TNB SUBSTATION (PRIMAVERA)

ITEM

DESCRIPTION

PRELIMINARIES

1
2
3

Site clearance
Hoarding and signage
Temporary work

EARTH WORK

Cut to formation level (26 x 18 x 0.3)

PILING WORKS

1
2

Test pile (Dinamic test, PDA)


Piling (spun piles/ driven piles- 12m)

SUB- STRUCTURE

QUANTITY

PRODUCTIVITY RATES

DURATION (DAYS)

MANPOWER

MACHINES

600 m2
100 m
-

1200 m2/ day


80 m/ day
-

1 day
2 days
6 days

1 general worker
2 semi- skilled, 1GW
-

1 Backhoe, 1 bulldozer, 2@3 dumb truck


1 backhoe, 1 concrete mixer
-

140.4 m3

7 m3/ trip/ truck x 6 trip x 2 truck


=84 m3/ day

2 days + 1 day down time = 3 days

1 GW (flagman)

1 excavator, 2 dumb truck ( x boleh


backhoe sbb takut jumpa batu), 1
bulldozer.

1 nos
21 nos

6 nos/ day/ machine

6 days
4 days

1 piler, welder (untuk sambung), 1


GW

Lean concrete (26 x 18)

468 m2

26 x 18 x 0.05 = 23.4 m3
6m3/ trip/ truck x 2 truck x 2 trip = 24 m3/ day

1 day

1 gang = 4 men (1 poker vibrator, 2


levelling, 1 bucket) + 1 GW

Ground beam
a) Rebar

8200 kg

120-250 kg
180 kg/ man day/ 4 men
=720 kg/ day

12 days

b) Formwork

360 m2

6- 12 m2
8 m2/ man day x 4 men
=32 m2/ day

12 days

c) Concrete

42 m3

9 m3/ trip/ truck x 1 nos


6 m3/ trip/ truck x 1 nos
= 15 m3

3 days

1 piling rig, 1 welding set, & oxy cutter

1 mobile crane, 1 pocker vibrator

4 barbender, 1 GW
1 bar bending cutting machine

4 carpenter, 1 GW
1 cutting table

1 gang concretor = 4 men + 1 GW


1 mobile crane, 1 poker vibrator

Con 1
(1)

(4)

Con 2

Con 3

(8)

(12)

F/work
1

TNB SUBSTATION (PRIMAVERA)


3

Ground slab
BRC & concrete

SUPER STRUCTURE

Column @ 4.5 m (height)

Roof beam + slab

468 m2 x 0.250
=11.7 m3

8 nos

9 m3/ trip/ truck x 3 truck x 3 trip


=81 m3

2 days

*BRC
= 250 m2/ day x 2BRC layer

250 m2/ day x 2 BRC layer

1 gang BRC = 2 men

1 set f/ work @ 1.5 m


4 set f/ work @ 6 m

6 days + 2 extra days prep work


= 6 days

4 barbender, 2 skilled (f/work), 1


gang concretor, 2 GW

3 days concrete for every 4 work days


(hari ke- 4 baru concrete)
= 12 days

4 barbender, 6 carpenter, 1 gang


concretor + 3 GW (+ 1 GW for
carpenter)

60- 90 m2
= 8- m2/ gang/ day

6 days

1 gang = 3 @ 4 roofer (2 installer,


welder (if steel)/ carpenter (if
timber), leveler, 1 GW

1 mobile crane, 1 welding set (if steel)

80- 120 m2
= 100 m2/ gang/ day

5 days

1 gang = 3@ 4 roofer

1 mobile crane

468 m2 x 0.15
= 70.2 m3

1 gang concrete + 1 GW
1 poker, 1 mobile crane, 1 backhoe

1 poker, 1 mobile crane, 1


barbending cutting machine, 1
cutting table

L 26 ; W 18
- construction joint ( tak boleh
tempat yg ada loading)
- Kena lebihkan 1/3 @ kurangkan
1/3 utk concrete for roof

ROOFING WORK

Roof structure

Roof covering

468 m2

TNB SUBSTATION (PRIMAVERA)


G

ARCHIRECTURAL WORKS

Brickwall/ brick work

26 x 4.5 x 2(t&b)
18 x 4.5 x 2(l&r)
= 396 m2

6- 12 m2
8 m2/ man day x 6 men
=48 m2/ day

Door & window

1 door & 4
windows

2 doors & 4 windows/ 2 men/ day

Plastering

396 x 2
= 792 m2

8- 12 m2
12 m2/ man/ day x 6 men
= 72

Floor finishes

468 m2

8- 12 m2
12m2/ man/ day x 4 men
=48m2

10 days

Painting
a) Skim coat

1260 m2
40- 80 m2
40 m2/ man/ day x 4 men
= 160 m2

8 days

60- 120m2
80 m2/ man/ day x 4 men
= 320 m2

4 days

b) Finish coat

6)

Door & window

MECHANICAL & ELECTRICAL

Fire protection *

Air conditioning (ACMV) *

Cold water system

Electrical works *

Telecommunication works *

Alarm & CCTV *

Sanitary & plumbing + pipeline water


reticulation

LPG piping

BMS

1 door & 4
window

4 painters
1 sky lift
4 painters

2 doors & 4 windows/ 2 men/ day

TNB SUBSTATION (PRIMAVERA)


10

Rain water system


*yang diguna pakai for this project

INFRA / EXTERNAL WORKS

M & E external work

9 days

3 M & E workers

1 backhoe

Drainage works

12 m3/ 4 trip x 3 lorry

6 days

2 drain layer, 1 GW

1 backhoe

Road works
a) sub- base (aggregate + sand)

300 m3

140 m3/ team/ day

3 days

3 skilled, 2 unskilled

1 backhoe, 1 roller- compactor, 1 back


pusher, 1 vibro compactor

b) road base (crusher run)

700 m3

140 m3/ team/ day

7 days

3 skilled, 2 unskilled

1 backhoe, 1 roller- compactor, 1 back


pusher, 1 vibro compactor

c) binder coarse (ACBC)

120 m3

120 m3/ team/ day

1 day

3 skilled, 2 unskilled

1 paver machine, 1tandem- roller (sekali


dgn steam roller)

d) wearing coarse (ACWC)

120 m3

120 m3/ team/ day

1 day

3 skilled, 2 unskilled

1 paver machine, 1tandem- roller (sekali


dgn steam roller)

e) road kerb

100 m

80 m/ team/ day

2 days

2 skilled, 1 unskilled

1 kerb machine

f) road marking

400 m

300m/ team/ day

2 days

2 skilled, 1 unskilled

1 thermoplastic machine

g) road signage

4 nos

12 nos/ team/ day

1 day

2 semi- skilled

1 backhoe

1
2
3