Checklist for Block Works

Ativities/Items to be
Inspected
a). Preparatory Inspection
MS/ITP/Shop Drawing
1
Approved
Materials Approved by
2
Client or Engineer
b. Final Inspection
Check Setting out and
1
Surface Preparation
Blocks are dampened with
2
water before installation
Mortar Mix as per approved
3
MS
Number of course as
4
specified and approved
Blockwork joints were
properly filled with mortar
5
and rake to form key for
plaster
Wall ties are fixed at
junctions of concrete walls
6
and columns and all
requiered
Horizontal stack provided as
7
per method statement
All required MEP
8
embedments and openings
are in placed
Alignment and verticality
9
checked
Compressible filler and
10
sealant provided
11
Curing is made
ITEM

Conforms
Engineer/ Client/
Contractor
Remarks
(YES/NO)
Consultant Employer