Documente Academic
Documente Profesional
Documente Cultură
Appendix N
Appendix N Instrumentation and Monitoring
N1.0
The contractor shall provide, install, maintain, calibrate and where necessary
reinstate instruments and monitor all of the works, including temporary works
as shown on the drawings and as summarized in Table N1. The contractor
shall also make all necessary alterations to suit his proposed method of
construction and site condition as agreed by the Engineer.
N2.0
N3.0
The Contractor shall adopt a unique referencing system for the instruments
that is acceptable to the Engineer, such as :
XXX-XXXXXX-XXXXX-XXX-XX
Instrument number
Instrument type
Structure number, if any
SB chainage
Contract number
N4.0
The instrument types, purpose and depth are summarised in Table N1.
Locations of the proposed instruments are shown on the Drawings.
Table N1 : Proposed Instrument Types, Purpose and Depth
Instrument Type
Open Standpipes /
piezometers /
Observation Wells
Inplace / vertical
Inclinometer
Ground settlement
point
Building movement
point
1108 PS
Purpose
To monitor change in
groundwater level and
piezometric heads in soils /
rock
To monitor the temporary
retaining wall deflection / To
monitor subsurface lateral
ground movement
Depth
Temporary retaining
wall toe level / To be
determined on site
Temporary retaining
wall toe level / In rock /
within stable ground as
determined by the
Engineer on site
On ground surface
October 2012
D/MTRCL/SCL/1108/PS/001/A1
Appendix N
Instrument Type
Purpose
Tilt plate
Utility monitoring
point
Vibration monitoring
point
Magnetic probe
extensometer
Tell-tale
Strain gauge
Real-time monitoring
using ADMS
To monitor structure
movement when soft ground
tunnel / adit construction is
in progress
To monitor convergence
when tunnel / adit
construction is in progress
To monitor the accuracy of
installation and performance
of ground freezing works
Tape extensometer
Instruments*
associated with
ground freezing (e.g.
thermocouples for
freeze body
temperature,
precision gyroscope
for freeze tubes
position, etc.)
Depth
On selected buildings
and structure
On selected utilities
On ground surface
Temporary retaining
wall toe level / In rock /
within stable ground as
determined by the
Engineer on site
On buildings and
structures
On Temporary strut /
ring beam
On selected buildings
N5.0
The Contractor shall review the existing instruments installed by the Employer
and shall take over and maintain the instruments. For each of the existing
instruments, the Contractor shall identify the location, check that the
instrument is still in working condition and indicate it on the instrument
location plan as required under Clause 23.11 of the M&W Specification.
N6.0
1108 PS
App. N 2/6
October 2012
D/MTRCL/SCL/1108/PS/001/A1
Appendix N
(a)
(b)
(c)
N7.0
After agreement with the Engineer of the formal initial readings, the
Contractor shall initiate background monitoring or completion of installation of
new instruments, which shall, for the latter, be within 60 Days of the Date of
Commencement. During background monitoring the Contractor shall not carry
out any active construction works within 100m.
N8.0
After the Engineer has accepted that the background conditions have been
established, regular monitoring shall commence. The requirements for the
different phases of regular monitoring for each instrumentation type are
shown on the drawings. Unless shown otherwise, these requirements shall
be followed throughout the monitoring of the instruments. Based on the
Contractors construction methods, he shall indicate in the Instrumentation
Schedule the construction activities that require active monitoring. The
Engineer will advise and may amend the list of construction activities that
require active monitoring and the stages that will permit background
monitoring to be undertaken.
1108 PS
App. N 3/6
October 2012
D/MTRCL/SCL/1108/PS/001/A1
Appendix N
N9.0
The Contractor shall carry out daily visual inspection on the ground and
structures around the active monitoring zone. The Contractor shall inform the
Engineer and the IMC immediately for any new sign of distress observed
during the inspection.
N17.0 The Contractor shall take over the instrumentation as set out below upon
commencement of the Contract.
1108 PS
App. N 4/6
October 2012
D/MTRCL/SCL/1108/PS/001/A1
Appendix N
Table N2 : Existing Groundwater Level Monitoring Installation to be Monitored
Hole No.
Installation Device
Piezometer Tip Depth
Standpipe Tip Depth
11202/
(m below existing ground level) (m below existing ground level)
SCL/DH073(P)
30.00
10.00
SCL/DH073a(P)
30.00
10.00
16.45
6.00
SCL/DH076(P)
2209/
SCL/DH067(P)
20.00
NA
SCL/DH070(P)
NA
21.00
SCL/DH072(P)
NA
20.50
SCL/DH075(P)
28.00
NA
SCL/DH078(P)
26.00
NA
SCL/DH0303(P)
36.14
NA
SCL/DH0304(P)
40.50
NA
N18.0 Movement shall be monitored against Alert, Action and Alarm trigger levels
(AAA trigger levels) in accordance with MTRC M&W Specification Clause
2.18 and are set as follows:
-
N19.0 On reaching the Alert Level, the Contractor shall inform the Engineer within 24
hours. The contractor shall review the movement, assess the effects on
adjacent structures and predict further movements. A Detailed Plan of
Action shall be proposed by the Contractor to the satisfaction of the Engineer.
The Contractor shall implement the Response Actions identified in the
Detailed Plan of Action for reaching the Alert Level.
N20.0 On reaching the Action Level, the Contractor shall immediately implement the
Response Actions given in the Detailed Plan of Action for reaching Action
Level. Work may then only proceed if the remedial measures have been
implemented and are, in the opinion of the Engineer, shown to be effective.
The Contractor shall make appropriate amendments to the Detailed Plan of
Action where necessary.
N21.0 On reaching the Alarm Level or if any undue settlement or damage to
adjacent roads, buildings, structures or utilities are observed, the Contractor
shall notify the Engineer immediately. The Contractor shall implement
emergency response actions including suspending all construction activities
within 50m of the instruments, unless otherwise agreed by the Engineer.
The Contractor shall provide a report detailing the full history of movements
and remedial measures adopted in relation to the actual construction
1108 PS
App. N 5/6
October 2012
D/MTRCL/SCL/1108/PS/001/A1
Appendix N
sequence. The report shall be reviewed and interpretation of events given to
the Engineer with recommendations for enabling work to proceed. Work
may only resume upon the written instruction of the Engineer.
N22.0 The AAA trigger levels as shown below and on the Drawings, whichever is
more stringent, shall be followed:
Table N3 : AAA Trigger Levels for Monitoring
Structure /
Monitoring Point
Utilities settlement
Vibration induced by all
vibration-producing
construction activities
Existing buildings
settlement
Groundwater
drawdown with
reference to lowest
historical groundwater
level
1108 PS
Tender Addendum No. 1
Alert
Action
Alarm
12mm
7.5mm/sec
20mm
12mm/sec
25mm
15mm/sec
20mm
30mm
40mm
500mm
800mm
1000mm
App. N 6/6
November 2012