Article information:
Access to this document was granted through an Emerald subscription provided by emerald-srm:462515 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald for
Authors service information about how to choose which publication to write for and submission guidelines
are available for all. Please visit www.emeraldinsight.com/authors for more information.
The current issue and full text archive of this journal is available at
www.emeraldinsight.com/0969-9988.htm
ECAM
21,3
276
Alexander Soo
School of Civil Engineering, The University of Sydney, Sydney, Australia, and
Bee Lan Oo
Downloaded by Northumbria University At 23:47 14 November 2016 (PT)
1. Introduction
Demand is part of the large domain of market conditions that affect many decisions
revolving around construction contract auctions (Runeson and Skitmore, 1999).
These decisions force contractors to make judgements in an attempt to balance out the
market opportunities and risks (Thorpe and McCaffer, 1991), and thus, affecting their
bidding behaviour in order to achieve their firms objectives (Skitmore, 1989). Skitmore
(1989) classified construction firms objectives under three main categories: monetary,
non-monetary and market related, where construction demand by nature affects all
three categories.
Construction
demand on
contract auctions
277
ECAM
21,3
278
Runeson and Skitmore (1999) explained changes in demand being related to productivity
and cost. One example they utilised was that, in order to expand the firms capacity,
new factors of production would need to be employed, because of the lower skill level
and lower productivity of the new factors, the costs would increase (i.e. productivity growth
or contraction has an effect on demand and prices). Skitmore (1987) also noted that
construction demand was affected by seasonal changes, where certain seasons would
exhibit higher price levels and vice versa. Akintoye and Skitmore (1994) suggest that the
general factors affecting construction demand could be classified under the PESTL
(political, economic, social, technological and legal) framework. Focusing on the UK
construction industry, they grouped the general factors of demand into economic
conditions, construction price, real interest rate, unemployment level and profitability. Their
results show that private sector construction demand was responsive to changes in the real
interest rate and profitability, but not the changes in construction price levels, whilst the
demand was negatively correlated with unemployment. Hillebrandt (2000), on the other
hand, identified ten general leading indicators of construction demand as follows:
(1)
population;
(2)
interest rate;
(3)
economic crises;
(4)
(5)
(6)
(7)
government policy;
(8)
expectation of demand;
(9)
(10)
Construction
demand on
contract auctions
279
ECAM
21,3
280
management such as need for work, number of competitors and current workload.
Ahmad and Minkarah (1988) also performed a survey questionnaire on the top 400
contractors in the US with a response rate of 90 contractors. They found that the top
five factors affecting the d2b decision were type of job, need for work, client, historic
profit and degree of hazard. For the mark-up decision, the top five factors were degree
of hazard, degree of difficulty, type of job, uncertainty in estimate and historic profit.
Similar to the study by Shash (1993), need for work appears to be an important factor
considered. In another study on Canadian construction contractors, Fayek et al. (1999)
found that the d2b decision was also influenced by the need for work, and that the
mark-up size was affected by the need for work and the number of competitors for the
project. Dulaimi and Shan (2002) also performed a survey on medium and large sized
contractors in Singapore and found that, regardless of firm size, both groups of
contractors considered the economic situation greatly. In terms of the factors affecting
mark-up size, there is again a common consideration for the need for work and current
workload. As the former studies were performed in different countries and different
time periods, Ling (2005) performed a meta-analysis of the data sets (of five international
surveys) to isolate the global factors that affected the margin (mark-up) size. She found
that, irrespective of the geographical location of the project, the current workload
and need for work are key factors affecting margin size. Hence, with market conditions
and demand being found as important factors affecting contractors bidding decisions, it
can be conjectured that these factors are significant and hence deeper understanding of
their effects can lead to insight into bidders behaviour how bidders consider and adapt
their strategy to differing market conditions of varying levels of demand.
2.4 The effect of construction demand
Empirical studies performed to date have shown quite conclusively the effect of
construction demand in construction contract auctions. De Neufville et al. (1977)
analysed 691 highway projects and found that the mark-up ration was different
between good years and bad years (with good years have more projects available for
bid and bad years have less projects available). In good years, it was found that bidders
applied higher mark-ups to projects and in bad years bidders applied lower mark-ups
in their bidding attempts. In line with mark-up changes due to changes in demand,
Andrews and Brunner (1975) also found that contractors changed their bidding
strategy in response to varying levels of construction demand. In a study by Oo (2007),
senior managers of Hong Kong and Singapore construction firms were invited to
participate in a bidding experiment that observed their bidding behaviour in
booming and recession market conditions. She found that the probability of a bid
decision was lower in a booming scenario, whilst higher probability was recorded in
times of a recession. This finding is in line with the study by Bevacqua and Elias (1992)
whom found that there were more bid attempts in weak years as opposed to strong
years representing the need for work.
In terms of the effect of general market conditions (also incorporating some aspect
of demand), Runeson (1988) found that prices changed systematically by a range in
excess of 20 per cent over the economic cycle, and that such changes were attributed to
market conditions such as demand and capacity utilisation. Runeson (1990) attempted
to incorporate the effects of changes in market conditions into a bidding model and was
successful in developing a method to assess the probability of a winning bid and the
probability density function of the profit. A study by Flanagan and Norman (1985)
identified a bid price rule for sequential bids. Their model demonstrated that bid prices
Construction
demand on
contract auctions
281
282
Figure 1.
Experimental treatment
scenarios
Number of Projects
ECAM
21,3
10
9
8
7
6
5
4
3
2
1
0
0
10
Round Number
Booming
Recession
Each subgroup was provided with a start-up capital of $400,000 and were required
to bid for general building projects ranging from approximately $5 to $12 million
(where monetary figures represent the unbiased construction cost estimate). The general
building projects consisted of schools and public buildings. These hypothetical projects
were created using the information from past real contracts obtained from the NSW
e-tendering web site (https://tenders.nsw.gov.au). Overheads were required to be paid for
in each bidding round. Each subgroup also has a capacity limit of five projects on hand at
any time point, the cost to exceed this capacity limit attracts a cost penalty representing
outsourcing costs.
The experiment was conducted for ten rounds (one round per week) with each
bidding round simulating a time period of six months. Within a timeframe of one hour,
the participants were required to decide which projects to bid for and the bid price,
if deciding to bid at all. The bid price submitted was expected to cover the construction
cost in addition to a mark-up adjustment for profit, overheads, risk and competitive
factors. The general instruction to the participants was that their ultimate aim was to
survive and prosper in which the lowest bidder wins the job, but how this was
achieved was left to them. Feedback information was provided at the beginning of
every bidding round that consists: details of the winning bid and identity of winning
bidder (from round 2 onwards); profit/loss statements and capacity utilisation
information (from round 2 onwards); and a statement of the market outlook of
construction demand. The market outlook statement detailed the expected trend of the
number of projects in the subsequent round(s) (i.e. whether the number of projects
available were expected to increase, decrease or remain constant) and the period of the
outlook was dependent on the demand scenario and trend (refer to Figure 1).
Experiment participants were notified that the subgroup with the highest account
balance by the end of the ten bidding rounds would win a cash prize. The cash prizes
were awarded to the respective subgroups with the highest account balance in the
booming and recession scenarios. This incentive scheme was implemented in order to
promote serious participation in the experiment and to prevent dropouts.
4. Results and discussion
The results and discussion are presented in three parts. The first part presents an
exploratory analysis of bids obtained from the bidders in both the booming and
recession scenarios. The second part details statistical analysis of cross-comparison,
at several time points, between the booming and recession groups. This is then
followed by an assessment of the seriousness of bidders bidding attempts.
4.1 Exploratory analysis
Table I shows the sample size for both the booming and recession groups. For the
booming group (i.e. bidders A1-A5), a total of 290 bids were obtained with ten no-bid
decisions. For the recession group (i.e. bidders B1-B5), a total of 271 bids were
submitted with 29 no-bid decisions. A Kolmogorov-Smirnov test on the two data
samples is not normally distributed ( p-valueo0.05), and thus non-parametric
statistical tests were used for subsequent analyses. At first glance of the frequency of
no-bid decisions, one might be tempted to suggest that the results are not in
agreement with the studies by Oo (2007) and Bevacqua and Elias (1992), where higher
no-bid decisions are expected with an increase in number of projects. Here, the
disparity is due to different research design, whilst the two previous studies focused on
two extreme market conditions booming/strong and recession/weak years, the levels
of demand in this experiment were varied over ten rounds. Taking the recession group
as an example, the true recession period is from rounds 1-5 as this represents a
decrease in the number of projects available. Rounds 6-10, on the other hand, represent
a recovery period, where the number of projects increases again. Looking at the
no-bid decisions for the recession group, the majority (23 out of 29) of the no-bid
decisions were recorded in the recovery period, suggesting the results are in general
agreement with the two studies aforementioned. Other possible factors affecting this
observation are the bidders current workload (or jobs on hand) and accumulated
profit/loss as the experiment proceeded.
For the exploratory analysis, scatter plots were created to show the spread of data
for both the booming (Figure 2) and recession (Figure 3) groups. The y-axis scale is the
mark-up ratio and is defined as the contractors bid divided by the unbiased cost
estimate. A mark-up ratio of one indicates that the bidder had placed a bid at the cost
estimate level. A mark-up ratio 41 indicates that the bidder had placed a mark-up on
top of the cost estimate and vice versa, a mark-up ratio o1 indicates that the bidder
had decided to bid below the cost estimate. The trend line attached to the data points
is a LOWESS curve and stands for locally weighted scatter plot smoothing.
The LOWESS fit line is based on local polynomial least squares fit to a set of data
points. The fit is then robustified which is defined as resmoothing of the curve for
several iterations to provide a more accurate trend representation of the data set
(Hardle, 1990). The robustified LOWESS curve is more resistant to effects of noise
and/or marginal outliers in any particular data set.
For the booming group, it can be seen that there are a few kinks in the LOWESS
curve from rounds 3-5. This may be seen as rapid adjustments to bidding strategy
after the initial two rounds, possibly due to the time taken to learn about the bidding
environment. It should be noted that feedback information regarding profit and loss
was provided at the beginning of round 3 (due to a minimum time frame of two rounds
Bid
No-bid
Construction
demand on
contract auctions
283
Total
Scenario
Booming
Recession
290
271
96.7
90.3
10
29
3.3
9.7
300
300
100.0
100.0
Table I.
Sample size for booming
and recession groups
ECAM
21,3
Markup ratio
284
Figure 2.
Booming group
scatter plot
1.4000
1.3800
1.3600
1.3400
1.3200
1.3000
1.2800
1.2600
1.2400
1.2200
1.2000
1.1800
1.1600
1.1400
1.1200
1.1000
1.0800
1.0600
1.0400
1.0200
1.0000
0.9800
0.9600
0.9400
0.9200
0.9000
0.8800
0.8600
0.8400
0.8200
0.8000
Bidder
ID
A1
A2
A3
A4
A5
4
5
6
Round Number
10
to complete a hypothetical project), thus this may have been a wake-up call for those
bidders with aggressive bidding strategies in initial bidding rounds. The mark-up ratio
trend from round 5 onwards is stabilised and represents consistent bidding behaviour
(constant level of mark-up). A possible conjecture for this behaviour stems from
bidders need for work, having gained sufficient amount of work on hand, even though
the number of projects is decreasing (round 6 and onwards) there is little need to alter
the bidding strategy until more capacity is available.
For the recession group, it can be seen that there is a continually decreasing
mark-up ratio trend from the LOWESS curve. The gradient of the curve is steepest
from rounds 1-4, reflecting the rate of decrease in number of projects (see Figure 1).
This result is in line with theoretical expectations, with a decreasing number of
projects available, and a constant number of competitors, the competition becomes
more intense, thus forcing lower mark-ups in order to win job(s). Round 5 (the trough)
appears to be the turnover point where the decreasing slope turns to a lower gradient.
One possible explanation for the trend observed from round 6 and onwards can again
be related to bidders need for work. During the recovery period (round 6 onwards)
some bidders were still in need for work and continued to apply lower mark-ups in
order to win job(s).
Markup ratio
1.4000
1.3800
1.3600
1.3400
1.3200
1.3000
1.2800
1.2600
1.2400
1.2200
1.2000
1.1800
1.1600
1.1400
1.1200
1.1000
1.0800
1.0600
1.0400
1.0200
1.0000
0.9800
0.9600
0.9400
0.9200
0.9000
0.8800
0.8600
0.8400
0.8200
0.8000
Bidder
ID
B1
B2
B3
B4
Construction
demand on
contract auctions
285
B5
4
5
6
Round Number
10
A key observation from both LOWESS curves is that for the booming group, the mark-up
ratio trend is consistently above 1.0, however, for the recession group, the mark-up ratio
drops below 1.0. This suggests higher overall mark-ups were being applied for the
booming group, and lower mark-ups (or mark-downs) were recorded for the recession
group. These results are in line with the findings from De Neufville et al. (1977) where they
found that in good years bidders applied higher mark-ups and in bad years, bidders
applied lower mark-ups.
4.2 Cross comparison between groups
At the broadest level, a Mann-Whitney U-test was performed in order to test the
difference in distributions of the mark-up ratio for the booming and recession groups
(i.e. the effect of two different experimental treatments). The test results reveals that
the mean mark-up ratio for the booming group is higher than the mean mark-up
ratios being applied for the recession scenario (mean rank: 305.18 (booming); 255.12
(recession), U 32,282, Z 3.657, p 0.000). This means that the two different
experimental treatments resulted in statistically different mark-up ratio distributions,
providing evidence that the bidders do consider the level of construction demand in
their bidding decisions. Although a higher overall mark-up ratio (i.e. higher mean rank)
Figure 3.
Recession group
scatter plot
ECAM
21,3
286
was recorded for the booming group as expected, a possible explanation for the difference
in mean mark-up ratio can be traced back to the difference in the scenarios. In the
booming scenario, the number of projects were increasing for the first five rounds, thus as
the number of projects increase, the level of competition decreases and the bidders
were able to apply higher mark-ups and still win job(s). As the bidders gained enough
harvest from the first five rounds, they did not need to significantly alter their bidding
strategy to become more competitive in the remaining rounds of the bidding experiment
(see Figure 2). However, for the recession scenario, the number of projects were decreasing
for the first five rounds, thus the level of competition was increasing with each passing
round, whereby contractors would have bid aggressively (lower mark-up) in order to win
job(s) and offset the operational costs of the firm (at the very least). As some bidders were
likely still in need of work, the low mark-up trend continued, albeit slowing down as the
construction demand was recovering (see Figure 3).
At the second level, Table II shows the results of an in-depth analysis on specific
bidding rounds and subseries of bids using Mann-Whitney U-tests. First, a test was
performed on the first bids of the two groups. The results show that there is no
significant difference in the mean mark-up between the booming and recession groups
( p 0.641). This is expected as all the bidders were assumed to start off at an
inexperienced state. As Fu et al. (2004) suggests, inexperienced contractors would not
be very competitive in their initial bidding attempts, however, their interpretation of
the bidding environment would be improved over time through learning. Hence,
an alternative interpretation of the insignificant difference is that the difference in
the experimental treatments (booming and recession scenarios) has no impact on the
bidding participants in the first bidding round. Next, from the exploratory analysis,
it has been identified that there are a few key time points of interest for cross
comparison. These include: first, round 3 that represents the point where the bidders
had gained experience in the bidding experiment; second, round 5 peak and trough of
the booming and recession scenarios that appears to be the turning point a change
in the LOWESS curve slopes (mark-up stabilisation for the booming group and a
change in aggressiveness in mark-up for the recession group); and third, round 9 the
stagnant demand expectation for both groups. Comparing the mark-up ratios for the
third bidding round from both groups yielded a significant p-value of 0.007. This
suggests that, at round 3, the bidders in the respective groups had begun to behave
differently in terms of mark-up decision and were affected by the varying levels of
construction demand. To further examine the effect of experimental treatments from
round 3 onwards, two subseries of bids (i.e. rounds 4-5 and 5-6) were considered by
using round 5 as the turning point. The test results show that there are significant
differences between the two groups. In rounds 4-5, just before the turning point, there
was a significant difference in the mean mark-up ratio between the booming and
recession groups ( p 0.041). After the turning point (rounds 5-6) there was also a
Bidding round(s)
Table II.
Bidding round(s)
cross-comparison
1
3
4-5
5-6
9-10
67
70
115
102
87
489.0
381.0
953.5
441.0
329
0.467
2.720
2.048
4.057
4.709
0.641
0.007
0.041
0.000
0.000
significant difference between the two treatment groups mark-up ratios ( p 0.000).
Rounds 9-10 represented a stagnant demand whereby the number of projects released
did not change. The results show that there was a significant difference between the
booming and recession groups ( p 0.000). Although the number of projects did not
change, the level of construction demand was clearly different at that point in time (eight
projects released for the recession group and three projects released for the booming
group), thus this explains the difference in the mark-up ratio. Again, this provides strong
evidence that the different experimental treatments were having an impact on the bidders
behaviour (through changes in mark-up decisions). It can be conjectured that from round
3 onwards, bidders needed to have considered the changing construction demand in
order to survive and prosper in the bidding environment. Those who did not adapt well to
the changing market conditions would have been compelled to alter their bidding
strategy in an attempt to improve their performance.
4.3 Seriousness of bidding
With the bidding forms (where bidders write down their bids), a blank field was
required to be filled in representing the percentage chance of winning each submitted
bid. In construction contract auctions setting where the lowest bidder wins, thus an
understanding of the bidding experiment would yield a logical result whereby higher
bids lead to lower chances of winning and vice versa, lower bids lead to higher chances
of winning. Hence, the Spearmans correlation test was used to test the participants
seriousness in bidding and as a sanity check for the results. The test was performed on
the entire population sample (both booming and recession groups included) with
the percentage chance of winning and mark-up ratio being the factors analysed.
The results show a strong negative correlation between the percentage chance of
winning and the mark-up ratio (rs 0.432, p 0.000). The negative correlation is as
expected, providing evidence that the bidders understood the mechanics of the
bidding experiment. This also suggests that they were serious in their bidding
attempts and were behaving logically.
5. Conclusion
This study examined the effect of construction demand on contract auctions utilising
an experimental research method. Two groups of inexperienced bidders were subjected
to two different demand scenarios, a booming demand and a recessionary demand.
The results show that the variations in the bid price level are affected by varying levels
of construction demand, in terms of the number of projects available for bidding.
From the exploratory analysis, it was found that there were more bid decisions when
the number of projects was decreasing, and that there were less bid decisions
when the number of projects was increasing. It was also found that the general
mark-up level for the bidders experiencing a booming scenario was higher on average
compared to bidders subjected to the recession scenario. Cross-comparisons between
the two groups revealed that the experimental treatments have an impact on the
bidders mark-up decisions. An in-depth analysis of subseries of bids over bidding
rounds shows that the inexperienced bidders in the experiment had taken two rounds
to learn about the bidding environment before their behaviour adapted to the varying
levels of construction demand.
The findings provide empirical support for construction demand effects on
bidders and how varying levels of demand may impact bidders behaviour.
In addition, this study has reinforced the notion that bidders do adapt to their changing
Construction
demand on
contract auctions
287
ECAM
21,3
288
external environment, and that the bid price level for contracts are affected by the
current market conditions. An identified limitation of this study is the use of
student subjects in the experiment, thus the experiment results are limited in
generalisation to inexperienced bidders. However, it was found that in this study,
the bidders were rational and serious in their bidding attempts. For further studies,
this experiment may be replicated with different considerations for the booming and
recession scenarios. For example, a continually decrease in number of projects
over time a prolonged recession. Also, it is likely to yield more insights on
inexperienced bidders learning process in recurrent bidding by running the
experiment for a longer duration. In addition, the experiment can be replicated using
experienced contractors in order to compare the results of inexperienced bidders to
experienced. For construction clients, this study has demonstrated a need to consider
the levels of construction demand in the industry in order to best design their
procurement strategies, especially when deciding on the timing to call tenders and
on an acceptable price for contracts. For construction contractors, enhanced
understanding of the interaction between construction demand and price, may
assist in formulation of a more effective bid, which has additional optimisation for the
current market conditions.
References
Ahmad, I. and Minkarah, I. (1988), Questionnaire survey on bidding in construction, Journal of
Management in Engineering, Vol. 4 No. 3, pp. 229-243.
Akintoye, A. and Skitmore, M. (1994), Models of UK private sector quarterly construction
demand, Construction Management and Economics, Vol. 12 No. 1, pp. 3-13.
Andrews, P.W.S. and Brunner, E. (1975), Studies in Pricing, Oxford University Press, Oxford.
Australian Industry Group (2011), Construction Outlook May 2011, The Australian Industry
Group.
Avery, D.A. (1982), Problems in locality in construction cost forecasting and control,
in Brandon, P.S. (Ed.), Building Cost Techniques: New Directions, E & FN Spon, London,
pp. 159-166.
Beeston, D.T. (1983), Statistical Methods for Building Price Data, E & FN Spon, London.
Bevacqua, A.J. and Elias, M.G. (1992), Profit Proceedings of the 36th Annual Transactions
of the American Association of Cost Engineers, AACE, Orlando, FL, 28 June-1 July
pp. L.3.1-L.3.8.
Chan, S.M., Runeson, G. and Skitmore, M. (1996), Changes in profit as market conditions change:
an historical study of a building firm, Construction Management and Economics, Vol. 14
No. 3, pp. 253-264
Davis Langdon (2010a), Leading Indicators, Residential, Davis Langdon, Adelaide, July.
Davis Langdon (2010b), Leading Indicators, Commercial, Davis Langdon, Adelaide, February.
De Neufville, R., Lesage, Y. and Hani, E.N. (1977), Bidding models: effects of bidders risk
aversion, Journal of the Construction Division, Vol. 103 No. C01, pp. 57-70.
Dulaimi, M.F. and Shan, H.G. (2002), The factors influencing bid mark-up decisions of large- and
medium-size contractors in Singapore, Construction Management and Economics, Vol. 20
No. 7, pp. 601-610.
Fayek, A., Ghoshal, I. and Abourizk, S. (1999), A survey of the bidding practices of Canadian
civil engineering construction contractors, Canadian Journal of Civil Engineering, Vol. 26
No. 1, pp. 13-25.
Fellows, R.F. and Langford, D.A. (1980), Decision theory and tendering, Building Technology
and Management, Vol. 18 No. 9, pp. 36-37.
Fine, B. (1974), Tendering Strategy, Building, 25 October, pp. 115-121.
Flanagan, R. and Norman, G. (1985), Sealed bid auctions: an application to the building
industry, Construction Management and Economics, Vol. 3 No. 2, pp. 145-161.
Fu, W.K., Drew, D.S. and Lo, H.P. (2004), Start-up and steady-state learning in recurrent
bidding, Building Research & Information, Vol. 32 No. 6, pp. 484-496.
Goh, B.H. (1996), Residential construction demand forecasting using economic indicators: a
comparative study of artificial neural networks and multiple regression, Construction
Management and Economics, Vol. 14 No. 1, pp. 25-34.
Hardle, W. (1990), Applied Nonparametric Regression, Oxford University Press, Cambridge.
Hillebrandt, P.M. (1985), Economic Theory and the Construction Industry, 2nd ed., Macmillan,
London.
Hillebrandt, P.M. (2000), Economic Theory and the Construction Industry, 3rd ed., Macmillan,
Basingstoke.
Killingsworth, R.A. Jr (1990), A preliminary investigation into formulating a demand
forecasting model of industrial construction, Cost Engineering, Vol. 32 No. 8, pp. 11-15.
Ling, F.Y.Y. (2005), Global factors affecting margin-size of construction projects, Journal of
Construction Research, Vol. 6 No. 1, pp. 91-106.
Lowe, D. and Skitmore, M (2006), Bidding, in Lowe, D. and Leiringer, R. (Eds), Commercial
Management of Projects: Defining the Discipline, Blackwell Publishing, Oxford,
pp. 356-389.
Ngai, S.C., Drew, D.S., Lo, H.P. and Skitmore, M. (2002), A theoretical framework for determining
the minimum number of bidders in construction bidding competitions, Construction
Management and Economics, Vol. 20 No. 6, pp. 473-482.
Oo, B.L (2007), Modelling individual contractors bidding decisions in different competitive
environments, PhD thesis, Hong Kong Polytechnic University, Hong Kong.
Rawlinsons (2011), Construction Cost Guide 2011, Rawlinsons, Perth.
Runeson, G. (1990), Incorporation of market conditions into tendering models, Proceedings of
the CIB 90, W55/65 Symposium, Vol.6, UTS, Sydney, March.
Runeson, G. and Benett, J. (1983), Tendering and the price level on the New Zealand building
industry, Construction Papers, Vol. 2 No. 2, pp. 29-35.
Runeson, G. and Skitmore, M. (1999), Tendering theory revisited, Construction Management
and Economics, Vol. 17 No. 3, pp. 285-296.
Runeson, K.G. (1988), Methodology and method for price-level forecasting in the building
industry, Construction Management and Economics, Vol. 6 No. 1, pp. 49-55.
Shash, A.A. (1993), Factors considered in tendering decisions by top UK contractors,
Construction Management and Economics, Vol. 11 No. 2, pp. 111-118.
Shealy, H.F. (1986), Right of way clearing for a modern rapid transit railway, Cost Engineering,
Vol. 28 No. 4, pp. 12-18.
Skitmore, M. (1989), Contract Bidding in Construction: Strategic Management and Modelling,
Longman Scientific and Technical, Harlow.
Skitmore, M., Runeson, G. and Chang, X. (2006), Construction price formation: full-cost pricing
or neoclassical microeconomic theory?, Construction Management and Economics, Vol. 24
No. 7, pp. 773-783.
Skitmore, R.M. (1987), Construction Prices: the Market Effect, Research report for the Royal
Institution of Chartered Surveyors, University of Salford, Salford.
Construction
demand on
contract auctions
289
ECAM
21,3
290
Stone, P.A. (1983), Building Economy: Design, Production and Organisation A Synoptic View,
3rd ed., Pergamon Press, Oxford and New York, NY.
Taylor, J.B. and Frost, L. (2009), Microeconomics, 4th ed., John Wiley and Sons, Milton.
Thorpe, T. and Mccaffer, R. (1991), Competitive Bidding and Tendering Policies,
Butterworth-Heinemann, Oxford.
Zikmund, W.G. (2003), Business Research Methods, 7th ed., South-Western, Mason, OH.
Corresponding author