Contents
Section 1: ITTO matrix................................................................................................ 3
Type 1 Matrix: Process group versus Knowledge area process................................4
Type 2 Matrix: Process group versus Knowledge area process................................6
Type 1 Matrix: Integration knowledge area.............................................................8
Type 2 Matrix: Integration knowledge area...........................................................10
Type 1 Matrix: Scope knowledge area...................................................................12
Type 2 Matrix: Scope knowledge area...................................................................14
Type 1 Matrix: Time knowledge area.....................................................................17
Type 2 Matrix: Time knowledge area.....................................................................20
Type 1 Matrix: Cost knowledge area......................................................................24
Type 2 Matrix: Cost knowledge area......................................................................26
Type 1 Matrix: Quality knowledge area.................................................................28
Type 2 Matrix: Quality knowledge area.................................................................29
Type 1 Matrix: HR knowledge area........................................................................32
Type 2 Matrix: HR knowledge area........................................................................33
Type 1 Matrix: Communication knowledge area....................................................35
Type 2 Matrix: Communication knowledge area....................................................36
Type 1 Matrix: Risk knowledge area......................................................................38
Type 2 Matrix: Risk knowledge area......................................................................40
Type 1 Matrix: Procurement knowledge area.........................................................43
Type 2 Matrix: Procurement knowledge area.........................................................45
Type 1 Matrix: Stakeholder knowledge area..........................................................48
Type 2 Matrix: Stakeholder knowledge area..........................................................49

Copyright protected

2 | Page

CAPM workbook

Section 1: ITTO matrix

Copyright protected

3 | Page

CAPM workbook

Closing

gControllin

Develop Project Charter

Execution

Knowledge Processes

Planning

Knowledge
Areas

Initiation

Type 1 Matrix: Process group versus Knowledge area


process

Develop Project Management Plan


Integration

Direct & Manage Project Work


Monitor & Control Project Work
Perform Integrated Change Control
Close Project or phase
Plan scope management
Collect requirements
Define scope

Scope

Create Work Break Down Structure


(WBS)
Validate scope
Control Scope
Plan schedule management
Define activities
Sequence activities

Time

Estimate activity resources


Estimate activity durations
Develop schedule
Control Schedule
Plan cost management

Cost

Estimate costs
Determine budget
Control costs
Plan quality management

Quality

Perform Quality Assurance


Control quality

Copyright protected

4 | Page

CAPM workbook

Plan HR management
Human
Resources

Acquire Project Team


Develop Project Team
Manage Project Team

Communicati
on
management

Plan communications
Manage Stakeholder expectations
Report performance
Plan risk management
Identify risks

Risk

Perform qualitative risk analysis


Perform quantitative risk analysis
Plan risk responses
Control risks
Plan procurement management

Procurement

Conduct procurements
Control procurements
Close procurements
Identify SH

Stakeholder

Plan SH management
Manage SH engagement
Control SH engagement

Copyright protected

5 | Page

CAPM workbook

Closing

gControllin

Execution

Knowledge Processes

Planning

Knowledge
Areas

Initiation

Type 2 Matrix: Process group versus Knowledge area


process

x
x
x

Integration

x
x
x
x
x

Scope

x
x
x
x
x
x
x

Time

x
x
x
x
x

Cost

x
x
x
x

Quality

x
x

Copyright protected

6 | Page

CAPM workbook

x
x

Human
Resources

x
x
x

Communicati
on
management

x
x
x
x
x

Risk

x
x
x
x

Procurement

x
x
x
x
Stakeholder

x
x
x

Copyright protected

7 | Page

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Integration knowledge area

Agreements
Project statement of work
Business case
Develop
project
charter

Enterprise environmental factors


Organizational process assets
Expert Judgment
Facilitation techniques
Project Charter
Project Charter
Outputs from other processes

Develop
project
management
plan

Enterprise environmental factors


Organizational process assets
Expert Judgment
Facilitation techniques
Project Management Plan
Project Management Plan
Approved Change requests
Enterprise environmental factors
Organizational process assets
Expert Judgment

Direct &
manage
project work

Project management Information


system
Meetings
Deliverables
Work Performance data
Change Request
Project Management Plan updates
Project Document updates

Monitor &
control
project work

Project Management Plan


Schedule forecast
Cost forecast

Copyright protected

8 | Page

CAPM workbook

Validated changes
Work performance information
Enterprise environmental factors
Organizational process assets
Expert Judgment
Analytical techniques
Project management information
systems
Meetings
Change Request
Work performance reports
Project Document updates
Project Management Plan updates
Project management plan
Work performance reports
Change requests
Enterprise environmental factors
Perform
integrated
change
control

Organizational process assets


Expert judgment
Meetings
Change control tools
Approved change requests
Change log
Project Document updates
Project Management Plan updates
Project Management Plan
Accepted deliverables
Organizational process assets

Close project
or phase

Expert Judgment
Analytical techniques
Meetings
Final PSR transition
OPA updates

Copyright protected

9 | Page

CAPM workbook

Develop
project
charter

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Integration knowledge area

Develop
project
management
plan

Direct &
manage
project work

Monitor &
control
project work

Copyright protected

10 | P a g e

CAPM workbook

Perform
integrated
change
control

Close project
or phase

Copyright protected

11 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Scope knowledge area

Project Management Plan


Project Charter
Enterprise environmental factors

Plan scope
management

Organizational process assets


Expert Judgment
Meetings
Scope management plan
Requirements management plan
Project Charter
Stakeholder Register
Scope management plan
Requirement management plan
Stakeholder management plan
Interviews
Focus groups
Facilitated workshops

Collect
Requirements

Group creativity techniques


Group decision making techniques
Questionnaires & surveys
Observations
Prototypes
Benchmarking
Context diagrams
Document analysis
Requirements documentation
Requirements traceability matrix

Define Scope

Project Charter
Requirements documentation
Organizational process assets
Scope management plan
Product analysis
Alternatives generation
Expert judgment

Copyright protected

12 | P a g e

CAPM workbook

Facilitated workshops
Project scope statement
Project documents updates
Scope management plan
Project scope statement
Requirements documentation

Create Work
Breakdown
Structure (WBS)

Organizational process assets


Enterprise environmental factors
Decomposition
Expert Judgment
Scope baseline
Project documents updates
Project management plan
Requirements documentation
Requirements traceability matrix
Verified deliverables
Work performance data

Validate scope

Inspection
Group decision making techniques
Accepted deliverables
Change requests
Work performance information
Project documents updates
Project Management Plan
Work performance data
Requirements documentation
Requirements traceability matrix
Organizational process assets

Control Scope

Variance analysis
Work performance information
Organizational process assets updates
Change requests
Project management plan updates
Project documents updates

Copyright protected

13 | P a g e

CAPM workbook

Plan scope
management

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Scope knowledge area

Collect
Requirements

Define Scope

Copyright protected

14 | P a g e

CAPM workbook

Create Work
Breakdown
Structure (WBS)

Validate scope

Control Scope

Copyright protected

15 | P a g e

CAPM workbook

Copyright protected

16 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Time knowledge area

Project management plan


Project charter
Enterprise environmental factors

Plan Schedule
management

Organizational process assets


Expert judgment
Analytical techniques
Meetings
Schedule management plan
Schedule management plan
Scope Baseline
Enterprise environmental factors
Organizational process assets

Define Activities

Expert judgment
Decomposition
Rolling wave planning
Activity list
Activity attributes
Milestone list
Schedule management plan
Activity list
Project scope statement
Enterprise environmental factors
Activity attributes

Sequence
Activities

Milestone list
Organization process assets
Precedence Diagramming Method
(PDM)
Leads and lags
Dependency determination
Project schedule network diagrams
Project documents updates

Estimate

Enterprise environmental factors

Copyright protected

17 | P a g e

CAPM workbook

Organizational process assets


Activity list
Activity attributes
Resource calendars
Schedule management plan
Risk register

Activity
Resources

Activity cost estimates


Expert judgment
Alternative analysis
Published estimating data
Project management software
Bottom-up estimating
Activity resource requirements
Resource breakdown structure
Project documents updates
Schedule management plan
Activity list
Activity attributes
Activity resource requirements
Resource calendars
Project scope statement
Risk register
Resource breakdown structure

Estimate
Activity
Durations

Enterprise environmental factors


Organizational process assets
Expert judgment
Analogous estimating
Parametric estimating
Three-point estimates
Reserve analysis
Group decision making techniques
Activity duration estimates
Project documents updates

Develop
Schedule

Organizational process assets


Enterprise environmental factors
Schedule management plan
Activity list

Copyright protected

18 | P a g e

CAPM workbook

Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity duration estimates
Project scope statement
Risk register
Project staff assignments
Resource breakdown structure
Schedule network analysis
Critical path method
Schedule compression
Resource optimization techniques
Modeling techniques
Critical chain method
Leads and lags
Scheduling tool
Project schedule
Schedule data
Schedule baseline
Project documents updates
Project calendars
Project management plan updates

Control
Schedule

Project management plan


Project Schedule
Work performance data
Project calendars
Schedule data
Organizational process assets
Performance reviews
Resource optimization techniques
Project management software
Modeling techniques
Leads and lags
Scheduling tool
Scheduling Compression
Work Performance information
Schedule forecasts

Copyright protected

19 | P a g e

CAPM workbook

Change requests
Project management plan updates
Project documents updates
Organizational process assets updates

Plan Schedule
management

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Time knowledge area

Define Activities

Sequence
Activities

Copyright protected

20 | P a g e

CAPM workbook

Estimate
Activity
Resources

Estimate
Activity
Durations

Copyright protected

21 | P a g e

CAPM workbook

Develop
Schedule

Control
Schedule

Copyright protected

22 | P a g e

CAPM workbook

Copyright protected

23 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Cost knowledge area

Project Management Plan


Project charter
Enterprise environmental factors

Plan cost
management

Organizational process assets


Expert Judgment
Analytical techniques
Meetings
Cost management plan
Enterprise environmental factors
Organizational process assets
Scope Baseline
Project Schedule
Human Resource management plan
Risk register
Cost management plan
Analogous estimating
Bottom-up estimating

Estimate Costs

Parametric estimating
Three point estimates
Project management software
Vendor bid analysis
Reserve analysis
Cost of quality
Expert judgment
Group Decision Making Techniques
Activity cost estimates
Basis of estimates
Project documents updates

Determine
Budget

Cost management plan


Risk register
Scope Baseline

Copyright protected

24 | P a g e

CAPM workbook

Activity cost estimates


Basis of estimates
Project schedule
Resource calendars
Agreements
Organizational process assets
Cost aggregation
Reserve analysis
Expert judgment
Historical relationships
Funding limit reconciliation
Cost baseline
Project funding requirements
Project documents updates
Project funding requirements
Work performance data
Project management plan
Organizational process assets
Earned value management
Forecasting
To-complete performance Index (TCI)

Control Costs

Performance reviews
Project management software
Reserve analysis
Work performance information
Cost forecast
Change requests
Organizational process assets updates
Project management plan updates
Project document updates

Copyright protected

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Cost knowledge area

25 | P a g e

CAPM workbook

Plan cost
management

Estimate Costs

Determine
Budget

Copyright protected

26 | P a g e

CAPM workbook

Control Costs

Copyright protected

27 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Quality knowledge area

Project management plan


Stakeholder register
Risk register
Requirements documentation
Enterprise environmental factors
Organizational process assets
Cost-benefit analysis
Quality tools
Benchmarking

Plan Quality
Management

Cost of quality (COQ)


Design of experiments
Statistical sampling
Meetings
Additional quality planning tools
Quality management plan
Quality metrics
Quality checklists
Process improvement plan
Project documents updates
Quality management plan
Process improvement plan
Quality metrics
Project Documents
Quality control measurements

Perform
Quality
Assurance

Quality management plan & control


tools
Quality audits
Process analysis
Organizational process assets updates
Change Requests
Project Management Plan updates
Project Documents updates

Control Quality

Project management plan

Copyright protected

28 | P a g e

CAPM workbook

Quality metrics
Quality checklists
Organizational process assets
Work performance data
Approved change requests
Deliverables
Project Documents
Seven Basic Quality tools
Statistical sampling
Inspection
Approval change requests review
Quality control measurements
Validated changes
Verified deliverables
Work performance information
Change requests
Project documents updates
Project management plan updates
Organizational process assets updates

Plan Quality
Management

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Quality knowledge area

Copyright protected

29 | P a g e

CAPM workbook

Perform
Quality
Assurance

Control Quality

Copyright protected

30 | P a g e

CAPM workbook

Copyright protected

31 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: HR knowledge area

Enterprise environmental factors


Organizational process assets
Activity resource requirements
Project Management Plan

Plan Human
Resource
management

Organization charts and position


descriptions
Networking
Organizational theory
Expert Judgment
Meetings
HR management plan
HR management plan
Enterprise environmental factors
Organizational process assets
Pre-assignment

Acquire Project
Team

Negotiation
Multi criterion decision analysis
Acquisition
Virtual teams
Project staff assignments
Resource calendars
Project management plan updates

Develop Project
Team

HR management plan
Project staff assignments
Resource calendars
Interpersonal skills
Training
Personnel assessment tools
Team-building activities
Ground rules
Co-location
Recognition and rewards
Team Performance Assessments

Copyright protected

32 | P a g e

CAPM workbook

Enterprise Environmental Factors


updates
Organizational process assets
HR management plan
Project staff assignments
Issue log
Team performance assessments
Work performance reports
Observation and conversation

Manage Project
Team

Project performance appraisals


Conflict management
Interpersonal skills
Change requests
Project documents updates
Enterprise environmental factors
updates
Organizational process assets updates
Project management plan updates

Plan Human
Resource
management

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: HR knowledge area

Acquire Project
Team

Copyright protected

33 | P a g e

CAPM workbook

Develop Project
Team

Manage Project
Team

Copyright protected

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Communication knowledge area

34 | P a g e

CAPM workbook

Project management plan


SH register
Enterprise environmental factors
Organizational process assets

Plan
communications
management

Communications requirements analysis


Meetings
Communications technology
Communication models
Communication methods
Communication management plan
Project documents updates
Communications management plan
Work performance reports
Organizational process updates
Enterprise environmental factors
Communications models

Manage
communication

Performance reporting
Communication technology
Communications methods
Information management systems
Project communications
Project management plan updates
Project documents updates
Organizational process assets updates
Work performance data
Issue log
Project communications

Control
communication

Project management plan


Organizational process updates
Information management systems
Expert judgment
Meetings
Work performance information
Change Requests
Organizational process assets updates
Project document updates
Organizational process assets updates

Copyright protected

35 | P a g e

CAPM workbook

Plan
communications
management

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Communication knowledge area

Manage
communication

Control
communication

Copyright protected

36 | P a g e

CAPM workbook

Copyright protected

37 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Risk knowledge area

Enterprise environmental factors


Organizational process assets
Project management plan
Project charter

Plan Risk
Management

SH register
Analytical techniques
Expert judgment
Meetings
Risk management plan
Enterprise environmental factors
Organizational process assets
Scope baseline
Project Documents
Procurement documents
Risk management plan
Activity cost estimates
Activity duration estimates
Stakeholder register
Cost management plan

Identify Risks

Schedule management plan


Quality management plan
Project Documents
Documentation reviews
Information gathering techniques
Checklist analysis
Assumptions analysis
Diagramming techniques
SWOT analysis
Expert judgment
Risk Register

Perform
Qualitative Risk
Analysis

Organizational process assets


Scope Baseline
Risk management plan

Copyright protected

38 | P a g e

CAPM workbook

Risk register
Enterprise environmental factors
Risk probability and impact assessment
Probability and impact matrix
Risk data quality assessment
Risk categorization
Risk urgency assessment
Expert judgment
Project documents updates
Organizational process assets
Enterprise environmental factors
Cost management plan
Schedule management plan

Perform
Quantitative
Risk Analysis

Risk management plan


Risk register
Data gathering and representation
techniques
Quantitative risk analysis and modeling
techniques
Expert judgment
Project document updates
Risk management plan
Risk register
Strategies for negative risks or threats

Plan Risk
Response

Strategies for positive risks or


opportunities
Contingent response strategy
Expert judgment
Project management plan updates
Project documents updates

Control risks

Project management plan


Risk register
Work performance data
Work performance reports
Risk reassessment
Risk audits
Variance and trend analysis
Technical performance measurement

Copyright protected

39 | P a g e

CAPM workbook

Reserve analysis
Meetings
Work performance information
Change Requests
Organizational process assets updates
Project management plan updates
Project documents updates

Plan Risk
Management

Outputs

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Risk knowledge area

Identify Risks

Copyright protected

40 | P a g e

CAPM workbook

Perform
Qualitative Risk
Analysis

Perform
Quantitative
Risk Analysis

Plan Risk
Response

Copyright protected

41 | P a g e

CAPM workbook

Control risks

Copyright protected

42 | P a g e

CAPM workbook

Outputs

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Procurement knowledge area

Enterprise environmental factors


Organizational process assets
Project management plan
Requirements documentation
Activity resource estimates
Risk register
Activity cost estimates
SH register
Project schedule

Plan
procurement
management

Make or buy analysis


Expert judgment
Market research
Meetings
Procurement management plan
Procurement statement of work
Make-or-buy decisions
Procurement documents
Source selection criteria
Change requests
Project documents updates

Conduct
Procurements

Procurement management plan


Organizational process assets
Procurement documents
Source selection criteria
Seller proposals
Project Documents
Make or Buy decisions
Procurement SOW
Bidder conference
Independent estimates
Expert judgment
Proposal evaluation techniques
Advertising

Copyright protected

43 | P a g e

CAPM workbook

Analytical techniques
Procurement negotiations
Selected sellers
Agreements
Resource calendars
Procurement management plan
updates
Change requests
Project documents updates
Agreements
Procurement management plan
Procurement documents
Work performance reports
Approved change requests
Work performance data
Contract change control system
Procurement performance review

Control
procurements

Inspections and audits


Performance reporting
Payment systems
Claims administration
Records management system
Work performance information
Change requests
Organizational process assets updates
Project management plan updates
Project documents updates
Project management plan
Procurement documents

Close
Procurements

Procurement audits
Procurement negotiations
Records management system
Closed procurements
Organizational process assets updates

Copyright protected

44 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Procurement knowledge area

Plan
procurement
management

Conduct
Procurements

Copyright protected

45 | P a g e

CAPM workbook

Control
procurements

Close
Procurements

Copyright protected

46 | P a g e

CAPM workbook

Copyright protected

47 | P a g e

CAPM workbook

Output

ITTO components

T&T

KA processes

Inputs

Type 1 Matrix: Stakeholder knowledge area

Project Charter
Procurement documents
Enterprise environmental factors

Identify
Stakeholders

Organization process assets


SH analysis
Expert judgment
Meetings
SH register
Project management plan
SH register
Enterprise environmental factors

Plan SH
management

Organization process assets


Expert judgment
Analytical techniques
Meetings
SH management plan
Project documents updates
SH management plan
Communications management plan
Change log
Organization process assets
Communication methods

Manage SH
engagement

Interpersonal skills
Management skills
Issue log
Change Requests
Project Management Plan updates
Project document updates
Organizational process assets updates

Control SH
engagement

Project management plan


Issue log
Work performance data

Copyright protected

48 | P a g e

CAPM workbook

Project Documents
Information management systems
Expert judgment
Meetings
Work performance information
Change Requests
Project Management Plan updates
Project documents updates
Organizational process assets updates

Identify
Stakeholders

Outputs

ITTO components

T&T

KA processes

Inputs

Type 2 Matrix: Stakeholder knowledge area

Plan SH
management

Manage SH
engagement

Copyright protected

49 | P a g e

CAPM workbook

Control SH
engagement

Copyright protected

50 | P a g e

S-ar putea să vă placă și