Documente Academic
Documente Profesional
Documente Cultură
Description to amendment
Date
dd/mm/yy
01
25/05/2013
02
05/09/2013
Revision: 01
Amended
by
Page 2 of 16
BD-HSE-P-0001
TABLE OF CONTENTS
1.0
PURPOSE ..............................................................................................................................4
2.0
SCOPE ....................................................................................................................................4
3.0
REFERENCES .......................................................................................................................4
4.0
5.0
RESPONSIBILITIES .............................................................................................................6
6.0
PROCEDURE .........................................................................................................................7
7.0
RECORDS ............................................................................................................................16
8.0
ATTACHMENTS .................................................................................................................16
Revision: 01
Page 3 of 16
BD-HSE-P-0001
1.0
PURPOSE
The purpose of this Procedure is to communicate the requirements to be applied to Bien
Dong POC activities to protect the health and safety of personnel and environment to
comply with all relevant legislation. Bien Dong POC understands that assessing the risks
involved in all its operations is a key component in delivering a safe, efficient and trouble
free operation.
2.0
SCOPE
This procedure outlines the requirements that apply to all personnel either employed or
involved in Bien Dongs operations and activities wherever that may be, to ensure that
health, safety and welfare is not compromised due to hazards and risks embedded in the
work environment.
3.0
REFERENCES
OHSAS 18001:2007 Occupational Health and Safety Management Systems
ISO 14001:2004 Environmental Management Systems
HSE Management System (HSE Manual)
4.0
For the purposes of this standard the following definitions are to be utilized:
Hazard:
Any condition, situation or behavior which, if not rectified, has the potential to cause
personal injury, damage to the environment or equipment. In the context of risk
assessment, a hazard may also be an event that could impact the success of the operation.
The success of risk assessment depends on effectively identifying all the potential hazards
associated with the operation.
Hazard Consequence:
The hazard consequence relates to the possible impact of a particular hazard arising, to
either the safety of personnel / asset/environment or to the success of the operations.
Hazard consequences may be related to Health, Safety, Environmental, Operational,
Financial or Reputational risks. The consequence can be classified under three categories Low, Medium or High - as defined in this procedure.
Frequency of Occurrence
Revision: 01
Page 4 of 16
BD-HSE-P-0001
The frequency of occurrence relates to the probability of the particular hazard occurring.
The frequency of occurrence can be classified under the categories Very unlikely to Very
likely or/and Rare to Almost Certain as defined in this procedure.
Risk
The likelihood of an undesirable event (Hazard) occurring, by multiplying the likelihood
and potential outcome should the hazard occur (it includes Environmental Impact). Risk
can be the combination of the probability of an event (Hazard) and its consequence
(ISO/IEC Guide 73:2009).
Risk assurance
Part of HSE management system focused on providing confidence that risk control
requirements will be fulfilled.
Risk Management
Coordinated activities to direct and control an organization with regard to risk (ISO/IEC
Guide 73:2009)
HSE management system
Part of an organizations management system used to develop and implement its HSE
policy and manage its HSE risks.
Risk Level
The likelihood of the hazard causing harm or damage to personnel, property or equipment.
It is defined as a combination of the hazard consequence, and the frequency of occurrence
of the hazard. The risk of a hazard occurring can therefore be assessed by evaluating how
severe the consequence could be against how often the hazard could occur.
Control Measures
The safety or operational measures that are either already in place or that will be taken to
reduce the level of risk to an acceptable level.
Residual Risk
The levels of risk remaining after the identified control measures have been implemented.
There are two categories of residual risk - safety and operational.
As Low As Reasonably Practical (ALARP)
The principle of ALARP dictates that even if the risk can be shown to be tolerable, it
must be reduced until the cost of further improvement becomes grossly disproportionate to
the risk reduction achieved. This may still result in the residual risk being defined as
Medium or High.
BDPOC: Bien Dong Petroleum Operating Company
BOD: Board of Director
HSE: Health, Safety and Environment.
PIC: Person In Charge.
Revision: 01
Page 5 of 16
BD-HSE-P-0001
5.0
RESPONSIBILITIES
All persons who are working for or on behalf of Bien Dong are required to be aware of and
comply with this procedure. The Bien Dong HSE General Manager, who is responsible for
the implementation of HSE throughout the Bien Dong organization, shall be accountable
for ensuring that Bien Dong activities are conducted in compliance with this document.
Deviation from procedure implies a contravention of policy.
5.1
Board of Director
Overall accountable for ensuring that all process associated with Hazard and
Environmental Aspect Identification/ H&S Risk assessments and Environmental Impacts
assessment are defined, controlled, followed and updated as required.
BOD has overall responsibility for ensuring that all potential new business is subject to a
thorough assessment of the H&S risks and environmental impacts from all aspects of
BDPOCs business (HSE, Operations and Financial, Reputational - if any).
5.2
Department Personnel
Department Managers are responsible for ensuring that this procedure is thoroughly
applied and implemented at worksites within their area of responsibility
Drilling / Operations manager has overall accountability for ensuring that all process/
procedures associated with risk assessments and environmental impacts are followed and
updated as required. Responsible for ensuring risk assessments and environmental impacts
are performed for all well operations in accordance with this procedure
The Drilling Superintendent / Lead Supervisor/Production OIM shall be responsible for:
The composition of the Risk Assessment Team and ensuring it is appropriate
Ensuring that risk assessments are maintained, updated and approved through the
lifecycle of the work scope
Ensuring that risk assessment documentation is filed in the appropriate location
The risk assessment is carried out as per this procedure
The personnel assigned to the Risk Assessment Team are present at the risk
assessment
All actions from the risk assessment are documented and closed out prior to the
operations commencing
5.3
HSE Manager
Review HSE plan where it is issued.
Review HAZID, HAZOP and control measure
Review all HSE Objectives includes Departments HSE Objective before approval
Review all HSE performances, monitoring and measurement results
Revision: 01
Page 6 of 16
BD-HSE-P-0001
5.4
6.0
RISK MANAGEMENT
This document shall be updated under the supervision of the Bien Dong HSE General
Manager. Recommendations for revision and updates shall be carried out in accordance
with change control procedures. Recommendation will then be made to the Bien Dong
Board of Director for consideration, and if appropriate, approval and dissemination.
6.1
6.2
Flow Chart
Revision: 01
Page 7 of 16
BD-HSE-P-0001
Relevant
person/section
Management
Relevant
Department
Relevant
Department
Relevant
Department
Processes
Define Scope of Risk
Management/Risk Policy and
Planning
Risk Recognition
(Identify Hazard/
Environmental Aspects)
Risk Prioritization
(Evaluate Risk/
Environmental Impacts
Managing Risk/Reduction
measure/Safety Assurance
Relevant
Department
Implementation/Monitoring
and Measurement
Relevant
Department
Relevant
Department
Revision: 01
Tasks
Page 8 of 16
BD-HSE-P-0001
6.3
Description
6.3.1
Risk Policy
Top Management of BDPOC defined HSE policy. It is appropriate to the nature and scale
of the Companys HSE risks and environmental impacts, it includes a commitment to
prevention of injury and ill health and continual improvement in HSE management and
HSE performance and commitment to comply at least with applicable legal requirements
and with other requirements to which the company subscribes that relate to its HSE
hazards.
Risk Management will be applied for all Bien Dong POC activities.
Planning is the strategy and tactics for achieving success. Top Management of BDPOC
carry out as a minimum
-
6.3.2
Annual HSE objectives planning and resource allocation at relevant functions and
levels within the Bien Dong POC and consistent with the HSE policy as well as
essence of risk.
Relevant action plans defined with designation of responsibility and authority, means
and time-frame for achieving objectives at relevant functions and levels of the
company and responsibilities.
Beside routine activities which controlled by HSE system, to control strictly of risk and
environmental impact, other high risk or non- routine activities (such as major
modification, Well Clean Up, SIMOPS, Start-up of operation...) are also considered to
establish HSE plan (BD-HSE-P-0001/F4) through risk assessment.
Context establishment defines what is at risk. The context can be defined at all
operational levels of company included a description of both internal and external
factors, stakeholders.
- Hazard/ Environmental Aspect Identification are the identification of uncertain events
and their associated consequences.
Selection of methods
The level and extent of Hazard/ Environmental aspect identification and risk/ impact
assessment activities vary depending on the scale of the installation and the stage in the
installation life cycle when the identification and assessment process is undertaken
+ For design and safety assessment (DSA), the procedure Design & safety assessment
procedure will be applied.
Revision: 01
Page 9 of 16
BD-HSE-P-0001
Page 10 of 16
BD-HSE-P-0001
-
JSA is appropriate for any critical job where the hazards and control measures need to
be formally assessed. The most common areas of application are: Routine job that have
the potential for serious incidents, routine job having a history of incidents, including
near misses, new job or job introducing new work methods, routine job being carried
out in unusual circumstances, non-routine or one-off job.
Phase
Conceptual Design
Detailed Design
Front End
Engineering Design
Operation
Any design criteria, safety critical elements developed during these early stages need to be
verified during commissioning for effectiveness from HSE point of view.
Hazard/ Environmental aspect identification and risk/ impact assessment activities may
need to be reviewed and updated if significant new issues are identified or if there is
significant change to the installation.
If there is no significant change these can be done in operation phase through activities,
task safety risk/environmental impact should be detailed from practical conditions and
study procedure and yearly updated.
It is strongly recommended that whenever a hazard is identified using one of the above
methods during operational phase, process safety is also considered. The best and most
effective risk management is achieved by selecting and implementing processes which are
inherently safe. Operational risk controls measures have human interaction to a great extent
and residual risk during operational phase always remains high, whereas by adopting
process safety measures residual risk is minimized to a great extent.
Refer Appendix 1: Guideline for Risk Assessment, Appendix 2 Risk Assessment Help
Card
b) Risk prioritisation (Risk/ Environmental Impact Analysis and Assessment):
Once the risks/ impacts are identified, the next stage is to understand the nature and
importance of them so that they can be managed appropriately. The risk prioritisation
phase has two parts:
Risk analysis/ Environmental Impact: Risks are analysed using either qualitative or
quantitative methods. The method chosen depends on the level of detail required for
decision making and the scope for quantifying the type of risk in question. Risk analysis is
based on two factors: likelihood and consequence.
Revision: 01
Page 11 of 16
BD-HSE-P-0001
The likelihood for common events is often calculated using a frequency approach, while
the Likelihood of infrequent events is often calculated using a probabilistic approach,
which is based on structured predictive analysis. The consequence can be measured in
many ways, such as effects on results or on the enablers of results. With qualitative
approaches risks are analysed against pre-defined bands of likelihood and consequence;
while with quantitative approaches a value is put on each risk.
RISK MATRIX
CONSEQUENCES OF HAZARD
ENVIRONMENTAL
SIGNIFICANT
IMPACT/ LONG
TERM FOR
TREATMENT
SIGNIFICANT
IMPACT/ SHORT
TERM FOR
TREATMENT
MINOR
IMPACT/ LONG
TERM FOR
TREATMENT
MINOR
IMPACT/
SHORT TERM
FOR
TREATMENT
NO MEASURABLE
EFFECT
INCIPIENT OR
SLIGHT
EFFECT
NO
MEASURABLE
EFFECT
HEALTH
LOSE
STRENGTH
LOSE HEALTH
SERIOUS
ILLNESS
MULTIPLE
FATALITIES
SINGLE
FATALITY/MAJO
R ACCIDENT
SEVERE
INJURY
LOST TIME
INFURY
NO SIGNIFICANT
EFFECT, FIRST
AID
DISEADE &
TREATMENT
SAFETY
FREQUENCY
(LIKELIHOOD)
5
4
3
2
1
Several
Single
Likely
Unlikely
-1
>10
10 to 10-3
10-3 to 10-4
10-4 to 10-5
<10-5
Very unlikely
-1
High Risk
(H)
Medium Risk (M)
Low Risk
(L)
Several
Single
Likely
Unlikely
Very unlikely
For semi quantitative analysis, BDPOC have applied Individual Risk per Annum (IRPA) in
judging the acceptability of risk and deciding how necessary to identify, assess and
implement risk reduction measures.
BDPOC acceptance criteria have been developed with reference to Vietnamese standard, in
which the intolerable boundary is a chance of one serious incident over 1.000 per annum
(greater 1x10-3 per year). The negligible boundary is a chance of one serious incident over
100.000 per annum (lower 1 x 10-5 per year), which is the risk of incident at work in the
very safest part of the industry.
Revision: 01
Page 12 of 16
BD-HSE-P-0001
Unacceptable
High Risk
Increased Risk
ALARP Region
Medium Risk
Lower tolerable Limit 10-5
Acceptable Risk
Low Risk
c) Managing Risk
This risk assurance process requires that: All significant risks arising from the studies
and the associated actions required to reduce these risks to acceptable levels are captured in
a Risk Tracking Register (Summary of Risk BD-HSE-P-0001/F02). The Register will
cover all such risks for the asset and should be owned by the relevant Line Manager;
At the secondly implementation or/ and update, BD-HSE-P-0001/F02 will be applied to
monitor result from previous assessment. HSE Manager is responsible for yearly approval
all BD-HSE-P-0001 /F2.
Revision: 01
Page 13 of 16
BD-HSE-P-0001
This Risk Tracking Register is regularly updated to monitor the status of all such risks and
actions. All risks which have been identified as requiring further work shall be tracked
until closed out. This process is identical to that which should be in place to manage
change and to implement recommendations arising from accident investigations and audits.
Decision-making should be as objective as possible. It should be recognised, however, that
decision-making is often very subjective, being influenced by psychological biases and
social pressures. Decisions are guided using models that categorise risk measures. The
simplest of these is the four Ts model described below.
TERMINATE
Avoid or
eliminate the and/or
loss exposure
TREAT
Risk and loss
control
activities
and/or
TOLERATE
Acceptable
level of Risk
and/or
TRANSFER
Insurance or
non-insurance
After the relevant Hazards/ Environmental Aspects have been identified, the Risks and
Environmental Impacts arising from them are evaluated either qualitatively or, if
appropriate, quantitatively. Risk reducing measures implemented as per ALARP.
If the specified risk tolerability criteria are not met then action is required to mitigate the
risk and thus ensure compliance with these criteria. The most appropriate risk mitigation
measures often involve a combination of controls. The mitigation hierarchy below must be
applied. Hazards not removed are termed residual risks and must be analysed in further
detail if they are still deemed to be not acceptable.
Risk Mitigation Controls
Increasing Control
The most appropriate risk mitigation measures often involve a combination of controls.
The mitigation hierarchy below must be applied. Hazards not removed are termed residual
risks and must be analysed in further detail if they are still deemed to be not acceptable.
Revision: 01
1 - ELIMINATE
Remove the risk entirely most preferred
option
Complete removal of the hazard. Hazards are designed out wherever this is
practical
2 - SUBSTITUTE
Use methods, tools, materials, equipment etc.
that have a lower inherent hazard
3 - ENGINEER
Provide an engineered solution to the risk
4 - ADMINISTRATIVE CONTROLS
Establish a procedure or instruction that
reduces the exposure
5 - PPE
The last line of defence least preferred
option
Personal Protective Equipment (PPE). The role of PPE is as a control measure, i.e.
it is used to minimise the consequences on an individual should an accident occur.
PPE does not eliminate risk or hazards.
Page 14 of 16
BD-HSE-P-0001
All High Risk environmental aspects are Significant Environmental Aspects. They should
be managed either by having an objective or operation control procedure.
6.3.3
Revision: 01
Page 15 of 16
BD-HSE-P-0001
6.3.4
6.3.5
7.0
RECORDS
The following records shall be retained as evidence of this procedures application:
No
Name of record
Hazard/Environmental
Aspect Register
Summary of Risk
SIMOPS
HSE Plan
2
3
4
8.0
BD-HSE-P-0001/ F1
Responsibility of
keeping
Relevant Depts
Time of
keeping
2 years
BD-HSE-P-0001/ F2
BD-HSE-P-0001/ F3
BD-HSE-P-0001/ F4
Relevant Depts
Relevant Depts
Relevant Depts
2 years
3 years
3 years
Code of Form
ATTACHMENTS
-
Revision: 01
Page 16 of 16
APPENDIX 1
GUIDLINE FOR RISK ASSESSMENT
PREPARATION
All reference documentation associated with the proposed operation being risk assessed shall be
available to the risk assessment facilitator / team. This shall include, but not be limited to:
Outline of proposed work location (including historical and current political / civil issues)
Outline of work program
Well information
Risk assessments from previous similar operations
Rig-up / equipment procedures
Relevant layout diagrams
Generic risk assessments
Relevant Bien Dong policies and procedures
Service providers generic risk assessments
Service providers procedures, etc.
RISK ASSESSMENT
The risk assessment shall be documented on the Risk Assessment Form BD-HSE-P-0001/ F01
the risk assessment shall:
Identify the operational steps to be risk assessed entered in the Risk / Hazard column
Identify possible risks and hazards associated with the operation - These hazards shall then be
documented in the Risk / Hazard column
Note: The Risk Assessment Help Card (Appendix 1) can be used to assist with hazard identification.
List the consequences of each risk / hazard in the Consequence column
Assess the severity of the consequence by assessing the Safety, Environmental impact, and by
assigning a consequence rating from the consequence table detailed in procedure - This
information shall be documented in the Consequence column
Assess the frequency of the hazard occurring and assign a frequency rating from the frequency
table in procedure. This information shall be documented in the Frequency column
Assess the risk of a hazard occurring based on the risk level matrix defined in procedure. This
information shall be documented in the Risk column
Having determined the risk of each hazard, identify all the appropriate control measures
required to reduce this risk to as low as reasonably practical. This information shall be
documented in the Control actions to Reducing Risks/ Environmental Impacts" column
Note: Control measures may be references to procedure with 5 levels control.
Assign a residual safety risk and a residual operational risk based on the control measures defined in
previous bullet. This information shall be documented in the Residual Risk column
Appendix 1
Page 1 of 2
If the residual safety and / or operational risks are not low, identify additional control measures
that can be taken. These shall be documented in the " Control actions to Reducing Risks/
Environmental Impacts"
Once the additional control measures have been identified, re-evaluate the risks
Re-assign the residual risk levels and enter the revised ratings in the Residual Risk column
If the residual level of operational risk is medium or high, seek the Project/Department
Managers approval to proceed
If the Project/Department Manager gives approval, proceed to the next step. If not, an
alternative solution must be found and the risk associated with it assessed before the operation
can proceed
The control measures identified in the risk assessment will be included in the work program or
the procedures referenced within it.
Appendix 1
Page 2 of 2
APPENDIX 2
When examining an activity in order to identify potential hazards, there are a number of basic questions
which may assist the process. It is important to identify all the significant hazards. The questions below are
intended to assist. You should not, however, allow yourself to be limited to these questions.
Useful Questions:
When will the job be done? (Daytime, night-time, time of year etc.)
Where will the job be done? (Remote area, at height, confined space etc.)
APPENDIX 3
THE HAZARDS AND EFFECTS CHECKLIST
Safety hazards
F = Flammable
MH = Major hazard
Se = Security hazard
WP = Work practice
Hazard
No
Health hazards
B = Biological agent
C = Chemical agent
E = Ergonomic agent
P = Physical agent
LS = Life style agent
Psy = Psychological agent
M = Medical issue
Hazard
Description
Sources
Environmental hazards
D= Discharge hazards
R = Use of natural resources
Pr = Presence
Safety Health
Env.
01
Hydro carbon
01.01
01.02
Hydrocarbons in
formation
01.03
LPGs (e.g.
Propane)
Process fractionating
equipment, storage tanks
MH
01.04
LNGs
MH
01.05
Condensate, NGL
MH
01.06
Hydrocarbon gas
MH
01.07
MH
01.08
Wax
01.09
Coal
02
Refined hydrocarbon
02.01
02.02
Hydraulic oil
02.03
Diesel fuel
Engines, storage
Appendix 3
MH
MH
Eff.
D
D
Page 1 of 11
02.04
Petroleum
spirit/gasoline
03
03.01
Cellulosic materials
03.02
Pyrophoric
materials
04
04.01
Detonators
04.02
Conventional
explosive material
04.03
Perforating gun
charges
05
05.01
05.02
Water under
pressure in
pipeworks
05.03
05.04
05.05
05.06
05.07
Non-hydrocarbon
gas under pressure
in pipeworks
Air under high
pressure
Hyperbaric
operations (diving)
Decompression
(diving)
Oil and
hydrocarbon gas
under pressure
06
Storage
WH
C
C
Pr
MH
WP
WP
MH
WP
Undersea operations
WP
Undersea operations
WP
WP
06.01
Personnel at height
>2 m
06.02
Personnel at height
<2 m
Slippery/uneven surfaces,
climbing/descending stairs,
obstructions, loose gratings
Appendix 3
MH
WP
Page 2 of 11
06.03
Overhead
equipment
06.04
Personnel under
water
07
Objects under
tension
07.02
Objects under
compression
08
08.01
On-water transport
(boating)
08.02
In-air transport
(flying)
08.04
08.05
08.06
08.07
MH
07.01
08.03
MH
Boat collision
hazard to other
vessels and
offshore structures
Equipment with
moving or
rotating parts
Use of hazardous
hand tools
(grinding, sawing)
Use of knives,
Galley, seismic line clearing,
machetes and
grubbing operations
other sharp objects
Transfer from boat
Basket transfer, rope transfer
to offshore platform
09
WP
WP
MH
MH
WP
WP
WP
WP
Environmental hazards
09.01
Weather
09.02
Sea state
09.03
Tectonic
10
Appendix 3
WP
MH
MH
Hot surfaces
Page 3 of 11
10.01
10.02
10.03
10.04
Steam piping
11
Temperatures
between
100 C and 150 C
11.02
Temperatures
greater than
150 C
12.01
12.02
13
13.01
14
14.01
14.02
14.03
15
MH
WP
WP
WP
MH
MH
MH
Hot fluids
11.01
12
WP
Cold surfaces
Cold ambient climate, JouleProcess piping
Thomson expansions (process
between
and leaks), propane
25 C and 80 C refrigeration systems, LPG gas
plants
Cryogenic plants, LNG plants,
Process piping less
LNG storage vessels including
than
tankers, vapour lines off liquid
80 C
nitrogen storage
Cold fluids
Oceans, seas and
Northern and Southern oceans
lakes less
and lakes
than 10 C
Open flame
Glycol reboilers, amine
Heaters with fire
reboilers, salt bath heaters,
tube
water bath heaters (line heaters)
Hot oil furnace, Claus plant
reaction furnace, catalyst and
Direct-fired
desiccant regeneration gas
furnaces
heaters, incinerators, power
boilers
Pressure-relief and blowdown
Flares
systems
Electricity
Appendix 3
Page 4 of 11
15.01
Voltage > 50 V to
440 V in cables
15.02
Voltage > 50 V to
440 V in
equipment
15.03
15.04
15.05
Electrostatic energy
16
16.01
16.02
16.03
16.04
16.05
MH
WP
MH
WP
WP
Electromagnetic radiation
Ultraviolet
radiation
Infrared radiation
Microwaves
Lasers
E/M radiation: high
voltage AC
cables
17
Flares
Galley
Instrumentation, surveying
P
P
P
17.01
Alpha, beta
Open source
17.02
Gamma rays
Open source
17.03
Neutron - Open
source
Well logging
17.04
Naturally occurring
ionizing
radiation
18
18.01
Alpha, beta
Closed source
18.02
Gamma rays
Closed source
18.03
Neutron Closed
source
Well logging
19
Appendix 3
Asphyxiates
Page 5 of 11
19.01
Insufficient oxygen
atmospheres
19.02
Excessive CO2
19.03
Drowning
19.04
Excessive N2
19.05
Halon
19.06
Smoke
20
20.01
H2S (hydrogen
sulfide, sour gas)
20.02
Exhaust fumes
20.03
SO2
20.04
Benzene
20.05
Chlorine
20.06
Welding fumes
20.07
Tobacco smoke
Accommodation, office
buildings, boats, aircraft
20.08
CFCs
21
C
C
MH
LS
D
Toxic liquid
21.01
Mercury
21.02
PCBs
21.03
Biocide
(Gluteraldehyde)
21.04
Methanol
21.05
Brines
Appendix 3
Page 6 of 11
21.06
Glycols
21.07
Degreasers
(terpenes)
Maintenance shops
21.08
Isocyanates
21.09
Sulfanol
Gas sweetening
21.10
Amines
Gas sweetening
21.11
Corrosion inhibitors
21.12
Scale inhibitors
21.13
Liquid mud
additives
21.14
Odorant additives
(mercaptans)
21.15
Alcohol-containing
beverages
21.16
21.17
21.18
21.19
Non-prescribed
drugs
Used engine oils
(polycyclic
aromatic
hydrocarbons)
Carbon
tetrachloride
Grey and/or black
water
22
22.01
Asbestos
22.02
Man-made mineral
fibre
22.03
Cement dust
WP
LS
WP
LS
Plant laboratory
22.06
Sodium
hypochlorite
Powdered mud
additives
Sulfur dust
22.07
Pig trash
22.08
Oil-based muds
Pseudo-oil-based
muds
22.04
22.05
22.09
Appendix 3
Page 7 of 11
22.10
Water-based muds
22.11
Cement slurries
22.12
Dusts
22.13
22.14
Cadmium
compounds and
other
heavy metals
Oil-based sludges
23
23.01
23.02
Hydrofluoric acid
Hydrofluoric acid
23.03
Sulfuric acid
23.04
Caustic soda
(sodium hydroxide)
C
C
D
D
Corrosive substances
Well stimulation
WP
Well stimulation
WP
Wet batteries, regenerant for
WP
reverse-osmosis water makers
Drilling fluid additive
24
24.01
24.02
24.03
24.04
24.05
24.06
Biological hazards
Food-borne bacteria
Contaminated food
(e.g E. coli)
Water-borne
bacteria
(e.g Legionella)
Parasitic insects
(pin worms, bed
bugs, lice, fleas)
Cold and flu virus
Human Immune
deficiency Virus
(HIV)
Other
communicable
diseases
25
Other people
Other people
Ergonomic hazards
25.01
Manual materials
handling
25.02
Damaging noise
25.03
25.04
Appendix 3
WP
Pr
Pr
Page 8 of 11
summer
25.05
25.06
High humidity
25.07
Vibration
25.08
Workstations
25.09
Lighting
25.10
Incompatible hand
controls
25.11
Awkward location
of workplaces and
machinery
25.12
Mismatch of work
to physical abilities
25.13
Mismatch of work
to cognitive
abilities
25.14
25.15
Poor organization
and job
design
Appendix 3
Pr
Pr
Page 9 of 11
25.16
Work planning
issues
25.17
26
Psychological hazards
26.01
Living on the
job/away from
family
26.02
26.03
Post traumatic
stress
26.04
Fatigue
26.05
Shift work
26.06
Peer pressure
27
Psy
Psy
Psy
Physically demanding or
arduous work, long or excessive
working hours.
Construction, operations or
drilling activities involving 24
hour working, saturation diving
operations, changing rest and
sleep patterns associated with
activities.
Pressure from others at the
work location to behave in a
manner which may affect wellbeing of the individual
Psy
Psy
Psy
27.01
Piracy
Se
27.02
Assault
Se
27.03
Sabotage
Se
Appendix 3
Page 10 of 11
27.04
Crisis (military
action, civil
disturbances,
terrorism)
Se
27.05
Theft, pilferage
Se
28
28.01
Water
Cooling water
28.02
Air
29
Medical
29.01
Medical unfitness
29.02
Motion sickness
30
30.01
High-level noise
30.02
Intrusive noise
31
M
M
Psy
31.01
Fire / explosion
31.02
Mechanical
damage
WP
31.03
Diving
WP
Appendix 3
MH
Page 11 of 11
Task
Hazards /
Environmental
Aspects
DATE:
S
R.N
E
R.N
Descriptions
(Risk/Impacts)
REVISION:
Risk Assessment /
Environmental Impact
Evaluation
(C=FxS)
F
BD-HSE-P-0001/F1
Revision: 02
DEPARTMENT/LOCATION
Form code
Residue
Risk /
Impact
(**)
Indicates for
supervision/
Monitoring of
controlled
action(***)
Note:
1. Abbreviations: R: Routine, N: Non routine, E: Emergency, H: health, S: Safety, En: Environment; C=FxS (C: Consequence, F: Frequency, S: Severity).
2. (*) Control action to reducing risks/ environmental Impacts ( Ex: Level 1- Eliminate , Level 2 Substitute, Level 3 Engineer, Level 4 Administrative
controls, Level 5 PPE)
3. (**) Residue Risk/ Impact after controlling action are implemented (mark point - Include frequency and severity after the control)
4. (***) Indicators for supervision/ Monitoring of controlled action: Examples: Number of incident/ accidents, rates of Occupational Diseases, micro
Environment Monitoring and Measurement, number of near-miss, Hazard report card, )
Prepared by
Reviewed by
Approved by
Page 1 of 1
Form code
BD-HSE-P-0001/F2
Revision: 01
DEPARTMENT
NO
Hazards / Environmental
Aspects
Prepared by
DATE:
Risks /
Environmental
Impacts
Area/ Location
REVISION:
Results of Risk
Description of
Assessment /
Emergency Situation/
Env. Impact
Result of changing from
previous Assessment
H
M
L
Reviewed by
Approved by
Page 1 of 1
Form code
BD-HSE-P-0001/F3
SIMULTANEOUS OPERATIONS
Revision: 01
SIMULTANEOUS OPERATIONS
FOR
WELLHEAD PLATFORM
DRILLING, COMMISSIONING &
PRODUCTION OPERATIONS
Rev
.
Eff. date
Originator
Reviewed by
Contractor
HSE GM
D&C GM
Approved by
OPS GM
OHSE Rep.
Page 1 of 1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
INTRODUCTION
SIMULTANEOUS OPERATIONS SAFETY AND ENVIROMENTAL POLICY
HAZARD INDENTIFICATION AND ASSESSMENT
SIMULTANEOUS OPERATIONS MANAGEMENT STRUCTURE
MANAGEMENT OF PERSONNEL
TRAINING
COMMUNICATION ARRANGEMENTS
PLATFORM WORK CONTROL ARRANGEMENTS
SIMULTANEOUS OPERATIONS LOGISTICS MANAGEMENT
CONTROL AND COMMUNICATION WHEN POSITIONING TAD RIG
INTERFACES BETWEEN INSTALLATIONS
SIMULTANEOUS OPERATIONS ENVIROMENTAL COMPLIANCE
OCCUPATIONAL HEALTH ISSUES
SIMULTANEOUS OPERATIONS EMERGENCY RESPONSE
SIMOPS HSE PERFORMANCE REPORTING AND REVIEW
INCIDENT REPORTING AND INVESTIGATION 44
SIMOPS CONTACTS
APPENDICES
Page 2 of 2
Form code
BD-HSE-P-0001/F4
HSE PLAN
Revision: 01
Rev.
Eff. date
Reviewed by
Originator
HSE GM
D&C GM
Approved by
OPS GM
OHSE Rep.
Page 1/ 2
1.0
PURPOSE
2.0
SCOPE
3.0
REFERENCES
4.0
RESPONSIBILITIES
5.0
6.0
PROCEDURE
7.0
RECORDS
8.0
ATTACHMENTS
Page 2/ 2