Documente Academic
Documente Profesional
Documente Cultură
TB Maintenance Concept
A lifetime of support for your investment.
Protecting your
Investment
Siemens are committed to helping maintain
your operations in the field.
The combination of our accurate build
information, component history and
component lifing data allows us to schedule
the correct maintenance, optimizing
operation, reducing downtime and reduces
the risk of component failure.
What do we provide?
Operational Maintenance
- Typical operational tasks
- Parts Kit
Scheduled Maintenance
- Typical maintenance work scopes
- Parts Kits
Maintenance Planning
- Maintenance scheduling
- General Parts Kits
12 - 13
14 - 15
4-5
6 - 11
Daily checks
Weekly checks
The gas starter motor may be lubricated (if fitted) and
the oil fog lubricator will be replenished.
Operational Maintenance
Operational maintenance activities are typically performed on a daily, weekly,
and monthly basis. Less frequent checks could be opportunity based
according to operational running regimes.
Quarterly checks
A simulated check of the over speed safety device to
be performed.
Generator holding down bolts and visible fixings are
checked to be secure in accordance with the
manufacturers recommendations.
Vibration levels are reviewed.
Lube oil pumps are checked for noisy operation and
output pressures are examined.
Six monthly checks
Bearings on all motors will be greased.
An external check of system protective devices to be
made.
Door seals, hinges, pivot pins and fasteners are
examined and lubricated as required.
A thorough cleaning of the flame trap to be performed.
On condition
Using the installed system, the compressor may be
cleaned and its recovery monitored to enable
adjustment of the period between cleaning. (The
combustion drain to be inspected for particles.)
For Hot wash or cold crank wash on fluid based
systems, the correct operation of all automatic drain
valves on systems with fluid wash systems may be
checked.
An inspection of the under base is made to check for
signs of corrosion. If necessary, corrosion will be
removed and protective treatment applied.
Parts Kit
All spare parts used during these checks would come from
an operational consumables kit. This kit would contain
easily replaceable items such as fuses, bulbs and filter
elements etc. These activities would normally be carried
out by suitably trained site personnel.
Components maintained
at calendar intervals are
done so on the basis of
safety, regulatory or as a
consequence of
application conditions.
Scheduled Maintenance
Scheduled maintenance is carried out based on either calendar intervals
or running hours, depending on the components under consideration.
Service exchange Gas Generators and Power Turbine
assemblies are recommended as an alternative to the B
Type (24,000 hours) inspection on the Gas Generator, and
on C Type (48,000 hours) inspection(s) on both the Gas
Generator and Power Turbine, where on-site internal
inspection of the complete gas generator and power
turbine assemblies are normally carried out, based on the
expected design life of the hot path components.
It is therefore recommended that any resulting overhaul
(strip/rebuild) of the Gas Generator and Power Turbine
sections is carried out at a Siemens SGT approved
workshop. This ensures that the correct processes and
tooling are utilized, including replacement of CT bladed
discs and the subsequent balancing of the Gas Generator
and Power Turbine rotor assembly is performed to the
correct specification.
Maintenance based on the running hours of the gas turbine may be
related to predictable events such as bearing and blade life.
A Service Inspection
This is recommended annually and consists of calibration
and system/ operational/ safety checks, filters and
consumables are changed and lubricant levels checked
and replenished. The condition of the combustion system
and first stage stators are checked by removal of the
combustor end covers.
The workscope of a typical A service for the TB gas turbine
is detailed below. The estimated time to complete the
workscope at site using two men (one Siemens personnel
and one customer assistant at a total of twenty man hours
per day) is approximately 7 days.
Pre-shutdown checks
All data from the Turbine Control Module (TCM) may
be recorded during the pre-shutdown checks.
The compressor may be cleaned and a post clean data
comparison performed.
Other checks include inlet guide vane operation,
vibration surveys, leak checks, filter checks, noise
levels of the pumps, fans, etc, various engine
temperatures and pressures, instrument/gauge checks,
liquid fuel piping vibration and a test of fuel
changeover, if applicable.
Shutdown procedure
The driven unit and starter motor hold down bolts are
checked for security and alignment; couplings are
regreased and rubber couplings are inspected as
required.
Electric motor and gas starters bearings are greased.
All pipe work, hoses and flexibles are checked and
replaced on condition.
A visual check is made of the vent dampers and their
operation.
Electrical
Copies of controls software are taken as required,
including package or driven units.
Certified electrical equipment in hazardous areas is
inspected, if applicable.
Fuel actuators are calibrated.
Planned inspection
intervals of 8000 fired
hours, or annually, with
an intermediate
inspection every third
year or 24000 fired hours
and major inspection
every six years or 48000
fired hours, give low cost
maintenance and high
availability.
B Service Inspection
This is recommended at 24,000 hours and is the A type
service plus a total strip of the gas generator to inspect
critical components and assess their suitability for a
further three year life cycle.
The work scope of a typical B service for the TB gas
turbine is detailed below. The B service can be
performed at site or as a Workshop Overhaul at a Siemens
Service Centre.
The estimated time to complete the work scope at site
using 2 men (one Siemens personnel and one customer
assistant at a total of 20 twenty man hours per day) is
approximately 14 fourteen days.
All A Service activities are included, plus the following:
Gearbox
A visual inspection of the internals is made and
clearances are recorded on build sheets.
Package
The gas fuel throttle is stripped down, if required.
Core Engine - Gas Generator (GG)
Bearings and labyrinth seals are dismantled and
inspected.
The compressor rotor and stator blading is cleaned by
hand, as required, with clearances recorded on build sheets.
C Service Inspection
This is recommended at 48,000 hours and in addition to
the B type service, involves a strip of the power turbine.
The work scope of a typical C service for the TB gas
turbine is detailed below. The C service can be
performed at site or as a Workshop Overhaul at a Siemens
Service Centre.
The estimated time to complete the work scope using 2
men (one Siemens personnel and one customer assistant
at a total of twenty man hours per day) is approximately
twenty one days.
All A and B Service activities are included plus the following:
Package
Flow tests are carried out (certain configurations).
Power Turbine (PT)
The PT is dismantled and the blading, bearings and
labyrinth seals are inspected. All findings and
clearances are recorded on build sheets
Diffuser welds undergo dye penetration crack
detection and are repaired as required.
Parts Kit
Spares for these maintenance intervals consist of various
kits, an inspection replacement parts kit will contain
those items that are definitely to be replaced during
servicing, and an inspection contingency kit will
contain critical components that may be replaced during
the annual inspection depending on their condition. In
support of these it is recommended that an emergency
backup spares kit should be held on site to cover other
items that may be found at fault during servicing such as
valves, thermocouples and igniters.
Maintenance Planning
Planned maintenance reduces the cost and disruption of unscheduled outages
Maintenance planning should cover at least the following
areas:
Maintenance Scheduling
The maintenance schedule of the equipment depends on
annual running hours and the component life consumed,
assuming that the gas turbine is running 8,000 - 8,500
hours per year.
Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Technical overview
STA-RMS consists of five components:
Data acquisition: this is automatically recorded within
the control system of the equipment.
* Siemens Turbomachinery
Applications - Remote Monitoring
System (STA-RMS)
Help Desk
24/7 Hotline Support with duty CSM and technical
specialists.
The 24/7 Hotline Support can ensure help is there when
you really need it, either by telephone or through secure
online connection.
Our help desk is available to assist you with any kind
of technical issue, as part of an LTP or Service Support
Agreement, whether it is for performance fine tuning or
breakdown assistance.
www.siemens.co.uk/energy