DETAIL SCHEME/ METHOD

FORMAT NO. : QF 9949 18

PLANNING DEPARTMENT

PROJECT :
DOC. TITLE

REV. : R1

Construction of Elevated Viaduct DMRC- Laxmi


Nagar, Delhi

DATE : 15-03-05

REV. : R0

DATE:
16/02/08

Method Statement for Casting of Station Building


Track Level/Platform Level Slab

DOCUMENT NO.

Page No. : 1 of 5

PLNG/3550/QF 18/17

METHOD STATEMENT FOR CASTING OF STATION BUILDING


TRACK LEVEL /PLATFORM LEVEL SLAB

Part Design & Construction of viaduct and structural work of 3 elevated stations
Laxmi Nagar, Scope Tower, Preet Vihar on Yamuna Bank Anand Vihar
Corridor of Phase II of Delhi MRTS Project.

CONTRACT - BC 10

Prepared By
Name

: Sanjay Kumar Singh

Reviewed By
Name

: Satyendra Kumar

Approved By
Name

: P K Mishra

Designation : Sr. Engineer - Planning

Designation : QA Manager

Designation : GM

Signature

Signature

Signature

Date

: 16.02.2008

Date

: 16.02.2008

Date

: 16.02.2008

DETAIL SCHEME/ METHOD


PLANNING DEPARTMENT

PROJECT :
DOC. TITLE

REV. : R1

FORMAT NO. : QF 9949 18

Construction of Elevated Viaduct DMRC- Laxmi


Nagar, Delhi

DATE : 15-03-05

REV. : R0

DATE:
16/02/08

Method Statement for Casting of Station Building


Track Level/Platform Level Slab

DOCUMENT NO.

1.

PLNG/3550/QF 18/17

Page No. : 2 of 5

INTRODUCTION:

The method statement describes the methodology for the construction of the slab at concourse
level for Construction of Station Building on Yamuna Bank Anand Vihar Corridor of Phase
II of Delhi MRTS Project.

2.

PURPOSE:

The purpose of this method statement is to describe the construction procedure to be followed
at site and is in the line of technical specifications of contract document.
3.

RESPONSIBILITY:

The various departments will involved in the casting of Track Level/Platform Level Slab and
they will be responsible for their work as indicated in the organisation chart.

4.

RERENCE DOCUMENT:

Technical Specification
Good for Construction Drawings for Track Level/Platform Level

5.

MAJOR EQUIPMENTS DEPLOYED

DETAIL SCHEME/ METHOD


PLANNING DEPARTMENT

PROJECT :
DOC. TITLE

REV. : R1

FORMAT NO. : QF 9949 18

Construction of Elevated Viaduct DMRC- Laxmi


Nagar, Delhi

DATE : 15-03-05

REV. : R0

DATE:
16/02/08

Method Statement for Casting of Station Building


Track Level/Platform Level Slab

DOCUMENT NO.

Page No. : 3 of 5

PLNG/3550/QF 18/17

Following are the major equipments deployed


Sr. No.

6.

Equipment

Planned Qty.

Batching Plant of 60 cum / Hr Capacity

1 No.

Transit Mixer of capacity 6 cum

6 No.

Concrete Pump

2 No.

Vibrator MK7

2 No.

Vibrator Needle of 60 mm dia

4 No.

Tower Crane of 1 Ton.

1 No.

BRIEF METHOD OF CONSTRUCTION

The Casting of Track level/Platform Level slab will be followed by erection of Staging for
track level/Platform Level slab. After erection of staging, shutter will be erected both in
longitudinal and lateral direction.
After erection of shutters, reinforcement tying will be carried out as per the Good for
Construction drawing and bar bending schedule.
The concreting will be done using two nos of concrete pump in five parts (Grid Wise).The
grade of concrete will be as per the Good for Construction drawings. The rate of pouring will
be maintained between 15 20cum/hr.
The concreting will be produce using 60 cum/Hr batching plant installed at casting yard and will be
transported in Transit mixer of 6 cum capacity to the pouring location. Pouring of concrete will be
done using the concrete pump. After pouring the concrete will be vibrated using 2 nos. MK7 vibrator
and 4 nos. 60 mm dia needle vibrator. Batching Plant of other project situated around 2 Km from the

DETAIL SCHEME/ METHOD


PLANNING DEPARTMENT

FORMAT NO. : QF 9949 18

Construction of Elevated Viaduct DMRC- Laxmi


Nagar, Delhi

PROJECT :
DOC. TITLE

REV. : R1
DATE : 15-03-05

REV. : R0

DATE:
16/02/08

Method Statement for Casting of Station Building


Track Level/Platform Level Slab

DOCUMENT NO.

PLNG/3550/QF 18/17

Page No. : 4 of 5

stretch will be used as a back up. One no. MK7 vibrator along with one no. 60 mm dia needle will be
kept as standby. One no concrete pump will be kept as a standby arrangement.
Curing will be done using the ponding method.
At every stage of concreting for the purpose of establishing checks on every stage of works separate
checklist as enclosed will be maintained for each activities involved in the casting of Track
Level/Platform Level Slab.
7.

8.

RISK INVOLVED
i)

Working at Height

ii)

Trespassing of other workers in the working zone

iii)

Working with heavy Equipments

iv)

Fall of materials from the height

SAFETY PRECAUTIONS
i) Safety net will be provided to prevent the fall of materials on the vehicle/human from the

height.
ii) Traffic signs (warning signs, diversion signs etc) to keep alert of traffic and make aware

that the work is in progress.


iii) The Equipments will be operated within the safe working radius and all the equipments

will be properly maintained and checked. No personnel will be allowed in the area of
working/swing radius of the crane and other equipment.
iv) All workers would be made aware regarding the methods of work and safety awareness

through toolbox talks.


v) Employing safe working practices
vi) Unauthorized / outside persons will not be allowed to enter inside/near the test assembly during

DETAIL SCHEME/ METHOD


PLANNING DEPARTMENT

PROJECT :
DOC. TITLE

REV. : R1

FORMAT NO. : QF 9949 18

Construction of Elevated Viaduct DMRC- Laxmi


Nagar, Delhi

DATE : 15-03-05

REV. : R0

DATE:
16/02/08

Method Statement for Casting of Station Building


Track Level/Platform Level Slab

DOCUMENT NO.

PLNG/3550/QF 18/17

Page No. : 5 of 5

the erection of girders and at the time of test.


vii) All the workers will be provided with necessary safety equipments.
viii) Availability of site First Aid facilities.
ix) Proper Lighting arrangement during the night or low visibility.
x) Dedicated and experienced safety officer and team will be deployed to ensure that test shall be
carried in safe condition.

9. SAFETY AND RISK ASSEMENT/MITIGATION MEASURES:


Safety and risk assessment/mitigation measures will be taken as per the SHE Policy Phase II
version 1.2
9.

CHECKLIST
1. Reinforcement Inspection Checklist
2. Checklist for Formwork
3. Concrete Inspection Checklist
4. Safety Checklist
5. Concrete Pour Card

10.

ENCLOSURE
1. Responsibility Chart for Construction of Track Level Slab
2. Risk Assessment
3. Quality Assurance Plan