Documente Academic
Documente Profesional
Documente Cultură
Applied Energy
journal homepage: www.elsevier.com/locate/apenergy
School of Electrical Engineering and Computer Science, Queensland University of Technology (QUT), Brisbane 4000, Australia
Department of Electrical Engineering, Hong Kong Polytechnic, Hunghom, Kowloon, Hong Kong
c
Department of Electrical, Electronic and Computer Engineering, University of Pretoria, South Africa
b
h i g h l i g h t s
Community based residential distribution grid reinforcement.
Overvoltage problems due to large integration of rooftop PV.
Probabilistic estimation of intermittent PV generation.
Impact of feeder R/X ratio is analysed.
Coordinated control of PVs and Battery Energy Storage systems to address the voltage violation.
a r t i c l e
i n f o
Article history:
Received 6 November 2013
Received in revised form 6 August 2014
Accepted 7 August 2014
Available online 27 August 2014
Keywords:
Distribution networks
Photovoltaic (PV)
Low Voltage (LV) line
Droop control
Battery Energy Storage (BES)
a b s t r a c t
Large number of rooftop Photovoltaics (PVs) have turned traditional passive networks into active networks with intermittent and bidirectional power ow. A community based distribution network grid
reinforcement process is proposed to address technical challenges associated with large integration of
rooftop PVs. Probabilistic estimation of intermittent PV generation is considered. Depending on the network parameters such as the R/X ratio of distribution feeder, either reactive control from PVs or coordinated control of PVs and Battery Energy Storage (BES) has been proposed. Determination of BES capacity
is one of the signicant outcomes from the proposed method and several factors such as variation in PV
installed capacity as well as participation from community members are analyzed. The proposed
approach is convenient for the community members providing them exibility of managing their integrated PV and BES systems.
2014 Elsevier Ltd. All rights reserved.
1. Introduction
Large scale renewable generation such as Photovoltaics (PVs),
wind, hydro, geothermal plants are usually installed in remote
locations from load centers which require reinforcements to transmission networks. Signicant research works have been carried for
transmission reinforcement in terms of optimization between cost
incurred with renewable generation and network expansion [13].
Various methods such as mixed integer linear programming,
dynamic programming, genetic algorithms and simulated annealing have been used in the past [48]. Studies related to distribution
network reinforcements, whereas, had attracted less attention in
the past due to simplistic radial passive networks [9,10].
291
of electricity from the network and receiving the payments for the
exported energy into the grid.
Installation of rooftop PVs can be an alternative to cater increasing peak demand deferring the need for immediate grid reinforcement [18]. It is also capable of providing ancillary services such as
voltage regulation and reactive power compensation [19,20].
Although large integration of PVs in the distribution systems does
provide signicant benets to Distribution Network Service Providers (DNSPs) as well as end users, it does bring few technical
challenges. Active generation from PVs has degraded the voltage
prole of the feeder. Moreover, intermittent nature of PV generation due to irregular solar insolation makes it difcult to forecast
the generation leading to abnormal system operation. Proper distribution reinforcement technique is required to address these
issues.
Authors in [21] have determined the optimum position and
capacity of distributed generators in a radial feeder. Their objective
is to maximize the capacity considering the technical challenges
from DNSPs perspective. The network reconguration and minimizing the active power losses using optimization methods are
elaborated in [2225], which are deterministic in nature and do
not consider customer participation. The variable participation of
community members in the reinforcement process is important
for the reliable operation.
In this paper, a new community based grid reinforcement methodology is proposed to allow higher level of rooftop PV installations. The most prominent technical challenge associated with
high level penetration of PV, overvoltage problem, is also
addressed. To ensure acceptable voltage prole, Reactive Capability of PV Inverter (RCPVI) is used. However, RCPVI may not be
effective in highly resistive networks. Moreover, limiting the real
power generation or installation capacity of PV to prevent overvoltage problem may not be a cost effective option. Such capacity
limitation and/or real power sacrice will result in revenue loss for
customers and active power generation loss for DNSPs. Instead of
capacity limitation or power curtailment, distributed energy storage is proposed in this paper. The development of grid reinforcement approaches by introducing storage system is proposed in
[26] using capacitor banks [27] and super capacitors [28]. Super
capacitors have high power density and are suitable during intermittency caused by clouds transients. However, these capacitor
banks have fast charging-discharging cycles which, over a longer
period of time, would lead to high loss factors [29]. Battery Energy
Storage (BES) systems, whereas, is shown to have promising future
with increasing applications in distribution systems [30].
The proposed method aims to resolve both over voltage problems due to high penetration of PVs and low voltage problems
due to peak loading. RCPVI and Battery Energy Storage (BES) are
proposed as a way to improve the voltage prole. The effectiveness
of RCPVI alone for voltage improvement may be limited by the R/X
ratio of the feeder. Therefore, an Integrated PV and Battery Storage
(IPVBS) system is proposed for individual community member
depending on the feeder characteristic. In the community based
approach, decentralized storage is proposed and hence the
improvement in voltage prole is dependent on community participation. The intermittent characteristic of PV generation using
probabilistic analysis is considered. The efcacy of the proposed
methodology depends on the active participation of community
members (end users).
The paper is organized as follows: Section 2 describes the community based grid reinforcement approach. The analysis of two
decisive criteria is explained in Section 3. Section 4 describes the
test network and the associated simulation results are shown in
Section 5. Section 6 presents economic analysis followed by conclusion in Section 7.
Start
Take all necessary network information (feeder no, bus
no, R/X ratio, load profile, PV generation profile) as input
Calculate Net Generation (PV generation-load)
for every hour for the particular year
Calculate Pr() using probabilistic estimation
Yes
Is Pr()0.5?
No
No
Use only
RCPVI
Select the worst case scenario from the PV generation and load
profile, run the load flow using mvd, Vcri to determine the BES sizing
Get the required BES sizing for all the houses
End
292
#1
"
J1 J2
DP Dd
DV
DQ
J3 J4
V
where J1, J2, J3, J4 are the elements of Jacobian matrix; Dd and DV
are the vectors of voltage-angle and voltage-magnitude corrections
respectively; DP and DQ are the vectors of real power and reactive
power mismatches respectively. Using Jacobian following sensitivity matrix is obtained:
0 jVj
J1 jVjJ2
J3 jVjJ4
" Dd
1
DP
DV
DP
Dd
DQ
DV
DQ
#
2
Q PV generation
PPV generation=S*PF
Q
Qno PV generation
V bh;max 1
DPreduced;max P
i1;...;H DV i
j1;...;H DP j
mv d
max
DPreduced;max
V bh
DP reduced;max V bh 1
DV i
j1;...;H DPj
DPh;reduced mv d V bh 1
mmf
DV=DPmax
RX RX cri
aa PrfNetGenN ag
PrfNetGenNm g
Nm
X
iN1
Nm
X
Prm
i aa
10
iN1
293
CI
11
VI
12
VInormalized
VI
VImax
13
CT can be modeled as inversely proportional to CI and proportional to VInormalized and can be represented as a linear combination
of CI inverse and VInormalized as shown in (14)
CT 0:5
1
0:5 VInormalized
CI
14
NetGenN
GHI
CT
15
Distribution type
t2 = 3
0<x<1
t2 < 3
x<0
t2 > 3
Else
294
DjVj
J1 J2 DP
J3 J4 DQ
Dd
16
K minfN : NetGenN 2 ng
17
18
Fd 2
Controller
11 kV/240 V
Fd 4
Fd
Fd
Fd 6
5
d
295
Power (kW)
12
18
24
100
90
80
70
60
50
40
30
20
10
0
1 minute
Time (Hour)
1 hour
Fig. 6. Percentage of different types of days using CI and VI using 1 min, 15 min and
1 h solar data.
1.12
House 1/2
House 11/12
1.06
0.94
0.88
1
13
19
Time (Hour)
Rural Voltage (pu)
15 minute
1.12
1.06
1
0.94
0.88
1
13
19
Time (Hour)
Fig. 5. 24 Hour voltage prole for urban (top) and rural (bottom) case in normal
situation during summer.
5. Simulation results
Simulation results after applying Community Based Grid Reinforcement approach in the test network are demonstrated in this
section. This section includes the probabilistic estimation of PV
generation considering the indexes associated with cloud transient
and determination of the RXcri. After these analyses, required BES
sizing are determined considering several factors such as participa-
296
0.16
f (x)
0.14
0.12
0.1
0.08
0.06
0.04
2
0.02
0
-2
4
1
x
Histogram
90
60
80
50
70
40
60
50
30
40
Loading at maximum Q injection
Loading at zero Q injection
Incremental Loss
20
20
10
10
0
0
3
R/X ratio
Fig. 8. Permitted loading and incremental loss variation with R/X ratio.
Q PV
max
6 kVAR;
13
15
14
3.46
15
4.25
Table 2
Modication factor value for different R/X ratio.
65
11
100
R/X ratio
30
Pearson 5 (3P)
19
R/X ratio
mmf
11
1.56
12
2.12
13
2.75
increase in the BES sizing in observed for feeders with R/X ratio
beyond 10. High R/X lines have higher losses and hence worst voltage prole. A modication factor (mmf) is multiplied with the droop
coefcient (mvd) to calculate the required BES sizing. mmf for higher
R/X ratio is listed in Table 2.
Required BES sizing depends on the participation of the community members as well. If some of the community members do
not wish to participate in the grid reinforcement process, other
members will need to install higher capacity of BES. This capacity
of BES increases with the decreased participation from the community members as shown in Fig. 10.
BES capacity also varies with the position of the non-participating houses. Fig. 11 shows the required BES capacity in the network
if the position of two non-participating houses changes from bus 1
to bus 6 (end of the feeder). With the increase in distance along the
feeder, BES capacity from other houses increases. If the houses
towards the end of the feeder choose not to participate in the grid
reinforcement process, the network would require higher BES
capacity from rest of the houses to maintain the acceptable voltage
prole. R/X ratio beyond 10 requires mmf.
The effect of different capacity of PV inverters on the required
BES capacity for each house is summarized in Table 3.
With the decrease in the total generation, BES capacity also
decreases. The total generation of 72 kW from the residential PV
(6 kW * 12 houses) require total BES capacity of 22.4 kW h
(1.87 kW h * 12 houses).
297
4
3.5
2.5
R/X=5
R/X=6
R/X=7
R/X=8
R/X=9
R/X=10
2
1.5
0.5
25
35
45
55
65
House 11/12
0.94
7
13
19
Time (Hour)
0
15
House 1/2
75
85
1.06
1.06
0.94
1
13
19
Time (Hour)
Fig. 12. 24 Hour voltage prole for urban (top) and rural (bottom) case with PV and
BES system.
6
5.5
R/X=5
R/X=6
R/X=7
R/X=8
R/X=9
R/X=10
4.5
4
3.5
3
2.5
2
1.5
1
0.5
0
Bus 1
Bus 2
Bus 3
Bus 4
Bus 5
Bus 6
distance i.e. nearly 75% of feeder [39]) in Fig 3. For the given network, 65 kVAR is required, which requires investment of $3500
3750 from the DNSP (assuming $5055/kVAR [40]). Whereas, considering ZnBr based BES system were to be used with PV systems,
each house holder will have to invest $670, requiring a total of
$8040 for a given test network (Flow batteries are the most appropriate batteries to be used for these purposes due to their continual
efciency with deep discharging and costs around US $335/kW h
[41]) .
Hence, although one time investment in D-STATCOM is less
when compared with total investment in BES ($8040), however,
BES provides long term technical benets in terms of peak shaving.
D-STATCOM can regulate voltage variation with reactive compensation only and cannot supply real power during peak demand.
Moreover, new technological innovation in the batteries may bring
down cost signicantly, making the proposed scheme economically attractive.
7. Simulation results with real network data
Table 3
BES capacity with different set of PV generations for all the houses.
House
H 1/2
H 3/4
H 5/6
H 7/8
H 9/10
H 11/12
Total
PV gen (kW)
BES (kW h)
PV gen (kW)
BES (kW h)
PV gen (kW)
BES (kW h)
PV gen (kW)
BES (kW h)
PV gen (kW)
BES (kW h)
5.48
1
5.21
0.9
2.66
0.8
0.09
0.4
2.34
0.3
0.91
1
2.51
0.9
0.64
0.8
0.26
0.4
1.45
0.3
4.95
1
2.4
0.9
5.77
0.8
1.01
0.4
2.42
0.3
3.23
1
1.56
0.9
0.03
0.8
3.89
0.4
0.58
0.3
5.98
1
4.8
0.9
4.65
0.8
4.39
0.4
0.79
0.3
0.47
1
2.59
0.9
4.9
0.8
3.89
0.4
5.65
0.3
42.05
12
38.13
10.8
37.3
9.6
27.07
4.8
26.47
3.6
6. Economic perspective
Selection of a suitable battery type plays an important role to
justify the economic benet of integrating PV with BES system
for voltage control purposes over conventional techniques such
as D-STATCOM.
The optimum reactive power requirement to eliminate voltage
violations for the test network is determined iteratively using load
ow studies by placing D-STATCOM at the 5th bus (two third the
298
Fig. 13. Rural network (collected from an Australian DNSP in South-East Queensland region).
Table 4
Network parameter list for the selected rural network.
To site
Conductors
P17074-F
P6130-J
P64240-D
P17072-H
P14509-E
P17071-G
P6138-G
P6139-F
P13848-G
P6137-I
P42377-C
P6135-J
P7248-H
P6134-H
P17075-F
P17074-F
P6130-J
P64240-D
P17072-H
P14509-E
P17071-G
P6138-G
P6139-F
P13848-G
P6137-I
P42377-C
P6135-J
P7248-H
1.06
1.02
0.98
0.94
Stored kWh
Supplied kVAR
Voltage (pu)
From site
LV
LV
LV
LV
LV
LV
LV
LV
LV
LV
R/X ratio
62
18
38
38
76
64
54
94
50
72
104
78
38
78
0.90
0.34
0.34
0.34
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.34
0.90
0.23
0.31
0.31
0.31
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.31
0.23
0.0555
0.0060
0.0128
0.0128
0.0681
0.0573
0.0484
0.0842
0.0448
0.0645
0.0931
0.0699
0.0128
0.0699
0.0140
0.0056
0.0117
0.0117
0.0171
0.0144
0.0122
0.0212
0.0113
0.0162
0.0234
0.0176
0.0117
0.0176
3.98
1.09
1.09
1.09
3.98
3.98
3.98
3.98
3.98
3.98
3.98
3.98
1.09
3.98
12
18
24
12
18
24
12
18
24
6
1
-4
10
5
0
Time (Hour)
Fig. 14. Voltage prole (for connected to bus P6134-H), supplied reactive power
prole and stored energy prole.
9.0010.00 h), excess generation from PV is started to store in corresponding BES. In parallel, reactive power is absorbed by PV inverter in a coordinated way to limit the voltage in peak generation (12
noon). This stored energy is supplied to the corresponding house in
coordination with reactive power supply from PV inverter to keep
the voltage within lower acceptable limit during peak demand
time (19.00 h). Different houses have different requirement of
reactive power absorption/supply (shown in 2nd plot, Fig. 14),
however the accumulated energy stored plot is almost same for
all the houses (shown in 3rd plot, Fig. 14) to ensure same BES
sizing.
On the other hand, Fig. 15 has two plots showing the hourly
stored energy (between 9.00 and 16.00 h) and hourly supplied
energy (between 17.00 and 23.00 h) for the BES connected with
bus P6134-H. The plots show that all the stored energies are supplied back to corresponding hour on daily basis.
From all these gures the conclusion can be made that, voltage
prole is perfectly maintained for a rural network with signicant
Hourly Supplied
Energy (kWh)
f x; a; b
expb=x c
bCax c=ba1
References
1
0
12
18
24
18
24
Time (Hour)
Hourly Supplied
Energy (kWh)
299
12
Time (Hour)
Fig. 15. Hourly stored energy and hourly supplied energy prole.
f x; a; b
expb=x
bCax=ba1
where a and b are shape parameter and scale parameter respectively. Ca is the gamma distribution of a. The location parameter
(c) needs to be incorporated in this distribution to take care of
the skewness. Thus the distribution becomes the Pearson 5 distribution (Inverse Gamma Distribution with location parameter).
The PDF is now dened over the range c < x<+1 as,
300
[36] Glover JD, Sarma MS, Overbye T. Power system analysis and design. 5th
ed. Cengage Learning; 2012.
[37] Energex Regulatory Proposal for the period July 2010June 2015 [July, 2009].
<http://www.energex.com.au/__data/
assets/pdf_le/0010/31789/
ENERGEX_s_Regulatory_Proposal_2010-2015.pdf>.
[38] University of Queensland (UQ) solar Photovoltaic data. <http://
uqld.smartersoft.com.au/user/reportEnergy.php>.
[39] Shahnia F, Majumder R, Ghosh A, Ledwich G, Zare F. Voltage imbalance
analysis in residential low voltage distribution networks with rooftop PVs.
Electr Power Syst Res 2011;81(9):180514.
[40] Molinas M, Suul JA, Undeland T. Low voltage ride through of wind farms with
cage generators: STATCOM versus SVC. IEEE Trans Power Electron
2008;23(3):110417.
[41] Akhil A. Evaluating utility owned electric energy storage systems: a
perspective for state electric utility regulators. Sandia handbook. DOE/EPRI
2013 electricity storage handbook in collaboration with NRECA.