Documente Academic
Documente Profesional
Documente Cultură
J. Jaimes
J. Melendez, J. Colomer
jjmora@silver.udg.es, gilberto@uis.edu.co
Industrial University of Santander UIS
Bucaramanga - Colombia
jajaimes@isa.com.co
Electrical Interconnection ISA
Bucaramanga - Colombia
quimmel@eia.udg.es, colomer@eia.udg.es
Institut dInformAtica I Aplicacions
Universitat de Girona (Spain)
I.
INTRODUCTION
0-7803-7967-5/03/$17.00 02003 E E E
111. QUANTITATIVE
RELIABILITY EVALUATION
OF POWER
TRANSMISSION SUEBTATIONS
The complex switching arrangement differences power
system reliability evaluation from the substation reliability
evaluation. Consequently, it is necessary to develop models,
which consider breaker operation in electrical substations.
Previous works considers evaluation of reliability by using
decision trees [14].
In this paper we use the minimum cut set approach [ 151
[161. This treatment allows the substation evaluation, outlining
the fault mode identification and its best configuration.
Elements identified as critical require action strategies to reestablish normal conditions, in the even of fault. These
strategies are presented in IV. The first group treats nondestructive faults, while the second one considers power
transformer and breaker destructive faults (contingency
plans).
...
111.
iv.
V.
vi.
9
G8
-I+
Fig. 2. Minimal cut sets for the substation of Breake arid a half configuration
presented in Fig. 1.
B. Reliability data
To carry out a quantitative reliaklility evaluation,
interruption data is needed. The fault rate ( I ) and the
restoration rate (r) are commonly used fcr calculating the
unavailability index (U), the Energy Non Supplied (ENS)
index or other reliability indexes. [15][ 161.
r, =-2
.14[hours]
(3)
C;11
$Ab(., + rb)
=
8 760
faults
for
[F]
U,, = r,,/z,,
Ai?;<<1
(4)
]:!I
average supplied load (L), and the total unavailability time per
year (U), as presented in (7)
E = LAwmge UTOtlll
(7)
D. Critical Equipment
In table 1, the critical equipment determined by the
previous methodology is presented for the substation called
San Mateo, of the CTE Oriente.
Substation
Load Circuit
.._^
San Mateo
Toledo
Critical Equipment
IATR, BI. L170. L171. L190. L191. A220.
A221, L230, L231, L250, L2.51, L270, L270
B1, L171, L171, L190, L191, A220, A221,
L230, L231, L250, L251, L270, L271
B1, L172, L171, L190, L191, A220, A221,
IV. RESTORATION
STRATEGIES
The restoration strategies have been developed for the
critical equipment selected in III: These strategies are
classified in two types: a) Under-fault procedures, as plans to
restore the electrical service in case of non destructive faults
of switching, control and protective substation systems, and b)
Contingency Plans as procedural guides to substitute failed
power transformers and breakers [20].
A. Methodology
The strategy used for the transmission substation
restoration contains five basic phases, as it is presented in fig.
4. It intends a systematic analysis of the problem nature,
including summary and analysis of information, elaboration of
restoration procedures, simulation, experimentation and/or
discussion and finally, the training on restoration procedures
determined as research results.
Not
The average load (L) and the unavailability index (U) are
used to calculate the Energy Non Supplied ENS. The ENS
might be used to estimate economical and financial costs of
out in the event of a power substation non-destructive fault. identification, verification of the adequate backup equipment
The fault is evidenced by the activation of an alarm, a breaker operation and finally, description of possible causes and
trip or an erroneous operation of the switching and control proposed solutions for this contingency.
equipment (Fail to closelopen breakerslsectionalizers), andor
Finally, the fault procedures for control and protection
protective system. Under-fault procedures contain a equipment are designed to offer a methodology, which helps
relationship of fault situations, possible causes and solutions the equipment condition determination. These procedures help
in table format, and a simplified basic control circuit [20].
the operator to identify erroneous equipment and report it.
Under-fault procedures were developed with a general Generally, is not recommended i i corrective action due the
structure, which include such aspects as: Object, scope, complexity of the faulted equipment as numeric protective
relays, programmable logical controllers and other digital
resources, activities priority and executers qualification.
Four types of clearly differentiated under fault procedures control devices.
were defined. Those to attend contingencies arising in
operative activities, those associated to alarms, those of
ancillary services and those for control and protective
equipment. Addressing by the under-fault procedures, the
substation operators play an active role under emergency
conditions
The first fault procedures are designed to assist nondestructive faults evidenced by non equipment response to
openinglclosing orders, during the execution of an operative
switching procedure. These fault procedures are organized as
presented in figure 5 .
The second, under fault procedures associated to alarm
signals are designed to attend contingency events that have
audio or visual indication in the substation control room.
These procedures are ordered to allow recognizing causes and
solutions to problem solve. These main procedure parts are:
alarm identification, alarm verification, and revision of alarm
circuit drawings.
C. ContingencyPlansfor destructivefaults
..............
..............
......
Y*
*CENS
Fig. 9. San Mateo Substation
Considered effect
2.700E-02
282.94
7.103505
1.000E-01
10.09
1.00
7.640ENO
7.166504
1.000E-01
3,000E-03
1.00
3.000E-03
1.301E-01
59.53
7.7443+00
Active faults
Active faults overlapped with stalled
breakers
Total results
v . &PLICATION
OF RESTORATION STRATEGIES
Table 2. Results of the quantitative reliability evaluation for the line to ATR
of San Mateo substation, before applying the restoration strategies
Considered effect
[E]r
[hours]
[*--I
wm
2.7OOE-02
7.103E-05
133.18
8.77
3.596ENO
6.231E-04
Active faults
1.000501
1.00
1.000E01
3.OOOE-03
1.00
3.000E-03
Total results
1.301E-01
28.44
3.700E+00
Table 3. Final results of the quantitative reliability evaluation for the line to
ATR of San Mateo substation, after applying the restoration strategies
h e # 124
Gwl:
Restore the power transformer (ATR) fiom San Mako Substation
a
:
Not available transformer on San Mate0 Sulxtation.
k!&dOIC
...
Fig 10: Cases and CBR cycle: Retrieve, Reuse, Retain and Revise.
REFERFNCES
Resolution CREGO61-2000.
Energy and Gas Regulatory
Commission. Colombian Energy Ministry, 2000.
Lambert-Torres, G.; Ribeiro, G.M.; Costa, C.I.A.; Alves-da-Silva, A.P.;
Quintana, V.H. Knowledge engineering tool for training for substation
operators Transmission and Distribution Conference, 1996.
Proceedings. 1996 IEEE on Pages: 72 - 77.
Young-Moon Park; Kwang-Ho Lee. Application of expert system to
power system restoration in sub-control Center IEEE Transactions on
Power Systems, Pages: 629 - 635. May 1997 Vol. 12 Issue: 2
Hong-Tzer Yang; Wen-Yeau Chang; Ching-Lien Huang On-line fault
diagnosis of power substation using connectionist expert system IEEE
Transactions on Power Systems, Pages: 323 - 331 Feb. 1995 Vol. 10.
Issue: 1.
Mahdy, Y.B.; Stanek, E.K.; Abdel-Salam, M.; Zaki, M. An expert
system for specifying the major substation components: machine
learning approach Industry Applications Society Annual Meeting,
1991., Conference Record of the 1991 IEEE on Pages: 1216 - 1222
v01.2.
Spina, J.; Meyer, W.; Scherer, J.; Wood, R.M. Commercial
applications of knowledge based systems: initiatives in the electric
power industry Computer Software and Applications Conference, 1990.
COMPSAC 90. Proceedings, Fourteenth Annual International on Pages:
420 - 423.
C.M. Huang, H.L. Jiang, W.Y. Cbang, C.L. Huang, A Petri Nets
Model for Fast Substation Service Restoration E E E Catalogue N
98EX137. 1998. Paw.. 473 - 478.
Lo, K L , Ng, H S , Grant, D M , Trecat, J , Extended Petri net models
for fault diagnosis for substation automation Generation, Transmission
and Dismbution, IEE Proceedings, Volume 146 Issue 3, May 1999
Page(s) 229 -234
Agganval, R , Yonghua Song Artificial neural networks in power
systems I11 Examples of applications in power systems Power
Engineering Journal on Pages 279 - 287 Dec 1998 Vol 12 Issue 6
[lo] Nagabhushana, B S , Chandrasekharaiah, H S Analysis of SSR using
artificial neural networks [power system simulation] Intelligent
X. BIOGRAPHIES
Juan Jose Mora-Fl6rez. Received his BSC in Electrical
Engineer from lndustnal University of Santander (US),
Interest Areas
Quality