Documente Academic
Documente Profesional
Documente Cultură
The combined effects of traffic loading and the environment will cause every
pavement, no matter how well-designed/constructed to deteriorate over time.
Maintenance and rehabilitation are what we use to slow down or reset this
deterioration process. Maintenance actions, such as crack sealing, joint
sealing, fog seals and patching help slow the rate of deterioration by identifying
and addressing specific pavement deficiencies that contribute to overall
deterioration. Rehabilitation is the act of repairing portions of an existing
pavement to reset the deterioration process. For instance, removing and
replacing the wearing course in a pavement provides new wearing course
material on which the deterioration process begins anew. Reconstructing an
entire pavement, however, is not considered rehabilitation but rather new
construction because the methods used are generally those developed for new
pavement construction. This section will discuss the following:
Maintenance options for flexible and rigid pavement. Basic preventive and
corrective maintenance options.
Rehabilitation options
for flexible and rigid pavement. Basic
rehabilitation options to include
overlays and their design procedures.
2 FLEXIBLE - MAINTENANCE
Pavement maintenance describes all the
methods and techniques used to preserve
pavement condition, safety, and ride quality,
and therefore aid a pavement in achieving
its design life (Hall et al., 2001). The
performance of a pavement is directly tied to
the timing, type and quality of the
maintenance it receives. This section, taken
largely from Roberts et al. (1996), describes
the more common U.S. preventative and
corrective maintenance options for HMA
pavement. The timing of these maintenance
items is discussed in Pavement Management.
2. Rejuvenators
3
2. Slurry Seals
4
2. Bituminous Surface
5 Treatments
2. Non-Structural Overlays
6
2. Patching
7
2. Summary
8
often too extensive to warrant filling with crack sealer; they usually require an
area treatment such as a patch or reconstruction. Crack filler material is
typically some form of rubberized asphalt or sand slurry.
Other
Info:
Other
Info:
Fog seals are suitable for low-volume roads which can be closed to
traffic for the 4 to 6 hours it takes for the slow-setting asphalt
emulsion to break and set.
An excessive application rate may result in a thin asphalt layer on
top of the original HMA pavement. This layer can be very smooth
and cause a loss of skid resistance. Sand should be kept in reserve
to blot up areas of excess application.
2.3 Rejuvenators
Rejuvenators are products designed to restore original properties to aged
(oxidized) asphalt binders by restoring the original ratio of asphaltenes to
maltenes. Many rejuvenators are proprietary, making it difficult to offer a good
generic description. However, many rejuvenators contain maltenes because
their quantity is reduced by oxidation. Rejuvenators will retard the loss of
surface fines and reduce the formation of additional cracks, however they will
also reduce pavement skid resistance for up to 1 year (Army and Air Force,
1988). Because of this, rejuvenators are generally appropriate for low-volume,
low-speed roads or parking lots.
Purpose Preventive maintenance. Restore original properties to aged
:
asphalt binder. Rejuvenators may be able to postpone the need for
a BST for a year or two.
Material
s:
Mix
Design:
Other
Info:
Other
Info:
Enhance appearance.
2.6.1 Categories
Non-structural overlays can vary widely in composition depending upon local
practice, traffic and general purpose. A loose classification of non-structural
overlays follows (NAPA, 1995):
1. Light volume/residential traffic. The primary objective in light traffic areas
is to retard asphalt binder aging of the underlying pavement. Since heavy
traffic loads are not of great concern, overlays are generally less stiff
(resulting in a more workable mix, increased durability and flexibility and a
potential for the overlay to reheal under traffic) and use smaller-sized
aggregates.
2. Heavy, high-speed traffic. The primary objective in heavy, high-speed
traffic areas is to prevent rutting and provide good friction. Because of
this, overlays typically use larger angular aggregate and more durable
mixes such as SMA or OGFC.
Thin lifts require less HMA per foot of road length than thick lifts. This can
result in high paver speeds (in excess of 21 m (70 ft.) per minute).
Compaction may not be able to keep pace with these high speeds.
Thin lifts will cool quicker than thick lifts. This can result in little time
available for compaction before the thin overlay reaches cessation
temperature (sometimes as little as 3 to 5 minutes). Therefore, roller
variables should be set to account for this (e.g., enough rollers and an
adequate roller pattern to compact the material before it reaches
cessation temperature).
Thin lift construction produces greater screed wear. If the lift depth is less
than about twice the maximum aggregate size, the HMA may tear under
the paver screed. Very thin lifts (less than 25 mm (1 inch)) can be
damaged by the screed dragging large particles.
Density control is difficult. Thin lifts provide fewer options for aggregate
particles to rearrange under compaction. Thus, mat densities will tend to
be less uniform than those associated with a thicker lift. This should be
recognized if pay is in any way tied to mat density.
2.7 Patches
Patches are a common method of treating an area of localized distress. Patches
can be either full-depth where they extend from the pavement surface to the
subgrade (see Figure 10.12) or partial where they do not extend through the full
depth of existing pavement (see Figure 10.13).
Full-depth patches are necessary where the entire depth of pavement is
distressed. Often times, the underlying base, subbase or subgrade material is
the distresses root cause and will also need repair. Partial depth patches are
used for pavement distresses like raveling, rutting, delamination and cracking
where the depth of crack does not extend through the entire pavement depth.
Patching material can be just about any HMA or cold mix asphalt material as well
as certain types of slurries. Typically some form of HMA is used for permanent
patches, while cold mix is often used for temporary emergency repairs.
One form of patching, pothole patching, probably receives the greatest amount
of public attention. Pothole patching procedures cover a wide range of methods
and intentions from permanent full-depth patches to temporary partial depth
patches. Two general patching procedures are described next.
Semi-Permanent Pothole Patch (see Figures 10.14 and 10.15) (from
FHWA, 1998)
1. Remove all water and debris from the pothole.
2. Square up the pothole sides so they are vertical and have in-tact
pavement on all sides.
3. Place the patching material into the clean squared-up hole. The material
should mound in the center and taper down to the edges so that it meets
flush with the surrounding pavement edges.
4. Compact the patching material starting in the center and working out
toward the edges. Compaction can be accomplished using a vibratory
plate compactor or a single-drum vibratory roller. Check the compacted
patching material for a slight crown. This is done so that subsequent
traffic loading will compact it down to the surrounding pavement height.
1. Place the patching material into the pothole without any preparation or
water/debris removal.
2. Compact the patching material using the patching truck tires (usually 4 to
8 passes).
3. Check the compacted patch for a slight crown. If a depression is present
add more patching material and compact.
Although it may seem that the semi-permanent technique would produce a
higher quality patch than the throw-and-roll technique, the FHWA's Long Term
Pavement Performance (LTPP) Study found that the "throw-and-roll technique
proved just as effective as the semi-permanent procedure for those materials for
which the two procedures were compared directly" (FHWA, 1998). Since the
semi-permanent technique is more labor and material intensive, the throw-androll technique will generally prove more cost effective if quality materials are
used.
2.8 Summary
Pavement maintenance prolongs pavement life by slowing its deterioration rate.
This section has described some of the more common maintenance options in
the U.S. Each option's effectiveness is dependent upon a multitude of local
conditions. For most smaller agencies, the best advice when considering
pavement maintenance options is to talk to local contractors and nearby
agencies about what types of maintenance options have worked best in your
local area.
3 FLEXIBLE - REHABILITATION
Engineering judgment
Component analysis
Mechanistic-empirical analysis
is milled. All three types of rigid pavement (JPCP, JRCP and CRCP) have been
successfully used as classical whitetopping (McGhee, 1994).
The chief advantage of classical whitetopping is that it requires minimal surface
preparation. However, minimum overlay thicknesses tend to be in the 125 - 175
mm (5 - 7 inch) range, which is quite thick and possibly unsuitable in situations
where a specific elevation must be maintained such as in curbed areas or under
bridges.
The design procedure contained in
the 1993 AASHTO Guide is virtually
identical to the AASHTO empirical
design for new rigid pavements
with one exception: The effective
modulus of subgrade reaction (k) is
determined based on the existing
flexible pavement resilient
modulus. Although perfectly
acceptable, this method gives little
credit to the existing pavement's
remaining strength.
Figure 10.16: Thin Composite
Whitetopping at the Mn/ROAD Test
3.2.2 Bonded - Thin Composite Facility
Whitetopping
Thin composite whitetopping (see Figure 10.16) is a PCC overlay intentionally
bonded to an existing flexible pavement with a PCC slurry or grout in order to
create a composite pavement section (Mack, Hawbaker and Cole, 1998). This
composite section, acting as a single layer, is thicker than just the PCC overlay
and thus, results in substantially reduced maximum slab tensile stresses (on the
order of 1/2 for edge stresses and 1/4 for corner stresses) (Mack, Hawbaker and
Cole, 1998). Overlay thicknesses tend to be 50 - 175 mm (2 - 7 inches) thick but
can be thicker for high volume roads; overlays in the 50 - 100 mm (2 - 4 inches)
range are often referred to as "ultra-thin whitetopping" (UTW). Thin white
topping (i.e., bonded PCC overlay greater than 100 mm (4 inches) thick) is
considered appropriate for all situations and traffic levels. UTW as conceived and
developed in the early 1990's is intended more for lower-volume roads, vehicular
parking areas and light duty airports (Mack, Hawbaker and Cole, 1998).
The chief advantage of thin composite whitetopping is that it can be made
thinner than classical whitetopping because of the composite layer action.
However, issues with slab size, joint location and bonding effectiveness can
complicate its use. This subsection covers:
Structural design
Joint design
Other considerations
Reduces the moment arm of the applied wheel load and minimizes the
stresses due to bending.
Reduces the curling and warping stresses by reducing the size of the slab
that can curl or warp.
Because of the short joint spacing, the overlaid PCC slabs transfer load to the
underlying flexible pavement by deflecting downward as a unit rather than
bending (Mack, Hawbaker and Cole, 1998). Figures 10.17 and 10.18 show two
different joint spacings.
3.3 Summary
Rehabilitation essentially reverses the effects of deterioration by adding or
replacing material in the existing pavement structure. Although there are
several common methods of rehabilitation (HIPR, CIR and overlays) this section
has concentrated on structural overlays - those used to increase a pavement's
structural capacity. Non-structural overlays are treated in Flexible Maintenance.
New road construction in the U.S. is not nearly as prolific as it has been in
previous generations. Urban areas have filled out greatly and the ratio of
existing roads to new roads is now quite high. Consequently, rehabilitation (and
not new construction) has become the dominant force in today's pavement
design and construction arenas.
4 RIGID - MAINTENANCE
Slab stabilization only fills the voids under a slab, it should not be
confused with slab jacking, which is used to raise the elevation of a
depressed slab.
4.4 Patches
Rigid pavement patches are used to treat localized slab problems such
as spalling, scaling (e.g., reactive aggregate distress, over-finishing the
surface), joint deterioration, corner breaks or punchouts. If the problem is
limited in depth, then a partial depth patch may be appropriate, otherwise a full
depth patch is recommended. A high quality patch can be considered a
permanent repair, although all patches are treated as a form of pavement
distress. Although HMA is sometimes used for emergency patches, PCC should
be used for permanent patches. Fast-setting PCC is often used to minimize
setting time.
Figure 10.26:
Full-Depth Patch
Preparation
Figure 10.27:
Pouring a Small
Full Depth PCC
Patch on a
Residential Street
A PCC full depth patching process proceeds as follows (ACPA, 1995):
1. Locate the area to be patched. If the area to be patched is too close to an
existing joint or crack, the patch area should be extended as follows:
o
2. Remove the damaged material. Usually, full depth saw cuts are used to
isolate the repair area from the rest of the pavement. Then, the isolated
section is lifted out as a whole or broken up and removed.
3. Prepare the patch area. The base material and subgrade is compacted,
smoothed and dried (see Figure 10.28). Dowel bars holes are drilled into
the adjacent slab transverse sections and dowel bars are inserted to
provide load transfer across the patch boundary. Slab replacements
longer than about 4.5 m (15 ft.) require longitudinal tie bars as well (see
Figure 10.29).
4. Apply a bonding agent. A cementitious grout is used to help the patch
material bond to the original slab material.
5. Place, finish and cure the PCC. The PCC should be placed so that the
patch is of the same elevation as the surrounding slab. Vibratory screeds
are often used to strike off and finish full depth patches.
4.5 Summary
Pavement maintenance prolongs pavement life by slowing its deterioration rate.
This section has described some of the more common maintenance options in
the U.S. Each option's effectiveness is dependent upon a multitude of local
conditions. For most smaller agencies, the best advice when considering
pavement maintenance options is to talk to local contractors and nearby
agencies about what types of maintenance options have worked best in your
local area.
5 RIGID - REHABILITATION
The combined effects of traffic loading and
the environment will cause pavements to
deteriorate over time. Although
maintenance can slow the rate of
deterioration, it cannot stop it. Therefore
eventually the effects of deterioration need to
be reversed by adding or replacing material in
the existing pavement structure. This is called
rehabilitation. Formally, rehabilitation can be
defined as (ITS, 2000):
HMA overlays. HMA overlays are used for two primary purposes:
structural and non-structural. Structural overlays are thicker and are
designed to add structural support to the existing rigid pavement. Nonstructural overlays are designed as a wearing course and are generally
assumed to provide no additional structural support.
PCC overlays. PCC overlays are structural in nature and can be divided
into two types (Mack, Hawbaker and Cole, 1998):
the direction of traffic flow and must also be parallel to one another so
that the retrofitted dowel bars do not restrict slab expansion and
contraction.
2. Insert dowel bars into the slots (see Figure 10.31). Each dowel bar is
placed on a small support to keep it at the correct elevation. A Styrofoam
joint reformer and plastic end caps are used to allow the slab to expand
without bearing on the grout.
3. Fill the slot with grout (see Figure 10.32). A small maximum aggregate
size (e.g., 10 mm (0.4 inch)) is used to ensure the grout fills in completely
around the dowel.
4. Diamond grind the entire pavement area (see Figure 10.33). This removes
any elevation differences due to faulting or grout placement.
Retrofitting dowel bars has grown in popularity over the last 10 years and has
resulted in good pavement performance.
5.3.1 Unbonded
An unbonded PCC overlay consists of a relatively thick PCC layer (typically 125 305 mm (5 - 12 inches) thick) over an existing rigid pavement. Bonding between
the existing pavement and overlay is intentionally prevented by using a slurry
seal, BST, or HMA bond breaking interlayer. This intentional separation allows
the original pavement and overlay to act independently of each other and helps
prevent distresses in the existing pavement from reflecting through into the
overlay (ACPA, 2001). Unbonded overlays are generally used as an alternative
to rubblization when the existing rigid pavement is badly deteriorated. Their
primary advantages are that they (1) can be applied over a badly deteriorated
pavement without much surface preparation and (2) they do not require the
existing pavement to be removed. Their primary disadvantages are (1) because
they are relatively thick and placed directly over the existing pavement, they add
substantially to roadway elevation, which could pose overhead clearance
problems, and (2) they are relatively expensive.
where Dol
:
Df
De
ff
where De
:
ff
Fjcu
= joints and cracks adjustment factor accounts for the extra loss of serviceable
life caused by deteriorated transverse joints
and cracks in the existing pavement.
From a remaining life calculation. This method does not account for
any benefits from pre-overlay repair. The following equation is used
to determine the remaining life as a percentage of total life:
where RL
:
Np
N1.
5.3.2 Bonded
A bonded PCC overlay consists of a relatively thin PCC layer (typically less than
100 mm (4 inches) thick) over an existing rigid pavement. The overlay is
intentionally bonded to the existing pavement with a PCC slurry or grout in order
to create a composite pavement section (McGhee, 1994). Bonded overlays are
generally used to add structural capacity to existing rigid pavements that have
little deterioration (e.g., no faulting or spalling and cracked slabs should be
replaced before overlay). Their primary advantages are that they (1) are thinner
than unbonded overlays and (2) their structural design accounts for the strength
of the underlying pavement. Their primary disadvantages are (1) they should
not be applied over badly distressed pavements because the distress may affect
bond quality, and (2) they are dependent upon good bond development - if for
some reason this does not occur, the pavement could be structurally inadequate.
where Dol
:
Df
De
ff
where De
:
ff
Fjc
Fdu
Ffat
From a remaining life calculation. This method does not account for
any benefits from pre-overlay repair. The following equation is used
to determine the remaining life as a percentage of total life:
where RL
:
Np
N1.
5.5 Summary
Rehabilitation essentially reverses the effects of deterioration by adding or
replacing material in the existing pavement structure. This section has
concentrated on structural overlays of existing rigid pavements. These overlays,
which can be either flexible or rigid, are used to increase a pavement's structural
capacity. In order to do this, they must be structurally designed using one of
several methods. Flexible overlays tend to be less expensive, thinner and
quicker to construct, while rigid overlays are more expensive, thicker and take
longer to construct, but may offer longer life. The choice of overlay type and
method is highly dependent upon local practice and conditions.
Finally, new road construction in the U.S. is not nearly as prolific as it has been in
previous generations. Urban areas have filled out greatly and the ratio of
existing roads to new roads is now quite high. Consequently, rehabilitation (and
not new construction) has become the dominant force in today's pavement
design and construction arenas.
Subgrade analysis
Traffic analysis
Subgrade Analysis
Subgrade material testing is encouraged even if original design records are
available. The resilient modulus (MR), CBR or R-value tests appear to be the
easiest to use with this procedure. For actual design, the design strength of the
subgrade must be characterized in terms of resilient modulus. Therefore CBR
and R-values must be correlated to resilient modulus values. If test data in terms
of MR, CBR, or R-value are not available, subgrades can be placed into one of
three classes for design purposes as follows:
Poor soils. Soft and plastic when wet, generally composed of silts or clays.
Typical properties are: MR = 30 MPa (4,500 psi), CBR = 3, R-value = 6.
Medium soils. Include soils such as loams, silty sands, and sand-gravels
which contain moderate amounts of clay and silt. These soils can be
expected to lose only a moderate amount of strength when wet. Typical
properties are: MR = 80 MPa (12,000 psi), CBR = 8, R-value = 20.
Conversion Factor*
0.0
0.0
0.1 - 0.3
0.3 - 0.5
0.5 - 0.7
0.9 - 1.0
Traffic Analysis
The Asphalt Institute treatment of traffic includes consideration of volume
composition, and axle weights, with the goal being to develop the equivalent
number of ESALs. To estimate the ESALs for the overlay design period, at least
two approaches can be used, depending on availability of site specific traffic
information. One approach provides broad traffic classifications and the
associated ESAL amounts, as illustrated in Table 3. The second approach
includes the use of "truck factors" (the average ESALs per truck number) along
with the number and type of trucks that are expected to use the facility. This
approach can accommodate a wide variety of truck information ranging from
only an estimate of the percent of the Average Daily Traffic (ADT) that constitutes
trucks to estimates of trucks broken into the categories of single and multi-units
(as illustrated by "vehicle type" in Table 3).
Truck factors are shown in Table 7.3 for a variety of vehicle types, with the
average being 0.4 ESAL per truck averaged over all highway and truck types.
5,000
10,000
100,000
1,000,000
3,000,000
10,000,000
Table 4. Average Truck Factors Compiled from FHWA Data (after Asphalt
Institute, 1983)
Truck Factors
Vehicle Types
Rural Highways
Interstate
Other
All
Urban
Highways
0.02
0.02
0.03
0.03
0.02
0.19
0.21
0.20
0.26
0.21
Combined
. Single-units
0.56
0.73
0.67
1.03
0.73
0.07
0.07
0.07
0.09
0.07
(a) 3-axle
0.51
0.47
0.48
0.47
0.48
(b) 4-axle
0.62
0.83
0.70
0.89
0.73
0.94
0.98
0.95
1.02
0.95
0.93
0.97
0.94
1.00
0.95
0.49
0.31
0.42
0.30
0.40
. Tractor semi-trailers
. All trucks
Example
A two-lane highway has the following characteristics and resulting overlay
requirement:
1. Traffic
Figure 1: Sketch of Asphalt Institute Design Chart for Full-Depth HMA (redrawn from Asphalt Institute, 1983)
Deflection Analysis
The Asphalt Institute recommends that a minimum of 20 deflection
measurements be taken each mile and randomly located in the outer wheelpath.
From this data for each "uniform" pavement section, a "representative rebound
deflection" is determined as follows:
RRD = (x + 2s)(f)(c)
wher
e:
RR
D
The above "c" values are generally representative for flexible pavements located
in areas with modest annual freezing and thawing (a Freezing Index of say less
than 700F-days) or a wet climate. A higher "c" is likely needed in areas with
severe winter freezing and thawing. The Roads and Transportation Association of
Canada (RTAC) (RTAC, 1977) uses a multiplier of 2.5 to convert Benkelman Beam
measurements taken during the fall period (September 1 to October 15) to
"maximum spring values." This ratio of 2.5 is a bit higher than generally
observed in the U.S., possibly reflecting the generally more severe winter and
thaw periods in Canada.
The deflection measurements can be used to estimate the remaining life of the
pavement or the needed thickness of asphalt concrete overlay. To determine the
required overlay thickness, Figure 2 is used with the RRD and ESALs as the
required input.
2. Deflection data
RRD = x + (2s)(f)(c)