PROJECT CONSORTIUM

2015_21 BENI SUEF CCPP

Sr

INDEX

01

Cover Page

001

index

002

P & ID

003

LINE LIST AND ISOMETRIC

004

Instrument & VALVE LIST

005

SUPPORT LIST AND DRAWINGS

006

PUNCH LIST

009

WELDING RECORDS AND NDE REPORTS

010

CALIBRATION GUAGE

011

PRE-TEST INSPECTION CHECKLIST

012

HYDROSTATIC TEST REPORT

013

POST TEST INSPECTION CHECK LIST

014
015
016
017

1020/FP 211 Att.01 Rev.0 07 Apr. 2016

YES

NO

REMARKS

PROJECT CONSORTIUM
2015_21 BENI SUEF CCPP
PRE-TEST INSPECTION CHECK LIST

Pre-Test inspection checklist

Sr.
01

Visual weld inspection

02

NDE status

03

Document check

04

Mechanical check and punching

05

Punch list code a clearance

06

Piping conforms to drawings, marked up P & ID and isometric drawings

07

All pipe supports installed & temporary spools installed

08

Test spades/temp. Blinds installed

09

Instruments removed/blocked

10

Check valve internals removed/jacked

11

Control valves removed/isolated

12

PSV/TSV removed/isolated

13

Expansion joints removed

14

Orifice plates removed

15

Gate valves in open position

16

Ball/plug valves in half open position

17

Strainer/filter element removed

18

All vents and drains available

19

Pressure source located upstream of check valves

20

All welded/threaded joints are exposed and accessible

21

Pressure gauges calibrated, PRV calibrated and installed

22

Water analysis

23

Pre cleaning completed and accepted

24

Released for hydrostatic testing

RESULT
Yes

REMARKS:

DETAILS

SUBCONTRACTOR

NAME
SIGNATURE
DESIGNATION
DATE

1020/FP 211 Att.01 Rev.0 07 Apr. 2016

PSP QC

SIEMENS

OWNER

PROJECT CONSORTIUM
2015_21 BENI SUEF CCPP
PRE-TEST INSPECTION CHECK LIST
RESULT
No

OWNER

1020/FP 211 Att.01 Rev.0 07 Apr. 2016

N.A.

PROJECT CONSORTIUM
2015_21 BENI SUEF CCPP
POST-TEST INSPECTION CHECKLIST
FORM No. (10)

PROJECT

BENI SUEF COMBINED CYCLE POWER PLANT

OWNER

UPPER EGYPT ELECTRICITY PRODUCTION CO.

TEST PACK No.

CONTRACTOR

ELSEWEDY ELECTRIC PSP

DATE

SUBCONTRACTOR

REF. FQP No.

Post test inspection Checklist

P&ID:
SYSTEM:
DESIGN PRESSURE:
Sr.

TEST PRESSURE:
Items To Be Checked During Post-Test

Yes

01

Flushing completed

02

Drying completed

03

Remove temporary test spades/blind &Install new gasket/complete bolting

04

Process blinds/spades installed

05

Reinstate instruments

06

Reinstate check valve internals

07

Reinstate control valves. Flow direction correct

08

Reinstate PSV/TSV

09

Reinstate expansion joint

10

Reinstate orifice plate in correct flow direction

11

Reinstate strainer/filter element

12

Check all vents and drains are capped/plugged

13

New gaskets installed on reinstated flanged component, Rebolted & tightened

14

Punch list clearance

RESULT
NO

15
16
17
18
19
23
24
REMARKS:
DETAILS

SUBCONTRACTOR

NAME
1020/FP 211 Att.01 Rev.0 07 Apr. 2016

PSP QC

SIEMENS

OWNER

N.A.

PROJECT CONSORTIUM
2015_21 BENI SUEF CCPP
POST-TEST INSPECTION CHECKLIST
SIGNATURE
DESIGNATION
DATE

1020/FP 211 Att.01 Rev.0 07 Apr. 2016