Documente Academic
Documente Profesional
Documente Cultură
Contents
1.
Purpose................................................................................................................
2.
3.
2.1
2.2
3.2
3.3
3.4
3.5
Trial Operations..............................................................................................
4.
Airport Opening....................................................................................................
5.
Timelines..............................................................................................................
6.
7.
6.1
6.2
6.3
6.4
6.5
6.6
Fuel Supplies................................................................................................
6.7
Staff Recruitment.........................................................................................
1. Purpose.
The following chapters explain the preconditions that will effect the
proposed airport opening date for the new KAIA.
During the phases that follow, all stakeholders are in the preparation
process of employing additional staff and familiarizing and training those
staff to be ready to operate at their new workplace.
RECRUITMENT SHOULD BE TAKING
PLACE NOW.
4. Airport Opening
Preparations have been underway to plan and carry out the
first move and the first commercial flight for more than twenty
four months at this stage. All construction related processes
and operational readiness functions have been completed
successfully and the airport can open.
5. Timelines
The complexities of harmonizing all the construction,
administrative, regulatory and operational functions to be able
to reach a preliminary handover date firstly and to reach the
opening date secondly with all things in place and in good
operating condition is a mammoth task with all stakeholders
needing to provide their total commitment.
It is very difficult to know when recruitment and training
should be undertaken if stakeholders are confused about the
construction schedule. Any construction delays can cause
recruitment and training processes to be out of line and
retraining is likely to be required.
Additionally many functions cannot take place without other
functions being completed. Critical path items will delay
airport opening.
10
11
12