Documente Academic
Documente Profesional
Documente Cultură
Coding System
Project Code
Standard Code
A project Code system provide the framework for project
planning and control & is used to interface with:
Management & Supervisors
Numbering of drawing & specs
Procurement documents
Scheduling codes
Cost Codes
Accounting codes
<#>
<#>
Division
Level 2
Level 3
Level 4
Level 5
03 11 13.25
5000
All concrete items
Concrete Forming
Structural Cast-in-Place Concrete forming
Forms in Place, Columns
Structural cast-in-place concrete forms
made of plywood and used once for jobbuilt 8 8 columns
Accuracy
and
complexity
to produce
Project life cycle
<#>
Index to be converted
Index on 1967 base =
<#>
<#>
C2 = C1 (
Q2
Q1
Where:
0.8
)
150,000
120,000
C2 = 5,020,850.62
$5,000,000.00
<#>
I2
Q2
)*(
I1
Q1
C2 = C1 (
x
)
Previous Example
2103
Estimated Cost = 4,200,000 (
248
Estimated Cost = $ 42,576,003
<#>
*(
150,000 0.8
)
120,000
<#>
Solution:
<#>
<#>
<#>
Building
construction cost
data published by
R.S Means
<#>
Steps:
1. Identify all direct cost activities (WBS).
2. Perform Quantity takeoff for each activity (from
drawings only for activities constructed by the contractor not
for those subcontracted).
<#>
<#>
<#>
A ($/day)
P (Unit/day)
4 - Estimate L Labor direct cost
B ($/Unit) =
<#>
Solution:
Carpenters and 1 laborer are required at $48.45/hr and
$37.90/hr from R.S. Means, respectively.
1. Crew labor cost A:
A ($/day) = [Hourly rate ($/mhr) * 8 h/day]
= [3 * 48.45 + 1 * 37.90]* 8 = $ 1466.00/day
2 - Crew daily output P: Given (P = 375 SFCA/day)
3 - Unit labor cost B = A/P
B ($/Unit) = ($1466.00./day)/(375 SFCA/day)
B = $ 3.91 / SFCA
4 - Total labor direct cost L = B * QTY
L ($) = ($ 3.91/SFCA)*(500 SFCA) = $1954.667
<#>
<#>
<#>
Steps:
1. Identify all direct cost activities (WBS).
2. Perform Quantity takeoff for each activity
3. Estimate direct cost for each activity.
<#>
Steps:
1. Identify all direct cost activities (WBS).
2. Perform Quantity takeoff for each activity
3. Estimate direct cost for each activity.
4. Calculate total direct cost of all activities.
5. Estimate total project indirect cost
6. Estimate project mark-up
7. Total project bid = Direct Cost + Indirect Cost + Mark-up
<#>
Steps:
1. Identify all direct cost activities (WBS).
2. Perform Quantity takeoff for each activity
3. Estimate direct cost for each activity.
4. Calculate total direct cost of all activities.
5. Estimate total project indirect cost
6. Estimate project mark-up
7. Total project bid = Direct Cost + Indirect Cost +
Mark-up
<#>
Cash Flow
Cash flows can be estimated by attempting to assess
flows from:
(1) Projects in progress
(2) Projects under contract but not yet begun
(3) Potential projects, which will start during the
coming period for which forecasts are being made
<#>
Cash Flow
<#>
Cash Flow
Example
<#>
Cash Flow
Example
<#>
Cash Flow
Example
Total bid cost of a project = $200,000
Contractor bill at the end of the month
- Finish the work exactly following the schedule
- markup = 25% of the total cost of the project
Owner Payment to contractor
- 10% retainage of all validated progress payment
claims until 50% of the contract value has been built.
- All retainages will be released to contractor in the
owners last payment
-Transfer the payment 30 days later
Payment = 1.25(direct cost + indirect cost)
<#>
- 0.10{1.25(direct
cost + indirect cost)}
Cash Flow
Example
<#>
Cash Flow
Example
<#>
Cash Flow
Overdraft
Examples: Automobile dealers, clothing stores etc.
The amount of overdraft is calculated by a number of factors,
including the amount of markup or profit the contractor has in
a bid, the amount of retainage held by owner, and the delay
between billing and payment by the owner
<#>
Cash Flow
Overdraft Calculation
Interest rate is 1% per month
<#>
Cash Flow
Overdraft Calculation
<#>
Cash Flow
Overdraft Profiles for multiple projects
<#>
Thank you !
Q&A?