Documente Academic
Documente Profesional
Documente Cultură
Document No.:
SOP-XXXX
Title:
1.
2.
Page 1 of 12
1.1
1.2
To outline the procedure by which the Validation Services Department periodically evaluates
the performance of previously validated facilities, equipment, systems, and processes. This
evaluation includes a periodic review of performed critical changes/repairs. Reviews will be
performed to determine the impact to the validated state of the facilities, equipment, systems,
and processes. The objective of the program is to verify that systems continue to operate
within the criteria established in the original validation and according to current Company
guidelines.
SCOPE
This procedure applies to previously validated facilities, equipment, systems, and processes
that are used to manufacture or to support the manufacture of pharmaceutical products
intended for clinical or commercial distribution at XXXXX facilities.
2.1.1
2.2
The Critical Change Review (CCR) will include applicable Change Control,
Preventive Maintenance Interval Evaluation, Maintenance Work Orders, and
Quarterly EM Trend Report Review (where applicable).
REFERENCES
3.1
4.
XX
OBJECTIVE
2.1
3.
Revision:
SDSOP-XXXX
RESPONSIBILITY
4.1
The Validation group is responsible for verifying that facilities, equipment, systems, and
processes used in the manufacture of product for clinical or commercial distribution remains
in a validated state.
4.2
The Validation group maintains a system that is capable of providing notification when critical
validated facilities, equipment, systems, and processes requires requalification.
4.3
The Validation group is responsible for generation of a protocol and final report per SOPXXXX to obtain approval and documented evidence of the requalification activities. SOPXXXX provides guidance on the responsibility of the Validation Department and approval of
the protocol and final report.
4.4
Validation, Quality Assurance (QA), and identified impacted departments are responsible for
reviewing the summary reports and taking the appropriate actions as requested.
SOP-XXXX
Title:
5.
6.
Revision:
XX
Page 2 of 12
DEFINITIONS
5.1
5.2
Last Significant Data Point Either the date of last data generated or the date of the
reviewed lab test results.
5.3
HEPA filters inside controlled areas are recertified following established schedules
per SOP-XXXX.
5.3.2
5.4
5.5
User The functional area that principally utilizes, or is responsible (Owner) for, the
equipment or facility.
PROCEDURE
6.1
General
6.1.1
Once facilities and/or equipment have been validated, they are considered to be in
a state of control. If validated conditions and control parameters remain
unchanged, the system continues to operate in a validated state.
6.1.2
6.1.2.2
SOP-XXXX
Title:
6.2
Revision:
XX
Page 3 of 12
CCR
6.2.1
The Validation group performs CCR for major equipment, processes, and/or
systems and summarizes the results in a CCR report. In instances where several
changes were made in which each was identified separately to have "no impact" to
the validation, the collective changes will be reviewed to reassure that a validated
state has been maintained. These reviews may also initiate additional testing or
data gathering activities (e.g., another change control) up to and including, when
appropriate, a comprehensive revalidation.
6.2.1.1
6.2.2
Access the Critical Changes/Repairs database and select the method for identifying
the critical changes/repairs for the equipment, process and/or system that requires
a review to be performed.
6.2.3
Review the critical changes/repairs that were performed during the period of the
review that are not PM based (i.e., corrective work orders). Review the database
list for the specified equipment, process, and/or system selected and obtain a copy
of each Critical Change/Repair and associated Maintenance Work Order (MWO)
performed.
6.2.3.1
Include in the review how many MWOs were generated and what they
were for. Compare the number of MWOs and critical changes/repairs to
determine the collective impact (if any) to the equipment, process,
and/or system. Include this data in the summary report.
6.2.3.2
6.2.3.3
Determine if there are any trends to the type and number of MWOs and
critical changes/repairs that have occurred. If a trend is identified,
discuss the findings with the impacted departments and QA to
determine the appropriate action(s) to be taken. This data will be
included in the summary report.
6.2.3.3.1
6.2.4
6.2.5
Review and evaluate the critical changes/repairs performed and determine the
collective impact to the equipment, process and/or system (per SOP-XXXX).
6.2.6
Generate a summary report that will consist of, but not be limited to, a summary of
change control and/or MWO files reviewed, and evaluation of quarterly EM trend
reports (if applicable).
SOP-XXXX
Title:
6.3
XX
Page 4 of 12
6.2.7
The summary report to be generated may be a stand-alone document, with its own
distinct protocol number, or part of a revalidation package.
6.2.8
If the summary report identifies any adverse impact to the validated state of a
process, environment, equipment, or utility, contact the impacted department(s) and
QA to determine the appropriate action(s) to be taken.
6.2.9
6.2.9.2
Revalidation
6.3.1
6.3.2
The need for revalidation may also be triggered by any of the following:
6.3.3
6.4
Revision:
6.3.2.1
6.3.2.2
6.3.2.3
6.3.2.4
The format, issuance, tracking and approval of validation protocols are described in
SOP-XXXX.
Periodic Requalification
6.4.1
SOP-XXXX
Title:
6.5
Revision:
XX
Page 5 of 12
6.4.2
6.4.3
6.4.4
If any test, acceptance criteria, or protocol requirement is not met, the activities are
halted (as applicable) and deviation is generated in accordance with SOP-XXXX.
Requalification Schedule
6.5.1
6.5.2
The schedule for requalification is established based upon the critical nature of the
facility and equipment in question and regulatory requirements. Without the
documented approval of at least the system owner, Validation, and QA, the time
period between requalification of the systems described in this procedure does not
exceed the time specified in this procedure.
6.5.3
6.5.2.1
The requalification date is derived from the last significant data point in
the current Validation review.
6.5.2.2
6.5.2.3
6.5.2.4
SOP-XXXX
Title:
6.6
XX
Page 6 of 12
Requalification Execution
6.6.1
6.7
Revision:
6.6.2
The minimum protocol requirements for critical systems are defined in the protocol
and are approved per SOP-XXXX (which includes Quality Assurance).
6.6.3
Any revisions to the approved protocol are subject to review by original signatories.
6.6.4
6.6.5
6.6.6
Deviations and exceptions from the protocol procedure or acceptance criteria are
documented in the final report.
6.6.7
The completed requalification final report is submitted for review and final approval.
The approved final report is filed with the original validation package.
6.6.8
6.6.9
6.7.1.2
6.7.1.3
SOP-XXXX
Title:
Revision:
XX
Page 7 of 12
6.7.1.4
6.7.2
6.7.1.4.2
Each SIP process is evaluated annually (i.e., for tanks and lyophilizers).
The thermal mapping/BI challenge must be repeated such that the
locations are consistent with the most recent PQ.
6.7.2.1.1
6.7.3
6.7.2.2
6.7.2.3
The plan includes a single test run performed consistent with the original
validation. The run includes biological indicators (BI) that are placed
inside the system adjacent to the thermal sensors, e.g., thermocouples.
At the end of the BI challenge, the BI Test must be performed within
4 hours. The results of the requalification study are assessed with the
data from the previous requalification, original, or most current validation
for consistency.
SOP-XXXX
Title:
Revision:
XX
Page 8 of 12
6.7.4
6.7.3.2
6.7.3.3
HVAC systems are evaluated every three years, with a review period
that covers six years. The cumulative review period is integrated into
the CCR review period wherein a six-year time frame is evaluated.
6.7.4.2
6.7.4.3
6.7.4.4
SOP-XXXX
Title:
6.7.5
6.7.6
6.7.7
6.7.8
Revision:
XX
Page 9 of 12
Critical utility systems are evaluated every three years, with a review
period that covers six years. The cumulative review period is integrated
into the CCR review period wherein a six-year time frame is evaluated.
6.7.5.2
6.7.5.3
6.7.5.4
Packaging Line
6.7.6.1
Packaging lines are reviewed and evaluated annually for their impact on
the validated processes.
6.7.6.2
6.7.6.3
The equipment train includes all the major equipment on the packaging
line.
6.7.7.2
The collective impact from change control, work orders, and events
since the last validation or verification are reviewed in terms of their
collective impact on the process performance. Revalidation can be
performed as needed.
6.7.7.3
6.7.7.4
6.7.7.5
Media Fill
SOP-XXXX
Title:
Page 10 of 12
6.7.8.2
6.7.8.3
6.7.8.3.2
Fill Duration
6.7.8.3.3
Corrective Interventions
6.7.8.3.4
Batch Size
The trending data is captured from documents such as the MPRs and
filling event log.
Room Qualification
6.7.9.1
6.7.9.2
6.7.9.3
6.7.10
XX
6.7.8.1
6.7.8.4
6.7.9
Revision:
6.7.9.2.1
6.7.9.2.2
6.7.9.2.3
6.7.9.2.4
6.7.9.2.5
Cleaning Validation
6.7.10.1
6.7.10.2
SOP-XXXX
Title:
7.
XX
Page 11 of 12
ATTACHMENTS
7.1
8.
Revision:
Requalification Schedule
REVISION HISTORY
Rev.
XX
Summary of Changes
Update continue verification of process validation section to align with standard process
parameters document. Delete process that has no SPP document on Attachment 7.1.
SOP-XXXX
Title:
Revision:
XX
Page 12 of 12
Attachment 7.1
The systems listed in the table below is intended to be a representation of types of equipments or
systems incorporated into the requalification schedule at the site.
BUILDING
001
002
002
001
002
TYPE
Steam
Sterilization
Dry Heat
Depyrogenatio
n
HVAC &
Critical Utilities
CURRENT SYSTEMS
REQUALIFICATION
SCHEDULE
Autoclaves
Lyophilizer
Tank SIP
Depyrogenation
Tunnel
HVAC
RO
3 years
WFI
PS
Nitrogen
CDA
Annually
Annually
REFERENCE
DOCUMENTS