Sunteți pe pagina 1din 73

BUILDING CONSTRUCTION I (BLD 60303)

PROJECT 01: EXPERIENCING CONSTRUCTION


ASSIGNMENT 1: EXPERIENCING, DOCUMENT AND ANALYSIS CONSTRUCTION PROCESS

ANG AVERLLEN 0321444 | ONG SHI HUI 0320303 | NG WYN JANE 0319440 | LIM ZIA HUEI 0321031
JACK LEE 0325810 | LEE ZI YING 0320435 | LIM ZANYU 0325034 | LIM YANG KANG 0320538

CONTENT
1.0 INTRODUCTION
1.1 INTRODUCTION OF SITE

2.0 SITE AND SAFETY


2.1 PLANTS AND MACHINERY

3.0 EXTERNAL WORK


3.1 SETTING OUT AND EARTHWORK

6.0 SUPERSTRUCTURE
6.1 COLUMNS
6.2 BEAMS
6.3 SLABS
6.4 WALLS
6.5 STAIRCASES

7.0 DOORS AND WINDOWS


7.1 DOORS
7.2 WINDOWS

4.0 FOUNDATION
4.1 REINFORCED CONCRETE PILE FOUNDATION
4.2 REINFORCED CONCRETE PILE CAP
4.3 COLUMN STUMP FORMATION
4.4 SHALLOW FOUNDATION

5.0 BASEMENT
5.1 BASEMENT CONSTRUCTION
5.2 RETAINING WALL

8.0 ROOF
9.0 SUMMARY
10.0 REFERENCES

INTRODUCTION

1.1 INTRODUCTION TO THE SITE

Second site visit

KELAB UKAY RESIDENCE

First site visit

BSP VILLAGE COMMERCIAL CENTRE

01

INTRODUCTION

1.1 INTRODUCTION TO THE SITE

BSP VILLAGE COMMERCIAL CENTER

Jalan Saujana Putra, Bandar Saujana Putra, Jenjarom, 42610,


Selangor
Land Acres: 16 Acres
Total Units: 164 Units
Project Type: 2 & 3 storey shop office
Gross built-up: 2 storey (from 2,761 sq.ft.), 3 storey (from 4,425
sq.ft.)
Layout: 22 x 70 ; 22 x 80
Accessibility: Can be accessible via 4 major highways
(Elite, Skve, Kesas & LDP)

-Multi-storey shopping mall


-Extensive food and beverage choices
-Friendly environment pedestrian walk street
-Ample parking
-Innovative lifestyle zones
-Dedicated entertainment zones.
-Open air plazas and courtyards.
-Supermarket street bazaars.

Located at the vibrant


heart of Bandar
Saujana Putra in
Puchong, Selangor.

02

INTRODUCTION

1.1 INTRODUCTION TO THE SITE

BSP VILLAGE COMMERCIAL CENTER - FLOOR PLAN


2 STOREY SHOP OFFICE - INTERMEDIATE LOT
(22 X 80)
2 STOREY SHOP OFFICE
(22 X 70)

GROUND FLOOR

FIRST FLOOR

GROUND FLOOR

FIRST FLOOR
03

INTRODUCTION

1.1 INTRODUCTION TO THE SITE

KELAB UKAY RESIDENCE

Jalan Kelab Ukay 2, 68000 Ampang, Selangor, Malaysia.


Land Acres: 0.75 Acres
Total Units: 15 Units
Project Type: 5 storey superlink house (3+1+1 storey with roof top garden)
To Setapak

To Batu Caves

To Duta
To KLCC
To KLCC
To Cheras

-Located within an upscale and mature residential area.


-Impressive exterior with a blend of modern linear design and floor-to-ceiling glass panels.
-Unobstructed mountain view that extends to the living area and master bedrooms.
-Cool breeze air from the greenery surroundings.
-Within a 24-hour guarded community.
-Easily accessible to Kuala Lumpur and Petaling Jaya via major highway networks.
-Easy access to complete basic and support functions
-6.000sf contemporary home with private lift leading to all levels.
-30 feet setback in each unit to provide ample parking space for 4 cars at the drive way.

04

INTRODUCTION

1.1 INTRODUCTION TO THE SITE

KELAB UKAY RESIDENCE - FLOOR PLANS

ROOF TOP
The 800-square-feet roof
top garden providing
excellent views of the
surroundings

1ST FLOOR
En-suite master
bedroom 1, 2 en-suite
bedrooms

GROUND FLOOR
Car porch for 4 cars, a
spacious living area,
dining room, wet and dry
kitchen

LOWER GROUND 1
En-suite bedroom 2 and
family hall

LOWER GROUND 2
A large service area
that offers the
convenience of laundry
and storage space
05

SITE & SAFETY

LIM YANG KANG 0320538

2.0 SITE AND SAFETY


The construction industry has long been considered as a difficult, dangerous and dirty occupation due to the high number of accidents,
injuries and deaths. Construction workers are exposed to different rinks. Example: falling from heights, movement of the plant and
machinery, electrical shocks, drowning, excessive noise and etc.

SIGNAGES
The reason of placing safety sign is to deliver
the important of the information to public and
warn the public about hazard that could be
happen in construction site. No only that, the
sign provides information of who is working
and the contact as well.

PROHIBITION /
DANGER
ALARM
WARNING

FIREFIGHTING

NO DANGER

SIGNAGES FOUND ON SITE


The safety signages showed and informed that
before entry the construction site, everyone have to
wear appropriate personal protective equipments.

MANDATORY
Different colours and symbols of signages give
identify different actions or procedures to be
used.

Warn drivers about the construction site


ahead.
06

SITE & SAFETY

LIM YANG KANG 0320538

2.0 SITE AND SAFETY


PERSONAL PROTECTIVE EQUIPMENT
Personal protective equipment is clothing and equipment designed to be worn by workers to protect them from injuries. It is a must for
workers to wear PPE all the time on site. Fine will be given to those who dont abide the rules.
EYE PROTECTION
Safety goggles protect against eye injuries while
workers weld or cut materials & against dust or other
eye irritants.
SAFETY HELMET
Protect the individuals from injuries caused by falling
objects.
EAR PROTECTION
Ear plugs should be worn to protect the ears from
damage especially when it is near or using loud
machinery.
HAND PROTECTION
Gloves is a must protect a workers hands from
splinters and other sharp objects.

ATTIRE
-Long sleeve, short sleeve shirts and tshirt are allowed
-tight fitting or suggestive is not
allowed.
-must not be exposed in the torso area.

ATTIRE
-Pants and shorts must not be
tight fitting.
-Shorts must be no higher than
mid-thigh.

FOOT PROTECTION
Closed toe shoes only. Work boots are preferred
but thick soled tennis shoes will be allowed.
07

SITE & SAFETY

LIM YANG KANG 0320538

2.0 SITE AND SAFETY


SCAFFOLDING

SAFETY NET

Scaffolding is a temporary structures that used to support


people and hold materials that are to be used for
construction or repair of buildings and other structures.
They aid safety of the workmen and allow access to areas
that are difficult to reach. They are constructed by using
metal tubes with metal platforms or with bamboos and
wooden planks.

A kind of falling protection system that protect workers from falling


by covering the edge of the building especially when the building are
to be construction up to the height that may cause falling if
precautions are not taken by the workers.

DIAMOND
MESH
PLANKING

RUNNER

Anchor securely to eliminate friction wear and prevent enlargement.


Maximum size of mesh opening less than 6 inches

BEARER

SILL
DIAGONAL
BRACE

JOINT CONNECTIONS VARY


ACCORDING TO
MANUFACTURER

Safety nets should be used when work


place is more than 25 feet above ground
where the use of scaffolds are impractical.
08

SITE & SAFETY

LIM YANG KANG 0320538

2.1 PLANTS AND MACHINERY


EXCAVATOR
Excavator is the machine that can excavate the soil of
various types forcefully and then using hydraulic
system a hydraulic force is generated and utilizing
this force bucket is pull back towards the machine.
Bucket of excavator is replaceable. If front bucket is
exchange with some other attachments then
excavator can be used for multi-purpose. For
example: pile diver, hydraulic jack hammer etc

THE ARM
-Consists of a bucket and a boom.
-Can be replaced by hammer or
breaker.
-Does the digging work.

THE CAB
-The drivers seat consists
of the control systems and
steering

CRAWLER
EXCAVATOR
-Two endless tracks.
-used in hilly areas where
risks of sliding of machinery
are on the verge.
-Low ground pressure
because of spreading of load
on large area and also used
where soil support is weak.

THE SWING
-Ability to turn
360 degree.

THE FEET
-Two types of excavators bases.
-Wheel excavator use on hard
surface.
-Crawler excavator use on unstable
surface.
09

SITE & SAFETY

LIM YANG KANG 0320538

2.1 PLANTS AND MACHINERY


MOBILE CRANES
A mobile crane is a cable-controlled crane mounted
on crawlers or rubber-tired carriers or a hydraulicpowered crane with a telescoping boom mounted on
truck-type carriers or as self-propelled models.They
are designed to easily transport to a site and use with
different types of load and cargo with little or no
setup or assembly.

THE JIB
-This lattice like structure
frees up the boom to extend
fully and provide maximum lift
range.
THE COUNTERWEIGHTS
-Keep cranes from
becoming unbalanced
while hoisting heavy
loads.

WORK BASED ON SIMPLE


CONCEPT
-Transmission of forces from
point to point through a fluid. Two pistons fit into glass
cylinders filled with oil and
connected to another.If
downward forces apply to one
piston, then the force is
transmitted to the second
piston through the oil in the
pile.

THE BOOM
-It is the most recognizable part of the crane. Does
heavy lifting of materials such as beam and
column.
10

SITE & SAFETY

LIM YANG KANG 0320538

2.1 PLANTS AND MACHINERY


BACKHOE-LOADER

LOADER

The backhoe loader is an engineering and excavation


vehicle that consists of a tractor, front shovel and bucket
and a small backhoe in the rear end. Due to the small size
and versatility, backhoe loaders are common with small
construction projects and excavation type work.

A loader is a heavy equipment machine used in construction to move


aside or load materials such as asphalt, demolition debris, dirt, feed,
gravel, logs, raw minerals, recycled material, rock, sand, etc. into or
onto another type of machinery.

THE BOOM
-Bent upwards to make
it easier to dig.

THE BACKHOE
-Use to dig up hard compact
material or lift heavy loads.

THE TRACTOR
-Move easily over all
kind of rough terrain by
controlling the steering
in the cab.

THE LOAD
-Use to pick up and push
large amount of loose
materials into holes.

THE CAB
-Drivers seat consists of the
control systems and steering.

THE BUCKET
-Use to load materials.
-Can be replace by other devices and tools.
-Different size of buckets.

11

SITE & SAFETY

LIM YANG KANG 0320538

2.1 PLANTS AND MACHINERY


CONCRETE MIXER TRUCK
The concrete mixer is a device that homogeneously
combines cement, aggregate such as sand or gravel,
and water to form concrete. A typical concrete mixer
uses a revolving drum to mix the components. For
smaller volume works portable concrete mixers are
often used so that the concrete can be made at the
construction site, giving the workers ample time to use
the concrete before it hardens.

CONCRETE COMPRESSOR PUMP

Concrete mixing chamber.


BRACKET
ROLLER

Standard environmental air


pollution prevention device
to be relocated.

STEPS OF THE CONCRETE MIXER TRUCK WORK

Pump wet concrete safely through


a delivery system if pipes and
hoses within its published rating
and specification. Stability of the
concrete pump during operation is
provided for the outriggers and
front jack controls for the
outriggers are located on the sides
of the concrete pump.

Control system
12

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

SETTING OUT AND EARTH WORK


-

Site clearing
Site layout and Security and safety
Setting out and levelling

SITE CLEARING

Process of bulldozer removing shrubs

- A construction site is usually prepared in two steps : clearing the vegetation and also cut and fill the surface soil. It can be done by hand
or by machineries depending on the scale of the site.
- Based on the scale of the sites selected, the machineries needed for clearing the site includes : Multipurpose excavator, bulldozer,
dumper, since they can not be done manually.

Process of multipurpose excavator clearing site, particularly removing trees

13

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

SOIL FILLING
After all the vegetations are removed from site, it will be followed by the process of soil filling, which basically cuts and fill the topmost
surface of the soil, to produce an even surface for the site. The fill dirt used is usually the subsoil and underlying soil parent material which
has little soil organic matter or biological activity. They are taken from a location where soil is being removed as a part of leveling an area for
construction, while it may also contain sand, rocks, and stones, as well as earth.

Different in level of soil

The other site was built on slope (2 floor


basement and 3 floor above ground floor). Soil
investigation plays a much more important
part in this site, as it helps to reduce the risk of
erosion and land massing. More work is done
to prevent accidents from happening, such as
the construction of retention walls and deeper
piling for foundation.

Cut and fill the soil

Even ground level

RETAINING WALL
- To hold the soil
together
- Prevent the
happening of erosion
to disrupt the
construction progress
A deeper foundation
compared to a normal
construction site

14

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

SITE LAYOUT 1 AND SITE SECURITY

- Retention pond

- Temporary site office


- Temporary residential area for workers
- Temporary material storage
- Temporary toilet

- Temporary toilet for workers

- Construction area

- Site security
- Entrance to site

- Site boundary and temporary fencing

15

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

SITE LAYOUT 2 AND SITE SECURITY

- Site security

- Temporary site office


- Temporary toilet
- Temporary material storage

- Temporary electricity supply


- Temporary drainage
system

- Water trough

- Site boundary and


temporary fencing
- Construction area
16

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

SITE SECURITY AND TEMPORARY FENCING


TEMPORARY FENCING
- Not allowing random
people to enter the site
without permission
- As a safety boundary to
prevent construction
accidents to occur or harm
neighbours

SITE SECURITY
- Security against theft
- Security from vandals
- Protection from innocent trespassers
The need for and type of security required
will vary from site to site according to the
neighbourhood.

HOARDINGS
- A closed boarded fence
adjacent to public highway
and footpath
- Needs to be adequately
constructed to provide
protection for the public,
resist impact damage,
resist anticipated wind
pressures and adequately lit
at night
- Must obtain a license or
permit from local authority
17

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

SITE SETTING OUT AND LEVELLING


This task is usually undertaken once the site has been cleared of any obstruction and any reduced-level excavation work is finished. The first
task is to establish a baseline to which all the setting out can be related.

Site
boundary

Alternative
method for
corner

Temporary
bench mark or
site datum post

Corner post

Footpath

TEMPORARY BENCH MARK


This is a fixed point on site to
which all levels are related and
should be established at an early
stage in the contract.
Where possible it should relate to
an ordnance bench mark
On site it can be any permanent
feature such as a drain cover or a
firmly driven post

SETTING OUT - 3:4:5 METHOD


Using pythagoras theorem
- Calculate the distance from
the first peg to the second (A)
- Lay out the distance from first
peg to third peg (B)
- Using formula :
A + B = C
- The square root of C will give
an answer and secure a 90

Nail in
centre of
post

Cord marking
outline of
building
18

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

SETTING UP SIGHT RAILS


Ensure all desired height achieved vertically.

Staff reading gives


height of
collimation of level

Necessary staff
reading calculated
to give level at
desired height

Level

DATUM
- Altitude zero taken at mean sea level,
this varies between different countries
- Most common are identified as
carves arrows cut into walls of
permanent structures

Sight line

Sight rail
posts

Temporary bench
mark or site datum
post

Ground
level

TAKING SITE LEVELS


The nearest OD bench mark may be
impractical to access. The alternative
is to establish a datum or temporary
bench mark (TBM) from a fixture such
as a manhole cover

19

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

TEMPORARY SITE OFFICE AND MATERIAL STORAGE


Overview of the site office 1 and temporary residential for
workers

Exterior view of the site office

- Site office located near to the boundary of the


construction site, safe from building construction
period
- Easily taken care of, also next to temporary living area
of some of the workers and their family

Material storage and checkpoint

SITE OFFICE
- A temporary space to
accommodate site managers,
provide space for site
meetings and also provide
storage for site
documentations
- Must be reasonably
practicable, sufficient working
space and arranged nicely and
taking into account necessary
working equipments

MATERIAL STORAGE
- Area of space required to
protect, control materials, that
are to be kept on a
construction site during
building process
- Planned to ease accessibility
and reachability
- Guarded from theft or
vandalism
20

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

Location of site office 2

Interior view of the site office

Exterior view of the site office 2

TEMPORARY TOILET
- Located at an easy accessible place,
preferable near site office
- Kept clean at all time to prevent
mosquitoes or causes uneasy smell
21

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

TEMPORARY DRAINAGE SYSTEM

DRAINAGE SYSTEM
- Important feature during a
construction process to allow
unclean water and
construction wastes to flow
out smoothly
- Keeping the construction site
clean at all times, prevent
diseases from spreading
- Prevent the growth of
mosquitoes which will cause
disturbance to the neighbours
or receiving complains
- Prevent clogged drains,
causes uneasy smell
- A feature to reduce pollution
happening at construction
sites

DRAINAGE
- The black colour pipe
allows soils, silts to be
removed
- The green colour pipe
shows water being
transported out to main
drainage system

RETENTION POND
- Settle suspended
sediments and other solids
- Assist with flood
management & improve
water quality

WASH TROUGH
- Used to wash off dirt
from plants and
machineries
- Also a spot for workers to
clean off, water flows out
easily
22

EXTERNAL WORKS

LIM ZANYU 0325034

3.1 SETTING OUT AND EARTHWORK

TEMPORARY ELECTRICITY SUPPLY

Electrical power inside the site

Temporary electricity supply before entering the


site

Electric supply used

- Temporary electricity supply is installed for use throughout the whole building
construction process
- Allowing site office to function, providing a conducive space through lighting
and air-conditioning
- Provide lighting for construction site during the night
- Enable certain plants and machineries to work on-site
23

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.1 REINFORCED CONCRETE PILE FOUNDATION


PIles used on the site are
reinforced concrete columns, which are
precast and driven (hammered) into the
ground down to a level of firm and stable
bearing ground for supporting the load.

Situations which lead to the necessitate use of piles are:- Insufficient load bearing capacity is offered by the soil at a shallow depth, but sufficient is
available at a greater depth
- The nature of the soil at a shallow depth is variables and performance is unpredictable in
site.
- Soil at shallow depths are subject to shrinkage or swelling.
- Building are subjected to an uplifting force, and require to be anchored to the ground.
By the way in which they are
installed
Ground level

Load Structure

Ground level
Pile Cap

Pre-cast
Reinforced
Concrete pile

By the way in which they transfer


the load to the ground
Ground level
Pile cap
Load

Weak strata

Weak Strata

Bearing
Ground

Piles
Displacement Piles

Bearing Ground

Pre-cast RC pile is set in the ground by


forcing or driving a solid pile to the
required level below ground, thus
displacing the surrounding subsoil thought
which it passes.

End Bearing Piles


End bearing pile act by passing through
unsuitable strata to bear directly upon soil
with adequate bearing capacity
24

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.1 REINFORCED CONCRETE PILE FOUNDATION


SEQUENCE OF PILE INSTALLATION:
1. Delivery of precast Reinforced Concrete square piles.

2. Testing of Reinforced Concrete piles

Type of shoe :Concrete


Block

15mm Thick
Plate

Available as initial and extension piles in


standard lengths of:-

Flat Pile Shoe(female


shoe) - as extension
pile
Solid Cast Iron

3m
6m
9m

The length required may vary among piling


point.

12m
Pointed pile shoe (male
shoe) - as initial pile

Main
Beam

Hydraulic
Beam
Ground level
Test Pile

Dial
Anchor Pile
Gauge
- It is advisable to test load at least one pile per delivery by jacking
against kentledge placed over the test pile.
- The test pile should be overloaded by at least 50% of its working
load and this load should be held for 24 hours.
- The test pile should not form part of the actual foundation.
25

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.1 REINFORCED CONCRETE PILE FOUNDATION

Pile Space

Extension Pile

Joint
Bearing
Ground

Initial Pile
3. Marking of the
length of piles.

4. Lifting and
fitting pile into the
piling machine and
placement of pile
onto piling point.

5. Driving of pile
into the ground.

6. Joining of piles
with welding when
insufficient pile
length occurs.

7. Driving of pile
until bearing
ground. Bearing
ground on site are
average 37 m below
ground

Pile Space
- Piles should be spaced at such a distance that the group is economically formed and at the same time any
interaction between adjacent piles is prevented.
- The minimum spacing for end bearing piles is 750mm or not less than 2x pile diameter, whichever is greater.

8. Final
26

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.2 REINFORCED CONCRETE PILE CAP

- Piles are not usually used singly but are


formed
into
a
group.

Piling Layout Plan

Column Stump
Load
Pile Cap

Load equally
distributed
onto bearing
ground

RC Piles

Pile Cap
Reinforcement

- The load is equally distributed over the


heads of piles in group via a reinforced cast
in-situ concrete pile cap.

3 Storey Corner lot


Require 5p pile cap to support
additional level of ground
compared to the 2 storey lot
beside

2 Storey lot
While a 2 storey lot only
needed a 4p pile cap to
support the load
27

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.2 REINFORCED CONCRETE PILE CAP

Pile Caps plan in site

- The plan shape of


the pile cap should
be as conservative
as possible, and this
is usually achieved
by having an
overhang of 150mm.

Pile cap reinforcement

- The main reinforcement is two-directional formed in loops over the pile heads to spread the loads.
- To provide structural continuity, the reinforcement in the piles is bonded into the pile cap; this may necessitate
the breaking out of concrete from the heads of piles to expose the reinforcement.
- The heads of piles penetrate the bottom of pile cap some 100 to 150mm to ensure continuity of the members.

Actual preformed pile cap


reinforcement

28

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.2 REINFORCED CONCRETE PILE CAP

Pile
reinforcement

Sequence of pile caps construction:


Pile
reinforcement

Pile

Formwork

Excavated pit

lean
concrete
1. Excavate pit to expose
piling
Reinforcement

2. Laying of 50mm thick lean concrete and cutting-off


pile heads to expose reinforcement

Column stump

To ensure
the position
of the
column
stump
4. Install pile cap
reinforcement.

3. Install pile cap formwork.

5. Install column stump reinforcement

concrete

6. Concreting pile cap, compacting pile


cap.
29

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.2 REINFORCED CONCRETE PILE CAP

Formwork

7. Levelling and hardening of RC pile cap

9. Concreting and hardening of column


stump

8. Install column stump formwork

10. Removal of formwork

11. Backfilling
30

4.0 F O U N D A T I O N (SITE VISIT)

LEE ZI YING 0320435

4.3 COLUMN STUMP FORMATION

Sequence of column stump formation :

1. Manually straightens the rebars


using hand to ease the cutting
process.

2. Fitting of rebars into the cutting


machine.

Bent
rebars
Fitting of
rebars

3. Cutting of rebar into required


length.

On site bar bending and fabrication yard


Tying
reinforcemen
t with soft
iron wire

Bending
of rebars
4. Rebar bending via power-assisted bar bending machine.

5. Bent bar fabricated into cages for column stump.

Completed
column stump
31

4.0 F O U N D A T I O N (REFERENCE)

LEE ZI YING 0320435

4.4 SHALLOW FOUNDATION

Types of spread footings :


Deep
foundation

Shallow
foundation

Transfer
load directly
to
supporting
soil by
vertical
Pile hit bearing
pressure
ground for support
due to
due to unsuitable
adequate
soil
soil.

Isolated
footings
support
freestandin
g columns
and piers

The lowest part of a


shallow
foundation
are spread footings.
They are extended
laterally to distribute
load over an area of
soil wide enough that
the allowable bearing
capacity of the soil is
not
exceeded.
Footings
should
always
rest
on
undisturbed soil free
of organic material

Strap footing is a column


footing connected by a
tie beam to another
footing in order to
balance asymmetrically
impose load.

Continuous
footing is a
extended
RC footings
to support a
row of
columns

Combined footing is a RC
footings for perimeter
foundation wall or
column extended to
support an interior
column load..

Strip
footings are
the
continuous
spread
footings of
foundation
wall

Raft foundation is a thick


RC slab that serves as a
single monolithic footing
for numbers of columns
or an entire building.
32

5.0 B A S E M E N T (SITE VISIT)

LIM ZIA HUEI 0321031

5.1 BASEMENT CONSTRUCTION


Basement is the portion of a building which provides accommodation and is below ground level. There are few types of basement
construction which is precast concrete basement construction, concrete block basement construction as well as reinforced poured
concrete basement construction. Reinforced poured concrete basement construction is used in the site.

REINFORCED POURED CONCRETE BASEMENT CONSTRUCTION

Reinforced poured concrete basement construction is a multiple steps operation.


This type of basement construction is much more stronger and resistant to water
infiltration than other two types. However, waterproofing is still needed for the
basement walls and the added water-tightness of poured concrete will give you a
second line of defense against damaging water intrusion.

33

5.0 B A S E M E N T (SITE VISIT)

LIM ZIA HUEI 0321031

5.1 BASEMENT CONSTRUCTION


CONSTRUCTION OF REINFORCED CONCRETE
BASEMENT

Timber
formwork
Bracing
STEP 1: First, forms are erected according to the structural or
architectural plans.

STEP 2: Next, reinforcing steel bars are assembled within the forms and
tied together.

STEP 3: When that is completed, concrete is poured into the


forms.

STEP 4: When the concrete is two or three days old, the forms are
stripped away and the concrete basement walls remain. The
concrete is strong enough to support itself after seven days.
34

5.0 B A S E M E N T (REFERENCE)

LIM ZIA HUEI 0321031

5.1 BASEMENT CONSTRUCTION


CONCRETE MASONRY BASEMENT
CONSTRUCTION

PRECAST CONCRETE BASEMENT CONSTRUCTION

-Efficient and economical material.


-Strong, fireproof, thermally efficient and termite-resistant.
-Requires no formwork and is available almost everywhere.
-Ribbed, split-face, slump, fluted and other decorative block
can give the basement interior an appealing look.
-Provide comfortable living or storage space at about half
the cost of above grade construction unless soil conditions
or high water table prohibit them.

-They are built in factories.


-Simplify basement construction.
-Save time as well as money.
-Result in warmer and drier basements.
-The walls comprise high-strength concrete panels as they are
poured in controlled conditions in factories. They are
guaranteed to achieve the intended design strength.
-Do not require concrete footer.
35

5.0 B A S E M E N T (SITE VISIT)

LIM ZIA HUEI 0321031

5.2 RETAINING WALL


A retaining wall is a structure that holds or retains soil behind it. Retaining walls are used in the construction of basement below ground
level, wing walls of bridge and to retain slopes in hilly terrain roads.

REINFORCED CONCRETE RETAINING WALL

Ground
level

Basement

Footing

-Uses reinforcement bar to give more strength


to the retaining wall structure and improving
its ability to hold the soils behind it.
-Resists the lateral pressure by structural
action such as bending.
-Texture and appearance affected by the use
of formworks, composition of concrete mix
and surface treatment after casting.
-Provides greater speed of construction and
control of quality.
-Structural stiffness reduced ground
movements to adjacent settlement during
subsequent excavation.

Reinforcement steel
bar

36

5.0 B A S E M E N T (SITE VISIT)

LIM ZIA HUEI 0321031

5.2 RETAINING WALL


CONSTRUCTION OF REINFORCED CONCRETE RETAINING WALL

Rebar

---12 inches----3 feet--

Base reinforcement Stem reinforcement

STEP 2: Install steel reinforcement bars


as the construction drawings using
cover blocks and spacer chairs to
position them.

STEP 1: Line out the


foundation trench on the
ground and excavate the
trench.

Footing trench

STEP 3: After inspecting the rebar, pour


the concrete into the footing trench.

Open side

Earth side

Sheathing

-12--

Brace

Brace as support

Timber formwork

Drain

stake

Footing

STEP 4: Install the wall formwork


after the footing cures.

---12--

Stud

Spacer block removed as concrete


is poured

STEP 5: Pour concrete of specified strength in


the forms and properly vibrate it to ensure
compaction of the concrete.

STEP 6: Install drainage stone and tile on top


of the earth side of the footing along the wall
after the wall is done. Cover the stone with
proper filter fabric and backfill after that. 37

5.0 B A S E M E N T (REFERENCE)

LIM ZIA HUEI 0321031

5.2 RETAINING WALL


GRAVITY RETAINING WALL
Types of gravity retaining wall:

Poured concrete

Masonry unit

Stone

-The thickness of wall increases with height.


-Resists the lateral earth forces by its weight and any soil resting on it, hence, is rather massive in size.
-Typically shorter in height.
-Usually are sufficiently enormous to be unreinforced.
-Monolithic cast walls are generally formed on site.
-Usually built in stone masonry, and occasionally in plain concrete.
-Plain concrete gravity walls are not used for heights exceeding about 3m, for economic reasons.
38

6.0 S U P E R S T R U C T U R E (SITE VISIT)

JACK LEE HOR KIT 0325810

6.1 COLUMNS
SUPERSTRUCTURE
is the part of any structure that is built above its foundation or basement.
It serves the purpose of the structures main intended use.
Concrete was used for both sites superstructure casting as it is able to withstand
great compressive forces from 20-40 MPa while reinforcement bars would
complement the concrete by giving the structure greater tensile strength.

COLUMNS
are vertical structural elements which transfer load from the roof, beams, slabs,
ceilings, and its own weight to the foundation.
Columns found
at the sites
were columns
of square and
of rectangular
sections.
Their rebars
had 40D and
T12/T16 traits.

Thin metal
wires called
links are tied
around
intersecting
joints to
prevent
movement
Square

Rectangular
39

6.0 S U P E R S T R U C T U R E (SITE VISIT)

JACK LEE HOR KIT 0325810

6.1 COLUMNS
COLUMN INSTALLATION
Casting
concrete

Excess
rebar for
lapping of
the next
upper
floor
columns

Main rebar
for column
Yorks
Lapping for
column
stump

Reinforcement bars are set up


by lapping onto the bars below
them (in this case, for the
ground floor, would be the bars
of the column stumps).

Wooden
formwork

Formwork inserted where columns


should be.
Yorks: clamping devices to maintain the
column form and prevent the formwork
from spreading under fluid pressure of
the concrete casting.

Concrete is casted into the


formwork. Formwork is
shaken to eliminate any air
bubbles and even out the
concrete layer.

Concrete goes through a hydration


reaction to increase its strength
up to 2.5 times. Formwork is
removed after 3 days and rough
edges are smoothened out.

40

6.0 S U P E R S T R U C T U R E (SITE VISIT)

JACK LEE HOR KIT 0325810

6.2 BEAMS
BEAMS
are horizontal structural elements which carry transverse
load (mostly from the slabs) to the columns and/or walls.

150mm spacing
between each tie

R6 link

Much like the columns, the reinforcement for the beams


also have ties and have smaller links holding them
together.

The main components of the concrete


used at the Ukay Residence are:
Cement
Sand
Granite (as coarse aggregate)
Water (for hydration reaction)

41

6.0 S U P E R S T R U C T U R E (SITE VISIT)

JACK LEE HOR KIT 0325810

6.3 SLABS
SLABS
are flat and horizontal surfaces which transfer
load to the beams and are supported by the
beams and the columns.
Ground slab layers

Higher ground slab

Concrete slab
Resists compressive forces
BRC mesh (200x200)
Reinforcement: transfers load to beams
Damp-proof membrane
Prevents water from leaking through
Anti-termite spray
Repels termites
Lean concrete
Provides flat bottom on uneven terrain
Hardcore (granite)
Backfilling: fills any void in the ground

The (suspended) ground slabs of the site


have more layers than slabs installed
above the ground floor. Higher floor slabs
are basically Bar-Reinforced Concrete
which have the following layers:
Concrete
BRC mesh
Concrete
Slabs used at the
site are mainly
two-way slabs.
42

6.0 S U P E R S T R U C T U R E (SITE VISIT)

JACK LEE HOR KIT 0325810

6.2 BEAMS & 6.3 SLABS


BEAM & SLAB INSTALLATION (GROUND FLOOR)
Alignment of ground beams
are set out with simple
planks first.

Formwork is then inserted


where beams should be.

BEAM & SLAB INSTALLATION (FLOORS ABOVE)


Scaffolding is set up around
existing columns to support
the formwork of the beams
and slabs which are
installed together above
ground floor.

Formwork is inserted where


beams and slabs should be.
Lean concrete is inserted to
prevent reinforcement bars
from rusting before
reinforcement is set up.
Concrete is casted and
cured. Formwork is removed
after drying.
Slabs are installed (in
sequence to their respective
layers as listed previously)
separately from beams
when on the ground.

BRC mesh is put in place as


reinforcement and then
concrete is casted.

Scaffolding and formwork


are dismantled after
installation is complete.

43

6.0 S U P E R S T R U C T U R E

(SITE VISIT)

NG WYN JANE 0319440

6.4 WALL
Wall is a vertical structure that made up of stones or bricks. It divides or enclosed an area to provide habitable space and protection. Walls
in buildings form a fundamental part of the superstructure and it is for load bearing, fire resistance, sound and thermal insulation purpose.

TYPES OF WALLS
MASONRY WALL

- Formation of a wall which modular blocks bond


together with mortar
- Durable
- Good sound, fire and thermal insulation
- Non-combustible product
- Great flexibility in form and appearance

REINFORCED CONCRETE WALL

- Load bearing wall


- Texture and appearance affected by the use of
formworks, composition of concrete mix and
surface treatment after casting
- Provides greater speed of construction and control
of quality
44

6.0 S U P E R S T R U C T U R E

(SITE VISIT)

NG WYN JANE 0319440

6.4 WALL
TYPES OF MATERIAL

CEMENT SAND BRICK


- Made up dolomite lime, clean sand
and fly ash
- Pearl-grey in color
- Pressed and allowed to harden in
closed vessels under steam pressure
- Cheaper than clay brick

CLAY BRICK

CONCRETE

- Made up of clay
- Dark orange or deep red
- Many finishes and size available
- Dried and fired with high temperature

- A composite material made up of


coarse aggregate, cement, water and
admixture.
- Harden through hydration

TYPES OF BOND
- Bond is the arrangement of bricks in rows which designed for the appearance and tied the walls together
STRETCHER BOND
- Use for internal wall
- Half brick thick
- Use to separate the
space

FLEMISH BOND
- Use for external wall
- One brick thick
- Two hours fire resistance
- Sound proof

45

6.0 S U P E R S T R U C T U R E

(SITE VISIT)

NG WYN JANE 0319440

6.4 WALL
TYPES OF JOINTS

mm

215
BRICK
RAKED
JOINT

BRICK

- Raked joint
- Protect the edges of masonry units
- For weather-resistant purpose
- Can be formed by using trowel or steel rod

65mm
ER

102

TCHE

HE
AD

STRE

.5m

CONSTRUCTION PROCESS
CONSTRUCTION OF MASONRY WALL
GET THE LENGTH OF THE
WALL

CONCRETE FOOTING

SET A MARK EVERY 10mm

OARD S
WOOD B

UPPORT

STEP 1: Preparing the mortar (mixture of cement, lime, sand and water, a bonding agent in masonry construction)
STEP 2: Spread a layer of mortar bed as footer.
STEP 3: Put the bricks down at each side corner. Measure and mark the length.
STEP 4: Set up a line to keep courses straight. Start to lay the bricks from corner on mortar bed and check the balance using spirit level.
STEP 5: Continue the laying process, cut off excess mortar with trowel. Repeat the process till the destined height. Check the height and make
sure each new course is an additional 10mm high.
46

6.0 S U P E R S T R U C T U R E

(SITE VISIT)

NG WYN JANE 0319440

6.4 WALL
CONSTRUCTION TECHNIQUE

1. Layering Technique
- Arrange in an angle of 45 at the
top
- Fill up the space of the last few
rows to prevent the occurrence
of gap that make the layering
process harder

5. Damp Proof Course


- 20mm thick DPC is installed
on the ground floor brick work
before leveling course cement
mortar

2. Wire Mesh
- Use to hold every 4 layers of
bricks together

3. Stiffener
- Horizontal stiffener is added
when the length of the wall
exceed 4 meter
- Vertical stiffener is added when
the height of the wall exceed 3
meter

4. Dowel Bars
- R6 (mild steel 6mm) is added
between every 4 courses of
brick wall to prevent collapse

6. Setup Line
- To maintain the verticality and
horizontality of the brick wall
during layering process

7. Cement Pit
- Mark the thickness of
plastering (13-15mm) on a
brick wall

8. Glass Fibre Mesh


- To minimize and repair cracks
- Reinforced plasterboard joints
and patching plaster board
holes
47

6.0 S U P E R S T R U C T U R E

(SITE VISIT)

NG WYN JANE 0319440

6.4 WALL
CONSTRUCTION PROCESS
CONSTRUCTION OF REINFORCED CONCRETE WALL
PLA

NK

S
VERTICAL
POSTS
STEEL BARS
HORIZONTAL
MEMBERS

RACKERS
STRUTS

STEP 1: Timber formworks are erected to


the required size on site
WIRE INSTALLATION PROCESS

STEP 2: After the completion of erection


of steel bars within the formwork, the
formwork is closed.

STEP 3: Concrete is poured and left to


cured. The reinforced concrete wall is
completed after the removal of
formworks.

STEP 2: The PVC pipe in the gap is sealed


with caulking. It is to provide thermal
insulation and control water penetration.

STEP 3: Plastering and wet cement are


used to fill the gap.

PVC
PIPE

STEP 1: Wire is put into a PVC pipe as a


protection and it is then placed into the
gap that has been drilled.

48

6.0 S U P E R S T R U C T U R E

(SITE VISIT)

NG WYN JANE 0319440

6.4 WALL
PLASTERING PROCESS

STEP 1: Rough surface plastering


- Used for external wall surface to prevent
the easily defection from the surrounding.

STEP 2: Coating
- Skim coat is applied to the rough surface
of wall in order to smoothen them.

STEP 3: Finishing
- Desired colour of paint is applied for
aesthetic purposes.

REFERENCES
DRY WALL
- Non-bearing wall
- Fast and easy to install
- Light and good fire
insulation
- Susceptible to water
damage, moulding and
external forces

GLASS WALL
- Allow transparency
- Remain compressive
strength
- High cost
- Requires specialist
consultants and
contractors
- Weather resistance
- Strong but brittle
49

6.0 S U P E R S T R U C T U R E (SITE VISIT)

NG WYN JANE 0319440


LIM ZIA HUEI 0321031

6.5 STAIRCASE

STRAIGHT RUN STAIRS

Plan

Elevation

- Used in new home construction


- Have no turns
- Cheaper to construct than other types of
stairs
- Easy to ascend or descend

U-SHAPED STAIRS

Plan

Elevation

- 2 parallel flights joined by a landing that


requires 180 degree turn in the walk line
- Can be easier to fit into an architectural
plan
- Landing offers a resting point while
ascending

L-SHAPED STAIRS

Plan

Elevation

- A landing is added at the 90 degrees bend


transition point
- Can be located in a corner of a room
- Provide privacy and a visual barrier
between floors

50

6.0 S U P E R S T R U C T U R E (SITE VISIT)


6.5 STAIRCASE
Landing slabs
The flat area of flooring between
flights of staircase to act as a
resting place for people
Nosing
A projecting edge, as the part of the
tread of a step extending beyond the
riser or a projecting part of a
buttress.
Soffit sheathing
The covering of underside of an
architectural feature, such as beam,
arch, ceiling and stairs
Tread
The horizontal
part of a step

Riser
-

The vertical
part of a step

NG WYN JANE 0319440


LIM ZIA HUEI 0321031

Ledger
A horizontal timber in a scaffold,
attached to the uprights
Support the putlogs

Dead Shores
Also known as vertical shores
As temporary support for the flooring,
roofs, walls and etc by providing
horizontal members known as
needles.

Wedges
wooden wedges used vertically and
horizontally underneath a staircase in
slots cut into the stringers to secure
riser and treads
Stringer
This pertains to the portion of a stair
running along the stairs side.
Helps to support the surface portion
of stairs on which people walk on it
51

6.0 S U P E R S T R U C T U R E (SITE VISIT)

NG WYN JANE 0319440


LIM ZIA HUEI 0321031

6.5 STAIRCASE
CONSTRUCTION PROCESS

Concrete poured
from top to
bottom

Joist

Reinforcement
bar
Riser
board

Decking

Timber
formwork
Timber formork

STEP 1: The timber formwork is


build for reinforced concrete
stairs cast in-situ

Riser
cleat

STEP 2: The high tensile


reinforcement bar is placed
within the both side of the the
formworks and it is lapping with
the starter bar of slab.

STEP 3: The stringer and riser


softboard is then constructed
for the purpose of creating the
riser and tread after pouring
concrete into it.

STEP 4: The concrete is then


poured from top to the bottom.
Concrete vibrator is used to
make the concrete mix evenly. It
is then left to dry for 3-4days.
52

6.0 S U P E R S T R U C T U R E (REFERENCES)
6.4 STAIRCASE
TIMBER STAIRCASE

GLASS STAIRCASE

- Solid timber or medium density fibreboard


sheet (MDF) may be used in the
construction.
- Timber treads need to be coated with a
non-slip finish to provide a slip resistant
surface.
- The top of each riser should be located into
a groove in the underside of the tread
- Joints should be further supported by angle
blocks 75 mm long and 38 mm width on the
shorter edges, glued to the riser and tread.
- Open tread stairs are for external use.

- Add an air of exclusivity and design


elegance.
- Perfect for commercial applications.
- One of the most striking and modern
feature.
- More time consuming, technical, costly and
potentially dangerous.
- Uses special architectural glass which is
chemically treated, tempered and
laminated.
- Can reach a width up to 3 meters.
- Can span over several floors.

NG WYN JANE 0319440


LIM ZIA HUEI 0321031

STEEL STAIRCASE

- Normally grey in colour and extremely


strong.
- Great for areas where there are major
earthquakes.
- Can be moulded to any shape.
- Stainless and water resistant.
- Termites resistant.
- Easy to set up since it is readily
manufactured.
- No requirement for painting or powder
coating.
- Cost more than timber staircase.

53

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.1 DOORS
Door is a movable screen across an opening, providing
access to a building or between rooms within a building.
Performance requirements of doors:
- Weather exclusion
- Security
- Fire resistance
- Thermal and sound insulation
- Privacy
- Operation
- Durability

Rough
opening

Head
Jamb
Stop
Casing
Threshold

MATERIAL FOR DOORS


Kelab Ukay Residence
- Main Entrance: Solid Timber Door
- Others: Timber, Steel, Aluminium
and Glass Doors

54

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.1 DOORS
LINTEL
Lintel is placed typically on top of doors and windows. The function of lintel is just the same as an arch or beam to support the
load transfer from the upper brick wall.
Load
Brick Wall
Lintel

2 T10
Deformed Steel Bar

Link
1 R6- 150 spacing
Mild Steel Bar

DOOR FRAME
A door frame is attached to the opening in which a door is to be fitted. Door frames
fitted with a sill are designed for one of two conditions:
-

Doors opening out;


Doors opening in.

In our study site, they are just used aluminium door frame.

55

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.1 DOORS
DOOR OPERATION

SWING

-Exterior and interior use


- Requires space around doorway
for door swing.
- Normally turns on hinges about
side jamb when pushed or pulled,
but may also be pivoted from head
jamb and threshold.
- Most convenient operation for
entry and passage.

SLIDING DOOR

-Exterior and interior use


- Requires no operating space but
difficult to seal against weather and
sound.
- Doors slide on overhead track and along
guides or a track on the floor.
-Offers access only through 50% of
doorway width.
- Used on exterior as sliding glass doors.

56

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.1 DOORS
REFERENCE ( DOOR OPERATION )
1. Surface Sliding

FOLDING DOOR

- Interior use ( Balcony )


- Hinged door panels fold flat against one
another when opened.
-Bifold doors divide into two parts in L
shape, require little operating space, and
are used primary as a visual screen to
enclose closet and storage spaces

Similar to bypass sliding door but provides


access through full width of doorway.
No operating space required but is difficult to
weatherproof, so it is just suitable for interior
use.
Door is surface hung on an exposed overhead
track.

2. Pocket Sliding

Door slides on an overhead track into and out


of a recess within the width of a wall.
Doorway has a finished appearance when
fully open.
Often used where a normal door swing would
interfere with the use of a space.

Kelab Ukay Residence


57

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.1 DOORS
CONSTRUCTION PROCESS

STEP 1: Mark the placing


for door.

STEP 5: Lintel is constructed on


the top of the door frame. Then,
measure inside of frame.

STEP 2: Place the door


frame according to the
dimension state at the
construction drawing.

STEP 6: Install and nail


the door hinges into the
side of door.

STEP 3: After placing the


door frame, the bricks
should be laid.

STEP 7: Core hole for


lockset on the door and
install lockset.

STEP 4: Fill cement mortar


from every two level of bricks
at the gap between the door
frame and masonry wall.

STEP 8: Install door.

58

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.2 WINDOWS
A window is an opening in the wall or roof of a building that is fitted
with glass or other transparent material in a frame to admit light or air
and allow people to see out.

SIZE OF WINDOWS
Kelab Ukay
Residence

3050
575

1200 550 725

600
1400

Rough opening

3000
1000

Casing Trim

Living

Window Frame

2805
725

Head

135
5

72
5

1000

Jamb
Exterior casing:
Not always used.
Drip cap or head
casing

Sill

1500

900

Family 1

Powder Room
59

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.2 WINDOWS
WINDOW OPERATION
1.

2.

Fixed

3. Awning

Consist of a frame and stationary


sash.

Awning windows have operating


sashes that swing outward on hinges
attached to the top of their frame.
When open, the sash is able to direct
ventilation

Casement
-

Have operating sashes that are sidehinged and usually swing outward.
When open, the sash is able to direct
ventilation.
The inner end of the sash may slide
along a track on the sill or jamb as
the sash swings outward.
Kelab Ukay Residence

MATERIAL USED
1.
-

Laminated glass
Built up in layers.
Composed of an outer and inner
layer of polyvinylbutyral( PVB).
Flexible layer retain the glass when
it is broken.
60

7.0 D O O R S & W I N D O W S

ONG SHI HUI 0320303

7.2 WINDOWS
CONSTRUCTION PROCESS

STEP 1: Rough opening of


brick wall are measured.

STEP 2: 1X1 aluminium


subframe is placed into the
rough opening and apply
cement screed to secure
subframe.

STEP 5: Install aluminium frame for


the window frame. Then, measure the
inside of the window frame.

STEP 3: Measure length


and height of the inside.

STEP 6: Cut the glass for the


windows referring to the
measurement.

STEP 4: Install vertical


frames.

STEP 7: Install the hinges and


handles into the windows.
61

8.0 R O O F S

ANG AVERLLEN 0321444

A roof is part of a building envelope. It is the covering on the uppermost part of a building or shelter which provides protection from
animals and weather, notably rain but also heat, wind and sunlight. The word also denotes the framing or structure which supports that
covering. A roof may also provide additional living space, for example a roof garden.
-

MONOPITCH ROOF FEATURES


The monopitch roof is always made out of one single
roofing surface. This kind of roofing is true to its
name; Mono meaning single and the slope is referred
to as the pitch. Monopitch roof construction is
generally stand alone roofs which imply that you dont
need to attach them to any part of your roof. They
differ considerable from traditional roofs which
usually tend to have various pitches and slopes on
various parts of the roof.

Sloping roof may be categorized into


Low-slope roofs up to 3:12 and
Medium-to high slope roofs 4:12 to 12:
12
The roof slope affects the choice of
roofing material, the requirement for
underlayment and eave flashing. And
design wind loads.
The height and area of a sloping roof
increase with its horizontal
dimensions. Sloping roof planes may
be combined to form a variety of roof
forms.

Sloping roof may have structure of


1.
Wood or steel rafters and sheathing
2.
Timber or steel beams,purlins and
decking
3.
Timber or steel trusses.
62

8.0 R O O F S

ANG AVERLLEN 0321444

METAL SHEET ROOFING

Standing or batten

Nailing strips can provide if roofing


is laid over a non-nailable roof deck.

Standing seams are made by folding


up the adjoining edges, then folding
their upper portion in the same
direction

Batten seams are made by turning


up the adjoining edges against a
batten and locking them in place
with a metal strip.

Seams
Horizontal and valley
seams are flat and
usually soldered.
Vertical seams are
spaced depending on
the starting width of the
metal sheets and the
size of the standing or
batten seams.
STANDING SEAMS

BATTEN SEAMS

Metal pan may continue down to


form a deep fascia.

63

8.0 R O O F S

METAL ROOF PANEL


with standing batten for
pitch of roof provides better
protection to the building
from damaging rays and
weathering

ANG AVERLLEN 0321444

TANALISED
ROOF BATTEN
MONOPITCH ROOF
-

FASCIA
PLASTERBOARD

Layer of insulation between


rafters and layer to underside of
joists.
RAFTER BIRD-MOUTHED
over wall plate, and to be fixed to
blockwork with galvanised steel straps.

A single-sloping roof surface


Provides good drainage on
rainy days.
Large open end is shaded
from sunlight to reduce heat
thus decreasing temperature
of the building

Ceiling joists at
high level bolted to
roof joists and
fixed

64

8.0 R O O F S

ANG AVERLLEN 0321444

Blocking may be required on steep slopes to stabilize


purlins.

Cladding fastened to
this flange

Purlin spacing is determined by


decking span.
Thermal insulation may be
applied over roof deck

Narrow
flange

Broad Flange
Bolt in flange
at end of lab

Purlins may frame to the roof


beams with use of metal hangers.

Critical depth
of beam

Rafter

RAFTER is a series of inclined members to a


roof covering which is fixed.
PURLIN is a price of timber laid horizontally
on principal rafters of a roof to support the
common rafter

Ceiling may be applied to create concealed


space for piping, wiring, and thermal
insulation.
65

8.0 R O O F S

ANG AVERLLEN 0321444

METAL ROOF DECKING


Metal roof decking is to support vertical loads and works as a weather resisting system. It transfers the shear loads due to natural forces
such as earthquakes or wind forces to lateral force resisting system.

The primary and secondary


roof beams support open-web
steel joists, a site cast
concrete slab, or precast
concrete units.

Roof overhangs may be


achieved by extending the
secondary roof beams over
their supports
PURLIN SPACING = DECKING
SPAN

Sloping roof beams support


purlins.
BEAM SPACING = PURLIN SPAN

Girders support roof beams at


ridge and eaves.

Roofing membrane over rigid Overhanging framed within the depth of


foam or lightweight concrete primary beam; Web stiffeners
insulation.

Curtain wall panels or facing


veneers may be supported either
by steel edge beams or by a
concrete slab cast over metal
decking.

Spice plate
Ends of beams
may be
tapered or
lightened with
cutouts.
66

8.0 R O O F S

ANG AVERLLEN 0321444

A flat roof is a roof which is almost level in contrast to the many types of sloped roofs. The slope of a roof is properly known as its pitch and
flat roofs have up to an approximate 10 pitched angle. Flat roofs are an ancient form mostly used in arid climates and allow the roof space
to be used as a living space or a living roof.

An upturned edge beam can


form a parapet wall.
A metal reglet may be cast
into the parapet to receive
cap flashing.
The
slab
can
be
cantilevered beyond its
perimeter supports to form
an overhang.
An edge or spandrel beam
can support a nonbearing
curtain wall.
Metal anchors may be cast
into the spandrel beams to
secure the curtain wall
panels.

Wear course
Roofing membrane
Lightweight concrete insulation
Vapor retarder

Steel bearing plate


Wood strap
Split-ring connectors
-

Smooth troweled
finish to receive
insulation and
roofing

Built-up column
support matches
truss thickness

Reinforced concrete
roof slab

67

8.0 R O O F S

ANG AVERLLEN 0321444

Basket Strainer

ROOF GUTTER

Cap

Rain gutter, a narrow trough or duct which collects rainwater from the roof of
a building and diverts it away from the structure, typically into a drain. Main
purpose of a gutter is to protect a buildings foundation by watershed water
away. It also helps to reduce corrosion, preventing leaks in the basement.

Strap

Copper
flashing

STRAP HUNG GUTTER


ON SLOPING ROOF

Gutter
Outlet

Elbows
Expansion
Joint Cap

An method of attaching copper


gutters on sloped roofs. Copper
apron strip is fastened to the
gutter with a single lock seam and
is nailed to the roof with copper
nails .

Screen
Wall
Bracket

Fastener

Downspout

Bracket
Elbow or shoe
Copper Gutter

Splash Block
68

8.0 R O O F S

ANG AVERLLEN 0321444

As the roof gutter works by controlling the flow of the rainwater from entering neither the formwork nor wall which will cause damage to the
painting and the appearance of the building itself. Hence, the roof gutter takes an important role in roofs which is to sustain the building.

Non-rusting
material with
slotted
openings

Dome-slotted to
prevent clogging
Roof
membrane

Combined
flashing collar
and gravel stop

Edge of sump

Water cutoff
mastic

Strainer

Clamping
Ring

Flange

Roof
decking
Outlet to drainpipe

Stripping Felts

Insulation

Insulation
taper
towards
drain

Metal
flashing
Stripping Felts
Deck clamp

Taper insulation
to drain

Weephole

69

SUMMARY

Being able to visit multiple construction sites and witnessing all the thoughtful planning, precise measurements, and
hard labour that goes into the building construction in person has been a great privilege to us all. We were able to
receive a much greater perspective and appreciation toward all the fine details that go into constructing a building
from seeing the building process right in front of our very eyes that no amount of words in a textbook can give us and
we would strongly urge any aspiring architects out there to take the initiative to seek out ongoing construction sites
for their own enlightenment.
Besides being able to better understanding the various topics from our module Building Construction I, visiting these
sites expanded upon our knowledge from our previous semesters Building Materials as we got to actually the
practical uses of all the different materials we studied on up close that cant be seen in the final design such as brick
and concrete in some cases.
When designing any structure, many factors must be taken into consideration. Of course its design will be of
majoritys main concern especially if the majority are the public, but how practical the structure is along with the
planning and process of how it starts from nothing and rises from the ground to stand on its own are just as
important if not more.

70

REFERENCES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.

Home page. (n.d.). Retrieved May 08, 2016, from http://falcon.vodien.com/~sinyuana/catalogsearch/result/?cat=4


Types of stairs - Advantages & Disadvantages. (n.d.). Retrieved May 17, 2016, from https://www.keuka-studios.
com/types-of-stairs/
Home Construction Part 2 (Concrete). (2014). Retrieved May 19, 2016, from http://www.powertochoosehq.
com/concrete
Precast Foundation Walls. (n.d.). Retrieved May 19, 2016, from http://www.hgtv.com/remodel/mechanicalsystems/precast-foundation-walls
TYPES OF REINFORCED CONCRETE RETAINING WALL -Civil Engineering Home. (2014). Retrieved May 19, 2016, from http:
//theconstructor.org/structures/types-of-reinforced-concrete-retaining-wall/8393/
Cast-In-Place Retaining Walls. (2007). Retrieved May 19, 2016, from http://www.concreteconstruction.net/concretearticles/cast-in-place-retaining-walls.aspx
Four Common Types of Rigid, Monolithic Concrete Retaining Walls. (n.d.). Retrieved May 19, 2016, from http://www.
concretenetwork.com/concrete/poured_concrete_retaining_walls/four_types.htm
Presentation on Slab, Beam & Column (n.d.). Retrieved April 28, 2016, from http://www.slideshare.
net/musabbirahmed75/presentation-on-slab-beam-column
Range of safety signages supply by Proguard Malaysia http://www.proguardsafety.com.my/pro-safety-signage.html
A Guide to Scaffold Use in the Construction Industry https://www.osha.gov/Publications/OSHA3150/osha3150.html
Chudley, R. & Greeno, R. (2010). Building construction handbook. Amsterdam: Butterworth-Heinemann.
D.K.Ching, F. (2008). Building Construction illustrated (4th ed., pp. 3.05-3.09). New Jersey: John Wiley & Sons, Inc.
Barry, R. (1999). The Construction of buildings Volume 1 (7th ed., pp. 10-16). Blackwell Science.
Allen, E. & Iano, J. (2004). Fundamentals of building construction. Hoboken, N.J.: J. Wiley & Sons.
Barry, R. The Construction Of Buildings. Oxford: Blackwell Scientific Publications, 1992. Print.

71

S-ar putea să vă placă și