Documente Academic
Documente Profesional
Documente Cultură
Prof D. Quiun,
Pontificia Universidad Catlica del Per, Peru.
dquiun@pucp.edu.pe
1. INTRODUCTION
The vast majority of earthquake fatalities in the last century have resulted from building failures with a
growing disparity between vulnerability of those in developing and developed countries. The greatest
risk is by far presented to inhabitants of non-engineered adobe structures (Figure 2) as demonstrated in
the 2003 Bam (Iran) earthquake, where many of the thousands of deaths were attributable to vulnerable
adobe (sun-dried mud brick) structures. This is due to the nature of the material (high mass, low strength,
brittle) and, in the case of non-engineered housing, also the lack of proper design and maintenance.
Figure 1: Examples of typical failure modes for nonengineered masonry dwellings [Blondet].
Construction type:
Construction cost
Built by
Building Regulations
Typical income
bracket of owner
Land tenure and
financial loans
Earthquake insurance
2. OBJECTIVES
What are the main technical, social and economical considerations for the dissemination of seismic
retrofitting techniques to remote rural communities? This paper aims to:
Highlight key successes and failures of previous programs for the dissemination of seismic
retrofitting techniques in rural Peru.
Propose a general model for projects to disseminate seismic adobe construction/retrofitting techniques
to rural communities and outline the larger-scale interventions required to support these programmes.
Figure 5: House design for reconstruction programme. Incorporates steel wire mesh at intersection of orthogonal
walls, RC ring-beam and timber roof [San Bartolome].
Members of PUCP conducted a five-day training course in construction of the reinforced adobe houses for
20 SENCICO technicians plus 42 selected rural persons from high-risk communities. The members of the
community then built their own houses under the supervision of the trained maestros. Each mason was
assigned two assistants and supervised the construction of up to three houses at any one time. COPASAGTZ technicians supervised the rural construction three days per week and each zone had one permanent
SENCICO technical supervisor. The programme was in collaboration with the local government.
360 houses of 36m2 plan area were constructed within 17 months with construction costs of
approximately $1700 per house (approximately $50/m2) (Error! Reference source not found.). GTZCOPASA provided 67% of the cost of the house with the beneficiaries providing 33% mainly through
the supply of local unskilled labour and local materials.
3.1.2. Phase 2: Protection from Natural Disasters with a Focus on Food Security
Phase 2 sought sustainability of the intervention by motivating the communities to strengthen their
homes. Several public workshops showed videos of phase 1 and instructional material was distributed
on anti-seismic adobe construction and the manufacture of adobe blocks. The public was then engaged
in the construction of public buildings such as school classrooms and small health centres. 30 trained
masons from phase 1 were employed to facilitate.
3.2. Pilot Project to Construct a New Town: Ruruca, Arequipa (2007 - 2008)
The pilot project of Ruruca was intended to enable the development of a government model for a
program of capacitation and mass dissemination of safe, low cost rural houses to vulnerable
communities. The new town of Ruruca consists of 17 adobe houses reinforced with a number of
different seismic resistant systems.
The local municipality conducted the planning for the new town, collaborating NGOs and technical
agencies provided training and materials for reinforcement and the new community constructed their
own houses, paying for the basic construction costs (i.e. not including the cost of reinforcement). 7
masons were employed with experience of reinforced adobe through the Arequipa programme (section
3.1). The 64m2 modules had final construction costs of $5270 ($83/m2).
3.3. Reconstruction programme following the 2007 Pisco Earthquake (2008)
Following a major earthquake in 2007 (Mw=8) near Pisco a team from PUCP and the NGO CAREPeru designed a program for reconstruction and mass dissemination of seismic construction techniques
in adobe utilizing a reinforcing technique that uses a polypropylene mesh (commonly used for fencing)
to provide confinement of walls [Rubios]. This project was carried out with the collaboration of
SENCICO and the Fund for the Reconstruction of the South (FORSUR), an autonomous fund created
by the Peruvian National Government to lead the post-earthquake reconstruction process.
Key stages of the project are shown in (Figure 6). The community capacitation programme
incorporated literature and videos and taught 883 in theoretical workshops and 276 in practical
exercises and live construction. The construction of each 4-roomed, 50m2 house cost $3,155 ($65/m2).
4. DISCUSSION AND CONCLUSIONS
4.1. Main Findings
All adobe houses built in these programmes were intact and performing well, with the exception of
some errors due to lack of full-time supervision (Figure 7a). Other NGO and cooperation agency-led
programmes in nearby areas followed on from these programmes using similar models. E.g. following
the Arequipa programme (section 3.1) 97 houses of the same design were built in the Arequipa region
of Yarabamba in a project managed by SENCICO and funded by the Italian Government and UNDP.
NGOs and cooperation agencies led and bore the brunt of the costs in the programmes presented. E.g.
in Ruruca (section 3.2) the modules had construction costs of $5270: 77% borne by the technical
agencies (COPASA-GTZ and COSUDE), 20% by the beneficiaries and 3% by the local government
[COSUDE]. Note that for the technical agencies involved, when considering overheads and
operational costs they collectively incurred a total cost of $7,841 per module. This represents an
additional 93% over the purely construction costs incurred by them, showing that operation costs are a
significant consideration for NGOs and technical agencies involved in rural construction projects.
Following the programmes no self-funded adobe dwellings have been retrofitted or built with
reinforcement. Several non-reinforced adobe structures built by communities after the programmes
also showed errors (Figure 7), showing that many lessons had been lost because of no further training
input after the initial programmes.
One reason that communities members named for not funding the reinforcing of their own homes was
that although the reinforced adobe dwellings were considerably cheaper than confined masonry they
were still more expensive than unreinforced adobe (Table 2). However, consider the case of the
Arequipa programme where the difference in price between reinforced and traditional adobe houses
was nearly $1000 but the cost of the reinforcement was only $112. The difference comes in additional
features such as a ground slab and foundations, concrete ring beam and more expensive roof
construction. Therefore, the basic mesh retrofit to an existing house would cost less than Table 2
would suggest, and fulfil the basic goal of preventing or prolonging collapse provided other structural
repairs are not needed. However, this basic cost may still be beyond the means of many families.
Another reason named for lack of take-up by the communities was the poor perception of adobe.
Many of the wealthier families were reconstructing their homes of masonry or confined masonry,
especially in Pisco and Chincha (section 3.3) where materials are readily availability in nearby urban
centres. However, many of these confined masonry houses had multiple stories and showed dangerous
defects such as exposed rebar and unsupported ring-beams (Figure 3).
Traditional adobe
Steel mesh reinforced adobe
Confined masonry
Total cost
$850
$1,774
$3,400
Cost/m2
$24
$50
$95
Relative cost
100%
217%
408%
Figure 8: Breakdown of construction costs for 36m2 reinforced adobe house in the Arequipa Reconstruction
Programme ($1774/house) [Haider].
National or Regional
Government
Grant or apply for funding
for mass-dissemination
programmes
Multilateral Financial
Institutions
Grant funding and advise on
programme
Funding Administrator
Administer the funding to the
enacting organizations and obtain
materials etc
Private Sector,
Government Technical Departments,
Universities
Transfer the necessary technical and procedural
knowledge
NGOs,
Cooperation Agencies
Implement the proposed programme
Masons,
Target Communities
Learn the retrofitting technology
and provide hand labor in
construction/retrofitting
Long-term support
Retrofitted Homes
Figure 9: Interrelation of organizations for programmes of mass-dissemination of seismic retrofitting techniques
[adapted from Rubios].
Regions must be identified whereby adobe is the predominant material and it is inappropriate to
promote other materials (due to local poverty and inaccessibility of the region).
Building codes for adobe construction in seismic regions must be developed in order for
governments to be able to support the construction of public buildings of adobe in remote areas.
Some countries do have empirical guidance on adobe reinforcing but not on detailed analysis of
adobe structures that would allow accurate, engineered designs.
Local governments must lead by example in areas of predominantly adobe construction by
constructing public buildings (e.g. municipality offices) of engineered adobe and engaging the
community in the construction of these buildings.
Government incentive programmes need to be established to financially assist communities to
reinforce existing adobe structures, reducing future vulnerability.
Given the high operational costs of NGOs and cooperation agencies acting in remote locations and
the dangers of unsupervised self-construction in adobe, local municipalities must be empowered to
support repeated construction and retrofitting programmes at regular intervals so that knowledge is
not lost with time.
7
The buildings most at-risk are built without engineering input, so programmes must target
communities directly. The cascade model (training technicians to teach a larger number who
then supervise self-construction) is an effective way of reaching large numbers of the community
whilst minimizing cost.
Remote communities cannot afford well-constructed houses using modern methods of
construction. However, these communities are not using reinforced adobe at their own cost due to
other basic needs and the poor perception of adobe. This shows that financial incentives are
required and that public adobe buildings are needed to raise confidence in adobe as a construction
material.
Lessons taught to communities are lost over time. Therefore, long-term interventions are essential.
Operational costs are a significant proportion of the total project costs for NGOs and technical
agencies, making long-term interventions difficult. Local municipalities have long-term presence
but lack capacity and funding. Therefore, capacitation of local municipalities is a necessary feature
for the sustainability of any community project.
ACKNOWLEDGEMENT
The research was funded by the Educational Trust of the Institution of Structural Engineers through
the Pai Pan Li travel grant 2009. Many thanks to the following for their invaluable assistance and
guidance throughout the field investigation in Peru: Arch. Patricia Cardenas of SENCICO, Arch.
Edward Chuquimia and Juan Carlos for their guidance in Arequipa; Urbano Tejada, Mr Salustiano
Garca, Alvaro Rubios and Stefano Bossio for their assistance around Pisco and Chincha; Erik
Trigoso and Jesika Rodriguez for their support in Trujillo; Prof Julio Rojas Bravo for his help in
Cusco and Nancy Trujillo and the staff of PUCP for hosting the investigation.
REFERENCES
Blondet, Marcial and Garcia, Gladys V. (2006), World Housing Report: Adobe Construction, World
Housing Encyclopedia (electronic report on the Internet).
COSUDE (2008), Sistematizacion del proyecto piloto de vivienda rural en rururca region Arequipa.
Haider J., Chuquimia E., Huerta J., (2005) Retos en la Adopcin de Tecnologa Sismo-Resistente
para Viviendas de Adobe en la Sierra Peruana, proc. SismoAdobe, Peru.
Rubios A. (2009) Propuesta de Reconstruccion Post-Terremoto de Viviendas de Adobe Reforzado,
Civil Engineer (Masters) Thesis, Catholic University of Peru.
Perez-Palma, P. (2004) Estudio socioeconomico de las familias participantes del Proyecto Cuencas
Andinas y Proyecto de Gestion de Riesgo de Desastres Naturales con Enfoque de Seguridad
Aimentaria de la Zona Castilla y Condesuyos Arequipa, COPASA-GTZ, Arequipa, Peru.
Quiun D. (2009) World Housing Report: Reinforced Adobe, Report Num 107, World Housing
Encyclopedia (electronic report on the Internet).
San Bartolome ., Quiun D., Zegarra L. (2008) Performance of Reinforced Adobe Houses in Pisco
Peru Earthquake, proc. 14WCEE, Beijing.