CLIENT

CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

S.
No.
1.

Activity job
stages
Entering the
work area.

Hazards
(What can go wrong)
Working without Valid Permit
Personnel Injuries due to
slips, trips & falls.
People hit by moving
Vehicles
Manual Handling.
Awkward position.
Damage to nearby structures.
Overturning of Equipment.
Poor housekeeping.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust
lightening, etc.
Heat stress.

Controls
(How to prevent it)
Valid permit to be obtained from POS and
ORPIC before starting any job.
All people should undergo POS & ORPIC
Induction.
Tool Box Talk to be conducted before
starting any job on daily basis.
A Competent Supervisor should be
available at site at all times.
First Aider should be present at site at all
times.
First aid facility will be available onsite at
site at all times.
Adequate drinking water facility available
at site at all times.
Adequate rotation and intervals will be
provided to the crew to avoid heat stress.
Area to be barricaded to avoid any people
entering the work area.
Competent and trained people should
operate the equipment.
In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.

Page 1 of 18

Action
party
AWS

Contingency
(If control fails & result in
accident)
If in case of any incident
initiate Emergency Response
Plan.
Seek Medical assistance
POS Emergency contact:
23220000 (ext.: 666),
99247666.
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

Remarks

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

2.

Mechanical and
Manual
Excavation

Working Without valid


permit.
Personnel Injuries due to

Ensure adequacy of resources required and


plan the work area properly to avoid
accumulation of materials, spills, wastages,
etc., that harm personnel at site.
Establish clearly maintained walkways and
for movement of vehicles / equipment,
wherever possible.
Plan & control vehicle / equipment
movement with the presence of an
authorized banksmen.
Banksmen should accompany the vehicles
all the times.
Materials will be stored at the work face in
an orderly and safe manner.
All the materials shall be stacked in
designated area in proper way, over
stacking shall be avoided.
Establish a site clean-up schedule for
collection & disposal of wastes, spills,
accumulations, etc.
Warning signs to be placed to warn the
people.
Use of PPEs (Safety Shoes, coverall, safety
goggles, helmet, etc.).
Valid permit to be obtained from POS &
ORPIC before starting any job.
All people should undergo POS & ORPIC
Induction.

Page 2 of 18

AWS

If in case of any incident


initiate Emergency Response
Plan.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

slips, trips & falls.


People hit by moving
Vehicles
Cave-ins, Collapse of
excavation.
Water in the excavated pits
Ground water logging
People falling into the
excavated pit.
Unsafe Access or Egress.
Toxic gas.
Dust.
Noise.
Insufficient lighting
Manual Handling.
Awkward position.
Damage to nearby structures.
Damage to U/G utilities.
Electrocution.
Working under OHL.
Overturning of Equipment.
Poor housekeeping.
Adverse weather condition
like Extreme heat, Extreme

Tool Box Talk to be conducted before


starting any job on daily basis.
Ensure sufficient water is available at site
and also convey the message in Daily Tool
Box Talk.
A Competent Supervisor should be
available at site at all times.
Banksmen should accompany the vehicles
all the times.
Area to barricaded and cordoned off to
restrict the movement of people.
Adequate signboards and flickering lights
to be fixed to warn the night users.
Before starting any excavation U/G utility
drawings to be obtained and the utilities to
be marked at site.
Manual trial pits to be taken to locate the
path of the U/G utilities.
Check the UG /AG services through metal
detectors, if there is possibility of Utility /
cables.
Soil condition shall be checked by
competent person/ engineer prior to start
the work.
Adequate sloping to be provided.
Adequate no. of dewatering pumps to be
kept stand by.
Sufficient access and egress to be provided.

Page 3 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Seek Medical assistance


POS Emergency contact:
23220000 (ext: 666),
99247666.
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

high winds, Extreme dust


lightening, etc.
Working on Slope.
Heat stress.

Ladders shall be secured using suitable


means.
Safe distance to be maintained and
flagmen to be provided along with the
equipment.
Reflective clothing to be worn while
working near equipment.
Sufficient no. of lights to be provided.
Excavation should be inspected on daily
basis, before people entering pit.
Mechanical excavation shall be stopped in
case of any UG power cables/ utility was
exposed during excavation and shall be
informed to concerned MMC/ ORPIC
authority before carry further work.
Gas test to be conducted before people
entering the excavated pit.
All vehicles should be fitted with reverse
alarm.
Life line to be provided along with safety
harness to all the labours while working on
slope.
Goal post to be provided to warn the
equipments while working near overhead
Lines.
Banksmen should accompany the vehicle
while working under OHL.
Excavated material to be kept at least 01

Page 4 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

3.

Installation of
Cable Trays

Working Without valid


permit.
Personnel Injuries due to
slips, trips & falls.
People hit by moving
Vehicles.
People falling into the
Concrete Trench.
Unsafe Access or Egress.
Toxic gas.
Dust.
Noise.
Manual Handling.
Awkward position.
Electrocution.

Mtr away from the edge of the pit.


In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.
Adequate PPE to be used for the job.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to
be carried out.
Valid permit to be obtained from POS &
ORPIC before starting any job.
All people should undergo POS & ORPIC
Induction.
Tool Box Talk to be conducted before
starting any job on daily basis.
Ensure sufficient water is available at site
and also convey the message in Daily Tool
Box Talk.
A Competent Supervisor should be
available at site at all times.
Banksmen should accompany the vehicles
all the times.
Area to barricaded and cordoned off to
restrict the movement of people.
Adequate signboards and flickering lights
to be fixed to warn the night users.
Sufficient access and egress to be provided.

Page 5 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

Defective Power Tools.


Personal Injury to sharp
edges.
Unguarded Power tools.
Working at Height.
Fall of Materials.
Poor housekeeping.
Heat Stress.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust
lightening, etc.

Ladders shall be secured using suitable


means.
Sufficient no. of lights to be provided.
Gas test to be conducted before people
entering the excavated pit.
All power tools should be inspected before
use.
All power tools should have adequate
guards.
Periodical inspection of power tools to be
carried out.
Only trained and competent people should
be allowed to operate power tools.
Only trained and competent people should
carry out erection and alternation of
mobile scaffolding.
Before using the mobile scaffolding it has
to be inspected and certified by a
competent scaffolding inspector.
Mobile scaffolding has to be inspected and
recertified on weekly basis by a competent
scaffolding inspector.
All loose materials to be kept in a bucket or
container while working at height.
While shifting the mobile scaffolding no
persons should be on the top.
Scaffolding wheel should be of good quality
and in good condition.

Page 6 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

4.

Unloading of
Cable drums,
Cable Trays &
Cable tiles

Before climbing the scaffold worker has to


make sure the wheel lock has been
secured.
In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.
Adequate PPE to be used for the job.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to
be carried out.
Working Without valid
Valid permit to be obtained from POS &
ORPIC before starting any job.
Permit.

All people should undergo POS & ORPIC


Personnel Injury.
Induction.
Manual handling
Tool Box Talk to be conducted before
Lifting Equipment Failure.
starting any job on daily basis.
Lifting Gear Failure.
A Competent Rigging Supervisor and
Damage to nearby structures.
Rigging crew should be available at site at
all times.
Damage to U/G Utilities.
Unstable or Non secured load First Aider and first aid facility to be made
available at site at all times.
Falling of Load.
Drinking water available at site at all times.
Ground not level or too soft. Adequate job rotation and intervals to
Overturning of Equipment.
avoid heat stress.
People hit by equipment.
Area to be barricaded and signboards to be
placed to avoid any people entering the

Page 7 of 18

AWS

If in case of any incident


initiate Emergency Response
Plan.
Seek Medical assistance
POS Emergency contact:
23220000 (ext:666), 99247666
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

Contact / Collision.
Loading capacity exceeded.
Load swings in the air.
Shattered windows.
People hit by the truck or
equipment.
Slip, Trip & Fall.
Heat stress.
No boom angle indicator.
Improper load rating.
Inadequate inspection and
maintenance.
Uneven road, traffic control,
over other moving vehicles.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust
lightening, etc.

work area.
Flickering lights to be installed on the
barricades to warn night users.
The area to be checked for U/G utilities
before placing the crane.
No defects should be there on windshield
or window glass.
Crane should be placed on leveled surface
and far away from structures.
The place where crane to be placed should
be leveled and compacted properly and
test to be taken.
Only Competent and Authorized operator
should operate the crane.
Plan & control vehicle / equipment
movement with the presence of an
authorized banksmen.
Access road to be prepared and compacted
properly.
Adequate PPE to be used for the job.
Suspend all lifting activities if wind speed
exceeds 25 mph.
No people should work underneath the
suspended load while shifting.
Proper lifting plan to be prepared before
doing any major lifting activities and to be
approved by ORPIC / MMC.
All Lifting Equipments and Gear's should

Page 8 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

possess a valid third party certificate.


All Lifting Equipment's and Gears should be
inspected before carrying out the job.
All people should wear reflective jacket at
all times.
Tag line rope to be tied before lifting the
load.
A trained banksmen will be provided along
with the vehicle.
Boom radius indicator should be in working
condition along with the cutoff switch.
Before using the crane a daily inspection to
be carried out to make sure all key
elements are in working condition.
Cut off switch to be in working condition to
avoid exceeding the SWL.
In case of Hiab operation: Operator shall be
positioned opposite side of the truck to
that which load will be lifted or lowered.
Operator shall have clear view of the area
where the load will be lifted from and
lowered onto.
All the cable drums shall be protected with
edge stopper to prevent roll over.
Tagline /ropes shall not be snagged, must
be observed during lifting.
The work area to be kept clean and free of
obstruction.

Page 9 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

5.

Pre padding of
the Trench

Working Without valid


permit.
Personnel Injuries due to
slips, trips & falls.
People hit by moving
Vehicles.
Cave-ins, Collapse of
excavation.
Water in the excavated pits
Ground water logging.
People falling into the
excavated pit.
Unsafe Access or Egress.
Toxic gas.
Dust.
Noise.
Manual Handling.
Awkward position.
Overturning of Equipment.
Working on Slope.

After finishing the work, housekeeping to


be carried out.
In any adverse weather condition, work will
be stopped and resumed after conditions
are apt for the job.
Valid permit to be obtained from POS &
ORPIC before starting any job.
All people should undergo POS & ORPIC
Induction.
Tool Box Talk to be conducted before
starting any job on daily basis.
Ensure sufficient water is available at site
and also convey the message in Daily Tool
Box Talk.
A Competent Supervisor should be
available at site at all times.
Banksmen should accompany the vehicles
all the times.
Area to barricaded and cordoned off to
restrict the movement of people.
Adequate signboards and flickering lights
to be fixed to warn the night users.
Adequate no. of dewatering pumps to be
kept stand by.
Sufficient access and egress to be provided.
Safe distance to be maintained and
flagmen to be provided along with the
equipment.

Page 10 of 18

AWS

If in case of any incident


initiate Emergency Response
Plan.
Seek Medical assistance
POS Emergency contact:
23220000 (ext:666), 99247666
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

6.

Cable Pulling
and Laying

Electrocution.
Working under OHL.
Poor housekeeping.
Heat Stress.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust
lightening, etc.

Working Without valid


permit.

Reflective clothing to be worn while


working near equipment.
Excavation should be inspected on daily
basis, before people entering pit.
Gas test to be conducted before people
entering the excavated pit.
All vehicles should be fitted with reverse
alarm.
Life line to be provided along with safety
harness to all the labours while working on
slope.
Goal post to be provided to warn the
equipments while working near overhead
Lines.
Banksmen should accompany the vehicle
while working under OHL.
In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.
Adequate PPE to be used for the job.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to
be carried out.
Valid permit to be obtained from POS &
ORPIC before starting any job.
All people should undergo POS & ORPIC

Page 11 of 18

AWS

If in case of any incident


initiate Emergency Response
Plan.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

Personnel Injuries due to


slips, trips & falls.
People hit by moving
Vehicles
Cave-ins, Collapse of
excavation.
People falling into the
excavated pit.
Unsafe Access or Egress.
Toxic gas.
Dust.
Noise.
Manual Handling.
Awkward position.
Overturning of Equipment.
Working on Slope.
Electrocution.
Working under OHL.
Poor housekeeping.
Heat Stress.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust
lightening, etc.

Induction.
Tool Box Talk to be conducted before
starting any job on daily basis.
Ensure sufficient water is available at site
and also convey the message in Daily Tool
Box Talk.
A Competent Supervisor should be
available at site at all times.
Area to barricaded and cordoned off to
restrict the movement of people.
Adequate signboards and flickering lights
to be fixed to warn the night users.
Sufficient access and egress to be provided.
Safe distance to be maintained and
flagmen to be provided along with the
equipment.
Reflective clothing to be worn while
working near equipment.
Sufficient no. of lights to be provided.
Gas test to be conducted before people
entering the excavated pit.
All vehicles should be fitted with reverse
alarm.
Workers shall be taught in cable laying and
pulling techniques including the
requirement for ensuring good manual
handling techniques.
Workers shall not run while cable pulling.

Page 12 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Seek Medical assistance


POS Emergency contact:
23220000 (ext:666), 99247666
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

7.

Post Padding of
the Trench

Working Without valid


permit.
Personnel Injuries due to
slips, trips & falls.

Sufficient manpower to be employed for


cable laying and pulling.
Good communication to be carried out
during cable pulling
Rollers shall be used for easy pulling of the
Lines.
Life line to be provided along with safety
harness to all the labours while working on
slope.
Goal post to be provided to warn the
equipments while working near overhead
Lines.
Banksmen should accompany the vehicle
while working under OHL.
In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.
Adequate PPE to be used for the job.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to
be carried out.
Valid permit to be obtained from POS &
ORPIC before starting any job.
All people should undergo POS & ORPIC
Induction.
Tool Box Talk to be conducted before

Page 13 of 18

AWS

If in case of any incident


initiate Emergency Response
Plan.
Seek Medical assistance

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

People hit by moving


Vehicles
Cave-ins, Collapse of
excavation.
Water in the excavated pits
Ground water logging
People falling into the
excavated pit.
Unsafe Access or Egress.
Toxic gas.
Dust.
Noise.
Insufficient lighting
Manual Handling.
Awkward position.
Overturning of Equipment.
Poor housekeeping.
Working on Slope.
Electrocution.
Working under OHL.
Heat Stress.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust

starting any job on daily basis.


Ensure sufficient water is available at site
and also convey the message in Daily Tool
Box Talk.
A Competent Supervisor should be
available at site at all times.
Banksmen should accompany the vehicles
all the times.
Area to barricaded and cordoned off to
restrict the movement of people.
Adequate signboards and flickering lights
to be fixed to warn the night users.
Adequate no. of dewatering pumps to be
kept stand by.
Sufficient access and egress to be provided.
Safe distance to be maintained and
flagmen to be provided along with the
equipment.
Reflective clothing to be worn while
working near equipment.
Trenches should be inspected on daily
basis, before people entering pit.
Gas test to be conducted before people
entering the excavated pit.
All vehicles should be fitted with reverse
alarm.
Life line to be provided along with safety
harness to all the labours while working on

Page 14 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

POS Emergency contact:


23220000 (ext:666), 99247666
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

lightening, etc.

8.

Laying of Cable
Tile & Warning
tape.

Working Without valid


permit.
Personnel Injuries due to
slips, trips & falls.
People falling into the
excavated pit.
Unsafe Access or Egress.
Dust.
Noise.
Manual Handling.
Awkward position.

slope.
Goal post to be provided to warn the
equipments while working near overhead
Lines.
Banksmen should accompany the vehicle
while working under OHL.
In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.
Adequate PPE to be used for the job.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to
be carried out.
Valid permit to be obtained from POS &
ORPIC before starting any job.
All people should undergo POS & ORPIC
Induction.
Tool Box Talk to be conducted before
starting any job on daily basis.
First Aider and first aid facility to be made
available at site at all times.
Drinking water available at site at all times.
Adequate job rotation and intervals to
avoid heat stress.
Area to be barricaded and signboards to be
placed to avoid any people entering the

Page 15 of 18

AWS

If in case of any incident


initiate Emergency Response
Plan.
Seek Medical assistance
POS Emergency contact:
23220000 (ext:666), 99247666
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

Poor housekeeping.
Heat Stress.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust
lightening, etc.

9.

Backfilling and
Compaction

Working Without valid


permit.
Unsafe Access or Egress.
People falling into the
excavated pit.
Dust.
People hit by moving
vehicles.
Working on Slope.
Electrocution.
Working under OHL.
Noise.
Vibration.

work area.
Flickering lights to be installed on the
barricades to warn night users.
Adequate PPE to be used for the job.
All people should wear reflective jacket at
all times.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to
be carried out.
In any adverse weather condition, work will
be stopped and resumed after conditions
are apt for the job.
Valid permit to be obtained from POS &
ORPIC before starting any job.
All people should undergo POS & ORPIC
Induction.
Tool Box Talk to be conducted before
starting any job on daily basis.
A Competent Supervisor should be
available at site at all times.
Proper and sufficient no of access & egress
to be provided.
Adequate no of dewatering pumps to be
kept in standby for use.
Area to be barricaded and adequate
signages to be placed to avoid people
entering the work area.

Page 16 of 18

AWS

If in case of any incident


initiate Emergency Response
Plan.
Seek Medical assistance
POS Emergency contact:
23220000 (ext:666), 99247666
AWS Emergency Contact No.:
91409583, 91395892,
91395890.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

Personnel Injury.
Adverse weather condition
like Extreme heat, Extreme
high winds, Extreme dust
lightening, etc.
Heat stress.
Slip, Trip & Fall.

Proper respiratory protection will be given


to avoid the dust.
Banksmen to be provided to control the
traffic.
Vehicle to be fitted with reverse alarm.
Stopper shall be in practice to control the
movement of equipment near trench edge.
Life line to be provided along with safety
harness to all the labours while working on
slope.
Goal post to be provided to warn the
equipments while working near overhead
Lines.
Banksmen should accompany the vehicle
while working under OHL.
Adequate type of PPE to be used for the
job.
Periodic rest breaks / stretch-outs / crew
rotation.
All moving parts to be adequately guarded
and shall not be removed.
The person operating the roller to be
trained on operation.
Adequate First Aid provision to be provided
at site.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to

Page 17 of 18

Date: 07/11/2016
Location: From Substation
to MCC Building and to Oil
Jetty.

CLIENT
CONTRACT NO.: 4600002029

EPC FOR REVAMP OF OIL PIER JETTY AT PORT OF SALALAH


(RAYSUT)

CONTRACTOR.

JOB HAZARD ANALYISIS


Doc. No: 2029-PJ-JHA-017

Rev no:01

Date: 07/11/2016

Job description: JHA for Cable Laying.


Member present: HSE Department, Project department, Operation Department.

Location: From Substation


to MCC Building and to Oil
Jetty.

be carried out.
Note: During execution if any disturbance or emergency occurs to the process the job will be suspended immediately and shall be resumed after the issue
has been resolved.

PPE to be used during execution of the Job:


Hard hat, Safety Googles, Protective Clothing, Hand Gloves, Ear Plug / Muff, Nose mask, Safety Boots., Safety Harness.
Other Misc. Equipments to be used during execution of the Job:
Hand Tools, Road Barriers, Safety Cones, Excavator, Backhoe loader.

Page 18 of 18