Heavy Equipment Truck mixer, Plate compactor and crane facility or mobile pump for
pouring concrete
Activities Equipment Wheel borrow, Surveying Instrument, Metal Tape
Section B: Prerequisite
1. Testing works for the piles shall be completed prior to blinding works.
2. Work will commence after prerequisite activities such as drainage works etc. If
applicable.
Surveyor would conduct site survey to establish the lines and levels of the areas
of the blinding to be casted. The mark shall be as per the approved drawing.
2. Application
The shuttering form on the blinding must be fixed, aligned and leveled properly
before start pouring concrete.
A check list will be submitted to the Engineer to check the setting out, soil
compaction, dimensions, alignment, thicken and the level for the shutter of the
blinding.
The Anti-termite shall be sprayed on the compacted blinding area by using the
approved materials.
Page | 1
Section D: Safety
All works will comply with the safety procedure or instruction as set out in project
safety plan and municipality rules and regulations.
Basic PPE will be worn by all staff or laborers.
Trained operator or drivers would be engaged to control or operate heavy
equipment machine