Documente Academic
Documente Profesional
Documente Cultură
Utility SurveyS
Detailed guidance notes for
specifying a utility survey
Issue 4
OCTOBER 2011
10 TSA
Endorsed by:
TABLE OF contents
Section 1 INTRODUCTION
1.1 Objectives
1.2
Process
1.3 Definition
1.4
Benefits
1.5
What is involved in a utility survey
1.6
General considerations in procuring a utility survey
1.7
What one should look for in a utility survey contractor
Section 2
Equipment and techniques
2.1 Electromagnetic locators(EML)
2.2
Ground probing radar (GPR)
2.3 Other detection techniques
2.4
Closed circuit television (CCTV)
Section 3
Levels of survey
Section 4
Section 5
Section 6
Timescales
Section 7
Excavations/Ground truthing
Section 8
Section 9
Traffic management
Section 10
Section 11
Section 12
Environmental issues
Section 13
TRAINING
Appendix 1
Appendix 9
1 INTRODUCTION
1.1
Objectives
Process
Definition
Service Tracing
b.
c.
d.
e.
CAT scan
f.
1.4
Benefits
b.
c.
d.
1.6.1 Limitations/Expectations/
Misconceptions
There is a perception held by many that all
buried pipes, cables and ducts can be detected
and mapped irrespective of their size, duty,
depth, location, material type, geology and
proximity to other utilities. A well designed
and executed survey should be able to detect
up to around 95% of utilities but it may not
be possible to achieve a 100% detection rate.
It should be noted that most utility surveys
are commissioned to map mains rather than
services to private properties (See section 14).
If services are to be included then this should
be made clear at the tendering stage (Section
4). Services to properties can be difficult to
detect particularly small diameter plastic gas
and water pipes laid at a depth of one metre
or more.
Due to the high cost associated with damage
to fibre-optic cables comment should be made
here on the detectability of this type of utility.
Larger fibre-optic cables are likely to have
metal sheathing making them detectable with
both EML and GPR (see Section 2). Unsheathed
cables laid within a duct should be detectable
with GPR but not with EML unless access to
the duct is possible with a tracer cable. Small
diameter fibre-optic cables laid directly into the
ground are likely to be undetectable.
A utility survey is not a condition survey.
However, the use of CCTV within gravity
drainage systems, or any accessible pipes
and ducts, as an addition to the survey would
provide useful information on the service and
structural condition of the pipes. Similarly trial
excavations dug to verify the results of a utility
survey would also provide verification of, for
example, the extent of corrosion of a cast iron
gas main.
2 equipment
And techniques
A number of techniques involving different
types of equipment can be part of a utility
survey as discussed below. It should be noted
that the use of EML in active mode and
GPR is restricted when working on railway
signalling cables.
2.1
2.1.6 Passive
The passive detection method is usually the
last to be employed within a site based utility
survey. It has two effective modes - Power
and Radio.
2.1.8 Positioning
As with all survey methodologies, there is no
point in accurately tracing utilities if they are
not positioned correctly when permanent
records are required. If the EML system is being
used for the clearance of a borehole position,
then it could be argued that marking the
ground is sufficient and adequate. But in the
event of a subsequent utility strike during the
drilling process it would benefit the surveyor
if documented records could be produced of
what had been found and marked out on the
ground. Such a procedure will give all parties
concerned an added confidence in the services
procured/rendered.
For the borehole situation an indicative plan
with a few dimensions from above ground
features is most likely adequate. After all,
what is important is that the borehole is drilled
in a clear area, not actually where the services
are. Generally, however, the positions of the
traced utilities need to be accurately portrayed
within an accurate representation of the site
area. Otherwise, once the paint marks fade,
the remaining drawing will only be indicative
at best. This would not be of any use on city
based civil engineering projects where space
within the already over congested subsurface
environment is very limited. With designers
basing the positioning of new build or essential
utility diversions on the location of existing
utilities provided through utility surveys it is
essential that everything is thoroughly traced
and that every located utility is topographically
positioned to a common survey grid.
2.2 Ground penetrating (or probing)
radar (GPR)
Single
frequency
Multi
frequency
Single scan
line (per pass)
High density
arrays
10
11
12
13
2.4
b.
Magnetics
c.
Ground conductivity
d.
Earth resistance
e.
Metal detectors
f.
g.
Seismics
h.
Optical (laser)
i.
Microgravity
j.
Acoustic
k.
2.5
3 levels of survey
The table given in Appendix 1 lays out a
suggested stepped approach to carrying
out buried utility surveys. The levels increase
in complexity from a relatively simple
reconnaissance survey to a comprehensive
search with the greatest likelihood of
detecting all the services within the survey
area. By specifying the level required for a
survey at the time of tendering, the client
can compare prices and have confidence
that any survey commissioned will be fit for
purpose. It is important, however, to specify
the maximum survey transect spacing to
ensure the density of the data is adequate
for the survey requirements. The connectivity
between detected, potential pipes becomes
less effective and less accurate with increased
spacing. This sample interval will also help
determine the difference between buried rocks/
debris and pipes. In complicated environments
a close spacing is essential (0.5m or less)
whereas, in areas that contain just a
few services that travel consistently along,
say, a road a larger interval would suffice
(1m or more).
14
4 inputs
from the client
As part of a successful survey a good brief from
the client is needed. It is the intention of these
guidance notes to provide sufficient information
for a client to be able to draw up such a brief
particularly with reference to the schedule
in Appendix 1. Advice on the preparation of
such documents will be given in Appendices 2
and 3 which are still in preparation. However,
as part of the brief, the client should provide
information to the tenderer particularly where
that information is already to hand. Examples
are given below
4.1
Topographic Survey
15
4.2
Records
Access
Known Hazards
Insurances
16
5 outputs from
the contractor
(deliverables)
5.1
Recorded Survey
17
6 timescales
The client should be aware of time scales
and constraints involved in carrying out utility
surveys. Apart from the time needed to carry
out the field work and the reporting, other
factors may well extend timescales for delivery
of the final survey results. These can include
utility record searches where several weeks
may elapse before requests for information are
received and approval of traffic management
proposals particularly where road closures
are involved.
A typical programme should include the
following key stages:
1. Pre-fieldwork preparation including
search of utility companies records
(if appropriate).
2.
Commencement of fieldwork.
3.
Completion of fieldwork.
4.
Commencement of reporting.
18
7 excavations/
ground truthing
Excavation of hand-dug trial holes or smaller
intrusions made using vacuum excavation are
the safest ways to confirm an accurate depth
and position on a utility where there is not
already access via a manhole or inspection pit.
This technique can also be used as a quality
assessment of work carried out by a contractor.
Any intrusive work should be carried to the
requirements of HSG 47 (see Section 15).
It should be pointed out that reinstatement of
the trial hole may be an appreciable part of the
cost particularly if it lies within the carriageway
or areas of quality landscaping.
19
8 accuracy/
confidence ratings/
limit of liability
8.1 Accuracy
8.2
20
Confidence ratings
Limit of liability
21
9 traffic
management (TM)
All work in the highway needs to be carried
out in accordance with the Traffic Management
Act 2004 and the Traffic (Scotland) Act.
Traffic management needs to address
pedestrian traffic as well as vehicular traffic.
In deciding on the scale of TM needed the
following should be considered:
a) The intrinsic health and safety of all
those involved in the survey work and
all who may come into contact with it
(eg pedestrian and motorists)
b) Consultation with the highway authority
and police
c) In the case of major TM consultation
should also be made with residents and
local traders
d)
Suspension of parking
e)
Bus diversions
f)
g)
22
23
11 manhole/
node survey issues
The water drainage industry has well
established procedures for the recording of
drainage manholes. However, the results of
these surveys are often not available to survey
contractors carrying out utility surveys. It is
therefore wise to include lifting the covers on
all manholes, inspection pits and valve etc
within the survey area. Additionally it may be
advisable to include the lifting of covers of
the next manhole on run or within a buffer
zone of say 5m around the survey area to
allow a better understanding of utilities to
which there is no access within the survey area.
Consideration should be given to following a
utility to the next available access point outside
of the survey area if its position is known from
record drawings.
Entry into manholes requires confined space
entry training and equipment. Most utility
survey organisations do not, as a matter of
course, carry such trained personnel and so
are unable to enter manholes. It is therefore
assumed here that the information to be
recorded is that which can be obtained from
ground level. If it is felt that man entry into a
particular manhole is needed then this may well
require a separate mobilisation and pricing.
If manholes are obstructed by, for example,
parked cars then the contractor should advise
the client so that the obstruction can be
removed. Similarly difficult to lift or broken
covers should be reported so that they can be
eased or replaced. This would require a revisit
by the contractor for which re-imbursement
should be made.
It is the responsibility of the contractor to
obtain any permission necessary to lift manhole
and inspection pit covers.
Cover position
b)
Cover dimensions
c)
Cover material
d)
A cover photo
e)
Chamber dimensions
i)
12 environmental
issues
One of the most common environmental issues
associated with utility surveys is the use of
spray paint. Spray paint is used extensively to
mark up the results of the search onto (mainly)
hard surfaces.
Consideration should be given to:
1) Colour codes for the different types of
located utilities (see Appendix 4).
2) Good practice in the use of paint sparingly and discretely (ie length and
width of each line sprayed. Gap distance
between each line sprayed)
3) Use of bio-degradable paints,
wax crayon or French chalk.
4) Marking out of GPR survey grids which
can involve large amounts of paint
marking transect start and finish points
5) Policy on cleaning off paint particularly
in footways / pedestrian areas.
6)
iii.
25
13 Training
Utility location & mapping has been in
existence for many years but due to some
poor working practice and a lack of consistent
training, it has gained a varied reputation
within the wider community, even though it
plays a vital role in the mitigation of risk from
service strikes.
Equipment
All manufacturers of utility detection equipment
offer training in the use of their equipment.
This varies from informal demonstrations to
a formal certificated course. It is essential
that a utility surveyor fully understands the
equipment, including the theory behind the
technology, the practical application and its
limitations in certain environments, in order to
achieve the best results.
Topographic Equipment
The use of Total Stations and GPS will be
required to spatially record the position of
detected utilities and features. Manufacturers
again offer training or more formal training is
available from private training providers such as
The Survey Association survey training courses
at The Survey School (www.surveyschool.co.uk)
or Universities.
First Aid.
Confined Space.
Gas Detection.
Manual Handling.
Working at Height.
Site specific training will sometimes be
required. For example Personal Track Safety
(PTS) for rail sites or Electric Sub Station
Safety Training. Construction sites require any
operative to undertake a site specific induction.
Some utility companies require specific training
26
27
14 glossary of
words, terms
and acronyms
Word
Definition
Electromagnetic locator
28
Word
Definition
EuroGPR
29
Word
Definition
30
Word
Definition
31
15 bibliography
and websites for
further reading
The Survey Association
http://www.tsa-uk.org.uk
Royal Institution of Chartered Surveyors (RICS)
Surveys of Land, Buildings and Utility Services at Scales of 1:500 and larger
Client Specification Guidelines - 2nd Edition 2003
ISBN 0-84506-539-3
American Society of Civil Engineers
Standard Guideline for the collection and depiction of existing subsurface utility data
(CI/ASCE 38-02) 2002
ISBN 0-7844-0645-6
Chartered Institution of Civil Engineering Surveyors (CICES)
http://www.ices.org.uk
Health and Safety Executive
Avoiding Danger from Underground Services
HSG47 2000
ISBN 0-7176-1744-0
http://www.hse.gov.uk/
HMSO London
New Roads and Street Works Act 1991
ISBN 0-1054-2291-6
Radiodetection Ltd
abc & xyz of locating buried pipes and cables for the beginner and specialist
Downloadable pdf from: http://en.radiodetection.com/Document_links.asp?sec_id=2726
Ofcom Ground Probing Radar Licence 603010
http://www.ofcom.org.uk/radiocomms/ifi/wtf/#gp_radar
European GPR Association (EuroGPR)
http://www.eurogpr.org
National Underground Assets Group (NUAG)
http://www.nuag.co.uk/
32
33
appendix 1
Chart showing Levels of Survey
Levels of Survey
Maximum survey
transect spacing
Typical application
Limitations
Level 1
N/A
N/A
Such a reconnaissance
survey will advise the
client on the most
appropriate way to fulfil
the survey objectives.
It will allow the
methodology of any
further survey work to
be carefully determined
using the most
appropriate techniques
so making the follow
up detailed survey cost
effective and timely
This is an advisory
survey only so no
on site mark up or
CAD plans would be
produced. However,
photographs are
usually taken during
the visit which should
be submitted with the
report
34
Levels of Survey
Maximum survey
transect spacing
Typical application
Limitations
Level 3
Electro-magnetic
location survey in
passive and active
mode with located
services being marked
onto ground surface.
Includes cover lifting
to allow line threading
/ sonding. Recorded
manhole survey can be
added as an option.
Advisable to have
Levels 1 & 2 surveys
carried out in addition
Level 4
A Level 3 survey but
with the addition of
ground probing radar
(GPR) in stake out
mode to supplement
EML results. Advisable
to have Levels 1 & 2
surveys carried out in
addition
To be used as above
but where non-ferrous
pipes may be expected
Increased likelihood of
detecting non-ferrous
pipes and ducts.
Unless specified record
plans of survey results
may not be produced
35
Levels of Survey
Maximum survey
transect spacing
Typical application
Limitations
Level 5
Better understanding of
complex areas as close
centred GPR being
deployed
The most
comprehensive level
of survey
Highest expectation of
picking up all services
and other underground
obstructions. Intrusive
investigation on
selected targeted areas
will verify results
GPR to be maximum
0.5m centres
orthogonally in busy
urban situations
down to 2m centres
orthogonally in rural
highways. In open
spaces such as parks
and playing fields
orthogonal spacing can
be increased to 5m but
client to determine %
coverage with GPR and
where it is to
be located
Level 6
GPR to be maximum
0.5m centres
orthogonally in busy
urban situations
down to 2m centres
orthogonally in rural
highways. In open
spaces such as parks
and playing fields
orthogonal spacing
can be increased to
5m. All with 100% area
coverage
Key
Level 1
& Level 2
Preliminary/
reconnaissance levels
of survey
Level 3
& Level 4
Level 5
& Level 6
The most
comprehensive levels
of survey and reporting
36
appendix 2
Flow chart with advice to clients for specifying a survey
What sort
of survey do you
require?
A comprehensive and
detailed survey of the
utilities on site
Level 1 or 2
survey needed.
Go to page 38.
Level 3 or 4
survey needed.
Go to page 39.
Level 5 or 6
survey needed.
Go to page 40.
Please Note
These flow charts are not a step by step procedure for procuring a utility survey but provide a series of notes giving
guidance as to what to consider during the process
The flow starts at the point of identifying a need for a utility survey and ends when enquiries (tenders) have been sent
out to bidding survey contractors
It assumes the general prodedure for obtaining competitive tenders is familiar to the users of the guide
37
Level 1 or 2 Survey
identified as appropriate
Yes
No
Select and contact two or three
contractors offering this service
to get competitive quotes
(TSA can help with this)
38
Level 3 or 4 Survey
identified as appropriate
Level 3 survey
would suffice
No
Do you need to
find non-metallic pipes
and cables?
Yes
Please Note
It is advisable to have at least a Level 1 survey carried out in advance of any fieldwork
39
Level 5 or 6 Survey
identified as appropriate
No
Yes
Please Note
It is advisable to have at least a Level 1 survey carried out in advance of any fieldwork
40
appendix 3
Appendix 1 lays out the various levels of survey that can be considered by the client to obtain
the best value for money in commissioning a utility survey. Appendix 3 sets out a corresponding
method of measurement that should accompany a specification using the levels of survey.
There are options included within the method of measurement that are not mentioned in
Appendix 1. These options are suggested to add value to the survey so taking advantage of the
costs incurred in mobilising a survey team to site. As an example a series of options are suggested
to enhance the manhole surveying so exploiting the lifting of its cover.
An Excel version of this method of measurement can be downloaded from TSA website to help
configuring it to specific needs and incorporation into tender documents.
41
Section A
Summary of Scope of Works
Item
No
Description
Included in
scope
Unit
(m2)
No.
(m2)
(m2)
(m2)
(m2)
(m2)
(m2)
Quantity
Rate
Total
Quantity
Rate
Total
Section B
Level 1 Survey
Item
No
Description
Included in
scope
Area of search
(m2)
Item
Item
Item
Item
Yes/No
Unit
Item
Total
42
Section C
Level 2 Survey
Item
No
Description
Included in
scope
Unit
Item
(m2)
Yes/No
Item
Yes/No
Item
Quantity
Rate
Total
Item
Yes/No
Item
Total
* Requires Level 1 survey to have been carried out
Section D
Level 3 Survey
Item
No
Description
Included in
scope
Item
(m2)
MH/node survey
a) Visit MH/node
b) Photograph cover
Unit
Yes/No
Number
Yes/No
Number
e) P
roduce schematic of MH
chamber including all
connections*
Yes/No
Number
f) R
ecord depth to invert of all
connections*
Yes/No
Number
g) C
arry out active EML survey
(sonding/line tracer)*
Total
Number
d) P
hotograph interior
of chamber*
Rate
Number
c) Lift cover
h) Incorporate results of MH
survey into drawings*
Quantity
Number
Yes/No
Number
Item
Yes/No
Item
Total
* Requires item 5 to be included in scope
43
Section E
Level 4 Survey
Item
No
Description
Included in
scope
Item
(m2)
MH/node survey
a) Visit MH/node
b) Photograph cover
Unit
Number
Yes/No
Number
e) P
roduce schematic of MH
chamber including all
connections*
Yes/No
Number
f) R
ecord depth to invert of all
connections
Yes/No
Number
g) C
arry out active EML survey
(sonding/line tracer)*
Total
Number
d) P
hotograph interior
of chamber*
Rate
Number
Yes/No
c) Lift cover
h) Incorporate results of MH
survey into drawings*
Quantity
Number
Yes/No
Number
(m2)
Item
Yes/No
Item
Total
* Requires item 6 to be included in scope
44
Section F
Level 5 Survey
Item
No
Description
Item
(m2)
MH/node survey
Included in
scope
Unit
a) Visit MH/node
Number
b) Photograph cover
Number
c) Lift cover
Number
d) P
hotograph interior
of chamber
Number
e) P
roduce schematic of MH
chamber including all
connections
Number
f) R
ecord depth to invert of all
connections
Number
g) C
arry out active EML survey
(sonding/line tracer)
Number
h) Incorporate results of MH
survey into CAD drawings
Number
(m2)
Yes/No
(m2)
Yes/No
(m2)
Yes/No
(m2)
Yes/No
(m2)
Yes/No
Quantity
Rate
% of whole
area
Item
Item
Total
45
Total
Section G
Level 6 Survey
Item
No
Description
Item
(m2)
MH/node survey
Included in
scope
Unit
a) Visit MH/node
Number
b) Photograph cover
Number
c) Lift cover
Number
d) P
hotograph interior
of chamber
Number
e) P
roduce schematic of MH
chamber including all
connections
Number
f) R
ecord depth to invert of all
connections
Number
g) C
arry out active EML survey
(sonding/line tracer)
Number
h) Incorporate results of MH
survey into CAD drawings
Number
(m2)
Yes/No
(m2)
Yes/No
(m2)
Yes/No
(m2)
Yes/No
(m2)
Yes/No
Quantity
Rate
100% of whole
area
Item
Item
Total
46
Total
Section H
Other Requirements/Options
Item
No
Description
Included in
scope
Unit
Yes/No
(m2)
Traffic management
Yes/No
Item
Yes/No
Item
CCTV of drainage
Yes/No
Linear
metres
Yes/No
(m2)
Yes/No
Number
Yes/No
(m2)
Yes/No
Number
Yes/No
Item
10
Yes/No
Item
Quantity
Rate
Total
47
Total
appendix 4
Colour codes for on site mark up and drawing line codes
Despite carrying out extensive enquiries no published guidance appears to be available advising
on the colours and line-styles to be used in both marking up the detected lines of utilities on
site nor for the depiction of such utilities in drawings. However, the National Joint Utilities
Group (NJUG) Publication Volume 1 Issue 4 Guidelines on the positioning and colour coding
of underground utilities apparatus published in 8th January 2009 provides information on the
colours used for buried ducts, pipes, cables and marker/warning tapes. These NJUG guidelines
have been used as a basis for the schedule below. As most survey suppliers only stock seven
different colours of spray paint and wax crayon (namely black, green, orange, red, blue, white and
yellow) it is pragmatic to limit the on-site mark up to seven colours.
Utility
Buried
Duct
Buried
Pipe
Buried
Cable
Buried
Warning
Tape
On Site
Mark-up
CAD
Drawing
Line Colour
Gas
Yellow
(or pale
green)
Yellow or
yellow with
brown stripe
N/A
Yellow
with black
legend
Yellow
Yellow
(see Note
1 below)
Water
Blue or
grey
Blue
Blue
Blue
Blue
N/A
Black with
green stripes
N/A
N/A
Blue
Blue (with
note)
N/A
N/A
N/A
Blue
Blue (with
note)
N/A
Blue with
brown stripes
N/A
Blue or
blue/black
Blue
Blue (with
note)
Oil/fuel pipelines
N/A
Black
N/A
Various
Black (see
Note 2 below)
Black (with
note)
Sewerage including
foul, surface water,
combined and
pumping mains
Black
Not specified
N/A
N/A
Black (see
Note 2 below)
Brown
Electricity (HV)
Black or
red tile
N/A
Black or
red
Yellow with
black and
red legend
Red
Red
Electricity (LV)
Black or
red
N/A
Black or
red
Yellow
with black
legend
Red
Red
Telecommunications
Grey,
white,
green,
black or
purple
Light grey
or black
Various
White
Magenta
48
Highways
Authority Services
Buried
Duct
Buried
Pipe
Buried
Cable
Buried
Warning
Tape
On Site
Mark-up
CAD
Drawing
Line Colour
Street lighting
England and
Wales
Black or
orange
N/A
Black
Yellow
with black
legend
Red
Red
Street lighting
Scotland
Purple
Purple
Yellow
with black
legend
Red
Red
Traffic control
Orange
Orange
Yellow
with black
legend
Green
Green
Street furniture
Black
Black
Yellow
with black
legend
Green
Green
Telecommunications
Purple/
orange
Black
Various
White
Magenta
Motorways
Buried
England and Wales Duct
Buried
Pipe
Buried
Cable
Buried
Warning
Tape
On Site
Mark-up
CAD
Drawing
Line Colour
Communications
Purple
Grey
Yellow
with black
legend
White
Magenta
Communications
power
Purple
Black
Yellow
with black
legend
Red
Red
Road lighting
Orange
Black
Yellow
with black
legend
Red
Red
Motorways
Scotland
Buried
Duct
Buried
Pipe
Buried
Cable
Buried
Warning
Tape
On Site
Mark-up
CAD
Drawing
Line Colour
Communications
Black or
grey
Black
Yellow
with black
legend
White
Magenta
Road lighting
Purple
Purple
Yellow
with black
legend
Red
Red
Notes
1. Yellow printed out on drawings is low contrast against a white background. If photocopied
in black and white yellow is likely not to reproduce and will not appear on the copy.
2. Black is not an ideal spray paint colour to use on blacktop and blue disappears at night
under sodium lighting.
3. It is recommended that orange is used for marking out the GPR survey grid on site and for
unknown utilities on drawings.
4. When drafting up the results of a survey in CAD it is recommended the base mapping is
greyed out to increase contrast with the utility lines and so improve clarity.
49
SV = Stop Valve
AV = Air Valve
Top number is the nominal pipe diameter in millimetre (old imperial markers will show inches)
Bottom number is the distance to the utility from the face of the marker in metres (old imperial
markers will show feet)
Simplified Key for Line Types in Interpretation Drawings
NB
Confidence rating levels are for all parameters of a utility not just depth
Depth to be to the top of the utility unless stated otherwise
If depth cannot be assessed then the code NK to be used where the depth normally is shown
Additional information such as size and material type can be added if known
50
appendix 5
Examples of output the following page shows an example of the results of a utility
survey using the key from Appendix 4.
51
52
appendix 6
Detection Capabilities of Different Techniques
Equipment
Electromagnetic
locators and
signal generators
Mode
Depth
Range
Depth
Determination
Minimum
Size
Notes
Passive
Up to 3m
No
N/A
Depth depends on
signal on service and
length of service.
May not detect well
balanced electricity
cables
Induction
Up to 3m
Yes
(+/-5% of depth
under normal
conditions)
N/A
Connection
Up to 10m
depending
on signal
strength
Yes
(+/-5% of depth
under normal
conditions)
N/A
Sewer
Sonde
Up to 15m
depending
on Sonde
type
Yes
(+/-5% of depth
under normal
conditions)
Depends
on Sonde
type.
Smallest
Sonde
diameter
15mm
Up to 3-4m
depending
on ground
Yes
(+/-10%)
Sometimes
better in
good ground
conditions
25mm
(see note
in Section
1.6.3)
6m
No
0.7m
GPR
(100MHz to 1GHz)
Ground
Conductivity
(Geonics EM31)
53
Vertical
dipole
GPR vertical resolution for different antenna frequencies and soil conditions
Medium
Air
Concrete
Dry Soil
Damp Soil
Wet Soil
Er
14
25
Velocity m/nsec
0.3
0.12
0.1
0.08
0.06
25
12.00
3.00
4.80
1.20
4.00
1.00
3.20
0.80
2.40
0.60
50
6.00
1.50
2.40
0.60
2.00
0.50
1.60
0.40
1.20
0.30
100
3.00
0.75
1.20
0.30
1.00
0.25
0.80
0.20
0.60
0.15
200
1.50
0.38
0.60
0.15
0.50
0.13
0.40
0.10
0.30
0.08
400
0.75
0.19
0.30
0.08
0.25
0.06
0.20
0.05
0.15
0.04
900
0.33
0.08
0.13
0.03
0.11
0.03
0.09
0.02
0.07
0.02
1000
0.30
0.08
0.12
0.03
0.10
0.03
0.08
0.02
0.06
0.02
1500
0.20
0.05
0.08
0.02
0.07
0.02
0.05
0.01
0.04
0.01
Antenna
Frequency
MHz
Key
Wavelength= velocity/frequency
Resolution = wavelength/4
It is also worth looking at the following link to the Mapping the Underworld website where the
results of a questionnaire on accuracy of geophysical utility mapping are presented:
http://www.mappingtheunderworld.ac.uk/qupdate1.html
54
appendix 7
Policy on the use of GPR in utility detection
1. Survey Strategies
1.1 In theory, there are two basic (GPR) survey approaches for the detection of buried
utilities, namely
a) The use of a dense grid of orthogonal data which is then processed and interrogated back
in an office environment; and
b) On-site interpretation where the radar data is interrogated by the field surveyor during
data collection.
1.2 In the former case, the lines of utilities are established and incorporated into final CAD
drawings. In the latter case, the radar data is interrogated by the field surveyor during data
collection and the lines of utilities are marked on the ground for possible later topographic
survey and incorporation into CAD.
1.3 In reality, these two apparently radically different approaches extend into a range of survey
strategies, based primarily on one or the other of these two approaches.
1.4 For all survey strategies, the density of the survey data collected has a direct effect on the
likelihood of detection. The less dense the data set, the greater the risk of non detection.
2. Advantages of Off-Site Interpretation
2.1 This approach offers an increased potential to resolve multiple targets which is of increasing
importance in urban contexts.
2.2 Quality control, in terms of probability of detection can be appraised in a more rigorous
manner.
2.3 This strategy allows the use of different grades of personnel to collect and to interpret the
data, although this may not always be appropriate.
3. Advantages of On-Site Interpretation
3.1
3.2 This method also allows the detection of utilities within their context at the time of the
survey.
3.3
3.4
The operator is strongly motivated to monitor data quality during the survey.
4.
4.1 This approach potentially involves a greater input of time both in data collection and in
post survey processing and hence is potentially more costly.
55
5.
5.1 It is difficult to ensure all utilities are detected reliably in a complex environment containing
multiple services.
5.2
5.3 There is a potential for loss of quality control which is heavily dependent upon the
experience of the GPR surveyor.
6. Guidance to EuroGPR Members
6.1 The European GPR Association recognises the importance of adequate data collection.
Survey parameters such as sampling intervals and area coverage will vary from one site
to another. It is therefore important to adopt an approach which recognises the risk and
outcomes of non-detection within the context of each individual survey.
6.2 While recognising that it may not be either practical, or, possibly, cost effective to adopt
rigorous full area coverage with off-site post processing in all cases, it is essential for
both the GPR survey provider and the survey client to be aware of the potential risks of
curtailment. The important underlying principle of the survey method adopted should be
to set out the level of service and any inherent risks resulting from that method. For this
reason, some members may choose to offer a tiered service.
6.3 The European GPR Association also recognises that survey clients may tend to focus on
the cost of the survey at the expense of the potential risks of the survey method. There is
a need for good detailed technical advice to those commissioning a GPR survey. EuroGPR
will co-operate with the Survey Association and other professional bodies who also interact
with our client groups in order to draw up and distribute this advice.
6.4 It is essential that the GPR survey provider is capable of demonstrating professional
competence. The Association expects that its members will be capable of justifying their
approach to the survey. They should also be capable of substantiating any technical claims
that they make for equipment or specialist software by demonstration or other appropriate
means.
Date Approved: 5th March 2009 (European GPR Association Meeting)
This policy was kindly supplied to TSA by Erica Utsi, Chair EuroGPR
56
appendix 8
Professional Indemnity Insurance Considerations
It is believed that utilising the methodologies outlined in the guidance notes will have a
positive impact on the utilities survey, both in avoiding problems and dealing with them if
they should arise.
Full understanding between the parties regarding the scope and limitations of the utilities
survey is likely to avoid problems due to perceived short comings or misunderstandings
regarding what is possible
Giving the client the choice of survey enables greater client understanding and buy in to
the results of the survey
In the event of a problem, greater clarity regarding type of work undertaken and clear
instructions from the client regarding the same assist in bringing clarity to the duties of the
surveyor in the performance of their appointment, and identifying whether there have been
any short comings in that performance
It ensures that a written agreement is drawn up between the surveyor and the client
The written agreement and greater clarity can assist in avoiding problems, or at worst,
prevent ambiguity from unnecessarily lengthening a claim and incurring costs as a result,
to the benefit of both sides
The surveyor must ensure that their administrative procedures (terms of business
agreements, recorded instructions including verbal communications, etc) are clear
and unambiguous
Above all they must be demonstrable (i.e. provable) as this area will be under intense
scrutiny and question in the event of a claim
Clients should be aware of the following Disclaimer (echoing considerations set out earlier in the
guidance notes):
Please note that not all buried pipes, cables and ducts can be detected and mapped in
consideration of their depth, location, material type, geology and proximity to other utilities.
Even an appropriate and professionally executed survey may not be able to achieve a 100%
detection rate.
57
IMPORTANT
Utilities surveyors should be aware that they are not relieved of their duty of care to their client.
Appropriate advice would still need to be given, even if the client is insistent on a particular level
of utilities survey, and no matter what disclaimers are used. Surveyors may deem it appropriate to
limit their liability.
An appropriate clause may be inserted into the surveyors contracts: (example)
Our Liability under this agreement shall be limited to << XXXX >> for any one claim or series of
claims arising out of any one source or originating cause.
Reference should be made to the Unfair Contract Terms Act 1977 in setting the applicable limit
within the clause and the reasonableness of the same to the sums involved. A court may set aside
a limitation provision if they deem it to be unreasonable.
Clients should ensure that the surveyor carries adequate professional indemnity insurance, so
that funds are available to meet any losses should there be a problem. Whilst the purchase of
professional indemnity insurance is not mandatory for the land surveyors profession, clients of
members of The Survey Association have the reassurance that this organisation makes purchase
of professional indemnity insurance mandatory and has an exclusive member arrangement
through Lockton Professions.
58
appendix 9
The primary author of this document was Peter Barker. It was developed by The Survey Association
Technical Committee under the Chairmanship of Graham Mills. We would like to thank all
members of the Technical Committee and TSA Council for their contribution.
Consultees and Acknowledgements
An early draft of the document was widely distributed to many organisations associated with
the utility survey industry. Of these, 17 companies and organisations responded with constructive
comments, some of them at some length. A list of these consultees is given below. Our thanks go
to all of them for their time and thought. It is much appreciated.
Particular thanks is due to Mark Dawson of the Health and Safety Executive for his input as well
to RICS and CICES.
Giovanni Alli
Pete Bevils
Jonathon Bogan
Nadia Boukhelifa
Gerry Bowditch
Mike Bushell
Peter Crouch
Dr Martin Cullen
Jes Galtress
Ray Hanney
Alan Jones
Nigel Knowles
Mike Langton
James Lewis
Guido Manacorda
Martin Shaw
Craig Simmonds
Alan Thunhurst
Erica Utsi
59
The Survey Association is also grateful to the following manufacturers for the use of the images
illustrating EML and GPR equipment in this section:
3D Radar
C Scope International Ltd
GSSI
IDS
Mal Geoscience
Pipehawk
Radiodection Ltd and
Utsi Electronics
60
November 2009
Original document
June 2010
Addition of Appendix 3
March 2011 Change of title to The Essential Guide to Utility
Surveys and addition of revision history
October 2011 Addition of Appendix 2 and minor additions to
Section 15
Endorsed by: