Documente Academic
Documente Profesional
Documente Cultură
REPORT
(CIVIL/BUILDING) ENGINEERING
BLDG 657 PROJECT MANAGEMENT
Professor: Dr. SANG HYEOK HAN
Yaseen Mohammed - 27677723
Amit Anahita Narges Sanjiv -
PROJECT SCOPE:
MAIN BUILDING
ACCOMMODATION BUILDING
1. Schedule planned data was obtained from the company, with cost estimated budgeted for
every task. The bar chart is produced in MS project for the planned schedule based on the
data and the curve was also developed for budgeted cost of work scheduled (BCWS) is
plotted.
2. Since this project is ongoing, the actual costs with schedule data were missing. So, the
actual schedule and the actual costs worked in the project are purely on assumption. The
curves for Budgeted Cost of Work Performed (BCWP) and Actual Cost of Work
Performed (ACWP) are plotted based on the assumed schedule and budgeted costs and
the actual cost.
3. The forecast and project analysis was based on 40 hours per week.
4. All the costs on tables and graphs are in AED (United Arab Emirates Dirham) which has
and exchange rate today (Oct 1st 2016) of approximately 0.3 Canadian Dollars.
Analysis data:
Report date: October 2016
Project start date (Planned): 20 November 2015
Project start date (Actual): 20 December 2015
Project end date (Planned): 13 May 2017
Project end date (Actual): 24 June 2017
Schedule over run: 31 working days
Project budget: 26,000,000.00 AED
Earned Value of the project11,269,119.00 AED (43.34 %)
Planned value of the project 14,098,434 AED (54.22%)
Project status analysis at report date October, 2016 and Estimate at Completion:
The figure below shows the status of the project by demonstrating if the project was on to the
planned estimate and schedule. With the plot of the graph, we can estimate the Cost Variance
(CV), Schedule Variance (SV), and the Accounting Variance (AV).
Conclusion:
The data for the case study was obtained from the company (Dhafir Development & Contracting
L.L.C). For the given data, an actual schedule was developed in excel by considering the delays
and the curves were plotted for earned value and actual cost of work performed. October 2016
was the month in which the project status was observed and was found to be behind schedule
with cost over run. Due to delay in the initial drawings of the project, it was clearly behind
schedule. Corrective actions were made but it couldnt effect the project progress much, and the
delays caused in site construction and finishing works were due to adverse weather conditions
were considered as the reason for the bad performance.