"
be
to
-130-
w_
L_
"
|
L "
transfer,
log,
accumulate,
cross-post
and
file
data.
An
List
in
f_
'
early
would
establishment
also
performing
items
that
assure
be
invaluable
surveys,
long
lead-times
are
fully
a Critical
to
vendor
are
they
of
_)arts
quality
engineering
especially
or
dcceptable
for
sole
to
those
source
meet
to
long
|-.
I_
term requirements
of the contract.
greatly
reduce
the probability
of
["
downtime
failure
and schedule
impact
due to vendors'
to meet
full-term
contract
commitments.
Several
different
4"
3.
I:
data
were
methods
used.
proprietary
This
route
f _
used
by
record
model
cor_trol
by
i.-':
trace,
all
and
_
and
_ac_
for
Tables
of
and
accept
method
possible
for
reduction
three
required.
.
I
::_
_
!
meet
would
would
eliminate
of
changing
the
be
the
one
the
forms
for
the
were
means
:_
used
acceptance
and
_:
fabrication
with
method
the
as
drawing
used
to
subassemblies
be
established
Proprietary
in
would
would
system
or
CEI's,
as
early
be
filing
no
index.
a result
not
of
the
a
as
be
because
This
of
'
because
longer
easier
overlooking
and
fabricate
requirements.
realized
formats
be
_i
acceptance_
where
all. trace
Retrieval
there
any
the
should
different
was
sheets
room,
to
(T/O)
of
would
and
azeas
components,
uniform
personnel
accomplished
Operation
Regardless
{o
fabrication
manufachuring,
drawing
route
dip
_as
by
shop
fabrication
the
acceptance
and
tracing
data
to meet
Shop orders
were
the
production
except
orders,
sheets
of
where
inspection
other
shop
utilized
machine
data
Fabrication
forms,
required
various
methods
traceability
requirements.
of
route
traceability
sheets.
Different
i
tracking
included
inspection
inspection
of
This would
production
system
a revision
a CCA;
shop
to
i.e.,
order.
(
I
-131-
+
+
.....
,+
,+
, +...........
*4
l
4.
F"
,
Retrieval
the
of
vast
amount
Development
[+
data
of
the
,--
beyond
_.
number
of
It
i_
of
critical
versus
++
5.
i--!
t
items
alleviated
requiring
by
reducing
traceability
inspection
and
a single
format.
that
will
sufficient
still
quantities
have
to
be
traced.
computerized
system
should
be
undertaken.
to
identify
was
over
to
the
a ccnsiderable
years
in
as
Some
daily
often
duties
that
of
requests
who
data
previously
for
z2quire0
by
of
data
could
not
for
trace
be
or
and
of
a
(
[.+
non-critical
nature.
Quality
personnel
were
handicapped
in
data
by
center
NASA
work
as
personnel
priority.
While
contractor
provide
costly
to
NASA
should
be
generated
access
in
order
i [
or
I-
'
i
data
but
,_
redundant
are
various
information.
_hrough
could
one
be
and reliability
scheduling
quality
request
this
under
the
sourcc,
retrieved
control
The
a
:+
is
also
!i
++
procedure
non-critical
requests
specific
requests
data
top
possible
require
the
it
;
+_
traceability
the
to
departments
have
system.
requests.
related
If
to
service,
reduce
trace
afforded
a manual
to
to
for
normally
advantageous
data
often
any
was
_ ,
for
problem
different
were
necessary
funneled
information
efficiently.
--132-i
_
+
contractor
requested
;_
to
retrieve
charts
requests
for
amount
to
and
_as
a result
either
order
matrices
Overtime
normal
was
in
prepare
comparisons.
performed
established
,
resulted
and
perform
never
data.
data
NASA
be
a manual
request
data.
update
of
overtime
[.
a continuing
traced.
study
[+i
being
trade-off
materials
of
a cost
This
L+
could
items
procedure
_ould
because
al]_ parts/materials
combinations
proved
to be impractical.
anticipated
Therefore,
I+'
for
acceptance
is
consuming
and
a matrix
receiving
fabrication
time
parts
%'he situation
[:
of
capability
for
and permutations
[_
was
'
_!
>'
C_.
i"
P,1
GU IDEL INi':S:
,: -
Method
i!|-
I - manual
traceability
some
_i.[_'
syctc:m
tasks
to
The
requirements,
:i:["
I_
capability.
Using
::-V;
_[;
trace
trace
_I"
centralized
would
quality
incoming
QC
having
Class
This
sheet
}[
verification
II
in
this
ECO
time
storing,
duty
procedure
in
for
o_'der
to
how
and
may
manpower
faster
retriew._l
and
not
_i
!
sto_-Jn 3
or
be
seve]:&l
;_
overall
traced.
:
inspection
route
representa%ive_._
work
requiring
have
request
system
of their
will
fabrication
the
quality
as paper
reduce
data
as part
prograw, s should
who
fo_: filing
central
as well
Future
and
only
mon_.tor
and verify
This will require a
info_.-mation
and
center
will
een_er.
representative
representatives
_':I'_::
assurance
to the
transferring
in manpower
paperwork
data
and
center.
be reduction
of
pro._;ent
requirements
data
a centralized
data,
data
Str_oamline
reduc:i:_.
9
a reduction
function.
filing
'_
a specific
traceability
requirements
for
data
attaining
%
non-essential
The
This
I
i
or
redundant
traceability
baseline
_ould
as
support
requests
for
requirements
include
traceability
should
information
be
data.
:,
established.
required
for
such
i '
events
material
to
review
reports
"
developed
which
_.
minimum
amount
Ii
RECO_IENDED
.I
i! i
[
2.
I.
design
board
corrective
could
3.
"
_.
be
-_;
!I
malfunction
defect
A system
satisfactorily
investigations,
analysis
could
and
then
unsatisfactory
be
operational
with
of changes.
GROUND
RULES
FOR
_NUAL
SYSTEM:
Non-critical
to bedocument.
traced past
Mus_ function parts
under are
NPB not
5300.4
inspection.
Central
data
center
storing
and
retrieval
will
studies,
activity,
actions.
receiving
':.
All
verify
trace
will
of
handle
all
traceablity
filing,
data
and
,.
data.
data
_._ to be
recorded
by
._
a single
system.
i!
_le
by
advantages
"
full-time
system,
'
.......
'
-133-
|
?
1
m
_"
Method
_ f
.....
- Computerized
contractor
has
reduce
traceability
the
The
_.
II
computer
identified
The
access
by
to
manpower
be
other
the
system,
to
future
this
requirements
proguammed
flol cbart
advantages,
- if
computerized
cou]_
trace
system
"
could
sub._:tantially.
follow
guidelines
QI"
than
a reduction
in
manpower
f-
requirements,
requests
would
for
data
be
and
faster
less
retrieval
control
on
in
who
response
may
use
to
any
this
T'
service.
Class
additional
f-:
can
i.
in
r"
GROUND
be
the
changes
.anpe_:er
compared
production
RULES
FOR
may
requirement&.
be
tracked
As-built
as-authorized
without
configvratJons
configurations
anywhere
process.
COMPUTERIZED
i.
Compliance
2.
Quality
3.
to verify
all
The contractor
4.
handle
all filing
All trace
data
is
_i:
I ["
still
with
SYSTEM:
NHB
assurance
5200.4.
must
have
effective
cont_'ols
data necessary
to rneet requirements.
must have
central
data center
to
f
i.
f
system
of
and storing
of
to be recorded
data.
by a sir : e
reporting.
i
t
tm
!
h
1
t
;1
1J
'
"L'
___,..:.,i ..
2 _--:---_-:, ,% .
........................
{
-'I, ........
,_
5.2
TASK TITLE:
Inspection
OBJECT__VE
[
{
manpower
,-
APPROACH
of
Verification
d'.._;cre]_an'cypa_er,
p__'oduction
inspection
de::n-timu.
:
Evaluate
present
discrepancy
re'pol-ting
in
production
defects,
and
i
amount
and
[.
:
In-Process
Reduce
IL
and
overtime.
in-process
This
system
to
of
production,
identify
major
down-time,
evaluation
fabrication
and
inspection
problems
excessive
will
that
resulte6
inspectJ.on
concentrate
testing
and
on
time
the
acceptance.
BACKGROU_D:
::
',
Apollo/Skylab
of
cunsistent
NPC-?00-2.
suit
It was
with
the
inspection
implemented
level
of
to
system
met
assure
a product
confidence
requirements
necessary
for
!.
qua].ity
ii
I"
L
I
to
criteria,
[
i_
<
man/space
[
i
rated
Quality
'
system.
The inspection
that end items
assure
established
and
met
testing
system
a]l ore-delivery
a very
detailed
Components
and sub-assemblies
whe,-e characteristics
could
were
not be
operation.
and
Some
components
was designed
acceptance
inspection
inspected
verified
most
system
at every
point
at a later
sub-assemblies
were
!.
not
i
:_
teste_]
until
'
'
sub-assemblies
test
after
had
failures
asse-_blies,
overtime
production
flow
at
difficult,
on
.
J,
:_
was
mnd
may
was
the
or
of
of
CEI
manufacturing
The normal
approximately
and
scheduling,
ratio
of
one
to
to
100%
to
maintain
of
new
level
for
not be
have
"
,%
inspection
reduced
manufacturing,
until
cause
level
would
the
quality
detected
component/sub-assembly
impossible
fabrication
could
inspection
the
since
reports.
required
been
component/
standards
schedules,
system
have
These
inspection
manpower
not
at
C,_.I.
malfunction
this
portions
investigation
action
shipping
under
defects
of
strict
Inspection
delegating
Then
meet
inspection
verification.
because
to
affected
Quality
by
integration
CEI
and
would
had
testing.
corrective
have
greater
'
been
'
impact
!
i
i
inspectors
eight.
This
to
production
caused
an
operators
inspector
-135-
to
I
|
i
have
a:_ malzy as
at
one
given
"
time
awaiting
'
Even
tLot,sn
sequence,
article
90%
of
This
: _ :
I t
"
the
Articles
and
It
accept
article
_n
the
one
[
_
the
of
hour
_"
average
years
which
required
an
cause
of
problem
material
line
unt_ 1
,
n_-ure.
of
the
inspection
a considerable
a complete
the
to
the
amount
and
review
of
tags
board
befol-e
an
step.
averaged
per
in
the
hours
to
action
time
government
process
approxim;_tely
This
the
a reject
fabrication
program,
corrective
of
of
write,
tag
next
four
were
initiation
actions
of
which
day.
out
There
last
engineers
years
the
preclude
involved
were
four
evaluate
to
to
the
/
t
quality,
to
satisfactorily
to
the
actions
:
Lost
in-line
Due
components
criteria
to
and
an
the
and
program
of
capability
time
due
amount
A.
became
production
inspection.
BACKGROUNE
of
_e
in-line
added
reject
reject
board
large
process
that
assen_;ly
fab._'icate
generated.
two
and
manufacturing
each
the
average
design,
one
to
of
were
review
of
an
10%
inspection
for
processed
material
I.
:
to
req_ired
tags
of
This
time
an
Approxj_,ately
only
nature
1,600
PROBLEM
flow
writing
recurrence.
and
9 down-
acc_;mi,lis:hed while
to
four
inspector
wos
presented
be
reject
in
inspezt
inspection.
not_,.i_:g to
was
completion.
disposil-ion,
last
manufocturin
inspectien.
fabricated
an
could
30,000
"
took
by
to
component.
non-conformance
tag.
opereto_ _ had
inspection
(additional)
or
in
inspection
article's
sub-assen_b!y
o_
an
the
being
at
of
times
that
resulLcd
articles
in-pxocess
was
amount
return
_._as returned
meant
occurr<:d
e'J.ght d[f_-erent
This
production
all
article
or
period.
many
the
seven
components
completed
lack
sub-assemblies
absolute
for
the
end
separately,
essential.
or
item
No
other
sub-assemblies
use
to
until
final
adequately
in-line
method
met
all
testing
test
inspection
would
assure
acceptance
and
acceptance
CEI.
-136w'
_.
This
of
{
even
was
a costly
a ._:mall percentage
manufacturing
was
assurance
charged
item
was
acceptance
One
to
to
sacrifice
acceptance
at
_"
will
a reduction
{'
the
various
in-process
,;
be
to
inspection
allow
amount
made
that
must
a person
of
to
must
be
insure
available
to
management.
for
In
be
good
quality
insure
that
end
by
decreasing
the
any
poor
detailed
then
,'L
practice
All
operator
tools
must
be
quality
is
not
the
manufacturJ
ng
specs,
fault
'
' :
discrepancy
feed
incentive
and
Only
also
for
performed
by
inspection
as
an
provide
level,"
proper
equirment,
inspection
be
basis
will
will
audit
component/sub-assembly
quality
personnel.
have
to
be
of
Quality
function
a check
of
operator's
monitored
on
engineering.
certification
status.
"
should
scheduled
operator
motivation.
manufacturing
This
to
critical
acceptance
All
back
m_,_-;tbe
hiring
certifiable.
the
of
delegate
cert_ficatS.on
from
This
could
to
_,
and
Delegation
order
of
item,
testing
level.
required.
a part
to
(Example-
the
down-time
operator
able
future
responsibilities
made
fin,
_
sub-asser._J!y
C _ersonnel.
be
of
in
sub-_ssemblies
inspection
qual__t-y
on
confidence
production
responsibility,
i ity
inspection
inspection
manufacturin
since
to
reliability.
and
of
in-line
It
made
and
De)egakion
characteristics
respon_;ibi
of
component
implemented.
required
i
the
of
the
in-line
components
assurance.
acceptance
design
reduce
'
of
unacceptable
with
assure
without
design
of
considered
to
way
contracts,
is
method
Any
test
failures,
an
operator's
part,
of
operator's
certification
It must
certification
component
affected
be
CEI
would
component
failures,
on
require
testing,
testing
be
but
completed
an
understood
defects
still
from
poor
quality
immediate
on
re-evaluation
classification.
clearly
acceptance
Schedules
encountered
would
program,
final
resulting
may
the
with
to
that
occur
same
100%
impacted
not
the
by
under
which
way
as
quality
of
operator
will
affect
defects
inspeciton.
sub-assembly
degree
an
or
::
a failure
CEI' s.
-137-
The
system
confidence
,re,
st
level,
be
under
established
delegated
to
produce
inspection
on
th<
sac,r:
the
sub--
[
asse:1_uly
level,
complel-c,]
,
that
CEI
level.
mal,uf,_ctu_ii,%'s
in
Once
of
an
this
will
remove
malfunctions.
very
at
actually
in
order
an
analysis
a possible
cycle
time
to
during
of
an
opurators
to
free
time
Coupled
with
down-time
production
and
failures,
explanation
or
100%
would
occur
costs.
12%
of
This
This
present
total
figure
system
items
a!Io_.s
to
several
items
to
before
their
it_m
for
qu(n;tioned
defect
allowed
35%.
some
Quantity
in
or
se_;iously
fabrication.
create
the
of
level
approximately
the
point
implement
standards
has
in
cause
to
be
a_o:u_.t of
reduction
inspector
to
no
action
any
inspection
when
increase
II.
defect)
as
corrective
will
single
this
percentage
returned.
or
on
neces._;ity,
reports,
insp_,?tion,
amounted
inspection
absolute
creditabi!iLy
ma!f1_nctJon
eliminating
for
a certain
inspection
a componcnt/sub-assem_!y
quickly,
time
an
of
ProJuction
flow
fs
metho0,
inspection
This
(malfunction
questions
ever
_.;ith 100%
c_Ltiflcation
evaluatior:s
etc.
existed
inspect
is
rejections
this
created
to
discrepancy
cycle.
time
required
process
paper_ork.
A.
Sampling
of
over
length
the
discrepancy
of
several
significant
i.
to
"
2.
.
25%
30%
action
40%
scrap,
or
of
obvious
rework
required
design
board
not
cosmetic
non-conformance
30%
to
or
repair.
to
40%
revealed
written
were
requiring
no
written
were
rework
action
for
by
nature
were
engineering
scrap,
covered
has
discrepancies
Remaining
as
contract
discrepancies
further
an
3.
of
nature
to
the
paperwork
facts.
a minor
35%
reporting
or
of
requiring
a nature
that
interpretation
material
"use-as-is"
authorized
of
of
or
repair
review
repair
procedures.
-z38-
i
J
As
stated
' _
were
' '
It is very
generated
before,
eve_
approximately
the last
significant
four
30,000
years
to mention
that
tags
of the program.
the four
previous
reject
tags
in the
total
(approximately
evolutionary
cost
reduction
Evaluatlon
60,000).
alaount of rejects
This
. if any
nearly
efforts
the
amount
A significant
can be
process
_lice
years
i
U
to A7I,B/fikyl_b produced
reject
attributed
must
are
of
reduction
to advancement
be considerably
shortened
to be realized.
of effectiveness
of reducing
non-conforming
paperwork,
_ !"
that
quality
after
':
i
and
_
defects
and
could
fabrication
positive
disposition
not be built
of first
into
article
ability
the product
has
shown
especially
qualification
unit.
Dispositioning
of non-conformance
by manufacturing
quality engineering,
was very difficult
without
continuous
aide
from
design
engineering.
All
were
of
'
i
guidelines
on what was rejectable
nature, not requiring
generation
manufacturing
specifications
a general
Specifications
!
J
engineers
nature
lacked
to make
conforming
which
Inspectors
had
a questionable
nature,
because
guidelines
them
accept
in a production
i.
Design
criteria
6t
_L
changes
!
for
engineering
acceptance
delay
while
engineering
after
conformances
to
the
were
future
suit
criteria
of the previously
was
articles
minor
were
qualified.
rarely
in that
would
effect
the
of
This
being
resulted
made.
to change
acceptance
Recurring
sou-
"use-as-is"
valid,
suit
everything
insufficient
was
was
qualified
of non-
conditions.
reluctant
were
few
manufacturing
to reject
evaluation
was
very
disposition
there
dispositioned
rationale
to allow
effecting
for
inspection
definitions
decisions
items.
gave
but
changed.
multiple
design
and
specification
Design
changes
of
reliability
configuration.
-139-
Obviously
:
reporting
. ..
have
applied
problems,
the
cannot
adequately
[
]
:
defects
....
in
be
(i)
accurate
' ""
t that
exceed
_ allow
design
utilized.
safety
effort
(2)
to
is
tool
_Cost
Ruduction"
for
of
that
these
this
evaluatic_n
realistic
creating
establish
engineering
defects,
evaluate
to- o set
instead
of
to
Areas
margins,
manufacturing
Unless
study
amount
non-conformance
Quality
tolerance
the
stages
effective
tolerances,
is
of
imps.eL
" ", _.
earliest
most
It
disposition
program
the
manufacturing
:
and
significant
are
methods
occur.
make
tolerances
specifications
positive
that
dispositions
"i
,o
/of
'
I minor
non-conformances,
defects
.generation
,
i.
during
(3)evaluate
to
of
determine
those
discrepancy
The
above
the
design
all
potential
that
will
cosmetic
not
and
require
paperwork.
tasks
require
concept
sufficient
of
f]ture
manpower
programs.
loading
Well
defined
C _
l
i
goals
must
a long-term
be established
cost reduction
RECOMMENDED
FUTURE
GUIDELINES
:
SUIT
GENE}L_L:
Early
Quality
paperwork,
and
design
phase
Manufacturing
realistic
that
assure
GUIDELINES
will
A.
to
realize
Manufacturing
previous
be
and
Quality
Engineering,
to
a solid
most
significantly
form
efficient
means
decision
during
not
of
inspection,
in
involvement
an_
causes
in-proces_
ineffectiveness
goals
the
All
detailed
making
the
improved
unless
together,
foundation
of
operation.
SPECIFIC:
The
Manufacturing
must
provide
the
capability
specifications
the
non-conformance.
'
Contractor's,
engineering
will
establish
program
METHOD:
is necessary.
Engineering's
Design,
_"
by
Manufacturing
excessive
the
departments
production
i-
PROGIh_M
involvement
non-conformance
i
early
in
program.
Manufacturinq
to
evaluate
Engineer
and
Manufacturing
Engineering
must
be
fabrication
methods.
exposed
aDd.procedures
disposition
and
to
with
Quality
pre-production
-140:
2
i
J
A basic
Y
'
cause
encountered
as
and
base
;
l
'
to
realistic
'
Manufacturing
the
for
production
Quality
analysis
desion
phase
discrcpancie_
will
will
evaluate
with
the
production
engineers,
Desi. _, Engineers,
have
an
fabrication,
determine
criteria.
aided
will
of
opportunity
engineer,
acceptance
Manufacturing
pre-production
design
serve
disposition
non-conformances.
and
working
of
establishing
Engineering
observe
and
affec
during
a solid
future
and
by
collect
Quality
data
and
necessary
to
--
generate
will
used
during
_.
s -
Specifications
will
for
the
be
actual
encountered..
This
will
result
to
be
will
designed
in
the
the
they
of
during
the
of
the
from
update
are
the
majority
aid
reduce
allow
as
ability
that
phase.
to
pxoblems
continued
also
specification
production
encountered
_ithout
This
the
evaluate
conformiies
phase
manufacturing
production
Engineer
basic
Manufacturing
nonproduction
Design
"design
Engineering.
interpretation"
category
40%
of
of
reject
total
tag_,
which
represented
30
to
discrepancies.
Manufacturing
classify
.
specifications
defects.
classification
production
range
the
phase
of
an
the
defect
of
the
the
Inspectors
covered
delays
by
for
of
reject
product.
Failure
will
any
of
and
the
to
produce
the
the
wide
criteria
program.
products
or
in
during
accept/reject
phase
must
defect
part
specifications
evaluations
minor
important
product
production
will
and
procedures
classification
interpretation
during
"
plays
phase
establish
design
Major
add
not
procedures
disposition
specifically
causing
of
questionable
rejects.
t
-141-
T1]ero
\
'.
is
possible
product,
conditions
defects
requiring
be
!
I
not
_'
du]:ing
manufacturing
must
design
and
eflort
be
inJ.tiatcd
or
the
minor
defects
involvement,
for
during
of
minor
major
specifications
all
phase
rejection,
engineering
The
categorize
cosmetic
requiring
complete
and
the
dispositioning
improving
should
the
and
procedures
for
the
preliminary
i_
design
stage.
This
of
rejects
involving
conditions
which
reduction
,f
idcntify
fief'e, howevcr,
evaluated.
use
i
v:ay to
defects
r-
["
no
other
30%
mJnor
of
all
should
result
in
significant
"cosmetic"
and
represented
25
to
rejects.
(--
Manufacturing
provide
and
f
I
specifications
workmanship
inspection
criteria
these
i,
;
to
I
L
for
This
operators
be
an
by
Many
or
procedures
guide
as
tolerance,
acceptance
a tolerance.
items
condition
Even
must
manufacturing
times
sample
acceptable
_._ritten criteria.
expressed
to
expressed
pictures
constitutes
]
j
t
standards
functions.
cannot
cases,
and
when
of
are
In
what
preferrable
acceptance
visual
is
aids
are
awareness
by
helpful
comparisons.
should
result
to
in
better
acceptance
standards;
it
manufacturing
will
also
,,,
reduce
to
'
""
the
amount
inspection.
category
of
reject
tags
of
The
must
most
at
contractor
applied
if
order
the
comprised
35
decrease
"obvious
to
expand
the
This
level.
to
criteria,
testing
This
confidently
Operator
guideline
acceptance
40%
inspection
acceptance/r_-jection
subassen_ly
in
presented
reduce
and
Proqram.
effective
the
will
which
interpretation
Certification
non-conformities
This
defects"
total
of
would
is
concept
delegate
be
implemented
n-u:_t be
certain
-142-
[i_
[,
quality
acceptance
criteria
This Operator
Certification
-*
_
L.(
probation
an
period
invidivual
can
requirements.
_
[_
capable
Quality
i"
_
and
and
E
_
L_
!
_
"
["
!
of using
product.
properly
meet
be
the
evaluate
whether
_i
certification
certified,
they
must
all tools
provided
to
They must be capable
be
insure
a
of reading
understanding
all manufacturing
specifications
procedures
pertaining
to the product
such as
fabrication
awareness.
inspection
and the
drawings.
just
ability
operations,
they must
Diligent
pursuance
of
produce
waiting
;
_
To
Table
of more
Operations
display
than
w_ll
[_
to
to other
departments.
Program
must
be a
a reduction
which
return
will
from
reduction
of obvious
40% of all previous
Quality
inspectors
of
up
result
in
inspection,
defects
defects,
required
to
They
must.,
to perfoxm
show
this
60%
of
_
i
in-line
less
down-time
also
a significant
support
a Quality
program
which
comprise
and a reduction
to
35 to
in
production.
a
I"
['
"I
__
o,
-143-
,_-
_'
'
iiJii
i i n
..
;.
N_
I"
',
1,
_ I@_-._
.....
_.@
_,_.
_,-
.._.rrr_ ,.;';".-.
I"
.,.
I" I.LJ
i_.
1_
_ _
'........
@!"
>)
_,__ J
-147-
"_,+
_ -",4n"o_'"
.|nb.-oink.lv
z,
],|
i n l/n
i I nl i
[.
++-
,"
+
++ I-
_t
_i.
E _ _
__
i
++iT.[
"
"
t
'
'
I.
( ,
|
++
._
+ I
,_
' . -'.
*,
,
I '
P
10
I_
<=+
"
P
_02.
/+:
m
'
+++,+..++
i
-.1.4 9-
,+
i.
I
"
"
I
;-
/'*
"._
;
(.
.. L;
'-
:_
,--4.... _
,-
.... _-. :_
..
'
L
J
"--it"-'
|
*
:ec_l
_u.
I_ _._
_'1]
_L,,/
Ii_
L_),o:, :. ,,
t......J
;_.,
u.
I t_#
_ _-_-:_ _
m-iu,I
o I' /
I,TI
, _
|
o
a_l_
.....
:_;_:
-155-
I]
I-
'+5'+ -$+
I
,
_
i+_
,_
r:-_: , F:t_(_,o
l_
imp,.
+_
i/
I.=O
I _m
!_
I_,_
i__
I_l_r
I_ ,
,, T
,,: ,
'
i
_+c_
"--
It
it+,+. {]. ...
,
.....
'
=,- '. +
i_i_i_
:'
<"
+ '
" +
l//
[,
Ii
illla
I _
I
I
'"_-__i_
, i...----_-+ i
i/i
',<_
'
il
"
-+_ i
+l! ,:h_ i._I _>_ .'_'i''b_>
,. _=//,
>'it')
,I-_"_I_,
17 c._i
!
,
I , -XSB..J
'
I'7
r-_"
....'I
i....
,
,i I
_.....r_
-+ _-_
_-..j_.>..l
'
i*
zo
o_
I-,_wl+lJll
'
!!+<_:
_.
'
_l'>,<_i.+_,_
_:__-+': _:_"_Y_,sL:_l_,_i
,_
, ,.,
_
_,+P_"
_
.I I,,.'- _'l ,..,,...,ll
i-T-'
I__
I _t__
....
_,,
,o_
_-_..
,+_L,_t_,
l_ill!
'1,"
l; _+'
:'
':
II
,r
:" +
I_
t.,,..i
' '
ivt
"_"
'
.......
,i
glmJ_
il/i_,
'
, ,di
I_
5.3
TITLE:
L (
Pyoduct
Assurance
OBJECTIVE:
Evaluate
the management
_.
control
of Quality,
Apollo,
Skylab
reconuaended
I
manpower
APPROACH
and ASTP
programs
to support
GROUNDRULES
for
during
Using
the
the
guidelines
5 2 r determine
projected
in support
used
were
organization
of
and
the Apollo,
Skylab
as a comparative
used
to project
operating
and
baseline.
recommended
ASTP
Guide-
manpower
i.
The
Product
1970
through
Primary
("
5.1 and
Assurance
were
discussed
Safety
Summary.
Product
used
and
utilized
programs.
savings.
:
procedures
lines
suit
and Manpower
systems
Reliability
in paragraphs
The
svit
Organization
2.
The
Assurance
1973
emphasis
proposed
manloaded
organization
was
was
Product
to support
in section
Compliance
3.
used
as
for
the
study
on manpower
assumed
to
for
future
be
Assurance
organization
the program
minimum
baseline.
reduction.
schedule
was
the period
was
shown
:;
:
5300.4
assurance
requirements
programs.
DISCUSSION:
through
i
"I
During
the
period
1973,
the
_arious
assruance
Safety
were
continually
Reliability,
organizational
changes
utilized
in order
for the
study,
functions,
being
to most
1970
Quality,
subjected
effectively
to
manpower
utilization,
As a result,
ILC had
Product Assurance
approach
of confining
the
optimize
formulated
overlapping
the
or redundant
functions
_his
philosophy
general
manpower
I
('
attempting
requirements
an
in-depth
of Quality,
Reliability
is reflected
for
future
evaluation
suit
%n the
Safety.
proposed
programs
of all
an_
without
Assurance
disciplines.
'
-162-.
_
?
/
'
r"
The
specific
; .-.
_is
report
cost
savi,,gs
X
_i
the
past
_-
manpower
!-
organization
[_
In
[.
rate
i_
requized
two programs
months.
order
was
and
studies
were
those
the
was
The
based
to
a 1/20
revealed
5.1
which
Flow
proposed
properly
factored
for
areas
potential.
deltas.
to
(Paragraphs
procedures
an
of
average
compare
these
reflect
the
production
5.21
presented
displayed
diagrams
manloading
on
and
the
were
and
the
the
rate.
a total'manpower
to
1973
production
rate.
the
levels
Comparison
savings
of
resulting
organizatins,
estimated
significant
constructed
.970
1/5
mo_t
in
of
of
of
production
manpower
these
436
man
|_,
I
!
r
t
f
I
I
i
I.
t._
-163-
OU
'-'"
;:
I-} _
U _
g
0
0
,m
:"
- [,
"
,-4
0
-_
-164-
[-_
L
2
["
6.0
TITLE:
_ "
Organization
OBJECTIVE:
Evaluate
and Cost
the
entire
Summary
.
program
i
_
management,
engineering
%
and quality
[.
Skylab
organization
(ASTP)
manpower
and ASTP
which
savings
suit
resulting
existed
during
programs.
from
the Apollo,
Determine
the
the
implementation
overall
of all
f-
|
L-!
_-
the guidelines
APPROACH:
"
The
reco_nended
..
ILC
program
future
management,
engineering
ASTP programs
were used as a comparative
baseline.
The
guidelines
identified
in Sections
III, IV and V were used
[,
future
suit
savings
was
management
DISCUSSION:
[-"
As
guidelines
recommendcd
program.
then
The
Apull0,
Skylab
manpo_J_r
required
resulting
summary
determined
by
(ASTP)
to support
and
to
of manpower
a comparison
of these
program
organizations.
a result
were
of this
study,
recommended
for
the
use
following
on future
major
suit
programs:
Ill
i.
Place emphasis
on qualification
of subassemblies
rather than the entire spacesuit
assembly.
[!
2.
production
item.
3.
Qualify
CEI wozst
[
_
the
to the
first
time. _,_b_
4.
_
_*.:_Z
the
drawing
manufacturing
rather
mission
........
_I_L_,
requirements
instructions
for
|_
5.
[_
with
6.
Reduce
in-process
component
Allocate
and
sufficient
time
early
develop
efficient
systems
7.
Perform
astronaut
fit check
8.
Streamline
the data
data
reporting
collection
requirements
%_a_'
..,_
_,..,,.,
by using
:::
configuration
inspection
subassembly
the
.'._.'/
f..A"_'_.<
Q
100%
than
....
t ,.,-/.....
_
.....
_..i':.."_
control.
Reduce
item
case
.,.,,._.: .. ,_
quality
_-
the
the
and
organizations
formulate
supported
suit
_"
[-
which
for
programs.
"'7"_
:_....
"'_"
_
and--replace
it
acceptance
in the program
to
and procedures.
at the user's
requirements
and
site,._^>
centralize
system.
-167-
I
ii
["
_
F
_
9.
Consolidate
The
manpower
program
level
required
Skylab
period
1970
(A7LB)
through
and
was based on
compare
these
_"
tO reflect
1/20
of
an average
organizations,
the
production
a future
guidelines
was then compared
at ILC to support the
suit
prog_s
during
the
estimated
rate.
6.1 illustrates
the
1970
through
1973
organization
1/5 production
rate.
In order to
the
production
rate
was factored
levels
of ma_)ower
Comparison
revealed
a
four
yeara total
period manpower
if the
Figure
functions.
1973.
he ma_loading
[_
ASTP
control
to support
program utilizing
the recommended
to the level of manpower
required
Apollo,
management
of these
required
suit
two programs
savings
of 1565
man
recommended
guidelines
the recommended
for
months
are
program
d_ring
followed.
manloading.
_ E
L
Li,
"
[
'E
E
.....
tD
'
-168-
[_.
"
:!I
_..,,
:'U
'E
.i
IE
IE.
IE
E
APPENDIX
-A7LB
- INDENTURED
A
PARTS
LIST
'_ E
Z
;E
.E
E
[-;,
%
!'
L_
[_
k k..,
r_
_ [._
_.
A7LB-109017
A6L-104025
Mounting
Plate,
Gas Connector
Gage Pressure
Dial Indicating
D
D
A6L-104035
Mount,
A6L-104034
A7LB-109029
Wrist
Ring,
Back
Disconnect,
Suit
Side,
Left
A7LB-109029
Wrist
Disconnect,
Suit
Side,
Right
A7LB-109013
A7LB-101189
A7LB-101190
Mounting,
Ring Neck
Upper
PLSS Attachment
Bracket,
Attachment,
"A7LB-101191
A7LB-104084
Bar, Attachment,
Arm Bear Assembly
"
I"
A7LB-109010
[:
!_ _. ["
I
<
J
J
Knob
& Shaft
Assembly,
Diverter
Mounting
Plate,
Diverter
Valve
Torso
Torso Limb
Limb Suit
Suit Assembly,
AssesL_bly, Integrated
EV
A7LB-109023
A7LB-109025
A7LB-100006
A7LB-100007
'_
'I {_
f
,
I ["
_|_,
!
I
["i
_ [_--_
i
'_ I"
i [
i
I',
L_
Seal,
Ball,
Race,
Outer,
Spacer
-A_B--10q-2.0 -3
_I_-]_
302
_4YI-_
-A2LD------_
A6L-101017
A6L-101016
-A_l_>l-i
_%6L-4_03
<
I'"
L,
",_
_i
35
.A_T.-!040!8
=A6L-10!044
A7LB-101155
A7LB-109018
A7LB-109020
ATLB-109038
"_=
. -___7
L_- ! __!285
li
Connector
,,
!
:
C
D
C
C
E
D
B
B
A
D
C
E
C
'
i
D
E
B
..
,_
Flange,
Outer,
Electrical
Flange,
Inner,
Electrical
Thig h-Cab ie_-Gu id st-Patch-As
semblyGuid_r-Cord-_TWO - ST Drawings
Cover-Strip
Assembly
,-.Wrist--
C
C
C
B
B
B
:
_.
B
B
B
C
Assembly,
Arm
Bearing
Arm
Bearing
Pest_-St_?-Assemb_-y,---Tor
so
F_%s_-ener--_a peT--Pi-l._-En t r a nce-Z-_ppe
Four
- ST Drawings
D
C
C
S-t-_i_>-Asse mb_y-_
ae_
S_r ip_--Ba se--_i_2--(Pa t tern ).
-A6L_IO4018
"
Wiper
Port
Inner
Race
D
D
Assembly
PLSS
Four
- ST Drawings
One - MS Drawing
Ring Retaining,
Convolute
Tab, Locking
Arm Bearing
A7LB-104135
A7LB-104136
i [_
:
Gage
A7L-104046
A7L-104060
A7LB-104092
A7LB-104130
ATL-104076
Valve
Housing
Assembly,
Inner
Gas
Spring
Gas Connector
Ring Clamping
& Multi
H20
'"
_.
..
D
B
C
:i
':
S_r-ilmr-Base-4-7-_.P attern.) -
._
TWO
S u-._w-r-Ned i_f.i
ed-----
ST
Drawings
Connector
[i
[.i
1
/ 7! /
"'j
'"
, ........
+ i2
+"
+
Y
A7LB-101225
k++
_
P
"
I!
|+
-+-.
I
_'
I+_
I
+
1"
+I
,,
L,;
Assembly,
Outer
C
B
B
'
"
D
Gas
Connector,
Gas
Connector,
D
D
i
!
Base Plate,
Shoulder
Cable
Connector
Cover
Shoulder,
Cable
Connector
Terminal;
Swaging
Cable
C
D
C
R_ve%_7_
e __! e r-_e_t-r_in_t+ --Re_r--Neek
Ring & Cable
Guido
Assembly,
Shoulder
Ring & Cable
Guide
Sub-Assembly,
B
E
Shoulder
Ring Form
Angle,
Reinforcing
Support, Guide,
Swivel Shoulder
Tubing
Washer,
Thrust
Shaft,
Pulley
Shaft,
Swivel
Washer,
Thrust
i.7LB-104101
Bushing,
Assembly
Clevis
Clevis
Pulley
Assembly
----Pu-l-l_q_-A_emb-lY7
-e_l_-Pulley
Cable
Three
- ST Drawings
Four - ST Drawings
Four - AN Drawings
Pu_-ey--AseemblyT--W_i__-Pulley
& Bearing
Assembly,
Waist
Cover,
Pulley
Assembly,
Waist
LH
Clip,
Pulley
Assembly,
Waist
LH
Cable
Guide
Screw,
LM Restr.
Attachment
Bracket,
LN Restr.
Attachment
Weldment,
Pulley
& Bearing
Pulley
Two - ST Drawings
One - MS Drawing
Assy.,
ATLB-101197
A7LB-101165
Pulley
Cable
Assembly,
A7LB-101160
A7LB-10164
ATLB-101199
ATLB-101157
Clip,
Pulley
Assy.,
Waist
RH
Cover
Pulley
Assy.,
Waist
RH
Screw,
LM Restr.
Attachment
Bracket,
LM Restr.
Attachment
& Bearing
Guide
E
D
C
C
C
C
C
C
C
_
_
ATLB-101167
ATLB-101197
"i "
"
Guide
A7LB-104106
A7LB-104096
A7LB-104094
A7LB-104102
A7LB-104103
A7LB-104094
--ATLB-10!!55
A7LB-101197
A7LB-101164
A7LB-101160
A7LB-101165
A7LB-101199
A7LB-101157
Tube,
Flared
Cable
TWO - ST _rawings
Plate
Mounting
Rear
Housing
Outlet
|"
Assent]y,
A7LB-109016
A7LB-104100
-A_LB--I-04_98
A7LB-104128
I_
tJ
Guide
Plug,
Water
Connector
Housing
Assembly,
Outer
Inlet
A7LB-104105
A7LB-104097
{_
Cable
A7L-101035
A7LB-109016
.A_74_
B __.i_2+35
A7LB-104095
A7LB-104140
{ii
i+
A6L-101045
A7L-101116
A7L-101117
ATLB-101229
[_
"
w
A7LB-101226
[i
[i
+
+
Waist
LH
Waist
C
C
C
B
B
A
D
D
C
D
C
B
B
..
+_i
._
D
B
A
,i
C
C
_
_.
C
D
t
C
'
........
'_
+_
,.++_.+
+.
i[ +:_+_
+_
!
_4_ _
I"
.......
_,
:;_i:_.O]llliqlll;tltihanO]|hni_m,_._
L"_ | II
,.
-_
._
k..
_ ["
L.
-_
_..
A7LB-101167
A7LB-108038
A7LB-108038
A7LB-101122
A7LB-104106
A7LB-101123
A7LB-101124
....
--_
_
[
A7LB-101122
A7LB-104106
A7LB-101123
i%7LB-101124
-_9_=B-q4)415 _
"4_;B-_-S44_i -
[_
--A7LB- !0 _! 53
--A6/=-14)90_I
--A_LB _i_70
li
--A2LB_A_0OA_
r.-
[__
l_
-!
L
.
:
"
I_
,"#_' "
_'
I',
.l
[.i
[i
D
B
I
_i
One - MS Drawing
Sleeve
Plenum
, Mtg. Diverter
Valve
Sleeve,
Plenum,
Mtg. Diverter
Valve
Bracket
Assembly,
Neck Turn Around
RH
A
C
C
C
! }
!
4
Ferrule,
Guide
Bracket,
Right
Hand
Tubing
Two - ST Drawings
Assembly,
Bracket
Neck
Ferrule,
Guide
Bracket,
Left Hand
B
D
C
B
-A_LB_I40
4
A7LB-101182
A7LB-101183
--Aq4_-I0119 _
A7LB-101184
A7LB-1011P5
A7LB-101214
Pulley
Drawings
Assembly,
-- _L._
Pa_-%crn
Around
LH
_'
_
C
B
D
,,
"
CB
D
E
E
.......
Co_r--Aseemb_5_r-Shou%de_--R_ghtTwo - ST Drawings
L o ep--T_pe_d
"_-f-ie_
Pa __tern
Two - ST Drawings
..Leb_l--As_ em _!_._a_g
A7LB-101253
A7LB-101187
A7LB-101256
Pin,
Plate, Slider,
Spring Mounting
Retainer
Housing
Lock,
Restraint
Two - MS Drawings
Three
- ST Drawings
Inlet
& Torso
Plenum
Plenum
Gas Connector
Plenum
Torso
Duct
P a_ _ er-.n--Spacer
Assembly,
D
D
B
B
C
C
Four
- ST Drawings
P a t-_r-n-Lock Assembly,
Restraint
Zipper
Housing,
Lock,
Restr.
Zipper
Tab Ass_,
L.oc__-Lock
Tab,
Lock-Lock
Pin,
Lock-Lock
A7LB-101186
, "_S
802 5
A7LB-108022
Turn
RH
Bushing,
One
- ST Centering
Drawing
Strike,
Zipper
Lock
A7LB-108018
A7LB-108020
A7LB-108021
Waist
Tubing
Two - ST Drawings
C_y_"
cr _ _ _._i_:yT--Fn_eu-ld
......
P a t%_ r n
_v_.
_/_B-LS4_
[i
Weldment,
Two - ST
B
C
E
E
C
C
C
C
B
C
Zipper
Assembly
Tnlet
Torso
Vent
C
E
A
B
D
D
C
D
D
._
,,_
_ 7..d
--It7
!.!_--!
C_70 29 -"-A-7LI3-L_70@"'
k
r
--I_77,';15.7.05)
0
--;_7i.-9c 7 07-6
/_act_Au& c_:_J!}:-,__U'
.'pp
c__A_m_C
I,_,-4-c.
-- .__
i
,,:
'
I.
f
'
,
I"
!I
'
--AqL--] F ,'0.'5
I T
I
-A-,.,B-._:
_0 5 [,
-A-7
L B--I-Z-70
56
-Ag_B--I Z 7 056
--_-7
LB-_I_-704 _
----9_7
bZ--!C=7050
--A7LE
-!Cq-0-5/9
--A-7LB--I $7 0 6 5
-.-__7LB--I-S-7
06 G
--A:_L-B-% 5-7G 6:7-4_ LB-jLS-7_6 _
--A?LB-_IC-7 0.52-A_LD--I_P,J- _-_
I=P_!_>7 C_3l-=J%7L---.I_7_;
12
--_-L--I-S70 69
--A/LLB _20
--_B-_I2
29
9.
_n e
E
D
.Pattcxn--One - S'ffDrawing
2,1it er.I__
P-,n_L._r_-,-i'e.ttez-n
4'e_-te?:-n-P<]t% e z_--Pc t% ._.r-n
P a Et_r _
P_ h-t_r-_&P -_-t
_er-r
4:_t-t_er_
_.
7a t_er_
Pa _er4%P _.d--A_e _,_ly7--Sheuld er
Pa_ter n
Part or n
One - ST Drawing
F_s_ene_-_-S t_'/_-Low_p/--_q_i st
F_._. nc_-S/.r-i_r-TOr_,_
C
E
E
E
E
D
D
D
C
C
C
C
D
C
D
D
C
B
E
E
t.
!
.-_
_LB---I-S
7-0 6_-
P_-t ern
A.7LB--2 _ _,_32-_-A_'..:-__.-wo--3.!
,_,,,,-d_
Comf-or.t---P_d--Aaa_ ._l_-r--Knee
Pattez-n
Pa-t_be__,_-
D
C
C
I
'
--AT 5B----..,l_7--0-3.2
--A-7-_B--q-7,-7-0-7-9
=.
"
.
,
1
II
--A_LB_ISI-O 8_-
- A_LB_ --l-Z-7-0
1 Z-7078
_--A-TLB
_7
-A_B_6-1
--_0_02_9
--A-TL_-I $7049
.--- A2-LB--1-.S-7-94 9-- -AqLB--l_qq4)gq.
B
D
C
C
B
Drawing
_ -Pa_e.v-n
-Pa4_t_-m,-Pa_-_tcrn-- _as tenez_-S_,
-----Patter-_- -_ate_
Pa.bter.n.
B
D
D
D
C
C
E
Neck
E
J
J
C
[
i
_A_L B--I0-_0 34
-A-7LB- 107035
-4_7LB-157099
......
--A-7J_B-.I
S 2100
r_
_.
:
-"
-A-7LD- IC7052
U--A-7-I:,B--tZ-70 -5-5
---Aq-_B--Iq)
12-1-2
--A6!_ 1 S10 I-5
-A_LLB-q-S-141-7
."
--k_qLD---ISI41&...
ATLB-104085
i"
_t-5
i
F
'
!
t-
1
"
I..
..'
)
ii.
I
[
'/
_
Pat_tern
"_wo
- ST Drawings
Arm Assembly,
Lower
C
B
D
B
C
Left
Cenvoi_--As_em_bow
A7LB-104156
C
C
C
C
B
D
E
B
Fourteen
- ST Drawings
F_ s tc n er--St r.i.
p-A_c_-mbl_
Neck
Five - ST Dra_.,ings
Guid e--As s emb!_ ,_F-Crotch-eab{ e
P0 bt-er_-P._t_-e_n-
-_213
[--
Convolute,
Six - ST
-3
-A7-LB-_I041-2_
-Aq.LB- 1041-25
---A_B--I-Z-._
062.
---A6L--1090 01.
--A_L--1S4004
-A_434-I-24
A_r/%
-"A-7-,5--J:Z-4-_
,__
--4_B- l_. OGI
--ATL-_- ! Z4 O 48
A6L-101044
A7LB-1040854 ! 57
-4_7_B--I_
A7LS-104156
---A_LB_I$_I_3
_B--I-0412-7
--W_LB--1-04_2.5
----A_LB--IZ,:0 62-
Elbow
Drawings
One - MS Drawing
F ac_t_er--S%-r_i.pT-_r/_
-L wr-_-L
Re&_
laddo r-_k_sem_kv-,-_5 e f t
I',_str_--As_ embl_ur- "__i__
e ft
Pat tern--Tape_--Looi_,
Patter_
Medi f_ed
C
B
E
'
D
B
'
A
D
E
E
D
B
B
Bladde_--Asseml_fT--W_:-i_t--C-one,
Seven
- ST Drawings
......
'p._
_-_)-_
_"
n
P _.t,gor-r. _
Five - ST Drawings
Pn __prn .
Two - ST Drawings
Washer,
Eyelet
Six - ST Drawings
Two - AN Drawings
L.
Arm
Assembly,
Lower
Right
Ca_n__la4_--As
se_.ly-r--Blbow
Convolute,
Elbow
Six - ST Drawings
One -. MS Prawing
Fa s tener--S t_i_-4_r is_--r-Lwr_- R.
-Rest r,--&---Bl
add er--As seml>ly-r-4_i_
P,este._b_y_
Wrist
C_n_ : Right
-. Pattern--
D
B
D
D
B
C
B
B
B
"-_
E
E
D
B
A
D
_;
E
D
--A6L_ 10 9 0 01
Tape_-Loop_-Modi_-_ed
--A4_--1S40
PSeven
a t_r_ - ST
B
B
Drawings
:
_
].
I
_
: "_
-_--ATLB=I04124
--A-_LB=J.Z4060
n%qLB-IZ4061-
" [.
,
L-
_A_LB-
1-Z_048
A6L-101044
.
A7LB-104093
[.
,
t.
A7LB-106061
--AI4=B--I
06_
"
_
-ATL=IZ603-7.
P
''
|.
c4_7L--10_01-9
-A?LB-q4)6074
-A-_-S6
_27
_Bladder _tls-_.
eP_bly_,_._]/isl__ioilc
,_P__
Pat_re.on__
Pahtern_
D
D
D
B
C
B
B
Two
Six - AN
ST Drawings
Dra:.;ings
Bracket Cable Retention
AB
C
D
D
B
D
E
D
--A_LB-_I_61-I8
_0-18
Patter-n--l_a-t-t_r
_Three - ST Drawings
E
D
B
"
__5_/_--i_
---A_-I_-I
J)604-5
60!9 - 03
-AqL-IS6046
Pa
t_-e_n---Patch
,--Reinforceme nt
P-attera
C
D
C
_-A_41_I-Z
G044
----A7L-IZ6043
.....
... I_6042
----A_60
_-!
1_'7T
:-
Pat_e.rn-Pat te r-_---Pa%_-ern
P_ ttern-Six - ST Drawings
Rest-r_iat_--Ne_l--&--Se!c A_emi_ls_--Boot
-Lef-%Sclc A==_,'_b!y, Left
P_t_-er4_--.
Pa_-t_m
Nut, Flanged
P: tt_r_----Pat_ern_
--
,.,
_%_4=B-_-06072
---A-7-IzB-_0-607-!
-A6L_IZ 6007
_3
A7L-106012
_4.6031
--A? L--14_6_32
,
[..
{:L.
-AT-LB---1060_-0
...K2L=lS6029
[_
I_
A7L-106010
A7L-106013
_1460A6
A?L-IZ6_3
,
_-
i_
I,
i
'_
D
D
D
D
B
E
D
C
C
B
D
D
One - ST Drawing
IIeel--Assembl_ot
__
B
D
D
One - ST Drawing
Screw, Heel Shank
Screw, Arch Shank
Irosele--A_se_l_fv--Re_t-_a _.
Pat-4_r-n
Two - ST Drawings
B
B
B
D
D
B
I_
i,"
<
Li
{!
,
.
I
I
B
| ",
I
I_
I
'
\
"
F
I
r'"
A7L-106014
_l_-/_q
C_i7
Arch/IIeel
P_-t-ter-n
--9_71_--14_
607-7--Aq 5-I-S 607-7........
Pa C tern-Pa b t_r-n---
_IS607.8
A7L-106005
-A-Tqr-l.
Z 6O0 !
--AqL--_Z6 00-2.......
_-S
6008
--A-?
L- -IS 6 0 _
-A_L- ]_ 60-36---A_L-I.%60 _
_L_I
Z6&_
B
B
Patterd_
Restraint
Assembly,
Pat%e_n
Da t ter-nP a%-t-ern
.Pa-teern-Pa _:tern
Boot,
Ferrule,Shrinkable
Cord
Tube,
Tube,
Shrinkable
_/_T--Boot
Guide,
|.
A6L-106007
_25
Two - ST Drawings
Ferrule,
Cord Guide,
P a_to:._-
I
_"
_1_602-2
--A_60/_
9a%te_-n
Pa _ t_era----
Ii
Six - STDrawings
Five - ST Drawings
One - ST Drawing
Boot Assen_ly,
TLSA
-ATJ;B--10$063
_I17
_-A_q=--l_3-7
_i06_18
__
I.,"
[..
.
..
,"
L.
-,
|"
0! 9
-A/L/3=_60_.4
A-7-DB.--I
S612.7
-ATLB--I-Z 612-3
_ATLB_IZ6118
%A2/J3=I_6038
Right
B1
adder--Li_
P_;tern
<
I;
[i
Small
Small
C
C
C
C
B
C
D
D
C
Right
or--&-4_ n_--Ass_,_,l.yT-_8o o t
_t-t_-n -O_t_ole--Assembly
i :lad_ght
Two - ST Drawings
Li____J_ly_-Boot
L1m_.XS-= ..... .. _ ....
"
" A e_mhl_,
n,-,,-,t-_ Left
P-at,t,ern-Pat tora-Patte;4_---
B
B
B
E
E
E
D
D
B
P
E
D
D
E
_%_L--IS604.5
--ATL--106019-03
---A3L-IS6046
----A_L-.IZ 6044
P= t Set-R------Three
- ST Drawings
Pa_t-ern-Pa tt-ern.-.
Pa_tern--P a%_t,e_R----
C
B
C
D
C
D
-,_._I_-1_, 6042
---AXL=_Z 6041
Pattern
Pat-teJ_
D
D
Six
[.
B
D
D
D
B
C
C
C
C
A6L-106007
A7L-106007
A7L-106007
ATLB-106061
Left
P-a_ter-nPa%_r4%
C able_&-_r-_le-Aesemb
%"
C
B
-.A-7J.-_-0$ 00-7 _i
Shank
- ST
Drawings
L.
[_
!
i "
--A?4__
12___
Reshra//zt__Hee/_
&_SolP__As_emhl
Right
S ol_-A _ emi)iy-r-_i_h _
PAtjze_n.
4_7I,B-q_60_-I--A6L--IZ6 007
r
[.
'
i
t
"--A7 Ir I-Z6033
A7L-106012
----A-7
i,-1 Z 603 I.
---A-TL-1Z 6032
_--A4qLB_IO_I0--
"
---A7L- IS607-5_
---A7_--I-S
6029
n a t-"
b-__ I%--Nut,
Flanged
Pattern_
P_ttern- -.
One - ST Drawing
He(: .L-A_;s e'nl__ly_
....
....
ATL-106010
I"
A7L-106013
-A74_-I_)604-6........
A7L-106014
i_
.
I"
__.
#
_
[
[..
i ..
--A3/_-_960-7-7--A/L_IS6018
_.S6_7-8
J
".
"
-Aq4_-Z
60 _.?
4_I-06
'_n"
A7L-106007
A6L-106007
A7L-106007
A6L-] J,_007
__v_6025
.-A2/.-IZ&0 24
--A_ L-IZ 6022
-A ;-L_I_60 L7
I"
A7LB-101270
A7LB-101271
o'
ATLB-!0!272
E
D
C
C
B
D
D
B
D
Pa_.
I_%--P_ t.to_,_-One -.ST Drawing
Screw,
Heel Shank
CD
B
B
Screw,
Arch
Shank
Iasole-A s s emb_y_,--Rest-ma_n_--Right
Two - ST
Arch/Heel,
B
C
Drawings
Shank
P;_t tern.P_e_m-
B
B
P_t_r-n
A7L-106005
---A_-L-_.Z 6001
--A-71,-1 Z6002
-A7L-IS6008
--A_LLIS 602-1
--A_L--I_6036
.
I
y___Boot
Restraint
Assembly,
_a t-te r_n
P a4_-t_z_
n-I_1_t_rnPa_t_4_-P a-t_=r_
Boot
Right
D
D
D
D
C
C
Pa _ter4_--
_"_^
Tube,
Ferrule,
Shrinkable
Cord
Guide,
Tube,
Shrinkable
Two - ST Drawings
Ferrule,
Cord
Pat ter_-----P_at.bar.n_
Pa t_r_-P a t-t_m_n-
Guide,
Small
C
C
B
Small
Sixteen
- ST Drawings
Five
- ST Drawings
One - ST Drawing
Swage
Fitting,
Crotch
Cable
Thimble,
Crotch
Cable
C a_a
_ag-$k_7--N_l
on
"
C
D
D
D
C
.
,
B
B
C
D
C
. [.
i
'
'
!
I
["
i
;
A7LB-105004
(-ATJ,B---I
0 .5045----
Leg Assembly,
TLSA
Left
l_cs trainLAszembl_--Low_
Left
.-b7I_B--I-S
50_9
E
r--Leg-Co ne,
D
_ttern
--A6L-I Z 5003
Pa t te_O______
Two - ST Drawings
T apeT--l_9oi_-,MoO i-f-i_ dTa pev--L oopv -/4odi/ied
Eight
- ST Drawings
Pulley
Assen_)ly,
Cable
Crotch
T_Ipev--_
p_--Mod i.fied
Co_e r_-A_ scmb/_{-_lig
h--Con_o/u_ev--Le
Loo1>7--Ta_od_
Z-_ed-
_
i
i_
A6L-105031
--A6L-_ 09001
-A-_LB-105026
"--A6L--14>8001
--A6L--I_-502_9
-Aq_B --I-S
5 026
--A_AB-q_q_ 0_J-
!'
-A_LB-14) 502 _.
-AT/_B--1S I_L9
4%_AB_I$5021
ATLB-105023
[ "
I
"
P_ttcxn----_t-t_gr-a-
--Aq_B--10 5033
ATLB-105036
A7LB-10_006
!
I
_LB--105007
-A-7J.B--1-_ 500 =.
_%6L--.LZS006
5007
,.
-A6L-I_9001
_5OO9
-A_4._501O
--AT-LB--IZ 5009
_-_@I-208
.A6L-105019
_.A6_--Ig50 2-4
[i.
"
[.
I'
_%_L_L0503
l_[
'
25
Pa
Sixt_er-n
- ST Drawings
C en%__ex_lY_
P_" t_ _
_r-_
Convolute,
Thigh
One - ST Drawing
D
C
Tapa_-J_pv--_0dii/ed
Eight
- ST Drawings
B!edder
Azzemb!y,
T_hlq_-J.ef-t
Pat_ =_=_Ba_mra%-".trip Assembly
,_ _._e_.-eh_
Disc,
Medical
Injection
P __+_t.er-a----Five - ST Drawings
C
B
E
D
D
D
B
B
B
Bladd
Left
em-A&s
E
C
C
D
D
D
B
_.onvolut-e-Assemb!y_
}thee
Terminal,
Cable
Swaging
Convolute,
Knee
One - ST Drawing
Restr a int- As semb lyT- Th-i_
P a t-t_e
_:n-_
Pa_-t-ern
Pa+ter-
D
B
E
D
B
B
embly-r-Lewer--Le_,
Str.ilm_Aeeem_4__hmcnt,
."attireFive - ST Drawings
Cover
..A6L-105032
A6L--14_50 l_
__A6L.-.IS5013
f-t
C
B
D
C
E
C
B
E
Pattern
--A_.LB_IOI208
-ATLB-I-S 5008
D
B
C
__-_
se_-b]v.
Y_uee Con-o
T=.pu, L_-_spv--Med-i-f--i-edPa%_rn
.
Pattern
":nt
_,,t_
D
D
B
D
D
D
D
I:
(
1
[i
%
?--q_'r"
.............
.,
-,,
' -
i
I
i
$
! [
k
_"
8
Two - ST
Pa t-ter_-.P_-t
t or4%-_
--2_g_B--iS 501{ .
---A-7-LBi-S 5018
A6L-101044
A7LB-105004
---A_LB-_I-S5089
-A6L--I 05015
.-A6 L--I_50 _
.
I
'
E
"
B
C
C
Washer,
Grommet
Eight
- ST Drawings
Two - AN Drawings
Leg Assembly,
TLSA Right
_'
Drawings
E
B
A
E
P-._.
t_er-n
Right
._lap--&-4_.Lid_%_t-.--Assemb
ly
Pattern-Drawings
Two - ST
T __
p o__r
-_-"h9
_i-f-i_
d -T.ap__-_k_
i_f-i<_d
Eight
- ST Drawings
Pulley
Assembly,
Cable
Crotch
T_pe _ Loo_r-d4odif-_:od--
_A6L=IOS/?JII
-A6 L-_I0900 !
A6L-105031
_K6/-_L0_L00L
--A6L_Iq)
-A?LB_I(_-50_6
90 (_l-----A6L--IS5 O 29
Co.ver._2_s_y_,__high
Tape_(_p-,--/4o4i-f-i
pa_h_rn
ed
Convo!_4_
D
D
C
D
:
:
B
C
C
B
D
C
___ight
C
E
B
E
A? LB_I_5027
-4_LB_05
!
Pakter
Six - ST Drawings
Convo lu_e--As s embly-r--T.h.igh-
_2-4
--A7LB- 1S 502-1
ATLB-105023
A7LB-105036
ATLB-105006
{
---A6L-qZ5006
---A6.L_IZ 50 0-7-
"
--A-6-_-1-09.00 004t
_I-$4
.-_7L9-!05009
_9
D
D
Thigh
Terminal,
Cable
Convolute,
Knee
One - ST Drawing
_il_t-As-__e_m_b!y_
----A_I,B-_4AS007
-Pa t{_r_-Convolute,
B
C
Swaging
Th__gh
C
D
B
E
Cone
Patter.-.
- Pattez_%--
B
E
T_%p__@7-44_
_d-.Pa_er_
Five
- ST Drawings
nl_,l_o_m_l_:."
_g_
Pat_ern
...........
_,
_-=
Att_chment
_(-h__
CB
E
E
D
D
- [I
,,
r3
l
w
L.
F'
[
L
--A-7_B-lJ_O 0O
B! adder--As;, em/_,
Right
Rat to rn
--A-7I,B-_I$5007
'
F-
"--A_-LB- I S 5008
|.
t
---Aq-LB--iOa-q98
r"
.
-A6L-q0 50 _2---_
_-A6L-_I 0-5_32
---ATrL--I-S_{}I-2
_% f_I_--155_13
,'-
_-7_B--I-0_0-2-9
. A7LB-105015
'
A7LB-IZ5019
A6L-401042
i,
:
Cover_
--A_LB_I_I2-_2
_-A61_09001
ATLB-!09012
I "
A7LB-101126
-ATLB-_i_.I-I_3
--A_-LB -_ICI 42.0
--AT_B-4GIA4_I
_Tq_B-IG-14-2 O.....
_74_ BLIG 14 _i
-_A/LB--IC/_7/-
.......
-AS;-LD--IC_II2
4-
I,
ATr_-_
A7
r_.__n- !C __
! 30_
307
-._.7
LB-1S ! 4 ! 5
-_-7L_--I_-I-B96
-A_LD_IC i17 _
"
I
.,
....
...A-7.-I,.B
- _,._- 40-0
_C-I_/,3
-@:_=B--I_-I1-83
-q_74_--iC_iG4;8
Preformed
UTCA
Transfer
Ilose Assembly,
Clamp,
Mod, Preformed,
Two - ST Drawings
Plug
Mounting
Ring
"O" Ring
A7LB-101269
Cover--and--T.r_ansf<_r--H.ose-A_sembly-r-_CTA
Male Disconnect,
Urine
Tzansfer,
Mod.
I"
|_
.
D
D
A7L-104005
A7L-104005
ATL-104005
I-
n_
E,atlu2rD.
A7L-105003
r-
-_we.r--Leg-C_
D
B
D
D
D
D
D
C
C
UCTA
Band Type
ST Drawings
MS Drawing
AN Drawings
Swage
Fitting
D
C
B
D
D
D
B
A
A
D
Cab _i=a
9 T -M e d-i-f-ied
T _q_ov--Loop_-_1od4_f-i4_%--Screw,
Hex, Socket
Head,
Cap
C
C
D
Torso
Assembly, elabl-yTLSA ,--T_:s e
Re _t-r&iaa_--Ass
Pat _ _ rn
J
J
D
_
Pa_ra ;,rqa
_attern
P_t__ er_
C
D
C
J
P._t_
___rda
_
%_%er n
_ a_t er4_
J
C
_a t--ter_a
._attcrn
J
E
Pa ,_er,._
Pc t tcraa---
P a t-t_ra%--9atter_-_
D
E
l:
.
3,
/ ?-'
I
)
[-
ii
!
i
._ [
-A_DB-IO1309
--A-TLB-1CI 309
---ATLB--IC117.9
A7LB-101252
_A7-b_-.-iOi_ -.50
......
A7LB-101251
"
-AILLB-_l0-1q_ 2....
--AI_4Z
I_21
--_c7_B-I-$I-390
.--A-TI_Bi S 13a 2
I,
'
-A_AB-q-0 -1.231
i'i
"
I.
I
[.
" i
I..
._%ILP=101237
-A_LB--IGI-_20
---AILB1 S 1-3-2-2
A-A_B-q_0A_-II
A7LB-101195
A7LB-101195
LB_IF_I-I-9_
.3_TLB=I01210
-3tlLB--10121!
_A3LB-IS
1245
,mA__._'Lc
-_I n n
.........
---A-7-bB--IC-I
198
-_7LB-I_
i-1-9.5
-A_LB_IS-I-193
--A_LB-4_I-Lg_
-A3LB-I_I-9_
--A_L B--IGI-II_
A7L-101017
I
_.
)"
.i "
! I
,
I
.KILB--ICII82-_%-TLB--IGI4 82
-A7LB-.IC i181
_%_-LB--IC1181
-A7LB-ISI.178
_O1-1-7-5
.A7LB- 101140
_TLB-101_I5
AT.LB--1S 1 i_.9.
ATLB-ISI3.0.1
Pa t-t-e_-'_
Pa.t-tern
Patheru___.
Hook ,. Donning
Aid
4)on n-i-l_j-._i_L-Asc._e
_bLy_--Sl_.ide-_a_
Eye, Donning
Aid,
Slide
Fastener
Three
- ST Drawings
E
E
C
i-_er C
C
B
':
;
_
,
T_c_bbing_Ax_semb
Right
ly.T_/_ea r_r_N e ck_R e ___t
ra/n t D
P_tter___
D
l,et-t-e_,_Pa_.t.er.n
F-i-t_t-i_.
n _T-_e _t-r__eGk-r
One - ST Drawing
Wehbi_g--A._semb!y,
Left
Rear,
BAtter_n
Pat-Gern
F it-t-iag_c-_aq-_t
Fastener,
One - ST
Fastener,
I)a%._er _--
Slide,
Drawing
Slide,
--Rea
N_h
,--_
Restraint
,---Rent_
Vertical
Horizontal
C
C
;. _
:
C
B
_. :
{ ;
) "
il]J
C
C
C
i
i _
_
E
B
E
J
; :
_.
D
D
Three
- ST
Pattern
P &t-te r4_
P a_-_er4_-Pat te_u_
Ba_r4%
Pa_t_r4_
B
C
C
J
C
C
J
Drawings
Patto;;n
P a tte r4_Double
Bar
',
.
"
D
D
"D"
Ring
_at_-_n
Pattern
P@ __
t er_
Pa_t_mPattern-_"attcrnTwenty-six
- ST Drawings
B ladd er--A _s embl_r--T_r_._
----_a%_h--A_sembl_',
St-r_e-Req-i_f-r-_pper
P_4_e r n
Ps_-
B
C
C
D
D
D
D
B
J
C
C
C
5
,
....
_.:,
I"
_._--aW.m--k_t-_---------
"
..
_A_B--I
0-i26_7-.
-A_ _B--IS:I-4
06
--4Y74_B-IS1-40 6
_-A74_B-I-SIA07
_7-LB--1C _ _2
A_ I,B--IG
i_%3&
&.
4674_B-q_l-l-5
6
4_B--IC_ 13 _
"_i_-4:i_
5
_Cq-l-30
A7T;R-1Ol I 3_
--AI_B--IC-I
12 5
,"
_: r,
_
Two
- ST Drawings
P_t-ter-a----
B
C
<
. ;
C
C
'
pattern
Pa%_rn
P_#tern
E
E
Padhtex_
P at-te_n
Pattern
Pat-t_er
n
Pak..tern
Pa t_e_
E
J
J
J
J
E
Pa_te_n
Pat-Eer-_
St-r-_p-At_-aohmeBt--Aesemb _--1-5P-_h_aTwo - ST Drawings
St--r-ig-A%--a
eh men t--AseemS_2--l_ Pattern
Two - ST Drawings
E'
E
E
C
B
E
C
B
'
_ ."
,
_
-:
_ -,:I
"
r|
I_]
"
"
_A:LLB-_C-LI-3@
-_A24_B--l_=l-laa
4W4_B--I-01.20
8
-9_7LB--14_386
_ ["_
I I'
._
-A_LB.-I0120 8
*A--7__3-85
i,-_.
_i-si-ae:
_ l.
_.
:
7 1:
_i
["
___2LB.-!Z !317
A7LB-!Z!315
-A-7_-]:-3-2-B
_I-Z-I-318
----A_LB_I-Z
!3!6
__i_
04
P_.n
....
....
Two - ST Drawings
Pat __ --P_. _e_a
Pa_ern
Pa t-t_T_Pattern
_
Pattern
B
E
E
C
E
E
D
_ .
C
C
C
C
_ ,:
i {:
"
_
_B
-l-SLI-58
....
,-A_LB_IGI!5?
--A-74-,B--t-S14 5 4 ....
_
B-4G 11-54
."attar_.
Da.t_ern
P_e-_n---Ba-h:i:,e-r--r+
, [.
: "
-A_LB_IC!__31
:-ATLB-!C !!31
Pa t_,n--Pa +t_n
"' 'J['/
}
A7L_-3CII26
-A.7-I,B--]._,.l.l.2.6
......
:: ::
:
Dat-_re_-Pa_tera--
"
',
::.
_.
--
D
D
D
'[!
i
,
i t
( "_
I "l
l,
"
/_&
'
--A-7_B-_5 i_-94
Pa-t_orqq
_-i_rn----
P_/utern
.... -Pat-tern----
P-a-_.a--
P_t-t_-_n
P ee-t-er-n-Pa%_er4_l_4_r_2a_r4x
--Pa_-t-_.
_a
C
C
C
C
D
C
:
i
i_
._
'
C
C
D
C
C
C
C
[
._
-A-74TB_xI5
,_
'
_B=-251797
-A-7-LB--2_ -l-B-i-i-
{.[._
,-_
'Ii
"
) ii
I
_2_a=m._/J__9
_,B-;AS/m_O. !
,_2
__18!2
_ "A_LB-_2_5_I 3
- _LB=gA_.79
2
-__5-i-7-9
3
-A 7LB.--2_IS_I0
_5_-_5
_-_
--A_B-4_5_-7-9
_
--A_LB=2.5!794
8,11
_--_
A7!-B-25!79
8 .....
.-
...... _a_
Patt era%-Pa_
.-Pa&t-t-er-_
Pa
_a ..
Po t-_e.
_-tern_
_ _"
_
_ 1"
'
I:
:,i', " [..
):'o ,
_ I
B
J
D
C
C
Right
Pattern_
....
<
",
"
"
c
Ba_r-_
PaCer-n-Pa_tcrn
D
C
C
-A-7_II=_
.4
--A_aB-_4)I055
A7LB-2ZII72
-,-a_ _/_Y' Its _'1_1
_ ...... 173
_51!
_4
._-in,- ,.Vent
Rei_t
Ring, Flourel
1_**ern
Pattern
C
C
D
D
D
..........
i_
_
_%-7-_-_42-_ 6
--A_I_2-_I/_8_
"92J_B.-_2ZI/2.6
i(
Eighteen
- ST Drawings
Arm Assy., Lower,ITMG.,
Pa
t=he_n-Pa_t_n
Iza_r..n.-
-9_=B--2_-7_ 1
,.
_:
_,
I_-" A7LB-201170
I-,\
--_74_R-_5i-7_
.__-2
5!799 :
_5,!
779
.......
,-:
i
.:
'0'
,..
]
',%
:
,,, ,
Pa_._;oEa--
} 1
'I
_j
"_"
_r_B-
Z5_ _4,
P_.ttern_
_ATL_--1513_8_
_-251799
_A4CbB--2_t_u90
-_7-LB--2_-_I-79_
A7Y,R- 95] 809
Patt_n-Pa t-ter4_.
Pa%-ter4_
Pa%ter-n
Pattern_
D
C
C
C
C
[]
""
_A_q_B_l180-_
4_2-5-1-79-i "
P@
tern
Pattern_
C
C
_/5-1-79-2
_1793
--A_-I,B--2=%I-7
94
--bT/_-_ "1-815-----A_LB_2_I-7@-5
Pa%-t_ern-Pat t-e_,
Pa %-t-c
ra
P&Stor-n
P_q_tG_ n-
D
C
C
C
C
P att_r-n
P_
.na_r_
C
C
C
L.
[-
-I
i
i
. ["
I_r.,
_ i
'_
_Aq/_B---_i-79
_
_A7LB_5
!798
-A2LB- 2 518 !!
--A_LB-_I-7-9$
Patter-n---.
--A_-L_--2513_.l
_tern
P.atterm
_a_t_r_ _
Patte_rD__
C
D
'
-A_ LB_5
_
r"
[,
[_
)
t
<
!
''
L_
I_-LI
--A7 LB ----251.813.
.-A2.LB=/51/_9
--A-7-LB=-2.SIS/.0
.-A_-LB---25 !79 6
-A_LB=25_ _97,,
_A2.LB--25iI_8
-AT LB-_--_LSII
A7LB-251799
, ,,
.
A7LB-20iI56
!
'
.[ _
--A_m_-a-5_818
-A7LD -251919
'"
_!.
..
D
C
C
C
C
Eighteen
- ST Drawings
Pocket Assembly,
Datolist
E
J
Pat een.n
Pattern
, pa_n
P_n__
_ ,
pa J-_r n
Pettern
-@aC_&er-_
Pa_ern
_
_-1_27
=A,_-B-251827, ,,
A7LB-201127
_!___
_.
_attern
Ring,
__rn
E
E
E
E
Rectangular
'
D
C
-!
.(',
?
<
, _-.._
[ L
I Ec
_I
A7LB-104138
A7LB-103056
2&_q_B__8
One
One
Ring,
Glove Wrist
Assy.,
P_t_er_
Glove
Comfort,
One -Assy.,
ST Drawing
Pat t_=r4%One - ST Drawing
A7LB-i01121
4%_tLB_20-l-18_
Wristlet
Cre.::C_mm_and
-4_7LB=251860
-A?_B--251860
_ATLB-251860
r.
I,.
Pattern
Pa_r4_-
_'
D
D
D
D
J
J
D
D
D
D
D
__7
p"i
D
D
Torso
Assy.,
shal_.
Pattern
Pa_t_rn
Par tern
Pattern
Pattern
_0
D
C
ATLB-201177
__:,_
9
-A_LB--_
3
A7 LB-_-51-_5/--AVLB--2-512_3
A_';_B- 2-=1-753
-A-_:,6_5
_Zl?_.9
E
B
C
B
B
C
C
A?L__-3_.!G__
Right
Five - ST Drawings
Ring, Mounting,
Itmg,li20. Corm
Cap Assy., Pry.
A7LB- 2CI_84n
_ATLB-2CI67
=A?LE- 2C!685
_$I_- 2Z!__5"_
C
E
C
A7LB-109039
A7LB-109050
.ATLB-2_I&69
-ATLB--2C!669
--A7 LD-_C_ 70
[2
"
Left
pa_4;ern
pa
l-t_ rn
-A_I,B-qC
!__5
-ATLB_II66
6....
-ATLB-2C_IZ 66
A
B
Pat t_v_er4_
Pat_ern
_25!860
-..A-7-I,B----2.,51..g6.0.
---A_LB-_$1_&0 ......
A7LE 251S_0
Comfort,
A7LB-103056
.__. ,__ I ,_',_ _o
_
"-
"
- AN Drawing
- ST Drawing
_?Y.n-___1
51
7__1
Tmg.
Pattern
Pattern
P_ ___n
D
D
D
Pattern
Pn_t__rn
Pa t_---
C
C
D
_%a_term_Da,t_.rn
Pattern
Pa ttcrn
C
D
C
D
2attcr._
" .........
" ......
Pa_.er_
P=_ttern
[J
_:
:i
,"
)
,
'
"L
i; L
l
Ill
ill
"" +
_.TLB- 25!8!6
_2LB=a318
I"
L_
____7Ln-_90!]67
_TT.n-)__1 7 61
:A?L_-2 Z!7 ._!
_74_B-q_l-7_l
!6
4_LD-!Tr61
x_. n_,, i`T&_
A_i_.n-_9_
17_!
"
li "71" D_
'
-- --,,.,..A2-Lli-l._& 679
"
', E
I[___ 11/_l 1 _
Dosimeter
D
D
D
DD
D
'
AB
B
A
E
D
E
Pattern
Pat tern
P__ttern
E
D
D
o-. + +,=,,-,-,
_%attar=__
E
B
lr___.I-,I-r.._t._.
*'/0
Pattern
P=_ttern
*)a t_r"
E
D
E
__6.79
j_TLN,?0] 67R
-_"'" 201."29
Pattern
_e_vn
Part=tin
E
D
D
Reinf---/Zent
-_ n=,,
A7 r-_-gnl I _5
'
ATL_--20I_ 79
_-20_67_
.K7LB-.+201629
---_
,I-.1'- n':," T1
Four
MS Drawing
Drawings
One - - ST
Six - ST Drawings
Two - MS Drawings
F !-_plAis_mb!-/, Entrance
Pat ter_-_
Pattern
_B-20!!6_
-AqAB--20 16 _4
_ A7L__-2n!=.77
_[IT
'
Paef_-rn
Pattern
i.=_l
__8
i_L-_.51_&8
-ATL "^' oA_
D
D
D
Pocket,
P__t%ern Assy.,
Pat e_efT,
_!677
__2T-_
n- 201678
- A?LB-20!_'!0
AE
B
E
D
D
D
pa f_tern
I"_ "';"
L <
Two
pa _ -_n MS Drawings
Four - ST Drawings
F!ap Assy., UCD/REV
Pnt_'Prn
Pattern
Patter
-_ -
DIn:
....
A7L-201045
A7 L- 25 !!.:B
_._L--25 !! 68
Pattern
Pattern
pn tf_n
__TT_._n-_ _ 1 nS__
"
..P._f_rn
_i_-ee
_ AS__,I_- ; i,e__
N
LJ
,)
ii
+
i
_0,.i "
I
-
.....
++.-.,--
.,,
_-
.A7LB- 2c.I649
Pattern
A7LB- 215239
Pa_t_n
Pan-tern
__.7
LB- 2C!6A 6
Pattern
Patter._Pattern--
J
D
D
_-25!746
-_ATLD-251746
P___ttern
Pattern
Patte-_r_-Pattern
Pa_&e_n
Pattcr_ --
D
D
Pattern
--A2LB_
17 4 2
_A7LB-_gC1642
A7T-B -2Z1742
_.7L__ - 2C !_42
_
_T.D--9_I
_A
_'lT.I_--901
_A
"-_
-n
Pattern_at t_rn_-_
-A?L__-2CI_ A.
5
_ .... ._n.A.
_7LD ": n. A'7
..... " _" _"
_A?T_n__95I_645
_'tf
__')
_ ,_w
_,
_I.'7
"t" _,.._..L.
---,L
T_.
4-4-^----
--
J
J
A G
_'J_'I "7 A
B
J
Pat.tcrn
......
P.einf. Ve._t-
A?L_- 2CI_ _.
_
---AT-LL2_IO54
_--
E
E
E
Six - ST Drawings
Film A__semb_Znner
,_ ATT.n-991!58
....
E
C'
LPatt_rn
_att&zr.,Fatt&_-n
_attcrn
Pattern
n.
4. _.------
D
J
J
D
D
D
Y'__ 4- 4.._,_._ m_
_a_=_tter_
D'._'_'^_
:'a _ t &_.-,n
.....
--
DD
Im,.._
4-4-_,,,.,..__
_-,'- _-,--,,
_B_2517
a.4
_.. ,,.k.
c n";AA
--AqLD-2 517 =_
-
[1 "
0c;'
N
C
D
D
_--A_LLB_I644
_B2Z!__44
__--
_A7
.A7__n__95]745
Pa _
_T_--_I
r'-')
E
D
|
!
i
L
,
APPENDIX
PRESENTATION-
- MANAGEMENT
SYSTEMS
STUDY
*'i
'i
|_
I"
,,,
|,
r 1
L
LQ
t .,,_4
:
, J
""
STUDY
TASKS=
t"
-"
"
PROGR_'I
MANAGEMENT
CMO
GOVERNMENT/CONTRACTOR
MANAGEMENT
REPORTS
ASTRONAUT
FIELDOPTIONITEMCONTROL
IMPROVED
CONFIGURATION
r_NAGEMENI
METHODS
BUSINESS
MANAGEMENT
I_
ANALYSIS
OF COSTDATA
BUSINESS
MANAGEMENT
SYSTEM
.'.
i
PROGRAM
CONTPOL
MANUFAC]URING
DOCUMENTATION
ANDCONTROL
SYSTEMS
PROGRAM
PHASING
PHILOSOPHY
_"
,
)
'
'
"
;:: _
_
,w_,.
,'
"=,
ENGINEERING
INTERFACE
CONTROL
DOCUMENTATION
CONTRACT
ENDITEMSPECIFICATIONS
FIELDOPERATIONAL
DOCUMENTATION
ENGINEERING
ORGANIZATION
,.L
_.
_:
;i
i]
QUALITY
TRACEABILITY
INSPECTION
ANDIN-PROCESS
VERIFICATION
_L_,
,
_j
.J
,,;
f"3
_,,
;n
,[;
,,_11
7.
L.
PROGRAF'I
MANAGEMENT
E
_i
I) MANUFACTURING
DOCUMENTATION
ANDCONTROL
SYSTEMS,
2) IMPROVED
CONFIGURATION
MANAGEMENT/CONTROL
METHODS,
3) GOVERNMENT/CONTRACTOR
MANAGEMENT
REPORTS,
[i
4) PROGRAM
PHASING
PHILOSOPHY,
[',"
5) ASTRONAUT
FIELDOPTIONITEMCONTROL,
Li
E_
I
I
{.
J
[!C
-_
r_
'
[!r
ENGINEERING
DRAWINGS
& MANUFACTURING
DOCUMENTATION
_:
PROBLEM
- OVER
90%OFTHEDRAWINGS
CONTAINED
REDUNDANT
INFORMATION,
i '
I'
.[:
1) MANUFACTURING
ANDINSPECTION
INSTRUCTIONS
(TO'S)
Ii.i
WEREUTILIZED
ASTHEPRIMEINSTRUCTIONS
FOR
OPERATIONAL
PERSONNEL
RATHER
THANTHEDRAWINGS,
A, SUBASSEMBLY
DRAWINGS
GENERATED
WERECOMPLEX
li
I!
,
L
,-.
ANDUNWIELDY,
OPERATIONAL
PERSONNEL
HAD
DIFFICULTY
USING
THEM,
B, DRAWINGS
WEREPRODUCED
ANDPARTNUMBERS
ASSIGNED
FROMANENGINEERING
VIEWPOINT,
MANUFACTURING
REQUIREMENTS
WERENOTGIVEN
PRIORITY,
i
_
2) TO'SCONTAINED
ALLTHEINFORMATION
ONTHE
DRAWINGS
ASWELLASSUPPLEMENTARY
INSTRUCTIONS
REQUIRED
TOFABRICATE
A SPACE
SUITASSEMBLY,
3) BOTHTO'SANDDRAWINGS
WEREMAINTAINED
--DUAL
i,"
CONTROL
PROCEDURES
a
L!
T
'
L_J
"C"
'
I"
I
DATACOLLECTION
ANDDISSEMINATION
PROBLE/.];
I_
VARIOUS
DOCUMENTATION
WASGENERATED
TU MEETCONFIGURATION
p
Z.
ANDMATERIAL
TRACEABILITY
REQUIREMENTS,
i,
1) THEINITIAL
_IPHASIS
WASPLACED
ON CONTROLLING
[:
CONFIGURATION
ANDTRACEABILITY
FORSPACESUITSBEING
FABRICATED,
[
.
i'...
L,
2) AS THEPROGRAM
BECAMEOPERATIONAL,
ADDITIONAL
REQUIREI,
IENTS
WEREENCOUNTERED,
3) NEWDOCUMENTS
WERECREATED
BY INDIVIDUAL
DEPARTMENTS
i.i
WITHOUT
CONSIDERING
UTILIZING
ORMODIFYING
EXISTING
[_
REPORTS,
i
p,
1,
i,
Li
",.
-]
"1C
"i
..
RECOrD.GUIDELINES:
[,
'
1) DELEGATE
AUTHORITY
FORDATACOLLECTION
AND
DISSEMINATION
TO ONESPECIFIC
GROUP
I.
w
"
!i
2) DETE_IINE
AS EARLYAS PRACTICAL
WHATINFORMATION
WILLBEREQUIRED
WHENTHEPROGRAMBECOMES
OPERATIOI4AL,
[i
3) FUNNEL
ALLADDITIONAL
REQUIREMENTS
THROUGH
THE
l)
[]
DELEGATED
GROUPFORoPTIMIZATION
OF DATA
rr-
DISSEMINATION,
L;
!
!-
:i
t ]
-.,......
, !
Na5
t-
EO
PROGRAM
PHASING,
PHILOSOPIIY.
E
P
_
II
ANYDELAYORREDESIGN
DURING
DESIGN
VERIFICATION
OR
QUALIFICATION
TESTING
HASA DOMINO
EFFECT
ONTHESUBSEQUENT
"PROGRAM
MILESTONES,
1) DVTWASCONCURRENT
WITHTHEFABRICATION
OFTHE
n
QUALIFICATION
UNITANDQUALIFICATION
WAS
PARALLEL
TOTHEFABRICATION
OFPRODUCTION
SPACESUITS.
2) "FINE
TUNING"
CHANGES
WEREINCORPORATED
INDVTAND
E_I
QUALIFICATION
UNITS
WITHOUT
COSTTRADE-OFF
STUDIES,
3) THEDVTANDQUALIFICATION
PROCEDURES
WEREBASEDON
MISSION
REQUIREMENTS
OFANENTIRE
SPACE
SUIT
ASSEMBLY,
(,?
A, PROGRAM
SCHEDULES
WEREBASEDONTHEENGINEERING
DEFINITION
OFTHELONGEST
DURATION,
,i
4) THEDESIGN
ENGINEERS
COULD
_IOT
ADEQUATELY
EG
TRAIN
IHEPROJECT,
MANUFACIURING
ANDQUALITY
ENGINEERS
PRIOR
TOFABRICATION
OFTHEDESIGN
VERIFICATION
SPACE
SUIT,
t
5) THESUITCONTRACTOR
ANDTHEGOVERNMENT
ARE
INVOLVED
INWHATCHANGE
ISORISN'T
FEE
"
E
E
[
C
[
E
C
m
_o
!}
[l
BEARING
DURING
QUALIFICATION
TESTING.
P
r"
RECOMMENDED
GUIDELI
tIES:
tC
F
'-
1) ESTABLISH
REQUIRED
CYCLELIFEOF EACHMAJOR
SUBASSFJ,IBLY
ARMS,LEGS,GLOVES,
ETC.AND
[i
PERFORM
CYCLEQUALIFICATION
ANDDESIGN
VERIFIC_TION
t
, c,
OFTHESESUBASSEMBLIES
INSERIES.
i_:"",'2.-C
_ .",,-."
" =
"
'
r _
i"
"
-
"
2) ALLOWENOUGH
DEVELOPMENT
TIMETO PERMIT
THE
DESIGNENGINEERS
TO ALLOCATE
TIMETO PROJECT,
[,
MARUFACTURING
ANDQUALI_Y
ENGINEERING.
3) COSTTRADE-OFF
STUDIES
sHOULD
BE ACCOHPLISHED
BEFOREINCORPORATIO;I
OF "FINE.TUNING"
CHANGES
INDVIOR QUALIFICATION
UNITSONCEFABRICATION
I !'"
HAS STARTED.
[i
4) PERFORMING
DVI"
ANDQUALIFICATION
TESTIHG
ON A
['"
L,.
SUBASSEMBLY
BASISALLOWS
ADDITIONAL
FLEXIBILITY
WHILEPERFORMING
TESTING.
THUSREDUCING
DELAYS
_USEDBY QUALIFICATION
FAILURESOR
;
!"
UNANTICIPATED
DELAYSINRELEASING
ACCEPTABLE
ENGINEERING
DEFINITION.
['
5) FIRSTAPTICLE
CONFIGURATION
INSPECTION
COULD
i-
i.
BEPERFORHED
UPON
COMPLETION
OFQUALIFICATION
TESTING
OFEACH
SUBASSEMBLY,
r'%
l
L:
_I_
[i
!
" "
"
'
.,
IMPROVEOCONFIGURATION'MANAGEMENT
[_
"
1)
"
. .
2)
[_
"..
3)
IDENTIFICATION OF CONFIGURATiONDIFFERENCES
REQUIREDTIME-CONSUMINGPAPERSEARCHES
CHANGES OCCURRED AT COMPONENT OR"
" WHEN
LOWERCONFIGURATIONLEVELS
_i
4-)
5)
APPROXIMATELY50 cMO.-RELATEDIJOCUMENTS
...
.,
[._
WERE
ACTIVE DURING THE SKYLAB/ASTP
PROGRAM
["
- .
I.
=,,
6)
MANUFACTURING
& qUALITY ORIGINATED
ADDITIOI"ALDOCUMENTATION FOR TRACE
AND ACCOUNTABILITY REQUIREMENTS
"
I/
"
l
t
_
;"
J'i
i
_
,
:-
."
!
,
. CONTROLS
:.& METHODS
."
PROBLEM#1 - COMPLEXDRAWINGS& CONTROL
SYSTEMSEXISTED DUE TO MULTIPLE
CONFI GURAT! ON CHANGES
"
'
,=
RECOMMENDED
GUIDELINES
t
I_
1)
"
"
1_
1
-
;
-.
_,-.
.."
..
L
,
t.
,
!
2)
'o.
"
A PROPOSEDSYSTEM,WHICH IS INCLUDED
IN THE FINAL REPORT, SHOULDBE
"
;'
A)
- _ ":o "
-_" *
""
-'.o
IMPLEMENTAN
AUTHORIZEDCONFIGURATION
AND
TRACEABILITY
SYSTEM_,'IHICH'IiOULD
CONSOLIDATEINTER-RELATED MANUFACTURIHG,
QUALITY AND CMODATA.
."
[..
MOB KI T STATUS
TRACEABILITY
'
.
DELIVERY SCHEDULE
.;
p-o
W
..
"_
..
2
'"'
e_
:
2
; .'
-t
'
'
:'i,"
" ") "o',e
.. ,:.':
-.
'
"
[!_i
"
IMPROVED
CONFIGURATION
mNAGEMENT
CONTROLS/METHODS
[_
PROBLEM
#2: INCORPORATION
OF ACCEPTABLE
ALTERNATE
PARTSREQUIRED
FORMALCONFIGURATION
CHANGES,
[_
"
1) PERTHECEISPEC,EACHCOHPONENT
COULDONLY
BE REPLACED
WITHOTHERCOMPONENTS
HAVING
THE
"
L,
[
t
[,
!J
I'
SAMEPARTNUHBER,
2) EXISTING
SPAREPARTSWEREMODIFIED
OR NEW
PROCUREMENT
WASAUTHORIZED
BECAUSE
AN
INTERCHANGEABILITY
VEHICLE
DIDNOTEXIST,
_.
_o
RECO_IENDED
6UIDELINES:
_.
o
[_
n
I
[_
"
A SYSTEM
SHOULD
BE DEVELOPED
TO IDENTIFY
ANDcONTROL
USEOF ACCEPTABLE
ALTERNATE
PARTS,
U
F]
GOVERNMENT/CONTRACTOR
MANAGB_ENT
REPORTS
LC_
E
[]
Li
SIMILARREPORTS
WEREPREPARED
BY DIFFERENT
CONTRACTOR
GROUPS.
"
@
o
NO
I) MOSTREPORTSWEREUNCONTROLLED,
REQUIRING
,FORMAL
REVIEW
AND/OR
CONCURRENCE
PRIOR
TO
RELEASE.
2) NO CENTRALDATASOURCE_ISTEDAND RESULTED
_-i.
f-
t
I_
IN CUSTOr,
IERAND COI_RACTOR
COUNTERPARTS
FAVORING
EACHOTHER'SDATA (CMO,ENGINEERING,
OA,
R,
3) _ACH INTERDEPARTMENTAL GROUP OF THE
SUIT CONTRACTOR CREATED AND MAINTAINED
THEIR O_:IN
FILES TO PERFORM THEIR DALLY
TASKS.
l;
[i
L'-;
"
A.
AT
THE CONTRACTCR'S
FACILITY.
IN
AT LEAST
ii REDUNDANT
FILES EXISTED
SOME CASES 50 DIFFERENT CMO-RELATED.
B.
DOCU_;IENTS
IVEREINCLUDED IN FILES.
REORGANIZATION& RELOCATIONOF INIEC,-
[
f-
DEPARTI_ENTALGROUPSCAUSEDMUCH
DUPLICATION. .....
[!
"
[_
LJ
(
[J-:(_
RECOI.IMENDED
GUIDELINES: UTILIZE
A DATACENTRALIZATION
SYSTFJI
TO:
A. MONITOR
ANDCONTROL
ALLDATADISTRIBUTIONS
B, MONITOR
THEDATAREPRODUCTION
POLICiES.
C, ALLNEW
UTILIZE
ONECENTRAL
TO INPUT
DATA,
.DATASOURCE
L
[
o.
ASTRONAUT
FIELDOPTIONITEMCONTROL
........
[i
L
"
"
FIELDOPTIONAL
MODIFICATIONS
RESULTED
INCONFIGURATION
CHANGES,
MULTIPLE
DRAWING
REVISIONS,
ADDITIONAL
f-
i_,
, TRACKING
SYSTEMS
ANDMASSIVE
HISTORICAL
FILES.
i
1) APPROXIMATELY
30 FIELDOPTIONAL
ITEMS
(FOI'S)
WEREAVAILABLE
INANYCOMBINATION
TO THECREWMAN,
[-r.
2) SUITFITCHECK,
CREWMAN
GENERALLY
SELECTED
FOI'S
DURING
THE
.....
[.-_
L
A. TIMEWOULDNOTALLOWINCORPORATION
FOR
VERIFICATION.
[i
B. ON INITIAL
FIELDUSEOCCASIONALLY
NEWFIT
PROBLEMS
OCCURRED,
I!
F
L
,
3) STANDARD
FOI'SWERESHIPPED
AS PARTOF THE
SUITCONFIGURATION
WHENNOTDESIRED
BY THE
CREWMAN
(VALSALVA
DEVICE,
COMFORT
PADS,ETC,),
[-
u I-I
!(_.
I!
RECOMI.]ENDED
GUIDELINES: .
i) INSTALL
ALLFIELDOPTIONAL
ITEI]S
IN THEFIELD,
_?
2) IDENTIFY
ANDCONTROL
FOI'SAT A TYPEIILEVEL,
PREPARE
THELISTING
'OFFOI'SAS A TYPEI,
";
DOCUMENT
A, DO NOTMAKEFOI'SPARTOFTHECONTROLLED
DRAWING
SYSTEM,
3) PROVIDE
FOI'S
ONLYWHENSPECIFICALLY
REQUESTED
[i
_
_
BYTHECREWMAN,
.
.
......-..........
--T,--TT_
"
....
-..........
,__c,_--_
_
_--
=j
'
[._.
t,
CEISPECIFICATIOrIS
I:
PROBt
1.
,
.L
NUMEROUS
CHANGES
TO CEISPECIFICATIONS
CEIWEIGIff
CHANGES
SEPARABLE
COMPONENTS
REQUIRED
CLOSE
TRACKING
F. -
"
L,
EXCESSIVE
CHANGE
ACTIVITY
OCCURRED
DURING
PROGRAM
CREWOPTIONITEMS
_DED THROUGHOUT
PROGRAM
EFFECTED
WEIGHT
ANDCREWOPTIONITEMLIST
_.
ICDT_UI.ATION
CHAIIGES
OCCURRED
AT HIGHRATETHROUGHOUT
PROGRAM
NINklNS..
ALLOWSUFFICIENT
SAFETY
FACTOR
OH SPECWEIGHT
_
,
,
i
i
DELETEREQUIREMENT
TO REFLECT
ICDLISTINCEISPECS
CUSTOMER
SIGNATURE
ON ICDSHOULD
SUFFICE
i
T'
I
DELETECREWOPTIOI,_
LISTFROMCEISPECANDCOIITROL
_..
BYOTHERLOWERLEVELDOCUMENT,
(
\
f,._
-E
i_
L_
,!
,_
Z
z
r,_
I_.
,,
I--
__
t
E
In
_L
':
-I
'
[
PRo L .I.
,.
- F
_
-
!
;_
" MAINTAIN
EXPENSIVE
TO PREPARE
ArID
[_
"
CONTAINED
HIGHLEVEL
OFTECHNICAL
DETAIL
ILLUSTRATIONS
EXPENSIVE
!.I
I_
I_
ALLCLASS
I ANDITCONFIGURATIONS
MAINTAINED
3 MODELS
AT ONCE
OTHEROPERATIONAL
DIRECTIONS
(FOB'S,
SSN,SRP)
REFERENCES
RESTRICTED
[
L
f
I
'
SEPARATE
ANDDIFFERENT
INSTRUCTIONS
AT DEPOTAND
FIELD
TO'SFORNEWFAB.
:_
-i
I.
MM FORTEARDOWN
ANDREBUILD
MM RESTRICTED
TO NON-STRUCTURAL
REPAIRS
CHANGE
ACTIVITY
EXCESSIVE
1970- 1971,- 80 CHANGES
EFFECTING
2378
PAGES,
173ILLUST.
"
i
i:
LEVEL-OF-EFFORT
METHOD
OF MAINTENANCE
t,
L.;
r
_"
f
|
Ci
I
,:
CHANGES
DIRECTED
W/OREGARD
TO COST
INITIAL
STANDARD/,IAINTAINED
.i
,_
'
i1
[_
[i
_- _ ""
z
'-'
l
t
,,,
,_
"i
_'"
I_'s
Ii
_,.,
e_'
"
LIE
_o
,'i!
(
[.i
If
I"
INSPECTION
& IN-PROCESS
VERIFICATION
_"
PROBLEM_
AMOUNT
OF IN-PROCESS
DISCREPANCY
PAPER,
PRODUCTION
"DOWNTIME"ANDMANPOWER
REQUI:._D
TO CLEARPAPERWORK,
[,
F
"
1) THETOLERANCES
ON VARIOUS
DIMENSIONS
WERE
"TIGHT"
TO INSURE
QUALITY
WORkmANSHIP,
t-
2)
100%
I NSFECT]ON
-PRODUCTION,
WAS
PERFORMED
ON
ALL
ITEMS
IN
i
?
"
3) MANUFACTUR!NG
ENGINEERING
WASNOTDELEGATED
ANY
RESPONSIBILITY
FORDISPOSITIONING
A REJECT,
I'
[.
A, EACHREJECT
TAGREQUIRED
AN AVERAGE
OF ONEHOUR
TO PROCESS,
[!
B, MAJORANDMINORDEFECTS
WERENOTCLASSIFIED
AND
INDICATED
ON THEINSPECTION
INSTRUCTIONS
E
w
i
L
'_._i
_;'_
_''_
.--+i
__ _-_
..
( i
PROGRAM
GUIDELIIIES:
_ i,[",
"-"
4
+" ;
+E
_,- ;_
"," J:
I) INSURE
ALLTOLERANCES
AREPRACTICAL
PRIORTO
RELEASE
OF DVTPRODUCTION
DOCUMENTATIOII.
THE
RENLTSSHOULD
I_EREVIEWED
AFTERDVT,AND
TOLERA!ICES
REVISED
AS NECESSARY
FORTHE
: QUALIF-ICATION,
UNITS
! ,
,
J
:
"
IL
--
:,
:-
:.
2):CLASSIFICATION
OFDEFECTS
+) []
:_;:
It
_+
/
!
+
+--"
L
_'"
-
+>
3) A MININI+I
OF IN-PROCESS
INSPECTION
SHOULD
BE
PERFORMED
BY QUALI-TY.
THEEMPHASIS
SHOULD
BE
PLACED
ON SUBASSEMBLY
INSPECTION
ANDTESTING.
+.
4) BANUFACTURIIIG
SHOULD
BEDELEGATED
GREATER
I-
:-
; +_
2
.2
,<
_.
RESPONSIBILITY
FORIN-PROCESS
INSPECTION.
::
i
++,:-, .=
'+
++_
_'_"-I_
++.
.>
5) MANUFACTURING
ENGINEERING
SHOULD
BE
RESPONSIBLE
FORDISPOSlTIONING
MINOR
REJECTS.THISWOULDELIMINATE
APPROXIIIATELY
70%OF THEREJECT
TAGS.
;+"
" L
[i
t
J
-..
2-
(,
-I1
I_
,_._'_,
J
- .. . *
,
r_
i.-.
TRACEABILITY
F
r
HIGHLEVELOF MANPOI'IER
REQUIRED
TO t'_INTAII'I
-["
TRACEABILITY
SYSTEII,
STANDARD
TRACESYSTEI.}
DEVELOPED
INTOTOTAL
HISTORICAL/VERIFICATION
CAPABILITY,
F
U
CONTAINED
ALLFIELDAIID
DEPOTTRACEDATA,
MANUAL
SYSTEI.I
CAUSED
HEAVYMANLOADING,
_.
L
CRmCAL
PARTS
A_D
r_TERIALS
NOT
IDE,TIFIED.
"
REVIEWIHDICATES
25%IIEED
NOTBE TRACED
L.
[_
F:
L!
I_
_
ALLI_TERIALS
TREATED
EQUALLY
VARIATION
INTYPESOF TRACESYSTEI'IS
UTILIZED
(SHOPORDERS,
PIRS,FIRS)
COMPLICATED
DATARECORDII'IG
ANDRETRIEVAL
INCREASED
CHANCE
OF ERRORS
"
VARIED
ANDREDUNDANT
REQUESTS
FORDATA
RETRIEVAL
TIMECONSUI'IItlG
TRACEABILITY
I'.IATRIX
NOTFEASIBLE
: I
CAUSED
HIGHLEVELOF OVERTII'.IE
SOt,
IEREQUESTS
OF NON-CRITICAL
NATURE
I"
.(
NO REQUEST
SYSTEI4
OR REQUEST
"CHAIN-OFCOFIIIA{ID"
EXISTED
.i
_,
t
"
'I
L;
BETHODI. STREAMLINE
ANDMAINTAIN
A MANUAl,.
SYSTEM
RECORD
ALLTRACEDATABY ONESYSTEM
IDENTIFY
NON-CRITICAL
fIATERIAL
ANDDO NOT
[_
:" [i
"
_i
'
[i
TRACEBEYOND
RECEIVING
INSPECTION.
DO NOTTRACECLASSIICHANGES
"
TRANSFER
FILING
ANDMAINTENANCE
TO A CEtlTRAL
PROGRAfl
DATACENTER.
QUALITY
TO MONITOR
ANDVERIFY
ONLY.
REDUCES
QUALITY
CLERKREQUIREIEIITS.
ESTABLISH
"DATAREQUEST"
CONTROLS
ANDPROCEDURES.
[;
,
[
L,
METHODIT:COI'IPUTERIZE
DATASYSTEM
REDUCT
IOtl
IN I.]AI,IPOI'IER
[i
LESSFILINGREQUIREMENTS
FASTER
ANDMORECONTROLLED
RETRIEVAL
[)
MORERELIABLE
DATA
CLASSII CANBE TRACKED
AT LITTLEINCREASE
[_
I
;,
._COST.
"_.
I '
I .
i-'
i ;
[i"
-
_
_=_ _ _-....-:=-.-_
--..,,__
I
!
"2
d_
.!
I!
L._
['._.
SW_MARY
|_
I_
MAJORGUIDELINES
RESULTING
FROI'I
s'r'UDY:
"'F
"
[-'
1) PLACEEMPHASIS
ON QUALIFICATION
OF SUBASSEMBLIES
[-
RATHER
THANTHEENTIRE
SPACESUIT
ASSEMBLY.
2) FACIFIRSTPRODUCTION
ITEMRATHER
THAN
QUALIFICATION
ITEM,
i_
3)
CEIWORST
CASEMISSION
REQUIREr'_ENTS.
FIRST TIEIE
4) QUALIFY
REDUCE
DTO
RAWING
REQUIREI_IENTS
BY USING
MANUFACTURING
[_
INSTRUCTIONS
FORCONFIGURATION
CONTROL,
5) REDUCE
100%IN-PROCESS
INSPECTION
-- REPLACE
WITH
._ [
COMPONENT
ANDSUBASSEMBLY
ACCEPTANCE
TESTING,
11
6) DEVELOP
ALLOCATE
TIIIE
EARLY
INPROGRAM
TO
ESUFFICIENT
FFICIENT
SYSTEFIS
A,DPROCEDURES,
7) PERFORH
ASTRONAUT
FITCHECKAT USER'S
SITE,
8) STREAMLINE
DATAREPORTING
REQUIREMENTS
ANDCENTRALIZE
DATACOLLECTION
SYSTEH,
I_
9) CONSOLIDATE
PROGRAM
MAtlAGEMENT
CONTROL
FUNCTIONS,
i:L
Q
#,
1
F"
LC;
r
L'
POTENTIAL
MANMONTH
SAVINGS
r!
L:
,_.
i-
_.
F]
TOTALPOTENTIAL
SAVINGS
1565 IVIANMONTHS
'
SUr,
IMARY