Documente Academic
Documente Profesional
Documente Cultură
Procedure
MarineCommissioningProcedure
Page1of28
LEBM002500
7.3 Vessel Operating Procedure for Acquiring Sea Trial Data (Prop) ........... 18
7.4 Analysis of Sea Trial Test Results (Propulsion Systems) ......................... 18
8 CAMPAR for Data Analysis .................................................................................. 18
8.1 CAMPAR Fuel Rate and Performance Analysis ........................................ 18
8.1.1 Engines Properly Loaded........................................................................ 20
8.1.2 Engines Over-Loaded.............................................................................. 21
8.1.3 Electronics or Fuel Delivery .................................................................... 22
8.1.4 Engines Under-Loaded ........................................................................... 23
8.1.5 Vessel Design ........................................................................................... 24
8.2 CAMPAR Boost Pressure Analysis .............................................................. 25
8.2.1 Acceptable Boost Pressure .................................................................... 25
8.2.2 Inadequate Air System ............................................................................ 26
8.2.3 Engines are Under-Loaded .................................................................... 27
9 Cooling System Evaluation ................................................................................... 28
10 Hyperlinks ............................................................................................................. 28
11 Supporting Documents ....................................................................................... 28
NOTE of Supersession
Introduction
2.1 Foreword
Commissioning is generally defined as the process by which an equipment, facility or plant is
tested to verify its functions according to its design objectives or specifications. We can have
partial or complete commissioning depending on the state of completion of the vessel.
As all definitions generally leave room for interpretation, the details need to be adapted for every
commissioning. It is incorrect to confuse the commissioning with some operational tests. It is
important to understand that the sea trials have to be seen as a part of the commissioning
process of the installation, hence using the terms commissioning and sea trials as the same thing
is not correct. Caterpillar approved sea trials ensure that all the systems and circuits of the vessel
are properly scrutinized and matched with the power system.
Engine-specific information and data is available from a variety of sources, however TMI is the
preferred source. A list of sources is provided in the reference section of this guide. Systems and
components described in this guide may not be available or applicable for every engine.
NOTE: The owner of the commissioning process remains the dealer and its local organization.
A list of hyperlinks can be found at the end of this document in Section 9 of this document.
MarineCommissioningProcedure
Page2of28
LEBM002500
The success of a project depends by the synergy of all the composing activities: It is important
that regardless of the business structure adopted by the dealer, sales people will collect
information for every new project. Information should be organized and made available.
A powerful tool is the Marine Service Interlink web database. Information on this database can
be found on Power Net.
Field experience confirms that a proper commissioning of the installation and thorough sea trials
will pay back both in terms of customer satisfaction and in preventing future problems. Proper and
uniform documentation of the process, communication, and updated records are necessary steps
to achieve these results. Understanding the engine and the marine engine room components are
pre-requisites for any engineer involved in a commissioning. Mastering the Caterpillar A&I
guidelines, Caterpillar Project Guides, Cat ET, and CAMPAR are necessary for a proper
understanding of the vessel behavior.
The engine installation should be designed to give safe, efficient and reliable operation. A poorly
designed installation can hinder serviceability, and make routine maintenance and repairs difficult
and costly. The neglect of specific design requirements for mounting, alignment and support
systems can lead to poor performance and increased operational costs or even severe damages.
Commissioning
For our purposes, we assume that the commissioning process begins with the installation
review of the dealer and ends with the acceptance of the vessel by the customer. Neither the
sales nor the vessel design review are included in the process. Despite this, the importance of
the design review remains and dealers should, as much as possible, take an active role in
matching the installation and the propulsion system.
It is worth mentioning the design review, or pre-installation, process. Product News Marine
Engine Installation Process (LEXM3285, found on Power Net) provides an overview of this
information. This publication documents the standard marine engine installation process and
outlines the appropriate tools and documents necessary to properly evaluate a marine engine
installation. Notably from this document The purpose of this process is to ensure that the vessel design will meet Caterpillar guidelines
prior to engine purchase and delivery. This is completed, as a general rule, for the first hull of a
production run, during any significant change to a production run, for any custom boat, or for a repower installation.
1. Caterpillar selling dealer defines Caterpillar engine installation requirements using the
Application and Installation guides and, if needed, Marine Application Support Center.
MarineCommissioningProcedure
Page3of28
LEBM002500
2. Selling dealer and boat builder complete the Design & Construction Review Form
(SEHS8716) and determine if the current design will meet Caterpillar guidelines.
SEHS8716 can be found on Power Net.
3. Selling dealer and boat builder work together to ensure design will meet Caterpillar
guidelines.
4. Selling dealer submits the Design & Construction Review Form to the Marine Service
Interlink web database.
MarineCommissioningProcedure
Page4of28
LEBM002500
NOTE: Regarding any long term preservation requirements, refer to Special Instruction
Storage Procedure for Caterpillar Products (SEHS9031, found on SIS Web).
If for any reason the vessel was in lay-up and the engines were left non-operational for an
extended period, ensure and document the proper start-up procedures, as per SEHS9031 (found
on SIS Web), are performed.
The pre-start-up checklist is meant to assist the commissioning engineer during a safety and
functional assessment of the engine room and its equipment. Small items such as leaks or loose
wires, missing sensors, or incomplete documentation could turn the sea trials into a nightmare
the intent of these checklists is to 1) help ensure the actual sea trial will be completed as
seamlessly as possible and 2) provide sea trial documentation.
NOTE: Upload all additional information in the Marine Service Interlink web database.
Some checks and inspections are listed below. Refer to the Marine Commissioning Checklists in
***EDIT*** for a complete list of suggested activities.
-
MarineCommissioningProcedure
Page5of28
LEBM002500
2.
3.
4.
5.
6.
7.
8.
9.
NOTE: Some modification to this chart may be required, depending on your particular rating or
application requirements.
Time (minutes)
1000
1200
1400
1600
1800
1900
2000
2100
2200
Wide Open Throttle (WOT)
Sea Trials
Sea trials, regardless the type, are the most effective way to evaluate the vessel performances in
its real environment.
Effective sea trials, although not required by Caterpillar, provide data for the evaluation of
propulsion system performance. This data will also aid in the identification of system problems
that can lead to potential performance problems. This will help both the customer and the dealer
to develop maintenance and repair schedules that will provide the most economical and efficient
cost of operation.
There are three types of sea trials, each of which will be discussed later in this section.
-
MarineCommissioningProcedure
Page6of28
LEBM002500
Prior to conducting a sea trial, electronic and control functional tests should be conducted. Each
test will include an electronic functionality test to verify proper operation of all gauge panels,
electronic components, data link, J1939 wiring requirements followed, compare vessel
instrumentation to the service tool, throttle, mechanical throttle linkage check, switch operation if
equipped (synchronization, slow vessel, trolling, trip clear and engine shut-off).
Photographs are a valuable documentation tool. Throughout the commissioning process,
document both the good and the bad of engine installations. In addition to specific photos, such
as air inlet and exhaust connections, water connections, and vibration isolators (mounting
groups), also capture photographs of:
-
Ensure the latest released version of Caterpillar Electronic Technician (ET) with Sea Trial
Data Logger is installed. ET is used on electronic engines to communicate ECM monitored
engine parameters.
Sea Trial Data Reduction Software: Computer-Aided Marine Performance Analysis Report
(CAMPAR), which is available on Marine Service Interlink.
Cat Communication Adapter: Used to communicate engine monitoring information between
the engine ECM and Cat Electronic Technician (ET). 317-7482 Comm. Adapter 3 is
preferred. 171-4400 or 275-5120 Comm. Adapters are also acceptable.
Cat Data link Y Cable. Cable assembly 211-4988 that joins the data link between the port
and starboard engines which provides the necessary connection to record both engines in
sea trial data logger simultaneously.
NOTE: This cable will not be required if the OEM has included the coupling of the engines data
links in the vessel wiring or the Plug and Run wiring system was ordered from Caterpillar Inc.
NOTE: The Cat Data Link cable only transfers data on the Caterpillar Data Link (CDL).
Parameters being broadcast on J1939 network will not be broadcast via CDL cable.
CAMPAR is the official software developed by Caterpillar to evaluate sea trials. The data that is
taken during sea trials will be compared to and plotted against the performance data that can be
found in TMI by test spec number. CAMPAR is used to aid certified marine analysts in:
-
Formulating actual and factory-specified test results for marine propulsion engines and
transmissions.
Producing a graphic representation of the actual and factory-specified fuel rate, boost
pressure and exhaust temperature results for propulsion systems utilizing fixed pitch
propellers under normal operating conditions.
Making consistent interpretations and recommendations from the test results, for marine
propulsion engines and transmissions.
CAMPAR is accessed through the appropriately named tab on Marine Service Interlink. A
CAMPAR User Guide can also be found on MSI. If the CAMPAR tab does not appear or the link
MarineCommissioningProcedure
Page7of28
LEBM002500
is not valid, contact the MSI help desk for CAMPAR access.
CAMPAR follows the easy rule of garbage in garbage out. This means that incomplete or
inconsistent data will not produce reliable results.
GPS Interface Module (recommended, but not required). The GPS interface module with the
addition of a hand held Global Positioning System (GPS) will transmit the vessels speed, latitude,
longitude and heading to the Cat Data Link for recording these parameters via sea trial data
logger. Refer to SENR5002 for GPS to GPSIM connections.
Before a test of the propulsion and/or auxiliary engines and transmissions, install the diagnostic
tool, thermistors and pressure pickups needed to obtain the performance data that is required.
This is accomplished in part by installation of Caterpillar self-sealing probe adapters into test
ports.
Probe seal adapter groups are for use with the temperature and pressure measuring diagnostic
tools. They allow probe insertion through the center, and they seal when the probe is removed.
The adapters can be permanently installed and are equipped with a hex head plug to eliminate
leakage and debris accumulation. The following probe seal adapters are available through
Caterpillar:
-
The location of these test points are given in the general dimension drawings, and are indicated
by a system of 900 series numbers. The drawings also give the thread type and size at each
location. The installation drawings showing specific test ports and corresponding sizes are
available on the Engine Drawing Design Center (EDDC).
MarineCommissioningProcedure
Page8of28
LEBM002500
Refer to EDDC or Caterpillar Project Guides for available 900 points for your particular engine.
Blow-by/Airflow Indicator
Engine Timing Indicator
Signal Generator
Electronic Position Indicator
Multi-Tach II
Digital Thermometer
Fuel Flow
Pressure Meter
Burn Rate Meter
DigitalPressureGroup(1984240)
Required for all sea trials.
Digital Pressure Group (198-4240) permits a check of air cleaner restriction, oil pressure,
manifold pressure and fuel pressure. Provides readings in psi and kPa. Group covers pressure
ranges from 15 psi to 150 psi (100 kPa to 1000 kPa).
FuelGravity
Required for all sea trials.
MarineCommissioningProcedure
Page9of28
LEBM002500
Fuel Gravity (API). 1P7408 thermo-hydrometer and 1P7438 beaker are used to measure the API
gravity and temperature of diesel fuel so corrected horsepower ratings can be calculated.
CrankshaftDeflection(ONLY3500&3600engines)
Required for all sea trials.
Crankshaft Deflection. Starrett 696 Crankshaft Deflection Dial Indicator is used to ensure the
cylinder block has not been unduly stressed by incorrect engine mounting, resulting with
crankshaft deflection.
DialIndicator
Required for all sea trials.
Dial indicator with magnetic base are used for basic alignment measures between the flywheel
and coupling or coupling and gearbox.
DigitalMultimeter(1464080)
Required for all sea trials.
Digital Multimeter for measuring electrical values and type K thermocouples.
InfraredThermometerII(1236700)
Required for all sea trials.
Infrared Thermometer II is for measuring surface temperatures.
FuelFlowMeter
Required for all sea trials.
Caterpillar fuel flow meters are the most accurate and versatile measurement tool to aid the
Caterpillar Marine Analyst in the evaluation of engine performance and fuel consumption during
sea trials. Caterpillar fuel flow meters should be the preferred method to collect fuel consumption
data over the fuel rate displayed via Cat ET or the engine display.
The Fuel Monitor System (FMS) is available in several different arrangements.
Part Number
Engine Family
368-9911
C18 and
smaller
308-7271
Always note the accuracy of the measuring tool when performing fuel flow measures.
accuracy of the meters can be calculated using the following formula:
The
% Accuracy, Max. Error = (.5 x Supply Rate)(.5 x Return Rate) /Burn Rate
When it is installed and connected correctly, the Caterpillar Fuel Monitor System can provide
MarineCommissioningProcedure
Page10of28
LEBM002500
accurate fuel flow measurements for Caterpillar marine diesel engines. Before installation and/or
connection of the unit, locate the fuel supply and return lines for the engine, and determine the
best location to make a connection. The fuel supply flow meter must be connected between the
fuel supply tank and the fuel transfer pump. The return fuel flow meter must be connected into the
fuel line that goes to the fuel tank. Use the hoses and connections from the hose adapter groups,
as needed, to make these connections.
NOTE: Make sure the area for fuel line disconnections and fuel monitor line connections is
absolutely clean. No debris or paint chips must be permitted to enter the fuel system or the
meters. When connecting a meter, always connect it so the flow of fuel is in the same direction as
the fuel flow arrow on the side of the flow meter.
MarineCommissioningProcedure
Page11of28
LEBM002500
Temperature situations. Ambient capability charts for applicable engine serial numbers can be
found in TMI. Complete PMS tables can be found in SIS Web.
MarineCommissioningProcedure
Page12of28
LEBM002500
MarineCommissioningProcedure
Page13of28
LEBM002500
Fuel burn can be measured two ways. ECM data (ADEM 2 and newer) is normally accurate
within +/-5%. In most cases, this data is acceptable to use. If you suspect something wrong
with the data or you have an engine problem then you should use the mechanical flow
meters to back up the ECM data (mechanical flow meters not required for OEM sea trial).
Seawater inlet restriction. In no case, should the seawater pressure, measured at the
seawater pump suction, restriction be more than 3.5psi/24Kpa gauge.
Seawater outlet pressure. This will give a flow rate based on the head from TMI data for the
auxiliary pump.
Vessel speed GPS and speed log must be recorded. This will establish a base line if future
performance questions arise.
MarineCommissioningProcedure
Page14of28
LEBM002500
In addition to evaluating the propulsion systems performance, the sea trial includes an
evaluation of auxiliary systems. Most auxiliary performance evaluations can be conducted
dockside, under the intended load at rated speed. The crew should be notified of the test
procedure, and informed as to what will be required of them during the test. Use Cat ET to
record all information, physical description, and performance data. For load step checklist and
start-up checklists, please refer to the Appendix.
Generally, the load required with the vessel at mooring is only a fraction of the power demanded
when in operation: reserve some time during sea trial to test the different generator sets with real
loads and the load sharing apparatus. However, the best option to test the generator set
packages is using a load bank, usually available from the shipyard.
MarineCommissioningProcedure
Page15of28
LEBM002500
to use the Data Log function in Cat ET during the entire test.
The engine should be operated until it and related systems are at normal operating
temperatures. Prior to beginning the sea trial, the engine room hatch must be closed, After the
engine is at operating temperature and the correct operation of all supply systems is verified,
start to load the generator in steps 0, 25, 50, 100% load. Operate each load step for a minimum
of 10 minutes with C7-C32 engines and minimum of 15 minutes with 3500 and above models. A
110% load step for the duration of one hour might be required by some classification societies,
but this 110% test is normally completed on the test bench at the dealership.
Ensure the following parameters are recorded at minimum:
-
Please refer to ***EDIT*** for Auxiliary and Genset Sea Trial checklists.
NOTE: After completion of a Complete PAR on all 3500, C175, and 3600 engines that are
mounted on rails, again record crankshaft deflection at the crankshaft center throw while the
engine is hot. Refer to Special Instruction SEHS7654. For additional 3600 instruction, refer to the
3600 A&I Guide LEKM7301.
Compare the Cat ET and manually recorded data with the data available in TMI.
Compare, if applicable, the 900 series designated systems pressures and temperatures,
MarineCommissioningProcedure
Page16of28
LEBM002500
with recorded values with the values given in the TMI On-Line System Sea Trial screen.
Compare crankshaft deflection values with specifications found in OMM.
Indicate any deviations in your Commissioning Report
General Information
Sea Trial Steady State
Sea Trial Transient (usually pleasurecraft only)
MarineCommissioningProcedure
Page17of28
LEBM002500
of this manual:
-
Boost Pressure
Fuel Burn
Load Factor
Desired Engine Speed
Actual Engine Speed
Engines rated up to 1400 rpm Low idle, then 600 rpm and every 100 rpm up to full
throttle.
Engines rated between 1401 to 1800 rpm Low idle, then 1000 rpm and every 100 rpm up
to full throttle.
Engines rated 1801 and above Low idle, then 1000 rpm and every 200 rpm up to 300 rpm
below rated. Then every 100 rpm to full throttle.
Once the sea trial has begun, move the throttle lever to a position to achieve the desired engine
speed and allow the engine speed to stabilize. This is necessary to obtain accurate steady state
values.
NOTE: For the best results, acquire the entire data run traveling in one direction. Currents and
wind have a definite factor in boat performance and engine loading.
NOTE: After completion of a Complete PAR on all 3500, C175, and 3600 engines again record
crankshaft deflection at the crankshaft center throw while the engine is at operating temperature.
Refer to Special Instruction SEHS7654. For additional 3600 instruction, refer to the 3600 A&I
Guide LEKM7301.
MarineCommissioningProcedure
Page18of28
LEBM002500
marine propulsion engine to the original factory performance specifications for that specific
engine. This comparison is made for the entire operating range of the engine. If the fuel rate and
boost pressure data from the marine PAR test are within the acceptable range for load and
performance specifications, it is an indication that the engine is operating correctly and the
propulsion system was sized satisfactorily.
However, if the actual fuel rate and boost pressure curves fall outside the acceptable range for
load and performance specifications, adjustments and/or repairs for the fuel system and/or
engine loading conditions may be necessary. In addition, further investigation may be needed for
the hull, rudder, propeller, etc.
The Fuel Rate graph is generated from the CAMPAR program consisting of three parameters.
-
The Red Zone is derived from engine specific data which is downloaded by the CAMPAR
program from TMI
The Actual Engine Data generated by the sea trial
The Propeller Demand (Prop Demand) curve from TMI
There are five possible results from the Fuel Rate graph as seen below. In each of these
instances, the boost pressure graph should also be taken into consideration prior to concluding
the sea trial analysis.
MarineCommissioningProcedure
Page19of28
LEBM002500
MarineCommissioningProcedure
Page20of28
LEBM002500
MarineCommissioningProcedure
Page21of28
LEBM002500
MarineCommissioningProcedure
Page22of28
LEBM002500
MarineCommissioningProcedure
Page23of28
LEBM002500
MarineCommissioningProcedure
Page24of28
LEBM002500
Three different scenarios are possible results as seen below. In each of these instances, the
fuel rate graph should also be taken into consideration prior to concluding the sea trial analysis.
8.2.1 Acceptable Boost Pressure
Maximum Boost Pressure Value Intersects the Green Zone. This is an indication that the
engine(s) are able to produce acceptable boost pressure, which is one indication that the
engine(s) are able to produce acceptable power. If the engine(s) are not able to achieve rated
speed, but the highest engine speed and boost pressure achievable still intersects the Green
Zone, the engines are operating properly. Engine performance conclusions should not be made
on only one parameter. The fuel rate graph should also be taken into consideration prior to
concluding the sea trial analysis.
MarineCommissioningProcedure
Page25of28
LEBM002500
MarineCommissioningProcedure
Page26of28
LEBM002500
MarineCommissioningProcedure
Page27of28
LEBM002500
In process
10
Hyperlinks
11
Supporting Documents
MarineCommissioningProcedure
Page28of28
LEBM002500
LEBM0025