Documente Academic
Documente Profesional
Documente Cultură
Pumping concrete
Prepared by: Laing Design and DevelopmentCentre
Special considerations
Figure 1: A pump with boom-supportedpipeline.
or 2
Hydraulic
1 or 2
Cylinders
Weight
Heavy
Dependson size
Mounting
Skid, trailer
Skid,lorry or trailer
Mobility
Usually mobile,
Usually mobile,
flexibledischarge
flexible discharge
Large volumes,
long distances
Average contracts
where sufficientsize
of pours, difficult
access, largesingle
pours
Maximum
pumping
rate
23 m3Ih
70 m3/h, depends on
Typical
pipeline
diameter
75 mm
Use
400 m horizontal
100 m vertical
Flow
Steady
Pulsating
Economics of pumping
Pumping concrete can be economical in many circumstances,
and can be considered for the whole range of pours from 5 to
5000 m3.
Savings due to reduced construction time are often greater
than savings due to reduced handling costs. Other factors to
consider may include dismantling, maintenance, attendance,
and hire of other equipment such as cranes, formwork and
vibrators.
Hydraulic pumps
The most commonly used pumps are hydraulically operated.
They are lighter than mechanical types and can be lorry
mounted. They are therefore highly mobile and are used for
many jobs in building and civil engineering. The use of quick
release couplings enables rapid assembly and dismantling,and
most lorry-mounted pumps are equipped with articulated
booms with permanently rigged pipelines which can reach to
heightsof up to 36 m without theaddition of extra pipeline. The
most common diametersof pipeline used are 100 and 125 mm.
However,small diameters of 75 mm or less can be used in highly
congested situations. For diameters of less than 75 mm, an
aggregate size of less than 20 mm may be required.
Hydraulic pumps are smoother in operation than the
mechanical types. They impart a steady speed and consequently
steady pressure to the concrete,thusavoidingthe high pressure
peaks inherent with mechanical drive. They are therefore less
likely to suffer from blockages.
The combination of smootheroperationand higher velocities
in small bore pipes improves the vertical pumping distance to
about a quarter the horizontalpumpingdistance as compared to
only a tenth for mechanical pumps. Vertical pumpingheightsin
excess of 300 m can be achieved in very special circumstances.
Hydraulicoperation has a furtheradvantage in that pumping
rates can be controlled from zero to maximum by varying the
delivery of the hydraulic drive pump. Outputs as high as
125 mi/h are claimedfor the larger twin cylinder models.
In practice, outputwill be highly dependenton factors such as
available labour, pumping distance, height, pumpability of the
concreteand continuity of concretesupply. Outputs are usually
less than those quoted by manufacturers for pumping
equipment.
cylinder
discharging
cylinder
charging
valve closed
valveopen
hopper
hopper
valveclosed
valve open
output
Figure 2. A typical twin cylinderhydrau(icmobile
pump.
CumulativeO/
wateremitted
.1.
.J
30
40
.1
50
Time seconds
Figure 3. Comparative curve for the bleed test to
determine the pumpabilityof concrete.
Concrete under investigation is placed in a specially
designed cylinderandpressurized. The rate at which
waterbleeds from the concrete is then measured and
plotted on a graph. The resultingcurve is compared
with Figure 3 and, it lies in the centralzone,
probably indicates that the mix will be pumpable. If
the curvelies outside the 'pumpable'zone the mix
can be redesigned accordingly.
if
pressure
P
friction F
Figure 4: Representation
of plugflow.
consulted.
P>R+F
where
pump pressure
Cementcontent
High
Low
Low
High
Aggregatevoid content
1.
2.
3.
4.
Decreasecement content.
Adjustaggregate coarse/fine ratio to increase voids.
Increase water content.
Use 'wetting agent' admixture.
2.
3.
4.
o 0.
0
--
320 m3 maximum.
42%
COG,
a,
CO
important pours.
For pumping over very long distances or when pumping to
great heights, twopumps may be required. Twopumps working
at optimum pressure are better than one pump working at
maximum pressure.
With some machines, the remote control fitted enables safe
and efficient working of the pump with the pump operatorup to
40 m fromthe pump itself. This enables the operatorto be better
concrete.
CO
x
CO
0
Waiting for
concrete
.0
Remixln on site
Workability wrong
Blockages
4%
Postioning trucks
10%
3%
3%
0)
0-
0
CO
C.)
13%
1/o
8j
150200
mm
thick Suspended
Large 1 m thick
raft
column
foundation
slab.
Tamped
finish
Control input
to pump
Control pump
Extend and
inspectpipeline
Direct output
23
10
25
Vibrateconcrete
Distribute and
finish
Placing rate m3/h
(for tamping)
2025
Pumplocation
Position the pump or pumps so that pipelines are as short as
possible, need as little repositioning as possible, and are as
straight as possible.
0
0
0a,
Angleof bend
90
450
30
22.5
'pump
Equivalent
horizontal
distance, m
Equivalent vertical
distance, m
12
0.7
0.5
6
4
relief valve
Figure 9: Pumpingdownhill.
The pipeline
Arrange for all pipes, other than fixed booms, to be either
horizontalor vertical.Theconcretein thepipemaytend to bleed
and, if the pipes are inclined, the water will tend to run down
whenever movementstops. Thiswill cause the concreteto lose
water at the top and a blockage may occur.
Gravity assists the pumping of concrete downhill but air
pockets may form at the highest point of the pipeline as the
concrete falls away from it. Include slight bends in the line to
increase reistance and, where possible, slope the pipeline
upwards a little at the end of the descending section.
Sometimes, particularlywhen large volume pumps are used at
full load, pipelines need to be anchored at bends to restrict
movement. These pulsating movements must not be allowed to
affect the formwork or reinforcement.
Pipes should never be added. Pipework should always be
broken back towards the pump, starting at thefarthestpointfirst
and finishing close to the pump. Pipes removed during
concretingmustbe cleared of concreteand cleaned. Inspection
of all joints for grout leaks is carried out while the pump is
running and again when pumpinghas stopped for the day,by the
pump operator.
If the pipeline is uncoupledat any pointto pump to another
placing point, make sure that the concrete remaining in the
unused pipe beyond the joint is not allowed to harden. Do not
uncouple anypipeline without the pump operator'spermission.
Pumping
If
Discharge
lengths.
14
1.
10
iIiIiI1iiIii:
Cleaning out
For short pipelines and boom-supportedpipelines much of the
concrete can be drawn back into the hopper by reversing the
pump. This makes cleaning easier. Alternatively pipes can be
disconnected and emptied of concreteindividually.Empty pipes
can then be washed with a hose.
Sometimes the air or water line can be conveniently
connectedto the discharge end of the pipe. The concrete can
then be discharged close to the pump where it can usually be
more easily removed. In addition, the cleaning plug can be
10
12
14
directed onto the ground near the pump and is less likely to be
lost.
Safety
References
1.
2.
Further reading
BRITISH CONCRETE PUMPING ASSOCIATION.
Acknowledgements
Theassistanceof the Plant AdvisoryService ofJohn Laing ConstructionLtd and of
the British Concrete Pumping Association in finalizing this digestis gratefully
acknowledged.
CI/SfB
q4
D3i
LDC 666.97.033.13
Concrete Society Digests are written by indinidoal aothors, onder the
editorial control of a Working Party of the Edocation, Training and
Publications Steering Groop.The editor forthisDigest was P. K. Donaldson.
Corrent members of the Working Party: R. Iatt IChairmanl, G. 1.
Blackledge, R. Blundell.I. N. Clarke (Secretaryl, E F. Homphries. F. V.
fenkins,S. H. Perry. Formermembers: S. R.ArnoldlChairmanl.l.D.Dewar,
P. K. Donaldson, D. M. Lambert.
j.
ISBN0721013066
tSSN0266-383X
Published by The Concrete Society
Devon House, 12-15 DartmouthStreet, LoodonSW1H 9BL
Designed and printed by the Cementand Concrete Association
Wesham Springs, Slough 5L3 6P1
Furthercopiesmay be obtainedfrom:
Publications Distribution. Cement and Concrete Association
Wesham Springs, Slough 5L3 6Ff,
quotingreference number53,045
Price GroupC52