Sunteți pe pagina 1din 18

Installation Manual: TL-2 Plastic Water Filled Barrier

TL-2 Plastic Water


Filled Barrier

Installation Manual

ANOTHER AMORFLEX DEVELOPMENT

Installation Manual: TL-2 Plastic Water Filled Barrier


Table of contents
Introduction

System overview

Before installation

Limitations and warnings

Safety statements

Installation preparation

Parts identification

Bill of materials

Installation instructions

Installation examples

10

Installation checklist

11

Maintenance and repair

12

APPENDIX Technical Drawings


Plan and elevation

13

Isometric end #1

14

Isometric end #2

15

Twin pin connector

16

Approval letter

17

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 2

Installation Manual: TL-2 Plastic Water Filled Barrier

Introduction
TL-2 Plastic Water Filled Barrier made up of plastic units that when joined together using a
steel connector and filled with water provide positive work zone barrier protection to
temporary construction sites and other miscellaneous roadside activities. TL-2 Plastic Water
Filled Barrier has been designed and tested to meet the evaluation criteria of NCHRP 350
Test Level 2 (TL-2) for a longitudinal barrier.
When correctly installed it is capable of stopping, containing or redirecting an errant vehicle
in a safe manner under NCHRP 350 impact conditions.
TL-2 Plastic Water Filled Barrier is the worlds first 100% polyethylene water filled barrier (no
steel reinforcement) to have been judged to have satisfied the evaluation criteria of NCHRP
350 Test Level 2 (TL-2). The unique TL-2 Plastic Water Filled Barrier polyethylene
composition, profile design and twin pin connector allow the barrier to be installed straight or
down to a minimum radius of 28m if required.

System overview
TL-2 Plastic Water Filled Barrier is designed and constructed to provide acceptable structural
adequacy, minimal occupant risk and safe trajectory as set forth in NCHRP 350 for
longitudinal barriers.
When impacted with an 820kg or 2000kg vehicle at speeds of up to 70kph and angles up to
25 degrees, the impacting vehicle is stopped, redirected or contained in a safe manner.

Before installation
Placement of TL-2 Plastic Water Filled Barrier shall be in accordance with the design as
provided for the temporary work zone. Installation shall be in accordance with the installation
instructions supplied for this product.
Depending on the circumstances at the site, installation including the filling of a unit (using a
truck mounted water tanker) should take no more than 1 minute for each 2.0m unit.
TL-2 Plastic Water Filled Barrier is a highly engineered safety device made up of a relatively
small number of parts. Before starting installation ensure that one is familiar with the make
up of the system.

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 3

Installation Manual: TL-2 Plastic Water Filled Barrier


Limitations and warnings
TL-2 Plastic Water Filled Barrier has been rigorously tested and evaluated per the evaluation
criteria in the NCHRP 350 guidelines for a longitudinal barrier. The impact conditions
recommended in NCHRP 350 are intended to address typical in-service collisions.
When properly installed and maintained TL-2 Plastic Water Filled Barrier allow an impacting
vehicle to be stopped, contained or redirected in a safe and predictable manner under the
NCHRP 350 impact conditions.
Vehicle impacts that vary from the NCHRP 350 impact conditions described for longitudinal
barriers may result in significantly different results than those experienced in testing. Vehicle
impact characteristics different than, or in excess of, those encountered in NCHRP 350
testing (weight, speed and angle) may result in system performance that may not meet the
NCHRP 350 evaluation criteria.
The TL-2 Plastic Water Filled Barrier can be installed with the ArmorZone End Treatment. If
this treatment is not used then the end of the barrier must be shielded or flared as per NZTA
requirements. Please contact CSP Pacific if you require further assistance.

Safety statements
General safety

All required traffic safety precautions should be complied with. All workers should
wear required safety clothing (high visibility vests, steel capped footwear, gloves
etc.)

Only authorised trained personnel should operate any machinery. Where overhead
machinery is used, care must be taken to avoid any overhead hazards.

Gloves should be worn at all times.

Safety statements

All installers must be well clear of the water tanker when the units are being filled.

TL-2 Plastic Water Filled Barrier is a stand alone barrier and does not require at
any stage during installation that the surrounding soil is dug or drilled in anyway.

The empty units weigh 50kg each and should be unloaded by two personnel. Do
not attempt to lift a unit which contains water.

Final positioning of the empty units and placement of the steel connectors should
be done by 1 personnel so as to remove the risk of hands and fingers being caught
between the components.

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 4

Installation Manual: TL-2 Plastic Water Filled Barrier


Installation preparation
Getting started
It is essential that TL-2 Plastic Water Filled Barrier is installed correctly. Please carefully read
and understand the following instructions before installing.
TL-2 Plastic Water Filled Barrier is designed so that it has exactly the same components and
barrier setup whether in a roadside or median application. For all installations, start at one
end and connect the units together until the correct barrier length and position is achieved.
Preparation
Before installing TL-2 Plastic Water Filled Barrier, ensure that all components required for
the system are on site and have been identified. TL-2 Plastic Water Filled Barrier are a highly
engineered safety device made up of relatively small number of parts. Before starting
installation ensure that one is familiar with the make up of the system. Refer to the Parts
identification and Bill of materials below.
Ensure that the area where TL-2 Plastic Water Filled Barrier is to be installed is flat enough
and compacted so that the ground conditions will not significantly alter the height of the
vehicle in relation to the height of the barrier.
Tools required
There are no tools required to install the components of TL-2 Plastic Water Filled Barrier.
The plastic units can be manually lifted and positioned by 2 personnel and the twin pin used
to connect the units is simply dropped into position.
Each unit requires approx 560L of water. Using a large truck mounted tanker will allow for
fast barrier construction. A hose of up to 100mm in diameter can be used to fill the units.

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 5

Installation Manual: TL-2 Plastic Water Filled Barrier


Parts indentification

2.0m TL-2 Plastic Filled Barrier unit


(100% polyethylene)

Twin Pin connector


(hot dipped galvanised)

Bill of materials
For every 2.0m (linear) of temporary barrier the following components are required:

2.0m TL-2 Plastic Water Filled Barrier unit


1 required

Twin Pin steel connector


1 required

Water
560 litres required

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 6

Installation Manual: TL-2 Plastic Water Filled Barrier


Installation instructions
Standard installation
Step 1 Site preparation
It is preferred that TL-2 Plastic Water Filled Barrier is installed on compacted flat, level
ground.
Ensure that sufficient width and traffic control is available before installing TL-2 Plastic Water
Filled Barrier. Due to the bulky nature of the units, deployment will be from a flat deck truck
or similar. Each unit requires 560L of water and it is recommended that a large truck
mounted tanker is used.
TL-2 Plastic Water Filled Barrier should be installed in a tangent position to the direction of
travel.
TL-2 Plastic Water Filled Barrier units are dispatched in stacks of 15 with a unique triple
strapped configuration to ensure safe unloading of each different tier. (Shown in figure 1)
Using a fork hoist or similar the rows of 5 units can be lowered to ground level and from there
manually moved into position. (Shown in figure 2).

Figure 1

Ph 0800 655 200 or visit www.csppacific.co.nz

Figure 2

January 2011 Page 7

Installation Manual: TL-2 Plastic Water Filled Barrier


Step 2 Placement of the barrier units
Unload the units and set out in a row along the intended barrier position. Make sure
the configuration of the ends will fit together where they join. (shown in Figure 3)
Lifting the units is a 2 person job; they weigh 50kg each when empty.
Slide the units into position. (Shown in figure 4).

The units must fit flush together so that the vertical holes on each unit line up.
(Shown in figure 5 & 6).
Note: None of the units are fixed to the ground in any way.

Figure 5

Ph 0800 655 200 or visit www.csppacific.co.nz

Figure 6

January 2011 Page 8

Installation Manual: TL-2 Plastic Water Filled Barrier


Step 3 Connecting the barrier units
Once the units are flush fit aligned, the twin pin connector can be positioned down
the 2 vertical alignment holes. (Shown in figure 7 & 8).
The connector sits in the vertical holes under its own weight only and is not connected to the
barrier units in any other way.
Note: If slight curvature of the barrier is required, position as required at this point.

Figure 7

Figure 8

Step 4 Filling the barrier units


Lifting the flap on the top of the unit will allow access to the 125mm diameter water fill
hole. (Shown in figure 9).
Using a truck mounted tanker fill each unit to the top with water. (Shown in figure 10).
Check that there are no leaks before filling the next unit. If there is a leak the unit must be
replaced. It may be possible to fix at a later stage depending on the damage.

Figure 9

Ph 0800 655 200 or visit www.csppacific.co.nz

Figure 10

January 2011 Page 9

Installation Manual: TL-2 Plastic Water Filled Barrier


Installation examples

TL-2 Plastic Water Filled Barrier Standard installation (straight)

TL-2 Plastic Water Filled Barrier Standard installation (curved)


Note: A minimum 28m radius curvature can be achieved when the flush fit connection is
made between TL-2 Plastic Water Filled Barrier units. This positioning should be done before
the units are filled with water.
Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 10

TL-2 Plastic Water Filled Barrier


Installation

Y/N

Y/N

The lugs of each unit have a flush fit with each other and the twin pin
steel connector is positioned through both vertical holes in the lugs of
each unit.

The lid and bung are attached to each unit correctly so as to ensure
the units will remain full of water as intended.

Each unit is filled to the top with water. (approx 560L) Check for leaks.

The barrier is not fixed to the ground or any other device in any way.

The end of the barrier is installed with an AmorZone End Treatment or


shielded/flared as per NZTA requirements.

Location:
Installed by:

Date:

Inspected by:

Date:

For more information contact CSP Pacific on


Ph 0800 655 200 or visit www.csppacific.co.nz

Installation Checklist

The set-out of the barrier is as per the design instructions.

January 2010

The units are positioned on level ground.

Installation Manual: TL-2 Plastic Water Filled Barrier


Maintenance and repair
Maintenance
TL-2 Plastic Water Filled Barrier is maintenance free. Although it is recommended that
inspections are carried out on barriers that are installed for long periods of time. Each unit
has a lid and filter assembly to ensure that the barrier is only filled with water. However, in
extreme conditions it may be possible for evaporation to take place and it is important that
the units remain full.
Repair
After a typical impact
Recommended tools:

Flat deck truck


A truck mounted water tanker
A crow bar or similar

Replacement parts required for a severe impact:

TL-2 Plastic Water Filled Barrier units


Steel Twin Pin connectors
560l of water for each unit

Key steps:

Separate the damaged components by removing the steel connector.


Drain any units that are partially damaged.
Assess which components are damaged and replace with new parts accordingly.
Connect replacement units to the undamaged section of the barrier and align as
required.
Fit the replacement steel connectors between each unit.
Fill all the units with water.

For further information consult TL-2 Plastic Water Filled Barrier - Installation Instructions
section in this Product Manual.
After fire damage
TL-2 Plastic Water Filled Barrier is made of polyethylene and joined together using steel
connectors. It is possible that under extreme conditions, like Australian bushfires, that the
components of the system can be damaged. If this is the case replace the components as
described above and as outlined in TL-2 Plastic Water Filled Barrier Installation
Instructions.
Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 12

Installation Manual: TL-2 Plastic Water Filled Barrier


Appendix Technical drawings
Plan and elevation

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 13

Installation Manual: TL-2 Plastic Water Filled Barrier


Isomeric end #1

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 14

Installation Manual: TL-2 Plastic Water Filled Barrier


Isomeric end # 2

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 15

Installation Manual: TL-2 Plastic Water Filled Barrier


Twin Pin steel connector

Ph 0800 655 200 or visit www.csppacific.co.nz

January 2011 Page 16

July 2010

Interim Acceptance for Safety Barrier Product

Product:

Armorflex P2 TLTL-2 Plastic Barrier


Safety Barrier - Temporary

Expiry Date:

30 June 2011

The Armorflex P2 TL-2 plastic barrier system has been tested in accordance with NCHRP Report 350
and is deemed to comply with the required evaluation criteria for Test Level 2 (TL-2). Pending further
updates to the NZTAs M23 Specification for Roads Safety Barrier Systems, the Armorflex P2 system is
granted interim acceptance by the New Zealand Transport Agency for use on the state highway
network, with the following conditions:
Product Identification

Conditions of Use
The Armorflex P2 temporary barrier system must be installed and maintained in accordance with the
product installation/maintenance manual and relevant NZTA specifications. NZTA specifications and
standards shall prevail where there is discrepancy between the product manual(s) and the NZTA
specifications and standards.
Installers must ensure that they are familiar with relevant conditions, requirements and limitations of
the system, particularly with regard to the appropriate length of need, minimum installation length and
test deflection. Vehicle impacts that vary from the NCHRP Report 350 impact conditions may result in
significantly different results than those experienced in testing.

The Armorflex P2 temporary barrier system has been evaluated in accordance with the Test Level 2
criteria presented in NCHRP Report 350 under the following test conditions:

820kg small car impacting at an angle of 20 and a nominal speed of 70kph;

2,000kg pick-up truck impacting at an angle of 25 and a nominal speed of 70kph.

Units MUST be connected with the appropriate steel connecting pin and filled with water when in use.
Since there is currently no crashworthy terminal for the Armorflex P2, its ends should be flared away
from approaching traffic or adequately shielded.
A copy of this Interim Acceptance Letter must be appended to the Installation Manual.
Expiry of Acceptance
This acceptance expires on 30 June 2011 and replaces any previous acceptance. New installations of
the Armorflex P2 must not be deployed on the state highway network after the expiry date of
acceptance unless a further period of acceptance is granted or the product has been formally included
in the M23 Specification for Roads Safety Barrier Systems, in which case the M23 specification would
replace this interim acceptance.
The New Zealand Transport Agency reserves the right to rescind or modify, at any time, acceptance of
the Armorflex P2 temporary barrier system.

Authorised by the National Traffic and Safety Manager

S-ar putea să vă placă și