ROAD GRAVELLING OPERATIONAL EXPENSES

(PARTIAL) FOUR ROAD PROJECTS

1. ROAD GRADER
P40,000 X 2DAYS =
P80,000.00
2. DIESEL 2DAYS CONSUMPTION (GRADER KOMATZO LG-2H)
200 LITERS X P33.00 =
3. ELF PER TRIP FR. ILIGAN TO MARAWI (RENT) P2,500
4. DIESEL/ TRIP P700.00
5. MIX SAND/BASECOURSE PER ELF DUMP TRUCK P1,500.00
6. HAND TOOLS
7. GMA TERMINAL LABOR
8. MOBILIZATION/ SUPERVISION
9. PLATE COMPACTOR (RENT) 15 DAYS/P1,000.00 PER DAY
15,000.00
SUB TOTAL

SUBMITTED BY:

SMA BUILDERS
SARIMANOK, MARAWI CITY

6,600.00

25,000.00
30,000.00
10,000.00

P166,600.00