Documente Academic
Documente Profesional
Documente Cultură
Planning
Depth Referencing
This article describes the various depth references used for drilling onshore and
offshore wells: Reference Datum, Chart Datum (CD), Mean Sea Level (MSL), High
Tide (HT), Low Tide (LT), Water Level (WL), Lowest Astronomical Tide (LAT), Depth
Subsea (SS)
Reference Datum
For operations involving a rig, either onshore or offshore, all depths (either along
hole or true vertical) are referred to the drill floor of the rig which initially drilled the
well (original drill floor).
These depths below drill floor (BDF) measured from the rotary table Kelly bushings
(RTKB) are in turn referred to a universal datum, the Chart Datum (CD), for the local
area.
Note: For onshore operations, the reference point for depth is the mean sea level
(MSL) and the rotary table Kelly bushings (RTKB).
The height of Mean Sea Level (MSL) above CD is usually known (C)
Tide Tables
For offshore operations the Drilling Supervisor shall ensure that the correct Tide
Tables are available on the rig. Tide Tables are predictions and may not be accurate
because of local environmental conditions e.g. changes in atmospheric pressure and
surges caused by conditions outside the immediate area. Marine department may
be consulted if additional guidance is required.
Land Locations
The land elevation above MSL shall be provided by Petroleum Engineering and shall
be noted in the drilling programme.
For individual wells the depths are referenced to RTKB.
This article describes the standards for Drillpipe and Bottom Hole Assembly (BHA).
The master drill pipe tally book shall be kept by the Driller in the dog-house
and in the Tool Pusher office. This is to be updated every tour.
Both the drill pipe single and stand columns shall be totaled vertically and
compared to the cumulative total.
When the totals show no discrepancy, the column is to be initialed by the
driller on tour.
The Contractor Toolpusher will make a daily check and also initial the totals.
When drilling or reaming, connection depths shall be written on the
Geolograph record at the time of the connection.
The Contractor toolpusher shall make a physical check of the total drill pipe
on hand daily.
Drill pipe checks shall be made at each trip before and after reaching casing
depths.
Each individual drilling tally assembly item shall be annotated.
All drill pipe RIH to be drifted as per API.
Drillpipe
The submerged BHA weight is the weight of the drill collars only. When a jar is
included in the string it is the submerged weight of the drill collars below the
jar.
The Heavy Weight Drillpipe is not included in the weight of the BHA, unless a
minimal assembly is used where the HWDP is planned to apply the weight on
bit.
The attached BHAs are recommendations and the Drilling Supervisor should
use his own judgement to determine the correct number of drill collars.
Do not install a stabilizer next to a crossover. (The cause of most failures of
crossovers and stabilizer connections is misalignment of the tooljoints).
Stabilizers with eccentricity between the connections and the blade OD will
also suffer early fatigue failure.
When PDC bits are run, a shock sub should not be included in the BHA but a
drilling jar should be included.
Avoid in general the use of too many connections next to each other.
(Homogenous load distribution to be considered)
Do not run more DCs than required.
Do not run a jar as standard, but only if required. (Jar, if required, to be
installed at optimum position, i.e. one DC between jar and HWDP).
No safety joints shall be run in drilling assembly
Shock subs are more flexible than DCs, especially 6 in: and smaller sizes.
Do not run a different assembly on a check trip during logging or prior to
running casing than the one used for drilling.
Do not run stabilizers, which are more than in under gauge as one of the
bottom three stabs in a packed hole assembly.
Do not change assemblies halfway. Time consuming reaming results in
deteriorating hole conditions with a risk of sticking the assembly
mechanically.
Ensure that all assembly items have the required bore back and stress relief
grooves prior to use.
Weight on Bit
The Maximum WOB is 75% - 90% of the submerged BHA weight.
Limit WOB to 75% when drilling is rough.
Increase WOB to 90% when drilling is smooth.
General Practices
4. Position rig
5. 30in conductor (multi-well
jackets only)
6. Drill 36in hole (exploration
wells only)
formations
Drilling Operations
Description by hole section (text); use the Drilling Supervisors Daily Diary notes as
the basis along with daily drilling reports etc. Write out a description of events.
Note especially information on how best to drill each formation encountered; include
suggested bits, parameters, mud properties, drilling practices etc.
Bit performance analysis; planned vs actual performance, constraints on bit
performance, notes on how the bit & BHA selection and parameters could be
improved.
Mud performance analysis. Show planned vs actual performance, problems
encountered (especially borehole stability related), how these problems were
handled, suggestions for improvements on the next well.
Casing and cementing performance analysis. Discuss problems encountered,
comment also where performance was good.
Specific problem areas; fishing jobs, other remedial work, kicks etc.
Other items not covered by the above areas.
Conclusions and Recommendations. How time could be saved, problems avoided or
reduced, anything to improve performance next time.
Logistics
Equipment lists as shown in the Drilling Programme; show any deficiencies in these
lists. (i.e. update for future reference)
Highlight any problems regarding vessels, helicopters, road transport etc.
Conclusions and Recommendations.
Service Companies
Problems with equipment, personnel, procedures or contracts.
Conclusions and Recommendations.
Geological Results
Prognosed vs Actual lithology encountered.
Conclusions and Recommendations.
General
Communications and Computers.
Anything else not covered above.
Conclusions and Recommendations.
Appendices
Directional surveys and well plots.
Bit record.
Casing and cementing reports.
Formation Integrity Test reports.
Print off showing pore pressures, fracture gradients, mud densities and overburden
gradient against depth. (E.g. Sperry Sun PPFG printout)
Hole Section Summaries showing this well and offset wells for comparison (refer
Drilling Manual on CD).
Copy of the Drilling Programme, Technical Justification and Amendments to the
Drilling Programme
List of personnel who supervised planning, drilling and evaluating the well.
Drilling Standards
Depth Referencing
All depths (either along hole or true vertical or plug back /packer) must be
referenced to the original Rotary Table Kelly Bushings (RTKB) of the rig which initially
drilled the well (original derrick floor). Mean sea level and sea bed must also be
reported.
On new wells, depths shall be recorded in feet below RTKB. On a sidetrack well
depths shall similarly be recorded in feet below RTKB but shall also be referenced to
the original rig drill floor elevation. Sidetrack wells are to be named as WELLNAME
(Mother bore), WELLNAME-A (sidetrack 1), WELLNAME-B (sidetrack 2), etc.
Chemical Stocks
A sufficient quantity of mud and chemical stocks shall be available at the well site to
drill the well or a portion of the well. Stocks of Barite/CaCO3/Salt shall be available
to weigh up the mud in emergencies.
Surface Equipment
Rig surface equipment requirements will be covered in the Drilling Contractors
contract. All rig floor gauges, recorders and alarms shall be functioning properly.
Inspection of drilling lifting equipment shall be performed prior to commencement
of all wells and inspected every six months.
Downhole Equipment
Responsibilities
The Drilling Supervisor and Operations Engineer shall ensure that:
there are no anomalies in the programme
all technical and safety issues are addressed
all personnel at the rig site involved with the programme clearly understand
their duties and responsibilities.
While activities and tasks related to the drilling progress are ongoing, it is the
responsibility of the Drilling Supervisor to ensure that there is no divergence from
the Drilling Programme unless a revision has been approved in accordance with the
Drilling Programme revision procedure.
This article describes the sequence of operations and the general practices for a
typical onshore well.
Operations
1. Prepare access road and
well lease
General Practices
Minimize environmental impact due to
survey/construction
- Prepare environmental report and map
- Obtain final survey of Lat./Long/Evaluation
- Avoid natural drainage routes, significant
topographical disruption. Early contractor site
inspection
Arrange timely water supply (well/logistics)
Cellar dimensions are rig-specific
Stove Pipe depth; minimum 6ft.
Drilling Contractor will install stove pipe.
Ensure conductor is vertical, stove pipe flange is
level;
use spirit level to confirm
Pre-spud topics: target zones, geology, drilling,
electric logging, DSTs (field safety/pre-spud
meeting also held)
Follow Drilling Contractor rig move procedures
Communications between vehicles and sites
required at all times
Rig-down and rig-up camp the same day if possible
Sheaves and travelling block to be inspected during
move
Rathole/mousehole to be drilled while WOC
(conductor)
Drill 26in hole to depth specified in Drilling
Programme
Drill using water with viscous pills
If circulation is lost drill blind
Ensure hole is cleaned regularly
Rig up, make secure and pressure test all test lines
Fill annulus prior to opening test tool, thereafter
monitor level
Drilling Supervisor to be present during all
setting/opening/recovery and unseating/POOH of
DST tools; tests will not start in darkness
Well is to be monitored for swabbing; continuous
fill-up is NOT permissible while POOH
Follow reverse-out procedures to ensure optimum
recovery
Run 5.1/2in/7in/7.5/8in casing or liner
Measure, drift and number casing, clean/inspect
threads
Conditioning trip, spot a 40 bbl. Hi-Vis pill (70 FV)
Change bottom rams to casing rams and pressure
test
Thread lock float shoe and float collar
Make up shoe track, check float equipment with
water
Centralizers as per Drilling Programme
Pup joint will be located above each pay zone if
available
Mud left in annulus after cementing will be treated
with Biocide
Pre-flush brine will be equivalent density to mud;
treat with SAPP and Biocide
Calculate cementing volumes using caliper values;
use top and bottom cement plugs
TOC to be 200 ft. above highest hydrocarbonbearing zone (minimum)
Displace with cement unit, using water (containing
corrosion inhibitor if specified). Reciprocate casing
until plug bumps
Hold pressure at 500 psi above displacement
pressure for 15 minutes
Confirm actual TOC with displacement pressure off
Drill out cement to shoe-track
Run bit and scraper to TD inside casing
Log CBL/USIT/GR for zonal isolation
Circulate well to clean filtered brine
Pressure test casing to 3 500 psi
Run completion as per Programme
Perforate well according to log analysis
Clean up well until BS&W<1%
Flow well
Suspend for completion by Production Department,
or/
Submit notice of Intention to Abandon including
proposed plug intervals to operations
Drilling Supervisor
The Drilling Supervisor shall provide prior to any particular operation written
instructions to the Drilling Contractor Toolpusher and service personnel. These
instructions shall include but are not limited to:
general sequence of programme events
potential hazards
contingency procedures in the event of occurrence of identified potential
problems
drilling parameters to be used
safety and environmental issues.
Drilling Contractor
It is the responsibility of the Drilling Contractor to drill the well to the correct
programme specifications and to provide a wellbore that is fit for purpose, subject
to the terms of the contract.
The Drilling Contractor shall not compromise safety or well integrity in order to
reach the drilling objectives.
Toolpusher
The Drilling Supervisor shall approve and provide written instructions to the
Contractor Toolpusher prior to any particular operation.
Driller
The Drilling Contractor Driller, who is responsible for the rig crew, shall carry out the
drilling operations written instructions prepared by the Drilling Supervisor. He shall
ensure that drilling and associated operations are carried out with due regard to
optimum drilling, wellbore integrity and rig crew safety, e.g., pressure control and
crew personal safety.
The quality of work shall be monitored and controlled primarily by the Drilling
Supervisor, with support from the Head of Offshore / Onshore Operations, to ensure
that the well objectives are not compromised.
Meetings shall be held every morning with the well site personnel (Drilling
Supervisor, Contractor Tool Pusher, service personnel) to plan the operational
aspects relevant to:
safety issues
the forward programme
out of service equipment which may impact drilling operations
scheduling equipment/materials availability
weather forecast and supply boat/craft movement
The Drilling Supervisor shall ensure that he is informed immediately of any
significant deviation from normal operational conditions e.g. increasing levels of
over pull, increasing levels of back-ground gas, slow ROP, gain or loss, change in
direction parameters, abnormal formation, drop / rise in press. etc.
The Drilling Supervisor shall ensure that all key rig personnel are familiar with rig
equipment and standard drilling practices e.g. well control drills, flow checks. All key
personnel must be certified with updated well control, H2S and safety courses.
Seismic line
Shot point
Coordinates UTM
CORING REQUIREMENTS
Coring Policy (on shows etc.)
Possible cored intervals
Estimated No. and thickness of cores
Restrictions on core size
Special requirements (oriented core, fiber glass inner barrels, low invasion
system, etc.)
SAMPLING REQUIREMENTS
ELECTRIC LOGGING REQUIREMENTS
Top Hole Section
Logs required
Optional logs
No. of runs
Estimated duration
Intermediate Hole Section
Logs required
Optional logs
No. of runs
Estimated duration
Reservoir Hole Section
Logs required
Optional logs
No. of runs
Estimated duration
Cased hole logging
Logs required
Estimated duration
-
VSP
-
REQUIREMENTS
Type of survey (VSP / check shot)
Estimated duration
Special requirements
TESTING REQUIREMENTS
Type of test