Participant workbook
CAPM workbook
Contents
Section 1: ITTO matrix................................................................................................ 3
Type 1 Matrix: Process group versus Knowledge area process................................4
Type 2 Matrix: Process group versus Knowledge area process................................6
Type 1 Matrix: Integration knowledge area.............................................................8
Type 2 Matrix: Integration knowledge area...........................................................10
Type 1 Matrix: Scope knowledge area...................................................................12
Type 2 Matrix: Scope knowledge area...................................................................14
Type 1 Matrix: Time knowledge area.....................................................................17
Type 2 Matrix: Time knowledge area.....................................................................20
Type 1 Matrix: Cost knowledge area......................................................................24
Type 2 Matrix: Cost knowledge area......................................................................26
Type 1 Matrix: Quality knowledge area.................................................................28
Type 2 Matrix: Quality knowledge area.................................................................29
Type 1 Matrix: HR knowledge area........................................................................32
Type 2 Matrix: HR knowledge area........................................................................33
Type 1 Matrix: Communication knowledge area....................................................35
Type 2 Matrix: Communication knowledge area....................................................36
Type 1 Matrix: Risk knowledge area......................................................................38
Type 2 Matrix: Risk knowledge area......................................................................40
Type 1 Matrix: Procurement knowledge area.........................................................43
Type 2 Matrix: Procurement knowledge area.........................................................45
Type 1 Matrix: Stakeholder knowledge area..........................................................48
Type 2 Matrix: Stakeholder knowledge area..........................................................49
Copyright protected
2 | Page
CAPM workbook
Copyright protected
3 | Page
CAPM workbook
Closing
gControllin
Execution
Knowledge Processes
Planning
Knowledge
Areas
Initiation
Scope
Time
Cost
Estimate costs
Determine budget
Control costs
Plan quality management
Quality
Copyright protected
4 | Page
CAPM workbook
Plan HR management
Human
Resources
Communicati
on
management
Plan communications
Manage Stakeholder expectations
Report performance
Plan risk management
Identify risks
Risk
Procurement
Conduct procurements
Control procurements
Close procurements
Identify SH
Stakeholder
Plan SH management
Manage SH engagement
Control SH engagement
Copyright protected
5 | Page
CAPM workbook
Closing
gControllin
Execution
Knowledge Processes
Planning
Knowledge
Areas
Initiation
x
x
x
Integration
x
x
x
x
x
Scope
x
x
x
x
x
x
x
Time
x
x
x
x
x
Cost
x
x
x
x
Quality
x
x
Copyright protected
6 | Page
CAPM workbook
x
x
Human
Resources
x
x
x
Communicati
on
management
x
x
x
x
x
Risk
x
x
x
x
Procurement
x
x
x
x
Stakeholder
x
x
x
Copyright protected
7 | Page
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Agreements
Project statement of work
Business case
Develop
project
charter
Develop
project
management
plan
Direct &
manage
project work
Monitor &
control
project work
Copyright protected
8 | Page
CAPM workbook
Validated changes
Work performance information
Enterprise environmental factors
Organizational process assets
Expert Judgment
Analytical techniques
Project management information
systems
Meetings
Change Request
Work performance reports
Project Document updates
Project Management Plan updates
Project management plan
Work performance reports
Change requests
Enterprise environmental factors
Perform
integrated
change
control
Close project
or phase
Expert Judgment
Analytical techniques
Meetings
Final PSR transition
OPA updates
Copyright protected
9 | Page
CAPM workbook
Develop
project
charter
Output
ITTO components
T&T
KA processes
Inputs
Develop
project
management
plan
Direct &
manage
project work
Monitor &
control
project work
Copyright protected
10 | P a g e
CAPM workbook
Perform
integrated
change
control
Close project
or phase
Copyright protected
11 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Plan scope
management
Collect
Requirements
Define Scope
Project Charter
Requirements documentation
Organizational process assets
Scope management plan
Product analysis
Alternatives generation
Expert judgment
Copyright protected
12 | P a g e
CAPM workbook
Facilitated workshops
Project scope statement
Project documents updates
Scope management plan
Project scope statement
Requirements documentation
Create Work
Breakdown
Structure (WBS)
Validate scope
Inspection
Group decision making techniques
Accepted deliverables
Change requests
Work performance information
Project documents updates
Project Management Plan
Work performance data
Requirements documentation
Requirements traceability matrix
Organizational process assets
Control Scope
Variance analysis
Work performance information
Organizational process assets updates
Change requests
Project management plan updates
Project documents updates
Copyright protected
13 | P a g e
CAPM workbook
Plan scope
management
Output
ITTO components
T&T
KA processes
Inputs
Collect
Requirements
Define Scope
Copyright protected
14 | P a g e
CAPM workbook
Create Work
Breakdown
Structure (WBS)
Validate scope
Control Scope
Copyright protected
15 | P a g e
CAPM workbook
Copyright protected
16 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Plan Schedule
management
Define Activities
Expert judgment
Decomposition
Rolling wave planning
Activity list
Activity attributes
Milestone list
Schedule management plan
Activity list
Project scope statement
Enterprise environmental factors
Activity attributes
Sequence
Activities
Milestone list
Organization process assets
Precedence Diagramming Method
(PDM)
Leads and lags
Dependency determination
Project schedule network diagrams
Project documents updates
Estimate
Copyright protected
17 | P a g e
CAPM workbook
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
Copyright protected
18 | P a g e
CAPM workbook
Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity duration estimates
Project scope statement
Risk register
Project staff assignments
Resource breakdown structure
Schedule network analysis
Critical path method
Schedule compression
Resource optimization techniques
Modeling techniques
Critical chain method
Leads and lags
Scheduling tool
Project schedule
Schedule data
Schedule baseline
Project documents updates
Project calendars
Project management plan updates
Control
Schedule
Copyright protected
19 | P a g e
CAPM workbook
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Plan Schedule
management
Output
ITTO components
T&T
KA processes
Inputs
Define Activities
Sequence
Activities
Copyright protected
20 | P a g e
CAPM workbook
Estimate
Activity
Resources
Estimate
Activity
Durations
Copyright protected
21 | P a g e
CAPM workbook
Develop
Schedule
Control
Schedule
Copyright protected
22 | P a g e
CAPM workbook
Copyright protected
23 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Plan cost
management
Estimate Costs
Parametric estimating
Three point estimates
Project management software
Vendor bid analysis
Reserve analysis
Cost of quality
Expert judgment
Group Decision Making Techniques
Activity cost estimates
Basis of estimates
Project documents updates
Determine
Budget
Copyright protected
24 | P a g e
CAPM workbook
Control Costs
Performance reviews
Project management software
Reserve analysis
Work performance information
Cost forecast
Change requests
Organizational process assets updates
Project management plan updates
Project document updates
Copyright protected
Output
ITTO components
T&T
KA processes
Inputs
25 | P a g e
CAPM workbook
Plan cost
management
Estimate Costs
Determine
Budget
Copyright protected
26 | P a g e
CAPM workbook
Control Costs
Copyright protected
27 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Plan Quality
Management
Perform
Quality
Assurance
Control Quality
Copyright protected
28 | P a g e
CAPM workbook
Quality metrics
Quality checklists
Organizational process assets
Work performance data
Approved change requests
Deliverables
Project Documents
Seven Basic Quality tools
Statistical sampling
Inspection
Approval change requests review
Quality control measurements
Validated changes
Verified deliverables
Work performance information
Change requests
Project documents updates
Project management plan updates
Organizational process assets updates
Plan Quality
Management
Output
ITTO components
T&T
KA processes
Inputs
Copyright protected
29 | P a g e
CAPM workbook
Perform
Quality
Assurance
Control Quality
Copyright protected
30 | P a g e
CAPM workbook
Copyright protected
31 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Plan Human
Resource
management
Acquire Project
Team
Negotiation
Multi criterion decision analysis
Acquisition
Virtual teams
Project staff assignments
Resource calendars
Project management plan updates
Develop Project
Team
HR management plan
Project staff assignments
Resource calendars
Interpersonal skills
Training
Personnel assessment tools
Team-building activities
Ground rules
Co-location
Recognition and rewards
Team Performance Assessments
Copyright protected
32 | P a g e
CAPM workbook
Manage Project
Team
Plan Human
Resource
management
Output
ITTO components
T&T
KA processes
Inputs
Acquire Project
Team
Copyright protected
33 | P a g e
CAPM workbook
Develop Project
Team
Manage Project
Team
Copyright protected
Output
ITTO components
T&T
KA processes
Inputs
34 | P a g e
CAPM workbook
Plan
communications
management
Manage
communication
Performance reporting
Communication technology
Communications methods
Information management systems
Project communications
Project management plan updates
Project documents updates
Organizational process assets updates
Work performance data
Issue log
Project communications
Control
communication
Copyright protected
35 | P a g e
CAPM workbook
Plan
communications
management
Output
ITTO components
T&T
KA processes
Inputs
Manage
communication
Control
communication
Copyright protected
36 | P a g e
CAPM workbook
Copyright protected
37 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Plan Risk
Management
SH register
Analytical techniques
Expert judgment
Meetings
Risk management plan
Enterprise environmental factors
Organizational process assets
Scope baseline
Project Documents
Procurement documents
Risk management plan
Activity cost estimates
Activity duration estimates
Stakeholder register
Cost management plan
Identify Risks
Perform
Qualitative Risk
Analysis
Copyright protected
38 | P a g e
CAPM workbook
Risk register
Enterprise environmental factors
Risk probability and impact assessment
Probability and impact matrix
Risk data quality assessment
Risk categorization
Risk urgency assessment
Expert judgment
Project documents updates
Organizational process assets
Enterprise environmental factors
Cost management plan
Schedule management plan
Perform
Quantitative
Risk Analysis
Plan Risk
Response
Control risks
Copyright protected
39 | P a g e
CAPM workbook
Reserve analysis
Meetings
Work performance information
Change Requests
Organizational process assets updates
Project management plan updates
Project documents updates
Plan Risk
Management
Outputs
ITTO components
T&T
KA processes
Inputs
Identify Risks
Copyright protected
40 | P a g e
CAPM workbook
Perform
Qualitative Risk
Analysis
Perform
Quantitative
Risk Analysis
Plan Risk
Response
Copyright protected
41 | P a g e
CAPM workbook
Control risks
Copyright protected
42 | P a g e
CAPM workbook
Outputs
ITTO components
T&T
KA processes
Inputs
Plan
procurement
management
Conduct
Procurements
Copyright protected
43 | P a g e
CAPM workbook
Analytical techniques
Procurement negotiations
Selected sellers
Agreements
Resource calendars
Procurement management plan
updates
Change requests
Project documents updates
Agreements
Procurement management plan
Procurement documents
Work performance reports
Approved change requests
Work performance data
Contract change control system
Procurement performance review
Control
procurements
Close
Procurements
Procurement audits
Procurement negotiations
Records management system
Closed procurements
Organizational process assets updates
Copyright protected
44 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Plan
procurement
management
Conduct
Procurements
Copyright protected
45 | P a g e
CAPM workbook
Control
procurements
Close
Procurements
Copyright protected
46 | P a g e
CAPM workbook
Copyright protected
47 | P a g e
CAPM workbook
Output
ITTO components
T&T
KA processes
Inputs
Project Charter
Procurement documents
Enterprise environmental factors
Identify
Stakeholders
Plan SH
management
Manage SH
engagement
Interpersonal skills
Management skills
Issue log
Change Requests
Project Management Plan updates
Project document updates
Organizational process assets updates
Control SH
engagement
Copyright protected
48 | P a g e
CAPM workbook
Project Documents
Information management systems
Expert judgment
Meetings
Work performance information
Change Requests
Project Management Plan updates
Project documents updates
Organizational process assets updates
Identify
Stakeholders
Outputs
ITTO components
T&T
KA processes
Inputs
Plan SH
management
Manage SH
engagement
Copyright protected
49 | P a g e
CAPM workbook
Control SH
engagement
Copyright protected
50 | P a g e