Sunteți pe pagina 1din 8

Volume 14, Number 1, 2012

WIETE 2012

Global Journal of Engineering Education

A feasibility study approach for underground railways - a case study:


Line 4 of Athens metro
Kassiani Tsimplokoukou, Eleni Sfakianaki & George Metaxas
Technological Education Institute of Piraeus, Piraeus-Athens, Greece
Hellenic Open University, Patras, Greece

ABSTRACT: This article introduces a methodology for conducting feasibility studies for underground railways. The
study addresses the factors that determine station location, the attributes that enhance rail use through passenger
satisfaction. It incorporates the principles of CBA and financial analysis, presents the social impacts and their
requirements for the achievement of the social objectives, and discusses the benefits (social, economic, environmental)
that are accrued from the existence of underground railways that render them crucial elements for developing
sustainable cities. The case study based on Line 4 of the Athens metro has been used to provide an overall description
of the implementation of this methodology by using qualitative and quantitative data. The study reveals that the
feasibility of a project is improved by assessing its aspects on a global scale, while the perception of its utility by the
target-market is integral in its success.

Keywords: Feasibility study, underground railways

INTRODUCTION
The main interpretation that usually follows the term feasibility is one of the following: the case in which an alternative
option, a strategy plan, a design or a different location is proved economically preferable; the case in which an
alternative option is deemed appropriate in social or environmental terms and the case in which probable construction
and operation of a project can be financially viable as well as manageable [1]. A feasibility study is a multidimensional
set of actions which aims to analyse and evaluate a project in order to determine if its construction is feasible [2]. Such
a study refers to the assessment of results which concern the economic forecast in relation to other important factors,
such as socioeconomic efficiency and environmental impact [3]. The defining point of a feasibility study is the
necessary information that leads decision-makers to decide if the proposed option or project should be implemented
[1][2]. Its necessity in project development is considered significant, as the identification of errors in this stage
contributes to better performance of the project [3]. Thus, the success of a project is determined by the assumptions that
are set during the feasibility study process [4]. In some cases, a project is not profitable in economic terms; however, its
feasibility is attributed to serve another purpose [1].
The present research contributes to the engineering sector and, thus, engineering education by providing a new
methodology of feasibility study for underground railway projects, which balances social, environmental and economic
aspects. The elements that comprise such a study are identified and analysed separately, while the factors that further
improve the quality of a rail project, as well as probable parameters which increase the rail use are examined. The
second key part of this article refers to the application of this methodology based on a case study of Line 4 of the
Athens underground railway.
PROPOSED METHODOLOGY FOR A FEASIBILITY STUDY FOR UNDERGROUND RAILWAYS
The nature, location and the type of each project are factors leading to the diversification of feasibility studies [5].
Through a recent survey conducted by Shen et al in four different project categories (residential, commercial, public,
industrial), the elements that are taken into consideration have been defined [3]. These elements, which are illustrated in
Table 1, are categorised in three sections: social, environmental and economic. In this context, a thorough review of
guidelines about feasibility studies of appraisal methods for rail projects and of feasibility studies for particular
projects, has been carried out in order to lead to the development of a general structure of feasibility study for
underground railways. More specifically, the sources used include the following: feasibility study guidelines [6][7];
appraisal guidelines for railway projects and feasibility studies on specific rail projects [8][9]. In the latter case, seven

91

feasibility studies, which have been carried out for specific rail projects world-wide (in Australia, America, Canada,
Europe) were reviewed. This led to a better comprehension of the current implementation of feasibility studies applying
to real projects [10-16].
Table 1: Elements used for a feasibility study (Source: Shen et al [3]).

Economic
Elements

Social Elements
Environmental
Elements

Governmental strategic development policy, market forecast, market competition


Project function and size, demand and supply analysis, location advantage, technology advantage
Return on investment, tax policy, life cycle cost, life cycle profit, financing channels, budget
estimate
Investment plan, finance risk assessment
Influence to the local social development, development of new settlement and local communities
Provision capacity of employment and of public services, cultural and heritage conservation
Improvement to public health, provision of the infrastructures for other economic activities
Provision capacity of public infrastructure facilities, safety standards, land consumption
Eco-environmental sensitivity of the project location, waste assessment, noise assessment
Environmentally friendly design, energy consumption performance, air impacts, water impacts

Consequently, by synthesising the information from these diverse sources and by incorporating components that
emerged from research on the elements of which a feasibility study consists, a new methodology of feasibility study for
underground railways was developed, as illustrated in Figure 1.

Figure 1: Methodology for conducting feasibility studies for underground railways.


Location Assessment
The design of a railway line includes the examination of factors such as topological configuration, quantity of stations
and lines, frequency of lines and pricing [17]. The density of lines, the demanding period of parking time around the
station, as well as pedestrians' accessibility to the station, are differential variables regarding whether a probable
traveller will be attracted to use the metro or not ([17-19]). Locations that enable access to health, education,
entertainment services and provide connection to other railway stations should be probably planned to operate as
stations before the design of the line, while the location of other stations should preferably be chosen with criteria to
attract or serve a larger number of passengers [18].
Improving Project Quality
The basic criterion through which a transportation project is evaluated as qualitative is to meet user needs [20]. The
term quality is defined by the transfer that travellers experience while it is synthesised by elements, which are related to
the design and the operation of the railway line [21]. Access and egress time, service intervals, in-vehicle time, transfers
between modes, reliability information provision, system efficiency are some of these elements, while accessibility is
considered to be a key factor in determination of the use of rail as an alternative solution [22][23]. Reliability has been
found in various surveys to be a prominent element, which identifies transportation quality and influences passengers
choice [24]. Following a survey carried out by Brons, the factors that contribute to passengers satisfaction in order to
choose rail are travel comfort, reliability, station organisation and information, service schedule, dynamic information,
price/quality ratio, accessibility and ticket service [25].
Demand Analysis
Demand forecasting is an important step in a feasibility study as it assesses the necessity of the project [26]. The broad
coverage of areas, advanced connectivity and the placement of stations are factors that increase the demand for the use

92

of public transportation [27]. The outcomes of the demand forecasts are necessary as they contribute to the
determination of elements such as the roadway capacity and the length of station platforms [28][29]. This stresses the
importance of the precision in forecasting demand [28]. However according to recent statistical surveys conducted by
Flyvbjerg [28], and Flyvbjerg et al [30] related to the accuracy in demand forecasts in transportation projects, an
average of overestimation of 106% in rail projects was observed. In the same vein, Van Vee [31], and Flyvbjerg et al
[32] mention that the overestimation of demand is a common phenomenon while Holz et al support the view that the
quality of forecasts needs to be improved [33].
Costs of Underground Railways
The construction cost of a railway line varies even within the same city, as it depends on the technical characteristics
(subsoil, housing situations) of each project, which are linked to local conditions [32]. Further factors that determine
the cost of a railway are the length, planning and design parameters, the construction works and station equipment [34].
Large projects are characterised by wider variation in a scale from 40% to 200% [35][36], while the systematic
underestimation and final overrun of costs which has been noted depends, strictly and incrementally on delays and
extensive duration of the implementation phase [32][37]. Furthermore, regarding data presented by Flyvbjerg et al,
underground railways are four to six times more costly than at-grade ones [37].
With reference to the operational costs, these are increased by the existence of characteristics, such as ventilation,
lighting, air conditioning or platform screen doors, but simultaneously these factors increase the satisfaction of
customers by providing them comfort, reliability and quality of services [38]. Maintenance costs are usually estimated
by using historical expenditure figures [39].
Cost-Benefit Analysis
The economic appraisal of transportation projects is interlinked with cost - benefit analysis (CBA), as it is a main index
regarding the value of investment [33]. Through a comparison between costs and benefits by using the benefit cost ratio
(BCR), the economic net present value (ENPV) and the economic rate of return (ERR), the social value of the project
can be produced. The value of travel time savings is considered to be a key characteristic for transport studies as it
occupies 50-70% of the total benefit [29][40]. Vehicle operating costs (VOCS) are accrued by multiplying the default
operating cost per vehicle kilometre by the number of vehicle kilometres saved by the project [41]. The methods, which
are intended to evaluate the non-user benefits related to the prevention of accidents are referred to as the average danger
levels according to transport mode, while the environmental externalities generally depend upon the travel distances
and exposure to polluting emissions [6].
Financial Analysis
The financial analysis consists of the financial net present value, financial return on investment cost (FNPV(C) and
FRR (C)), sources of financing, financial sustainability, the financial net present value and financial return on the
national capital (FNPV(K) and FRR(K)) [6]. The FNPV is defined as the sum that results when the expected
investment and operating costs of the project are deducted from the discounted value of the expected revenues as per
Equation (1):

S0
Sn
FNPV = atSt =
+ ... +
t =0
(1 + i )n
(1 + i )0
where at =

(1)

1
t and t = time horizon.
(1 + i )

The FRR is defined as the discount rate that produces a zero FNPV as per Equation (2):

FNPV =

St

t = 0

(1 + FRR )

(2)

Financial sustainability is one of the most important features in a feasibility study [1]. The term financial sustainability
includes the possibility of a project not running the risk of a cash shortfall in any phase of its implementation for the
considered period of time [6].
Social and Environmental Assessment
One of the most important aims for the improvement of public sector projects according to Shen et al is to fulfil the
social objectives, which should be addressed in all public projects [3]. The potential social impacts, which are expected
from the existence and the operation of a railway project could be divided into three categories, namely socioeconomic
efficiency (passenger time savings, reduction of traffic congestion, cost saving to society), development plan of the city

93

(increase of productivity, efficiently function of urban areas, urban development) and social improvements (access for
all people, land acquisition) [38]. The large-scale tendency is that underground railways contribute to minimising the
negative effects of environmental pollution [41]. Noise pollution is minimised in underground transport infrastructure
compared with elevated and surface ones, while the saving of energy is of high importance. In addition, the
construction of an underground railway is associated with environmental preservation and elimination of crossings with
non-physical obstacles [38].
CASE STUDY - LINE 4 OF THE ATHENS UNDERGROUND RAILWAY
The second key part of this article refers to the implementation of the developed methodology in a case study, which is
Line 4 of the Athens Metro. The new Line 4 is U-shaped, is 33 km long and includes the construction of 29 new
stations [42].
Data and Procedure
The case study analysis of Line 4 of the Athens underground railway relied on qualitative and quantitative information
gathered through contact with Attiko Metro SA, by extracting data from AMEL SA, the Municipalities of Athens that
Line 4 will cross, relevant research papers, the European Commission and from field research. This information was
necessary to document elements for the location of Line 4, passengers satisfaction, expected ridership, estimated
project costs and revenues, benefits and financial attributes. Specifically, elements of the wider area (health-educational
services, important places, connection with other lines) of the probable station location were derived from field
research. The demographic data were gathered from the Municipalities of Athens that Line 4 will cross. Corresponding
data for passengers satisfaction were derived from a survey that Attiko Metro SA conducted in 2005. The data about
the expected demand and the estimated construction cost of Line 4 came from Attiko Metro SA.
The assumptions were built up by analysing estimated and actual data before and after the operation of the existing
metro lines. This information was derived by extracting elements from the Metro Development Study for Athens and
published data from Attiko Metro SAs annual economic report for 2007. Respective data about the operating and
maintenance costs emerged from published AMEL data. In addition, data about the reliability of metro services, the
capacity of rolling stock, necessary features for disable people that are incorporated in the design of the existing
underground service and the technical characteristics that enhance the safety of passengers derived from Attiko Metro
SA. Respective data about the recommended period of project appraisal, the discount rates, design life of an underground
railway project, probable funding from EU, and the conversion factors for monetary values were derived from the
European Commission.
Results and Analysis
Line 4 is expected to serve densely populated areas and the main avenues of Athens, as well as providing access to
health, education and to other important places. The priorities for services were set according to a relevant study
conducted by the Attiko Metro SA, in relation to the attributes that enhance passengers satisfaction. These are:
reliability, reasonably fast, personal safety, ticket service, travel comfort. The expected demand for Line 4 is about
500,000 passengers daily [42]. Regarding the demand estimation for Lines 2 and 3 (450.000 passengers), the first two
years the overestimation was around 83.67% and 63.64%, respectively. According to published data from AMEL SA
[43], the annual boarding for the year 2010 was approximately 170 million passengers. On the basis of the latter
elements, it was appropriate to assume that it would take three years to reach the predicted levels, with 50% of the full
expected demand to have being reached in the first year and 75% in the second year.
The estimated construction cost for Lines 2 and 3 was approximately 830 million in 1991, while in 1994 the
construction cost was redefined at about 952 million. However, according to the official data from the annual internal
economic report of Attiko Metro SA in 2007, a cost of 2.758 billion was presented, shaping the cost per route
kilometre at around 156 million. The latter indicates a cost overrun of 289.8%. The estimated construction cost of
Line 4 is 3.3 billion, which means that the construction cost, per kilometre, is 100 million [42]. For the purposes of
evaluation, it has been assumed in one case that the cost would equal to 3.3 billion and in a second case, in which a
cost overrun of 40% was added, the cost reached 4.620 billion. With respect to the annual operational expenses, by
proportionally calculating them for Line 4, these would be approximately 118 million (personnel expenses:
72,712,000, maintenance and repair costs: 4,810,000, other expenses: 39,712,000). The revenues were calculated
assuming a growth rate of 2.2% for a fifteen year period and an average price of 70% of the full price (1.40) including
multi-use tickets.
Through the cost-benefit analysis (Table 5), where the distribution of costs was assumed to be linear (five-year period
of construction), it was revealed that the main contributors to the present value of benefits are the travel time savings, as
they contribute to the 43% of the total benefits in the first year of the operation of Line 4, while in the last year of the
appraisal period, they contribute to the 48% of the total benefits. The benefits were categorised into user benefits (travel
time savings), non-user benefits (accident benefits, environmental externalities), fare revenue from new users and
residual value of rail assets.

94

Table 5: Cost-benefit analysis of Line 4 ( billion).


Present value of benefits
Present value of operating costs
Present value of capital costs

5.216
1.011
2.452
5,50
%
1.752
9.50
%
1.71

Discount rate
ENPV
ERR
B/C ratio

The positive ENPV indicates that the option will be economically feasible and it will, therefore, provide good value for
money. The B/C ratio identifies the relationship between benefits and costs, showing that the costs equal 1.71 of the
total benefits. In the case in which the benefits have been compared with an additional cost overrun, the project is
economically feasible, giving a positive ENPV (933 million). For the programming period 2007-2013, the European
Commission recommends that a 5% real rate should be considered [6]. The reference time horizon recommended for
the same period, regarding railways, is 30 years, while underground railways have a design life of 100 years. Through
the financial analysis (Table 6), it has been demonstrated that the project is not financially feasible, as the indicator
FRR (1.5%) is lower than the applied discount rate (5%), while FNPV is negative (-1,433 billion). For the project as a
whole, the revenue from passengers cover about 49% of the total costs, giving a financial BCR of about 0.49.
Table 6: Financial analysis of Line 4 (billion ).
Present value of revenues
Present value of residual value
Present value of operating costs
Present value of capital costs
Discount rate
FNPV (C)
FRR(C)
Financial BCR

2,183
534
1,303
2,857
5.00
%
1,443
1.50
%
0.49

Including the EU grant


Present value of capital costs
Discount rate
FNPV (K)
FRR(K)
Financial BCR

2,347
5.00
%
-932
2.40
%
0.6

The funding gap would amount to approximately 1.4 billion, while the funding from the European Union was
estimated to be 589 million. The period of amortisation of Line 4 is expected to be 35 years, as the revenue from the
project breaks even with its cost after 35 years of its operation.
The social performance of a construction project is assessed through the evaluation of social performance elements.
These elements, which are transformed into criteria accrued through the determination of the social objectives that are
expected from the existence of a railway project and are: reliability, capacity enhancement, community links and
networks, accessibility, reduced mobility - mobility for special users, affordability, geographic and personal safety. The
outcomes showed that an investment in an underground railway line is very valuable, since it provides the opportunity
for people with no means of private transportation to travel, it contributes to the upgrading of the areas around the
metro stations, as well as propelling the improvement of the quality of peoples life.
In relation to the environmental improvements, a study conducted before and after the operation of the metro revealed a
decrease in the levels of air pollution from 8% to 4% due to the reduction of private vehicles (reduced by 70,000) [42].
It is estimated that the new metro Line 4 will contribute to the decrease of the use of private vehicles by people who
bring up to 81,000 cars into Athens. This will lead to the reduction in air pollution, in greenhouse gas emissions and in
noise pollution. However, the amount of benefit depends on the regional vehicle emissions.
CONCLUSIONS
This article introduced a new methodology for conducting feasibility studies for underground railways, through which
diverse factors that could positively influence the education of engineers and the engineering culture overall were
examined. It has been framed from economic, environmental and social attributes, while the factors which stimulate the
rail use, through the passengers satisfaction, were incorporated into this methodology.
Analysis of the factors that determine station location revealed that locations that enable access to health, education
services and important places, as well as points within densely populated areas should be considered as possible locations

95

for metro stations. In relation to the quality of the project services, ten elements that contribute to passengers satisfaction
were determined, while reliability is considered to be one of the most prominent. The study further shows cost overruns
that occur in projects with a long implementation phase vary between 40% - 200%, while the average overestimation in
demand forecasts in rail projects is about 106%. As far as the environmental benefits are concerned, the large-scale
tendency is that underground railways contribute to minimising the negative effects of environmental pollution.
With respect to the second part of this study, the new methodology was applied to the case study of Line 4 of the
Athens underground railway. By comparing the economic performance of the project in relation to the benefits on a
social, environmental and economic perspective, as well as through the analysis of social criteria (affordability,
accessibility, safety) the feasibility of the Line 4 was evaluated. The study reveals that the feasibility of a project is
improved by assessing the project aspects on a global level.
It is recommended that the attributes that synthesise the quality of an underground railway project, as well as the
identification of factors that increase railway usage should be an integral part of a feasibility study, since the success of
a project is determined by the degree of its utility to those for whom it is constructed. The new methodology is based on
three main directions and their components, which support sustainability. It is of great importance to promote and
incorporate into the process of any feasibility study, elements that come along with the principles of sustainable
development. In this respect, professional practice will be able to meet future demands, and the quality of life can be
improved.

REFERENCES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.

Urkiagaa A., De las Fuentesa L., Bisb B., Chiruc E., Bodod B., Hernndeze F. and Wintgensf, T., Methodologies
for feasibility studies related to wastewater reclamation and reuse projects. Desalination, 187, 263269 (2006).
del Cano, A, Continuous project feasibility study and continuous project risk assessment. Inter. J. of Project
Manag.,10, 3, 165-170 (1992).
Shen, L., Tam, V., Tam, L. and Ji, Y., Project feasibility study: the key to successful implementation of
sustainable and socially responsible construction management practice. J. of Cleaner Production, 18, 254259
(2009).
Mackenzie, W. and Cusworth, N., The Use and Abuse of Feasibility Studies. Melbourne, VIC, 19-20 (2007).
Jaafari, A., Management know-how for project feasibility studies. Inter. J. of Project Manag., 8, 3, 167-172
(1990).
European Commission. Guide to Cost-benefit Analysis of Investment Projects (2008).
IPDF (Infrastructure Project Development Facility) Ministry of Finance Government of Pakistan. Project
Preparation/Feasibility Guidelines for PPP Projects (2008).
European Commission. Railway Project Appraisal Guidelines (RAILPAG).
Department for Transport. Transport, Wider Economic Benefits and Impacts on GDP, London (2005),
http://www.dft.gov.uk/.
Hamilton - Auckland Feasibility Study. Final Report. Richard Paling and Ross Rutherford (2006).
High Speed Rail Feasibility Study. Transportation Economics & Management Systems, Inc. in Association with
Quandel Consultants, LLC (2008).
Mildura Rail Feasibility Study. Final report. AECOM Australia Pty Ltd (2010).
Richmond Rail Transit Feasibility Study. Final report. Parsons Brinckerhoff Quade & Douglas, Inc. (2003).
Britomart West Rail Extension Feasibility Study. Final Report. URS New Zealand (2004).
Fairmount Line Feasibility Study. Final Report. KKO and Associates L.L.C (2002).
Feasibility Study on Rail Baltica Railways. Final Report. COWI A/S (2007).
Marna, A. and Garca-Rdenasb, R., Location of infrastructure in urban railway networks. Computers &
Operations Research, 36, 1461-1477 (2009).
Laporte, G., Mesa, J.A., Francisco, A. and Ortega, F.A., Locating stations on rapid transit lines. Computers &
Operations Research, 29, 741-759 (2002)
Daganzo, C.F., Structure of competitive transit networks. Transportation Research, Part B, 44, 434446 (2010)
ITA Working Group. Costs-Benefits of Underground Urban Transportation. Cost-Benefit Methods for
Underground Urban Public Transportation System. Tunnelling and Underground Space Technology, 5,1/2, 39-68
(1990).
Carse, A., Assessment of transport quality of life as an alternative transport appraisal technique. J. of Transport
Geography (2011).
Paulley, N., Balcombe, R., Mackett, R., Titheridge, H., Preston, J., Wardman, M., Shires, J. and White, P., The
demand for public transport: the effects of fares, quality of service, income and car ownership. Transport Policy,
13, 295-306 (2006).
Murray, A.T., Strategic analysis of public transport coverage. Socio-Economic Planning Sciences, 35-188 (2001).
Van Loon, R., Rietveld, P. and Martijn Brons, M., Travel-time reliability impacts on railway passenger demand: a
revealed preference analysis. J. of Transport Geography (2011).
Brons, M., Givoni, M. and Rietveld, P., Access to railway stations and its potential in increasing rail use.
Transportation Research, Part A, 43,136-149 (2009).

96

26. Economic Commission for Europe. A Set of Guidelines for Socio-Economic Cost Benefit Analysis Of Transport
Infrastructure Project Appraisal (2003).
27. Winston, C. and Maheshri, V., On the social desirability of urban rail transit systems. J. of Urban Economics (2006).
28. Flyvbjerg, B., Measuring inaccuracy in travel demand forecasting: methodological considerations regarding ramp
up and sampling. Transportation Research, Part A, 39, 522530 (2005).
29. Parthasarathi, P. and Levinson, D., Post-construction evaluation of traffic forecast accuracy. Transport Policy, 17,
428-443 (2010).
30. Flyvbjerg, B., Holm, M. and Buhl, S., Inaccuracy in traffic forecasts. Transport Reviews, 26, 1-24 (2006).
31. Van Wee, B., Large infrastructure projects. A review of the quality of demand forecasts and cost estimations.
European J., Environment and Planning B, 34, 4, 611-625 (2007).
32. Flyvbjerg, B., Bruzelius, N. and Rothengatter, W., Megaprojects and Risk: an Anatomy of Ambition. Cambridge
University Press, Cambridge (2003).
33. Holz-Rau C. and Scheiner, J., Safety and travel time in cost-benefit analysis: a sensitivity analysis for North
Rhine-Westphalia. Transport Policy, 18, 336-346 (2011).
34. Kim G., Kim K., Lee D., Han, C., Kim, H. and Jun, J.T., Development of a life cycle cost estimate system for
structures of light rail transit infrastructure. Automation in Construction, 19, 308-325(2010).
35. Abril, M., Barber, F., Ingolotti, L., Salido, M.A., Tormos, P. and Lova, A., An assessment of railway capacity.
Transportation Research, Part E, 44, 774-806 (2008).
36. Magnussen, O.M. and Olsson, N., Comparative analysis of cost estimates of major public investment projects.
Inter. J. of Project Manag., 24, 281-288 (2006)
37. Fyvbjerg, B., Bruzelius, N. and Van Wee, B., Comparison of Capital Costs per Route-Kilometre in Urban Rail.
(2008).
38. ITA Working Group Number 13. Underground or aboveground? Making the choice for urban mass transit
systems. A report by the International Tunnelling Association (ITA). Prepared by Working Group Number 13
(WG13). Direct and indirect advantages of underground structures. Tunneling and Underground Space
Technology, 19, 3-28 (2004).
39. Victoria Transport Policy. Guidelines for Cost Benefit Analysis (2010).
40. Shires, J.D. and De Jong, G.C., An international meta-analysis of values of travel time savings. Evaluation and
Program Planning, 32, 315-325 (2009).
41. Girnau, G.G., Blennemann F., Cost-Benefits in Underground Urban Public Transportation. Tunneling and
Underground Space Technology, 4, 1, 23-30 (1989).
42. Attiko Metro SA, www.ametro.gr.
43. Attiko Metro Operation Company SA, www.amel.gr.

BIOGRAPHIES
Kassiani Tsimplokoukou graduated with a Bachelor of Engineering degree from the
Technological Education Institute of Piraeus as a civil engineer. During her studies she was
employed in two laboratories in the Civil Engineering Department of the Technological
Education Institute of Piraeus. She worked on standard test methods for quality control of
construction materials, laboratory testing of concrete mix design and statistical analysis of
results in the Quality Control and Materials Technology Laboratory. She has also been
teaching as an assistant in the Computer-Aided Design Laboratory. Upon the completion of
her studies she enrolled in the Master's course, Management in Construction at Kingston
University (UK), School of Engineering, in cooperation with the Technological Education
Institute of Piraeus, Department of Civil Engineering, which she has recently completed. In
parallel she has worked in the fields of construction and management of commercial projects in Athens. Additionally,
she has gained experience in the supervision of public infrastructure projects, particularly in road construction and
installation of gas pipelines. Her experience has influenced her research interests. Specifically, her interests concern the
optimal management and development of infrastructure projects over their life cycle along with the principles of
sustainability. Future projects will include but are not limited to the principles of quality and environmental management.
Eleni Sfakianaki graduated from the University of Patras, Greece, as a civil engineer (five
year course). She then completed a Masters course in Construction Management at the
University of Sheffield, Civil Engineering Department, UK. She was awarded a full
scholarship from the University of Sheffield to complete a PhD in Environmental
Management with the use of GIS, which she successfully defended in 2000. Once she
completed her PhD, she was appointed a Lecturer at Kingston University's School of
Engineering, UK. She worked as a lecturer for three years full-time. She then started
working as a consultant in sectors such as construction management, environmental
assessment and tourism. She has gathered considerable experience in project management
and co-ordination. She has worked in some of the largest investment projects in Greece.
After she left Kingston University, she continued her academic career in Greece on a parttime basis. She taught at both undergraduate and postgraduate levels and continued research at the same time. Since last
year she has been an assistant professor at the Hellenic Open University, School of Social Sciences, Business

97

Administration Department. She has attended a large number of conferences and has published in referred journals. Her
main interests include engineering, education, total quality management, environment and economics. She also has an
interest in sustainability and the quality of life.
George Metaxas graduated from the National Technological University of Athens (NTUA),
Greece as a civil engineer. He then work as assistant lecturer in NTUA in postgraduate level
giving lectures on reinforced concrete, advanced fluid engineering, applied hydraulics and
methods of applied mathematics in hydraulics. Afterwards, he worked as a lecturer in the
Agricultural University of Athens (AUA) in the Hydraulics Department. He was later
appointed Professor at the Technological Education Institute of Piraeus (TEI) in Civil
Engineering Department. He was elected four times to be Head of the Department of Civil
Engineering and twice as Dean of the Faculty of Engineering. He established the
postgraduate courses in TEIs in collaboration with foreign institutes, and since 2000, he has
been the Field Leader of the postgraduate course of the Civil Engineering Department in
collaboration with Kingston University (UK). During 2004 he completed his PhD from
AUA. During his academic career he has been awarded with UNESCO International Centre for Engineering Education
(UICEE) Silver Badge of Honour for distinguished contributions to engineering education, outstanding achievements in
the globalisation of engineering education through the activities of the Centre, and, in particular, for remarkable service
to the UICEE. He has also been awarded an honorary Doctor of Engineering by Kingston University, UK. He is a
member in various scientific organisations such as the World Institute of Engineering and Technological Education. As
a civil engineer he has worked as consultant engineer with large consulting firms in Greece and has designed and
supervised large projects in Athens, Greece.

98

S-ar putea să vă placă și