Sunteți pe pagina 1din 6

METHOD STATEMENT

FOR
SPRAYTEK PLASTER

Revisions Details:
Rev.

Date of
Issue

06.03.05

Prepared
M. Asaad

Reviewed
Engineering
QA/QC
Manager
Manager
Dr. Nabil
T. Hozayen

Approved
Project
Director
Ziad Ammous

Description
1st Issue

CONTENTS
Sr.

Subject
Page No.

Originator:

HEE

Date of issue: 06.03.2005

Page No. 1 of 6

Identification

Document Number

Contract No.

Tower/ location

Discipline

Issuer

Doc. Type

Number

Rev.

4505

General

HEE

MS

00062

/var/www/apps/conversion/tmp/scratch_5/339763491.doc

Document No.: 00062


Rev.: 0
Date of Issue: march 06, 2005
Page No.: No. 2 of 6

METHOD STATEMENT FOR


SPRAYTEK PLASTER

1.0

Scope
3

2.0

References
3

3.0

General
3

4.0
4.1

Resources
Materials
3

4.2

Equipment
3

4.3

Personnel
3

5.0
6.0
6.1

Definitions & Abbreviations


3
Procedure
Pre-application
4

6.2
7.0

Application of Spray Plaster


4
Quality Control
5

8.0

Safety
5

9.0

Attachments
5

METHOD STATEMENT FOR


SPRAYTEK PLASTER

1.

Document No.: 00062


Rev.: 0
Date of Issue: march 06, 2005
Page No.: No. 3 of 6

SCOPE: -

This Method Statement provides the control sequence of construction and methodology that will be
used for the application of Spraytek Plaster of ceiling in overall project site as an alternative for Terraco
material.
2. REFERENCES: o Project Specifications Volume II, Part 2 of 5, Section 09200.
o Drawings issued for construction.
3. GENERAL: The Spraytek Plaster shall be applied to the concrete ceilings only, in accordance with the drawings,
project specifications and the product manufacturers recommendations.
4. RESOURCES: 4.1. Materials:

Spraytek Extra Coarse Spraytek Fine, approved as per SCAR 00019.

4.2. Equipment:

Spray machine
Compressor
Measuring containers
Leveling tools
Finishing tools

4.3. Personnel:

5.

Project Engineer
Site Engineer
QA/QC Engineer
Site Foreman
Masons (Applicators)
Helpers

DEFINITIONS & ABBREVIATIONS: PE


SE
QCE
FM
SO

Project Engineer
Site Engineer
Quality Control Engineer
Foreman
Safety Officer

METHOD STATEMENT FOR


SPRAYTEK PLASTER

Document No.: 00062


Rev.: 0
Date of Issue: march 06, 2005
Page No.: No. 4 of 6

6. PROCEDURE: Responsibility
6.1. Pre-application:
1.
2.

3.

4.
5.

Approved materials shall be used in accordance with the project,


specifications and manufacturers recommendations.
Before beginning with plastering, the following shall be ensured;
- First fix of Electrical Works connected with backgrounds
have been completed.
- Adjacent finish work is well protected to prevent any
damage to it or spots, marks and stains on it during the
progress of work.
The activity of plastering shall not commence unless the substrate
is suitable. Concrete debris, binding wire, any ridges and traces of
form oil or release agents shall be removed from the surface.
Dust, dirt and foreign matter shall be brushed away and the
surface shall be ensured to be clean and dry.
Any joints of uneven level shall be grinded.
Spraytek spray plaster doesnt require any key coat haking prior
to plaster.

PE/SE
PE/SE/MEP

SE/FM

SE/FM

6.2. Application of Spraytek Plaster:


1.
2.
3.
4.
5.
6.
7.
8.
7. QUALITY:

Fill the joints with Spraytek Extra Coarse to level the uneven
joints.
Apply one coat of Spraytek Fine and level the surface with 60 Cm.
spatulla.
After 24 hours touch up the surface using Spraytek Fine and
obtain a smooth surface.
the surface is ready to receive texture to the desired size using
spraytek Fine.
Over Spraytek Spray Plaster smooth surface 2 coats of paint can
be done.
Before applying Final coat, it shall be ensured that final fix of
Electrical Works is completed.
Curing is not required for the Spray Plaster system.
Accessories (lath, corner beads, stop beads etc.) are not required
for the Spraytek plastering of ceilings.

SE/FM
SE/FM
SE/FM
SE/FM
SE/FM
PE/SE/FM
SE/FM

METHOD STATEMENT FOR


SPRAYTEK PLASTER

Document No.: 00062


Rev.: 0
Date of Issue: march 06, 2005
Page No.: No. 5 of 6

Significant stages of work shall be ensured by Project Engineer/Site


Engineer to be conforming to the drawings, specifications and
manufacturers recommendations, including;
-

PE/SE/QCE

Substrate preparation
Application of different coats of spraytek plaster
Clearance of MEP before covering up the work

QA/QC Engineer shall monitor all these stages.

First completed example of installed plaster not less than 10 meter


square shall be submitted to Consultant to establish the required
standard before proceeding with the remainder of work.

PE/SE/QCE

Inspection Request (IR) shall be submitted to Consultant for the


following stages of work;

PE/SE/QCE

o First completed example of installed work on-site


o Routine inspection of spraytek works:
- Inspection of substrate condition
- Inspection of Completed work.

8.

9.

PE/SE/QCE

Check sheet attached as Appendix. 1 shall be used at each


Inspection stage.

SAFETY:

Proper scaffolding shall be used and safety harness to be used and


secured, if required.

PE/SE/FM/SO

Proper and safe working platforms shall be used, wherever


required.

PE/SE/FM/SO

All personal protective equipment shall be used as appropriate


according to the nature of the job.

SE/FM/SO

Housekeeping shall be of good standard and all off cuts and spills
shall be removed.

SE/FM/SO

ATTACHMENTS: Appendix. 1.
application.
Appendix. 2.

QC/FIN/3-583, Rev. 1 Check Sheet for Ceiling plaster


Brochure of Spraytek Plaster system.

METHOD STATEMENT FOR


SPRAYTEK PLASTER

Document No.: 00062


Rev.: 0
Date of Issue: march 06, 2005
Page No.: No. 6 of 6

S-ar putea să vă placă și