Documente Academic
Documente Profesional
Documente Cultură
Chemical Engineer1
Total.67
TRK TRAKTR
46 SERES
56 SERES
55-46
65-46
55-56
60-56
65-46
70-46
70-56
70-56 DT
70-46 DT
GOLDEN GENERATION
54 C
JUNIOR
Its production
stopped
It has sufficiency
certificate but
not produced
54 C
SPECIAL
66 SERIES
70-66
80-66 DT
80-66
2. INTRODUCTION
requires
both
theoretical
and
practical
knowledge.
3. REPORT
3.1. CLASSIFICATION OF PRODUCTION TECHNIQUES.
3.1.1. CASTING
One of the earliest processes for forming metals. Any metal that
can be melted and poured can be cast. Basically casting processes
consist of these steps; firstly, the material is to be melted and then,
liquid material is poured into a cavity which is called mold. Finally,
waiting till the material solidifies.
In TTF almost all parts of the tractors are initially cast and heat
treated materials before processing. In the early times casting was
being applied in TTF but later all cast components started to be bought
from foreign and Turkish casting companies. And this process is not
used any more.
3.1.2.1 Drilling
It is used for making holes or enlarging holes. The important
steps of the drilling process are; firstly the upper point of the drill forms
very small hall. As the drill goes through against the material, chips
start to form. Then chips are removed from the hole by means of
special shapes of drills. Because of friction between material and drill
temperature may get undesired values. Lubrication fluid can be used in
order to decrease the temperature.
3.1.2.2. Reaming
Reaming is the removal of small amount of material from the
surface of a hole for the purpose of bringing the hole to a more exact
size or improving the finish of an existing hole.
10
3.1.2.3. Turning
Turning is used for removing chips from cylindrical and conical
surfaces. Only workpiece rotates and cutting tool does the cutting
process. Cutting tool can go along three axes, so irregular surfaces can
be turned. Turning machine is generally called lathes. Besides turning,
lathes are capable of performing a variety of processes as given below.
a)Facing: Cutting tool must be fed towards only surface of the work
piece in order to get clean and flat surface. So the rough surface is
removed.
b)Cutting: If the tool is fed only towards the workpiece, that section of
workpiece is cut along the position of tool.
c)Drilling: Drilling on lathes is done with the drill that is in the
tailstock. Tailstock fed by hand against workpiece. Only workpiece
rotates and drill does not.
d)Boring: Lathe is used for enlarging a hole that is previously drilled.
This process is called boring.
3.1.2.4. Sawing
Sawing is a basic machining process in which chips are produced
by cutting the edges arranged in a narrow line. Each cutting edge
called tooth forms a chip as it passes through the workpiece. Sections
of considerable size can be reversed from the workpiece with the
11
3.1.2.5. Milling
In this process, multiple-tooth cutter is used so that cheap
removal rate is very high. Its job is mainly same with the shaping but
milling process is faster. Mostly the cutter rotates and workpiece is fed
to a cutter. At some milling machines, workpieces remains stationary
and cutter is fed to the workpiece. Milling process can be generated by
two different methods.
a) Up Milling: The cutter rotation is in the same direction with the
feed of the workpiece. Chip is very thin at the beginning and increases
in thickness, becoming a maximum at point where the cutter leaves
the workpiece. In up milling, chips are carried in the newly machined
surface so the surface finish is poorer than in down milling.
b) Down Milling: In down milling, maximum chip thickness occurs
close to the point where the cutter contacts the workpiece. The surface
quality of the workpiece is better than up milling because cutting
process is smoother.
3.1.2.6. Shaping:
It is used for generating flat surfaces. Cutting motion is always
straight line. Addition of these straight lines generates the flat surface.
12
In this process, high skilled workers are required and also this process
is very slow because cutting occurs during only the forward part of the
stroke. For these reasons, shaping processes have been replaced by
milling and broaching processes.
3.1.2.7 Broaching:
Broaching is a unique machining process in which chips are
removed by a number of successive teeth increasing in size, built on a
long tool named broach. Roughing, semifinishing and finishing teeth,
consequently the related processes are combined in a single tool. The
profile of the machined surface is the inverse of the profile of the
broach. The cutting action is performed in a fixed path, and with one
stroke of the broach the process is completed. Broaching is suitable for
mass production where the high production rate justifies the cost of the
expensive tool.
3.1.2.8. Abrasive Machining Process:
Abrasive machining is the basic process in which chips are
formed by very small cutting edges that are integral parts of abrasive
particles.
Grinding is the most common abrasive machining process.
Generally not suitable for bulk material removal but used for
dimensional accuracy and surface improvement by removing a small
amount of material from the workpiece surface.
13
3.1.3. Welding
In TTF the applied methods of arc welding are as follows:
3.1.3.1. Arc Metal Welding
14
3.1.4. Tempering
Steel, which has been quenched directly into the martensitic
region, is too brittle for most purpose and must be softened. Moreover,
15
16
125 mm
200 mm
3.2 module
280 Nm
17
+/- 45
-180/+40=220
4
15 mm
180 mm
25
325
300
165
mm
mm
mm
mm
252 mm
473 mm
112 mm
#15 Taper
(2.615)
85.5 mm
90 mm
M8x1.25x15 mm
Dp
3900 kg @ 41.4
Bar
1115 kg @ 41.4
Bar
115 mm
215 mm
22, 27, 32, 40 mm
ISO #30
200 mm
150 1500 rpm
5 150 rpm
152 mm
7 kg
6000 mm/min
6000 mm/min
7.5 kW
15.0 kW
3kW@1000rpm/50
Hz
30 Liter/min
1016 mm
2300 mm
2704x1650x3117
mm
2578x1650x3117
mm
6,820 kg
58 Amps., 43 kW
74 Amps., 43 kW
10 m3/hr
4 Bars
320 L
110 L
6L
Working area
Chuck diameter
Swing diameter
X path
Z path
Load time
Main spindle
Spindle flange acc. to DIN 55026
Spindle bearing arrangement - front
Maximum speed
Main drive
Three-phase AC motor 40% duty cycle
Maximum power
Full power as of spindle speed
Moment 40% duty cycle
Maximum moment
Feed drive
Rapid traverse speed X
Rapid traverse speed Z
Feed force in X and Z
Ball screw in X and Z
18
500 mm
600 mm
630 mm
400 mm
12 sec
size 11
190 mm
2000 rev/min
44 kW
75 kW
300 rev/min
1390 Nm
2350 Nm
20 m/min
15 m/min
18 kN
50 mm
8 fold
60 mm
400 V
24 V
230 V
50 Hz
3800 mm
1750 mm
4000 mm
13000 kg
314 mm2
1150 mm2
300 kN
750-1500 rev/min
300 mm
spindle
carrier
Total length
Connected load, total
Voltage
Main fuse
Supply line cross section
Control voltage
Control voltage, hydraulic system
Cooling water consumption
approx.
approx.
approx.
approx.
19
2260
4100
1350
1055
mm
mm
mm
mm
approx. 5000 kg
5.70 m
2.40 m
2.60 m
9000 kg
ELECTRICAL EQUIPMENT
Control
Voltage
Frequency
Control Voltage
Total Connected Load
Nominal Current
Recommended Wire Size
Main Spindle Motor
Nominal Speed
Maximum Speed
KB - output
Feed Motor Z-axis
Continuous Torque
NC-usable Speed
Feed Motor X-axis
Continuous Torque
NC-usable Speed
Hydraulic Unit
Central Lubrication Unit
Coolant
Chip Conveyor
MECHANICAL EQUIPMENT
General Data
Top point
Machining Spindles left Unit
Machining Spindles right Unit
Range of Workpiece Length
Workpiece Diameter
Spindle Units
Spindle Diameter
Drive Output
Spindle Speed
Tool Adapter
SIEMENS
3*400 V
50 Hz
24 V AC
35 KVA
50 A
5*10 mm2
Three-Phase Motors
1460 rev/min
4000 rev/min
11 kW
SIEMENS
9.5 Nm
2500 rev/min
SIEMENS
2.7 Nm
2500 rev/min
3.00 kW
0.07 kW
1.70 kW
0.50 kW
1200 mm
2
2
100-800 mm
10-70 mm/one set of jaws
80 mm
11 kW
2000 rev/min
HSK 63 DIN 69893
20
400 mm
10 m/min
0-10000 mm/min
300 mm
7.5 m/min
0-7500 mm/min
3-point-clamping
50 bar=20 kN
36/45 mm
1xprism/1xflat
10 70 mm
rigid
corrugated
GENERAL EQUIPMENT
Hydraulic System
Manufacturer
Drive Output
Oil Tank
Operating Pressure
Clamping Pressure max
Hydraulic Oil
Rexroth
3.0 kW
60 Liter
60 bar
60 bar
DIN 51502(-9)/HLP-ISO
VG68
27 cdm/min
Flow Quantity Q
Central Lubrication System
Manufacturer
Drive Output
Tank Capacity
Lubrication Pressure max
Continuous Flow Volume
Operating Viscosity
Lubricant Temperature Range
Ambient Temperature Range
Type of Lubricating Oil
Vogel
0.07 kW
3.0 Liter
35 bar
500 cm3
201000 mm3/s
0+80C
0+60C
DIN 51519/CGLP-ISO VG
68
Ruez
160 L/min at 1,7 bar
30 L/min at 22 bar
240 L
Water soluble cutting oil
TB 303/220
1,7 kW
Festo
4 - 6 bar
21
14 bar
40 L/cycle
Unit
mm/min
mm/min
H-400N
H500/40N
560
710
510
mm/min
mm
30-540
50-560
mm
100-610
150-660
kg
rpm
mm
kg
8,500
10 (rated
10 (rated
continuous
continuous
operation)/
operation)/
15 (rated
15(rated 30
30 min
min
operation)
operation)
ISO #40
50-10,000
400x400
500x500
400
500
mm/min
mm/min
mm/min
mm/min
mm/min
mm/min
mm
mm
30,000
1-8,000
30,000
1-8,000
30,000
1-8,000
150
95
mm
150
kg
12
HP
mm
22
510
320
350
be changed
Tool Icmaping force
Number of tools accommodated
Tool selection system
kg
pcs.
1,240
30
Random
75 mm
120 mm
30 mm
1.8 mm
0-0.05 mm/sec
180 mm
(standard)
Wheelhead approach for variation of diameter
225 mm
(optional)
Maximum wheel diameter
Minimum wheel diameter
Wheel bore
Maximum wheel thickness (one wheel)
Maximum width of wheel set (the total of wheel
thicknesses shall not exceed 125 mm)
Spindle speed
Wheel motor power (standard)
Wheel motor power (optional)
Weight of unit without profile truing attachment
Weight of unit with profile truing attachment
760
600
305
125
225 mm
750/930 rpm
10 HP
1.5 HP
800 kg
1000 kg
10 to 225 kV
20 to 450 kV
23
mm
mm
mm
mm
General Using Areas: To detect the casting defects in casting parts &
welding defects in welded parts.
Using Aim of TTF: Inspection of the casting defects in connecting rods
& crankshafts.
Operating Temperatures: 0C to 40C
All these machines are still working machines from different
teams of the factory. As I said before in the huge machine park of TTF
there are some very old fashioned (oldest was 1950 drilling machine)
and some last technological machines. But the grinding machine
(LANDIS)
was the most enthusiastic one for me. There are only two
of them in Turkey and both are in TTF. One has only one turning disk
whereas the other has two of them. The disks rotate in an extremely
high spindle and can remove up to 7 mm chip which is impossible with
an ordinary grinding machine. The abrasive particles on the disks are
CBN (Cubic Boron Nitride) which is the second hardest and expensive
material after diamond.
24
2.workpiece:
Production Procedure:
The forged part coming from side-industry named Position
Control Shaft is first inspected. Then it is normalised in the heat
treatment department and hardness is controlled before sandblasting
operation. After facing and center drilling the long part is turned, canal
is opened and threads are cut. The short side is turned and heat
treated for removing stresses after induction hardening. Again
hardness test is applied and the long part and the short part are
grinded to their exact dimension. The hole is milled to its exact
dimension. Finally the part is washed, air cleaned and sent to assembly
line after last inspection.
3.workpiece:
25
Production Procedure:
The name of the part forged from SAE 1040 is Gearbox reductor
control fork. As a first step it is tempered and sandblasted. After
17.3x36 mm hole is drilled and 18 mm is broached, the part is
washed and cleaned with air by two workers. Before further processing
the part is linearised. Then 8.3 mm is milled, vertices of the shoes are
rounded and the part is again washed. Since the shoes will be exposed
to high forces, they are induction hardened and heat treated. After
depth of induction is tested, 5.1 mm hole is drilled and chips are
removed before linearisation. Grinding to exact dimension, removal of
chips, washing and inspection for appropriateness are the last
processes on the part before getting assembled.
4.workpiece:
Production Procedure:
As the other parts Hydraulic Lifter Piston Arm Rod is first
inspected, tempered, passed through hardness tests and sandblasted.
Both ends of the part are face milled and pointed with center drill.
Then turned to its profile. After induction hardened, the part is heattreated and depth test is applied. The outer diameter is turned, an 11
mm hole is drilled and chips are removed. After examination the part is
coated with manganphosphate and inspected again.
26
5.workpiece:
Production Procedure:
The name of the last part I will go through is HK and GC Clutch
Separation Fork. It is first inspected according to its forged drawing.
Then it is tempered and sandblasted. After that 23.2 mm hole is
drilled and 24.052 mm is broached. The part is washed and air
cleaned by two workers. Then it is linearised and radial surfaces are
milled. After chips are removed M16x1.5 hole is threaded and 24.052
mm is broached again for the removal of chips. After linearisation and
inspection the part is coated with phosphate and the last inspection is
done.
27
28
Leve
l
-----0
Op
Item/
Description/
Se
q
----
Cost
Elem
-----------567871
20
20
Resource
Overhea
d
Sub-Elem
Dept
-----------------Gearbox
Red.
083-01 OG
Amrts
OG
Mak
e
Buy
-----Mak
e
ted
Yield/
Quantity
Item Unit C.
Res Unit
Co.
---------------5,104,702.
30
62,896.00
Basis
UOM
Rate or Am.
----------
-----AD
-----------------1
Dk
TL
0.3
114,976.00
Item
Res
units
29
Extended
C
-------------18,868.80
34,492.80
20
20
25
25
25
25
40
40
40
40
50
50
50
50
60
60
60
60
70
70
70
70
80
80
80
80
90
90
90
Overhea
d
Overhea
d
Resource
Overhea
d
Overhea
d
Overhea
d
Resource
Overhea
d
Overhea
d
Overhea
d
Resource
GNG
OG
Res
units
Res
units
TL
32,066.00
9,619.80
TL
64,426.00
19,327.80
Item
Dk
TL
0.3
114,976.00
TL
32,066.00
9,619.80
TL
64,426.00
19,327.80
Dk
TL
0.02
114,976.00
TL
32,066.00
480.99
TL
64,426.00
966.39
KSHAT- KS
Item
Dk
2.14
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KS
Res
units
Res
units
Res
units
TL
114,976.00
GNG
KS
TL
32,066.00
TL
64,426.00
KDHAT-
KD
Item
Dk
0.67
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KD
TL
114,976.00
76,574.02
GNG
KD
Res
units
Res
units
Res
units
TL
32,066.00
21,355.96
TL
64,426.00
42,907.72
KHHAT-
KH
Item
Dk
0.12
Overhea
d
Overhea
d
Overhea
d
Resource
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KH
TL
114,976.00
13,797.12
GNG
KH
Res
units
Res
units
Res
units
TL
32,066.00
3,847.92
TL
64,426.00
7,731.12
KSHAT- KS
Item
Amrts
KS
Dk
TL
1.36
114,976.00
GNG
KS
Res
units
Res
units
Res
units
TL
32,066.00
85,727.25
156,712.2
9
43,705.96
TL
64,426.00
87,812.64
KSHAT- KS
Item
Dk
Overhea
d
Overhea
Amrts
KS
TL
114,976.00
GNG
KS
Res
units
Res
TL
32,066.00
GNG(d) OG
086-01 OG
Amrts
OG
GNG
OG
GNG(d) OG
089-01
Amrts
OE
OE
GNG
OE
GNG(d) OE
GNG(d) KS
GNG(d) KD
GNG(d) KH
GNG(d) KS
Res
units
Res
units
Res
units
Item
Res
units
Res
units
Res
units
30
62,896.00
62,896.00
62,896.00
62,896.00
62,896.00
62,896.00
62,896.00
18,868.80
34,492.80
943.44
1,724.64
134,786.1
3
246,393.5
7
68,717.44
138,064.9
2
41,888.74
7,547.52
125,792.0
0
229,952.0
0
64,132.00
90
10
0
10
0
10
0
10
0
11
5
11
5
11
5
11
5
12
0
12
0
12
0
12
0
15
0
15
0
15
0
15
0
16
0
16
0
16
0
16
0
17
0
17
0
17
0
17
0
18
0
18
d
Overhea
d
Resource
GNG(d) KS
units
Res
units
TL
64,426.00
KSHAT- KS
Item
Dk
0.7
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KS
TL
114,976.00
80,713.15
GNG
KS
Res
units
Res
units
Res
units
TL
32,066.00
22,510.33
TL
64,426.00
45,227.05
KHHAT-
KH
Item
Dk
0.12
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KH
TL
114,976.00
13,797.12
GNG
KH
Res
units
Res
units
Res
units
TL
32,066.00
3,847.92
TL
64,426.00
7,731.12
081-01
OF
Item
Dk
0.41
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
OF
TL
114,976.00
46,565.28
GNG
OF
TL
32,066.00
12,986.73
GNG(d)
OF
Res
units
Res
units
Res
units
TL
64,426.00
26,092.53
KSHAT- KS
Item
Dk
1.13
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KS
TL
114,976.00
GNG
KS
Res
units
Res
units
Res
units
TL
32,066.00
130,152.8
3
36,298.71
TL
64,426.00
72,930.23
KSHAT- KS
Item
Dk
0.5
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KS
TL
114,976.00
57,488.00
GNG
KS
Res
units
Res
units
Res
units
TL
32,066.00
16,033.00
TL
64,426.00
32,213.00
KSHAT- KS
Item
Dk
3.45
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KS
TL
114,976.00
GNG
KS
Res
units
Res
units
Res
units
TL
32,066.00
TL
64,426.00
KSHAT- KS
Item
Dk
1.88
Overhea
Amrts
Res
TL
114,976.00
GNG(d) KS
GNG(d) KH
GNG(d) KS
GNG(d) KS
GNG(d) KS
KS
31
62,896.00
62,896.00
62,896.00
62,896.00
62,896.00
62,896.00
62,896.00
128,852.0
0
44,152.99
7,547.52
25,472.88
71,198.27
31,448.00
216,865.4
1
396,437.2
5
110,563.5
7
222,140.8
5
117,930.0
0
215,580.0
0.1
0
18
0
18
0
19
0
19
0
19
0
19
0
20
0
20
0
20
0
20
0
d
Overhea
d
Overhea
d
Resource
20
GNG
units
Res
units
Res
units
KS
GNG(d) KS
TL
32,066.00
TL
64,426.00
0
60,123.75
120,798.7
5
34,592.80
KSHAT- KS
Item
Dk
0.55
Overhea
d
Overhea
d
Overhea
d
Resource
Amrts
KS
TL
114,976.00
63,236.80
GNG
KS
Res
units
Res
units
Res
units
TL
32,066.00
17,636.30
TL
64,426.00
35,434.30
KHHAT-
KH
Item
Dk
0.12
Overhea
d
Overhea
d
Overhea
d
Amrts
KH
TL
114,976.00
13,797.12
GNG
KH
Res
units
Res
units
Res
units
TL
32,066.00
3,847.92
TL
64,426.00
7,731.12
567871V
Material
Gearbox red.
Semi-product
AD
1
781,000.00
GNG(d) KS
GNG(d) KH
Buy
1
Item
62,896.00
62,896.00
7,547.52
781,000.00
781,000.0
0
Item/
Description/
Mak
ted
Yield/
Leve
Se
Cost
Sub-Elem
e
Buy
Basis
l
-----0
q
----
Elem
-----------5122530
Dept
-----------------Position
-----Mak
----------
20
Resource
contr.
094-01
20
Overhea
OH
Amrts
20
d
Overhea
OH
GNG
Quantity
Item Unit C.
UOM
Rate or Am.
Res Unit
Extended C
-----AD
-----------------1
Co.
---------------3,664,923,
----------------
Item
Dk
0.25
32
62,896.00
Res
TL
114,976.00
28,744.00
TL
32,066.00
8,016.50
TL
64,426.00
16,106.50
Item
Dk
0.08
Res
TL
114,976.00
15,724.00
units
OH
Res
units
20
d
Overhea
GNG(d)
Res
d
Resource
OH
089-01
units
40
40
Overhea
OE
Amrts
OE
32
62,896.00
5,031.68
9,198.08
40
d
Overhea
GNG
OE
40
d
Overhea
GNG(d)
OE
50
50
d
Resource
Overhea
50
d
Overhea
50
d
Overhea
60
60
d
Resource
Overhea
60
d
Overhea
60
d
Overhea
70
70
d
Resource
Overhea
70
d
Overhea
units
Res
TL
32,066.00
2,565.28
TL
64,426.00
5,154.08
Dk
TL
0.48
114,976.00
TL
32,066.00
15,263.42
TL
64,426.00
30,666.78
Dk
TL
1.67
114,976.00
TL
32,066.00
53,421.96
TL
64,426.00
107,333.72
Dk
TL
1.8
114,976.00
TL
32,066.00
57,750.87
TL
64,426.00
116,031.23
Dk
TL
0.34
114,976.00
TL
32,066.00
10,966.57
TL
64,426.00
22,033.69
units
Res
units
KSHAT- KS
Item
Amrts
KS
Res
GNG
KS
62,896.00
29,938.50
54,728.58
units
Res
units
GNG(d) KS
Res
units
KSHAT- KS
Item
Amrts
KS
Res
GNG
KS
62,896.00
104,784.74
191,550.02
units
Res
units
GNG(d) KS
Res
units
KSHAT- KS
Item
Amrts
Res
KS
62,896.00
113,275.70
207,071.78
units
GNG
KS
Res
units
70
d
Overhea
90
90
d
Resource
Overhea
90
d
Overhea
GNG
OF
90
d
Overhea
GNG(d)
OF
12
d
Resource
KLHAT- KL
Item
Dk
2.73
0
12
Overhea
Amrts
Res
TL
114,976.00
313,539.55
0
12
d
Overhea
TL
32,066.00
87,443.98
TL
64,426.00
175,689.70
GNG(d) KS
Res
units
081-01
Amrts
OF
OF
Item
Res
62,896.00
21,510.43
39,321.79
units
Res
units
Res
units
KL
62,896.00
171,517.39
units
GNG
KL
Res
units
0
12
d
Overhea
GNG(d)
0
13
d
Resource
KLHAT- KL
Item
Dk
1.71
0
13
Overhea
Amrts
Res
TL
114,976.00
KL
Res
units
KL
33
62,896.00
107,803.74
197,068.86
0
13
d
Overhea
GNG
KL
0
13
d
Overhea
GNG(d)
KL
0
13
d
Resource
KSHAT- KS
5
13
Overhea
Amrts
5
13
d
Overhea
TL
32,066.00
54,961.12
TL
64,426.00
110,426.16
Item
Dk
1.15
Res
TL
114,976.00
132,567.33
TL
32,066.00
36,972.10
TL
64,426.00
74,283.18
units
Res
units
KS
62,896.00
72,519.09
units
GNG
Res
KS
units
5
13
d
Overhea
GNG(d) KS
5
14
d
Resource
KSHAT- KS
Item
Dk
1.11
0
14
Overhea
Amrts
KS
Res
TL
114,976.00
127,738.34
0
14
d
Overhea
GNG
KS
TL
32,066.00
35,625.33
0
14
d
Overhea
TL
64,426.00
71,577.29
Item
Dk
0.2
Res
TL
114,976.00
22,995.20
TL
32,066.00
6,413.20
TL
64,426.00
12,885.20
AD
TL
504,250.00
62,896.00
69,877.46
units
Res
units
Res
GNG(d) KS
units
d
Resource
0
15
Overhea
0
15
d
Overhea
GNG
0
15
d
Overhea
GNG(d) KG
20
Res
units
0
15
0
0.1
units
Res
KGHAT-
62,896.00
12,579.20
KG
Amrts
KG
units
Res
KG
units
Res
units
d
5122530
Position
V
Material
Contr.
Semi-product
Buy
1
Item
504,250.00
504,250.00
---------------3,664,923.3
2
=======
=
34
35
3.4.3 Location:
The factory was at first constructed for producing air craft
engines but then it was turned into the current tractor factory. Since
Ankara is the capital of Turkey and located
the
factory was next to the railway and the river and it already had the
machine park which could be used for the new tractor factory. Another
36
reason was that the AO land which belonged to the government could
be used without any finance.
different
departments
the
computers
have
different
capabilities but all are connected through a network system for best
communication. The computers in the workshop which are used by
37
are 6 SGI
crack
detection
unit
38
Parts are not only stored in the locations I show but they also
wait on the angled rails used for carrying from one machine to another.
3.6.2 Operation Types:
Since tractors are produced in large lots following an unchanging
repetitive process, we can say that TTF is a FLOW SHOP.
But there are many types of products which are produced
according to the demand so, we can also say that the production is
Batch Shop type.
39
jack
Bremze rooms
donkey
washer
rotating
cylinders
40
3.6.6 Productivity:
Gross Capacity Gross Capacity Losses = Net Capacity
Net Capacity Total of Deviations = Actual Net Capacity
Productivity=1+Net Capacity Losses/Gross Net Capacity+Indirect
Labor H./Gross
Net Capacity
(Heat Treatment working hours are not included in the calculations)
Deviations mentioned above are; electricity cut off, machine
failure, tool
conducts
the
demand
to
Production
Planning
42
which states that TTF can not obtain that part from any other producer.
So the probability of scarce exists in case that producer has scarce
resources itself and can not supply the demand.
Anyway TTF has scarce in educated workers after economic
crisis. Because the educated workers drawn away find different jobs if
they can.
cast cover
(128127/508566
7)
right support
(132003/514404
0)
left support
(132004/5144039
)
used
256 59 197
used
73 59 14
used
18
19
20
21
48
59
(+196)
185 71 114
114 44 73*
73
63
used
-11 159 59 100
100
71 197 71 126
29(+116)
145 44 101
10 101 63 38
(+150)
126 44 82
82
30(+101)
43
14
-57(+178)
121 44 77
52 77 52 25
71
24
160 60 100
38
60 131
-22(+249)
60 25
71(+109)
-35(+110)
(* It was realised that the number is greater than it should be when the inventory was counted )
Minus signs do not mean that the inventory is less than needed today
but it implies that if not ordered the number of items will not be
sufficient yesterday. Because, at the beginning of a day materials are
shown as assembled although they are not.
inventory
200
150
100
50
0
-50
16
18
20
22
44
24
26
60
inventory
100
50
0
14
16
18
20
22
24
26
-50
-100
day of the m onth
quality
- Zero stock
- Production suitable for the goal
45
System
improvement
with -
maximum specialisation
Motivation
with
reward
System
improvement
with
cooperation
and - Motivation with honourisation
punishment
- Obtaining resources competitively
- Maximum profit
reliance
- Optimum quality
is
graduated
from
Hacettepe
University-Psychology
Quality Assurance
Quality Systems
Human Resources
-
Communication
Education
Health
Security
Garage
47
4. CONCLUSION
The most significant experience that is gained in this summer
practice is learning how to apply the theoretical knowledge into
practice. This is improved by observing and discussing the technical
processes, mostly concerning the manufacturing methods, with the
engineers and the workers. With this way, more practical and
theoretical knowledge is obtained. In addition, learning to prepare the
technical drawings used in manufacturing and learning to use them in
making engineering calculations is another part of this experience.
48
49
aware of this fact but as a temporary solution they are filling this gap
with some experienced mechanical engineers.
As a result, this summer practice gave me some theoretical
knowledge, some experience, some skills that are directly applicable
and useful in my career in the future. I had the opportunity to observe
how the projects go on, the personnel relations among their superiors
and each other. So I can say that this summer practice has been very
useful in comparison with most of the lessons I have taken at school.
50
APPENDICE
S
51