Documente Academic
Documente Profesional
Documente Cultură
Development of wind power started in India during the 6th five-year plan (1983-84).
The national program for wind energy includes wind resource assessment activities,
R&D support, development of manufacturing and infrastructure capability,
installation, generation and manufacture of wind generators, policy support etc.
The Wind Resources Assessment Programme is being implemented through the State
Nodal Agencies, Field Research Unit of Indian Institute of Tropical Meteorology
(IITM-FRU) and Center for Wind Energy Technology (C-WET).
India is the only country in the world with a separate ministry for renewable energy
sources- The Ministry of New and Renewable Energy
T h e $B e g in n in g$
Lib e ra liza / o n $E ra $
R e fo rm s$
CHAPTER 4 TECHNOLOGY
A windmill captures wind energy and converts it into electrical energy.
A wind generation plant comprises of a supporting structure and turbines. In
India, turbines can comprise of 2 or 3 blades. A generator is attached to one end of a
wind turbine, which provides mechanical energy. The other end of the generator is
connected to an electrical grid. Small generators usually require less force to start, but
are not energy efficient. Large generators are very efficient in high wind speed, but
find it difficult to turn when its less windy. A step up transformer converts low
voltage from collection to high voltage level of electric power transmission and
distribution system.
The balance of plant comprises the remainder of the wind farm infrastructure,
including access roads, concrete foundations, operating platforms, an electrical
collection system, a step-up substation, interconnection infrastructure to the electricity
transmission system and an operation and maintenance building. The towers are
secured using concrete foundations and are connected to an electrical collection
system.
Two types of wind turbines namely stall regulated and pitch regulated are being
deployed in the country and abroad for grid-interactive power. The stall regulated
wind turbines have fixed rotor blades whereas pitch regulated wind turbines have
adjustable rotor blades that change the angle of attach depending upon wind speed.
Both technologies have their own advantages and disadvantages. Wind turbines are
also available with lattice, steel tubular and concrete tubular towers.
The central Ministry of Finance has stipulated several policies and incentives to boost
investments in this sector.
Incentive
Ministry
Implemen Description
Comments
ting
1.
MoF
Agency
Income
Accelerated
(Ministry
Tax Dept
depreciation
of
benefits
Finance)
investments quickly.
A significant decline in
April 2017.
(AD)
revoked.
Note: Only one of AD or GBI
2.
MoF
Income
Additional depreciation of
can be availed.
The extension of additional
Additional
(Ministry
tax Dept
depreciation to transmission
Depreciatio
of
n Allowance
Finance)
for power
installed by certain
projects
sector.
MoF
Income
Tax holiday
(Ministry
Tax Dept
of
Finance)
March 2017
project's operations.
However for Corporates
MAT @ ~21% shall be
applicable. The eligible date
for projects in the power
sector to avail the benefit
under Section 80-IA of the
Income Tax Act stands
extended from March 31,
2014 to March 31, 2017.
4.
MNRE
IREDA
Generation
(Ministry
(Indian
be provided to wind
Based
of New
Renewabl
Incentive
and
e Energy
(GBI)
Renewabl
Developm
e Energy)
ent
Agency)
maximum period of 10
years with a cap of Rs. 100
Lakhs per MW. The total
disbursement in a year will
not exceed one fourth of the
maximum limit of the
incentive i.e. Rs. 25.00
Lakhs per MW during first
four years. The GBI scheme
will be applicable for entire
12th plan period having a
target of 15,000 MW.
5. Priority
Sector
MoF
RBI
Lending
6.
Central
State
According to Electricity
Renewable
Electricity
Electricity
Purchase
Regulator
Regulator
Obligation
recommendations given by
(RPO)
Commissi
Commissi
<>.
on
ons
(CERC)
(SERCs)
2014 recommends to
Regulatory Commissions
(SERCs).
7.
Central
National
Renewable Energy
Renewable
Electricity
Load
Certificate (REC)
Energy
Regulator
Despatch
mechanism is a market
Certificates
Centre
(RECs)
Commissi
(NLDC)
on
facilitate compliance of
(CERC)
renewable purchase
obligations (RPO). This
concept seeks to address the
mismatch between
availability of RE sources
8. National
Ministry
Ministry
Renewable
of New &
of New &
100 GW (Solar), 60 GW
of 175 GW of RE capacity
Energy
Renewabl
Renewabl
Target of
e Energy
e Energy
175 GW by
(MNRE)
(MNRE)
future RE denominated
electricity system.
2022
9.
Central
State
Preferential
Electricity
Electricity
Feed in
Regulator
Regulator
Tariff
Commissi
Commissi
on
ons
(CERC)
(SERCs)
Several policies in addition to the one referenced above has been adopted by the
government to bolster the wind power sector, including 100% FDI in wind sector,
IREDA refinance scheme, National clean energy fund, Excise and customs duty
exemption, National Green Energy corridor, National wind mission and UDAY.
Return on equity;
Interest on loan capital;
Depreciation;
Interest on working capital;
Operation and maintenance expenses;
Methodology
1. Tariff Options
The electricity purchase tariffs for renewable energy projects, and wind power
in particular are calculated based on the projected cash flow of a generic 1 mW
plant over 25 years of useful life, including ROE at 10% P.A for the first 10
years, and 24% P.A from year 11 onwards.
For wind energy projects, India adopts constant tariffs over 13 years. A single all
2. Tariff Components
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Capital Investment
Capacity Utilization Factor
Operation and Maintenance expenses
Insurance cost
Debt-Equity ratio
Term of Loan and Interest
Life of plant and machinery
Return on Equity
Depreciation rate applicable
Interest and Components of Working Capital
3. Tariff Design
In terms of Regulation 10 of the RE Tariff Regulations, the tariff design for
renewable energy generating stations is as under: 1) The generic tariff shall be
determined on levellised basis for the Tariff Period. Provided that for
renewable energy technologies having single part tariff with two components,
tariff shall be determined on levellised basis considering the 6 year of
commissioning of the project for fixed cost component while the fuel cost
component shall be specified on year of operation basis. 2) For the purpose of
levellised tariff computation, the discount factor equivalent to Post Tax
weighted average cost of capital shall be considered. 3) Levellisation shall be
carried out for the useful life of the Renewable Energy project while Tariff
shall be specified for the period equivalent to Tariff Period.
Levelised Tariff
Levelised Tariff = (Arithmetical Average of Tariff over the life of the
plant/PPA) / Discount Factor
Discount Factor
Discount factor is the post tax weighted average cost of the capital on the basis
of normative debt: equity ratio (70:30) specified in the Regulations
Capital Cost
Capital cost is the total project cost, inclusive of all capital works like plant
and machinery, civil works, erection and commissioning, financing and
interest during construction, and evacuation infrastructure up to interconnection point.
--- Capital cost for wind energy project shall include wind turbine generator
including its auxiliaries, land cost, site development charges and other civil
works, transportation charges, evacuation cost up to inter-connection point,
financing charges and IDC
Useful Life
Wind energy 25
Control Period
Five years, first year being 2012-13 tariff determined for the RE projects
commissioned during the control period shall continue to be applicable for the
entire duration of the tariff period as specified in Regulation 6 of the RE Tariff
Regulations.
Tariff Period
13 years minimum
Interest On Loan
Sub-Regulation (1) of Regulation 14 of the RE Regulations provides that the
loan tenure of 12 years is to be considered for the purpose of determination of
tariff for RE projects. Sub-Regulation (2) of the said Regulation provides for
computation of the rate of interest on loan as under:
(a) The loans arrived at in the manner indicated in the Regulation 13 shall
be considered as gross normative loan for calculation for interest on loan. The
normative loan outstanding as on April 1st of every year shall be worked out
by deducting the cumulative repayment up to March 31st of previous year
from the gross normative loan.
(b) For the purpose of computation of tariff, the normative interest rate shall
be considered as average State Bank of India (SBI) Base rate prevalent during
the first six months of the previous year plus 300 basis points.
(c) Notwithstanding any moratorium period availed by the generating
company, the repayment of loan shall be considered from the first year of
commercial operation of the project and shall be equal to the annual
depreciation allowed.
Average Base rate for first six months of FY 14-15 10.00%
Depreciation
Regulation 15 of the RE Tariff Regulations provides for computation of
depreciation in the following manner:
"(1) The value base for the purpose of depreciation shall be the Capital Cost of
the asset admitted by the Commission. The Salvage value of the asset shall be
considered as 10% and depreciation shall be allowed up to maximum of 90%
of the Capital Cost of the asset.
(2) Depreciation per annum shall be based on Differential Depreciation
Approach' over loan period beyond loan tenure over useful life computed on
Straight Line Method. The depreciation rate for the first 12 years of the
Tariff Period shall be 5.83% per annum and the remaining depreciation shall
be spread over the remaining useful life of the project from 13th year onwards.
(3) Depreciation shall be chargeable from the first year of commercial
operation. Provided that in case of commercial operation of the asset for part
of the year, depreciation shall be charged on pro rata basis".
O&M expenses
(a) Wind Energy: Regulation 27 of RE Tariff Regulations provides that the
normative O&M expenses for the first year of the control period (i.e. 2012-13)
as ` 9 lakh per MW and shall be escalated at the rate of 5.72% per annum over
the tariff period for determination of the levellised tariff. Accordingly, the
O&M cost norm for wind energy as ` 10.63 Lakh/MW for FY 2015-16.
Subsidy
Regulation 22 of the RE Tariff Regulations provides as under:
The Commission shall take into consideration any incentive or subsidy
offered by the Central or State Government, including accelerated
depreciation benefit if availed by the generating company, for the renewable
energy power plants while determining the tariff under these Regulations.
Provided that the following principles shall be considered for ascertaining
income tax benefit on account of accelerated depreciation, if availed, for the
purpose of tariff determination:
i) Assessment of benefit shall be based on normative capital cost,
accelerated depreciation rate as per relevant provisions under Income Tax
Act and corporate income tax rate.
ii) Capitalization of RE projects during second half of the fiscal year. Per unit
benefit shall be derived on levellised basis at discount factor equivalent to
Post Tax weighted average cost of capital.
3. Tariff Calculation
The net/Gross generated value of electricity is computed on 1MW. The NPV of
total cash outflow over 25 years/ NPV of energy generated is taken for tariff
consideration.
StatewiseFeedInTariffs
ComparisonofFeedInTariffsofStates:
UnderProgressMaharastraandTamilNaduCovered.