Documente Academic
Documente Profesional
Documente Cultură
OUTLINE
1.
2.
3.
4.
MW
1400
1200
1000
800
600
400
200
30
20
28
29
20
27
20
20
26
24
25
20
20
23
20
20
22
21
20
20
20
20
19
17
18
20
20
20
15
16
20
14
20
20
13
20
20
12
Biomass
Baseload
capacity between 2014 and 2019, Uganda will have to bring at least 150MW on-stream
within next 3-5 years
If HPP Isimba/ HPP Karuma are delayed, the demand to bring additional capacity online
is even greater
3
Comparatively low REFiT tariff schedule (in some cases below levelized cost of
FiT Premium
Payment
Mechanism
World Bank /
MIGA
Guarantees
PRG Facility offered by the World Bank / MIGA to address political and
offtaker risks (outside focus of this presentation)
Private Debt/
Equity Facility
Facility (led by DB, open to other banks and investors) will offer debt
and equity instruments to private developers (no exclusivity, outside
focus of this presentation)
OUTLINE
1.
2.
3.
4.
5.
TA Facility
Payment Period
(US$/kWh)
(US$/kWh)
(Yrs)
0.079
0.02
20
Hydro (1 ><=8MW)
0.082 0.092
0.02
20
Hydro (500kW><=1MW)
0.109
Not included
20
Bagasse
0.081
0.01
20
Biomass
0.103
0.01
20
Biogas
0.115
No subsidy required
20
Landfill gas
0.089
Not included
20
Geothermal
0.077
Not included
20
Solar PV
0.362
No subsidy required
20
Wind
0.124
Not included
20
Technology
Note: The subsidy determination was done based on the 20 year PPA projects receive from UETCL.
1. Calculate the Net Present Value (NPV) of tariff subsidy over the duration of the 20-year
PPA RE projects will receive from UETCL (plus potential adjustments for hydrological
risk and cap on capacity factor).
2. Disbursement in two stages:
Financial and
Economic
RE projects need
to demonstrate
financial and
economically
sustainability
Compliance with
least-cost
development path
for the Ugandan
power sector
ESG
RE projects need
to comply with
KfW/ World Bank
Environmental
Social and
Governance
(ESG)
requirements
Call for
Proposals
Legal
RE projects need
to comply with all
necessary legal
and financial due
diligence
standards (KYC
rules, etc.)
RE projects need
to respond to the
call for proposals
run by KfW/ ERA
OUTLINE
1.
2.
3.
4.
10
Private Finance
(Debt+Equity)
Pays REFiT
From:
-GET FiT Private Facility
-Commercial Banks
-DFIs
-Equity Funds
-Others
IPP
Pays Premium on
REFiT to close gap
between REFiT and
LCOE
KfW
GET FiT Facility
(1USc-2USc/ kWh, depending on technology)
Delivers
power
Guarantee for
UETCL offtaker
risk
UETCL
PPA
Owns
100%
(20 years,
Standardized PPA,
based on REFiT
Government
of
Uganda
IDA-Loan for of
guarantee volume
and Indemnity
Agreement
OUTLINE
1.
2.
3.
4.
13
Project name
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Siti 1
Siti 2
Muzizi
Kikagati
Mount Elgon
Mubuku III
Kakaka
Nengo Bridge
Lubilia
Nyamagasani
Rwimi
Kymabura
Kinyara Sugar
Kakira Sugar
SCOUL Sugar
Alam Group
Tilda Rice
UgandaSolarOne
Equator Solar
Technology
Hydro
Hydro
Hydro
Hydro
Hydro
Hydro
Hydro
Hydro
Hydro
Hydro
Hydro
Hydro
Biomass
Biomass
Biomass
Biomass
Biomass
PV
PV
MW
planned
5,0
16,5
20,0
16,0
10,0
9,0
8,0
6,5
4,0
3,0
5,6
8,3
20,0
20,0
5,0
5,0
1,0
2,0
2,0
166,9
Investment
size (USDm)
19,0
36,0
60,0
48,0
30,0
25,2
28,0
18,2
14,0
9,0
15,9
24,9
60,0
60,0
15,0
15,0
3,0
6,0
6,0
493,2
Start of
construction
2013
2014
2014
2013
2014
2014
2014
2013
2014
2014
2013
2014
2014
2013
2014
2014
2014
2013
2014
Start of
operation
2015
2016
2016
2015
2016
2016
2016
2015
2016
2016
2015
2016
2015
2014
2015
2015
2015
2014
2015
Yearly output
(MWh/MW)
5.000
4.200
6.700
7.500
3.840
5.000
4.000
5.000
6.750
6.500
5.000
5.000
3.500
3.500
3.500
3.500
3.500
2.100
2.100
25,0
20,0
15,5
20,1
15,0
10,0
10,1
5,0
3,2
-
2012
2013
10,1
10,1
9,2
6,0
4,0
0,8
2014
2015
FiT premium support
2016
COD grant
2017
2018
2019
2020
80,0
30%
25%
70,0
60,0
20%
50,0
15%
40,0
30,0
10%
20,0
5%
10,0
-
0%
20122013 201420152016 20172018 20192020 202120222023 20242025 202620272028 20292030 20312032 203320342035 20362037
Public facility payment
Base FiT
Burden sharing (rhs)
Note: Dark blue represents GET FiT contributions; light blue represents contributions from UETCL / Ugandan rate payers.
Calculations based on 2% discount factor.
Burden sharing
90,0
35%
Biomass
Existing small hydro
Peak demand (base case)
Baseload
Planned large hydro
30
20
29
20
28
20
27
20
26
20
25
20
24
20
23
20
22
20
21
20
20
20
19
20
18
20
17
20
16
20
15
20
14
20
20
20
13
2000
1800
1600
1400
1200
1000
800
600
400
200
0
12
MW
1.800
1.600
1.400
GWh
1.200
1.000
800
600
400
200
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
11,0
10,5
10,0
9,5
9,0
8,5
8,0
7,5
7,0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
BACKUP
No.
1
2
3
4
SHP
SHP
SHP
HPP
B.
No.
1
2
3
4
5
6
SHP
SHP
SHP
HPP
HPP
SHP
C.
No.
1
2
3
4
5
6
7
8
9
10
11
12
Siti 1
Siti 2
Muzizi
Kikagati
Mount Elgon
Mubuku III
Kakaka
Nengo Bridge
Lubilia
Nyamagasani
Rwimi I
Kymabura
D.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
Project
Giciye I
Rukarara
Rukarara II + Rubyiro III
Musarara I or Gaseke
Mukungwa III or Nyundo
Akanyaru
Ntaruka B
Koko
Mukungwa IV
Ntaruka A
Nyiramuruta
Rwondo
Nyabarongo
D.
No.
1
2
3
4
5
6
7
8
9
Project
Ishasha
Bugoye
Mpanga
Bujagali
Project
Buseruka
Nyagak I
Nyagak III
Karuma
Isimba
Nyamwamba
Project
Project
Yala
Kamari
Tagabi
Gura
North Mathioya 1
North Mathioya 2
North Mathioya 3
South Mathioya
Maragua
Kipkurere
Kipchoria
Installed capacity
6.6MW
13MW
18MW
250MW
Commissioning
2011
2011
2011
2012
Developer
Ecopower
Tronder
SAEMS
BEL
Country
Uganda
Uganda
Uganda
Uganda
Installed capacity
9MW
3.4MW
4.4MW
600MW
120MW
14MW
Commissioning
2012
2012
2016
2019
2018
2015
Developer
Hydromaxx
WENRECO
UEGCL
UEGCL
UEGCL
SAEMS
Country
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Installed capacity
5MW
16,5MW
20MW
16MW
10MW
9MW
8MW
6,5MW
4MW
3MW
5,6MW
8,3MW
Commissioning
2015
2016
2016
2015
2016
2016
2016
2015
2016
2016
2015
2016
Developer
VS Hydro
VS Hydro
UEGCL
Tronder
Mt. Elgon Hydro Company
Kasese Cobalt Company
Greenewus
Jacobsen Elektro
Lubilia Kawembe Hydro
LTL Holdings
Ecopower
Ziba
Country
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Uganda
Installed capacity
4MW
9MW
2MW
0,438MW
2,5MW
4MW
5MW
1MW
1MW
2MW
1MW
1MW
17MW
Commissioning
2013
2011
2013
2012
2013
n.a.
n.a.
n.a.
n.a.
2014
n.a.
n.a.
n.a.
Developer
RW Mountain Tea
Ecopower
BTC, RECO
GIZ, SOGEMR
GoR, SOGEMR
MININFRA
GoR
REGREPOWER
MININFRA
BTC
MININFRA
MININFRA
Country
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Rwanda
Installed capacity
4MW
1MW
1MW
5MW
2MW
2MW
2MW
2MW
2MW
3MW
3MW
Commissioning
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
Source
n.a.
Unilever
Unilever
KTDA
KTDA
KTDA
KTDA
KTDA
KTDA
n.a.
Eastern Produce Kenya
Country
Kenya
Kenya
Kenya
Kenya
Kenya
Kenya
Kenya
Kenya
Kenya
Kenya
Kenya
20
60
PPP structure:
government: 30%, grant
private investor: 70%
18 USD million
42 USD million
2,33333333
60
12
1
Kikagati HPP
installed capacity in MW
investment costs in USD million
16
48
PPP structure:
government: 30%, grant
private investor: 70%
2,33333333
48
23,2
1
2,06896552
20
60
PPP structure:
government: 30%, grant
private investor: 70%
18 USD million
42 USD million
2,33333333
60
6,8
1
8,82352941
12 USD million
48 USD million
13,1 USD million
1 4,58015267
12 USD million
48 USD million
13,1 USD million
1 4,58015267
30 USD million
30 USD million
1
24 USD million
24 USD million
1
30 USD million
30 USD million
1
30%
25%
Equity IRR
20%
(10.0)%
15%
25,0%
10%
11,4%
15,0%
5%
3,6%
0%
Target EIRR
Revised WACC
Actual WACC
Actual WACC @ base
increase due to top-up
FiT
RETAIL TARIFFS
Charge
Domestic
Commercial
Medium
Industrial
Large
Industrial
Street Lights
Average
524.5
(USDc 21)
487.6
(USDc 19)
458.9
(USDc 18)
312.8
(USDc 12)
488.7
(USDc 19)
Peak
550.9
(USDc 22)
518.6
(USDc 21)
375.4
(USDc 15)
Shoulder
487.6
(USDc 19)
458.9
(USDc 18)
312.8
(USDc 12)
Off-Peak
380.8
(USDc 15)
376.3
(USDc 15)
256.6
(USDc 10)