Work Management
Work Order
Overview
The Work Order is the foundation for all maintenance organizations. Work orders define the
resources and items that are needed to conduct work. They can automatically generate through
the use of Preventive Maintenance Schedules, the issue of an inventoried rebuildable, breach of
quality results, or manually generated as a routine Work Order. These Work Orders are then
reviewed and shared with Operations to produce an estimated schedule.
Enterprise Asset Management Work Orders are created against assets.
They can be defined manually, or generated automatically based on a scheduled activity.
If you attach a manually created work order to an asset activity (normally the role of a Planner),
the work order will inherit the asset activitys attributes, such as the maintenance BOM,
maintenance route (operations), attachments, quality plans, cost information, and scheduling
rules.
The Work Order May be of the following Types:
Manual Work Orders
Preventive Maintenance Work Orders
Rebuild Work Orders
Manual Work Order
Navigation: Work Order>Work Order
Raju Chinthapatla
1. Navigate to the Find Work Orders window (Work Orders > Work Orders).
2. Choose New.
3. The Work Order number is assigned, but you can update it.
4. Enter an Asset Number requiring maintenance
5. Select an Asset Activity. Only Asset Activities associated with this Asset Number are
available.
6. Enter a Class code to represent the charge (expense) accounts associated with the Asset
Number.
This defaults from the Asset Number
7. Enter the Status. For example, Unreleased, Released, On Hold, and Draft.
8. Within the Main tab, the Department value defaults from the selected Asset Number
9. Optionally select a Work Order Type. Work Order Types enable you to differentiate Work
Orders, for example, Routine, Preventive, Rebuild, Emergency, or Facilities.
10. The Shutdown Type defaults from the Activity. This helps the planner group Work Orders
that may require shutdowns, so that they are planned together.
11. Optionally select the Notification Required check box.
12. Optionally select the Tagout Required check box to indicate that the Area must be secured
for operations required to execute this Work Order.
Raju Chinthapatla
13. The Planned check box is selected if the current Work Order was created from forecasted
Work Orders.
14. Optionally select the Enable Material Issue Requests check box to enable eAM to manage
material availability for the current Work Order.
15. Optionally enter Failure Information..
16. The Material Shortage region enables you to view material availability. This region
populates, after you have saved the Work Order. You can choose Check Shortage to view the
shortage details.
17. Optionally select an Activity Type.
18. Optionally select an Activity Cause to specify what situation caused this work to generate,
for example, Breakdown, Vandalism, Normal Wear, or Settings.
19. Optionally select an Activity Source to specify reasons Activities need execution, for
example,
Warranty Compliance, OSHA Compliance, or Military Specification Requirements.
20. Optionally select the Request tab to assign Work Requests associated with this Work
Order.
21. Optionally select the Approval History tab to view the Work Order's approval
history. A Work Order might require approvals or notifications at different stages of its
lifecycle.
Raju Chinthapatla
Raju Chinthapatla
24. Optionally choose Materials to view or add items from the associated Asset Number's
items list
25. Click the quantity tab in the material form and check the material availability and
reuirement.
Raju Chinthapatla
27. Optionally select a Work Order, then choose Value Summary to view a summary of
the actual, estimated, and variance costs for labor hours, equipment hours, and material
against the current Work Order.
Actual Costs: This is the accumulation of all costs for material and resource transactions
for the Asset Number's associated maintenance Work Orders, based on a specified period.
Estimates: A BOM (material parts list) and routing (resources) can associate with a Work
Order. When you select the Estimates tab, the estimated costs of all material and resources
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
Material Transaction
Navigation: eAM Transaction> Material Transaction
Raju Chinthapatla
1.
2.
3.
4.
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
1.
2.
3.
4.
5.
6.
7.
8.
9.
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
Raju Chinthapatla
1.
2.
3.
4.
5.
Raju Chinthapatla
Raju Chinthapatla
12. In the For Multiple Rules region, indicate how the predicted due dates are
determined for multiple rules.First or Last.
13. Within the Activity region, select an Activity. Activities associated with
Asset Numbers are eligible for scheduling.
14. Optionally enter a Tolerance In Days to indicate a minimum interval in days
that suggested
Work Orders' dates are spaced from each other.
15. Within the Date Rules tab, optionally enter Effective From and To dates to
specify the rule's expiration.
16. Enter a Base Interval In Days. For example, if you enter the number three, a
Work Order suggestion is created every three days.
17. Optionally within the Meter Rules tab, select a Meter Name to indicate that
Preventive
Maintenance scheduling is based on a Meter Rule.
18. The Interval and UOM fields work together. For example, for every 2000 miles,
this Asset
Number needs an oil change
19. You cannot enter the Last Service Reading. This field is automatically updated
with the meter reading information recorded at Work Order completion
20. If you populated List Dates within the Schedule Type field, select the List
Dates tab to define the specific due dates that Work Orders should transpire.
21. Optionally choose Last Service Info to enter last service information for the
current Asset
Number/Activity association. Enter Last Service start and end dates.
22. Save and Close the Schedule