STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 1 OF 3

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : GENERATOR,GENERATOR BAY PROTECTION

1.

PLANT DETAILS

THIS SYSTEM CONSISTS OF 4 MAIN CONTROL LABLES


TO PROVIDE CLASS A,B ,C TRIPS OF GENERATOR AND
GENERATOR TRANSFORMER & ITS BAY AND GIVE
ANNUNICATIONS TO CONTROL ROOM MONITORING .
NAME PLATE DETAILS
MAKE: ALSTOM
PROTECTION FOR GENERATOR,
GENERATOR TRANSFORMER & UNIT TRANSFORMER
2.

TESTING OBJECTIVE
TO PREVENT THE GENERATOR ,ITS TRANSFORMER AND ITS AUX
FROM FAULTS.
3.PROPOSAL
TRIPPING OF EQUIPMENTS ARE CARRIED OUT IN THREE CLASSES
DEPENDING UPON THEIR SEVERITY IN SPREADING&DAMAGING AND
OCCURRENCE PERIOD/DURATION.
CLASS A TRIPS
TRIPPING OF GENERATOR AND TURBINE ARE TO BE SIMULTANEOUSLY
CARRIED OUT WHEN THIS TYPE OF FAULT OCCURS.
CLASS B TRIPS
TRIPPING OF TURBINE SHOULD BE AT FIRST AND GENERATOR MUST
BE SUBSEQUENTLY TRIPPED ON REVERSE POWER PROTECTION WHEN
THIS TYPE OF FAULT OCCURS.
CLASS C TRIPS
TRIPPING OF GENERATOR ONLY REQUIRED WHEN THIS TYPE OF FAULT
OCCURS.
4.SERVICES REQUIRED
220 V DC SUPPLY,240 V 1 PHASE 50 Hz AC SUPPLY, GENERATOR
SYSTEM AND GENERATOR & UNIT TRANSFORMER .
5.0 SAFETY PRECAUTIONS
I)
FIRE EXTINGUISHER SYSTEMS READINESS
II) PROTECTION PANEL CHARGED CAUTION BOARD TO BE FIT
III) MEN & MATERIALS TO BE KEPT AWAY FROM PROTECTION PANEL
IV) IN CASE OF POWER SUPPLY FAILURE,EMERGENCY PROTECTION
OF EQUIPMENTS MUST BE ENSURED.
6. EMERGENCY PROCEDURE

/var/www/apps/conversion/tmp/scratch_4/331754411.doc

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 2 OF 3

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : GENERATOR,GENERATOR BAY PROTECTION

SUPPLY TO THE PANELS TO BE ISOLATED.


7. STATE OF THE PLANT
POWER SUPPLY MUST BE EXTENDED AT FIRST.ALL INPUT &
OUTPUT CONTACTS TO BE CHECKED. SETTINGS OF ALL RELAYS ARE TO
BE KEPT AS RECOMMENDED. ALL RELAYS AND METERS ARE TO BE
TESTED/CALIBRATED. PROTECTIONS MUST BE CHECKED OFFLINE & ON
LINE.
8. COMMISSIONING PROCEDURE
POWER SUPPLY CABLES & CONNECTIONS ARE TO BE MEGGERED.
PANEL IS TO BE THOROUGHLY CHECKED AGAINST SHORTING OR MIXING
OF POWER SUPPLIES. PRIMARUY INJECTION MUST BE CARRIED OUT TO
ENSURE INTERCONNECTIONS.
THE FOLLOWING TRIPS ARE ENVISAGED FOR THIS PLANT OTHER THAN
CUSTOMERS CHOICE OF ONE COMMON TRIP. THEY MUST BE CHECKED
ONE-BY-ONE BEFORE SYNCHRONISATION.
CLASS A TRIPS
I) 1.
GT PRV OPERATED (R,Y,B)
2. GT FIRE PROT TRIP (R,Y,B)
3. GT OLTC OIL SURGE OPERATED(R,Y,B)
4. GT HV & OVERHEAD LINE CONNECTION DIFF PROT (R,Y,B)
5. GENERATOR DIFF PROT OPTD (R,Y,B)
6. GEN OVERHEAD CONN DIFFERENTIAL (R,Y,B)
7. UT OLTC OIL SURGE OPERATED (TRF 1 & 2)
8. UT PRV OPERATED (TRF 1 &2)
9. UT DIFF (R,Y,B) OPERATED
II)
1. GENERATOR LOW FORWARD POWER
2. GENERATOR OVERVOLTAGE
3. GENERATOR STATOR EARTHFAULT
4. GENERTOR POLE SLIPPING
5. GENERATOR OVERFLUXING
6. GENERATOR FIELD FAILURE
7. GENERATOR DIFFERENTIAL PROTECTION
8. NEGATIVE PHASE PROTECTION
9. GEN PROTECTION (UF,OV,ROTOR E/F & 100 % STATOR E/F)
9. COMPLETION CRETERIA
GENERATOR & ITS BAY PROTECTIONS ARE SUFFICIENT FOR
PROTECTING GENERATOR AND GENERATOR TRANSFORMER FROM FAULTS.
10. APPENDICES

/var/www/apps/conversion/tmp/scratch_4/331754411.doc

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 3 OF 3

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : GENERATOR,GENERATOR BAY PROTECTION

DRAWINGS: O & M MANUAL OF GENERATOR,GENERATOR


TRANSFORMER AND ITS BAY PROTECTIONS
LOG SHEETS :
I)
AC,DC SUPPLY EXTENSION TO
PANEL
II) TEST REPORT OF PTs,CTs
III) READINESS OF AUX SYSTEMS

/var/www/apps/conversion/tmp/scratch_4/331754411.doc