Documente Academic
Documente Profesional
Documente Cultură
INSTALLATION OF
PARTITIONING
www.thefis.org
INSTALLATION OF
PARTITIONING
This project has been delivered with support from the CITB
Growth Fund, which aims to ensure that the construction
industry has the right people, with the right skills, in the right
CONTENTS
1 Foreword
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
2 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
2.1 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3.1.2 Programme. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
6.1 Bracing 13
7.2 Manifestations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
7.2.1 Partitions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
7.3 Blinds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
7.4 Doors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
7.5 Wallcoverings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
4 Contract planning. . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
6.11 Storagewall. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
6.11.1 Module options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
6.11.2 Finishes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
5.1 Setting-out. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
9 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
10 Acknowledgements. . . . . . . . . . . . . . . . . . . . . . . . . . .51
FOREWORD
This guide to the installation of partitioning has been
of partitions.
INTRODUCTION
2.1 SCOPE
This best practice guide covers the installation of all types of
partitioning systems up to a height of 3.6 metres.
Additional measures may be necessary to meet fire or
acoustic performance requirements when ceiling voids extend
over adjacent rooms. This may involve the installation of fire
or sound attenuating barriers above the partitioning in the
ceiling void or modification of the ceiling panels. The advice of
the manufacturer of the partitioning system should be sought,
together with reference to the FIS publication A Guide to
Office Acoustics. In some cases the services of an acoustician
or fire consultant may be required.
Waste management
always be observed.
www.hse.gov.uk/construction/cdm/faq/contractors.htm
forms:
remeasureable contract
Insurances
Liquidated damages
Defects liability period (now called rectification period
under JCT11)
3.1.2 Programme
milestone dates)
found at www.environment-agency.gov.uk/business/topics/
waste/32148.aspx
better if possible.
System manufacturer
System type
Location
should detail:
Layout
BS EN 1364-1(1999)
Gradient of floor
3.3.2 Specification
The specifier might wish to consider specifically how any
/ sliding
conform with AD M)
Description, single / double, single action / double action
Partition height:
Accessories switches
BS EN ISO 140-3(1995)
can ensure that key issues and details are considered in the
overpanel
System performance:
Fire resistance - BS 476-22(1987) or
Junctions
Incorporated features:
Function of building
Main contractors programme and building owners
stipulation affecting the sequence and working hours of
the works
CONTRACT PLANNING
Crucial to the success of a partitioning installation is the
the partitioning.
SPECIFICATION
METHOD
PROGRAMME
fully understood.
include:
the partition head and the soffit (see 6.1 Bracing and
prevail.
contractor.
10
CONTRACT PLANNING
partitioning materials are generally fragile and require very
careful handling and storage (see also 3.2.3).
period for their use. Clear gangways and access to lifts and
4.4 PROGRAMME
by others.
of progress.
It is important that the partitioning contractor works in
harmony with any associated trades such as suspended
all concerned.
11
floor track.
checked at floor, mid and ceiling height and checked for level
and true. Any surfaces that are not level should be noted.
in the partition run and any effect they may have on the
partition perimeter.
Plan drawings
It is usual to have a plan drawing showing the outline layout
the dimensions.
Elevation drawings
12
and structure
6.1 BRACING
Figure 1
provided that the fixing is directly into the ceiling grid main
is achieved
13
6.2 PERFORMANCE
(flanking transmission).
at www.acousticguide.org
6.3 SCREENS
Free standing screens are used to form flexible work spaces
14
monitor arms together with trays and tool bars are also
featured.
4 Office pods: are considered to be the informal meeting
screen installation.
where the panels (any type) are clipped into position and
can be easily removed or individually changed (see figure 2)
Figure 2
resistance.
Two floor pans are screw fixed to the floor on the partition
line for the first module approx 250mm in from each of the
15
LAMINATE SKIRTING
Figure 5
ALUMINIUM SKIRTING
In a similar way, upright post positions are
marked on the skirting lip, then the gap is
Figure 3
16
Figure 4
edge, the skirting foam cut away for the upright post and
DOOR FRAME
machined for lock keep and hinges. Door seals, hinges and
accurately set out the upright posts) and fixed to the head
The horizontal chairs are cut to fit the module, then the
floor shoe outers (inners are not used) and the floor transom
The floor shoes are fixed and the panel cut to size and
achieve up to 42dB(Rw).
are inserted.
17
manufacturers instructions.
stud framework.
Figure 6
18
machined for lock keep and hinges. Door seals, hinges and
below allow for the back face of the omega section being
Board joints are then taped and filled and screws at the
SKIRTING
The set out position for the stud transom will be in the
four categories:
into position.
requirements.
protruding down from the door head, and pushed upwards and
DOOR FRAMES
before fixing the frame stile into the stud using screws
are fitted, the PVC infill strips are cut and fitted to conceal
fixing screws.
The door frame seal and lock box can now be fitted and
19
Figure 7
correct overall length to suit the glazing frame. This sets the
fire rating.
device. A stud is cut to fit between the floor track and the
loosely fixed.
If a fully glazed or glazed to door head elevation is to be
long, are cut to fit between the floor track and the base
transom, one at each end and one in the centre (the return
20
Figure 8
studs and not on the face of the studs. Ply should not be
acoustic sealants.
Figure 10
partition has been boarded. Studs will have cut outs or push
Figure 9
Figure 11
21
will set the plumb line for the remaining glass run.
22
Figure 12
to 48dB(Rw).
ALUMINIUM
High bond tapes are applied to the vertical glass edges, and
once the panels are level and straight the inner faces of the
aluminium H shaped dry joint should be thoroughly cleaned with
an alcohol based glass cleaner. The tape is then peeled off and
the aluminium dry joint is bonded to the glass, taking care to
keep the face of the aluminium flush with the face of the glass
all the way up. The next panel of glass with tape already applied
is stood up, the tape peeled off and panel slid against the dry
joint section. The process continues in the same way.
For the glass panel which forms a 3-way junction, the tape is
peeled away and an edge protection strip is applied, then a
high bond tape is applied to the flat surface of the section.
Figure 13
Figure 14
Ensuring that the glazing of the main front run is installed with
a dry joint centred on the offset run, the tape is peeled away
be pilot drilled and fixed tight either side of the glass to tie
and the offset panel carefully pushed against the front run dry
joint, with firm pressure applied all the way down to ensure a
complete bond.
PVC
cure for 24hrs, the toggle clamps are removed and the gaps
the glass, others rely on a tight friction fit (see figure 14).
Figure 15
each edge (see figure 15). Softer circular PVC profiles with
tape on either side are also available for a less visible joint.
Soft, bubble type pvc profiles sided with adhesive tape can
edges and cleaned before the profile is cut to size and then
visual appearance.
23
the glass leaves remain aligned (see figure 16). Gluing tubular
using instant adhesive applied at the top edge of the joint. The
and the glass pushed carefully onto the bubble ensuring that
then bonded in the same way at the bottom (see figure 17).
Figure 16
Figure 17
Figure 18
24
Figure 19
module elevations.
Figure 20
glazing profile.
GLAZED MODULES
25
GLAZED MODULES
common head and base profile for taking the glass. The timber
Figure 21
into the mullion, with a cover strip to cover the joints and also
section for full height doors. This applies for both solid and
glazed elevations.
SKIRTING
infill strip. True timber skirting can also offer bespoke skirting
solutions, including chamfered, mitred or block details. On
SOLID MODULES
systems where the head and base section are the same profile,
is not being installed for its relocatable function, then rapid set
26
Figure 22
formed junctions.
working wall.
Figure 23a
Figure 23
be achieved.
WALL ABUTMENT
27
base track and slid into the head track. When vertical the
panel will arrive on site with its pre-finished face which can be
DOOR FRAMES
Door frames are factory prepared and painted and arrive
studs are then moved back into position to allow the door
manufacturer
door seals.
GLAZED PANELS
solid elevations.
Monobloc systems are set out with a head and floor channel
which are fixed to the ceiling and floor and plumbed level.
stud face and then pulled down over the hook-lugs into its
Any acoustic foams or seals are also fitted along with any
final position. The same occurs on the other side but this
sections that will allow for wireways at either the head or base
detail. Both the head and floor track will become recessed
be removed.
Between all panel joints, a joint infill is cut to panel size and
inserted in the gap. An acoustic seal is fitted in the horizontal
gap between the panels and the head and base tracks.
28
Figure 25
Figure 24
Within the gap, cleats are then fitted to lock the panels
60 minutes.
height partitions.
29
Figure 27
workspace.
for double point systems the panels can only park in the
30
into the ceiling track. This is best done at the point of the
automatic systems.
Figure 28
interstitial blinds).
a sound leak.
31
Figure 29
Figure 30
automatic and utilises flat, rigid panels that fold into the
32
vinyl coverings. The system is top hung without floor rails and
6.11.2 Finishes
and back panel brackets) before the left hand door is laid next
BS 6868.
the first divider panel except that double hinges will be used
6.11 STORAGEWALL
made available are plain shelves, combi shelves for filing and
roll out filing frames, horizontal coat rails, front to back coat
Figure 31
with full height doors, full height door with pelmet, doors with
its long sides, which are used to accept fixings and help with
doors and drawers and split doors. Units are supplied with
33
2 Measure out from the wall at ceiling level and attach the
divider panels.
centre screw.
11 Fit the locking bolts to the top and bottom shelves. Open
the doors and then close the locking door only. Looking
with screw.
12 Fit the lock handle to each right hand door. Ensure that
34
are fixed into the holes in the back panel, leaving the
by aluminium beads.
2 Hook-on panels: a framework of height adjustable slotted
fitted into the cross rail and the wall is progressively built
have tapered slots fixed on the back are then fitted onto
slots are then fitted onto the hook lugs on the studs.
Figure 33
of construction:
floor level.
35
figure 34).
Figure 34
for height, plumb and level and securely fixed to the ceiling
The product ranges will also include door hooks, toilet roll
36
37
reworked if necessary.
of reasons:
partitioning.
7.1 GLASS
Regulations covering the use of glass in partitions are
manifestation.
explosion.
7.2.1 Partitions
inspection easier.
38
office environment.
1500mm
1500mm
Second level
1155mm
Once the graphics are dry and finished, any water marks
should be cleaned off. Graphics should not then be cleaned
1000mm
First level
Figure 36
500mm
500mm
800mm
850mm
Figure 38
Figure 37
150mm
providing:
repeated
(no pitch is defined)
or
50mm
repeated
(no pitch is defined)
39
for cellular hollow core doors and 44mm and 54mm for
solid core doors.
Ideally, all doors should be delivered to site immediately
the rise and fall mechanism on the blind, but the opening or
closing of blinds can be remotely controlled, or the popular
method is by way of a control knob which is fixed to the
interior.
7.4 DOORS
40
site, best practice for FD30 or FD60 doors is for the vision
Effective clear
width (door stop
to projecting
ironmongery)
Effective clear
width (door stop
to projecting
ironmongery)
926mm wide
door leaf
926mm wide
door leaf
300mm minimum
unless door is
power operated
allow 20mm
Figure 37
Figure 38
Table 1
EXISTING BUILDINGS
NEW BUILDINGS
Minimum effective
clear B (mm)
Offset C (mm)
Minimum effective
clear B (mm)
Offset C (mm)
750
40
800
90
750
40
800
90
775
65
825
115
775
n/a
1,000
n/a
41
bar will support the top pivot pin. Back to back pull handles
or latch lock lever handles can be used although long pull
door. Also the gap between the frameless glass door and
Figure 39
possible afterwards.
42
preferred.
where the closer is fitted. The arm is usually jointed, but for
Not less than 45mm clearance from the rear of the handle
Figure 40
Document M include a
number of preferred
450mm
box which is embedded in the floor with only the top floor
HINGES
more suitable.
centred 250mm up
closers and will have little speed control, although some will
air pressure. Helical spring and chain link are typical examples.
250mm
43
DIGIT 3
DOOR WIDTH
DIGIT 5
SAFETY
Grade 1: safe
No other grades. All
door closers need to
meet the safety in
use essential
requirement
DIGIT 2
NUMBER OF TEST
CYCLES
Grade 8: 500,000
cycles
No other grades.
41
DIGIT 4
FIRE BEHAVIOUR
Grade 0: not suitable
for use on fire/smoke
door assemblies
Grade 1: suitable for
use
DIGIT 6
CORROSION
RESISTANCE
Grade 0: no
resistance
Grade 2: moderate
Table 2
decorative surface.
Grade 1: mild
Grade 3: high
2
5
*The fire rating system changed in July 2013, with the advent of
the Construction Products Regulations. The UK Building Regulations
transferred to a new system where fire performance is measured
using European test methods. The new levels required, Classes B, C or
D, are contained in the Building Regulations and cross reference to the
previous Classes 0, 1 and 3.
PREPARING WALLS
7.5 WALLCOVERINGS
training rooms.
4 Protective and decorative performance wallcovering:
developed for high traffic areas in hospitals, care homes,
schools, hotels and other installations where durability,
44
their ends.
edge. The left hand edge of drop two simply slides to the
head will alter the appearance of the head detail and may
HANGING WALLCOVERING
that the drops are parallel to each other and that a 50mm
wallcoverings include:
45
60 to 120 minutes.
Figure 42
46
Figure 44
47
the process.
appropriate keys
MAINTENANCE
without degradation.
48
49
REFERENCES
BREEAM
LEED
Ska
environmental performance.
www.leed.net
www.breeam.org
Food retail
Non-food retail
Retail banks
Restaurants.
This guidance is freely available along with an online
assessment tool, which can be used informally or for formal
certification using an RICS Ska Rating Accredited Assessor.
Assessments can be carried out at three stages: design,
handover and occupancy.
FIS is a Ska development partner.
www.rics.org/ska
50
ACKNOWLEDGEMENTS
10
FIS has grown over the past 50 years to become the leading
trade association for the interiors fit out sector of the
construction industry. FIS represents companies involved in
the manufacture, supply and installation of all aspects of
interior fit outs and refurbishment.
FIS members operate in retail and commercial offices,
the public sector, banks and building societies, hotels and
leisure, airports, hospitals, and so on. Most work nationally
and an increasing number operate in Europe and beyond.
Quality and integrity lie at the heart of FISs philosophy
- each member is expected to act with the utmost
integrity, and to exercise the highest standards of business
practice and workmanship. At the same time, the Association
seeks to continually raise, maintain and ensure the
perpetuation of standards in order to remain a source of
quality membership.
fIS membership is not automatic and applicants are subject
to strict vetting procedures on application, as well as ongoing
vetting. In the case of contractors, this includes inspection of
recent contracts to assess workmanship standards.
www.thefis.org
51
INSTALLATION OF
PARTITIONING
FIS
Olton Bridge
245 Warwick Road
Solihull
West Midlands
B92 7AH
+44(0)121 707 0077
info@thefis.org
www.thefis.org
ISBN 978-0-9565341-4-9