Documente Academic
Documente Profesional
Documente Cultură
Rev 4
SAIC NUMBER
SAIC-A-2010
PROJECT TITLE
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
CONTRACTOR / SUBCONTRACTOR
EQPT CODE
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
PASS
FAIL
N/A
NOTE: Use Pre-test Punch List Form, SATR-A-2007, for listing of specific deficiencies, indicating location and/or references
A
Test Pack Verification & Review* (*Thorough & detailed review of specs for each new system's first package)
A1
SAES-A-004,
Para. 5.6.1
Schedule Q AttIV para 3.7
A2
SAES-A-004,
Para. 5.6.1
A3
SIS Sheet Data Verification (Safety Considerations & Limiting Factors in Pressure Test Calculations)
B1
SIS shall be prepared for all individual units of plant equipment which in
view of size, pressure rating and application are within the scope of
Saudi Aramco Engineering Standards and general industry codes
Page 1 of 12
SAEP-1160,
Section 6
Weld Database
SAES-A-005
Para 4.2
RE-INSP DATE
SAES-A-005
Para 5.1
B3
Page 2 of 12
SAES-A-004
para 4.2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
31-Mar-10
DATE APPROVED
QR NUMBER
SAIC-A-2010
PROJECT TITLE
ITEM
No.
Rev 4
SAIC NUMBER
31-Aug-11
WBS / BI / JO NUMBER
ACCEPTANCE CRITERIA
REFERENCE
PASS
SPEC CHECK SHALL BE UTILIZED BY SAUDI ARAMCO INSPECTORS FOR FIELD WALK-DOWNS
C1
All joints (flange, threaded, welded or mechanical seals) are left exposed
for visual leak detection during the strength test.
A) External coating & priming of joints is allowed only if approved by Insp
Dept Mgr & proponent Organization Representative.
B) The pipe itself can be externally primed & coated to a final coat.
SAES-L-150,
Para. 7.3
C2
All permanent flange joints were inspected, gasket mat'l verified &
properly torqued. (Review Flange joint report, SAIC-L-2014)
SAES-L-450,
Para. 9.4
C3
SAES-L-150,
Para. 6.2
C4
Vents and drain valves, both temporary and permanent, conforms with
the piping class or rating. ( Refer SAES-L-108)
SAES-L-105,
Para. 5.9
C5
SAES-L-150,
Para. 6.3
C6
SAES-L-150,
Para. 6.4
C7
SAES-W-011,
Para. 11.6
C8
SAES-W-011,
Para. 11.7
C9
SAES-W-011,
Para. 11.15.1
C10
SAES-L-108,
Section 4.7
C11
All in line valves that are not used as test isolation valves are in open
position.
SAES-A-004,
Para. 9.1.3
C12
SAES-A-004,
Para9.1.1
C13
SAES-A-004,
Para. 8.4.2
C14
SAES-A-004,
Para. 8.4.3
C15
SAES-L-110,
Para. 9
C16
All threaded joints up to the first block valve of hydrocarbon pipeline are
seal welded. Thread engagement has been verified & accepted.
SAES-L-110,
Para. 9.2
C17
SAES-A-004,
Para. 8.2
C18
SAES-A-004,
Para. 5.5.4
Page 3 of 12
Piping-
CONTRACTOR / SUBCONTRACTOR
FAIL
N/A
RE-INSP DATE
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
Rev 4
SAIC NUMBER
SAIC-A-2010
PROJECT TITLE
WBS / BI / JO NUMBER
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
C19
SAES-L-450
Appendix C
C20
Pressure gages and pressure recorders are calibrated within one (1)
month before the test. Check stickers at the time of the test.
SAES-A-004,
Para. 8.1.5.2
C21
SAES-A-004,
Para. 8.3
C22
SAES-A-004,
Para. 5.5.2
C23
SAES-A-004,
Para. 8.1.4
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
REMARKS:
REFERENCE DOCUMENTS:
1.
2.
3.
4.
5.
6.
7.
8.
Contractor / Third-Party
PMT Representative
Construction Representative*
Name, Initials and Date:
QC Inspector
Name, Initials and Date:
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
PID Representative
Performed Inspection
QC Supervisor
Name, Sign and Date:
Saudi Aramco
Name, Organization,
Initials and Date:
Y = YES
Page 4 of 12
N = NO F = FAILED
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
Rev 4
SAIC NUMBER
SAIC-A-2010
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
Rev 4
SAIC NUMBER
SAIC-A-2010
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
Engineering
Contractor QC
Pre-Test
Punch
Listing
Construction
Contractor QC
Clear 'A'
Items
Construction
Contractor QC
SAPMT
PID
Proponent
(By Request)
Clear
S. Aramco
'A' Items
Construction
Contractor QC
SAPMT
PID
Flushing &
Cleanliness
Construction
Contractor QC
SAPMT
PID
Proponent
(By Request)
Pressure
Testing
Construction
Contractor QC
SAPMT
PID
Proponent
System
Lay-Up
Construction
Contractor QC
SAPMT
PID
Proponent
(By Request)
Construction
Contractor QC
SAPMT
S. Aramco
Pre-Test
Punch
Listing
Reinstate
System
Final Insp
(Contractor)
S. Aramco
Final Insp
for MCC
Page 6 of 12
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
SAPMT
Rev 4
SAIC NUMBER
SAIC-A-2010
PID
Proponent
Page 7 of 12
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
Rev 4
SAIC NUMBER
SAIC-A-2010
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
Attachment - Pressure Testing Matrix for On-Plot Piping (Incl. UG Utilities, FW & Plumbing)
SYSTEM
Process
Piping
ON-PLOT NEW B31.1 & B31.3 CODE PRESSURE PIPING (SATIP-A-004 Series)
TEST PRESS
TEST CONSIDERATIONS & NOTES
& DURATION
As Calculated*
30 mins (min)
Piping Line Class List (Hydrotest Spec) lists all new process piping line classes (strength test
required per code) with exceptions for Service Test and other tests as noted below. NDE in lieu of
pressure test may be performed if requested & approved by SA Insp. Dept. Mgr. Process requests
per Sect 6 of SAES-A-004, and at a minimum, 30 days ahead of testing.
*Note: Unless limited by flanges, valves or other component (exceptions below), hydrostatic strength test pressures for every section of new
constructed line shall produce a hoop stress in pipe of 90% SMYS at test temperature. See Exceptions Below.
*Lube & seal oil piping is pressure tested with its own fluid at 1.5 times design pressure or 100 psig,
whichever is greater. Chemical cleaning precedes pressure testing. Joints shall be completely
cleaned* (oil free) before testing. *Baby Powder works best to clean/dry joints
Note: Leaks are common, difficult to identify as "active" or "non-active". Perform preliminary tests to identify all leaks, especially at flanged and
threaded joints. When evaluating leakage, utilize clean dry cloths to identify "active" leaks for repair. Oil residue found after wiping the joints (check
low points carefully) is cause for clean and retest. Always wait a minimum of 30 mins after wiping joints before reevaluation.
See Notes
30 mins (min)
Underground
Process Piping
As Calculated
See Notes
A) Test prior to backfilling (all joints exposed) & maintain test pressure for a minimum of 2 hrs B) If
justifiable (safety) & line must be back-filled, a 24 hr recorded test (Chart Recorder) reqd.
Flare Lines
(24" & above)
See Notes
30 mins (min)
Flare lines 24-inch NPS & larger with a design pressure of 75 psig or lower may be strength tested
pneumatically (75 psig is tested at 1.1 factor or 82 psig) per Para. 345.5 of ASME B31.3
Note: Test limits shall be downstream of isolation valves (beyond PZVs & locked valves for equipment). Portions of the test may be less than 24
inches from these valves to the flare header branch connection. Flare system Isolation Valves receive a pneumatic seat test at 5 psig in lieu of a high
pressure seat hydrotest. Conduct this test on a weekend to minimize personnel exposure. Perform a stored energy calc when requested by
Company. Test limits utilize blind flanges at removed isolation valve locations. Follow Pneumatic Testing SATIP.
Tested to 1.5 times the differential external pressure, but not less than 15 psig.
Vacuum Piping
See Notes
30 mins (min)
Perform a preliminary soap bubble test at 5-10 psig after construction is complete & threaded joints
are checked for engagement (two full visible thread rule). Coordinate with Compressor and Receiver
Service tests and final gasket installation.
LP Steam
(60 psig max)
Weld-Plus-Ends
Existing Plant
Piping
Incl. Tie-Ins
As Calculated*
30 mins (min)
RETESTING
REQMTS
See Notes
For revalidation purposes of existing plant piping, the test pressure shall be minimum required by the
Code ASME B31.3. The actual wall thickness of the piping and flange rating shall be determined and
taken into consideration when calculating the test pressure. In case of flanged tie-in connections, a
flange tester is utilized to conduct hydrostatic testing of flange butt weld.
Systems that already passed a successful pressure test require RETEST IF subjected to new
welding activities (Modifications, repair to pressure boundary) OR IF PWHT is reqd*.
Note: Seal welds of threaded connections & Attachment welds of non-pressure containing parts, such as wear pads DO NOT REQUIRE RETEST
UNLESS THE LINE REQUIRES PWHT (Including attachment welds & seal welds to the pressure boundary).
REPAIR
EXISTING
PIPING
See Notes
Every existing plant piping & pipeline, after repairs or alterations have been made that affect the
integrity of the pressure containing parts, shall successfully pass a hydrostatic test. The test pressure
shall be in accordance with the requirements of the applicable code.
Note: SAEP-310 requirements apply as well for pressure testing after Repairs, Upgrades, Refurbishment, etc
Open-Ended
Piping
EXEMPT,
VISUAL EXAM
Drains, vents & piping downstream of pressure relieving devices that discharge directly to the
atmosphere (max internal pressure 10 psig) are EXEMPT from testing. Drain holes installed, etc
Note: Test Package SIS Sheet shows design data & "EXEMPT" under required test pressure. Line(s) shall be visually examined.
Page 8 of 12
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
As Calculated*
30 mins (min)
Rev 4
SAIC NUMBER
SAIC-A-2010
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
Whether piping or tubing, between the root isolation valve and the instrument isolation shall be
pneumatically pressure tested (air or nitrogen) at 1.25 X design pressure of the piping system or
process equipment to which it is connected. Test duration shall not be less than 30 minutes.
Note: Instrumentation that could be damaged due to the test shall be disconnected. When pneumatic test is not practical (pressure greater than
1000 psig, physical configuration, etc.) test with liquid or water. (Flush, test & dry clean using a quality of water not harmful to lines).
Internally FBE
Coated Lines
As Calculated*
30 mins (min)
For internally Fusion Bonded Epoxy (FBE) coated piping system, the test pressure shall not exceed
5,000 psi for APCS 100, 101, 103 systems & 3,000 psi for APCS 102 System
Note: ALL Welding shall be completed (Design Issue), all internal coating and Holiday Testing PRIOR TO pressure testing.
Sampling Lines
See Note
See Note
Test separately (separate package) as required. Exemptions include sight glasses &
other instruments. Strength or Service test associated piping based on service
Note: ALL Code Piping construction (in-situ) that is not VENDOR supplied shall be tested. Utility = Service Test, Process = Strength Test
Skid-Mounted EXEMPT IF TESTED BY VENDOR 1. When testing with adjacent Lube oil system piping (no leaks = acceptance).
2. When code repairs are made to skid-mounted piping to correct misalignment,
per 01-SAMSS-010
Piping (Vendor)
(exceptions noted)
physical damage or any modifications in-situ, pressure test the affected spools.
FIELD HYDROTESTING OF NEW VALVES (SAES-L-108, Section 4.7 & SATIP-L-108 & SAIC-L-2042)
See Note
Location shall be specified by proponent & PID approved. SAIC-A-2031 Sect. J
Test Location
All new valves designated for isolation service (as specified by the Proponent) shall be
See
Note
Field Testing of
subjected to high pressure hydrostatic seat test prior to installation in line.
New Valves
Low pressure pneumatic seat test at 5 psig shall be substituted for high pressure
See Note
Exception
hydrostatic seat test for flare system valves. Identify & Segregate Early!!!
Exemption
Procedure
(Checklist Item D4)
See Note
Buttweld & socketweld end valves in NPS 2 inches and smaller are exempt
See Note
Test procedures, pressures, durations, & leakage acceptance criteria shall be equal to
those that the valves were originally purchased to. All resilient (soft) seated isolation
valves shall have zero leakage. See SAIC-L-2042
Note: Proponent specifies those Line Classes and valves subject to field hydrotesting. Valves received shall be carefully identified & given a unique
ID number for installation into the correct Line Class based on visual verification of construction stamp. Valves shall be given a unique ID &
corresponding test report document upon receipt, Valve ID shall be controlled, documents transferred into appropriate Test Pkg & Database (Piping
System, Line Class, Line Number, Location) per SAEP-1160. Procedure identifies all critical aspects of Valve Testing incl Receipt Inspection (internal
visual exam by qualified Inspector), pressure test, ambient lay-up (corrosion protection per mfg instructions & follow-up preservation reqmts) &
segregation control to prevent "mixing valves". Controlled System for Valve Placement exists.
Page 9 of 12
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
Rev 4
SAIC NUMBER
SAIC-A-2010
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
6.8 Potable Water Systems - Potable water piping inside buildings shall be tested per the reqmts of Uniform Plumbing Code (UPC). Exceptions
to UPC requirements are listed in SAES-S-060. THERE ARE 3 MAJOR EXCEPTIONS FOR INSPECTION AWARENESS
Potable water piping outside of buildings shall be tested per the requirements of SAES-S-040 (SAES-S-070, Section 18).
6.9 Utility Piping Systems - Utility systems, including irrigation piping & water distribution mains, shall be tested per SAES-S-070, Sect 18
6.10 Industrial Drainage and Sewers - Industrial drainage and sewers shall be tested per SAES-S-020 (SAES-070, Section 18).
6.11 Sanitary Sewers - Sanitary sewer systems within buildings shall be tested per reqmts of the Uniform Plumbing Code (UPC). Exceptions to
UPC requirements are listed in SAES-S-060. THERE ARE 3 MAJOR EXCEPTIONS FOR INSPECTION AWARENESS
Sanitary sewer lines outside of buildings shall be tested in accordance with SAES-S-070 Section 18.
6.12 Storm Water Drainage Systems - Test per SAES-S-030 (SAES-S-070, Section 18) Note: Only OWS portions are tested.
6.13 Miscellaneous Building Services Piping - Steam & condensate piping outside the jurisdiction of ASME B31.3, heating & cooling water piping,
vacuum & compressed air system piping for building services shall be tested per ASME B31.9, Building Services Piping.
6.14 Gas Cylinders - Gas cylinders shall be tested per Saudi Aramco Bottled Gas Manual. (Application - New Labs, etc)
6.15 Valves - Valves shall be tested in accordance with SAES-L-108, Section 4.7
6.16 Non Metallic Piping - Such as RTR, Thermoplastic, PVC/UPVC & CPVC shall be tested per SAES-S-070, Section 18.
Page 10 of 12
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
Rev 4
SAIC NUMBER
31-Mar-10
DATE APPROVED
QR NUMBER
SAIC-A-2010
31-Aug-11
Piping-
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cut off Date- March 2010)
Rev 4
SAIC NUMBER
SAIC-A-2010
31-Mar-10
DATE APPROVED
QR NUMBER
31-Aug-11
Piping-
SPEC AWARENESS
PIDs ATTENTION TO SPECS & SPEC-Check
(Piping Line Class Specs, WPS, NDT Specs, PWHT, PMI, etc) on Projects:
Initial Review of SPECS
1. Carefully recheck Contractor Piping Specs (Line Class Summary & Tables) as early as possible during or just
after Design is complete (as soon as they are issued and available).
2. This is done by checking Contractors specs against Line Class Material requirements listed in SAES-L-105. Give
special attention to critical systems & systems above 300#.
3. Average large projects can have as many as 50 different piping specs & details can be very hard to pick up in the
field. Pipelines have fewer specs and are easier to manage. THIS INCLUDES THE MAZE OF GASKETS!!!
4. Time taken for early review only takes an experienced plant inspector 2 days of review. Findings (often human
error) can be critical. Help prevent unplanned shutdowns on your projects & find substandard material specs before
they are installed or before they enter service.
5. Carefully check Contractor Special Process SPECS (WPS, NDT, PWHT, etc) as early as possible (as soon as
they are issued and available).
6. This is done by checking Contractors Special Process Specs against code and SA requirements (SAES-W-011,
Sect 17 for NDT & 13 for PWHT). SAES-W-012 is similar to SAES-W-011 in this respect
7. Ensure that notes are included in these SPECS that require increased NDT based on field welding and other
code considerations.
8. Clear violations such as our weekly highlight example (such as specs and drawings that use 3000# fittings on a
900# system instead of required 6000# fittings) must be itemized & brought to SAPMT attention early.
See attached Sample Weekly Highlight.
9. After all SPECS submitted by Contractor are accepted ... CREATE your custom SPEC-CHECK (sample
attached with instructions).
Commentary: This is a valuable review and exercise for all inspectors. Have all inspectors trained in this task for
self-reliance during future projects. This teaches critical lessons in Materials*, specification requirements* and
substandard installation identification*.
*FACT: MOST INSPECTORS ARE WEAK REGARDING KNOWLEDGE OF SPECIFICATIONS & ARE UNAWARE
OF MANY CRITICAL REQUIREMENTS! SPEC CHECK PUTS THESE DOWN ON PAPER (BY SYSTEM)