OBRAS PROVISIONALES

1,527.64

CARTEL DE IDENTIFICACION DE LA OBRA DE 2.60X1.80M

und

1.00

627.64

627.64

ALMACEN DE OBRA

mes

3.00

300.00

900.00

ESTRUCTURAS

53,105.95

PUENTE

53,105.95

TRABAJOS PRELIMINARES

2,775.77

DEMOLICION ESTRUCTURA DE C CICLOPEO


LIMPIEZA DE TERRENO MANUAL

m3
m2

23.42
57.60

110.11
1.72

TRAZO Y REPLANTEO EN PUENTE

m2

57.60

1.70

MOVIMIENTO DE TIERRAS

2,578.78
99.07
97.92
6,641.90

EXCAVACION DE ZANJAS PARA ZAPATAS CON MAQUINARIA

m3

60.00

17.03

NIVELACION Y CONFORMACION DE FONDO

m2

50.00

2.52

126.00

MEJORAMIENTO DE FONDO CON OVER e=8"

m3

20.00

71.89

1,437.80

AFIRMADO CON MATERIAL DE PRESTAMO E=6"

m3

30.00

75.71

2,271.30

RELLENO CON MATERIAL PROPIO

m3

20.00

26.75

535.00

ELIMINACION DE MATERIAL EXCEDENTE

m3

50.00

25.00

1,250.00

m3

1.50

111.51

CONCRETO SIMPLE
SOLADO 1:10 e=4" PARA ZAPATAS

1,021.80

167.27

ALETAS

167.27
6,724.71

CONCRETO EN ZAPATA F'C= 175 KG/CM2+30% P.G.

m3

6.72

281.02

1,888.45

ENCOFRADO Y DESENCOFRADO EN MUROS DE ALETAS

m2

35.80

48.43

1,733.79

CONCRETO EN MUROS ALETAS F'C= 175 KG/CM2+30% P.G.

m3

11.04

281.02

3,102.46

CONCRETO ARMADO

29,460.37

ESTRIBOS

17,426.57

ACERO DE REFUERZO FY= 4200 KG/CM2 EN ZAPATAS DE ESTRIBOS

kg

427.49

3.67

ENCOFRADO Y DESENCOFRADO EN ZAPATAS DE ESTRIBOS

m2

9.62

48.43

465.90

CONCRETO F'C= 210 KG/CM2 EN ZAPATA DE ESTRIBOS

m3

15.60

334.54

5,218.82

ACERO DE REFUERZO FY= 4200 KG/CM2 EN PANTALLA ESTRIBOS

kg

460.01

3.67

1,688.24

ENCOFRADO Y DESENCOFRADO EN PANMTALLA DE ESTRIBOS

m2

53.62

48.43

2,596.82

CONCRETO F'C= 210 KG/CM2 EN PANTALLA DE ESTRIBOS

m3

17.60

334.54

5,887.90

APOYO FIJO

und

1.00

1,034.25

1,034.25

APOYO MOVIL

und

1.00

3,856.36

3,856.36

ACERO DE REFUERZO FY= 4200 KG/CM2 EN LOSA

kg

775.12

3.67

2,844.69

ENCOFRADO Y DESENCOFRADO DE LA LOSA

m2

21.76

53.64

1,167.21

CONCRETO F'C= 210 KG/CM2 EN LOSA

m3

9.36

334.54

3,131.29

ACERO DE REFUERZO FY= 4200 KG/CM2 EN VEREDAS

kg

259.20

3.67

951.26

ENCOFRADO Y DESENCOFRADO EN VEREDAS

m2

7.70

53.64

413.03

CONCRETO F'C= 210 KG/CM2 EN VEREDAS

m3

0.91

334.54

304.43

TUBERIA DE DRENAJE

1.20

10.61

12.73

11.00

230.00

2.00

615.23

LOSA

12,033.80

VEREDAS

1,681.46

BARANDAS
BARANDA METALICA DE 3"

2,530.00

SEALIZACION
SEALES INFORMATIVAS

2,530.00
1,230.46

und

OTROS

1,230.46
1,894.02

JUNTAS DE CONSTRUCCION
TEKNOPORT DE 1"

1,568.89

94.02
m2

11.14

8.44

94.02

FLETE
FLETE TERRESTRE

1,200.00
GLB

1.00

1,200.00

GLB

1.00

600.00

IMPACTO AMBIENTAL
IMPACTO AMBIENTAL
COSTO DIRECTO

1,200.00
600.00
600.00
54,633.59

GASTOS GENERALES (14.36%)

7,845.34

UTILIDAD (10%)

5,463.36
==============

SUB TOTAL

67,942.28

IGV (18%)

12,229.61
==============

VALOR REFERENCIAL
SUPERVISION Y LIQUIDACION (5.95%)
EXPEDIENTE TECNICO

80,171.90
4,770.55
7,350.00
==============

PRESUPUESTO TOTAL

92,292.45