Sunteți pe pagina 1din 178

ENGINEERS STAMP:

CONTRACTORS STAMP:

Issue for Tender

Spanier

Drschticka

Laukemann

Dec 2009

Issue for Draft Tender

Spanier

Drschticka

Laukemann

23.10.2009

PREPARED

CHECKED

APPROVED

DATE

REV

DESCRIPTION

KINGDOM OF SAUDI ARABIA


SALINE WATER CONVERSION CORPORATION


RAS AZ ZAWR POWER AND DESALINATION PLANT-PHASE 1

FICHTNER GMBH & CO. KG

PACKAGE P POWER PLANT


TENDER DOCUMENTS
LOCATION:

TITLE:

East Coast

Volume IX: Part P-B13


INSTRUMENTATION AND CONTROL SYSTEM

PACKAGE:

P Power Plant
SCALE:

DOCUMENT No.:

None

SUBCONTRACTOR:

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

REV:

0
Sheet 1 of 178

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 2 of 178
Rev. 0

List of Contents
1. Control, Instrumentation and Monitoring Systems
1.1

General

1.2

Operation and control philosophy

8
8
12

1.2.1

General

12

1.2.2

Control centers

13

1.2.3

Operation of the main units

15

1.2.3.1

Degree of automation of the main process plants

15

1.2.3.2

Gas turbines generators

16

1.2.3.3

Heat Recovery Steam Generators

16

1.2.3.4

Steam turbine generator(s)

17

1.2.3.5

Common services systems

17

1.2.3.6

Electrical distribution system

18

1.2.3.7

Desalination units (Package D)

18

1.3

Scope of supply and services

18

1.3.1

General

18

1.3.2

Scope of equipment

19

1.3.3

Spare capacity after completion of commissioning

30

1.3.4

Services

30

1.3.5

Erection, cabling, wiring, labeling

32

1.3.6

Commissioning, trial operation, and acceptance tests

33

1.3.7

Documentation

34

1.3.8

Training

34

1.3.9

Special tools and spare parts

34

1.4

Particular Technical requirements

35

1.4.1

General

35

1.4.2

Structure of control functions

36

1.4.3

Field equipment

38

1.4.3.1

General

38

1.4.3.2

Settlement Metering Equipment

38

1.4.4

Distributed control system (DCS)

40

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 3 of 178

Rev. 0

1.4.4.1

General

40

1.4.4.2

Availability and redundancy

42

1.4.4.3

General hardware requirements

45

1.4.4.4

Software requirements

46

1.4.4.5

Process station

47

1.4.4.6

Data highway communication

58

1.4.4.7

Operator station

59

1.4.4.8

System diagnostics and configuration

69

1.4.4.9

Cyber Security

70

1.4.5

Task of the main control loops

71

1.4.5.1

Gas turbine generator unit control

72

1.4.5.2

Heat recovery steam generator unit control

73

1.4.5.3

STG unit control

75

1.4.5.4

LP and HP steam control valves (Scope of Package D)

77

1.4.5.5

Desalination unit control (Scope of Package D)

77

1.4.5.6

Plant master control

78

1.4.6

Signal exchange to other Control Centers

79

1.4.6.1

Signal exchange to the SEC SCADA system

80

1.4.6.2

Signal exchange with Maaden

80

1.4.6.3

Signal exchange with Fuel supplier (Saudi Aramco)

80

1.4.6.4

Signal exchange with SWCC headquarter

81

1.4.7

Burner management system (BMS) and Boiler protection system


(BPS)

81

1.4.7.1

Functional requirements

81

1.4.7.2

Design requirements

82

1.4.7.3

System architecture

82

1.4.7.4

Hardware requirements

83

1.4.7.5

Software requirements

83

1.4.8

Failure of the power supply shall not effect the built-in logic of the
BMS/BPS.Power supply

84

1.4.9

Plant Management System (PMS)

84

1.4.10

CCR equipment

86

1.4.11

Large screen projection panels (LSPP)

86

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 4 of 178
Rev. 0

1.4.12

Conventional fascia alarm system

87

1.4.13

Asset management system / field device tools (FTD)

89

1.5

Interfaces

89

1.6

Terminal points

92

1.7

Inspection and testing

92

2. Emission Monitoring System

93

2.1

General

93

2.2

Layout

93

2.3

Scope of Supply and Services

94

2.4

Particular Technical requirements

95

2.4.1

Exhaust gas Monitoring Stations

95

2.4.2

Effluent Monitoring

99

2.4.3

Cubicles and Measuring Containers

101

2.4.4

Data Acquisition/Storage/Evaluation/Visualization

101

2.4.5

Weather Station

105

2.4.6

Portable Noise Monitoring Equipment

105

2.5

Interfaces

106

2.6

Inspection and testing

106

3. Communication, Clock and Surveillance Systems

107

3.1

General

107

3.2

Scope of supply and services

107

3.2.1

General

107

3.2.2

Scope of supply

108

3.2.2.1

Telephone system

108

3.2.2.2

Portable radio system

109

3.2.2.3

Public address system

109

3.2.2.4

Process related CCTV surveillance system

110

3.2.2.5

Clock system

110

3.2.2.6

Office LAN/WAN system

110

3.2.2.7

Spare capacity after commissioning

111

3.2.2.8

Spare parts and special tools

111

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 5 of 178
Rev. 0

3.2.3

Scope of Services

112

3.2.3.1

General

112

3.2.3.2

Erection, cabling, wiring and labeling

113

3.2.3.3

Commissioning, trial operation and Acceptance tests

113

3.2.3.4

Documentation

114

3.2.3.5

Training

114

Technical requirements

114

3.3

3.3.1

General

114

3.3.2

Telephone system

115

3.3.2.1

General

115

3.3.2.2

Telephone system features

117

3.3.2.3

Interface requirements

120

3.3.2.4

Administration software and diagnostic facility

122

3.3.2.5

Signal tones

122

3.3.2.6

Subscriber facilities

122

3.3.2.7

Voice recording system

123

3.3.2.8

Telephone sets

124

3.3.2.9

Power supply equipment

126

3.3.3

Portable radio system

126

3.3.4

Public address system (PA system)

127

3.3.4.1

General

127

3.3.4.2

Central amplifier station

130

3.3.4.3

Master call stations

134

3.3.4.4

Indoor and outdoor call stations

134

3.3.4.5

Loudspeakers

135

3.3.5

Process related CCTV surveillance system

136

3.3.5.1

General

136

3.3.5.2

CCTV requirements

136

3.3.5.3

Cameras

139

3.3.5.4

Video system accessories

140

3.3.5.5

Interfaces to other systems

140

3.3.6

Clock system

141

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

3.3.7

Office LAN/WAN system

Page 6 of 178
Rev. 0

142

3.4

Interfaces

143

3.5

Terminal points

143

3.6

Inspection and testing

144

4. Generator Rejection Scheme

145

4.1

General

145

4.2

Scope of supply

145

4.3

Functional requirements

146

4.4

Technical requirements

148

4.4.1

Security and Dependability

148

4.4.2

Trip Time Performance

149

4.4.3

Execution Modes

149

4.4.4

User Interface

149

4.4.5

Special Tools

149

4.4.6

Fault Monitoring System

149

5. Integrated Security System

150

5.1

General

150

5.2

Layout

150

5.3

Scope of Supply and Services

151

5.4

Technical Requirements

152

5.4.1

Additional requirements for Intrusion Detection & Assessment


System (IDAS)

153

5.4.2

Additional requirements for Access Control System (ACS)

153

5.4.2.1

Door monitoring

153

5.4.2.2

Administration building access control

154

5.4.2.3

Metal detector

154

5.4.2.4

Under-Vehicle Surveillance System

154

5.4.2.5

Raising arm barrier

155

5.4.2.6

Turnstiles

155

5.4.2.7

Barriers at the gate house

156

5.4.2.8

Design and function

157

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 7 of 178
Rev. 0

5.4.2.9

Equipment

157

5.4.2.10

Operation

158

5.4.2.11

Recorders

159

5.4.2.12

Cards

159

5.4.3

Additional requirements for Video Surveillance System (VSS)

159

5.4.3.1

CCTV monitoring and recording

160

5.4.3.2

Digital video recorders (DVR)

162

5.4.3.3

Monitors

162

5.4.3.4

Redundancies

163

5.4.4

Additional requirements for ID Management System (IDMS)

163

5.4.4.1

Integrated access control and badging system

163

5.4.4.2

Alarm and event recording

164

5.4.4.3

Database and other data requirements

165

5.4.5

General requirements

166

5.4.5.1

Additional requirements for the security systems integration

166

5.4.5.2

Additional requirements for the Security Control Center (SCC)

166

5.4.5.3

Transmission system

171

5.4.5.4

Security equipment tagging

173

5.4.5.5

Security equipment and devices

174

5.4.5.6

Expandability

175

5.4.5.7

System grounding and ventilation fans

175

5.4.5.8

Graphical location maps

175

5.4.5.9

Device overview

177

6. Annexes

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

178

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 8 of 178

Rev. 0

1. Control, Instrumentation and Monitoring Systems


This Part of the Specification covers the supply of the Control,
Instrumentation and Monitoring Systems (P-B13.1), Emission Monitoring
system (P-B13.2), Communication, clock and surveillance systems (PB13.3), Generator Rejection Scheme (P-B13.4) and the Integrated Security
System (P-B13.5) for the RAS AZ ZAWR Power Plant (Package P) and
interfaces to the Water Production Island (Package D).
Typical overall DCS architecture is shown in Annex P-C13-1, wherein the
tie-in points to Water Production Island (Package D) are indicated.
The Tenderer shall show details of works involved and functions
achievable. The Tenderer shall submit in the Tender the program of work,
any outage requirements in order to minimize the unavailability of units
already in operation.

1.1

black box

General
The DCS will be applied as a total solution, providing the necessary control
and monitoring means for all main systems of the whole plant, including
also the Package D systems. Main systems are designated as systems
belonging to the main technological process and serving the main purpose
of the plant. The Human Machine Interface in the Central Control Room
with remote central operating and monitoring facilities will be uniform,
using DCS standard workstations. Workstations from proprietary systems
shall not be accepted.
One unified DCS system of the same make and type shall be provided for
the entire plant of Package P and Package D. The DCS system shall be
approved solution for combined cycle power and high pride desalination
plant. Make and type of the overall DCS shall be offered by the contractor
of Package P and the contractor of Package D shall provide the same
make and type of the DCS for all Package D units and equipment.
DCS manufacturer will be subject to SWCC prequalification.
DCS type will be selected upon the submittal at the time of engineering
phase and is subject to SWCC / Engineers approval.
All DCS hardware and software required for Package D units and
equipment will be within the scope of supply and services of the Contractor
of Package D. The integration of Package D part of the DCS into the
overall DCS as well as the coordination work and the merger of Package
D data base with Package P data base is under the scope of work of
Package P Contractor. The overall automation of the entire plant of
Package P and D as well as their operation and control by the Plant

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 9 of 178
Rev. 0

Master Controller (PMC) shall be within the scope of work of Package P


Contractor.
Alternative: Package D Bidder offers a DCS for Package D of different
make and type than the DCS supplied by Package P. In this case, the DCS
offered for Package D shall still fully comply with this Specification. The
interface between the two DCS systems shall be hardwired for all the
interlocks (for control) and protection signals and shall be well defined and
well coordinated by the Contractors of both Packages. Each Contractor of
both Packages shall provide the necessary hardware, such as modules and
interface devices as well as necessary software required for the interface
signals at his end. Cables and cabling work related to the interface signals
from the marshalling cabinets to the DCS cabinets as well as the internal
DCS cabinets wiring, marshalling cross-wiring and field connection of the
cables inside the marshalling cabinets is the responsibility of each Package
Contractor at his end.
Cables and cabling work related to the interface signals from the
marshalling cabinets of Package P to the marshalling cabinets of Package
D is within the scope of Package P. The overall coordination,
commissioning and operation of the interface signals are the responsibility
of Package P Contractor.
This Specification covers the supply of the control, instrumentation and
monitoring equipment for the new installations of RAS AZ ZAWR Power
Generation Island (Package P). This mainly includes those for the
elsewhere specified (Parts P-B1 through P-B8) gas turbine generators
(GTGs), heat recovery steam generator (HRSGs), steam turbine generator
(STG) and auxiliary systems. Over and above that, the control operation and
monitoring of the Water Production Island (Package D) shall be carried
out by means of an extension of the Power Generation Island DCS, as
described under Part D-B10 (Package D). Nevertheless, the
responsibility for the layout of the overall DCS of Power and Desalination
Plant (e.g. system architecture, spare capacities for common equipment and
common functions) shall remain within the hands of the Contractor for the
Power Island (Package P).
The control, instrumentation and monitoring equipment to be provided shall
be suitable for faultless and safe control and supervision of the entire Power
and Desalination Plant during all the operating conditions. All the supplied
control, instrumentation and monitoring equipment shall be suitable for their
installed location, and in particular, all outdoor equipment shall be suitable for
the specified ambient site conditions.
The Specification stipulates the minimum requirements for the design,
scope of supply of the required equipment and materials, fabrication,
inspection, testing and commissioning of the systems. The Contractor shall

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 10 of 178

Rev. 0

be responsible for the design of all hardware, software, interfaces to other


systems, system testing, documentation, delivery, installation, supervision
and field support for the systems as defined within this Specification.
All instrumentation and control works/ equipment not expressly called for
in this specification, but necessary at the discretion of the Engineer, for the
complete and proper installation and operation of the plant equipment and
accessories shall be performed and provided by the Contractor at no
additional cost to SWCC.
Make and type of PLC systems as well of the field instruments are subject for
approval of SWCC/ Engineer.
General design criteria for the instrumentation and control equipment are
stipulated in Part P-B03.
The Contractor shall adhere to the functional requirements, design criteria
and system configuration contained in this document. Where there is a
conflict between the requirements of the Specification and the Contractors
current standard system/technology, this shall be clearly defined in writing
as a deviation to the Specification. The Contractor may propose alternative
improved performance features as long as the system is made up of plant
proven hardware and software modules.
A general description and a layout of the Power and Desalination Plant are
included in Part P-A3.
The following explanation shall be considered as main aspects for the
technical concept of the Instrumentation & Control Systems. The plant
instrumentation and control equipment shall be selected and designed in
such a way that the operation as described below and the following
functions shall be performed for each power plant block and for the
desalination plant.
The concept shall take full advantage of the currently available integrated
control system technology to maximize plant performance and availability
as well as to achieve a cost-effective installation. To achieve this, the
control protective and supervisory functions required for the central
operation of all the plant facilities shall be implemented in a uniformed
Distributed Control System (DCS). But the DCS system should be
segregated at its automation level for the power plant blocks, common
systems and the desalination plants, such that each unit/system shall have its
own dedicated DCS process control station. This is required to achieve the
highest availability of the Plant. (see also Annex P-C13-1)

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 11 of 178
Rev. 0

Start-up, generator synchronization and loading of the GT units, the


HRSGs, ST, the demineralization plant and all auxiliary equipment from
the Central Control Room while using all the main full automatic start-up
and shut down sequence step and automatic function group programs
with one pushbutton operation for each unit of the power block.. Semiautomatic and manual modes shall also be provided for operator
selection.
Automatic start-up sequence will also be provided for all auxiliary
equipment in the plant.
Full automatic start-up and shutdown sequences will be provided for the
desalination units based on function group control. Minimum preparation
work which consists of filling of lines and establishment of the
recirculation system can be carried out locally and respectively by the
operator from the CCR operator stations prior to the full automatic
sequence.
Plant / Unit Master Controller-coordinated power plant block operation,
capable of handling unscheduled load changes as well as scheduled load
ramps.
Complete supervision of the whole plant, including the GTs, STs,
ROs, the thermal Desalination plant and auxiliary systems in the plant
Safe operation in case of Unit island/ house load operation
Automatic contribution to grid frequency control
Integration of the requirements of AGC (automatic generator control)
Safe shutdown of the units/ power plant block. Full automatic shutdown
sequences shall also be provided for all plant units and auxiliary
equipment including unloading, breaker opening and shutdown
The DCS system shall be applied as a homogeneous solution, providing the
necessary control means basically for the whole plant. However, depending
on the kind of the process hardware it should be allowed using package
controls for the gas turbines and for the control (governing) and protection
system of the steam turbines. In any case, the variety of the main control
systems in the Plant shall be limited to the minimum, i.e. the DCS type shall
follow either the type of the BPST/CEST or of the GTG control system. The
main controller of the GT, BPST/CEST, HRSG should be part of the DCS
and directly interfaced without gateways. This shall be a proven solution for
similar combined cycle power and desalination plants.
The BMS (Burner Management System) of HRSGs as a certified fail-safe
system shall be part of the DCS.
Interfacing with package control systems shall use standard interfaces and
protocols. However protection signals shall be connected hard-wired in
triple redundancy (e.g. 2 out of 3). Control signals shall be connected hardwired in dual redundancy. Emergency push buttons shall be provided for the
major plant equipment such as boiler, turbine and generator etc.
FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 12 of 178

Rev. 0

The Human Machine Interface in the Central Control Room shall be


uniform, using the same DCS standard workstations.
The use of black box systems with PLC's or local controls for ancillary
plants or systems is limited to secondary systems, i.e. systems which are not
affect the availability or the performance of the plant. The accepted black
box systems are mentioned in Part P-B03 clause 6.2. Only some special
cases can be considered subject to the Employer/Engineers approval. PLC
systems shall be of uniform type, compatible with the main DCS system and
shall be built single fault tolerant in all aspects. The application and the
manufacturer/type of these control systems shall be subject to
Employer/Engineer's approval.
The remote central operating and monitoring facilities will be installed in
the Central Control Room.
The Plant common auxiliary systems will be controlled by the DCS
workstations in the CCR, too.
The plant shall be interfaced with the LDC, with Saudi Aramco for Fuel
supply and metering and SWCC headquarter for limited amount of signals.
The plant shall be interfaced with Maaden for required amount of signals.
(see Annex P-C13-4)

1.2

1.2.1

Operation and control philosophy

General
The plant will be designed for base load operation, however, it shall be
possible to achieve a considerable turndown of power generation whilst
maintaining to full water production. This means, for the power and steam
generation units, in addition to base load operation, automatic start-up and
shut-down functions are also required for the on-line regulation of Power
and Desalination Plant.
Although part load operation of the desalination units will be infrequent, the
units shall be capable of unrestricted operation between 60% and 100%.
During the normal on-line operation of the plant, the main operatorfunctions, as carried out from the Central Control Room (CCR), shall be
those of supervision and selection of the appropriate pattern of running plant
to meet the electrical load and steam demand targets with optimum fuel
economy, generation and production security within any operational plant
constraints.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 13 of 178

Rev. 0

The essential plant operational management functions of starting up,


shutting down and load demand setting of the power and steam production
units shall remain directly under the operators control whilst the on line
regulation of the plant components (e.g. turbines, boilers, etc.) shall be fully
automated.
The automation shall meet the following objectives:
consistent start-up and shut-down of the plant under all operational
conditions;
to achieve minimum run up and loading times consistent with pre-set
thermal stress limits;
to meet the request of block control and plant master control
to meet plant output demand set by the load dispatcher;
to minimize fuel consumption during start-up, shut-down and normal online operational cycle;
to maximize plant life expectancy;
to simplify operation
The essential common plant systems (e.g. boiler feed, fuel, cooling water,
etc.) shall be automated to leave the overall control co-ordination of these
areas in the hands of the operator to ensure maximum flexibility of
operation.
The control system shall be designed so, that the plant can be safely
operated with a minimum number of operators.
A plant management system (PMS) shall allow access to all information of
the DCS and other related control, diagnostic and monitoring systems for
the shift supervisor, management like superintendent and operators.

1.2.2

Control centers
The control system shall be so designed, that full control and supervision of
the complete Power and Desalination Plant (power/ steam generation and
water production) shall be possible from a main CCR. The CCR shall be the
operational focus for the whole Power and Desalination Plant from where
all major plant items such as the GTGs, HRSGs, supplementary firing, STG,
thermal desalination units, RO and auxiliary systems like gas reducing
stations, feedwater, fuel oil system, electrical system etc. shall be capable of
being started, on-line regulated and shut-down.
The design, engineering and layout of the whole Central Control Room,
including the portion delivered by Package D with operator workstations,
printers and large screen device shall be carried out in the Package P
scope and shall be sub-contracted to a specialized company, which shall

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 14 of 178

Rev. 0

make the design, interior architecture, lighting, color, material and furniture
according to the state-of-art of the latest technology in CCR design
worldwide and shall comply with the international ergonomic standards.
It shall also be considered in the design that the general overall process
information to be displayed on the large screen monitors shall be visible to
all persons.
The interior design and execution of the CCR is fully under the scope of
work of Package P Contractor and the proposed specialized SubContractor shall be submitted with all qualification documents for
Employer/ Engineers approval.
In addition, there shall be a number of Local Electronic Rooms (LERs)
located in the main plant areas as follows:

each GT (adjacent to relevant GT unit)


HRSG;
STG
desalination units;
RO plant
Seawater Intake.
Fuel gas system
Fuel oil system
Compressed air system
Blending Plant and Potable Water System
Water Treatment Plant

These LERs shall serve for the accommodation of the control cabinets of the
DCS and PLC.
The LERs of each GTG shall be equipped with one Local Operator Station
(LOS). During normal operation the LERs (GTGs) shall be unmanned.
These LERs shall only be used during first start-up, emergency situation
and during maintenance. However, all control and supervisory facilities
available in the CCR shall, in general, be provided in the LER of GTG to
ensure that there is always a full back-up control facility in the event of a
major failure within the CCR area. Therefore, each GTG shall be provided
with one (1) operator station (one VDU, keyboard, mouse) located in the
LER for each GTG.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

where is the
location
Doosan

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 15 of 178
Rev. 0

Beside the Central control room (CCR) a local control room (LCR) shall be
foreseen for plants as follows:
Chlorination plant
CO2-plant and limestone plant (common LCR)
Each of these LCRs shall be equipped with one redundant operator station.
These LCRs shall have the same environmental conditions like the CCR (air
conditioned, dust free, vibration free, etc.).
The control cabinets of the DCS system will be established beside in a LER.

1.2.3

1.2.3.1

Operation of the main units

Degree of automation of the main process plants


The plant shall be designed with high degree of optimized automation,
safety protection and minimum of operator interface. The following
operational sequences relating to gas turbine generation, HRSG, steam
turbine generation, RO and thermal desalination units will be fully
automated, requiring the minimum of operator intervention under normal
conditions.
Cold start after maintenance
Defined as a start after major maintenance activities.
The start up of operation of the HRSG; SG and all supportive auxiliary
systems shall be coordinated remotely and supervised from the CCR, but
local field operators might be needed for venting, dewatering, draining of
pipelines etc. and other manual activities. The start up of GT might be
coordinated from local GT compartment, instead of CCR.
Normal Cold Start
Defined as a cold start that has not been preceded by major maintenance
activities.
The operation of the HRSG and all supportive auxiliary systems shall be
coordinated remotely from the CCR from where all control procedures
are initiated and supervised.
Warm Start - applies to GT, ST, HRSG units only
Defined as a start-up after an overnight shutdown. This will be carried
out and coordinated remotely from the CCR.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 16 of 178
Rev. 0

Hot Start
Defined as a start-up following a plant trip.
Fully coordinated from the CCR.
Normal and Emergency Shutdown
Fully coordinated from the CCR.
Electrical load management to meet plant output demand set by the load
dispatcher
Normal operation shall require in general a minimum of attendance by field
operators throughout the plant.
All the start-up sequences shall be designed for starting the unit as first unit
or as subsequent unit.
The essential common plant systems including the seawater system, the
condensate return, fuel supply and cooling water systems will be automated
to the group level, which leaves the overall control coordination of these
areas in the hands of the operator to ensure maximum flexibility of
operation.

1.2.3.2

Gas turbines generators


The operation of the GTGs, as specified in Part P-B1 shall be fully
automated. The automation shall provide for comprehensive control,
monitoring, and safe operation of GTGs from the Power Control Desk in
CCR (normal) and Local Operating Stations in LERs either through
independent GTG control systems interfaced to DCS, or through DCS
integrated GTG control systems (preferred). Automatic starting (with a
single command), synchronizing, loading and shutting down of the gas
turbine generators shall be provided. The only operator intervention
required shall be to select the fuel to be used and to set the load. The switchover from gas firing to oil firing shall be automatic, and switch-back from
oil to gas firing shall be manual. Fuel changeover should not create
disturbances in the operation.

1.2.3.3

Heat Recovery Steam Generators


The HRSGs, as specified in Part P-B2 shall be controlled, monitored and
operated from Power Control Desk in CCR (normal).
The start-up, loading and transfer to control mode of each HRSG shall be
automated from the point at which the turbine exhaust gas is admitted to the
HRSG. Preparation prior to HRSG starting shall be remotely by operators
initiation to satisfy the necessary pre-start conditions. Supplementary firing

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 17 of 178
Rev. 0

shall cut in and cut out automatically based on boiler load demand and GTG
load in addition to manual operating facility. However, the burner light up
and shut-down sequence as well as supervision shall be fully automated.
The HRSG initial preparations including start up of auxiliaries may be
initiated from the group, sub-group and drive level as appropriate. Initial
preparation shall be enabled with one single command. However once the
gas turbine exhaust gas enters the HRSG, the subsequent warm up and
loading sequence shall be fully automated.

1.2.3.4

what is this?

Steam turbine generator(s)


The STG(s) under normal operation will be supplied with live steam from
the HRSGs.
The operation of the STG shall be fully automated. Each STG, and its
associated auxiliary systems, as specified in Part P-B4 shall be controlled,
monitored, and operated from Power Control Desk in CCR (normal), either
through independent STG control system interfaced to DCS, or through
DCS integrated STG control system (preferred). The automation shall
provide for STG start-up, synchronization, automatic speed and voltage
regulation, exhaust pressure control during plant upsets, and shut-down. The
control systems shall provide for efficient and safe operation of STG(s) and
its auxiliaries through all the operating scenarios.
A Thermal Stress Evaluator (TSE) shall be provided. It shall monitor,
display and control the thermal stress levels of the turbine. It shall
automatically co-ordinate with the auto run up program in order to ensure
that the permissible turbine stress levels are never exceeded.
Control of the turbine in automatic mode is possible from plant DCS. Also
control of the turbine/generator on functional group level is operable from
plant DCS.

1.2.3.5

Common services systems


Common service shall be fully automated and monitored from the CCR as
part of the DCS.
The main steam systems, as specified in Part P-B5 including high pressure
steam system, steam bypass system, medium pressure steam system, low
pressure steam system, and deaerating steam system shall be, as a minimum,
fully automated for control, monitoring and operation from Common
Services Control Desk in CCR.
The main water systems as specified in Part P-B5 including boiler
feedwater system, condensate system, make-up water system shall be, as a

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 18 of 178

Rev. 0

minimum, fully automated for control, monitoring and operation from


Common Services Control Desk in CCR.
The common fuel systems, as specified in Part P-B6 including fuel gas
system, and diesel fuel oil system shall be, as a part of the DCS, fully
automated for control, monitoring and operation from Common Services
Control Desk in CCR.
In addition, other common services systems, as specified in other Parts of
Package P as well of Package D including waste water systems,
seawater supply system, closed cooling water system, service air and
instrument air system, potable water blending reservoir system, and other
systems shall also be controlled and monitored by the DCS and shall be
operated from Common Services Control Desk in CCR.

1.2.3.6

Electrical distribution system


The electrical distribution system of Power and Desalination Plant, as
specified in Part P-B12 and D-B09 shall be controlled and monitored via
DCS from the Electrical Control Desk in the CCR (normal). This shall, as a
minimum but not limited to, include operation and monitoring of LV & MV
switchgear, UPS, DC systems, etc.

1.2.3.7

Desalination units (Package D)


The desalination units, as specified in Package D shall be controlled,
monitored and operated, via the DCS, from the Water Control Desk in CCR.
The automation shall provide for automatic start-up, normal operation, and
shut-down from CCR of the desalination units. Start-up shall be enabled
with function group commands. The preparatory works for start-up and final
stages of shut-down shall be done from CCR.

1.3

1.3.1

Scope of supply and services

General
This sub-section sets out the scope for the control, instrumentation and
monitoring equipment for the installations covered by this Specification as
well as supplies and services, but without excluding other necessary
components and services not mentioned. This includes all control,
instrumentation and monitoring equipment within the CCR and LERs, and
associated field mounted equipment, which fulfils the control,
instrumentation and monitoring tasks as specified in the various parts and
sections. Sufficient instrumentation to the satisfaction of the Engineer shall

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 19 of 178

Rev. 0

be provided to meet appropriately the operational and safety requirements


of the plant.
The Contractor shall be responsible for all engineering, design,
manufacture, programming, configuration, documentation, materials,
supplies, factory and field testing, delivery, installation, start-up, tuning and
initial operation through completion of the work specified.

1.3.2

Scope of equipment
Field Equipment
all measuring and signal conditioning equipment (e.g. sensors,
transmitters, switches, analyzers, flowmeters, etc.) installed in the field
as well as in the CCR and LERs.
four (4) portable programmers (handheld computers) of each type (or
with the related software) for programming and calibration of SMART
transmitters and positioners.
all local instrumentation necessary for general start-up preparation, shutdown, local plant supervision and maintenance, including at least the
following:
Pumps

Suction and discharge pressure gauges


Gland sealing pressure gauge (if applicable)

Strainers and
Filters.

Differential pressure gauges

Heat exchangers

Temperature and pressure gauges upstream and


downstream, both tube side and shell side.

Lubrication and
Cooling systems

Pressure/temperature gauges, flow indicators at


appropriate locations to enable proper system
monitoring.

Tanks and Vessels

Level indicators, pressure and temp. gauges.

Common process
headers

Pressure, and temperature gauges

any other field equipment as required for the specified mode of operation
and for a safe and satisfactory operation and supervision of the plant.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 20 of 178
Rev. 0

Distributed Digital Control System (DCS)


All main systems shall be controlled by DCS. The typical overall DCS
architecture is shown in Annex P-C13-1, wherein the tie-in points between
Power and Desalination Plant (Package D) are indicated.
The plants main control system shall be a distributed digital control system
(DCS) in accordance with the technical requirements specified under Part
P-B13.1.4.4, including:
The DCS shall cater for the following main functions:
Signal acquisition, conditioning and processing
Closed-loop control
Open-loop control and interlocks
Plant and Unit Coordinator
Plant and Unit Master Control/ Load Control
Function group controls, sub-group controls and drive controls
Plant and equipment protection
Alarm and status annunciation
Data communication
Data displaying and information presentation to the operating staff
Data storage for periodic or post-trip analysis of the plant or equipment
analysis in form of curves, tables and lists (redundant historian server)
Supervision and plant performance calculation
System engineering and diagnostic
The following is a minimum list of systems to be controlled and monitored
by the DCS, but not limited to:
GT Units with their auxiliaries (if no package control was agreed, but in
this case operation and monitoring via DCS operator stations is required
at least)
HRSG including circulation systems, vent and drain systems, etc.
HRSG duct firing burner control and management system
Feedwater supply systems including auxiliaries
Steam system
Steam turbine control, start-up, run-down and protection and Steam
turbine auxiliaries (oil supply, turning device, drainage, etc.), (if no
package control was agreed, but in this case operation and monitoring via
DCS operator stations is required at least)
Steam Turbine Supervisory system (at least monitoring)
Evacuation systems
Condensate system
Circulating water system
Closed cooling water system

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 21 of 178

Rev. 0

Instrument and compressed air system (monitoring, pre-selection and


automatic change over)
Block related fuel supply systems
Black Start Diesel (monitoring and overall control)
Fuel gas compressors. (monitoring, automatic change over)
Diverter dampers of the HRSG.
The DCS shall include as a minimum, but not limited to the following
systems/equipment:
Single fault tolerant fiber optical plant (highway) bus (at least100 MB/s).
Redundant Fiber Optical Terminal (CCR LAN) Bus.
Redundant Processing Units and Server Units shall be provided to
connect the Plant Bus/highway bus to the Terminal Bus /CCR LAN.
Operator stations and large screen monitors in CCR, which are specified
somewhere else in the specification.
Local operator stations, which are specified somewhere else in the
specification.
Engineering stations, which are specified somewhere else in the
specification.
Diagnostic stations, which is specified somewhere else in the
specification.
Plant Management System (PMS)
PMS operator stations, which are specified somewhere else in the
specification.
Redundant optical switches to connect the DCS process control stations
to the plant highway bus redundantly and for bus-to-bus connection.
DCS process control station shall be designed to maximize the plant/ unit/
systems availability. Non-availability of any DCS process control station
shall affect a minimum process function. All DCS process control stations
shall be redundant and segregated according to their function, which shall
be provided at least as follows:
Each GTG (if no package control was agreed) shall be provided with
DCS process control stations for:
GTG Governor Controller.
Sequence and Auxiliaries Control.
Measurements and Supervisory System.
Failsafe Protection System.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 22 of 178

Rev. 0

Each HRSG shall be provided with the following DCS process control
stations:
Boiler Control System.
Boiler Failsafe Protection System.
Failsafe BMS for the Supplementary Firing Burners.
Each ST shall be provided with the DCS process control stations for:
ST control, Governor control (if no package control was agreed)
Sequence and Auxiliaries Control.
Measurement and Supervisory System.
Failsafe Protection System (if no package control was agreed)
Identical DCS process control stations shall be provided for the fuel gas
supply system/ gas compressors per unit.
Separate DCS process control stations shall be provided for the fuel gas
common system.
DCS process control stations shall be provided for the fuel oil system.
DCS process control stations shall be provided for the steam and water
systems.
DCS process control stations shall be provided for closed circuit cooling
water system, chemical dosing and chemical sampling system.
DCS Process Control Stations shall be provided for the condensate and
feed water system.
DCS process control stations shall be provided for each of the diverter
damper package for each HRSG.
DCS process control stations shall be provided for the Plant Master
Controller and Plant Protection Co-ordination.
DCS process control stations shall be provided for the electrical system
of the power plant following the specified segregation principles and
shall be located near to the switchgear panels.
DCS process control stations shall be provided for any other
equipment/system not mentioned above but deemed to be necessary at
the discretion of the Employer/Engineer.
In order to maximize the availability and the reliability of the plant/ units/
process, the total number of process control station will be defined at
beginning of the engineering phase based on the final plant configuration.
Redundant interface modules and serial data links to the PLC black box
control panels, which are specified elsewhere and subject to the
Employer/Engineer's approval.
Redundant interface modules and serial data links to the Substation
Control and Monitoring System (SCMS) as well to LDC including a
interface cubicle (located in 380kV substation).
Plant highway bus connection shall be provided and connected to the
Package D DCS cubicles distributed in the Plant.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 23 of 178
Rev. 0

Each unit shall be provided with separate marshalling cabinets, which shall
be supplied from the supplier of the DCS cabinets and shall have the same
material, color and size.
Maxi-Thermipoint connection or similar, reliable modern connection
technology shall be used inside the marshalling cabinets. .Each marshalling
cabinet with doors from the front and the back side shall be provided with
20% spare capacity in the termination blocks to be counted after completion
of commissioning. The number of marshalling cabinets to be provided for
each unit/system shall be decided taking into consideration the quantity and
size of cables in-and-out. It shall be ensured that in no way the marshalling
cabinets are over-crowded with cables in the entrance opening and/or inside
the cabinet. This all is subject to the Employer/Engineers approval.
Any other equipment not specified above but deemed to be necessary shall
also be provided at the discretion of the Employer/ Engineer.
Integration of Water Production Island (Package D)
All DCS equipment directly assigned to Water Production Island (Package
D) as shown in Annex D-C10-1 and described in more detail in Part DB10 shall be integrated in the overall DCS supplied under the Contract for
the Power Generation Island (Package P). Furthermore, all facilities and
software functions commonly used by Water Production Island and Power
Generation Island, e.g. central data base of DCS, shall be under coordination and responsibility of the Contractor for Power Generation Island.
Plant Management System (PMS)
A Plant Management System (PMS) as highest level in the control hierarchy
shall comprise at least
redundant PMS server
Operator stations for shift supervisor, superintend office and engineering
room with color laser printer
Operator station for each of the operator desks (each power block,
common systems, RO, each thermal desalination part)
network
data exchange to Office LAN (for access for unlimited number of staff)
WEB access to PMS from office PCs
License for unlimited use and unlimited tags for SWCC
Integration of data provided by Package D
High end quality hardware and software tools should be used for the PMS.
(The PMS can be of PI system or equivalent.)

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 24 of 178
Rev. 0

Various PLC based control systems for package equipment (if


approved by the client)
including two programming devices for each type of PLC together with all
required software licenses.
Asset management system/field device tool (FDT)
The asset management system for instruments, transmitters and actuators
shall consist of:
Centralized configuration and diagnosis station including hardware, all
necessary programs and software tools
Redundant server
Suitable number of portable handheld devices
Two (2) operator stations in the engineering room (one (1) for each
package)
Sufficient number of licenses (at least 5)
Integration of data provided by Package D
Vibration Monitoring System (VMS)
The vibration monitoring system shall consist of:
Centralized configuration and diagnosis station including hardware, all
necessary programs and software tools
Redundant server
Suitable number of portable handheld devices
Two (2) diagnosis stations for the control room (one (1) for each
package)
Engineering station for the engineering room
Diagnosis station for the T&I (Test & Inspection) office
Sufficient number of licenses (at least 5)
Necessary field equipment
Integration of data provided by Package D
The principle of the system is shown in Annex P-C13-8.
The requirements for the vibration monitoring system are described in Part
P-B03-4.9.
Central Control Room Equipment
Normal operation of the plant shall be performed from VDUs of the
operator desks in the CCR. One operator shall have two operator stations
containing two VDU each. For the overview different large screen panels
have to be installed in the CCR, too.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 25 of 178

Rev. 0

For operation of the complete Power and Desalination Plant different


operator areas shall be foreseen as follows:
power generation control desks (for each block)
common facilities and services control desk
water control desks (1x RO, 3x thermal desalination, 1x desalination
common systems)
and control desk for electrical services
The CCR shall, as a minimum, accommodate the following equipment:
Five (5) or six (6), if relevant Power Control Desks (PCDs) each
comprising of:
Three (3) operating stations
each operating station consists of two TFT-based Visual Display
Units (VDU) with a dedicated CPU and graphic display controller,
keyboards and mouse, related to each PCD the following equipment
shall be provided:
one (1) hardcopy laser printer (color and black/white),
one (1) Large Screen Projection Panel (LSPP),
hard-wired emergency shut-down push-buttons for each of the
GTGs, HRSGs and STGs,
one (1) control desk
two (2) operators chairs;
Water Control Desks (in the Scope of Package D, D-B10)
comprising of 5 control desks:
Desk for RO (two (2) operator stations)
Desk for thermal desalination part 1 (three (3) operator stations)
Desk for thermal desalination part 2 (three (3) operator stations)
Desk for thermal desalination part 3 (three (3) operator stations)
Desk for desalination common (three (3) operator stations)
each operator station shall consist two TFT-based Visual Display
Units (VDU) with a dedicated CPU and graphic display controller,
keyboard and mouse,
related to each desk section the following equipment shall be
provided:
one (1) hardcopy laser printer (color and black/white),
one (1) Large Screen Projection Panel (LSPP),
hard-wired emergency shut-down push-buttons,
one (1) control desk
two (2) operators chairs;
Remark: Furniture (desk and chairs) to be supplied by Package P
because of identical design of these pieces of furniture.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 26 of 178

Rev. 0

one (1) Electrical/ Common Services Control Desk comprising of:


three (3) operating stations , each consists of two TFT-based Visual
Display Units (VDU) with a dedicated CPU and graphic display
controller, keyboards, mouse,
one (1) Large Screen Projection Panel (LSPP),
one (1) hardcopy laser printer (color and b/w)),
one (1) control desk
four (4) operators chairs;

one (1) Shift Supervisors Operator Desk comprising of:


one (1) operating stations , each consists of two TFT-based Visual
Display Units (VDU) with a dedicated CPU and graphic display
controller, keyboards, mouse,
one (1) laser printer (color),
one (1) control desk
one (1) shift supervisors chair;

Operator Stations for crosswise operation (for each of the above


mentioned desks), each consists of one TFT-based Visual Display Units
(VDU) with a dedicated CPU and graphic display controller, keyboards,
mouse
(see as reference therefore Annex P-C13-5)
All control desks shall be supplied with audible/ visual equipment for the
DCS alarms and annunciations which shall be of different tones for
different units
LCD indicators (red color, 120 mm TEXT height) shall be provided in
the CCR panel for display the total power production and the total power
export as well for the water production and water export.
Data Exchange (SQL-/ WEB-server) including firewall for data
exchange to other systems (e.g. office LAN, enterprise systems) and
necessary software licenses, if any
Furthermore equipment of communication systems (e.g. telephone) shall
be built into each control desk or in panel.
Gas detection and fire detection panel /desk, fire fighting panel, panels
for building management system (HVAC, chiller plant), CCTV as well
the black start panel shall be considered for installation within the CCR,
too.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 27 of 178

Rev. 0

one (1) set of furniture consisting, as a minimum, of one (1) integrated


filing cabinet (total length min. 10m) and one (1) integrated side board
for each of the above mentioned desks, one (1) writing desk with
adequate space for spreading an A0-size drawing on top, one (1)
common filing cabinet for storing drawings and documents, and one
common (1) side board, wall whiteboard (min. 1000mm x 1500mm),
lockers (min. 2m) for spare and consumables
Printer desks / sideboards
Fire proof cabinet for software and data holder storage
Meeting area (table and chairs)
Regarding to the modern design of the control room area all doors, windows
including shutter or venetian blinds, partition walls have to be planned,
supplied and installed.
The restroom/ toilets and the kitchenette of control room area have to be
fit out with all sanitary installation and kitchen furniture (sink,
refrigerator, stove, microwave, kitchen things, all other furniture as well
table and chairs).
Specialized company shall do the final design/ layout of the Central Control
Room. This documentation is subject to separate approval. The design of
arrangement, lighting, colors, interior architecture and materials, etc., shall
be prepared by careful consideration of the ergonomic aspects and up-todate control room design principles.
Local Electronic Room (LER) equipment.
The LERs shall mainly accommodate the DCS process stations or PLC
cubicles.
In addition, the LER for each GTG shall be provided with the following
equipment:
one (1) Local Operator Station (LOS):
The LOS shall be complete with VDU, keyboard, mouse or track-ball
and the conventional control elements, such as emergency shut-down
push-buttons.
one (1) set of furniture consisting, as a minimum, of two (2) operator
chairs, one (1) writing desk with adequate space for spreading an A0-size
drawing on top and for accommodating the specified (ref: Sub-section PB12.10) telephone instrument(s), one (1) filing cabinet for storing
drawings and documents, and one (1) side board.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 28 of 178

Rev. 0

Local Control Room (LCR) equipment.


The LCRs shall be provided with the following equipment, each:
two (2) Local Operator Stations (LOS):
The LOSs shall be complete with TFT based VDU, keyboard, mouse
and the conventional control elements, such as emergency shut-down
push-buttons.
one (1) printer
one (1) hardcopy printer
one (1) set of furniture consisting, as a minimum, of two (2) operator
chairs, one (1) writing desk with adequate space for spreading an A0size drawing on top and for accommodating the specified (ref: Subsection P-B12.10) telephone instrument(s), one (1) filing cabinet for
storing drawings and documents, and one (1) side board.
Engineering and Diagnostic Room Equipment
An engineering room shall be located adjacent to CCR, and shall, as a
minimum, accommodate the following supply:
One (1) Engineering Station and one (1) Diagnostic and Documentation
Station for each of the DCS sections comprising of:
two (2) TFT based Visual Display Units (VDU) each with a dedicated
CPU and graphic display controller, keyboards, mouse,
one (1) A4/ A3 -format color laser printer,
two (2) chairs;
one (1) desk for accommodating the above mentioned equipment with
adequate space for spreading an A0-size drawing on top
Two cabinets for each DCS section
Furniture for one (1) Engineering Station and one (1) Diagnostic and
Documentation Station for each of the Package D DCS sections
comprising of same equipment like for Package P
four (4) sets of working desks and chairs
one (1) storage cabinet for keeping consumables;
one (1) cabinet for keeping ready-to-refer essential plant documentation
and drawings;
one (1) filing cabinet (min. 15m)
One PMS station including desk/ chair
One CEMS station including desk/ chair
Operator stations for asset management system / FDT (2x) including
desk/ chair
One vibration monitoring system (VMS) for diagnostic. including desk/
chair
Two personal computers with office applications
Fire proof cabinet for software and data holder storage
One fire proof cabinets for routine backup software

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 29 of 178
Rev. 0

Additional Engineering stations have to be provided during


commissioning and tuning period in sufficient number that parallel
commissioning works can be carried out independent for the different
systems and process areas.
Portable stations (e.g. Laptop) for diagnostic and programming functions
shall be included in the scope with the relevant functions for diagnostic and
programming features for programmable components e.g. transmitters and
actuators.
Settlement metering equipment
A special billing and metering system shall be installed for accounting all
media exported to Maaden and SEC as well to PS 1. The metering system
shall consist of settlement meters, back-up meters and quality
measurements, described in the tables below.
Fuel gas supply pipeline to
Maaden
Process water (from thermal
desalination) to Maaden *
Potable water to Maaden*
* in the scope of Package D

Device
Flow meter

Location
Plant boundary

Flow meter

Plant boundary

Flow meter

Plant boundary

A metering system foreseen for the media exchange to SEC/ SWCC shall be
foreseen, which consists of settlement meters, back-up meters and quality
measurements, described in the tables below:
Each power connection to SEC
380 kV substation and 13.8 kV
substation
Drinking water to Substation*

Device
CT / VT
Meter
Flow meter
Quality
measurement

Location
Substation
Relay and
protection room of
substation
Plant boundary
Plant boundary

* in the scope of Package D


A metering system foreseen for the fuel supply systems shall be supplied,
which consists of settlement meters, back-up meters and quality
measurements, described in the tables below.
Fuel gas supply pipeline
Back-up fuel supply
FICHT-5296110-v5-RAZ_TD_P-B13.DOC

Device
Flow meter to
SWCC plant
Flow meter

Location
Plant boundary
Ship unloading

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 30 of 178
Rev. 0

Device

Location
station / Pipeline

An automatic meter reading system shall be supplied for collection and


validation of all metering signals.
A commercial billing system shall be provided for accounting.
All meter signals shall be considered in the metering systems which
included also the meters supplied by Package D.
Miscellaneous equipment
Conventional alarm annunciation system with fascia, installed in the CCR
for a small number of selected alarms of critical systems, e.g. 380kV,
230kV (200 alarms shall be the basis for the offer).

1.3.3

Spare capacity after completion of commissioning


At least 20% free channels of each I/O modules shall be available after
final commissioning for future modification.
At least 20% free space shall be available in all cubicles, junction boxes and
marshalling racks after final commissioning for future ad-on items. This
free space shall be distributed inside the cubicles in such a way that
additional terminals, equipment or modules may be added to any group of
controls. At least 20% spare cores shall be provided in each control and
monitoring cable. All spare cores shall be terminated.
Each module shall be sized such that no more than 60% of its installed
capacity is utilized during normal operation and shall not exceed 80% even
under extreme load condition.

1.3.4

Services
The Contractor shall provide all services required for a safe, reliable,
efficient and trouble free instrumentation and control equipment, complete
in every respect, without excluding other necessary services not mentioned
below. These services shall include but not be limited to:
design of all equipment to be supplied
examining of interface documentation
co-ordination and integration of all DCS equipment/functions supplied
under Package D, Part D-B10

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 31 of 178
Rev. 0

co-ordination and integration of all central control room equipment


supplied under Package D, Part D-B10 in order to ensure a uniform
layout and design of CCR
Detailed study of a specialized company for CCR design and layout
including the lighting, color, material, interior architecture etc.
considering carefully the ergonomic standards and the up to date control
design principles.
co-ordination and interfacing with external or separate systems like
Continuous Emission Monitoring System (CEMS)
Water quality monitoring system
Vibration monitoring system (VMS)
Plant Management System (PMS)
Asset management system / Field device tool
SCMS and SCADA system
Black start diesel generator
Fire and gas detection system and fire fighting system (FGAP)
HVAC Building management system
and others
co-ordination and integration of Package D related signals / data in the
PMS, VMS, asset management system / field device tool and CEMS /
water quality monitoring system
documentation of all equipment to be supplied including revision of
existing documentation where modified
programming of all digital equipment
testing in the Contractors/Vendors workshop and on site (FAT and SAT)
packing, transportation to site, unloading and proper storing
on time delivery of all documents needed for proper assembly
handling from site storage to the point of final installation
erection of all parts to be supplied
commissioning of all equipment
loop checks from field instruments to DCS operator station
trial operation
acceptance tests
The Contractor is responsible for the co-ordination of the interfaces and
overall design of all package control equipment or other control equipment
supplied by other sub-contractors and for making sure that the design of this
equipment and the submitted documentation is in line with the General
Project Requirements (Part-P-A3) and Technical Specification (Part-PB03), but it is expected that this co-ordination activities shall be done by the
supplier of the main control, instrumentation and monitoring equipment.
The Contractor (Package P) is responsible for the overall DCS layout and
design of the entire Power and Desalination Plant. Special attention shall be
drawn to all facilities (hardware and software) commonly used by Package
P&D.
FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 32 of 178

Rev. 0

As far as the final execution of the work is concerned all design data,
interlocking conditions, control loops and logic diagrams supplied by the
various sub-contractors shall be checked, verified and closely coordinated
with the other sub-contractors of the corresponding equipment. For this
purpose close collaboration with all sub-contractors supplying control
equipment shall be arranged.
All important design documents shall be submitted for approval to the
Engineer. The Contractor shall submit a detailed time schedule for the
drawing approval procedure at the beginning of the design phase.

1.3.5

Erection, cabling, wiring, labeling


The scope of this Contract covers complete erection, cabling and wiring of
all control, instrumentation and monitoring equipment and shall comply
especially with the General Requirements stated under Part P-B02 and PB03.
Connection of process stations and other central equipment supplied by
Contractor Package D, Water Production Island, to the data highway of
the overall DCS shall be done by Contractor Package P, Power Plant,
including all required cables and installation materials. However, the
redundant bus interface modules with their software and bus protocol inside
the DCS process stations of Package D plant shall be provided by
Contractor of Package D. Generally all necessary I&C cable and cable
trays between Package P and D shall be provided by the Package P
contractor. The connection works at the interfaces (e.g. at terminal strip in
the interface cubicles) of Package D shall be carried out by Package D
contractor.
The Contractor shall be, in all cases, fully responsible for the correct
installation and erection with regard to the measuring and control functions
of all the supplied equipment.
The Contractor shall make all necessary provisions for the site testing and
commissioning of the control and instrumentation systems which include
but shall not be limited to the following:
the test calibration of all instruments prior to installation. The
instrumentation used for calibration or check of operational
instrumentation shall carry a valid test certificate from an approved
authority and not from the contractor.
the functional test of instruments once installed;
the loop testing of all measurement and control loops;

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 33 of 178

Rev. 0

the site demonstration test required confirming that all control and
supervisory function conform to their respective functional specification.
All tests performed on site, including the results and deficiencies, shall be
recorded and the test protocols shall be submitted to the Engineer for
approval.
All cabling for the field equipment in the scope of this Contract, shall be
supplied, laid, labeled and terminated.
For the supplied field cabling all necessary cable routes, supporting
traywork and intermediate marshalling shall be provided. Marshalling
cabinets shall be provided in the central control building or in the LER.
A common system of earthing for cable armoring, cable screens, signal
cubicle earthing shall be agreed with Engineer.
All field equipment including local instruments, transducers, valves,
actuators, sensors, junction boxes, cabinets shall have nameplates with the
instrument tag number and descriptor. All equipment in CCR, LER and
LCR, control module, power supply, circuit breakers, fuses and control
systems shall have name plates. The nameplates shall be fixed to the
mounting plate, the mounting brackets or junction box. Loosely attached
nameplates by wires are not acceptable. Label material and writing shall be
selected to withstand the environmental conditions where they are mounted.
The label size and fixing place shall be selected to allow easy reading.
Inside the control cabinets, all control equipment shall be labeled.

1.3.6

Commissioning, trial operation, and acceptance tests


The Contractor shall be entirely responsible for the commissioning of the
DCS in conjunction with the plant system. Commissioning shall be carried
out in accordance with the commissioning procedures prepared by the
Contractor and approved by the Engineer.
The scope includes:
adjustment of control parameters, alarm limits and other adjustable
parameters;
optimization of closed loop control systems;
modification or correction of control functions during optimization, if
necessary, VDU displays, logs, etc;
optimization of alarm annunciation and SER functions and the associated
printing functions;
trial operation;

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 34 of 178

Rev. 0

performance of acceptance tests;


correction of any latent errors found within the DCS.
The general requirements regarding inspection and testing are included in
Part A5 of the Specification.

1.3.7

Documentation
All documents and information requiring checking and approval by the
Engineer in accordance with Part A3 shall be submitted.
All important design documents shall be submitted for approval to the
Engineer as per approved procedure.

1.3.8

Training
The Tenderer shall include in his offer the provision for training for all I&C
systems and equipment to the client's management, operation and
maintenance staff in accordance with the requirements specified under
Part A3.
The training shall cover the main control system like all DCS hardware and
software components, different PLC systems, CEMS, VMS, PMS, BMS or
equivalent.

1.3.9

Special tools and spare parts


All necessary spare parts (for five years operation), wear and tear parts,
maintenance equipment and special tools shall be part of the scope of supply.
The Tenderer should consider at least 10% of all different, installed I&C
components (CPUs, I/O Modules, fuses, transmitters, operator stations,
etc) or at least one individual piece of equipment as required spare parts in
the scope. All these spare parts shall be priced individually.
The Tenderer shall include a list with individual prices of all spare parts he
recommends should be held by the employer to enable the plant to be
operated efficiently considering maintenance and repair.
Any parts ordered must be strictly interchangeable and suitable for use in
place of the corresponding parts supplied with the contract works. Each
spare part item shall be marked with the equipment name and designation
number corresponding to the appropriate section of the operation and
maintenance manuals.
All required spare parts, wear and tear parts, maintenance equipment and
special tools (see also Part A3) shall be part of the scope of supply.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 35 of 178
Rev. 0

All special tools such as PLC programming tools, instrument calibration


tools, smart transmitters/ positioner communication tools, hand-held
calibration tools and electronic workshop tools shall be part of the scope of
supply.

1.4

1.4.1

Particular Technical requirements

General
These Technical Requirements shall be binding for the specified
Instrumentation and Control System (I&C) within the Scope of the
Contract. They do not relieve the Contractor of any of his responsibilities.
Should it not be possible to comply with specific provisions of these
Requirements, or if their observance would result in technical
disadvantages, the Contractor is obliged to point this out at the tendering
stage in the form of a deviation list which will be subject to review and
approval of the Engineer/Client. Once a final deviation list is approved at
the tendering stage, no other deviation will be accepted after Contract
Award. The Contractor is obliged to settle the design in accordance with the
Specification, considering the approved deviations only, in consultation
with the Engineer.
Equipment for the systems shall be planned, manufactured and installed in
accordance with this Specification, relevant laws, regulations, standards,
codes, guidelines and recommendations. The Contractor will be liable for
all defects resulting from non-observance of these.
The I&C shall be so designed, that full control and supervision of the
complete Power and Desalination Plant (Package P & D) shall be possible
from the CCR whereas additional local operation of the GTGs shall be
possible from LERs located in the main plant area adjacent to each GTG.
The I&C within the scope of supply shall permit complete and centralized
operation and monitoring of the plant, and the automation shall provide for
the following:
normal automatic operation of the plant, for example, during changes in
the boiler, turbine or desalination loads;

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 36 of 178
Rev. 0

all functions for protecting plant equipment shall perform, in all cases,
reliably and without manual intervention. The plant protection system
shall prevent the units from reaching impermissible loading conditions,
and, should any faults arise, shall keep their consequences within the
specified limits. The same applies for switch-on and switch-over
functions of redundant and reserve equipment with the possibility for
pre-selecting the operating equipment.
the plant shall be put into and taken out of operation by manual initiation
of the functional group controls of all subsystems. Start-up and loading
times shall be kept to a minimum consistent with pre-set thermal stress
limits. All drives required for start-up and shutdown of the units in
accordance with the specified control philosophy shall be remotely
controlled from the CCR.

1.4.2

Structure of control functions


In order to meet the requirements of plant safety, availability and
transparency of plant operations, the automation equipment shall be
hierarchically structured into automation levels. By means of this
hierarchical structure of the automation installations, the tasks of each level
shall be clearly assigned. Interfaces shall be readily apparent.
The components of the subordinate level shall be so designed and
configured within the system, that they can fulfill their intended actions
without requiring the control function of their supervisory level. The
defined process variables (set-point conditions) shall be achieved and
maintained by means of the control installations assigned to this automation
level.
For this plant the Individual Drive Level, Sub-Group-Level, Group Level,
Unit-co-ordination Level, and Plant-co-ordination Level shall be foreseen
(see Principal Hierarchical Structure at Annex: P-C13-3)
Drive level
start, stop, protection for individual drives. Position control for regulating
actuators.
Sub-group-level
the combined or sequential control of associated drives such as main
pump drives and associated discharge/suction valve drives. Pre-selection
and stand-by/automatic switchover facilities. Closed loop control
functions.
Group level
sequential control co-ordination of sub-group controls.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 37 of 178

Rev. 0

co-ordination of sub-ordinate regulating function operating in a cascade


configuration.
Unit co-ordination level
start-up, shut-down, on line co-ordination and protection of the units. Set
point generation. Block controller shall be included for the power blocks.
Plant Master Controller (PMC)
On top of the control hierarchy a plant master controller should be
installed to control and monitor the whole plant electrical power
generation and water production.
In general, the operator shall have direct access to all five control levels
through the VDU based Human Machine Interfaces (HMI) located in the
CCR. Manual intervention shall be possible at any stage of operation and
the sequence of control shall be able to continue at the correct point of the
program in the correct mode when returning to automatic control. No
protection / interlock bypass shall be allowed.
Unit cross operation shall be implemented for the package P and D (Power
and desalination plant).
Plant Management System (PMS)
A PMS shall be provided with the following functions and features:
operator guidance giving him the most appropriate configuration of
running plant to meet the predicted and current power and water
demands with the given available plant.
a visual display of the measured plant efficiency deviation from the
reference plant efficiency .
alarm warning when the operational configuration of the plant must be
changed to maintain adequate control margins.
an off-line function permitting the operator to explore the influence on
plant output, efficiency and control margins of different plant operating
configurations.
Plant optimization package
All metering equipment data shall be transferred to the PMS
All potable water metering and the quality monitoring system data shall
be transferred to the PMS

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.3

1.4.3.1

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 38 of 178

Rev. 0

Field equipment

General
All field equipment supplied under this Contract shall comply with the
relevant requirements of Part P-B03.
Local direct reading instrumentation and controls not forming part of the
central control and supervisory system shall be provided as follows:
for general plant start-up preparation
for local plant systems which are not required for automatic start-up and
require no direct remote supervision or control
for the indication of the operational state of the plant where remote
monitoring instrumentation is not required
for local plant supervision, testing and maintenance
where required for the convenient checking of other instrumentation (e.g.
pressure switches)
wherever stipulated by relevant codes.

1.4.3.2

Settlement Metering Equipment


The proposed measuring, instrumentation, sampling and analyzing
equipment shall be described by the Tenderer and information on type,
detection principle, range, accuracy and sensitivity of the instrumentation
shall be provided in its Tender.
The main data on scope of supply and type and design of equipment and
instrumentation of the metering and monitoring system are to be stated in
Part P-A4.
Reference is made to Annex P-C13-4.

1.4.3.2.1

Electricity metering
The settlement and back-up electricity metering equipment shall comply
with the requirements of the Metering Code, as stated in The Saudi
Arabian Grid Code in its latest edition.

1.4.3.2.2

Fuel metering
The fuel metering system (settlement and back-up) shall be designed and
constructed along Saudi Aramco standards.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.3.2.3

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 39 of 178
Rev. 0

Water metering and quality monitoring system


Potable water output to Maaden will be metered and quality monitored in
the supply line downstream of the water tanks. The metering equipment is
located in pumping station PS1 area and shall be supplied by Package D.
Drinking water output to Substation shall be metered in the supply line. The
metering equipment is located upstream relevant interface point within the
plant fence and shall be provided and installed by Package D.
Distillate water output to Maaden will be metered and quality monitored in
the supply line downstream the distillate header and will be supplied by
Package D. The metering equipment is located at the fence of RAZ
Phase I area.
Water output shall be metered in line with the requirements of the latest
revision of ISO 4064 / OIML R49 which applies to water meters
irrespective of technology.
The metering equipment requirements for water transfers are dependant
upon the maximum water flow rate. These capacities are categorized and
defined as follows:
W1 for maximum flow rate greater than 100 m/hour (this will typically
be for pipeline DN greater than 100 mm bore)
W2 for maximum flow rate less than (or equal to) 100 m/hour (this will
typically be for pipeline DN equal or less than 100 mm bore)
Accuracy requirements:
Condition
Flow rate range *
Q2 to Q4
Q1 to Q2

W1
1%
4%

Meter Accuracy
(Supplier certified)
Q2 to Q4
Q1 to Q2

0.5%
3%

Limit of error
Metering system
W2
2%
5

1%
3%

(*) Q1 minimum flow rate, Q2 transitional flow rate, Q3 permanent flow rate, Q4 overload
flow rate, for further information see OIML 49.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.3.2.4

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 40 of 178

Rev. 0

Automatic meter reading system (AMR):


The redundant automatic meter reading system shall collect and validate all
metering signals. The data collection and validation process shall perform
the following function:
Establish robust billing data for each media/supply;
Identify potential metering equipment and communications links
failure/faults; and
Identify unauthorized interference with or manipulation of settlement
data.
The system shall be capable to be used for the daily collection of all
electronic settlement data from all meters. All electronic data relating to the
settlement process shall be stored in a secure manner.
After preparation the data shall be transferred to the commercial billing
system and the Plant Management System (PMS).

1.4.4

1.4.4.1

Distributed control system (DCS)

General
The plant shall be monitored, controlled and safeguarded by a distributed
digital control system. That shall include all gas turbines, steam turbine(s),
steam/feedwater/condensate systems, desalination units and common
equipment.
Each piece of vital equipment such as GTGs, HRSGs, ST, etc. shall be
provided with its own protection system that is approved for the application
by official authorities to the approval of the Engineer. These systems shall
bring the plant equipment in a safe status in case of major or catastrophic
failure of the DCS. The protection systems will be monitored and controlled
by the DCS using a serial link but the control (e.g. emergency shut-down)
shall also be possible via conventional (hard-wired) control interface (pushbuttons) located in CCR, LERs (for GTGs) and in the field. Preferably
protection systems shall be integrated part of the DCS.
This sub-section covers the minimum requirements for the design and
fabrication of the DCS. The Contractor shall be responsible for all
hardware, software, interfaces to other systems, system testing,
documentation, delivery, installation, commissioning, supervision and field
support and any other services as required for the procurement of the system
as defined within this Specification.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

what is mean of

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 41 of 178

Rev. 0

The design of the DCS shall conform to the state of the art, and shall already
have been proven in at least three other similar plants (combined cycle
power and high pride desalination plants) for more then three years. For all
control, instrumentation and monitoring systems the latest versions of
proven hardware, firmware and software modules, which are available on
the date of shipping, shall be supplied. This is subject to the approval of the
Engineer. However, prototype equipment will not be accepted.
Only high quality systems from reputable suppliers preferably with
established local back-up for maintenance and after-sales technical and
spares supports shall be offered.
For the system offered, a guarantee shall be given that spare parts will still
be available at least 15 years after commissioning of the plant, and that pincompatibility of modules shall be maintained over this period.
The system shall be designed to allow an easy extension in case of
subsequent modifications on the controls and the associated signal
processing equipment for hardware and software.
As the process of the power plant is divided into sub-processes performing
the functions in their areas largely independently, the same division of
functions shall also be maintained in the DCS.
The DCS system shall achieve the functions of data acquisition, signal
conditioning, closed loop control, open loop control, calculation, alarm
processing and annunciation, sequence of event recording, historical and
real time trend recording, graphic display of process and communication
with other devices/systems. All equipment shall be synchronized by the
master clock system.
Electrical protection and process protection shall be realized in the I&C
system.
The architecture of the DCS shall accommodate both functional and
physical distribution of the hardware and the software throughout the site
while allowing system wide access to the distributed data. It shall be
possible to display, operate and control any equipment/ system of the plant
from any operator station.
System configuration shall be simple and flexible with regard to reconfiguration of loop connection and display formats to suit changes in
operational requirements. System software security, including data base
configuration, controller loop tuning parameters shall be accessible by a
access security system like finger print reader, keycards with PIN, password
or similar. The guideline of HCIS has to be considered.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 42 of 178
Rev. 0

All systems shall require minimum maintenance or routine calibration, and


shall have comprehensive off-line and on-line self checking and self
diagnostic capabilities including self-test failure alarms etc. for all control
modules and nodes. Comprehensive status information recording and
reporting shall be provided for all systems allowing for efficient fault
detection and tracing.
To satisfy the unit cross-operation the system shall offer the possibility to
use technology like access to the DCS with WEB-Browser functionality
from additional workstations to all DCS-operated plant/ systems. WEB
server(s) with the related software as well licenses (if any necessary) for
additional workstations/ PC have to be considered. Access shall be
password protected.

1.4.4.2

Availability and redundancy


The highest demands are placed on the control, instrumentation and
monitoring equipment with regard to availability, plant safety and
reliability. No common single point of failure must exist in the systems. All
vital system functions that can affect large part of the plant operation shall
be duplicated with automatic bumpless/smooth switch over and fault
reporting and diagnostic facilities. Control system signals shall be dual
redundant and protection systems shall be triple redundant. A single fault
shall not cause a trip or loss of performance and shall not cause loss of the
protection system. The redundancy shall be complete including the
processors, interfacing modules, power supply modules, station bus etc.
The data highway system shall be single fault tolerant and separated for the
different units of the plant (see Annex P-C13-1). One failure in the data
highways shall not reduce the availability of any of the system components
or degrade system performance. Failure recovery shall be smooth, bumpless
and automatic. Connection of additional equipment shall be possible on line
without disrupting operation. Any data communication failure shall not
disrupt process control.
The assignment of the various displays on the VDUs shall be flexible and
simple, so that in case of failure of a VDU, any remaining VDU can take
over its function.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 43 of 178

Rev. 0

The power supply sources and configuration for all the DCS equipment and
process stations shall be dual-redundant. However, in case of total power
interruption for the control system the DCS shall:
set all outputs (analogue or digital) to a programmed fail safe position
retain the system (control) configuration or execute an automatic restart
(reload) without operators intervention while maintaining the fail-safe
status on all outputs. Control shall be initiated by the operator (all
controllers shall be manual and all sequences, motors etc. stopped unless
otherwise specified).
In case of major or catastrophic failure of the DCS, a safe shut-down of the
plant must be guarantied. To fulfill this requirement the fail safe concept
(normally energized principle) will be used and plant protection equipment
will be fed from DC battery systems and/ or UPS as appropriate.
The redundant I/O or automation processors (CPU) shall be installed in
different rack and shall be supplied by different power supply. The I/O
modules used for control and protection shall be designed in redundant
hardware.
Distributed installation should be taken into consideration when assigning
the hardware to the process plant components. The system shall be
structured to reflect the redundancy provisions of the Plant so that no single
fault within the system will cause an operational disturbance or spurious
operation or make a standby plant unavailable. This means among others
that control functions of redundant equipment should not be installed in the
same hardware module or rack.
The possibilities of the redundant design shall be taken into account when
planning the system architecture. It is essential that the following parts be in
redundant design, but not limited to:
central modules whose failure would result in the loss of extensive or
critical functions;
the DCS communication system;
the DCS process control station modules and components;
components for operation and monitoring (workstations);
power supply;
any other element a failure of which will disable large portion of the
plant or create an unsafe operating condition.
The I/O modules in the DCS process control station shall be provided
redundant as follows:
Control system signals shall be dual redundant and protection system
signals shall be triple redundant.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 44 of 178
Rev. 0

All analogue and binary output modules and drive modules for open-loop
and closed-loop control shall be provided redundant for each module
regardless of the redundancy in the field equipment/devices.
All analogue and binary input modules shall be redundant following the
redundancy in the field equipment/devices such that each of the
redundant field equipment/device shall be connected to a separate
module and rack.
If the input signal is sourced from a single equipment/device, which is
important for the reliability and availability of the unit/system, it shall
then be connected to redundant input modules or shall be multiplied and
connected to two separate input modules if the DCS does not support
redundancy in the input modules as an inherent characteristic of the
system.
As far as the system and the components are concerned internal safe design
shall be applied. It means that no single failure of system elements, on-line
change of I/O modules and interface modules or external influences (shortcircuits, wire break, noises, etc.) will cause erroneous operation or
deterioration on any hardware or software system. The circuitry shall be
protected against interactions between modules and systems.
No single control system fault shall directly cause any of the following
conditions:
complete loss of generation from one GTG/HRSG/STG or desalination
unit;
loss of communication between the HMI in the CCR and the plant
control system such that safe shut down and on-line operation cannot be
maintained from the CCR.
Special precautions shall be taken to provide maximum reliability for
"Vital" control loops whose failure could result in major financial losses or
threaten human life. These measures shall be implemented as 2 out of 3
voting (including primary elements) in redundant processor units or as a
redundant process interface.
In case of a hardware failure within the automatic controls, the
corresponding process station shall be automatically switched-over to the
redundant unit and shall not degrade the system performance or cause any
operational disturbance. Operating station is not automatically switchedover.
In addition to the above measures, for areas of the plant in which proper and
reliable functioning of measurements and process control equipment is
essential for the prevention of human injury or death, fail-safe and typeapproved systems are employed.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 45 of 178

Rev. 0

All control subsystems shall have a demonstration or calculation of the


MTBF. The Contractor shall provide MTBF figures related for each
subsystem and the overall figure for the proposed system.

1.4.4.3

General hardware requirements


The DCS shall mainly consist of automation level with geographically
distributed process control stations and a plant bus system to connect all the
process control stations together in a single fault tolerant data highway
structure, servers and process coupling devices, which connect the plant bus
to the operation level bus system, which shall also be provided in a
redundant single fault tolerant structure and the operation level with the
operator stations and other necessary equipment.
In the interest of a neat and clear space saving layout of installation, easy
maintenance, simple starting-up, operational checking and fault-recognition,
a control, instrumentation and monitoring system made up of a small
number of matched standard subassemblies with plug-in modules shall be
provided. The instruments and components used, shall be made of highgrade materials and their data shall be based on the most unfavorable design
conditions (worst-case design), with regard to temperature, voltage, RF
interference etc. It shall be possible to replace individual modules during
plant operation without causing a trip or any disturbance of the plant. All
replaced control module and nodes connected to the DCS network shall
boot-up automatically upon switching the power source ON.
The design of the system hardware shall be distributed, based on the main
units of the plant, i.e. for each main unit of the plant (boiler, turbine etc.)
separate process stations shall be provided. Dedicated DCS process stations
shall be provided for protection that shall be physically and functionally
segregated from the process control stations.
The plant general auxiliaries shall be distributed in separated control
stations, so that failure of one control station shall not lead to total plant
loss.
The process stations shall be supplied as fully assembled and functional,
pre-wired, programmed and tested, in lockable steel cabinets, fully
accessible front and rear.
The uninterruptable power supplies for all vital equipment such as process
stations, data highway equipment etc. shall be duplicated with a static
automatic changeover switch. A power failure alarm shall be provided.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.4.4

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 46 of 178
Rev. 0

Software requirements
The system software shall contain functional software modules that will
perform the basic control, monitoring and calculations. Function blocks in
the form of standard software modules shall be available. These modules
shall be stored in a non-volatile memory (Firmware).
The function blocks will be linked to build the required control functions.
Control blocks should have individual control data base. Implementation of
the control functions shall be easily possible using readily understandable
configuration procedures. All configuration modifications shall be
implemented on-line.
The library of software modules shall contain all the functions required for:
closed loop control, such as PID, analogue and step output, multivariable control, bias, cascade control, adaptive gain, etc.
standard software modules for motor/ actuator control logic shall be
available, covering the functions described under 'Drive control' in clause
'Open loop control'.
standard software modules for sequence control, such as sequence header
and step modules.
standard software module for the selection of the operating and stand-by
units and automatic change-over from a faulty unit to the selected standby unit.
calculating functions such as generator capability curves, operating
characteristics, etc.
The configuration control software shall include provisions for setting each
loop's scan rate. The configuration software should also be able to be
implemented by means of fill in the blank templates or other user friendly
approaches that allow the user to easily create and modify control strategies
by lining the predefined algorithms.
The DCS system shall have provision to develop sequences and shall be
capable of being programmed directly from logic flow charts using an
operator oriented language.
The system shall be furnished complete with working programs. All
software design, development, debugging, reprogramming tasks and final
configuration back ups which are required to achieve operation in
accordance with this specification shall be provided and shall be
Contractors responsibility.
Test software for on-line and off-line test shall be provided with the system
and shall conform to the same standards as system software supplied with

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 47 of 178

Rev. 0

the system. The software shall ensure that there is no risk of corruption of
operational data in this mode of operation.
Backup software must be practically tested and certified.

1.4.4.5

Process station

1.4.4.5.1

General
The process stations shall consist of a redundant microprocessor based
system or multi-functional computerized controllers with the appropriate
process interfaces. They shall contain all functions that are necessary to
keep the process running without operator's intervention and independent of
the availability of a workstation or the state of data highway. The cubicles
shall be accommodated in related LERs or in the CER.
The main functions of the process stations shall be acquisition of digital and
analogue signals from the process, signal conditioning and processing,
output of digital and analogue signals, closed loop control and open loop
control. All system clocks shall be synchronized. This includes also
synchronizing of external systems (e.g. burner management system if not
realized in DCS).
Control loops that obtain data via the data highway shall revert to safe state
on data highway transmission failure.
In order to ensure high availability, the hardware shall be functionally
distributed, i.e. a limited number of inputs and outputs per module and
individual modules for closed loop control, functional group control and
drive control, so that any failure shall have limited effect.
Failures shall be indicated by alarms and LEDs, and logged, including the
hardware address of the failed module. All process and C&I alarms shall be
provided with proper texts to indicate the nature of the fault.
The DCS process control station shall be provided as single fault tolerant
and shall be structured as entirely redundant in all aspects including the
processor modules, power supply modules, communication modules,
interface modules, I/O bus, I/O modules, relays, electronic and electrical
components, etc. The hardware shall be of utmost reliability and shall have
modular construction. Each module shall be of plug-in, on-line replaceable
type.
The DCS process stations shall be loaded maximum to 60% during normal
operation and maximum of 75% during operational disturbance

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.4.5.2

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 48 of 178
Rev. 0

Signal input and output processing


Dedicated hardware modules for input and output signal conditioning shall
be provided. The process I/O shall be able to accept signals from
commercially available signal sources such as 1 - 5 V DC, any kind of RTD,
thermocouples, mA signals and digital signals. Conversion into engineering
units and linearization of the signals shall be possible. The input modules
shall have line break monitoring facilities.
The system I/O shall be designed to meet the following general
requirements:
The DCS I/O shall be of intelligent microprocessor based I/Os with real
time tagging/ stamping
The I/Os shall have a self-diagnostic system.
Any input shall withstand a steady signal of 24 V or 10 times normal
input, whichever is the greater. Overload of any channel shall not effect
any other
The process I/O operation shall not be affected or damaged by ground
faults of field equipment
The process I/O operation shall not be damaged by a short circuit in the
field wiring
All field signals (analogue and digital) shall be hardwired to the process
interface (I/O)
When assigning occupancies to modules process redundancies shall not
be nullified, i.e. I/Os from redundant process equipment shall be
accommodated in different modules, preferably in different process
stations.
A selection of scanning rates shall be applied, which shall in all cases be
adequately high to ensure safe and efficient control of the plant.
It shall be possible to remove all I/O modules without disconnection of
plant cables.
High insensibility against noises and other disturbance signals (e.g.
walkie-talkies). The requirements of EN 55011have to be fulfilled, at
least.
High insensibility against over-voltage (IEC 60 255-151 class II)
20% spares channel shall be available in each I/O module.
Drive protections shall be implemented in the I/O level.
The I/Os shall be individually isolated for each channel.
The outputs of analogue and binary output cards shall be short circuit proof.
To compensate for possible hardware failure on testing, an 'override
function' shall be available to allow 'forcing' of the measurement associated
with a specific hardware input point (analogue or digital) or to mask
changes to an output (digital).

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 49 of 178

Rev. 0

A mechanical method of preventing incorrect positioning of I/O type


modules in the rack shall be provided.
For plant/equipment locations far from the CCR building such as seawater
intake, fuel gas system, etc., the DCS process control stations of that plant/
equipment shall be located in the Local Electronic Room (LER) at the
related plant/ equipment building connected by the DCS plant bus system.

1.4.4.5.2.1 Analogue I/O


The following minimum requirements shall be considered for the analogue
I/O modules:
For the analogue inputs the system software shall check for signal
integrity and if the input signal exceeds 5% of the specified range of the
zero and full signal range the measurement shall be declared invalid.
Analogue input modules which provide also the power supply for the
field transmitters will be preferred
The analogue output modules shall provide 4-20 mA DC, capable of
driving up to 600 Ohms total loop resistance. 24 V DC loop power to be
provided by the DCS
Each analogue output shall be short circuit proof
Normal thermocouple linearization shall be accurate to 0.25% of the
measured temperature. All type of thermocouples linearization shall be
available. For thermocouple signals automatic compensation of cold
junction temperature shall be provided. Cold junction compensation in a
special cold junction compensation box outside the DCS is acceptable
Linearity shall be within 0.2% of all inputs.
For analogue 4-20 mA inputs, the input resistance shall not exceed
250 Ohm.
Analogue inputs shall contain over range protection circuits to protect the
equipment from ground faults or high voltage either in common or
normal mode. Ground fault detection alarm shall be provided
Analogue signals shall be measured at a rate of 2 scans per second or
higher and shall be programmable per channel
Input modules for pulse inputs should be available

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 50 of 178

Rev. 0

1.4.4.5.2.2 Binary I/O


The following minimum requirements shall be considered for the binary I/O
modules:
Binary signals shall be measured at a rate of two scans per second
(normal) up to 20 scans per second for fast events.
A resolution of 1ms for all input digital signals with time stamping at the
input module as an inherent characteristic feature of the DCS.
The binary input modules shall be provided for 24 V DC.
Sense voltage to field contacts and input for proximity switches shall be
provided by the DCS.
Inputs shall be individually isolated.
The binary input modules shall be able to supervise the circuit integrity
and they shall ensure that the current through the closed contacts of
binary transmitters shall be at least 3 mA.
The digital output modules shall provide dry contacts rated at 2 amperes,
24 V DC and shall be selectable as normally open or normally closed.
Wire break detection.

1.4.4.5.3

Closed loop controls

1.4.4.5.3.1 General equipment design guidelines


The control valves and actuators shall comply with the general technical
requirements (Part P-B03 of this specification). The analogue position
feedback signal shall be used for control of the valve position.
The electric valve positioners shall be of solid state type (no contacts), plug
in/ drawn out units and shall be accommodated in cubicles in the related low
voltage switchgear room.
For each final control element (FCE), it is preferred that automatic singlechannel closed-loop control loops shall be provided to ensure that a failure
in one loop will have only limited effect on the plant. This does not apply if
the control loop hardware is in a fully redundant arrangement.
The closed-loop controls shall permit control actions from the open-loop
control functions or systems, such as automatic MANUAL/AUTO switchover and controlled OPEN/CLOSED actions of the control valve, and shall
issue corresponding checkback signals to the open-loop control.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 51 of 178

Rev. 0

Control loop gain shall be automatically adjusted through parameter control


when the number of effective Final Control Elements (FCE) changes, e.g.
with one or two pumps under closed-loop operation.
All closed loop controls shall be designed in redundant. The system should
permit the high/low limit of either controller output variable or set point of
each PID controller to be set individually. The high/low limit should be
indicated on the controllers faceplate.
In the event of transmitter failure or a fault in the measuring transducer, if
not in 2 out of 3 selection, the design shall permit the following options:
switch-over to a second transmitter or MAX selection with double
measurement of the same variable
control with a default value
switch-over to manual operation.
In case of failure of the auxiliary power supply or withdrawal of a plug-in
element, the control valves shall retain their position, or if necessary
traverse to a position which is safe for the process. Faults in the power
supply shall not result in any unwanted or dangerous switching actions.
Besides the modulating control function PID, the controllers shall contain
facilities for bumbles transfer, anti-reset windup, auto/manual switching,
parameter scheduling, cascading, feed forward control, signal exchange
with open loop controls, etc. Advanced control algorithms shall be provided
wherever they would result in advantages of process control. Due to a better
control quality self-adjustment of control parameters, use of state controllers
also with observer, adaptive controllers or multiple input multiple output
controllers shall be available.

1.4.4.5.3.2 Cascade control


The tracking of cascade loops has to be automatic so that the manual
balanceless and bumpless operation can be achieved at any time without
having to specially configure the signal tracking.
When a controller in a cascade hierarchy is turned off (cascade open) or to
manual mode, the upper level controllers shall sense the mode change of the
controller. The output signal of the upper level controller shall then track
the set point of the controller at the next lower level automatically.
When a controller output reaches a maximum or minimum limit the primary
(master) controller shall sense the condition (set point limits) of the
secondary (slave) controller and shall stop the adjustment of the set point of
the secondary controllers.
FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 52 of 178

Rev. 0

1.4.4.5.3.3 Feed forward control


In case of disturbances, feedforward control shall take place in order to
minimize the disturbance effect. For this, suitable control, instrumentation
and monitoring functions have to be provided, taking also into consideration
the status and availability of components. If useful, also automatic load
shedding shall be initiated by the control system.
The system shall allow implementation of feed forward control applications
and ratio control applications. Standard algorithms like lead/lag logic, ratio
control and free programming capability shall be provided. Moreover,
facilities to activate and deactivate feed forward and ratio controls have to
be provided.

1.4.4.5.4

Open loop controls

1.4.4.5.4.1 General
Open loop control shall be hierarchically organized and shall contain
individual drive controls and sequential controls for drive group level and
functional group level and unit co-ordination as well the function of plant
master controller (see Clause P-B13.1.4.2). In addition to these control
levels the protection and safety interlocks of the drives shall be provided by
the open loop control system.
As far as possible the design shall be so decentralized that a disturbance in
the control system shall not affect more than one sequence (e.g. one
feedwater pump). In the case of a higher degree of centralization a
redundant configuration is mandatory so that the controller shall
automatically switch to a back-up controller in case of failure.
To allow for the process redundancies 'Functional distribution' shall be
provided i.e. the grouping of the functional subgroups controlled by one
common redundant microprocessor shall be done in such a way that the loss
of the controller shall not cause any dangerous operational conditions or
plant shut-down. For example, if the control of feedwater pump 1 is
disturbed, the control of feedwater pump 2 has to be still available.

1.4.4.5.4.2 Sequential drive group and functional group control


Sequential Group controls are to be provided for start-up, operation and
shut-down of associated functional units and drive groups, i.e. it shall be
possible to start or stop main aggregates (e.g. feedwater pumps) with all
associated equipment by issuing one command.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 53 of 178

Rev. 0

To indicate the sequence progress special sequence displays shall be


provided. Via these displays the sequential steps within the individual
sequential programs and 'missing criteria' (error condition) shall be
displayed on the VDU. Sequences including time related events shall
include a time-out alarm indication.
Group controls shall be capable of being switched 'on' and 'off' and shall
have defined commands for 'automatic' and 'manual'.
Any faults in the control system that could cause the control sequence to
stop have to be confined to one control sequence.
Any faults in the control system or in the plant equipment shall lead to an
automatic changeover from a faulty unit to an appropriate standby unit.
If a sequence control is stopped for any reason it should be possible to:
resume automatically on any step in function of the prevailing plant
conditions
resume manually on any step in function of the prevailing plant
conditions
For this reason jump conditions shall be foreseen. Before entering in the
step the sequence logic shall check the status of the jump condition. If the
jump conditions are fulfilled the respective step commands will not be
executed and the control sequence will be continued with the next step of
the sequence. Jump conditions shall not violate any protections or process
safety.
In case if the sequence control stopped and the plant went for a safe shutdown the cause of the failure shall be indicated in the DCS.
Following functional groups shall be considered for the following but not
limited to:
Gas Turbines
The GTs shall have automatic sequence controls for start up,
synchronization and initial loading, further for normal and emergency shutdown, including all necessary function group controls also for all auxiliaries
and performing a complete automatic start-up or shut-down of the GT under
due consideration of the thermal stress and ranges of vibration.
Diverter Control

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 54 of 178
Rev. 0

The diverter at exhaust stack/ boiler inlet shall be operated automatically


and for emergency reasons manually from the central control room with
continuous position indication.
HRSG and Water-Steam Cycle
The start-up controller controls the individual function groups of the HRSG,
like burner, vent and drains, recirculation pump, etc. and the water-steam
cycle, like condensate system and feedwater system with the all the pumps
and drives belonging to the system.
Steam Turbine
The ST shall have automatic sequence controls for start up, synchronisation
and initial loading, further for normal and emergency shut-down, including
among others the following function group controls:
Turning-gear operation
Oil supply
Warming up and draining system
including all auxiliaries and performing a complete automatic start-up or
shut-down of the ST under due consideration of the thermal stress and
ranges of vibration.
Pumps
Function groups shall be provided for all main pumps, like FW Pumps,
Condensate Pumps, Circulation Pumps, Cooling Water Pumps, etc.
All the pumps shall be equipped with step logics for remote control of startups and shutdowns.
Other systems and auxiliaries
All necessary function group controls shall be provided, which are
necessary for the intended automatic start of the Plant, like fuel supply,
compressed air system, main cooling water system, etc.
The function group controls with their sub-controls respectively individual
drives shall be controlled by the start-up controller.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 55 of 178

Rev. 0

1.4.4.5.4.3 Drive control


Every remote operated drive or circuit breaker shall be controlled by means
of a drive control module as the standard interface between the DCS and the
switchgear. Drive control in the I/O level of the DCS shall be utilized for
drive control equipment such as motors, pumps, motorized valve, solenoid
valve, and actuators etc.
To this module all orders i.e. from the operator station via the keyboard,
step signals of the control sequences, interlocks or protection as well as all
check-back signals of the drive or switchgear shall be connected. After the
processing of these signals the control module shall issue the order to the
switchgear via I/O cards and coupling relays. Drive control in the I/O level
of the DCS shall be utilized for the motorized control actuators and the
protection. The functions of the drive control shall be integrated in a
dedicated multi-channel hardware module.
The Contractor shall describe in his offer the hardware and software
modules he intends to use for the drive control.
Drive control modules shall meet the following minimum requirements:
inputs for hardwired manual, automatic and interlock signals. Protection
signals shall have priority over other commands. If activated they shall
block the ON/OFF commands up to acknowledgment. There shall be a
visual display of this blocking action and it shall be capable of
acknowledgment. In cases where it is necessary, for safety reasons, to
provide a local emergency stop push-button, the operation of this pushbutton shall have the same effect as the operation of other protection
devices
dedicated outputs for ON and for OFF commands
in the event of on/off command arising simultaneously or commands
repeating alternately, provisions must be made to lock out these
commands
stop command of the actuator upon triggering of the stroke or torque
limit switch
signaling of drive position and operation status (e.g. local operation)
selection of local or remote operation mode
monitoring of any changes in status not brought about by the drive
control module
selective fault annunciation for drive connected faults such as differential
signals, i.e. the position of the drive is in opposition to a given command,
or trip by fault in the switchgear
processing time from incoming signals to outgoing commands shall be
less then 20 ms, in order to stop torque seated motor valves

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 56 of 178

Rev. 0

maximum of four drives control shall be implemented in each I/O


module
In the event of any tripping or failure, a group signal must be passed via the
annunciation equipment and the fault status must be displayed individually
for each drive in the appropriate operation display on the operator station.
In addition to the control via the VDUs it shall be possible (if necessary by
process requirements or requests of norms/regulations) to provide additional
local start/stop push-buttons. Local push-buttons shall be connected to the
respective drive control module in order to ensure that the same starting
conditions are achieved before an item of plant can be started from either
local or remote position. For this case on/off or open/closed shall be
indicated at the control place, locally.
The local controls shall act only if selected by a local/remote key on the
local control point. The local/remote signal shall be sent to the drive control
where the selection of the control mode shall be processed. If local
operation is selected, it shall be displayed on the VDU in the CCR and no
operation from other place shall be possible. The command from the
emergency stop push-button of the local control point shall be transmitted
directly to the switchgear.
For unidirectional motor drives (pumps, fans) the issued command shall be
an impulse (e.g. reset by switchgear feedback signal) which shall be
memorized in the switchgear by latching, so that the interposing relays shall
not be permanently energized.
The control command shall be reset by stroke end or by torque switches for
reversing drives (actuators for valves, dampers). Drives/actuators with
intermediate positions shall be designed either with a stop command or for
inching operation.
The interposing relays shall be housed in the motor control centers of the
switchgear and are to be considered as part of the open loop control system.
Solenoid valves that do not exceed the drive control module power limit
may be energized directly from the drive control module.
Individual controls of reversing drives shall be so designed that upon
withdrawing of the control cable plug connector the drive actuator will stop
and it will not be possible to set it in motion.
The control commands from the drive control module to the switchgear
shall be transmitted to the switchgear through two interposing relays at 24 V
DC, one for the ON and one for the OFF command. The coils of the
interposing relays shall be connected with free wheeling diodes.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 57 of 178

Rev. 0

An automatic restart of equipment following a brief interruption of power


supply (e.g. bus transfer) shall be provided by the control system (e.g. logic
for the specific restart sequence has to be provided.)

1.4.4.5.5

Protection and safety interlocks


To protect individual units or parts of the plant, interlocks are to be formed
in accordance with process criteria, which can be either active or passive
depending on their functions.
Active interlocks shall automatically disconnect units or parts of the plant
before they reach a critical operating condition or shall start certain units
(e.g. stand-by) in order to avoid a critical operating condition. In addition,
such dangerous conditions must be immediately indicated to the operating
personnel by means of an alarm.
Passive interlocks are intended to prevent operational errors or wrong
commands from being carried out in the event of selective faults in the
automatic control.
Active and passive interlocks must not be capable of being switched off
operationally from the control room. All protections have to work fully
automatically and independent of the operator and always have to be
effective for all procedures (manual, partial automatic, fully automatic). All
protections and interlock signals shall be implemented in hard-wired.
After a stop or close action by protection, the restart of the equipment shall
be possible only after the fault is rectified and the protection signal is reset.
Simple cancellation of protection signal by start command shall not be
possible. The protection action and the operator reset shall be recorded by
the DCS with real time stamping.
An evaluation to determine the appropriate Independent Protection Layers
(IPL) to control hazards is necessary. Safety Instrumented Systems are
intended to provide protection for people, property and the environment
against deviations in the processes. IEC 61508, IEC 61511 shall be followed
to determine, design, and build IPLs and especially the Safety Instrumented
Systems.
Every safety related loop has to be verified according to the standard IEC
61508, IEC 61511 that the requested and necessary Safety Integrity Level
(SIL) is fulfilled for the individual loop. The Contractor has to assess all
safety related loops to ensure compliance with the related requirements and
has to submit the report of these studies to the client.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.4.5.6

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 58 of 178

Rev. 0

Interlocks for alarm annunciation


Some alarm annunciation are of interest to the operating personnel only if
the corresponding part of the assembly or units are in the start-up, operating
or shut-down condition. These linked annunciations are usually made up of
signals showing conditions and process monitoring criteria. The alarms
shall be inactive when the relevant unit or equipment is supposed to be out
of operation.
Different tones of alarm annunciation shall be implemented in the operator
control desks for different units.

1.4.4.6

Data highway communication


The distributed controller modules shall communicate with the operator
stations and with each other through a data highway. The data highway shall
be a highly reliable and high speed bi-directional single fault tolerant data
highway system of fiber optic cable capable of data transmission over a
distance of a minimum of 1000 m without any repeater. However, extension
of the data highway shall be possible.
The communication system shall have all necessary fault diagnostics. The
data transmission shall be continuously supervised. Any errors should be
alarmed and recorded in the CCR.
The data highway shall be single fault tolerant. Under no circumstances
shall one single failure lead to an outage of the complete data system.
The speed of the data highway shall not be less than 100 Mbps. The data
highway shall connect all the systems to perform real time information
exchange between the various DCS components.
Loading of the data highway should not exceed 60% with full load
operation.
The data protocol used shall safeguard against erroneous data transmission
and allow for error detection, recovery and initiate switch-over to the
redundant data highway.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

1.4.4.7

Operator station

1.4.4.7.1

General

Page 59 of 178
Rev. 0

The operator interface should be provided by operator stations that permit


the operator to control and monitor the plant. In addition to the standard
displays provided by the system, it shall be possible to display the process
with corresponding graphic displays, control loop displays, electrical single
line schematics, group displays, on-line and historical trend curves, alarm
lists, all with dynamically updated process parameters on the VDU's.
Through the operating consoles it shall be possible to start or stop the plant's
equipment, control the various valves, pumps, solenoids etc., change modes
and set-points of controllers. All necessary information concerning process
behavior, control instrument and controller integrity for modulating control,
sequential control and alarm function should be immediately available to
the operator at the operator station.
All analogue signals from field equipment shall be shown on the VDUs, in
the dynamic graphic displays or/and other displays. It shall be possible to
provide a historical and real time trend display for analogue and status
signals.
For high availability of the plant redundant operator stations have to be
provided. Their number shall be chosen in such a manner that in case if one
operator station should fail, the normal operation of the plant would still be
possible using the remaining operator stations.
At any operator station the operator shall be able to choose any kind of
display and execute control on any of the VDUs from any of the keyboards.
A higher level of operator stations shall be implemented for crosswise unit
operation with level of operator station password and user name. Additional
operator station shall be provided for an additional operator for start-up
purpose or troubleshooting. The shift supervisor shall have access to all
systems of the Plant for monitoring. It is not foreseen that he will operate
the Plant.
Main memory shall be protected against loss or corruption in case of power
failure. Automatic reload and restart shall be provided not requiring
operators intervention. Contractor shall state in his proposal the size of the
memories, both used and installed.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 60 of 178

Rev. 0

The system shall be provided with the main and bulk memories of adequate
size including 40% spare capacity, i.e. 40% of the installed memory shall be
free for future extended functions after commissioning.
Bulk memory shall be provided with redundant hard disk drives (RAID 10)
and shall be redundant. CD/ DVD or tapes may be used only to load and to
extract or store programs or data.
VDU's shall be:
TFT-type
high resolution 1280 x 1024 as a minimum.
size minimum 20 inch
compliance with newest TCO standards
CE sign according EU-Directive 2004/108/EC
lowest pixel fault class (according ISO 9241 part 302 and 305)
LCD lifetime > 40,000h
Tilt-and-swivel base with height-adjust
High and fine drawing resolution for CAD applications.
Typical brightness 300 cd/m2
Typical contrast 900:1
Typical viewing angle horizontal/vertical 178 degrees.
Radiation immunity and suppression equivalent to CE certification
according RFI to EC directive
Video input
Plug and play
The intensity of the display shall be adjustable by the operator so that
characters and symbols shall be clearly legible from a distance of 1.5 meters
under high ambient lighting conditions.
The keyboard should have standard operator control keys. All keyboards
used for control of the process should be identical and should be clearly
labeled. Any keyboard shall be provided with a mouse.
To perform the described functions no operator programming should be
required. All features should be available through use of the functional
standardized faceplates. Pressing of illegal push-buttons during any
operation should be ignored and the error condition should be indicated on
the display.
All data entry and operator commands should be subject to two steps of
operating action so as not to cause any inadvertent actions. Regularly used
keys shall be of extra rugged design. Keyboard operation must be conceived
in such a manner that the selection of the different displays and access to the
process variables, motors and actuators shall be possible with only a few
strokes. In critical situations the switch from a general display to a display
FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 61 of 178

Rev. 0

suitable for direct control must be possible directly without the need to
select additional intermediate displays.
In addition to the capability of invoking control actions from dedicated
displays, the system shall also provide the facility of invoking such actions
via graphic displays.

1.4.4.7.2

Local operator stations


The Local Operator Stations (LOS) shall be connected directly to the DCS
station of each GTG. It shall be possible to operate the GTG independently
from the DCS operator stations in the CCR. All necessary control,
instrumentation and monitoring should be available at these local operator
stations.
VDUs and its peripherals shall be of standard industrial type.

1.4.4.7.3

Human-Machine-Interface (HMI)
The HMI of the DCS shall include a hierarchic visualization concept tuned
to the requirements of plant operation. Through it the operator
communication and monitoring shall be performed.
For this purpose graphic elements (plant displays, curves, loop displays,
alarm displays, operating windows etc.) arranged in a hierarchic order shall
display easily, quickly and transparently the status of the plant, of the
control equipment and of the control loops.
The highest demand in the designing of the HMI shall be placed on user
friendly displays. For the control room operator displays for monitoring,
information and control functions shall be provided. The displays shall
present process sequences and statuses in a functionally related manner.
HMI Update
The system shall be capable of scanning all inputs in such a manner that all
displayed data shall be updated within maximum 1 sec. The system shall be
capable of accepting spontaneous events from the process with a time
resolution of 1 ms (SER function), independent from the above mentioned
scanning cycle times. When a piece of equipment is not in service the
associated analogue and digital inputs shall not be eliminated from the scan
cycle. The system shall however be capable of inhibiting any nuisance
alarms during the period when the equipment is out of service.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 62 of 178

Rev. 0

Overview Display
An overview display should enable the operator to determine the overall
operation of a large segment of the plant. It shall indicate the alarm status of
all loops. The operator should be able to call up directly any overview
display.
Process Graphic Display
Dynamic interactive graphics of different sections of plant should be able to
be displayed on the operator stations. Graphic displays should be
configurable only through engineering environment (i.e. from a console by a
protected access via password, access card) and use symbols from a library
of standard/ user defined graphic symbols. Different plant sections should
be displayed on different pages.
Graphic displays should be of the interactive type with the possibility of
integrating process parameters ('live' points) through which it should be
possible to control the process. This includes control actions, such as
Manual/Auto, On/Off, Open/Close, setpoint generation, start of functional
groups, etc.
The operation status of individual drives, progress and status of functional
group controls shall be displayed on the graphic pages. Different colors
should be used to identify different status and events.
All process lines in graphic displays shall be colored according to its
process medium.
Face plate and trending information should be accessible from the graphic
displays directly through free format windowing facilities. All control
parameters should be displayed on their respective graphic pages. It should
be possible to view the process variable and alarm points, and to view and
change set point values, manipulated variables, and controller mode, etc.
from the graphic display.
Operator Input Windows
For operator actions operator input windows shall be provided. It shall be
possible to select operator input windows from any of the displays and to
open various operator control windows simultaneously on the screen.
When a particular operator input has been accepted by the DCS, this
condition shall be indicated to the operator by a change of color, short
blinking, short audible tone etc.
Process control operations shall be performed in two steps:
entering/setting of value
confirmation/execution of the entry.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 63 of 178

Rev. 0

In all cases the current and the entered data shall be shown separately.
Standard displays shall be used for adjustment of drives and open/closed
loop controls, e.g. for selection of remote manual operation. All relevant
values of the open loop or the closed loop controller (actual value,
manipulated variable, etc.) shall be displayed. All operator inputs shall be
transferred to the automation system only after the Execute key has been
pressed.
Group Display
A group display shall include the status of a smaller number (6 to 8) of
control loops, including:
bar charts with process variable, set-point and controller output
numerical values of process variable and set-point, in engineering units,
numerical value of output in percentage
status indication of binary inputs and outputs
status indication of functional group controls
control mode of each control loop
alarm condition in each loop
The grouping of the control loops shall be done based on the system or
equipment mode of operation and is subject to Engineer's approval.
Loop Display
The loop display shall contain all detail information of the individual
control or measurement loop, including:

configuration of the loop


control signals
control parameters
status of drive control and functional group control containing trip
signals, interlocks, criteria, actual step of sequence and commands
transmitter range
alarm set values
output limits
The detailed information shall be card coded or access code word protected
from unauthorized alteration.
Alarm Summary Display & Printout
All activated alarms shall be listed in chronological order. Alarms not yet
acknowledged shall be distinguishable by red and flashing annunciation.
The VDU shall display the message of occurrence and of disappearance.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 64 of 178

Rev. 0

All new alarm messages shall be displayed on the next available line and
shall flash until acknowledged from the keyboard. Every new alarm shall
activate a bell for 2 seconds to call the attention of the operator. If more
alarms are detected than are to be shown on the VDU, more recent ones
shall be displayed and the earlier messages shall be shifted to the alarm
backlog memory. In this case a special message on the screen will indicate
presence of messages in the backlog memory. Recall of backlog messages
on the VDU display shall be provided.
The alarm condition of each point should be displayed on the group display
by color change and blinking. Alarm acknowledges should be possible only
from the relevant (assigned) operator station. For all alarms a direct access
to the dedicated graphic display shall be provided.
On request the system shall list all the alarms implemented in the system,
grouped by equipment or function (i.e. boiler, turbine, common equipment,
electrical etc.), showing the alarm status of each alarm.
It shall be possible to transfer each VDU from one operator station by the
keyboard in alarm mode or monitoring mode. However, while in the latter
mode, occurrence of any new alarm shall activate the bell and the new alarm
shall be shown on the existing display (e.g. on the lowest line of the VDU).
Trend Display
The system should be capable of displaying both real time and historical
trends as follows :
real time trend. The real time trend should be for a minimum of 8 hours
at a sampling rate of 10 seconds.
historical trend. The historical trend should be for a minimum period of
96 hours. Historical data should be stored on a non-volatile memory
device such as hard disk. It should be able to be archived for recall.
long-term data archive. For the long-term data storage and retrieval CD/
DVD or tapes should be used. Data compression techniques shall be
provided to optimize storage capacity. Selection criteria for analysis of
analogue variables, alarms and events shall be available (period of time,
tag name, etc.).
The available storage should be sufficient for all analogue points for a
period of 1 month at a sampling rate of 1 second or better. Varying the
sampling rate or producing averages such as 1 minute, 2 minute etc. should
make it possible to store more points or for longer periods.
Real time and historical trends should be possible on any parameter or
variable like measured variable, set point, output, calculated value, etc. The
trend display should be single line type and bar graph type. It should also

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 65 of 178

Rev. 0

display information like loop tag, engineering units, span, current value,
alarm status, etc. of the trended variable. It should be possible to display by
scrolling or expanding the time base all of the trend data available on the
system. Selection of the tag and sampling time for real time and historical
trending should be possible from operator keyboard.
It should be possible to sample and store data of instantaneous and average
value at the intervals mentioned below:
at intervals of 1 second or higher for the real time trends
at 10 seconds, 1 minute and 10 minutes interval for historical trends
The system should also have a multi-trend feature from which it should be
able to display the set point, measured variable and output of any
combination of variables on the same trend variable.
Characteristic Curves
Multi-variable displays shall be provided to show the relationship between
individual process variables (e.g. pressure, flow rate). Actual values and
design operating points shall be displayed to determine whether a
component is operating correctly or is likely to exceed one of its limits.
Logging
The system should be able to assemble data and print various kinds of
standard. The system should provide the following basic types of reports as
a minimum:

event lists
incident (trip) review log
operator action reports
custom reports with fixed and variable formats

The above reports should use real time data, historical data, or calculated
data generated, by any node in the system or any connected device to the
system such as PLCs or plant management system. All points in the system
should be available for logging.
A report generation function should be available at the engineering
workstation for free-format reports generation of text and data. The report
types should be :

on demand
at a predefined time (hourly, shift, daily, etc.)
event triggered
real time events with six hours worth of data to help in diagnosing shutdown incidents.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 66 of 178

Rev. 0

These reports should be archived for further recall. Schedule assignment for
reports shall be flexible. Demand for immediate output of a report must not
affect any scheduled reports that have been set up previously.
The types or classes of data used by the report generator shall include:

analogue variables and associated parameters


operator entered values
status of multi state variables
alarm and event messages
calculated variables
historical data values and status
other retrievable tagged items

The report generator shall also be able to incorporate text supplied for report
titles, explanations, messages, etc. Data validity indicators have to be
propagated throughout report production to provide information on the
reliability of requested values.
Math functions to provide more complex reports (more than list of totals
and averages) shall be a standard tool of the report package. The software
package shall be easy to use and not require programming skills.

1.4.4.7.4

Alarm annunciation and sequence of events recording functions


(SER)
Abnormal operating conditions and events in the plant have to be
annunciated. For optimum identification of the cause of faults all alarms
shall be displayed on VDU and printed out in their true sequence of
appearance. Corresponding graphic or loop displays shall be immediately
accessible by selection of individual alarm messages.
Under operation control, it should be possible to enable/disable the printing
of all or selected alarms.
The design shall be as follows:
detection of fault and status annunciation in correct time sequence
changes in annunciation are to be shown with annunciation tag number,
alpha-numeric signal code, clear text and with date and time of day.
system shall be able of self-checking for system faults and creating
special control system alarms
Sources of alarms are:

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 67 of 178
Rev. 0

status inputs
analogue or derived variables
instrument alarms within the DCS (for example open circuit detection on
analogue inputs bad process measurement, etc.)
discrepancy alarms (i.e. both limit switches open etc.)
system fault alarms
data communication alarms i.e. errors data
alarms transmitted via serial links from sub systems
C&I alarms
process alarms
Alarms should be presented on the alarm display, the first being the newest
non-acknowledged alarm. It shall be possible to implement the first out
alarm in graphical display for the unit/major equipment. Different selection
criteria should be available at least:

acknowledged/unacknowledged alarms
priorities or states
period of time
systems or groups
sources of alarms

The display should list for each alarm:

the time of alarm followed by DAY/MONTH/YEAR


the alarm point tag
the alarm point description
the violation type such as, high, low, deviation, rate of change, "bad"
process value (high or low)
priority should be indicated by color
The alarm condition of each point should be clearly shown in group
graphics and individual point displays. Alarms should be displayed as
they happen on the correct screen in the allocated area. It should be easy
to determine from these displays if the alarm has been acknowledged (for
example, blinking indication for not acknowledgment alarms).
related messages and information like orders, instructions, cause-effect,
countermeasures, etc., shall be shown on the VDU on demand for each
alarm

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 68 of 178

Rev. 0

Regardless of its source, a configurable priority should be able to be


allocated to an alarm. For example, priorities could include:
shut-down safety alarms or fire alarms
vital alarms (abnormal process conditions which the operator may be
able to correct) before protection is activated
alarms which do not require the operator to be alerted, but which are to
be recorded
system alarms
Process alarms and 'return to normal' messages should be shown with a time
stamp as and when they occur. Alarm printing shall be on request of the
operator. The alarm archiving shall be done continually.
It shall be possible to process a selected number of signals in the Sequence
of Event Recording (SER) function of the DCS. Function of a fault recorder
must be realized. For this function the DCS shall provide a first out alarm
capability. In the case of an avalanche of alarms, the system should be able
to discriminate between them by time and date in the order of their
occurrence.
The time resolution of the SER function shall be 1 millisecond, i.e. if the
second event occurs 1 milliseconds after the first event, then the equipment
shall be capable of resolving the two events.
If alarms transmitted from other control systems (e.g. package systems) to
the DCS via a serial links are processed in the SER then these alarms have
to be transmitted with the corresponding time tag and the clocks of the two
control systems have to be synchronized. If this requirement cannot be
fulfilled then the processing of these signals in the SER is not allowed. In
this case the important alarms from the package control systems shall be
hardwired to the DCS.
The most important requirement for the SER function is that in case of plant
upsets correct time information shall be available for all signals processed in
the SER and that all signals of the plant which can trigger plant upsets shall
be included in the SER, i.e. the offered SER shall be a plant wide SER.

1.4.4.7.5

Printers and video copiers


Printers should be suitable for a control room environment and should
generate a minimum noise during operation. The printers shall be connected
to a printer network or to the terminal bus structure.
Printer failures shall be displayed as alarms on VDU of operator stations.
Logging Printing

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 69 of 178
Rev. 0

The logging printer should provide the following:


printing of hours, shift and daily logs
report printing on operator request
Alarm and Event Print functionality
The alarm printer should log the process and system alarm messages on
request, and should also the alarm history for each shift of operation or on
demand from operator console. Print out should show as a minimum the tag,
the process variable, description, date and time of occurrence, time of
acknowledgment and the time of return to normal.
The printer shall allow duplex printing.
Video Copy functionality
Color screen copying should be accomplished by a single push button
operation associated with the screen involved. The screen copier should be
able to print any screen displayed on any operator station..

1.4.4.8

System diagnostics and configuration


The engineering stations shall be accommodated in the engineering room
adjacent to the CCR. The engineering consoles shall be equipped with
VDU, engineering and functional keyboard and mouse used for tests,
configuration and tuning purposes.
The engineer's console shall allow system configuration, writing and
executing of user written macros, graphics development, report generation,
logging specification, system self documentation functions, system
monitoring functions (which show the result of self diagnostic tests), system
database load/save etc. In addition it should be possible to tune controllers,
change limit set-points, view all loop variables, configure control systems,
add and delete alarms. The engineer's console shall be capable for signal
simulation and signal dynamization.
Back-up facilities (e.g. RAID 1 - Mirroring) shall be provided to prevent
loss of data and software.
For the generation of process graphic displays, a standard library of symbols
shall be used. A graphics package should be available on the system. This
should be able to create user defined symbols and store them in user defined
libraries. In addition standard industrial ISA symbols such as heat
exchangers, pumps, compressors and tanks should be provided.
Configuration of the control function should be possible by simply selecting
a programmed algorithm and entering the required attribute information
such as input and output location and tuning constants. Control loop and
sequential logic should be built by linking the desired control function as

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 70 of 178

Rev. 0

they appear on control and sequential diagram. Modification should be


easily made by revising the attribute information and inserting and deleting
the control function.
Operation of the engineering console by unauthorized personnel shall be
prevented by the use of access cards or pass words.
The system shall monitor itself continuously for failures by means of selfdiagnostics. Diagnostic routines shall be applied for each control module.
Detailed diagnostic messages shall be displayed on the engineering
consoles VDU and printer, and group alarms shall be given at the process
operator's desk. The diagnostic display shall clearly identify in graphical
manner the faulty component, the nature of the fault and the component
location (at least panel number, rack number and slot number).
Diagnostic displays should be available to assist fault location. It is
expected that most faults will be quickly repaired by simple replacement of
a card or module. The diagnostic display should clearly identify the faulty
component, the nature of the fault and the component location.
If the required diagnostic functions/displays are not available in the
engineering station than separate diagnostic hardware/software within the
DCS shall be offered.
Remote accessibility shall be possible via DSL to allow the specialist for
example to troubleshoot all the DCS components for routine maintenance or
system repair or configuration.

1.4.4.9

Cyber Security
Due to the standardization of control systems (operating systems, software,
hardware and communication protocols) on the one hand and the growing
use of networks in plants and systems on the other hand the threats and
vulnerabilities of IT systems increase. Handling errors, malware (viruses,
worms, etc.) and unauthorized accesses are some of the main problems.
The vulnerability of the control system shall be minimized without loss of
functionality and stability.
Following items shall be considered generally:
Creation of a network topology scheme with special attention to all
interfaces (e.g. patched system, use of firewalls)

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 71 of 178

Rev. 0

Interfaces and security methods for


Interfaces to office LAN
Interfaces to black box systems
Interfaces to plant operation system
Interfaces to set off working places
Remote maintenance
Patches and software updates, including anti-virus scanners, are required to
lessen the possibility of cyber attacks upon known vulnerabilities and
exploits.
To ensure availability, confidentiality and integrity at least the following
item shall be considered:
Design of DCS with security measures, segregation and availability to
reflect the plant requirements
Measures to protect itself from unauthorized access from external
systems including the corporate office data network
Measures that enable secure remote operation according to process
requirements
Measures for disaster recovery
Safe operation if communication to external systems fails
Be documented and maintained in a manner that reflects the
requirements of the connected systems
The measures shall be based on international standards like ISO 27001,
IEC 62443 and ISA S99.
Access level authority shall be submitted to the Engineer approval at the
beginning of the design phase. A close cooperation for developing the final
operation and access philosophy to the plant, as well to the control & IT
systems is necessary between client and supplier, finally.
The requirements of the HCIS have to be considered.

1.4.5

Task of the main control loops


The description of the following control loops covers the main control
requirements and contains an outline proposal for meeting the requirements.
Alternative designs shall be proposed where cost/benefit or - with respect to
special mechanical equipment - technical improvements can be shown. Such
alternative designs, however, shall meet the minimum functional
requirements of the following descriptions.
The control ranges of the various individual control systems must not limit
the control range of the plant unit as a whole.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.5.1

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 72 of 178
Rev. 0

Gas turbine generator unit control


The control, instrumentation and monitoring system of the GTGs shall be
incorporated in the DCS.
If the control system will be delivered by the GTG supplier, the gas turbine
control package shall be fully integrated with the DCS such that all control
commands and supervisory data available within the package will be
transferred to the DCS to facilitate remote control and on-line supervisory,
including fully automatic remote start/stop operation, as well as satisfying
operational logging requirements.
The interfacing for non time critical signals shall be via redundant serial
link and for time critical signals (operator commands, command check-back
signals, protection signals, etc.) hardwired signals shall be provided.
Turbine supervisory instrument shall be provided for the gas turbine.
Detailed requirements regarding the amount of interface signals and the
functions included in the GTG control system are specified under Part B1
of this specification. Minimum requirements on the necessary
instrumentation, trip criteria and alarms are also included in this section of
the specification.
GTG Frequency Control
In addition to droop control, frequency control facility with grid frequency
correction function shall be provided with selection facility. The required
feature shall automatically regulate the grid (system) frequency at any set
value within the permissible range and under the limitation of GTG as
specified under Part B1. It is basically load control operation with feedback
to automatically correct the system frequency to set value. It shall be
possible to select any GTG unit or any block to frequency control mode.
Load sharing facility shall be provided if more than one unit is selected.
Diverter Control
The diverter at exhaust stack/boiler inlet shall be operated automatically and
for emergency reasons manually from the central control room with
continuous position indication.
For safeguarding the boiler the following process criteria shall be applied as
release or protection criteria:
Start-up gradients for steam pressure and temperature limits
Differential temperature of HP drum walls (measured)
Signals to be exchanged with the GT-control
Any other criteria which may arise during detail design and
commissioning
Local panel operation by key release shall be possible.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.5.2

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 73 of 178

Rev. 0

Heat recovery steam generator unit control


To perform the warm and hot start of the HRSGs, functional group control
shall be provided. This shall include the start-up and normal feed regulation,
the venting and draining of the steam lines via the remotely controlled drain
and vents as well as the opening and closing of the boiler main stop and
associated bypass valves.
During start-up the rate of change of drum pressure /temperature and boiler
stress shall be monitored. The starting sequence shall consider these values
to achieve minimum run up and loading times consistent with preset thermal
stress limits.
The following closed loop controls shall be supplied as a minimum.
Load Control
For each HRSG auxiliary firing facilities shall be provided, designed to
allow steam conditions to be maintain over the whole gas turbine load
range. The load control shall maintain the live steam pressure constant or
the boiler load constant (depending on the selected mode of operation) and
allocate the total fuel flow to the burners in operation or the position of the
GTG exhaust gas diverter.
Each burner group shall be controlled independently by one control valve
for each group.
To avoid burner shut-down through low fuel pressure the fuel controller
shall have a minimum fuel pressure control loop as back-up or shall apply a
minimum stop on the valve (by software).
Burner overloading is to be prevented by limitation of the maximum fuel
pressure.
In addition to the HRSG load control by changing the fuel flow when the
supplementary firing is in operation, it shall also be possible to control the
load of the boiler, without supplementary firing in operation, by adjusting
the GTG exhaust gas bypass damper, depending on the load requirements of
the boiler. This mode of operation is however, only possible as long as the
waste energy supplied from the GTG is higher than the requested boiler
load. In this case part of the GTG exhaust gas, which corresponds to the
energy surplus, will be fed to the stack. The mechanical construction of the
damper must ensure, that there is always sufficient opening for the exhaust
of the turbine.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 74 of 178
Rev. 0

Feedwater Control
A fully coordinated automatic control system shall be provided and shall
give the appropriate rate of delivery of feedwater to each HRSG to meet the
prevailing steam demand over the full operating range, whilst maintaining
the drum water level to within +25 mm of the desired setting. Under normal
load changing conditions of changing flow demand the transient departure
from normal water level shall remain within the drum tripping limits.
During and subsequent to all the plant operating modes including plant trips
the drum levels shall be maintained at their desired settings.
The water level in the boiler drum shall be controlled by a feedwater control
valves capable of maintaining the water level at a safe distance above the
entry to any down coming tubes, under any condition of design load change.
A single element and 3 element control scheme based on drum level and
steam/feedwater flow shall be provided. Automatic changeover between
single element and 3 element control in accordance with the steam flow
shall be provided in addition to a manual changeover facility. Under start-up
conditions and at loads up to approximately 30% MCR the water feed flow
shall be controlled by a single element system to maintain the drum water
level at the desired setting by controlling the position of the 30% duty
feedwater regulating control valve in response to deviations in drum water
level. Above 30% load the water flow shall be under the control of 3
element system whereby the feedwater flow is controlled to match the steam
flow requirements, whilst taking into account deviations of the drum water
level from the desired setting. 3 element control shall be performed by one
of the 2 x 100% control regulating valves with a duty/ standby selection
facility. The standby valve shall immediately and automatically take over
the control duty upon a failure in the duty control valve.
The drum level measurement shall be suitably compensated (pressure
correction) so that no drift in the zero and span calibration will occur when
the boiler starts from the cold to the normal operating condition.
The contractor shall carry out computational simulations taking into
consideration the most severe disturbance due to desalination/ ST trip or a
trip of another boiler in order to ensure that still the drum level will be under
control and that the trip limits will not be reached. Should the results show
that improvements on the boiler and/or on the I&C equipment are necessary
in order to meet the above requirement, then all the necessary modifications
shall be carried out.
Boiler Superheated Steam Temperature Control
The steam temperature control shall be achieved by feedwater injection into
the superheated steam between first and final stage of superheating.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 75 of 178

Rev. 0

A temperature closed loop control comprising of either a cascade control or


a two loop control shall be provided.
To improve the control loop accuracy the steam flow shall be used as a
feedforward signal.
Boiler Stress Evaluator and Lifetime Counter
In connection with the automatic control system of the boiler a stress
evaluator shall calculate the actual thermal stresses existing on any thick
part of the boiler (drum, headers, etc.), and compare them with maximum
permissible stresses.
Similar to the turbine stress evaluator, the permissible gradient variation
shall be indicated, recorded and incorporated into automatic start-up of the
combined cycle. The boiler stress evaluator of the HRSG shall be effective
during the start-up of the HRSG and shall affect the positioning of the
diverter damper. It shall not have any effect on the GTG loading gradient.
When the diverter damper is fully open and the HRSG is loaded, the boiler
stress evaluator shall be disabled.
All other functionality will be similar as those of the turbine stress
evaluator.
The stress evaluator shall be combined with HRSG Lifetime Counter.

1.4.5.3

STG unit control


The STG control, monitoring and protection system shall be delivered under
responsibility of the STG supplier. The remaining control functions in the
STG area such as gland steam pressure control, etc. shall be implemented in
the DCS.
Steam turbine governor controls shall be provided as specified under
Part B4.
The STG control, monitoring and protection system shall be coupled to the
DCS such that all controls, commands and supervisory data available within
the package can be transferred to the DCS to facilitate remote control and
on-line supervisory, including automatic remote start/stop operation,
synchronization, and load control as well as satisfying operational logging
requirements.
Turbine supervisory instruments shall be provided for the steam turbine.
The interfacing for non time critical signals shall be via serial link and for
time critical signals (operator commands, command check-back signals,

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 76 of 178

Rev. 0

emergency shut-down signals, etc.) hardwired signals shall be provided.


These interfaces however are only required if the STG Control System is
not an integral part of the DCS.
If the serial interface cannot transmit time information of emergency shutdown signals (turbine trip) then the emergency shut-down signals shall be
hardwired to the DCS and processed in the sequence of events recording
system (SER) of the DCS, so that in case of plant upsets correct time
information shall be available for the SER. If the emergency shut-down
signals are transmitted to the DCS with time information then it is
compulsory that the STG control system clock shall be synchronized with
the DCS clock.
Steam Turbine Stress Evaluator and Lifetime Counter
Thermal Stress Evaluator (TSE) shall be provided to monitor and control
the thermal stress on the turbine during auto run up. Maximum allowable
stress levels shall not be exceeded. Appropriate indications and alarms shall
be provided.
In connection with the automatic turbine speed/load control a stress
evaluator shall calculate the actual thermal stresses existing on any critical
turbine parts and compare them with the maximum permissible stresses.
The turbine stress evaluator shall supervise and monitor, based on the
surface temperature of the HP- and IP-rotor, the stress of the steam turbine
during all operating conditions and forms signal that limits the steam turbine
controller.
Because the surface temperature of the rotor cannot be measured, a
substitute metal temperature shall be provided. This measurement includes
thermocouples, which will be installed at proper places where the
temperature of admission steam is identical with the temperature of the
rotor.
The difference between actual and maximum permissible stress value shall
determine the max. permissible gradient of turbine speed or load changes.
Turbine speed or load permissible gradient variation shall be indicated in
the central control room.
These signals shall be incorporated into automatic turbine speed and load
control system. It shall be possible to put turbine stress evaluator on
advisory mode operation in which case its output signals shall be only
displayed but shall not influence turbine speed and load automatic control.
Alarms shall be provided when the difference between the actual and
permissible stress value exceeds its present minimum.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 77 of 178

Rev. 0

In addition to the stress evaluation a lifetime counter for each turbine shall
be provided. The counter shall calculate lifetime reduction compared with
rated operation dependent upon stresses, frequency, temperature, warm and
cold starts, load changes, over speed tests and other conditions according to
the design, data figures given by the Original Equipment Manufacturer.
Gland Steam Pressure and Temperature Control
The gland steam pressure controller shall maintain a constant pressure of
few mbar above the atmosphere in order to prevent air from entering those
parts of the turbine whose pressure is below atmosphere.
During start-up of the turbine, the steam is taken from auxiliary steam
header and later on from the turbine HP-part.
The gland steam pressure shall be measured by two transmitters.
The temperature controller shall keep the gland steam temperature
downstream of the gland steam cooler in an acceptable range by means of
injecting condensate through the spray water control value into the gland
steam cooler.
Detailed requirements regarding the amount of interface signals and the
functions included in the STG control system are specified under Part PB4.

1.4.5.4

LP and HP steam control valves (Scope of Package D)


The LP steam control valves and HP steam control valves for steam supply
of each desalination unit shall be controlled by DCS of Package D. The
LP/HP control shall be in full co-ordination with the STGs and the
associated desalination units.

1.4.5.5

Desalination unit control (Scope of Package D)


The Tenderer has to ensure compliance with the stipulated accuracy of
control and the safe and reliable operation of the whole unit.
The control equipment and monitoring facilities to be supplied shall ensure
continuous operation of the desalination units without manual intervention.
The change of production rate shall be done automatically without operator
intervention. The new production rate set point shall be implemented
gradually by the control system, by adjusting all relevant controllers set
points in such a way that the:
water quality is maintained.
chemical injection is optimized (even during the transition period)
brine heater temperature is optimized.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 78 of 178

Rev. 0

This control program shall have tuning capabilities to allow for optimum
control when there is a change of environmental conditions such as seawater
temperature.
This requirement shall necessitate optimization of all control parameters
during steady and transitional states of the plant.
Algorithms shall be developed and implemented in the DCS together with
the required instrumentation to perform efficiency calculation (e.g. related
to all MSF stages including the brine heater). The results of these
calculations shall be trended by the DCS. Fouling calculations and
production rate shall be performed for all stages on continuous basis.
The operator shall have the possibility to take partly or completely the
above described control scheme in manual setpoints adjustment mode.
The description of the control loops dealt with below covers the control task
and contains an outline proposal for performing the task concerned and is
provided only for bidding purposes.

1.4.5.6

Plant master control


The Plant Master Control level shall provide for control and monitoring of
the Plants electrical power generation and water production. It shall use the
respective demand set points, input either by the CCR operator or received
from the load dispatch center, and the current loading of the sub-ordinate
units, and accordingly generate outputs for safe and optimized control of the
sub-ordinate units (i.e. GTGs, HRSGs, STGs and desalination units). The
number of units/equipment in service along with their current loading shall
be used to determine if the new demands can be met. The operator shall be
alerted if the system is load limiting due to plant constraints. The electrical
power generation shall be distributed over the steam turbine generators and
gas turbine generators with HRSGs, operating in closed cycle, to meet the
electricity demand. If desalination demand is fixed, the GTGs shall be used
to meet the new demand, with appropriate control of HRSGs supplementary
firing rates. If the megawatt demand is fixed, increase or decrease in the
steam demand for the desalination units shall be achieved by varying the
HRSGs supplementary firing rates and GTGs load.
As part of the Plant Master Controller a program shall be realized in the
DCS coordinating in a sequence of priorities the start-up and shut-down of
the whole power plant block including which system/ unit to be started/
shutdown first and which one second and so on.
A sophisticated level of optimized automation technology shall be
implemented for the block master control.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 79 of 178

Rev. 0

It is recognized, however, that the greatest economy of operation and


minimal environmental impact is achieved by the close matching of steam
generation and steam demand with minimum resort to steam dumping. As a
consequence the Plant Management System (see below) shall give guidance
to the operational staff as to the most optimum configuration of operational
plant capable of meeting the electrical demands set by the load dispatch
center and water production requirements in the most energy efficient
manner.
The Plant Master Controller shall be provided for interlocked control of the
units including HP/LP & HP/MP bypass stations (if applicable), during the
plant upset conditions, including GTG trip, STG trip, HRSG trip,
desalination trip and load rejection.
In case of steam turbine or desalination trip, the Plant Master Controller
(PMC) shall immediately reduce the steam generation. This quick reduction
of steam flow shall be initiated by the trip signals from the respective units.
The PMC shall have the load/generation regime in case of island operation.
This shall lead the Plant to predefined conditions using power management,
load shedding, generation reduction, frequency response, management of
primary reserve and other similar features. The load/generation regime
includes also the tripping regime over the Plants units. Details are subject
for detailed engineering phase.
The PMC shall have the following master controllers:

Electrical Load Controller (ELC).


High Pressure Steam Header Master Pressure Controller (HP MPC).
Low Pressure Steam Header Master Pressure Controller (LP MPC).
Intermediate Pressure Steam Header Master Pressure Controller (IP
MPC).

A sophisticated software program shall be designed in the PMC to perform


the functions of each of the above master controllers.

1.4.6

Signal exchange to other Control Centers


Reference is made to Annex P-C13-4.

1.4.6.1

Signal exchange to the SEC SCADA system


The DCS shall provide an appropriate interface to the SCADA system,
according to The Saudi Arabian Grid Code (last valid revision).

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 80 of 178

Rev. 0

The requested signals (see therefore the schedules of The Saudi Arabian
Code).shall be made available at the LDC (located in Riyadh).
The Bidder shall provide all these signals like voltage, current, frequency,
Active Power and Reactive power measurements outputs and Plant status
indication and alarms to the supplied interface equipment (SCADA
outstation provided by Transmission Service Provider (named TSP) of
SEC).
Signal shall be exchanged with Fiber Optic Cable using IEC 60870-5-104
protocol.
All signals requested for Generator Rejection Scheme (see also P-B-13.4)
have to be exchanged between 380 kV substation (including signals with
Maaden) and RAZ plant.

1.4.6.2

Signal exchange with Maaden


Provisions shall be made for signal exchange to Maaden. Signals shall be
exchanged via the interface panel in the 380 kV substation.
At least the Maaden related metering signals (extracted from automatic
meter reading system) of fuel and water meters and relevant signals from
DCS shall be exchanged. Amount and list of signals will be defined in detail
design stage.
All interface equipment together with the cables connecting them to the
interface panel shall be included in the scope of supply of the Tenderer.
At least Maaden will provide a signal in case of huge load rejection for
preventive action in Contractors DCS for power plant operation which shall
be transmitted via 380 kV substation. The generation rejection regime is
described in P-B13-4.
The signal shall be available within 100 ms.

1.4.6.3

Signal exchange with Fuel supplier (Saudi Aramco)


Provisions shall be made for signal exchange (process signals/ metering
signals) with fuel supplier. Amount of signals will be defined in detail
design stage.

1.4.6.4

Signal exchange with SWCC headquarter


Provisions shall be made for signal exchange from the automatic meter
reading system to the SWCC headquarter. The information shall be
exchanged using a public line.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 81 of 178

Rev. 0

Details shall be agreed during detail design stage.

1.4.7

1.4.7.1

Burner management system (BMS) and Boiler protection system


(BPS)

Functional requirements
Burner start-up and shut-down shall be initiated from operator stations in
the CCR. The start-up program is required to run automatically and without
further manual intervention, following initiation by a manual or automatic
start command. A leak test for each burner shall be integrated into the BMS.
The shut-down program likewise shall run automatically without further
manual intervention following initiation by a stop command (manual or
automatic), through all the control steps necessary to shut-down an
operating burner.
The automatic control of dampers, gate valves, emergency shut-off valves,
ignition devices etc. shall be effected via the BMS.
The individual steps of the programs shall be displayed on the VDUs at the
Power Control Desk in CCR.
Indication of flame intensity shall be provided on the VDU, too.
In the BPS the following trip criteria as a minimum shall be provided:

boiler emergency off


boiler drum level low low/high high
GTG not in operation
circulating water flow low low
diverter damper position closed

In the BMS in addition to the control function of the supplementary firing


equipment the following trip criteria for the supplementary firing equipment
shall be provided as a minimum:

flame loss
fuel gas pressure high high/low low
control air pressure low low
cooling air pressure low low
diverter damper position closed

The boiler shut-down shall also be possible via emergency push buttons
installed locally and in the CCR.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

1.4.7.2

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 82 of 178

Rev. 0

Design requirements
Each HRSG shall be provided with a separate burner management system
and a separate protection system. The design of the equipment shall be fully
fail-safe and fault tolerant. A certified fail-safe system shall be provided for
the boiler protection system (BPS) and Burner Management System (BMS)
and shall be implemented in the DCS process station as a part of the DCS. It
shall be approved by an independent and recognized testing agency which
shall provide certificates of safety and/or performance for insurance
purposes and shall conform to SIL 3 according to IEC 61508.
The two-out-of-three logic shall be provided for all automatic trip functions.
Control and monitoring shall be realized via the operator stations of the
DCS, i.e. start-up, shut-down and complete monitoring of these sequences
shall be possible from the DCS. All BMS/BPS generated alarms shall be
made available to DCS for true analysis of faults/trips.
The boiler protection system shall be provided in a separate dedicated DCS
process station physically and functionally segregated from the BMS. It
shall be possible to operate and keep the boiler in service with its protection
system operational if the BMS/supplementary firing equipment is switched
off and/or out of service. BMS tripping shall not trip the boiler and shall not
cause a loss of the boiler protection totally or partially.
Together with the turbine protection systems it shall be possible to bring the
plant in a safe operational status. All necessary signal exchange with other
protection equipment shall be hardwired.
BPS signals are intended to disconnect, stop or start parts of the plant when
the plant has reached a critical operating condition by acting directly on the
switchgear. The switchgear shall be designed to accept signals from both
the DCS and the BPS.

1.4.7.3

System architecture
The BPS shall provide triple modular redundancy at I/O level by using 2 out
of 3 voting.
The BMS shall be designed at least in a modular redundant micro processor
based controller.
The offered equipment shall have the following relevant features:
the equipment shall be recognized third party audited or certified for this
kind of application
there should be numerous systems of this kind in use for industrial
control including BMS/BPS applications

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 83 of 178

Rev. 0

hardware and software should be standard catalogue products

1.4.7.4

Hardware requirements
Each BMS and BPS system shall be supplied as fully assembled and
functional, pre-wired, programmed and tested, in lockable steel cabinets,
fully accessible front and rear, complete with all technical and operational
documentation. The cabinets shall be installed in the related LER.
The modules shall be made-up of standard plug-in types and shall be so
arranged that the output reverts to safety when a module is removed from its
position. Dual or triple redundant analogue or digital inputs shall not be on
the same circuit board. They shall be in separate I/O bins and on separately
fused supply circuits. The supply voltages distributed to sensors, switches
and transmitters shall be individually protected - short-circuit proof such
that a fault on one input is not propagated to others. Failure of any input
sensor or its cables and connections shall give an alarm. The alarm shall be
available on the operator station.
Every relay and solenoid valve shall be controlled by a testable output
channel.
Redundant output channels must not be on the same circuit board or in the
same bin. It is however acceptable for all other circuits for an individual
burner to be on one board. Output channels should be short circuit proof.
The BMS/BPS shall be designed/ implemented with fail-safe philosophy.
It is not accepted, that two individual burners sharing the same I/O modules.

1.4.7.5

Software requirements
The sequence of operation and safety requirements will be incorporated in
an approved logic diagram. The programming device will be used to create
the application program. It shall be capable of connecting to the system and
monitor it on-line. The software shall provide off-line and on-line self
diagnostic facility for fault detection and identification, which shall then be
displayed at the operator stations.
The flame scanners shall be capable of differentiating between the flame of
its associated burner and extraneous lights caused by other burners or by the
hot furnace wall. They shall not be affected by the radiation or temperature
of the refractory. Adjusting facilities for flame monitor sensitivity shall be
installed locally. Loss of flame and system failures due to reasons other than
flame failures shall be separately annunciated in the CCR.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 84 of 178

Rev. 0

The memory/ software of the BMS/BPS shall be freezed after the final
commissioning of the BMS/BPS sort of ROM memory may be used. It shall
not be permitted even by the programming tool to modify the logic of the
BMS/BPS after the commissioning
The BMS/BPS software shall be of non-volatile memory.

1.4.8

Failure of the power supply shall not effect the built-in logic of the
BMS/BPS.Power supply
All DCS/PLC electronic cubicles shall have double infeed and dual
redundant safe power supply units each with power failure alarm. The
equipment shall be properly fused.
All operator stations, panels and printers in the CCR, local operator stations
in LERs, engineering stations and printers located in the engineering room
adjacent to CCR, electronic cubicles located in the LERs/relay rooms, etc.
shall be supplied from UPS system, specified in Part P-B12.
The power supply shall be designed with no more than 70% load in each
unit when operation individually.
The power supply for the DCS system and other digital control systems like
PLC shall be powered from redundant safe AC with 24V DC. Each DCS
cubicle and each other control cubicles shall receive two separate feeders
from redundant safe supply.
The power supplies for C&I systems shall meet the General Technical
Requirements as per Part P-B02.

1.4.9

Plant Management System (PMS)


A Plant Management System (PMS) shall be foreseen, which is the highest
level in the control hierarchy and shall be passive in nature. (The PMS can
be of PI system or equivalent.) Reference is made to Annex P-C13-9 and
Annex P-C13-10.
The License of PMS to SWCC to be considered should be of unlimited tags
and for unlimited use.
High end quality hardware and software tools should be used for PMS.
The redundant PMS servers shall be connected on-line to the DCS and all
other control systems having access to real time data of the Plant. Data of
the metering system shall be handled by the metering system, but also
shown at PMS. The Vibration Monitoring System (VMS) and Continuous
Emission Monitoring System (CEMS) shall be interfaced with PMS.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 85 of 178
Rev. 0

One PMS station shall be located in the superintendents office and for the
shift supervisor in CCR. Each operator desk shall have one PMS station to
get all information. One PMS station shall be also installed in the
engineering room. Data exchange to an external server shall be foreseen to
provide information for the office LAN. For the PMS, as it is giving the
operator guidance, it shall be located on each operator desk and on the desk
of the shift supervisor. Remote monitoring via web, LAN or WAN shall be
possible to view the plant status and efficiency calculation. Suitable security
measures shall be implemented for the external access to the system.
The following functions shall be implemented in the PMS:
operation guidance giving the most appropriate configuration of running
plant to meet the predicted and current power and water demands with
the given available plant (distribution of information shall be via the data
highway)
optimal load distribution
a visual display of the measured plant efficiency deviation from the
reference plant efficiency in meaningful units (generated power, fuel
consumption, etc.), identification of reasons and output of diagnostics.
alarm warning (when the operational configuration of the plant has to be
changed to maintain adequate control margins).
an off-line function permitting the operator to explore the influence on
plant output, efficiency and control margins of different plant operating
configurations.
mass and energy balances for the entire Power and Desalination Plant
printing of monthly and daily management reports including all
important parameters of the plant.
To achieve the above control functions the following supporting
functions are anticipated: on-line performance calculations
reference efficiency characteristics to be provided for each GTG, HRSG,
STG, desalination unit.
on-line efficiency assessment of each GTG, HRSG, STG, and
desalination unit.
Performance optimization of the major equipment
Data representation in a graphical form
entry facility for the expected daily electrical and water load demand.
entry facility for the plant outage log.
entry facility for unit prices in local currency
full on-line status monitoring.
calculation functions, statistical evaluation and integration of user
programs (to be executed automatically or manually).
trend log
incident (trip) review log

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

1.4.10

Page 86 of 178

Rev. 0

C&I log
Process parameter reports/logs
event information log
data export to standard office software
System software data base shall be open architect for flexible interfaces
Support decision taking processes by extending data access to all
relevant information

CCR equipment
Initial basic design drawings and preliminary and final drawings, showing
the detailed arrangement of CCR equipment shall be prepared by a
specialized company with this specification in mind and in compliance with
the requirements of sound ergonomics and aesthetics, good operability,
clear layout, interior architecture, color and expedient illumination. Final
layout shall be prepared by careful consideration of the ergonomic aspects
and up-to-date control design principles. The documentation is subject to
separate approval of Employer/ Engineer.
The layout of the operating consoles shall be such that in normal operation
one operator shall be able to handle the tasks allocated to each Control
Desk.
The CCR noise levels shall not exceed 45 dB (A). A clear layout shall
permit an easy operation and supervision of the plant.
In the area of the operator stations a suitable glare free illumination shall be
provided.

1.4.11

Large screen projection panels (LSPP)


For the Station overview display modular large screen projection systems
shall be provided, each in front of the different Control Desks. The LSPP
for the Water Control Desk will be supplied under the Contract of Package
D.
The projection system shall be state of art, preferably based on thin film
transistor-liquid crystal display (TFT LCD) or similar technology. The
minimum size of each display shall be 2000 x 1500 mm (WxH)
approximately.
The display shall be aesthetically integrated in a panel and into the CCR
environment in a manner that maximizes operator ergonomics. The system
shall be capable of displaying any graphic screen available in the DCS and

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 87 of 178

Rev. 0

special graphic displays created for the large screen projection system. The
system shall be supplied with dedicated keyboards and mouse.
The independent system shall be seamlessly integrated in the DCS
providing the same basic functionality as any other VDU-based DCS
display. The system is shown in the typical overall DCS architecture as per
Annex P-C13-1.
It shall be possible to use the system as one screen or as multi-screen
system.
The offer shall contain:
a detailed description of the projection technology including type,
resolution, optimum viewing distances, brightness and all required
hardware and software
a detailed description of the DCS interface for the system
references for the use of the offered system for power and/or desalination
plant
description of maintenance including maintenance intervals and
maintenance costs
number of plant overview displays for the system included in the offer.

1.4.12

Conventional fascia alarm system


The conventional alarm system shall be based on modular plug-in units. At
least 20% spare capacity shall be included.
The alarm system/plant signal interface shall be adequately protected to
minimise the possibility of damage to the alarm system resulting from input
disturbances such as grounding of either input lead, electromagnetic signal
pick-up etc. The method of isolation shall be stated (i.e. optical isolation
etc.) and the common mode and series mode rejection voltage levels for
signal interference and input stage damage shall be stated.
The field signal connections shall be to terminal blocks separating the
internal wiring from the external cabling. This may be arranged by a system
of shorting links associated either with the input marshalling terminations or
by facilities actually incorporated within the alarm monitoring system. The
facility shall ensure that any inhibit may be readily identified.
The display units shall consist of rectangular frames or bezels enclosing the
specified number of individual fascias, each of which shall be
approximately 32 mm x 50 mm or 32 mm or 25 mm in size as approved by
the Engineer. Each fascia shall be in the form of a window inscribed with
the specified legend. Alarm legends shall be in clear text succinctly and

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 88 of 178

Rev. 0

consistently describing the alarm condition. Alarm legends shall be


submitted to the Engineer for approval. Abbreviations, if approved, shall be
in accordance with an agreed schedule of abbreviations.
Alternatively, LED lamps for indication can be used and the alarm
description has to be written in adequate letter size beside.
The positioning of alarm windows on the control panel in the CCR shall be
arranged such that the indicators are arranged in logical manner to the plant
/ systems arrangements.
Two types of alarm sequence may be required as detailed in the specific
requirements.
(a)
(b)

individual alarms of the manual-reset type


as in (a) but including a first-up facility, if relevant

Generally type (a) shall include facilities for 'Horn silence' push-button,
'Alarm accept' push-button and 'Lamp test' push-button. Although automatic
reset is required, this shall not occur until an alarm has been accepted
irrespective of whether alarm status has disappeared prior to pressing of
'Alarm accept' push button.
'Horn silence' and 'Alarm accept' functions of conventional alarm fascias
and alarm system of DCS shall be combined that one single command will
quit the alarms in both systems.
For alarms of the first up type, the sequence shall identify the first alarm in
a group to be initiated by a different flashing frequency. This form of
identification shall continue until a separate First-up Reset button is
depressed which will allow the alarm to be treated in the normal manner.
Resetting the 'first-up' will allow subsequent alarms to initiate the first-up
presentation. Under no circumstances should a standing alarm inhibit
further operation of the first-up system.
The control equipment shall derive its power supply from the C&I system
supply as defined with specific requirements.

1.4.13

Asset management system / field device tools (FTD)


For configuration and diagnosis an asset management system shall be
provided for remote diagnostics and calibration.
The system shall be able to read all information from SMART transmitters,
analyzers and actuators independent of their manufacturer. Configuration
shall be possible from the centralized operator station (to be located in the

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 89 of 178
Rev. 0

engineering area of the CCR) through the data highway of the Plant DCS.
Data exchange with portable handheld devices shall be possible.
The system shall provide maintenance information and alarms for the O&M
crew to perform e.g. predictive maintenance activities.
Asset management system should have the following features:
FDT allows intelligent device-specific applications data (Status,
diagnostics, etc.) accessible to the system and enables applications such
as preventive and predictive maintenance and optimization
Field data that are available in intelligent field devices can be transferred
directly to the FDT.
Diagnostic function self-tests, calibration functions, update options for
parameters, or estimated remaining useful life time shall be realized in
the FDT.
Detect deviations in device functions at an early stage.

1.5

Interfaces
Interfaces for the specified Scope under this section shall be as indicated in
Part P-A3 (General Project Requirements-Limits of supply) as well Annex
P-C0-14.
The specific coordination works between package P and D shall be
considered as following.
DCS for Package P and Package D shall be of the same make and
type. The Contractor of Package D shall follow the decision made for
Package P. The Contractor Package P is responsible for the overall
DCS layout and design of the entire Power and Desalination Plant.
Integration and co-ordination of DCS equipment/functions supplied by
the Contractor Package D into the overall DCS shall be under the
responsibility of the Contractor Package P. Connection of process
stations and CCR equipment supplied by Package D to the data
highway shall be done by the Contractor Package P, including all
required cables and installation materials. In order to ensure a uniform
philosophy of:
control
protection
alarming
monitoring (e.g. graphic displays, colors)
operation
for the entire Power and Desalination Plant, the stipulation made for
Package P shall be taken on for Package D.
In order to minimize spare part holding, field equipment, instruments and
control systems shall be, as far as possible, of the same make and type
for Package P and Package D.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 90 of 178
Rev. 0

The asset management system / field device tool (see Annex P-C13-10),
vibration monitoring system (see Annex P-C13-8) as well as CEMS and
water quality monitoring system (see Annex P-C13-7) shall be unified
and interfaced. Package P shall provide the systems including bus
systems, redundant servers, operator stations and implementation works.
Package D shall provide the necessary field equipment for their scope
of supply of same make and type.
All CCR equipment (e.g. control desks, operator stations, printers) shall
be of uniform make and type. The stipulations made for Package P
shall be taken on for Package D. The integration and co-ordination of
CCR equipment and works supplied by Contractor Package D shall be
under the responsibility of Contractor Package P. A common general
layout for CCR shall be prepared by Contractor Package P. Connection
of CCR equipment (including cables) supplied by Package D to the
data highway of DCS shall be done by Contractor Package P.
The communication, clock and surveillance systems for the Power
Generation Island (Package P) and the Water Production Island
(Package D) shall be within the scope of supply of Contract Package
P. Therefore, all required data, drawings and information for
installation of telephones, loudspeakers, etc. in the area of Water
Production Island must be provided by Contractor Package D.
The following information shall be exchanged for co-ordination between the
Contractors at the given dates at the latest:
to be supplied
by/for

weeks after
award of
contract
(Package P)
4

make and type of DCS

Package P /
Package D

make and type of:


asset management system,
vibration monitoring system,
CEMS / water quality
monitoring
Plant management system
information for system integration
of:
asset management system,
vibration monitoring system
CEMS / water quality
monitoring
Plant management system
make and type of CCR equipment
(e.g. operator stations, printer,

Package P /
Package D

12

Package D /
Package P

30

Package P /

16

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Rev. 0

to be supplied
by/for
hardcopies, LSPP)

Page 91 of 178

weeks after
award of
contract
(Package P)

Package D

make and type of field equipment,


instruments and control systems

Package P /
Package D

16

preliminary layout and spatial


distribution of control desks and
panels in the central control room

Package P/
Package D1)

10

preliminary layout of instruments,


communication equipment,
emergency push buttons etc. on
the desks and panels

Package P/
Package D1)

final arrangement of control desks


in the central control room

Package D /
Package P

14

layout and building drawings for


installation of communication,
surveillance and clock systems

Package D /
Package P

26

fixed concepts concerning


control, protection, alarming,
operation and monitoring

Package P /
Package D

12

preliminary list of signals to the


DCS

Package D /
Package P

26

final list of signals to the DCS

Package D /
Package P

36

12

Package D /
Package P2)
20
26

Package D /
Package P2)

1)

for information
for final co-ordination
All documents have to be submitted to the Employer / Engineer for
Information.
2)

1.6

Terminal points
The terminal points for the specified Scope under this section shall be as
indicated in Part P-A3 (General Project Requirements-Limits of supply).

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

1.7

Page 92 of 178

Inspection and testing


The specified systems shall meet the relevant clauses of Part A5 as
applicable, unless otherwise specified in this section.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

Rev. 0

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 93 of 178

Rev. 0

2. Emission Monitoring System


2.1

General
This Part specifies all equipment required for emission monitoring of
exhaust gases and effluents released to the environment during operation of
Power and Desalination Plant.
The general technical performance requirements of the following systems
are covered:
Exhaust gas emission monitoring station(s)
Effluent monitoring station
Portable noise monitoring equipment
Data Evaluation System
with all necessary equipment for satisfactory operation of the emission
monitoring facilities.
All parameters requested in PME or in Royal Commission have to be
considered, even not mentioned explicit in the specification.
Contractor's supply shall include but not be limited to the engineering
design, manufacturing, performance testing, delivery, installation and
commissioning of the equipment.
All monitoring equipment for gaseous substances as well as the
corresponding calibration, data conversion and evaluation procedures shall
be in accordance with the relevant ISO Standards.
For the GTs/HRSGs the ISO Standards No. 11042-1 Measurement and
Evaluation and No. 11042-2 Automated Emission Monitoring shall be
applicable.
The systems and their components supplied shall meet this specification and
shall also conform to the applicable requirements of this and other general
clauses in General Technical Requirements.

2.2

Layout
The layout arrangement of the monitoring stations shall provide adequate
access for safe, simple and easy operation.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

2.3

Page 94 of 178

Rev. 0

Scope of Supply and Services


All equipment listed below shall be of high sophisticated technology
supplied from reputable manufacturers.
Therefore high end hardware and software designed for use in power plants
at this specific project circumstances shall be supplied.
Continuous monitoring equipment for the following exhaust gas emission
and reference parameters shall be provided for each GT/ HRSG stack and
each GT bypass stack:
NOx
SO2
Dust
O2
CO
CO2
Exhaust gas temperature
Exhaust gas pressure
Sample probes and sampling lines (unit-wise)
Measuring container with sampling system, analyzer, calibration bottles
for automatic calibration and data gathering (unit-wise)
Continuous monitoring equipment for the following effluent parameters
shall be installed at the discharge pipe of waste water and boiler
blowdown:
pH-value
Waste water discharge flow
Waste water discharge temperature
Data acquisition module (pre-processing unit)
Three (3) personal computer workplaces for separate evaluation of the
emission monitoring and sample analyses results with connection to the
main DCS system, allowing extraction of the emission monitoring data
and relevant reference parameters from the DCS for environmental
analysis and to send information to the CCR operator stations. Two PC
workplaces shall be located in the computer room of the central control
building, one workplace shall be located in the superintendents office.
Weather station
One (1) portable noise monitoring system for regular check of the noise
impact at different facilities of the CCPP shall be provided.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 95 of 178

Rev. 0

Documentation
All documents and information requiring checking and approval by the
Engineer in accordance with Part A3 shall be submitted.
All important design documents shall be submitted for approval to the
Engineer as per approved procedure.
Training
The Tenderer shall include in his offer the provision for training for all I&C
systems and equipment to the client's management, operation and
maintenance staff in accordance with the requirements specified under Part
A3.
The training shall cover all components of CEMS and effluent monitoring.

2.4

2.4.1

Particular Technical requirements

Exhaust gas Monitoring Stations


The RAS AZ ZAWR Power and Desalination Plant - Phase I consists of five
(5) or six (6) blocks with two (2) gas turbines and two (2) HRSGs each.
The Plant shall be equipped to continuously monitor and record the gaseous
stack emissions. Measurements shall be in accordance to the respective
regulations and national standards. Complete CEMS selected must comply
with local regulatory requirements from Kingdom of Saudi Arabia (e.g
Regulation of Royal Commission and Presidency of Meteorology and
Environment (PME) Environmental Protection Standards document No.
1409-01) for monitoring and reporting.
Exhaust gas emission monitoring stations shall be installed as follows:
one at each GT bypass stack
one at each HRSG and
Provision shall be made that all measuring sensors and instruments are
working properly under the prevailing measuring conditions.
The system main components shall be the

Sample probes
Temperature controlled heated sample lines
Condensate pots
Sample gas pumps
Sample coolers
Solenoid valves system
Multi-component analyzer system

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 96 of 178

Rev. 0

Calibration gas bottles filled with gas for automatic calibration


Data acquisition modules
Emission calculator
Emission Monitoring computer system for data evaluation

The sample coolers, analyzers and pre-processing equipment shall be


installed in individual air conditioned container near to the stacks at 0,00 m
level. The Emission Monitoring computers shall be installed in the
engineering room close to the CCR.
Equipment handling the samples shall be of corrosion and temperature
resistant material.
Appropriate protection against lightning has to be provided.
Measuring Instruments
Measuring modules for NOx, SO2, CO, CO2, Humidity, O2, as well as
sample temperature and pressure shall be provided for each monitoring
station, capable of future system extension (addition of sensor modules). For
the gaseous substances a multi-component Analyzer system shall be used.
Analyzer with self testing and auto calibration shall be provided.
Each exhaust gas emission monitoring station shall include the following
measuring instruments:
NOx-Monitor
Method: non-dispersive infrared absorption or UV
Analyzer including cubicle and sampling probe capable of self testing
and auto calibration
Measuring ranges: 0 - 1000 ppm in appropriate ranges
Resolution: better than 0.5 % of full scale of range used or 1 ppm,
whichever is greater
Repeatability: better than 1 % of full scale of range used or 1 ppm,
whichever is greater
Stability: better than 2 % of full scale of range used or 1 ppm,
whichever is greater, over a period of 2 h
Zero drift: better than 1 % of full scale of range used or 1 ppm,
whichever is greater over a period of 2 h
Noise: 0.5 Hz and greater, less than 1 % of full scale of range used or
1 ppm, whichever is greater over a period of 2 h
Response time: < 10 s from entry of the sample into the analyzer to
attaining 90 % of the final reading
Signal output: 4 - 20 mA
Status signal outputs

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 97 of 178
Rev. 0

ambient operation conditions: 5 - 50 C


calibration gas to be included
SO2-Monitor
Method: non-dispersive infrared absorption or UV
Analyzer including cubicle and sampling probe capable of self testing
and auto calibration
Measuring ranges: 0 - 50 ppm and, in appropriate ranges up to 1000 ppm
Resolution: better than 2 % of full scale or 2 ppm, whichever is greater
Repeatability: better than 1 % of full scale of range used or 1 ppm,
whichever is greater
Stability: better than 3 % of full scale of range used or 1 ppm,
whichever is greater, over a period of 2 h
Zero drift: better than 2 % of full scale of range used or 1 ppm,
whichever is greater over a period of 2 h
Noise: 0.5 Hz and greater, less than 2 % of full scale of range used or
0.05 %, whichever is greater over a period of 2 h
Response time: < 50 s from entry of the sample into the Analyzer to
attaining 90 % of the final reading
Signal output: 4 - 20 mA
Status signal outputs
ambient operation conditions: 5 - 50 C
calibration gas to be included
O2 Monitor
Method: Continuous Paramagnetic Oxygen Analyzer
Analyzer including cubicle and sampling probe capable of self testing
and auto calibration
Measuring ranges: 0 - 25 vol % in appropriate ranges
Resolution: better than 0.2 % of full scale of range used or 0.05 %,
whichever is greater
Repeatability: better than 0.2 % of full scale of range used or 0.05%,
whichever is greater
Stability: better than 2 % of full scale of range used or 0.05 %,
whichever is greater, over a period of 2 h
Zero drift: better than 0.2 % of full scale of range used or 0.05 %,
whichever is greater over a period of 2 h
Noise: 0.5 Hz and greater, less than 0.2 % of full scale of range used or
0.05 %, whichever is greater over a period of 2 h
Response time: < 50 s from entry of the sample into the Analyzer to
attaining 90 % of the final reading
Signal output: 4 - 20 mA
status signal outputs
ambient operation conditions: 5 - 50 C

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 98 of 178
Rev. 0

CO Monitor
Method: Non-dispersive infrared
Analyzer including cubicle and sampling probe capable of self testing
and auto calibration
Measuring ranges: 0 - 2 500 ppm in appropriate ranges
Resolution: better than 0.5 % of full scale of range used or 1 ppm,
whichever is greater
Repeatability: better than 1 % of full scale of range used or 2 ppm,
whichever is greater
Stability: better than 2 % of full scale of range used or 2 ppm,
whichever is greater, over a period of 2 h
Zero drift: better than 1 % of full scale of range used or 2 ppm,
whichever is greater over a period of 2 h
Noise: 0.5 Hz and greater, less than 1 % of full scale of range used or
1 ppm whichever is greater over a period of 2 h
Response time: < 50 s from entry of the sample into the Analyzer to
attaining 90 % of the final reading
Signal output: 4 - 20 mA
status signal outputs
ambient operation conditions: 5 - 50 C
CO2 Monitor
Method: Non-dispersive infrared analyzer
Analyzer including cubicle and sampling probe capable of self testing
and auto calibration
Measuring ranges: 0 - 20 % in appropriate ranges
Resolution: better than + 0.5 % of full scale of range used or 100 ppm,
whichever is greater
Repeatability: better than 1 % of full scale of range used or 100 ppm,
whichever is greater
Stability: better than 2 % of full scale of range used or 100 ppm,
whichever is greater, over a period of 2 h
Zero drift: better than 1 % of full scale of range used or 100 ppm,
whichever is greater over a period of 2 h
Noise: 0.5 Hz and greater, less than 1 % of full scale of range used or
100 ppm, whichever is greater over a period of 2 h
Response time: < 50 s from entry of the sample into the Analyzer to
attaining 90 % of the final reading
Signal output: 4 - 20 mA
status signal outputs
ambient operation conditions: 5 - 50 C
Dust Monitor

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 99 of 178
Rev. 0

Method: Continuous measuring of optical transmission or triboelectric


method
Analyzer including cubicle and optical installation or sampling probe,
capable of self testing
Measuring range: 0 - 200 mg/m3
Resolution: 2 % of full scale of range used
Detection Limit : 2 % of full scale
Signal output: 4 - 20 mA
status signal outputs
ambient operation conditions: 5 - 50 C
Measuring Locations
Sample extraction facilities for measurement of NOx, SO2, CO, CO2, O2,
H2O concentration as well as dust, temperature and pressure sensors shall be
installed at each GT bypass stack and each HRSG stack approximately 3 m
below the stack outlet on the highest boiler platform. The sample system
shall be switched automatically the extraction depending on operation mode
between bypass stack and HSRG probe.
The extracted exhaust gas shall be transferred through heated sample lines
to the measuring instruments mounted in the emission monitoring container.

2.4.2

Effluent Monitoring
All effluent monitoring shall take place at the outlet pipe of the waste water
monitoring basin.
The average effluent conditions will be as follows:
Average effluent temperature:
approx. 30C (depending on ambient
temperature)
Average effluent pH:
6-9
Continuous Measuring Instruments
One effluent monitoring station shall be provided, including the following
continuous measuring instruments:
Combined pH and Temperature Monitor
Method (pH): Redox electrode (Ag+/AgCl/Cl- or polymer electrolyte
system)
Method (temperature): Thermistor sensor (resistance measurement)
Analyzer including cubicle and pH-electrode capable of auto calibration
and self testing
Measuring range and resolution (pH): 0 - 14 + 0.05 pH
Measuring range and resolution (temperature): 0 - 60 C + 0.2 K
Automatic temperature compensation of pH measurement
On-line display for actual measurement values

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 100 of 178

Rev. 0

Signal output: 4 - 20 mA
Status signal outputs
ambient operation conditions: 5 - 50 C
Two spare pH-electrodes to be provided

Discharge Flow Monitor


Method: Electromagnetic flow sensor
Analyzer including cubicle and measuring sensor capable of self testing
Measuring range and resolution (pH): 0 - 14 + 0.05 pH
Measuring range and resolution (temperature): 0 - 100 C + 0.2 K
On-line display for actual measurement values
Signal output: 4 - 20 mA
Status signal outputs
ambient operation conditions: 0 - 50 C
Measuring Locations
Sample Extraction for Laboratory Analyses:
A tapping shaft for extraction of samples for laboratory analyses shall be
provided and installed at the discharge line of the waste water monitoring
basin, before the waste waters are mixed with the circulating cooling water
and discharged to the sea.
Continuous Effluent Monitoring:
The sensors for continuous monitoring of effluent pH and temperature shall
be located within the sample-tapping shaft. The flow sensor shall be
mounted within the discharge line.
The corresponding electronic equipment shall be mounted in a weatherproof
container to be located nearby the point of measurement at the discharge
pipe of waste water and boiler blowdown.
The corresponding analogue measuring signals (4-20 mA) and the status
signals (24V DC) shall be transmitted by multicore cables to the DCS.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

2.4.3

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 101 of 178


Rev. 0

Cubicles and Measuring Containers


All cubicles for air pollutant and for effluent parameter measurement shall
be mounted within weatherproof measuring container(s) with redundant air
conditioning.
All measuring containers shall be equipped with sun protection roofs. The
cubicles and containers shall be of solid and rigid design. They shall be
painted at least with two coatings.
Cubicles shall be constructed of braced rolled steel sheet of at minimum of
1 mm thickness with a rigid structure that will not distort during
transportation and after installation. The front door shall be equipped with
glass windows in order to allow the supervision of the instruments without
opening the front door. The cubicles shall have a pocket for the
documentation necessary for service and maintenance.
The doors of containers and cubicles shall have a lock.
The data acquisition system, analyzers and control systems shall be powered
by UPS.

2.4.4

Data Acquisition/Storage/Evaluation/Visualization
The results of the measurements performed automatically by the emission
monitoring equipment (continuous stacks and effluent emission monitoring)
as well as the required analogue and status signals shall be pre-processed in
a data acquisition module and transmitted to the main DCS. Separate
evaluation, storage and visualization for environmental analysis shall be
carried out on personal computer (PC) workplaces, which shall be
connected to the DCS for extraction of the relevant emission monitoring
data and reference parameters of plant operation.
Provision shall be made that all signal exchange between measuring
containers, power plant control panels and data evaluation system is made
using interfaces for galvanic signal isolation.
A structure of the CEMS is given in Annex P-C13-7.
Data Acquisition Module
The data from the continuous emission monitoring instruments shall be
converted to appropriate physical units in a pre-processing computer (data
acquisition module) which shall be connected to the main DCS system (per
block) for data evaluation, storage and visualization.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 102 of 178


Rev. 0

The data acquisition module shall sample the analogue and status signals,
perform corrections related to standard conditions, automatic comparison
with applicable limits and output of corresponding alarm messages,
calculate time averages of analogue signals taking into account the
corresponding status information and provide a circular data buffer of at
least five days of estimated emission characteristics. Data acquisition and
data evaluation shall be performed in accordance with approved regulations
of emission monitoring (e.g. ISO standards or equivalent). All monitoring
equipment provided shall also comply with local environmental regulations,
if applicable. The Contractor shall inform himself about the latest edition of
all applicable local standards and legislation.
The data acquisition module shall be adapted to facility requirements by
means of a configuration tool, no software programming shall be allowed to
follow changes of facility requirements.
All relevant signals (also from Package D) have to be considered in this
emission monitoring system.
Signal Output to DCS System and PMS
The actual emission concentrations of NOx, SO2, CO, CO2, Dust, and O2
measured at the installed exhaust gas monitoring stations, the effluent
parameters pH, temperature and flow, as well as the corresponding alarm
messages (instrument failure, limit exceeded) shall be made available for the
DCS system of the Plant as well on the PMS. CEMS data shall be visualized
in the DCS and PMS in tabular form or in graphical form.
All conventional signals interfaced with the DCS shall be made available as
potential free contact for binary and as galvanic isolated 4-20 mA for
analogue signals.
Data Extraction from DCS to the PC Workplaces
All PC workplaces for separate evaluation of environmental data shall be
connected to the main DCS system, allowing extraction of the pre-processed
emission monitoring data, as well as the relevant operational reference
parameters such as fuel consumption, generated power, etc. for any given
time period from the DCS for the analysis, correlation and assessment of
environmental impacts.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 103 of 178

Rev. 0

Design of PC Workplaces
One CEMS workplace shall be installed in the superintendents office.
Additional two computer workplaces and the CEMS engineering station
shall be located in the engineering room of the central control building.
All PC workplaces shall be equipped with the required standard office
computer hard- and software including spreadsheet calculation, graphic tool,
word processing, data base management, and modem connection to the
telephone system for on-line data transmission and sufficient data storage
capacity.
The application software of the PC Workplaces shall allow the following
functions:
Extraction of Data from DCS on request for environmental evaluation for
any selected time interval, collection of Channels ad lib, including gas
turbine operation data (GT fuel consumption, power output, etc.)
Password protected access to the computer system, user rights be
definable by a system administrator
Display of on-line values
Output of emission concentration values alternatively in mg/MJ, mg/m
at standard conditions, or ppm vd.
Automatic comparison with applicable limits, color indication and alarm
messages in case of exceeded limits. The Contractor shall inform himself
about applicable local/international standards and legislation.
Comparison shall be made using the unit mg/MJ and referring to the
actual calorific value of the fuel used. A corresponding input routine for
the calorific value shall be provided
Graphical presentation of results (bar charts, tables, trends) on monitor
and printer
Indication of margin left until limit is reached
Frequency distribution of data (classification)
Preparation, storage and handling and keyword access of free definable
record sheets
Automatic preparation of emission monitoring reports for monitor,
printer and modem from the system database. These reports shall be
saved and printed out in regular intervals or on request. The contents of
these reports shall be free definable by the user (e.g. report containing
mean and peak values within a defined time period)
Output for standard software (word processing, spreadsheet calculation,
database, graphic programs, etc.)
Diagnosis function for check of all connected subsystems

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 104 of 178

Rev. 0

Alarm Messages
Alarm Messages shall be displayed at data acquisition module and
automatically transmitted to the DCS system of the Plant in case of
instrument failures and in case applicable emission limits are exceeded.
In case of exceeded limits alarm messages shall be indicated at the DCS
showing the measured value and the corresponding limit value for
comparison. The alarm messages shall be repeated in intervals of some
minutes as long as limits are exceeded. The alarm messages shall not disturb
the normal software operation and working procedures.
Power failure and system failures of analyzers shall be monitored in the
central control room by a group alarm and transmitted automatically to the
DCS.
PC Workplaces
Specification of PC shall be of state of art during the installation with a
minimum requirement as specified.
Two PC workplaces shall be provided including the following hardware:

personal computers , each with the following specification:


high end PC
at least 2x 120 Gbyte IDE or SATA Hard disks
CD /DVD drive etc.
20, TFT Monitor
with mouse and Keyboard
Network adapter to DCS for data extraction from DCS and Office LAN
2 color printers
Office furniture (2 workplaces)
Safe power supply

All computer inputs/outputs software programs and documentation shall be


in English.
Access to the computer system shall be password protected, user rights shall
be definable by a system administrator.
Automatic data safety backup shall be performed automatically on a second
hard disk drive in regular intervals. System booting routine shall be possible
with both hard disk drives.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 105 of 178

Rev. 0

Data Output by DCS system


For evaluations of the emission monitoring data the software of the DCS
shall be designed for the following tasks:
Automatic data acquisition from connected sub-systems (data acquisition
module)
Display of on-line values
Output of emission concentration values alternatively in mg/MJ, mg/m
at standard conditions, or ppmv
Automatic comparison with applicable limits, color indication and alarm
messages in case of exceeded limits
Calculation of actual pollutant emission rates, based on calculated flue
gas volume flow rates
Data output and transmission to the two PC workplaces
Diagnosis module for check of all connected subsystems
Alarm functions on monitor and triggering of external alarm indicators
Periodical reporting in tabulation form shall be created automatically or
manually.

2.4.5

Weather Station
Weather station shall be provided for the following measurements:
ambient air temperature
ambient air pressure
ambient air humidity
wind velocity
All measurements of the weather station shall have local indication and all
signals shall be connected to the DCS for monitoring by the CCR operator
workstations.

2.4.6

Portable Noise Monitoring Equipment


The noise impact from plant operation shall be measured at different
locations in regular intervals to ensure compliance with applicable
standards.
For this purpose a portable noise monitoring system shall be provided
including the following items:
Sound level meter with standard features in agreement with the
regulations
Microphone and all accessories
Frequency analysis module

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 106 of 178

Rev. 0

Interface module for connection to personal computers


Noise level recorder
Printer
Calibration facilities
Maintenance materials
Meteorological instruments for hand use with sensors for wind velocity,
ambient temperature, humidity
Battery based power supply

2.5

Interfaces
The interfaces specified as follows are valid only for the system
demarcation and do not represent supply limitations.
Measuring instrument sensors at the HRSG and GT bypass stacks
Sensors of effluent monitoring instruments at the discharge pipe of waste
water and boiler blowdown
Water quality monitoring system
Connection to telephone system

2.6

Inspection and testing


The specified systems shall meet the relevant clauses of Part A5 as
applicable, unless otherwise specified in this section.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 107 of 178

Rev. 0

3. Communication, Clock and Surveillance Systems


3.1

General
This section of the Specification covers the supply of the specified
communication (telephone, radio and public address system), clock CCTV
(Closed Circuit Television) surveillance and LAN/WAN systems for the
entire RAZ-Phase 1 (Package P and Package D). The contractor package
"P" is responsible for the overall layout, design ,supply, installation and
commissioning for the entire RAZ-phase 1 (Package "P" and "D")
communication equipment.
The specified systems shall be state of the art and shall be adequately
proven for the specified application. Wherever applicable, the systems shall
meet the approval standards of the local regulatory authorities for the
specified application. Wherever applicable, other relevant parts of the
Specification shall be applied to meet the specified requirements of this
section.
The scope shall include all the works associated with the provision of the
following systems:

3.2

3.2.1

Telephone system
Portable radio system
Public address system
Process related CCTV surveillance system
Clock system
Office LAN/WAN system

Scope of supply and services

General
This sub-section sets out the scope for the specified communication, public
address system, clock, and process related CCTV equipment for the
installations covered by this Specification as well as supplies and services,
but without excluding other necessary components and services not
mentioned. This includes all the specified communication, clock and CCTV
equipment within the central control room (CCR), local electronic rooms
(LER), local control rooms (LCR), the relay rooms and associated field
mounted equipment, which fulfils the specified communication, clock and
CCTV tasks. Sufficient equipment to the satisfaction of the Engineer shall

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 108 of 178


Rev. 0

be provided to meet appropriately the operational and safety requirements of


the plant.
The Contractor shall be responsible for all engineering, design,
manufacture, programming, configuration, documentation, materials,
supplies, factory and field testing, delivery, installation, start-up, tuning and
initial operation through completion of the work specified.

3.2.2

3.2.2.1

Scope of supply

Telephone system
The complete system, as specified including, but not limited to the
following (Contractor has to define the quantities of equipments to cover the
whole Plant, for Package D the following numbers shall be considered):
IP-PABX (Private Automatic Branch Exchange) with exchange lines to
the public telephone system and spare capacity for additional users (at
least 1500)
At least 500 telephone sets (plus 250 sets for Package D)
At least 250 DECT components (mobile phones) (plus 100 mobile
phones for Package D)
one (1) telephone operators console
call monitoring and diagnostic software
one (1) system printer
one (1) set of uninterruptable power supply equipment including charger
and battery
tele-picture transmitter (telefax) (at least 10)
1 internal battery set.
5 chief-secretary extensions
One telephone set for each of the operator desks in the CCR
Two telephone sets for the supervisor in the CCR.
Four (4) telephone sets for e.g. the superintendent, for the lead electrical
engineer and two spare for direct LDC communication
One telephone set for each of any local control room, local operator
board, local GT cabinet, if applicable
Two telephone sets in each of the offices
Executive sets for the station manager, senior discipline engineers and
shift supervisors offices
At least one telephone set in each of the electric and electronic
equipment rooms unit-wise
At least one telephone set in each of the occupied (manned) rooms, like
workshops, etc.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 109 of 178

Rev. 0

At least one telephone set in each of the common rooms (meeting rooms,
canteen, training room, archive, etc.)
At least one telephone set for each major process, seawater, desalination
plant, etc., system indoor and outdoor
telephone booths for specified locations
necessary cables, junction boxes, etc
one (1) set of necessary furniture for operators console
interfaces to specified public address system

3.2.2.2

Portable radio system


The complete system, as specified including, but not limited to the
following:
Base station tower
Two hundred (200) sets of portable UHF transceivers (intrinsically safe
radios) and rechargeable batteries as well additional spare batteries with
charger units
Twenty (20) shall be provided for hazardous areas
Thirty five (35) fixed radio stations shall be provided for mounting in
cars
Five (5) desk radio stations with rechargeable batteries as well additional
spare batteries with charger units
Two hundred (200) carrying case with shoulder strap
Repeater stations, if necessary

3.2.2.3

Public address system


The complete system, as specified including, but not limited to the
following:
one (1) central amplifier station complete, for not less than 80 loudspeaker lines, and modularly expandable up to 150 lines
one (1) master call station located in CCR
sufficient numbers of outdoor and indoor call stations
sufficient numbers of outdoor and indoor announcing stations
(loudspeakers) to cover all the work space of the premises (at least 40 for
Package D have to be considered)
specified interfaces to the telephone system
one (1) set of uninterruptable power supply equipment including charger
and battery

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

3.2.2.4

Page 110 of 178

Rev. 0

Process related CCTV surveillance system


The complete system, as specified including, but not limited to the
following:
Sufficient number of color cameras including lenses, mountings and
housings to cover the Package P area (plus at least 40 for Package D)
color monitors for CCR, guard houses, administration building and fire
brigade and two additional locations
pan/tilt units for moveable cameras
video matrix switcher and control system
digital video tape recorders
video transmission system including cabling, launch, line, equalizing,
repeating amplifiers, etc
interface to other systems e.g. fire alarm system

3.2.2.5

Clock system
The complete system, as specified including, but not limited to the
following:

one (1) number of master clock (redundant) complete


at least fifty (50) numbers of slave clocks (and 20 for Package D)
Minimum of two(2) wall clocks for CCR
one (1) number of uninterruptable power supply equipment including
charger and battery
serial interfaces for synchronizing all control systems of the Plant (DCS,
PLCs etc.)
GPS (Global Positioning System) interface for synchronizing the Clock
System.
Final amount of clocks are subject for final requirement during the
engineering phase.

3.2.2.6

Office LAN/WAN system


As a minimum a Local Area Network (LAN) between all offices and
secretary offices, conference rooms, training rooms, computer rooms,
storekeeper offices, workshops and other locations with comparable
functions shall be provided for the in the Plant (Package P and D). The
scope contains the cabling, distribution/marshalling and connectors only
without computer equipment like servers, workstations and PC-s for the
complete Office LAN itself. However all components necessary for the

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 111 of 178

Rev. 0

network operation itself, like repeaters, switches, etc., shall be provided


together with the system.

3.2.2.7

Spare capacity after commissioning


At least 20% free space shall be available in all cubicles, junction boxes and
marshalling racks after final commissioning. This free space shall be
distributed inside the cubicles in such a way that additional terminals,
equipment or modules may be added to any group of controls. At least 20%
spare cores shall be provided in each cable. All spare cores shall be
terminated.
Each module shall be sized such that no more than 60% of its installed
capacity is utilized during normal operation and shall not exceed 80% even
under extreme load condition.

3.2.2.8

Spare parts and special tools


All necessary spare parts (for five years operation), wear and tear parts,
maintenance equipment and special tools shall be part of the scope of supply.
The Tenderer should consider at least 10% of all different, installed I&C
components (I/O Modules, fuses, etc) or at least one individual piece of
equipment as required spare parts in the scope.
The Tenderer shall include a list with individual prices of all spare parts he
recommends should be held by the employer to enable the plant to be
operated efficiently considering maintenance and repair.
Any parts ordered must be strictly interchangeable and suitable for use in
place of the corresponding parts supplied with the contract works. Each
spare part item shall be marked with the equipment name and designation
number corresponding to the appropriate section of the operation and
maintenance manuals.
All required spare parts, wear and tear parts, maintenance equipment and
special tools (see also Part P-A3) shall be part of the scope of supply.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

3.2.3

3.2.3.1

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 112 of 178


Rev. 0

Scope of Services

General
All services required for a safe, reliable, efficient and trouble free operation
of specified Communication, CCTV and Clock equipment, complete in
every respect, without excluding other necessary services not mentioned
below, shall be provided by the Contractor. These services shall include but
not be limited to:
examining of existing documentation
design of all equipment to be supplied
documentation of all equipment to be supplied including revision of
existing documentation where modified
programming of all digital equipment
testing in the Contractors/Vendors workshop and on site (FAT and SAT)
packing, transportation to site, unloading and proper storing
on time delivery of all documents needed for proper assembly
handling from site storage to the point of final installation
erection of all parts to be supplied
commissioning of all equipment, including modifications of the existing
systems, if essential for any specified integration with new systems
trial operation
acceptance tests
The Contractor is responsible for the co-ordination of the interfaces and
overall design of all package equipment or other equipment supplied by
other sub-contractors and for making sure that the design of this equipment
and the submitted documentation is in line with the General Project
Requirements (Part P-A3) and Technical Specification (Part-P-B03), but it
is expected that this co-ordination activities shall be done by the supplier of
the main control, instrumentation and monitoring equipment.
The Contractor Package P is responsible for the overall layout and design
for the entire RAZ-Phase 1 (Package P and D).
As far as the final execution of the work is concerned all design data,
interlocking conditions, control loops and logic diagrams supplied by the
various sub-contractors shall be checked, verified and closely coordinated
with the other sub-contractors of the corresponding equipment. For this
purpose close collaboration with all sub-contractors supplying control
equipment shall be arranged.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 113 of 178

Rev. 0

All important design documents shall be submitted for approval to the


Engineer. A detailed time schedule for the drawing approval procedure shall
be submitted by the Contractor at the beginning of the design phase.

3.2.3.2

Erection, cabling, wiring and labeling


The scope of this Contract covers complete erection, cabling and wiring of
specified Communication, CCTV and Clock equipment as well Office
LAN/WAN system and shall comply with the General Requirements stated
under Part P-B02 and P-B03.
The Contractor shall be, in all cases, fully responsible for the correct
installation and erection with regard to the functions of all the supplied
equipment.
All cabling for the field equipment in the scope of this Contract, shall be
supplied, laid and terminated.
For the supplied field cabling all necessary cable routes, supporting
traywork and intermediate marshalling shall be provided.
A common system of earthing for cable armoring, cable screens, signal
cubicle earthing shall be agreed with Engineer.
All field equipment shall have nameplates with the instrument tag number
and descriptor. The nameplates shall be fixed to the mounting plate, the
mounting brackets or junction box. Loosely attached nameplates by wires
are not acceptable. Label material and writing shall be selected to withstand
the environmental conditions where they are mounted. The label size and
fixing place shall be selected to allow easy reading.
Inside the electronic cabinets, all equipment shall be labeled.

3.2.3.3

Commissioning, trial operation and Acceptance tests


The Contractor shall be entirely responsible for the commissioning of the
specified Communication, CCTV and Clock equipment. Commissioning
shall be carried out in accordance with the commissioning procedures
prepared by the Contractor and approved by the Engineer.
The scope includes:
trial operation;
performance of acceptance tests.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 114 of 178

Rev. 0

The general requirements regarding inspection and testing are included in


Part P-A5 of the Specification.
The Contractor shall make all necessary provisions for the site testing and
commissioning of the specified Communication, CCTV and Clock
equipment which include but shall not be limited to the following:
the test calibration of all instruments prior to installation;
the functional test of instruments once installed
Cable test of all installed cables
All tests performed on site, including the results and deficiencies, shall be
recorded and the test protocols shall be submitted to the Engineer for
approval.

3.2.3.4

Documentation
All documents and information requiring checking and approval by the
Engineer in accordance with Part P-A3 shall be submitted.

3.2.3.5

Training
The Tenderer shall include in his offer the provision for training to the
Client's management, operation and maintenance staff in accordance with
the requirements specified under Part P-A3.

3.3

3.3.1

Technical requirements

General
These Technical Requirements shall be binding for the specified
Communication, CCTV and Clock equipment within the Scope of the
Contract. They do not relieve the Contractor of any of his responsibilities.
The Requirement of the Security Directives of HCIS (High Commission
for Industrial Security) have to be considered.
Should it not be possible to comply with specific provisions of these
Requirements, or if their observance would result in technical
disadvantages, the Contractor is obliged to point this out at the tendering
stage in the form of a deviation list which will be subject to review and
approval of the Engineer/Client. Once a final deviation list is approved at
the tendering stage, no other deviation will be accepted after Contract
Award. The Contractor is obliged to settle the design in accordance with the

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 115 of 178

Rev. 0

Specification, considering the approved deviations only, in consultation


with the Engineer.
Equipment for the systems shall be planned, manufactured and installed in
accordance with this Specification, relevant laws, regulations, standards,
codes, guidelines and recommendations. The Contractor will be liable for all
defects resulting from non-observance of these.
Wherever applicable, General Technical Requirements (Part P-B03) shall
be met, unless otherwise mentioned.
The specified Communication, CCTV and Clock equipment shall preferably
be fed from the Stations safe AC power supply system.

3.3.2

3.3.2.1

Telephone system

General
The requirements specified under Part "General Technical Requirements"
are to apply and where applicable, further regulations from the other
sections of this specification. The telephone system has to be in line with the
Security Directive SEC 8 of HCIS.
The Telephone System shall be interfaced to the specified Public Address,
Systems.
Equipment and system shall be provided with easy access for maintenance
and calibration. Depending on their location of installation, the telephone
sets needed for the telephone installation are to be provided in dust-proof,
water-tight or explosion-proof versions and connected by corresponding
control cables. All equipment shall be designed for at least 50 C continuous
operation temperature. Outside installed equipment shall be designed for at
least 60C operation temperature.
In plant rooms / areas with a high noise level (e.g. pump room, burner
gallery) etc. and in the open, suitable telephone booths are to be provided.
Call lights are to be mounted on the roofs of the booths. In addition, an
auxiliary bell signaling for each incoming call shall be installed in the
vicinity of each booth and operating simultaneously with the call lights.
A telephone set shall be installed in each room with located personnel and
in every main process area, as near as possible to the local control panels.
The telephone sets needed in the power plant are to be provided as desk or
wall telephone sets according to place of installation.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 116 of 178

Rev. 0

The central switching assembly including the marshaling distribution panel


and operators switchboard shall be installed in the administration building.
For the telephone system and the IP based CCTV System, a separate
network shall be installed.
The telephone system shall be a modern, state-of-the-art hybrid Private
Automatic Branch Exchange (PABX) which combines packet-switched IP
and traditional circuit-switched Time Division Multiplex (TDM) telephony
on one platform. The IP-PABX shall be of micro processor based design
with non-volatile memories and shall have voice recording facilities,
especially for the operator telephone sets. The system shall be modular in
design, enabling flexibility in re-configuring, building up and expanding the
system when required. The system shall be compatible to the public
telephone system.
In general, the telephone system shall be designed with the following
features:
Internal traffic
Internal calls are set up automatically by all subscribers via the central
exchange.
Direct outward dialing
Outgoing trunk lines shall be provided for high speed connection to the
public telephone network.
Incoming calls go direct, or if the extension number is not known, the
operator can connect the caller to the required subscriber.
After normal working hours or if the switchboard is unattended,
incoming exchange calls go straight through to one or more extensions.
Depending on the location the different kinds of telephone sets shall be
foreseen (e.g. desk telephone set, wall mounted, explosion poof type,
special heavy duty types with telephone booths and alarm bells).
Billing system according to the local regulations
Cordless telephones according DECT standard for use within the
complete plant
Connection with or integration of public address system and portable
radio system.
Polycom phone sets shall be provided for conference phone meetings
A conference call facility shall enable the switchboard or another central
subscriber to connect groups of up to 10 subscribers for conference calls.. It
shall consist of, but not limited to automatic switching equipment,
telephones with the specified features, telephone hoods, etc.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 117 of 178

Rev. 0

The power supply shall be taken from the respective power supply.
The system shall not require standby batteries for its operation. Upon a
power failure, designated extensions shall automatically be connected to
exchange lines. When power resumes, calls in progress shall be
uninterrupted until completed when that line shall revert to normal use.
The Contractor shall install a Master Distribution Frame (MDF) for all
signals. The contractor shall terminate all telephone extension and all trunk
circuits on the MDF. The MDF shall also be equipped with clip jumpers.
All lines with external link shall be protected against any high transient in
voltage due to lightning or HV equipment switching. The MDF shall be
grounded.
The Contractor shall provide all equipment grounding and protection from
lightning and hazardous voltage potentials. The minimum acceptable
specifications of the manufacturer for signal grounding necessary for the
prevention of ground loops, excessive ground currents, abnormal groundpath surges of either polarity or spurious noise pickups shall be informed
with the offer.
The IP-PABX system shall have a wide set of features, specifically provided
focusing to utility applications. The following features are listed as a
minimum requirement.
The Contractor shall be responsible for detailed design, installation and
implementation of all switching equipment and associated software. This
shall include the development of the database, system tests and training of
staff. The Contractor shall provide all hardware and software necessary to
build a complete and fully operational switching system.

3.3.2.2

Telephone system features


Alternate path routing
In case of faulty lines the IP-PABX shall submit call requests to other lines,
as far as alternate lines are available.
Automatic bypass facility
In case of outage of an IP-PABX it shall be possible to keep the telephone
system operational as far as possible by means of automatic and/or manual
switching operations. This means e.g. through-connection of trunk lines
and/or subscriber lines according to a predefined priority schedule.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 118 of 178

Rev. 0

Test Call through out the Network


Test call (section dialing) shall allow authorized users to make calls via
specific trunks or hardware to test the trunk lines. Test call shall be
extended through out (possibly in multi-vendor) the network.
Priority Call facility
Priority calls shall allow the dispatchers at LDCs to override a busy line,
thus reaching any substation in case of emergency.
Caller ID/Call Logging
The incoming callers phone number, or name and number shall be
displayed at system display phones which are sent from a trunk. Caller ID
signaling type FSK and DTMF shall be supported. Answered and not
answered calls shall be logged. Logged calls shall be called back by
selecting the relevant call and pushing the redial button/key.
Calling Line Identification Presentation
The incoming callers phone number, or name and number shall be
displayed at system a display phone which is sent from an ISDN line.
Answered and not answered calls shall be logged. Logged calls shall be
called back by selecting the relevant call and pushing the redial button/key.
Automatic Number Identification
The incoming callers phone number, or name and number shall be
displayed at system a display phone which is sent from an E1 or T1 line.
Answered and not answered calls shall be logged. Logged calls shall be
called back by selecting the relevant call and pushing the redial button/key.
Call Forwarding
At least four types of call forwarding shall be supported: all calls, busy, no
answer and busy/no answer.
Automatic Call Back on Busy
When a called line or subscriber is busy it shall be possible to execute a call
back. When the busy line or subscriber becomes free the system shall
automatically alert the user that the extension has become free. Once the
line is picked up it shall automatically redial the line / subscriber that was
initially busy.
Conferencing
The IP-PABX system shall allow to set up multiple conference calls from 3party up to 8-party calls at the same time.
Busy trunk facility
It shall be possible to break-in into a busy trunk as well as to perform a
forced release.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 119 of 178

Rev. 0

Remote Extensions for stand apart Cabinets


Instead of installing IP-PABX equipment in a remote place, remote
extensions may be cost effectively be connected via analogue or digital
trunks. The IP-PABX shall be capable to configure such trunks to connect
extensions directly.
Trunks
The IP-PABX shall support SIP-based IP trunks and extensions.
Networking
The IP-PABX system shall provide variants of interfaces to inter-connect
with public network or tie line networks according to the communication
network environment. Line terminals, including copper cable or optical line
interfaces, shall be possible so that separate transmission equipment may be
avoided.
With a flexible routing concept the IP-PABX shall optimize connections in
call set up:

Preference route
Overflow routes
Multiple routing
Alternative routing with digit conversion
Priority extension routing

IP-PABX feature access via PCs


The IP-PABX shall support Computer Telephony Integration (CTI)
compliant to ECMA recommendations for Computer Supported
Telecommunications Applications (CSTA) to provide access to all system
features via PCs.
PC touch screen
The IP-PABX system shall provide a PC touch screen dispatcher operator
console and phone based dispatcher operator consoles.
IP gateway
The IP-PABX shall provide an integrated IP gateway for IP trunks and
extensions.
IP DECT
The IP-PABX shall support IP DECT locally and remotely.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 120 of 178

Rev. 0

Management
Local and remote management shall be supported through TDM and IP. The
management software shall provide solutions for:

3.3.2.3

Configuration management
Alarm reporting
DECT management
Accounting management
SNMP Gateway
Announcement
Operation & Maintenance terminal

Interface requirements
The interface characteristics of the equipment shall include the following:
Trunk network
The trunk side interface for DPLC multiplexer, digital Microwave and for
the fiber-optic segments of the network shall comply with primary rate
interface according to ITU-T, Rec. G.703. In addition, the following
interfaces types and functionality for the interconnection of the IP-PABX
with existing telephone exchanges and subscribers via existing analogue
PLC links shall be provided as a minimum requirement:
Analogue trunks:

subscriber signaling
DDI/DDO via pulse, MFC, DTMF
Polarity detection

Cordless extension:

DECT (GAP standard)


WLAN (SIP standard)

EURO ISDN
- Basic rate (2B+D)
- Primary rate (30B+D)
- CCIS over ISDN
- CCIS over E1
- Channel Associated (CAS 2 Mbit/s)
- MFC

Digital trunks:

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 121 of 178

IP trunks:

10/100/1000 Mbit/s Ethernet


TCP/IP, H.323, T.38
G.711 A-law, -law
QoS (IEEE 802.1Q/p, ToS)
SIP (RFC 3261)
H.245
PROTIMS over IP
CCIS over IP

Analogue tie lines:

CEPT-L1
E&M (2/4 wire)
Loop disconnect
Local battery
CCIS over E&M

Digital tie lines:

CSTA interface:

2B+D or 30B+D with:


- BT DPNSS
- ETSI Q.SIG
10/100/1000 Mbit/s TCP/IP connection
(ECMA-179)

Subscriber interface
Signaling:
Transmission:
Termination:
Loop current

Rev. 0

Loop supervision
2-wire
600 Ohms resistive, balanced
20 mA DC minimum on a 1200 Ohm
loop (including instrument) with 42.5 volt
supply.

Cross-talk coupling
Worst case cross-talk attenuation shall be 75 dB minimum in the range
300 to 3400 Hz to be measured between any two pairs while connecting a
0 dBm level tone to the disturbing pair.
Absolute delay
The absolute one-way delay through the switch shall not exceed 1 nsec,
analogue-to-analogue, measured at 1800 Hz.
Bit errors
The exchange shall not introduce bit errors into a connection, which exceeds
one error in 108 bits averaged over a five-minute period.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

3.3.2.4

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 122 of 178

Rev. 0

Administration software and diagnostic facility


For each IP-PABX, it shall be possible for the user to enter the software
program and make changes and modifications regarding feature
assignments, line and trunk access, etc. PC shall offer local direct
connection to the IP-PABX, or centralized management and maintenance
for an IP-PABX network via PLC, F.O. and modems or combination of
them.
The Diagnostic facility shall allow the downloading of e.g. alarm history
and equipment status from each IP-PABX in the network to a
central station.

3.3.2.5

Signal tones
Signaling tones shall be in accordance with ITU-T. Telephone busy tones
(60 IPM) shall indicate that a telephone is busy. Fast busy tone (120 IPM)
shall indicate that the switching equipment or its trunk circuits are busy.
Answering tone shall be returned to the calling party to indicate that the
called number is ringing.
Tone and Pulse Compatibility
The switching equipment shall include Dual Tone Multi-Frequency
(DTMF) signaling.

3.3.2.6

Subscriber facilities
The IP-PABX equipment shall be implemented with the following network
and user facilities:
Direct Inward Dialing (DID): Routing of incoming calls from an
incoming trunk directly to the called party without operator intervention.
Direct Outward Dialing (DOD): Obtaining access to the telephone
network without attendant assistance.
Trunk to trunk queuing (TTQ): Facility to queue a trunk if the
requested trunk and/or alternative trunk are not available.
Multiple trunk access codes: Assignment of the trunk access codes
shall be flexible, accommodating one or two digit access codes.
Automatic Route Selection (ARS): The equipment shall allow for
automatic selection of the best available trunk route for outgoing calls.
If the primary route is blocked, the PABX switches shall be able to select
a secondary route.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 123 of 178


Rev. 0

Night answer service: Manual or automatic transfer or answering of


incoming calls from a specified subscriber number or energizing a
common signal. Any user shall be able to answer the call by entering a
single digit code.
Programmable function keys: The telephone sets shall have
programmable function keys for direct or speed dialing of subscribers
and substations.
Automatic re-dial: Calls to a busy telephone shall be re-routed to an
alternate user after a predefined number of call attempts.
Call forwarding: Calls to an unattended user shall be forwarded
automatically to another telephone of the unattended users choice.
Call transfer: Calls shall be transferred to another user by pressing a
one-digit code and entering the number of the user to which the call is to
be transferred.
Call on hold: The PABX switches shall be equipped to permit users to
place a call on hold and be able to dial a third party either local or
anywhere in the network. The user shall be able to release or hold the
call, establish a second consultation call, return to the original call or
connect the original call and the consulted party together.
Abbreviated dialing: Abbreviated dialing (1, 2, or 3 digits) of
frequently dialed numbers within or outside the substation. A minimum
of 50 numbers is required.
Call Waiting: A busy user shall receive a distinctive tone indicating that
a second call is waiting. The user shall be able to put the first call on hold
to answer the second call and be able to return to the original call.
Camp-on: If the called user is busy when a call is made, call-back
ringing shall inform the caller when the user becomes free using this
feature. After the extension answers the call-back ringing, the dialed
number shall be automatically redialed.
Off-Hook Call Announcement (OHCA): A caller shall be able to talk
with a busy user through the built-in speaker and microphone of the
called partys telephone set.
Whisper OHCA: A caller shall be able to give a message to a busy user
through the handset of the called partys telephone set.

3.3.2.7

Voice recording system


In the control center of the telephone system all incoming and outgoing
voice communications to and from the operators at any telephone sets
(Fixed-Phone, IP-Phone, WLAN-Phone and DECT-Phone) or within the IPPABX and the Hotline telephone sets must be recorded online. Suitable
voice recording equipment, external to or integrated within the IP-PABX,
must be provided and connected to the IP-PABX. Operational voice

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 124 of 178

Rev. 0

communication between the operators in the Control Centers and the


maintenance staff in the field (at substations) must be recorded online.

3.3.2.7.1

Voice recording functionalities


The voice recording system must provide the following functionality and
features as a minimum requirement:
Configurable phone numbers (extension numbers) for voice recording
Voice recording shall start immediately when the call is established
Start and end of voice recording shall be stored with a date and time
stamp
For all answered and unanswered calls (incoming and outgoing) the call
setup time from ringing tone issue to call connection shall be stored with
a date and time stamp
All data, date and time stamps and the correlated voice recordings must
be locally stored within the voice recorder for at least one week
Suitable automatic back-up functionality must assure:
that data or voice recording is not possible due to storage capacity of
the voice recorder
that a regular back up of data or voice recordings to external storage
media takes place
Suitable functionality shall be provided for search and playback of voice
recordings
Statistical analysis functionality shall be provided for:
Recorded voice calls
Duration of individual voice recordings in average
Voice recordings per day, week and month
Amount of successful / unsuccessful operator call (incoming and
outgoing)
Graphical presentation of the statistical analysis data
Access authority with different level password shall be provided for the
voice recording function.

3.3.2.8

Telephone sets
All IP-PABX switches and subscriber locations shall be equipped with Dual
Tone Multiple Frequency (DTMF) standard telephone sets and mobile
DECT handsets.
For the selected persons at the power station digital telephone sets allowing
for all exchange features shall be supplied. Switchboard extensions attached
to these telephone sets shall contain a single push-button facility for
important contacts (e.g. LDC, etc). Pressing a button shall automatically

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 125 of 178

Rev. 0

establish a call with the relevant attendant. These telephone sets shall be
connected to the existing exchange if the services described in this
specification are available.
Requirements for equipment
All telephones and associated equipment installed in the process area or in
outdoor locations shall have IP 65 weather protection in accordance to
IEC 60529. All telephones and associated equipment installed in hazardous
areas shall be certified explosion proof type in accordance with IEC 60079.
Suitable telephone booths have to be provided for plant rooms/areas with a
high noise level (e.g. STG hall, pump room, beside burner, etc.).
Desk telephone set
Desk telephone sets shall be used only in air-conditioned rooms and offices,
and shall have high impact, dust-tight and temperature-resistant plastic
cases.
Cordless phone system
The cordless telephones shall be according to DECT standard. Via a
sufficient number of base stations all areas shall be covered. The DECT
system shall form an integral part of the telephone system covering all of its
features. The mobile phones shall be provided with bag, charging station,
vibration alarm and head set.
Wall telephone sets
Wall telephone sets for use in rooms that are not air-conditioned shall have
water-and dust-tight (degree of protection at least IP 54) temperatureresistant plastic cases or to be contained in weatherproof container.
Wall telephone set, explosion-proof type
In hazard areas such as gas reduction station, etc. wall telephone sets with
explosion-proof and corrosion resistant metal cases shall be provided.
Alarm bell
For use as an auxiliary bell connected to the relevant telephone sets to meet
the following minimum requirements:
type of enclosure IP 54
housing, light metal, weatherproof
sound pressure level 110 dB (max.) distance 1 m.
In hazardous areas, the alarm bells used shall be exclusive of the explosionproof type.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 126 of 178

Rev. 0

Telephone booth
The telephone booths for well-mounting are to consist of high impact and
corrosion-proof steel or aluminium material (resistant to UV radiation) and
are to be equipped with the following:
one internal roof light, type IP 54 enclosure, fully wired with switch
one external call light, type IP 54 enclosure, marked on three sides
(mounted on roof of telephone booth)
IP 54 enclosure, for telephone connection cable and cable connection
telephone relay for auxiliary bell.
For installing telephone booths in hazardous areas all equipment used shall
be exclusively of the explosion-proof type.

3.3.2.9

Power supply equipment


The telephone system shall be provided with an independent UPS complete
with battery and charger, which shall automatically switch in, on mains
failure, and supply for at least 12 hours. The main supply for the UPS shall
be taken from the station essential supply.

3.3.3

Portable radio system


The portable radios shall suitable for use in such kind of plant with wave
absorbing building and structures like thick concrete walls, etc.
The numbers of channels shall be as specified in the HCIS guideline plus
two for employers purposes.
The transceivers shall be able to communicate effectively at every parts of
the plant including, turbine house, switchgear rooms, offices, chimney,
water treatment plant, open areas, coal handling area, etc. A central unit and
repeater stations shall be installed when appropriate to achieve total
communication within the plant. The minimum squelch sensitivity shall be
10 dB SINAD.
The portable transceivers shall be rugged enough for rough handling and
outdoor usage. They shall be weather-sealed against dust and moisture and
water to DIN IP 54 standard.
Charger units shall be foreseen at different locations for recharging the
batteries.
All accessories such as sling, protective casing, carrying attachment etc.,
shall be provided.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 127 of 178

Rev. 0

The portable radio system shall be carried out in accordance with the
guidelines of the High Commission of Industrial Security (HCIS).

3.3.4

3.3.4.1

Public address system (PA system)

General
A public address system (loud speaker system) shall be provided to cover
the entire RAZ-Phase 1 (Package P and D), as specified. The complete
PA system shall conform to the latest state of the art, in the field of PA
system engineering. The system shall be complete including central
amplifier station, master call station, remote call stations, loud speakers,
interfaces, cables, etc. as specified. The system shall be interfaced to the
specified telephone system. It shall be possible to make public
announcements from any of the extensions of the specified telephone
system. However, specified alarms as under shall be given priority over
such announcements. To facilitate public address the Plant shall be divided
into zones.
The requirements specified under Part "General Technical Requirements"
are to apply and where applicable, further regulations from the other
sections of this specification.
A central amplifier station must be set up for transmitting alarm signals and
broadcast instruction and information in the event of catastrophic failure or
the occurrence of various operational faults and breakdowns.
The system shall be provided with specified number of indoor and outdoor
call stations. The indoor call stations shall facilitate half duplex
intercommunication between respective outdoor call stations.
The PA system shall be designed for the following operating modes:
It must be possible to switch on the following different tone and frequency
signals with the appropriate alarm buttons

fire alarm
major, large scale breakdown
fuel alarm
all clear signal (for resetting of alarm)

Provision of fire alarm with two different tones one for actual fire and the
other for mock fire drill are to be included.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 128 of 178

Rev. 0

Priority control shall be given in accordance with the above tone


arrangement.
The following call types shall be provided and shall be signalized by a tone.
selective call (for example only the loudspeakers in the turbine area or
boiler area will be switched in)
group call from several loudspeaker lines
collective call from all loudspeaker lines
The loudspeaker announcement following the alarm signal must be recorded
and stored to be played back.
The alarm signal, instructions and broadcasted announcement will be
initiated from a master call station in CCR. Alarm signals shall take priority
over broadcast announcements.
In addition, each master call station shall facilitate intercommunication
(Press to talk, release to listen) in half-duplex mode with the following call
stations :
outdoor call stations
indoor call stations in LERs
Safety protection must be provided to ensure against accidental operation of
the respective alarm buttons.
The number and installation of the specified loudspeakers shall be suited to
the conditions of operation and to that of the environment in such a way that
alarm signals and broadcast announcements can be clearly understood by
the operating personnel.
As regards the acoustic irradiation of the individual rooms, which differ
very widely, and of external facilities, care must be taken only to install the
specified loudspeakers with a loudness level 6 dB above the prevailing plant
noise level.
Furthermore, care must be taken that "hearing double" does not occur. The
loudspeakers must radiate all pitches uniformly and free from distortion and
at a sufficiently constant volume.
The specified loudspeakers of each area to be irradiated shall be grouped to
form loudspeaker lines and connected to the amplifier station. Each

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 129 of 178


Rev. 0

specified loudspeaker shall be numbered and labeled with the loudspeaker


line to which it is connected.
The specified external loudspeakers must be suitable for continuous
broadcasting duty in an operable temperature range in accordance with the
specified site conditions.
The specified outdoor loudspeakers shall be mounted on hot-dip galvanized
tubular poles, including foundations.
The conductor cross-section of the individual loudspeaker lines shall be so
chosen that the voltage drop on the respective lines shall not exceed 10% of
the amplifier output voltage.
All required amplifiers, relays, switching and control elements, equalizers,
recorders etc. shall be mounted in the same steel sheet cubicle (central
amplifier station) clearly arranged on the modular construction principle and
using plug-in module technique. Suitable steps shall be taken for cooling
and ventilation.
All cable connections within the central amplifier station shall be designed
on the plug-in principle.
When in operation the whole loudspeaker system shall be supplied by the
required number of amplifiers. 6x 250 W (R.M:S) power amplifiers with
one 250 W power amplifier in reserve shall be provided, as a minimum.
In the event of a breakdown or output reduction affecting the performance
of a power amplifier, there shall be an automatic change over to the reserve
power amplifier, to ensure that the loudspeaker system continues to
function. The power amplifiers shall be monitored by pilot tone monitoring
equipment which shall send a group alarm to the master call station in the
event of a malfunction. This reporting of a malfunction shall be indicated at
the master call station both visually and by audible means. It shall be
possible to reset the audible alarm manually.
The central amplifier station as well as the associated loudspeakers shall be
designed for maximum continuous loading capability.
Equipment and system shall be provided with easy access for maintenance
and calibration. All equipment shall be designed for continuous operation at
50C ambient temperature. Outdoor installation shall be designed for 60C.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 130 of 178

Rev. 0

The panel/cabinet for the central amplifier station shall be in accordance


with those cubicles described in Part P-B02 clause 9 with regard to main
dimensions and design in order to achieve uniformity of appearance.

3.3.4.2

Central amplifier station


The central amplifier station shall consist of a metal clad cabinet with type
IP 32 enclosure or better for free standing installation with frame to take the
following plug-in units :
Power Amplifier
The power amplifiers shall be fully solid state and equipped with plug-in
modules in a compact steel case for rack-mounting and shall fulfill the
following minimum requirements in accordance with IEC-60268.

input symmetrical with level controller


power output: 250 W (sinewave)
rated output voltage at rated power output:100 V
frequency range: 300 - 12500 Hz l dB
distortion factor at 1000 Hz: 2% or better
signal - to - noise ratio: 80 dB or better

Electronic protection against overload and short circuit as well as


overheating, mains switch cut-out, status indication, overload indicator,
level controller, measuring instrument for modulation in percentage and in
volume units (VU).
Pre-amplifier
The pre-amplifier shall be fully solid state and equipped with plug-in
modules housed in a compact steel case for rack-mounting.
The appropriate adjustable inputs for microphone, alarm tone generator,
pilot supervisory unit, announcement tone, recorder, etc. which shall fulfill
the following minimum requirements in accordance with IEC 60268.

inputs protected against being over driven by electronic limiters


distortion factor: 1.5% (IEC 60268) or better
frequency range: 300 -12500 Hz l dB
outputs with short circuit protection
mains switch, status indication, level control, level presetting control by
screw driver, separate treble and bass adjusters, measuring instrument for
modulation in percentage and in volume units (VU), as applicable.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 131 of 178

Rev. 0

Intercom Amplifier
The intercom amplifiers shall be fully solid state and equipped with plug-in
modules suitable for rack mounting, and shall be used for the specified
intercommunication (half duplex) between call stations. Each intercom
amplifier shall fulfill the following minimum requirements:

audio frequency power : 5W (continuous sine wave)


microphone input (-70) dBm nominal level
gain adjustable between 0 and 40 dB
loudspeaker output : 5 W, 100 V into 2 K Ohms
short circuit proof: transformer, ungrounded
high level output : +19dBm

Automatic Recording/Playback Equipment


The recording equipment shall switch on automatically after an alarm signal
has sounded so that the subsequent broadcast announcement can be
recorded. If no announcement takes place, the recorder shall switch off
automatically after 5 - 10 seconds.
The playback equipment shall be capable of being switched on and off
automatically so that the recorded speech can be played back by master call
station.
The recording system shall be fully solid state and housed in a compact steel
case. The automatic recording/playback equipment must fulfill the
following requirements:

frequency range: 300 - 12500 Hz 1dB


distortion factor: 2% or better
recording and playback in mono
automatic start/stop and recording
manual control buttons for ON/OFF, start/stop, recording and playback
etc.
status indication lights.
Pilot Tone Generator
It shall be fully solid state and equipped with plug-in modules for
connecting to pre-amplifiers and power amplifiers. Automatic two-way
switch over from power amplifier to reserve power amplifier shall be
provided.
The pilot tone generator shall be provided for an output signal of 20-40 kHz.
Main switch and status indication shall be provided.
Electronic Filters

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 132 of 178

Rev. 0

Electronic filters shall be provided in accordance with the requirements and


shall fulfill the following:
frequency range: 300 - 12500 Hz 1dB
distortion factor: 1% or better
adjustable frequency levels.
Alarm Tone Generator
Electronic four-tone alarm generator, initiation of the three different alarm
signals and also the all -clear signal under remote control shall be provided.
Tone-frequency range 200 - 1000 Hz, tone and sequence of notes must be
variable, clock frequency steps are to be 1 to 4 Hz. The selected alarm tone
will run for about 30 seconds and then switch off automatically.
The period of the alarm signal shall be adjustable. Premature switch-off of
the alarm tone (false alarm) to be effected by repeated pressing of the
start/stop button.
The different alarm signals shall be electronically interlocked relative to one
another.
The output of the alarm tone generator must be ungrounded in accordance
with the requirements. The noise level control shall be possible.
Announcement-Tone Generator
It shall be provided with
electronic two-tone signal for signaling a broadcast announcement
initiation of the tone signal by remote control. Adjustable range for clock
frequency to be 400 - 600 Hz.
The output of the announcement-tone generator must be ungrounded in
accordance with the requirements, The noise level control and priority
control of announcement tone shall be possible.
Control Panel
Control panel shall be provided with loudspeaker and volume control,
selector switch for supervising and announcement and program signals of
the individual power amplifiers, and test jacks for impedance measurements
on the outgoing loudspeaker lines for each power amplifier.
The appropriate measuring instruments for measuring the power amplifier
input and output levels as well as for balancing of the power amplifiers shall
be included.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 133 of 178

Rev. 0

The control panel shall fulfill the following requirements:


inputs: 100 V, symmetrical, ungrounded
main switch
status indication
Panel
A panel shall provide for broadcasting announcements and initiation of
alarms from the central control unit and also for the pilot tone monitoring
unit. The appropriate enclosed relays with change over contacts and with
plug in base shall be mounted on a printed circuit board with the following
priority circuits:
1
2
3

alarm tone signals


tone signals
broadcasting announcements

The relay panel shall be provided with the following requirements:


relay panel output: 100 V, ungrounded
main switch
status indicator
Power Supply Panel
Power supply panel shall provide for the switching on and off of the central
amplifier station with automatic main cut-out and main pilot lamp. The
lamp must be proof against sustained short circuit and shall be automatically
ready for operation again after a short circuit clearance.
The loudspeaker system shall be provided with an independent UPS
complete with battery and charger, which shall automatically switch in, on
mains failure, and supply for at least 12 hours. The main supply for the UPS
shall be taken from the station essential supply.
Contractor shall be responsible to supply and install all necessary cabling
and protection for the feeder.
Cable Connection Panel
Cable connection panel shall provide for the connection of outgoing
loudspeaker lines, control unit, cable infeeds, control cable for control of the
cassette recorder. The necessary terminal boards, cable inlets, access panels,
etc. shall be provided. The terminal boards as well as all cables shall be
labeled.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 134 of 178

Rev. 0

To take the specified plug-in units standardized steel cabinets shall be used
with the appropriate contact strips for mounting in hinged frames.

3.3.4.3

Master call stations


The control unit with steel case IP 41 enclosure shall be built-in the
supervisors control desk (CCR) with the following requirements:

with microphone control station


pre-amplifier
switchboard
built-in monitoring loudspeaker with level controller
screw in dynamic microphone with flexible support with connecting
plug. Not sensitive to interference by structure borne sound
cardiod characteristic
frequency range: 300 - 12500 Hz
intercom facility with specified locations
the non latching alarm buttons for fire alarm, major alarm, fuel alarm, all
clear signal shall be protected against unintentional maloperation
(appropriate circuit logic).

The selector panel shall be provided with keys for collection, group or
selective calls with built-in pilot lamps, a red pilot lamp showing engaged if
the system is engaged by the alarm generator. Microphone button shall be
operative upon pushing in all buttons. Main switch, main pilot lamp and
cable connection box shall be provided.

3.3.4.4

Indoor and outdoor call stations


Each indoor call station shall be complete with

dynamic microphone on flexible neck


loudspeaker
matching transformer
call button with busy indication lamp

Each outdoor call station shall be complete with

microphone with cardioid characteristic etc.


microphone amplifier
loudspeaker with matching transformer
call button with call and busy lamps

The outdoor call stations shall be protected as a minimum to IP 54.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

3.3.4.5

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 135 of 178

Rev. 0

Loudspeakers
The following types of loudspeakers shall be provided as a minimum:
pressure-chamber loudspeakers with plastic or metal poles and with
swiveling mounting flange for wall mounting. Type IP 54 enclosure
(resistant to UV radiation) shall be provided for indoor and outdoor
mounting,
the pressure chamber loudspeakers shall be selected according to the
local operational noise level
wall mounted loudspeakers with type IP 54 enclosure and impact
resistant casings of either plastic or sheet steel for internal mounting.
ceiling mounted loudspeakers for mounting in false ceilings.
Hot dip galvanized tubular poles, 4.50 m long with flange and necessary
foundations for mounting outdoor loudspeakers shall be provided.
The loudspeakers must fulfill the following minimum requirements in
accordance with IEC 60268
frequency range 300 to 12500 Hz
power handling capacity : 5, 10, 20 or 30 W
built-in transformer for 100 V operation for output matching in stages
(1:1, 1:2, 1:4)
main sound pressure level 110 dB
cable connection box

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

3.3.5

3.3.5.1

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 136 of 178

Rev. 0

Process related CCTV surveillance system

General
In order to increase and enhance the level access security in control centre
and plant buildings a Closed Circuit Television (CCTV) shall be provided
as specified. The CCTV shall be fully automatic and shall provide for
comprehensive survey of specified locations. The CCTV shall, as a
minimum provide for process related CCTV surveillance of specified areas.
In each case, the CCTV system shall be entirely suitable to meet the
specified site ambient conditions and area classifications. The CCTV system
shall have facilities of remote control, motion detection, multi-user viewing,
real time viewing, pan, tilt, optical zoom, focus, mega pixel and other latest
technology functions. For outdoor cameras humidity conducts shall be
provided. Wherever necessary special protections to meet the location,
conditions shall be provided.
The CCTV shall be powered by a safe AC system. All field inputs/outputs
shall be protected against lightning surges. The system shall use a common
source for all date and time information. It shall have build in time
synchronization facility based on a GPS Clock System.
The CCTV shall be provided with an independent UPS system complete
with battery and charger and complies with the related HCIS requirement. It
shall automatically switch on the failure of the main supply.

3.3.5.2

CCTV requirements
The CCTV shall be designed for general video surveillance of the process
locations/areas.
The specific areas as listed below shall be considered as minimum
requirements. The specific areas shall be logically grouped for easy
operation into a smaller number of surveillance sites e.g. control rooms,
electronic rooms, outdoor areas etc. The CCTV shall be a state of art fiber
optic based system.
As a minimum, the following areas of buildings shall be covered by CCTV:
Process areas like fuel gas, fuel oil storage area, chemical storage etc.
Sea water intake

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 137 of 178


Rev. 0

Turbine hall
Burner level
Stacks
All process critical areas
Central control room
switchgear building
electronic/telecommunication rooms

In addition to the main offer as per this section, the Tenderer may propose
any superior alternative offer with reasons for the preferred solution.
The CCTV shall mainly consist of a mix of fixed and remotely controlled
cameras/positioning devices located in the specific areas, optimized number
of video alarm and control monitors, control system for remote control,
video recording equipment, video switching matrices, transmission
equipment and interfaces to the Fire Alarm Systems.
A fibre optic sub rack located in electronic room shall typically house FO
demultiplexers and other equipment required for converting optical signals
to electrical signals. An optimized number of time division multiplexers
(TDM) shall be used to combine the electrical video signals. Each TDM
shall facilitate simultaneous recording on a redundant digital video recorder
(DVR) in MPEG4 format and display on a multi-screen display monitor of
all allocated camera signals without loss of any video information.
Typically, each surveillance site shall be associated with a TDM.
A video matrix switcher located in electronic room shall switch the
electrical signals onto an optimized number of LCD monitors for alarm and
control. The video matrix shall be interfaced to a common computer system
of the employers Security System. This common computer system located
in control room shall provide a platform for integrating the specified
subsystems into a homogeneous employers security management system. It
shall include necessary hardware and software for controlling and
monitoring the cameras, field located positioning devices, video switching
matrix, interfaces, terminal server, VDU (Visual Display Unit) based
workstations etc.
The CCTVs main operator station which shall include a VDU based
workstation and an optimized number of LCD monitors shall be located in
the control room. The LCD monitors (size at least 19) shall facilitate
multiple screen displays. The subsystem shall be provided with
alarm/contact inputs and outputs for interfacing to employers systems like
fire alarm system etc. and security subsystems like access control subsystem
etc. The CCTV shall support PAL and NTSC.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 138 of 178

Rev. 0

The operation of the CCTV shall be exceptionally easy requiring no


knowledge of cameras or monitors or their locations/numbers. The
centralized computer shall be programmed with a sophisticated site plan
graphics controller function. The site plan controller shall be programmed
with a series of site maps overlaid with dynamic symbols or icons of all
controllable devices and alarms.
The CCTV shall provide for operator and manager modes of operation.
Both modes shall be password protected.
The operator mode shall provide as a minimum for:

selection of plans, sites


camera to monitor switching
information of the cameras inside the system
remote control of the cameras (depending on installed functions,
prepositions, zoom, focus, pan, tilt, switch on/off)
information on video monitor
information on sequences of cameras on video monitors
selection of a sequence of cameras
start/stop of a sequence, step by step forward or backward
alarm acknowledgement hand rail
stand-by mode
digital video recorder playback
control and monitoring of subsystems eg. access control

The manager mode shall provide as a minimum for:

all functions of the operator mode


password settings
operators guidance texts
icon settings (from plan to plan)
icon settings for cameras
camera programming including all specifications (pan, tilt, zoom,
prepositions, washer, wiper, heater, thermostat etc.)
icon settings for monitors
sequence programming
date and time settings
consultation and exploitation of event list
archiving and restoration of event list
setting, saving and restoration of system configuration
recording on video recording equipment and setting
report generation

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 139 of 178


Rev. 0

Each of the operator stations shall be provided with standard keyboard


mouse and subsystem health monitoring indicators. All failures/faults shall
be centrally annunciated. No single component, module or function shall
lead to total failure of the CCTV and the affect of such a failure shall be
limited to a maximum of one surveillance site. The CCTV shall be
modularly and fully expandable.

3.3.5.3

Cameras
The video cameras shall in general be of digital charge coupled device
(CCD) colour type. The sensor shall be of either 1/2 inch or 1/3 inch format
size.
Cameras mounted in areas where light levels do not change shall use remote
manual iris control and where twenty-four hour operation of the camera is
needed, an automatic iris lens or another means of electronic sensitivity
control shall be used.
Cameras shall have at least 30x optical zoom.
All cameras shall be provided with protective housings. Outdoor cameras
shall be provided with sunshades and weatherproof housings per IP65.
Indoor cameras shall be as per IP54. Outdoor housings shall be provided
with heater and thermostat to prevent the glass window at the front from
misting at low temperatures and washers/wipers for cleaning the glass
windows. Outdoor housings shall be designed for corrosive salty
atmosphere of the local site. Outdoor cameras shall be designed for day and
night use.
PAL and NTSC colour cameras shall have a horizontal resolution of 480
TVL while vertical resolution shall not be less than the CCIR standard of
625 lines or better at the composite video output. On site tests shall include
checks using standard resolution charts to confirm the specified minimum
TVL.
Cameras shall be provided with aperture and gamma correction circuitry to
boost bandwidth for sharper picture and correct any non-linearity
respectively. It shall be possible to adjust manually the gamma correction
from zero to one. Cameras shall be provided with synchronization facility to
prevent picture rolls during switching.
If cameras use mains AC supply for synchronization then it shall be possible
to achieve a roll free synchronization from different phases of AC supply.
Cameras shall be provided with automatic gain control to cover the entire
dynamic range of light levels in the applied area. Cameras shall be provided

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 140 of 178


Rev. 0

with automatic light control (ALC) which shall operate on the iris of the
lens to improve picture quality. Cameras shall be provided with electronic
sensitivity control and/or electronic shutter for automatic adjustment to the
dynamic range of light levels and shall have a high sensitivity with a
minimum sense illumination of .02 lux or less. Source impedance of camera
shall be 75 ohms. Cameras shall use standardized input/output connections.
Cameras shall be provided with auto/manual white balance control. Camera
sensitivity shall be specified at a given f-stop, scene reflectance, AGC off, a
gamma correction of 0.45. Camera S/N Ratio shall be better than 50 dB with
AGC and gamma correction turned off and sensitivity shall be accordingly
matched.
Camera resolution shall be specified by the active pixel size. Spectral
sensitivity of camera shall be based on both the type and dynamic range of
illumination levels. Supplementary lighting shall be used only in
exceptional cases.

3.3.5.4

Video system accessories


Pan/tilt units for moveable cameras shall be provided with manual and autopan operations, preposition facility, and feed through wiring. These shall be
low profile and shall be fully compatible with the cameras and housing
combinations. These shall be standardized across the locations. These shall
be powered by a safe AC supply. These shall be rugged and shall be
constructed with corrosion resistant hardware.
The CCTV system shall be provided with facility for digital video recording
of the critical surveillance areas without loss of video information. The
provision of video multiplexing to achieve this function shall be within the
scope of work.

3.3.5.5

Interfaces to other systems


All communication to other subsystems and the employers systems shall be
through standardized interfaces.
CCTV shall be provided with standard interfaces for input and output
(I/Os) control and monitoring signals. The required I/Os shall typically be:
contact inputs to CCTV from fire alarm system of the specified specific
areas e.g. electronic room, storage rooms, etc.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

3.3.6

Page 141 of 178

Rev. 0

Clock system
The Stations Clock System shall be state-of-the-art and as a minimum
include a redundant real time master clock, number of slave clocks,
independent power supply equipment, interfaces for synchronizing the
Plants control systems.
A principle structure for the clock system is shown in Annex P-C13-6.
The master clock shall provide for highly reliable, accurate and stable real
time information. It shall be provided with necessary interface for
synchronizing form standard GPS time signal.
The DCS shall have a redundant real time master clock which will be
synchronized by standard GPS time signal. The real time clock is used for
time synchronization for all the DCS and PLCs components, etc.. In case of
GPS failed, one of the master clock shall lead for the synchronization of all
the plant DCS components and other systems.
The master clock in turn shall provide necessary safe synchronizing signals
to the following:

the slave clocks (wall mounted, double face, etc.)


specified DCS
GTG control and safeguarding system
STG control and safeguarding system
Electrical system
Metering and billing system
maintenance/data management system
building management system
all supplied PLCs
CEMS
GRS
specified CCTV surveillance system
wall clocks of CCR and others
plant access control system
ISS
All other systems, which requires time synchronizing

The requirements specified under Part "General Technical Requirements"


are to apply and where applicable, further regulations from the other
sections of this specification. Equipment and system shall be provided with
easy access for maintenance.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

3.3.7

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 142 of 178

Rev. 0

Office LAN/WAN system


The Office LAN System shall be state-of-the-art.
The laying of star shaped cabling system shall be combined with the cables
of the telephone system with combined telephone/ data outlets in the offices.
The cabling shall ensure protection against electromagnetic disturbances,
which can occur in the Plant. Between buildings fiber optic cable shall be
installed.
For each office at least 1 outlet and further outlets one for each 10 m2 shall
be provided (2 outlets for 10 m2, 3 outlets for 20 m2, etc.).
The network system shall be according to the category 5 or better of the
Standard ISO/ IEC 11801 (EN 50173) with RJ 45 western type connectors.
The star shape cabling shall go to common marshalling places, one in the
administration building and another one in the control building, containing
among others the following equipment:
Marshalling racks for star shaped telephone system and data network
with the connected star shaped cables
Marshalling racks for multicore telephone cables, included in the scope
of the telephone system
Spare place and racks for the future servers, data switches, etc. of the
intended office LAN system
Power supply in a computer room of the control building for the future
installation of computer room equipment like servers, hubs, switches,
workstations, PC-s and peripheral equipment provided by others.
An uninterruptable power supply (UPS) shall be provided and shall be
located at the control building at RAZ-Phase 1 to support all essential
computing and networking equipment
All design drawings and diagrams for the LAN/WAN have to be submitted
for approval to Employer/Engineer prior to any implementation.
Network redundancy to be highly considered in the design on the levels of
power supplies, cable route, switches, communication cabinets location and
servers network adapters in order to guarantee 100% network availability
with no single point of failure for the LAN/WAN.
Minimum 24 Core fiber optic cables shall be laid for any route
(outdoor/indoor) in the proposed design.
Minimum 10 Gigabit Ethernet standard proven technology to be provided in
the LAN to build high-speed redundant connections between switches and
between switches and servers.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 143 of 178

Rev. 0

No redundant connection is required for client PC. Minimum 1 Gigabit


Ethernet to the desktop.
Number of ports is to be determined from the structured cabling formula
used for the buildings in order for covering the entire work area.
All switches must comply with the standard of Layer3/Layer4 switching
techniques.
Minimum specifications for Core Switches are as follow:
High Performance and high availability core switch for campus Backbones.
Switch provides scalable bandwidth and increased network reach with
support of Layer 2/Layer 3/Layer 4-7 intelligent services with a
performance reach up to 210 Million packets per second.

Redundant Load-Sharing Power Supplies.


Redundant Supervisor Engines, uplinks & system clock.
Redundant Switch Fabrics.
Hot Swappable Switching slot modules.
LAN, MAN & WAN convergence support.
Supports various WAN modules (E1, HSSI, E3, ATM & PoS) through
Flex WAN module option.
IP Telephony, Voice Gateway, Intrusion Detection System, NAM and
ATM OC-3 module options should be available.
HSSI = High Speed Serial Interface
E3
=34.368 Mbps
POS =Packet-over-SONET

3.4

Interfaces
Interfaces between Power Generation Island (Package P) and Water
Production Island (Package D) shall be as indicated in Part P-A3.

3.5

Terminal points
The terminal points for the specified Scope under this section shall be as
indicated in Part P-A3 (General Project Requirements-Limits of supply)

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

3.6

Page 144 of 178

Inspection and testing


The specified systems shall meet the relevant clauses of Part P-A5, as
applicable, unless otherwise specified in this section.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

Rev. 0

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 145 of 178


Rev. 0

4. Generator Rejection Scheme


4.1

General
This specification covers the required Generator Rejection Scheme (GRS)
and associated equipment for the Power plant Package P according to the
"General Technical Requirements", Part P-B03, according the Inspection
and Testing Part P-A5.
GRS pertains to the Special Protection Schemes class. The present
specification defines the functional and overall performance requirements;
however the Tenderer is encouraged to propose if deemed necessary
additions or alternatives to the suggested algorithms and dependability/
security features. Existing references on implementation of similar schemes
will be of particular significance in the selection of the Tenderer. If the
Tenderer has already implemented such schemes or similar, the offer shall
indicate technical details, years in operation and end-customer contact
persons.
The normally open operation of the new SWCC plant at Ras Az Zawr is in
connection with the SEC grid. In case of disconnection from the SEC grid,
the plant will operate in island mode. If the 380 kV overhead line
connections to the SEC grid are lost, then the Generator Rejection Scheme
(GRS) should trip the steam turbine generators.
In such an island operation mode island, if one the potlines of the smelter,
equal to 600 MW load, is disconnected it is necessary to reduce the excess
of available power in the plant in a very short time. A Generator Rejection
Scheme (GRS) that will trip a certain number of the gas turbine generators
has to be implemented.

4.2

Scope of supply
This section sets out the scope of Generation Rejection installations covered
by this specification as well as the requested supplies and services, but
without excluding other necessary components and services not mentioned:
One stand-alone automatic Generator Rejection Scheme located at the
380 kV SWCC substation (with interfaces to the Substation SCMS
LAN and FMS), housed in a factory-tested panel(s)

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 146 of 178


Rev. 0

All necessary works to design, engineer, test in factory and at site,


commission the core equipment, communication channels and the
associated interfaces to the SCMS LAN and to other remote control units
(if necessary)
All necessary hardware, cabling, extension cards, etc. required by the
above interfacing to communication channels and LANs included in the
Power Plant Package P and/or 380 kV Substation Contract.
The required software
All required hardware, cabling, etc. required for signal exchange with the
Aluminium Smelter at Maaden
All necessary hardware and cabling to connect the GRS to the auxiliary
DC and safe AC supply, local and remote fault monitoring systems
including the interconnection with the DCS of the power plant.

4.3

Functional requirements
A reduction of the excess power after the loss of the 380 kV connections to
the SEC grid or load rejection in smelter load (potline) can be obtained via a
controlled generation rejection scheme (GRS) considering:
cyclic calculation of the power balance from SCADA information (a
typical SCADA pool cycle of few seconds is sufficient);
calculation by off-line simulation and for each critical event (tripping of
one or two 380 kV lines) the total number of MW output to be reduced in
order to arrest the frequency under the 5% level (63 Hz)
non-intentional delayed trip of pre-selected units in case of event
occurrence and fulfillment of some simple security checks (voltage
above 0.9 p.u., frequency above 61.2 Hz)
based on unit output information from SCADA, selection of the
particular units which should be tripped for each kind of event
(considering the actual load and unit output from SCADA)
Overfrequency trip back-up
The excess power calculation is based on real-time balance (every SCADA
cycle) between the power exported from the SWCC power plant via the
380 kV lines to the Grid and also to Maaden through separate lines and the
total generation.
The number of machines to be tripped for a particular line outage can be
calculated by off-line simulations and be recorded in a look-up table.
Alternatively to the look-up table, it is recommended to explore as an option
a more advanced solution, based on the cyclic runs of a power system
analysis software with a simplified model of the network and the generation
units; these runs should determine more accurately for each event and actual

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 147 of 178


Rev. 0

system configuration the excess power DP to be rejected in order to arrest


the frequency under 63 Hz and the dynamic over-voltage under 1.25 Un.
The algorithm classifies in each SCADA cycle in descending order the
output sum of two GTs and the respective ST from each block Gi. The
accumulated tables are sub-totals Gi sorted by increasing MW, for
example for six GTs+ST combinations:
G1
G1+ G2
G1+G2+G3
G1+G2+G3+G4
G1+G2+G3+G4+G5
G1+G2+G3+G4+G5+G6
This algorithm is based on a pre-determined order of summing the generator
block outputs. The Contractor is free to propose as alternative other
algorithms for identifying the block combination which must be tripped, for
example by including as additional criterion the minimization of the number
of blocks, if not significantly impairing the execution speed and the security
of the overall scheme.
Since the configuration of the plant is not know and can be with five or six
generation blocks (GTs and ST), the combinations in the accumulated tables
have to be defined at a later stage.
The power which must be on-line is the difference:
Gi - DP
which is compared from the base to the top with the sub-totals list. The first
sub-total which is lower than the above figure gives the combination
number i which must be tripped, for example if:
Gi - DP > G1+G2+G3
then the combination G4 and G5 will be on the rejection list for the event
which causes a power unbalance of DP.
The GRS scheme should have also an over-frequency trip back-up function.
As back-up, it is proposed to implement a conventional over-frequency
protection using the same tripping logic as the GRS.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

4.4

4.4.1

Page 148 of 178


Rev. 0

Technical requirements

Security and Dependability


GRS trip function shall be event-triggered and permanently armed except
for:
manual disarming by operator from any of the hierarchical control
location
automatic disarming outside the normal operation tolerance bands for
voltage and
frequency
automatic disarming in case of component or function failure
The implementation of the GRS shall include features for fail-safe and fault
tolerant signal conditioning to increase the security and dependability of the
operation.
The controller requires the following 380 kV circuit breaker information:
Breaker status (three states)
Drive status (two states)
380 kV breaker trip command shall be two-pole.
The integrity of the hardware and associated interfaces to substation SCMS
- LAN shall be continuously monitored; alarms shall be issued for any
failure in the data acquisition or in the integrity of the hardwired signal
paths. The self-checking facilities shall not degrade the GRS performance.
Other security measures at platform hardware level like the cycle time
limitation for the look-up and accumulated tables, monitoring of the
position of critical control and test switches, must be provided an be subject
to approval in the detail engineering phase.
Since a remote access to the GRS is required, the design should consider the
consequence of unauthorized access on the security and dependability of the
scheme. The testing facilities and procedures shall be designed in such
manner as to exclude the risk of inadvertent operation.
The components of the GRS shall be designed to minimize the possibility of
component failure or malfunction due to electrical transients and
interference or external effects such as vibrations, shock, temperature. The
design shall recognize the effects of contact races, spurious operation due to
battery grounds, dc transients, RF interference or other similar influences.
DC supply shall be monitored to detect abnormal voltage levels, dc grounds.
GRS shall initiate breaker failure protection as all other 380 kV unit
transformer protections.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

4.4.2

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 149 of 178


Rev. 0

Trip Time Performance


The time elapsed from the line trip event causing the excess of power to the
issue of the 380 kV breaker trip command to the generating units shall not
exceed 300 ms. The signal exchange between the GRS and the 380 kV
breakers shall be considered as time-critical.

4.4.3

Execution Modes
GRS will be in armed mode in normal operation but shall be disabled at
operator request from each possible control location: local, SCMS or
remote. Following modes shall be implemented in addition to the armed
mode:
Advisory mode shall be made available to the SCMS operator to
visualise the actual look up table and take eventually preventive actions
for avoiding a rejection.
Test mode available to the SCMS operator, remote and power plant
operator in which the effect of tripping lines of generators shall be tested
(with automatic disabling of the trip circuitry and fault monitoring signal
exchange)

4.4.4

User Interface
The user interface shall be the operators consoles at the above mentioned
control locations. The dynamically updated accumulation and look up tables
shall be displayed on the operator request in clear easy interpretable tables.

4.4.5

Special Tools
Any hardware and software tools required to test, maintain, parameterize,
set the GRS are included in the scope of supply.

4.4.6

Fault Monitoring System


The output/input signals of the GRS shall be supervised by time-tagged
information to a central or local event recorder with resolution of minimum
1 ms. A time tagging synchronization between GRS and SCMS / FMS is
mandatory.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 150 of 178

Rev. 0

5. Integrated Security System


5.1

General
Saline Water Conversion Corporation (SWCC) intends to implement a
reliable Integrated Security System (ISS) comprising of following discrete
systems:
1)
2)
3)
4)

Intrusion Detection & Assessment System (IDAS)


Access Control System (ACS)
Video Surveillance System (VSS)
Identity Management System (IDMS)

The above system is required to safe guard SWCC assets by various


collusion threats from insider or outsider and to improve the overall security
& surveillance.
The Integrated Security System project should be engineered & build in
accordance to the High Commission of Industrial Security (HCIS)
standards.
This Part specifies the all equipment required for ISS of Power and
Desalination Plant.
All works, supplies & installation within this specification and scope of
work shall be certified by the Contractor to fully comply with all applicable
regulations.
The drawings enclosed with this Scope of Work and Technical
Specifications are only conceptual for the information of the Contractor and
are to be read in conjunction with this Scope of Work and Technical
Specifications. Contractor shall develop detailed design drawings for
construction based on these conceptual drawings.
The supplier of the ISS has to meet the requests according HCIS e.g.
qualification, license for public security etc. in order to insure HCIS
approval.

5.2

Layout
The layout arrangement of the ISS shall be provided according the
requirements of HCIS and should adequate for safe, simple and easy
operation.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

5.3

Page 151 of 178

Rev. 0

Scope of Supply and Services


The scope of work shall include as a package the supply, system design,
engineering, approval documents, installation, interface with existing
equipment (wherever applicable), erection, testing, commissioning,
acceptance tests, preparation of test reports and handing over a fully
Integrated Security System.
The scope of supply shall include but is not limited to a computer based
security system, CCTV cameras, TV monitors, video recorders, intrusion
detectors, work stations, card readers, door switches, uninterruptible power
supply, any special tools or test equipment and software for the purpose of
installation, maintenance, administration and operation of the system.
A functional design specification (FDS) shall be prepared for approval of
the ISS by the HCIS.
The factory acceptance test procedure (FAT) for the ISS shall be approved
prior to the execution of the tests.
The proposed system should provide a fully functional and integrated
command and control security system. This system shall assist the security
managers and security staff in maintaining the maximum level of security
for the site. The main control of the system will be from a dedicated security
control room.
The ISS shall include:
Intrusion Detection & Assessment System (IDAS)
Access Control System (ACS) with door monitoring system, access
control, metal detectors, raising arm barrier, turnstiles, barriers, undervehicles surveillance system.
Video Surveillance System (VSS) with CCTV system with recording and
playback facility with LCD screen technology display showing a site
map and lower level maps of buildings of various zones.
Identity Management System (IDMS) with computer based security
system for ID badge, security administration, event /alarm management,
recording of all the information, etc
Integration with public address, telephone and site radio system.
Security Control Center (SCC) including all security equipment as also
furniture.
All programmable equipments have to be supplied with software,
hardware communication protocol and documentation and necessary
licenses.
Cable, cable trays, conduits, channels and related accessories as required

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 152 of 178

Rev. 0

Power supplied for all the system components, including cameras,


sensors and recording system, should be powered by a centralized
uninterruptible power source fully compliant with SEC-07 Power
Supply.
Complete design and installation
The Contractor shall submit welding procedure specifications (WPS) and
procedure qualification records (PQR) and Quality Assurance Plan
(QAP) for approval before starting any welding work.
Training for the operation and maintenance of the system
Commissioning of the system
Preparation of the complete project documents such as wiring diagram,
as built drawing and factory acceptance test reports.
Supply and installation of the Integrated Security System shall be in
accordance of this section and with the latest edition of codes, standards,
specifications whenever it is referenced.
Following codes and standards shall be adhered to in this project:
Saudi Arabian Standard Organization (SASO)
National Electrical Code (NEC)
High Commission on Industrial Security (HCIS)
Safety and Security Directives (SSD)
National Electrical Safety Code (NESC)
Any deviations or conflicts in specifications, among the standards, or
between standards and this technical document, must be clearly highlighted
for SWCC approval. The most stringent shall apply unless approval in
writing from SWCC is obtained. The decision of SWCC shall be final and
binding.
The security devices/equipment shall be economically selected / designed
for continuous and reliable services with provision for future expansion/
addition of security devices.

5.4

Technical Requirements
The requirements given in the HCIS documents especially SEC5 shall be
considered for each subsystem. Additional requirements for the specified
systems are given afterwards as well in Annex: P-C13-11.

5.4.1

Additional requirements for Intrusion Detection & Assessment


System (IDAS)
The system shall be capable of handling at least 4 or more intrusion at a
time.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 153 of 178

Rev. 0

All intrusion shall be displayed in the related display screen in addition


to the bird view LCD monitor.
All fixed cameras shall be mounted at the height of 5 m from the ground
level.
All Pan-Tilt-Zoom (PTZ) cameras shall be mounted at the height of 7 m
from the ground level and it shall be 1-2 m behind the fixed camera.
All fence cameras shall be installed 8-10 m from the external perimeter.
All fence cameras shall be in front of the security lighting.
All cameras shall have the facility for the motion detection.
All cameras shall have optical zoom
The PTZ camera shall have the preset position to the area of intrusion in
the event of any intrusion.
The system shall have different tone for pre-alarm, alarm and system
trouble and shall be displayed in different color and code.
Intrusion area shall have different color & tone.
Micro wave and IR zone shall be designed in a zone concept covering a
distance of 100 m.
The range of micro wave shall be 8 m with no dead zone.

5.4.2

5.4.2.1

Additional requirements for Access Control System (ACS)

Door monitoring
Emergency exit doors, (i.e. normally closed), which are not used as
thoroughfares shall be fitted with electrical contacts that interface to the
workstation(s) in the security building. In addition, buildings that are not
frequently occupied shall be fitted with door contacts.
The switches shall be fail-safe.
The switches shall be the means by which door status, door identity tags,
etc., are monitored by the system. The Contractor shall provide eventlogging facilities for changes to door status and switch malfunctions.
Emergency exit doors in process buildings may be located in hazardous
areas. In such circumstances, the Contractor shall ensure that switches
are suitable for the area classification.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

5.4.2.2

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 154 of 178

Rev. 0

Administration building access control


Card reader shall be installed at the entrance to the administration
building and at specific locations throughout the building (e.g. computer
room)
A workstation shall be placed at the reception desk that will allow an
authorized user to access certain restricted functions of the access control
system

5.4.2.3

Metal detector
A stand alone metal detector shall be provided and installed at the entrance
gates. Supply and installation of walk through metal detector shall include
but not limited to the followings:
The walk through metal detector designed shall meet or exceeds the
standard of internationally recognized institution or organization like
F.A.A. Airport Security Regulations.
The walk through metal detector shall be supplied and installed along
with its controls, matching side table for keys and standard accessories
according to the drawings.
The walk through metal detector should provide comprehensive selfdiagnostics that continuously monitors the detectors internal circuitry,
external connections, and environment.
The walk through metal detector should have an automatic sensitivity
program selects the correct sensitivity for a specific weapon or test
object, eliminating the time consuming trial and error method.
The walk through metal detector range of detection is from head to toe of
the passing individual for effective performance
The walk through metal detector should that provides a visual display
that pinpoints the area(s) of alarm.
Sensitivity of the system should be adjustable.
Should be suitable for outdoor installation.

5.4.2.4

Under-Vehicle Surveillance System


The static under-vehicle surveillance system (UVSS) shall be supplied and
installed at all main gates for entrance side. The system shall be equipped
with the following minimum standard features:
Multi - camera system (color cameras for under-vehicle view, license
plate, face)
Day and night operation

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 155 of 178


Rev. 0

Zoom
Vehicle speed up to 20km/h
Computer with monitor and keyboard and software for image remaining,
screen scrolling, permanent recording, manual storing and reconciliation
between stored images
Long term storage, printer and data exchange

5.4.2.5

Raising arm barrier


The raising arm barrier shall be supplied and installed at the main gate for
entrance and exit side. This requirement is in support of the road blocker for
effective control of vehicle access. The raising arm barrier shall be equipped
with the following minimum standard features:
Electric drive torque motor shall permit short opening and closing
without the barrier boom bouncing in the end positions.
The lever system locks the barrier boom at both end positions.
In the event of power failure, the barrier can still be moved easily by
hand.
The drive motor along with the gear box, drive shaft and counter balance
spring shall be housed or mounted in an enclosure with door hinged on
one side for ease of maintenance access. The maintenance access door
shall be positioned towards the side of the road.
The housing or enclosure including the control panel shall be rated to
IP 66 of stainless steel materials and shall be provided with temperature
controlled space heater.
Arm Barrier system shall be heavy duty system with safety loops
emergency stop facility.
The rising arm should be manufactured from heavy duty light aluminum.

5.4.2.6

Turnstiles
The Contractor shall supply turnstiles at the inner gate of the main entrance,
and any other entrance that may be deemed necessary following approval
from HCIS.
The number of turnstiles will be determined by flow rate which is not less
than ten (10) persons per minute based on six (6) seconds per controlled
entry, including operation of the card reader and passing through when it is
released. Therefore turnstiles shall be fitted with card readers, the response
time for the system to open the door, or turnstile, once the ID card has been
read and PIN entered shall not be more than 2 seconds.
The turnstiles and readers shall have the following minimum requirements:

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 156 of 178


Rev. 0

The turnstiles installed shall conform to HCIS SSD-24.


Each turnstile shall have a single proximity smart card reader either side
of the barrier. The card reader shall be fitted with a keypad for entering
personnel identification number (PIN).
Entry to and exit from a site shall require the cardholder to have his card
read by the card reader and to enter his PIN in the keypad.
Proximity smart cards shall have a photograph of the cardholder, they
shall be rugged in design, easy to read and protected against forgery.
Security staff shall be able to retrieve cardholder digitized photographs
and access right information from the database so that pictures can be
displayed on terminals in the security control centre and gates when PIN
/card holders need to be verified.
Re-entry to the site shall be gained only after exit from the site by use of
the proximity smart card.
Access shall be denied if multiple entries using a single card are
attempted and if attempts are made to use a card that is damaged or
expired.
Alarms raised by the access control system should be displayed at the
guard gate closest to the alarm point and at the control console and event
logger in the security control room.
Authorized security personnel shall be able to set and change access
privileges of the cardholders for various zones within the site. They shall
also be able to set pre-determined expiration dates and times for visitors
and temporary staff.
The material of construction for the turnstiles shall be Stainless steel
conforming to HCIS SSD-24.

5.4.2.7

Barriers at the gate house


Barriers at the gate house shall be supplied and installed according to
HCIS-SSD-17
The barrier system must be electrically operated with manual over-ride.
The barriers shall be designed to fail-safe in raised position
The barrier must be able/ connected to interface to external control
systems such as the site security system, proximity smart card readers,
etc.
The barrier shall be painted red and yellow/ white in band of equal size.

5.4.2.8

Design and function


The system must allow exit and entry to or from a protected area by means
of individually coded pass-cards together with a memorized personal code
number.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 157 of 178

Rev. 0

Each access point of the protected area shall be controlled by a card reader.
Where both entry and exit are to be controlled the card reader shall be
mounted in close proximity to the door or turnstile and, on approval of a
card and personal code, the card reader shall operate an electrical release
mechanism thus allowing the card holder to pass.
Each card shall contain a unique code so that lost or stolen cards can be
blocked out of the system by means of a blocking unit. Where a single point
system is in use the blocking unit shall be a ten-way insert fitted within the
card reader. Where a multi point system is in use the centralized blocking
unit shall be a 24-way insert.
A conditional insert shall be used to program groups of cards to allow
access only during certain times of the day or on particular days of the
week. The validity of a particular group of cards shall be controlled by a
contact on an external time clock.
A clear text printer shall be included in the system to provide a continuous
record of each card holder's entry of exit together with the number of access
points used, the time, and the date. Attempted entries using blocked cards
shall be recorded also.
Where both entry and exit are controlled by card readers an electronic
memory shall be installed and readout facility added to the system. Its main
function will be to immediately indicate:
Whether a particular cardholder is within the protected area.
The prevention of one card being used to admit two or more persons.

5.4.2.9

Equipment
The card reader shall be a self-contained unit of modular design. It is to use
RF field technique for reading the card data, which will normally carry at
least 25 bits of information.
In addition to card information there will be a personal code of not less than
four digits, which the holder of the card must enter on the card reader
keyboard.
The card reader unit shall contain the following items:
1)
2)

Keyboards with minimum of nine push buttons for entering personal


code.
Proximity card reader section.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

3)

Page 158 of 178

Rev. 0

A system of lights and words identifying actions to be


taken/completed:
Amber light and word "COME"
Green light and the word "OPEN"
Red light and the word "REJECT".

The following equipment will be included in the card reader:


A motherboard containing the card reader control circuitry, a connector
strip for all external wiring, and four-edge connector to accommodate the
plug in inserts that are to be used.
A programmed conditional insert that enable acceptance of approved
card groups only.
A scrambling insert for personal codes. This insert will have a minimum
five variations.
The equipment shall be designed so that it will only react to cards that
contain readable elements that are part of that system.

5.4.2.10

Operation
The equipment shall operate in the following manner:
Touching sensitive part of card reader one of the three lamps identified
above shall light.
On identifying the code instruction the cardholder will dial his personal
code by means of the push buttons.
Correct dialing of the personal code will activate the open lamp and
spring the lock open for access.
In the event of a miscall or of the wrong number being dialed the reject
lamp will light up.
The door will remain open long enough for the cardholder to pass
through, but the time will be limited.

5.4.2.11

Recorders
Real time recording and printing.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

5.4.2.12

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 159 of 178

Rev. 0

Cards
The card in use shall be fully laminated and of data collection size. It shall
contain invisible and passive code elements.
Codes on the card shall be arranged as follows:
1. Octal code from which the personal code is derived.
2. System code from which the card reader identifies the particular card for
the system.
A separate list shall be provided with information about each individual
card with its personal code since there is to be no indication on the card of
the relevant code. This list will need to be given a high degree of security
within the system.
The cards shall be manufactured according to international standards for
data collection cards. The code elements shall be placed between two pieces
of high quality plastics material and RF welded together.
Cards shall be printed with a special number, which not connected in any
way with the actual or personal codes.
A computer lists shall be provided with the equipment showing:
1. Octal number.
2. Personal code number (5 different codes).
3. Blocking code.

5.4.3

Additional requirements for Video Surveillance System (VSS)


Reference is made to Annex P-C13-11.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

5.4.3.1

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 160 of 178

Rev. 0

CCTV monitoring and recording


For the integration of the CCTV system, the following facilities are
required:
The control of the CCTV facility from the console should have the ability
to select any camera in the system and determine the display destinations
(Monitor or the main LCD Display).
To control the recording of CCTV to the DVD recorders.
The system may have the possibility to display the output from any
CCTV camera in the system on PC Monitor. This display is in addition to
the display of the CCTV monitors.
If desired, the security guard may choose to record for a limited period
the CCTV input from a selected camera(s) after receiving an alarm
generated by VDM in combination with either one or the other intrusion
sensors (fiber optic cable sensor or microwave) to disk storage on the
computer system. This is in addition to the VCR recording required.
CCTV for fence and designated area surveillance
The designated areas shall include car parking area, substation,
hazardous materials tank farm area, and gasoline station located inside
the plant.
Sufficient CCTV cameras with appropriate lenses shall be installed to
cover the entire perimeter to allow assessment of unauthorized activity.
The number of cameras and lenses selected should be based on site
inspection and shall provide a scene area of at least 10m wide and 8m
high. camera(s) shall meet the hazardous electrical area classification in
hazardous material, tank farm location and gasoline station located inside
plant fence, as applicable.
Cameras are to be mounted on suitable height galvanized steel poles to
achieve clear view of facilities to be monitored. In hazardous material
tank farms, the dike wall may also be used for mounting the cameras.
The Contractor shall advise SWCC on the mounting arrangement for the
cameras.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 161 of 178

Rev. 0

The Contractor shall determine the number of pan, tilt and zoom (PTZ)
cameras to be installed at the entrance gates hazardous material tank
farms area and substations and gasoline station located inside plant fence,
as applicable.
The Contractor shall ensure that cameras can zoom to within a close
distance of the point of visual detection. The Contractor must provide all
results and calculations showing the effects of zoom capability.
If required the cameras shall be fitted with lights which give white
illumination to assist during night time surveillance Contractor to advise
the SWCC on mounting details and means of supplying power to fitted
lights.
Cameras must be able to identify intruder clearly at the end of its zone.
CCTV For Gate Surveillance
CCTV cameras shall be installed at the main gate and at the entrance to
supplement supervision of vehicle and personnel access to site.
At the entrance, PTZ cameras for displaying vehicle identity, vehicle
number, and an image of the driver shall be installed.
PTZ cameras shall be installed at the main gate for viewing and
recording movement in and out of the site.
Video switching shall be included with the system to enable monitors in
the security building to display and record images from selected cameras
including those at the gate.
Recording of CCTV Image
The Contractor shall provide a time-lapse digital DVD recorders allowing
recording of up to 960 hours. Additional facilities shall include slow
motion, freeze frame, forward and reverse frame advance, and alarm/ event
searches.
Local Storage and Snapshots
The recording shall be captured in a standard format, such as AVI or DivX..
Recording and replay shall be started with a single mouse click. If the video
source supports audio this should be recorded and replayed too.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 162 of 178

Rev. 0

The operator shall also be able to capture snapshots of live images from
individual cameras or the entire matrix. The snapshot shall be captured in a
standard graphical format, such as JPEG.
The snapshot shall include the following data:

5.4.3.2

Date/time of snapshot
Video source name(s)
Workstation name where snapshot was captured
The snapshot shall provide a print button for direct printing on a
connected printer.

Digital video recorders (DVR)


For recording of events, two DVRs are required. All DVRs must have a
hardware watchdog to have the highest possible availability. The recorder
must work in a network together and get a remote view station at the
operator desk. They must have triplex functions, all persons and vehicles are
entering and leaving the facility to be recorded, the images should be
digitally recorded or duplicated onto another medium or printed to
recognize and identify offender and to produce physical evidence of
incident which may subsequently be used in court or by the local
authorities.

5.4.3.3

Monitors
Monitors shall be of the following specification, which is the minimum:

Screen size shall be 21 inches.


Horizontal resolution shall be 600 lines or better.
Linearity shall be less than 2% of raster height.
The monitors will display the dedicated areas (as required). SWCC plant
layout will be designed and displayed on the big screen.

A large LCD Screen (63) shall be installed in the control room. Quad
system should be provided for having 4 pictures on the screen. It should also
possible to select the link of the screen to any camera to display any picture
using keypad.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

5.4.3.4

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 163 of 178

Rev. 0

Redundancies
The security system and security network shall have all the specified
redundancies. The high availability is required. Following have to be
considered in the design in general unless it has been specified somewhere
else:
Approximately 50% coverage of cameras and operation of both neighbor
cameras.
Coverage of IR sensors to cancel dead zones.
Standby server with mirror disk memory.
Hard Disk (RAID 5).
30% on video matrix switcher.
UPS and battery back up.
20% spare capacity for all fibers.
20% spare capacity in the termination and distribution panels (including
power breakers).
At least 20% spare capacity for I/Os network switches, Matrix switcher,
etc.
Different redundancies for software, hardware, cabling, power back up,
functionality and expandability will be considered, provided and defined in
the final design. Final approval for the redundancies will be approved
during engineering design stage.
Redundancy cable should be laid in a different conduit and at the distance of
at least 1 m from the main cable.

5.4.4

Additional requirements for ID Management System (IDMS)


Otherwise as specified in HCIS-SEC5 the Contractor shall ensure that
IDMS workstations are available in reasonable proximity to each plant
using these identification cards.

5.4.4.1

Integrated access control and badging system


This system must provide:
Facility to capture video image photographs, produce ID cards, build and
maintain a relational database, and control access to site locations
requiring cardholder ID, PIN, site, zone, date, days of week and time of
day.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 164 of 178

Rev. 0

Check for cards anti pass back and other attempts to evade the system.
Immediate alarm notification at the local guard gate and security control
room for attempted unauthorized entry, card reader errors, PIN errors, or
system malfunction at access control location (i.e., turnstiles, doors, gate
barrier etc.).
Recording of entry and exit of the site and controlled zone. The
minimum information required including time, date, cardholder ID, gate
or door location and directional status (in or out).
Detailed pre-programmed regular reports of entry and exit to the site.
These reports are to show as minimum for each holder, the holder's ID,
holder's name, and the last 180 days of entry and exit data for all entries
and exits to the site and controlled areas. This data to include as a
minimum, date, time and gate for each entry and exit to the site and all
controlled areas within the site.
Interface to proximity smart card readers, door switches etc.
Database management facility for the configuration of access control
equipment such as door switches, card readers and other control points.

5.4.4.2

Alarm and event recording


Alarm and event recording shall be provided with the following facilities
as a minimum requirement:
Alarms to be classified by category / level of importance (minimum of 3
categories or levels).
Alarms to produce audible and visual annunciation in the security control
room. All alarms to be tagged and displayed on occurrence on a mimic
panel console monitor and printed on the printer.
All alarms to be manually acknowledged by the security guard on the
console in the security control room.
All alarms and events to be recorded in detail on the system with date
and time stamping. Facility to add free text description of action taken or
other information to be provided.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 165 of 178

Rev. 0

Detailed pre-programmed and ad-hoc reports for all alarms and events to
be produced. These reports as a minimum to show the time and date of
all alarms and events, the source of the incident, the action taken, the
security guard responsible for the action, communication with other
parties. Report formatting facility is required to produce special reports.
Alarms shall be tagged and shown on semi graphic display, which shows
the zone location of the intrusion, and the door switches activated.
Display should clearly show different aspect in color and the status for
the various cases to be differentiated, alarms, access, secure and fault.
The database will be sized to hold all associated data relating to all
alarms and events for the previous 180 days (history).

5.4.4.3

Database and other data requirements


The security computer system shall have databases containing the following
information:
Data relating to vehicles that are resident on the site or frequently enter
the site. This data to include vehicle registration, type of vehicle, material
carried by the vehicle, owner/ user, dates of entry and exits from the site
and controlled locations.
Data relating to visitors who visited or could visit the site. The data held
to include name, organization and department represented, telephone
number, normal contacts(s) within the site, accompanied status within the
site.
Detailed database of all cards and cardholders.
Record of lost cards. Data to include date of issue, date of loss, date of
loss reported, and location of holder of card at time of loss.
Standing orders and security procedures.
Maps and drawings. The facility must allow for automatic call up and
display on the console of the appropriate maps and drawings on the
occurrence of alarms (i.e., door, switches and fence).
Facility for special and emergency telephone numbers.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

5.4.5

5.4.5.1

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 166 of 178

Rev. 0

General requirements

Additional requirements for the security systems integration


The system integrator shall be incompliance with the requirements of the
HCIS as a minimum with SWCC specifications for servers, work stations
and display monitor.
The integrator components shall be located in the security control room.
The integrator must have back-up facility or redundancy to ensure
operational continuity in the event of the device or components fail.
Access control shall be interfaces with the ISS.

5.4.5.2

Additional requirements for the Security Control Center (SCC)


Large Screen Displays shall be used to provide a continuous overview of the
status of all areas under the SCCs control. Refer Annex P-C13-11.
The Contractor has to provide and install an operator console finish to suit
all the monitors, recording system, keyboards, quad system, printers, alarm
terminals etc..
Fiber optic Ethernet board and other required interface cards and
accessories. DVD and CD drives, speakers, mouse, keyboard, color monitor,
and all requirements to match the installation (interface cards, converters,
and memory, SW etc) The stand-by server shall provide 100% back-up to
the server to avoid system malfunction (using automatic switching from
main server to stand by server) The server will be supplied with software
with licenses to manage and control the whole ISS system including
network, alarm management, CCTV and large screens systems. It shall
include all software drives for the system administration, operation, control
reporting maintenance etc. the contractor has to supply all required network
equipments such as network switch, modules, interface, boards, cables,
sockets, transceivers, connectors, software, accessories, user licenses etc. to
match the network requirements.
The CCTV should achieve all functional requirements specified in this
specification and in HCIS requirements for fence and site camera system.
Contractor shall provide powerful video matrix switchers with at least 96
inputs 32 outputs. The I/O will be sufficient number of inputs and outputs
suitable to the approved design with sufficient spare capacity for future
expansion. The video multiplex switchers are compatible to the offered

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

Page 167 of 178

Rev. 0

CCTV camera system and to the management software. The video


sequencing, adjustable dwell and automatic termination. It will control
zooming, focus iris, pan tilt of PTZ cameras using independent keyboards. It
is providing switching control from any camera to any monitor in the CCTV
system manually to automatically and with powerful alarm handling
capacity. Contractor is responsible for all required interface cards, cables,
installation accessories, software etc. required for the proper operation of
the video matrix switcher. The switcher system shall be installed in 19
cabinet compatible with all materials. The video inputs will come from the
cameras in the field. The alarm inputs are coming from Intrusion detection
system. The matrix output shall be linked to the monitors, keypads, and
quad equipment, recording system etc.
The field cabinets will be used for data collection and transmission systems.
20% spare capacity of cables, terminals, space etc has to be considered
inside the field equipment for future expansions.
The overall performance of the integrated security management system is
very critical and important for SWCC. The Contractor has to consult SWCC
in the customization and configurations of the whole security system before
implementation and guarantee the following performance criteria.

System stability
System availability
System integration
Systems connectivity
System upgrade-ability and expandability
Security functionality
Security coverage area
Response time and data throughput
False and nuisance alarm rate
Video transmission
System topologies
Redundancies
System security
Performance testing results and life time of equipment
System diagnostics
Performance

A PTZ, Day/Night type, color camera shall be installed outside the security
control room to monitor the corridor and the entry door of the control room.
A PTZ, Day/Night type, color camera shall be installed in the employee
entry/ exit gate, to monitor the entrance and exit of people on foot to the

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 168 of 178

Rev. 0

plant and to be displayed in a separate monitor screen (inbound/outbound)


in security guard console desk at the employee entry/ exit of main gate.

5.4.5.2.1

Security control console


The system main computer, alarm panel and video monitors shall be
installed in a security control room in the security building.
The computer system will be the focal point of all elements of the integrated
security system. The system must have a loop configuration providing 100%
resilience. The HMI (Human Machine Interface), must be available in
English and Arabic, all the software provided for the system shall be
Commercial Off The Shelf (COTS).
Most of the decisions concerning site security will take place in the security
control centre, hence all information gathered from the various system
components shall be presented in a manner that will allow security staff to
make critical decisions quickly, especially in high stress situations such as
an emergency. A security console is required to enable the security
personnel to manage all security related incidents in an efficient manner.
The security console shall have the following capabilities:
Ability to control the selection of input to be displayed on any monitor.
The console will integrate the use of the telephone, site radio, and site
public address system, from one location.
The console will be ergonomically designed so as to limit fatigue and
facilitate easy operation.
The Console must be configured for two operators to be seated and
working concurrently and independently.
All monitors and other visually displayed information to be completely
visible from the normal operating positions.
The furniture of the security control console for SWCC sites is part of the
Contractors scope of supply including chairs.
The system and console should be capable of handling at least 4 or more
intrusion at a time.
Operator Alarm:
The ISS shall support a manual alarm trigger by an operator to allow
alarm operating caused.
The operator clicks on the relevant location inside the location tree and
enters the specific alarm code. The alarm operating behind that trigger is
identical to alarms/events from detectors, which means all assigned
documents and drawings display.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

5.4.5.2.2

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 169 of 178

Rev. 0

Hardware and software requirements


Two servers shall be provided (one main and one stand by). The server shall
be from latest type of processor version in the time of the design
completion.
The servers shall be supplied with sufficient RAM, cache, mirrored hard
disk, fiber optic Ethernet board and other required interface cards and
accessories.
CD drives, speakers, mouse, keyboard, 21 LCD monitors and all
requirements to match the installation (interface cards, converters, and
memory, software, etc.).
The standby server will provide 100% back up to the server to avoid system
malfunction (using automatic switching from main server to standby
server).
The servers shall be supplied with database, network management software
to manage and control the whole ISS system including network, alarm
management, access control, CCTV and 63 LCD screen system. It includes
all software drives for the system administration, operation, control
reporting maintenance etc.
The system must be configured in redundant mode such that the failure of
communication loop for data collection will not impact operation of the
system.
The system shall be connected utilizing fully tolerant LAN technology via
server on an internationally accepted LAN standard (i.e. Ethernet, token
ring).
Cause and effects diagram shall be developed and submitted for client
approval to document the functionality of the software.
The system shall have multi-level password security with at least the
following levels:
1. SYSTEM MANAGER Allowed full authorization
2. SUPERVISOR Allowed full authorization for specific sites or zones
3. OPERATOR Allowed a subset supervisor to enable the operation of the
system.
4. MAINTENANCE Allowed authorization for Maintenance activities.
5. DEVELOPMENT Allowed authorization for program and data
development.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 170 of 178

Rev. 0

Computer system monitors must be of minimum size (21 inch LCD) and
resolution to clearly display all required information from the security
control positions at the system console. A 63 LCD screen shall be used
which displays site maps and lower level maps of buildings of various
zones.
Three printers are required. A black and white laser A4 printer, and two
color laser printers.
The system shall have internal diagnostic capability, which will clearly
display faults in any component or potential faults in an informative and
clear presentation with an alarm.
The Contractor shall provide all video imaging equipment and blank ID
cards required for ID badging.
The system must be configurable to allow increase of 20% of external
sensors and devices only by adding additional hardware and changing
software configuration.
The system should have facility to display 4 pictures on any monitor screen
(Quad system).
The system software must be bilingual (using both Arabic and English
languages) and shall be furnished with flexible multi level password and
pass-code access security features, and working files shall be archived on
hard disc, DVD or other storage medium. System operators shall be
provided with pass-codes to be used for logging on or off duty. System
passwords are usually required to modify or changes significant system
parameters, to enable or disable alarm points, perform system maintenance
operations such as deletion of outdated history files or to make global
changes in time, date etc.
If a non standard condition is detected by the system then discreet graphic
alert will be displayed and accompanied by an audible alert to gain the
operators attention. The alert graphic must continue to be until the non
standard condition has been resolved.
System display shall be menu driven with option selected by mouse or from
the keyboard.
Workstation shall allow personnel to configure the system including display
building, programming of site passes and system database.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 171 of 178

Rev. 0

The system must be configured so that a back-up controller is always on


line that can assume control of the entire security system in the events of a
catastrophic failure of the primary controller. The back-up system must be
continually updated by the primary controller so that all information is
accurate and up to date.
The security control room shall be provided with smart card reader (inside
and outside) and emergency exit button inside the control room.

5.4.5.3

Transmission system
Fiber optic (FO) transmission
From the remote cabinets, FO transmission is used for real time video, data
transmission and Ethernet-connection.
To reduce the amount of fibres multi-channel-transmitter should be used.
Here the requirement is, that no multiplex systems to be used. Multiplex
systems with only one transmitting frequency will have a time-delay
between the pictures and this is not acceptable. Also the transmitters /
receiver must have the facility for two independent data channel (bidirectional), Audio channel and Contact Closure inputs and outputs.
Malfunctions must be indicated via relays-outputs and LED in the frontpanel and to be reported to the ISS.
For each camera in an alarm zone, a different transmitter must be used.
For I /O device an Ethernet to FO. Converter is required.
Between Camera multifunction box and remote cabinet two-wire
transmission has to be used to protect the signal against EMV and
magnetic fields.
Fiber optics / coaxial transmission cables
ISS security system equipment and devices are installed at different
locations at SWCC plant.
These security equipment and devices work or function as a system through
integrator units. The integrator collects and processes the required data from
downstream security devices through transmission cables. These cables are
either fiber optics or coaxial cables. Supply and installation of transmission
cables includes but not limited to the followings.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 172 of 178


Rev. 0

The use of fiber optics is a must for all cameras for clarity of transmitted
pictures or images to the command control screen. Fiber optics cable
should have at least 50% spare capacity for future use. Only Fusion
splicing is acceptable for Fiber splicing. OTDR Tests to be run and
results to be submitted to SWCC/SWCC project Engineer. Cabling
system with minimum 15 years warranty and certification is preferable.
All Fiber installation components should be same type. Fiber cables
should have mechanical protection.
The means of installation shall be strictly in compliance to the relevant
HCIS.
For security equipment and devices other than those that are related to
cameras and videos a coaxial type cables can be utilized.
For AC power supply to the security equipment and devices; wires or
cables can be used depending on the application. However, for under
ground cable installation an armored type XLPE/PVC insulated shall be
utilized.
The means of installation shall be strictly in compliance with HCIS and
SWCC approval.
Matrix System
The matrix system has to provide all cameras to all monitors. The matrix
has to be modular-type that means future expansion must be possible.
The basic configuration is 128 inputs to 32 outputs.
A separate controller is used for the switching of the matrix, control of
PTZ cameras, connection to keyboards and third party devices. Supplier
has to provide a reference list for integrated third party protocols. As the
matrix, the controller must be expandable by adding data modules and
alarm modules.
A backup facility on a PC must be included.
The keyboards must have a touch-screen display (10.4) and a three axis
joystick.
Management System
The management and its graphical-user interface should help the user to
control the CCTV and the alarms from the perimeter protection.
To achieve this, graphics with a general overview and detail drawings of
the alarm zones has to be implemented under the supervision of SWCC
engineers and security supervisor.
All buttons and alarm descriptions must be in English and Arabic
language.
The system works with a migration server that means the database will
be on each PC and updated online

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 173 of 178

Rev. 0

Alarms-scenarios combine the alarm and the CCTV action to an


automated script.
Each action will be stored into the log-file.
In combination with the existing road blockers and sliding gates, the
management system controls the CCTV matrix in this way that the
related cameras are switched to the monitor in the guard house without
an action from the user.
The integration of third party devices must be possible on the base of
serial connection or IP-protocol.
All access to the system is regulated by user level defined in the relation
to the password. That means the user is identified by his password and
gets his own access on any machine.
Alarms are prioritized in a range from 0-99. This function allows the user
to specify the importance of an alarm and his position in the system. A
high priority alarm will be always displayed over a lower priority alarm.
The management system also takes care of the different FO receivers and
their functions. If something is damaged, the user will be informed which
receiver is lost. In the same way the Management system will control the
function of the DVR.

5.4.5.4

Security equipment tagging


All equipments shall be provided with equipment tag number for easy
identification and inventory. The equipment tag number shall be unique and
could be easily distinguished by the readers. The equipment tag number
shall be reflected in all documentation and drawings including
communication whenever appropriate for maintaining consistency. The
same tag number shall also appear in the security equipment or devices
itself.
The Contractor shall propose the equipment tag number for security
equipment and devices.
Indoor tags shall be of the plastic type while outdoor tags shall be stainless
steel.
All nameplates shall be permanently and legible marked in English.
Nameplates shall be installed on all devices or pieces of equipment for
which the use of identification may not be readily apparent, such as, but not
limited to, relays, contactors, push-button indicating lights and switches.
The end of all wires cable including splices and joints made in junction
boxes and at terminals shall be marked for identification. Instructions and
circuit details shall be furnished in Arabic and English with Arabic taking

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 174 of 178

Rev. 0

precedence as necessary for operation and safety. All controls shall be also
located to permit observation of the equipment controlled and at an effective
height for ready accessibility of operation.

5.4.5.5

Security equipment and devices


Contractor shall do the selection of the propose security equipment and
devices mainly on the basis of the followings criteria:
Latest technology in the market with proven integrity and quality for its
application.
Engineering and maintenance support from local vendor or its affiliates.
Availability of spare parts in the local market for a minimum of at least
10 years.
Future upgrade and expansion capability of its hardware integrator
without further modification requirements.
Future upgrade and expansion capability of its hardware and software
integrator with minimum requirements for any additional hardware and
software.
Design simplicity, redundancy and users friendly.
Technical compliance to relevant SWCC specs & HCIS directives as a
minimum.
The supplied hardware and software shall be fully licensed and the supplier
of the system will register all components and configuration. All parts of the
complete assemblies will carry the type and serial numbers to enable spares
to be easy identifies. The provided security system is planned to optimize
the security resources in SWCC and will improve the security process and
management in the plant. The provided security will comply with the
relevant safety directives issued by HCIS and with national and
international industrial standard for design, installation, performance,
reliability and safety.
The Contractor has to supply, install and commission all fiber optic cables
required for the security system.
The contractor has to run all fiber optical tests (OTDR, etc) and provide test
results to SWCC. Multi mode cables have to be used for video/data
transmission from the field substations to the ISD control centre.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

VOLUME IX: Part P-B13


Instrumentation and Control System

Doc No.:

5.4.5.6

Page 175 of 178

Rev. 0

Expandability
The Integrated Security System (ISS) shall be capable of being expanded
beyond the base by adding independent hardware and functions into the
system. The additional hardware and functions shall not affect the existing
hardware nor degrade the performance. Expansion shall be provided in the
following areas but not limited to:

5.4.5.7

Addition of any components of CCTV (like fixed / PTZ cameras)


Addition of LCD monitors
Addition of any ACS components
Addition of any components of IDMS
Addition of any components of IDAS
Addition of any components of VSS
Addition of any new zones.

System grounding and ventilation fans


The ISS systems and all related components shall be grounded in strict
accordance with the equipment manufacturers recommendation.
All ventilation fans provided in any system equipment shall be designed for
silent operation and shall operate at the lowest speed practical that will
provide sufficient air movement to meet the manufacturers requirements. If
the failure of ventilation fan pair or individual fan can lead to equipment
malfunction of damage, they the failure of each individual fan shall be
alarmed via the ISS. An indicator shall be provided on the front exterior of
each cabinet containing ventilation fans to indicate the occurrence of
ventilation fan failure.

5.4.5.8

Graphical location maps


The ISS shall support the display of location maps. A standard vector
graphics format, such as AutoCAD DWF, is the preferred location map
format.
The drawing format for the location maps shall support a logical
partitioning by defining sub-areas inside the drawing, by marking the area
and giving a logical name. The time-consuming conversion into a bitmap
format and the splitting into sections should be avoided
The ISS shall provide a location tree to allow easy selection of locations and
sub-locations. The location tree should have no limits in the number of
levels or sub-levels. Creating the location tree and the location names

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 176 of 178

Rev. 0

automatically by scanning the drawings for logical sub-areas should be


possible. A single click on the location/sub-location should show the
assigned graphics or sub-areas with all detector icons visible for that area.
The ISS shall provide a zoom and pan feature for zooming into a location
and move around inside the drawing, simply by using a standard mouse.
This allows operators to find a specific detector, door, or reader for fast
control, such as open door manually, show camera live image, and so on.
The ISS shall support multi-layered drawings and allows layers to be shown
or hidden depending on the incoming event. A manual layer control during
normal operation shall also be possible.
The ISS shall provide a library of standard detector icons for intrusion
detectors, doors, readers, cameras, and so on. It shall be possible to place
these icons directly onto the drawing. All assigned control commands
should be provided when clicking the icon.
When a detector point sends an alarm/event message, the assigned icon
animates inside the drawing, displaying the corresponding event color. The
location and the relative size of an icon shall be definable inside the drawing
and should be done by the architect.
The ISS shall provide a means of displaying icons corresponding to the
current detector status, e.g.
Door:
open - closed blocked
Barrier:
open - closed blocked
Camera:
motion alarm recording
All icons shall be provided in a vector format, so that when the user zooms
in and out, the size scales automatically to the view.
Moving the mouse cursor over a detector icon shall provide a tool tip with
detailed detector information, such as complete address, actual status, and
detector type.

5.4.5.9

Device overview
The ISS shall provide a real-time device overview of the entire systems
status. All connected subsystems shall be shown on a status tree, such as
intrusion detection system (IDS), video systems, access control hardware,
and individual detectors, as well as internal items, such as server or operator
status. A direct control into subsystems shall be possible by clicking on
panel/ detector address.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 177 of 178


Rev. 0

The device overview shall support state filtering/ sorting to search for
specific states, such as all detectors in malfunction or all doors in an open
state.
The states inside the device overview are shown using the same colors as on
the detector icon.

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

RAS AZ ZAWR POWER AND DESALINATION PLANT PHASE 1


Subject:

Doc No.:

VOLUME IX: Part P-B13


Instrumentation and Control System
Q

Page 178 of 178


Rev. 0

6. Annexes
Annex: P-C13-1
Annex: P-C13-2
Annex: P-C13-3
Annex: P-C13-4
Annex: P-C13-5
Annex: P-C13-6
Annex: P-C13-7
Annex: P-C13-8
Annex: P-C13-9
Annex: P-C13-10
Annex: P-C13-11

FICHT-5296110-v5-RAZ_TD_P-B13.DOC

DCS structure Block type (Package P)


DCS structure Block type (Package D)
Control Structure: Principal Hierarchical Structure
Interface Scheme for Metering & Signal Exchange
DCS Structure Crosswise Operation
Structure Clock System
Structure CEMS and Water Quality Monitoring
Structure Vibration Monitoring System (VMS)
Structure Plant Management System (PMS)
General Overview Plant Management Bus
Specific Requirements for ISS

S-ar putea să vă placă și