Documente Academic
Documente Profesional
Documente Cultură
Steel column
Lecture 10 - Page 1 of 6
m
n
m=
n=
0.80bf
N 0.95d
2
B 0.80b f
2
Lecture 10 - Page 2 of 6
2 f pu
t min = L
0 .9 F y
where: f pu =
Pu
BN
3.33 f pa
Fy
where: f pa =
Pa
BN
L = larger of
L = larger of
n
LRFD
ASD
Lecture 10 - Page 3 of 6
Example (LRFD)
GIVEN: A W14x82 A992 column has a factored axial load Pu = 700 KIPS. It
bears on a steel base plate using A36 steel. The footing has concrete fc = 3000
PSI.
REQUIRED: Design the column base plate.
Step 1 Determine required base plate area, A1 to avoid conc. crushing:
Pu
0.6(0.85 f ' c )
700 KIPS
0.6(0.85(3KSI ))
A1 = 457.5 in2
Step 2 Determine Optimized base plate dimensions:
0.95d 0.8b f
2
0.95(14.3" ) 0.8(10.1" )
2
= 2.75
N
A1 +
457.5in 2 + 2.75"
24.14
TRY N = 24 and B = 20 (Area = 480 in2 > 457.5 in2)
Lecture 10 - Page 4 of 6
N 0.95d
2
24"0.95(14.3" )
2
= 5.2
B 0.80b f
n=
2
20"0.80(10.1" )
2
= 5.96
Step 4 Determine minimum base plate thickness, tmin:
t min = L
2 f pu
0 .9 F y
Pu
BN
700 Kips
= 1.46 KSI
(20" )(24" )
m = 5.2
L = larger of
n = 5.96
t min = 5.96"
2(1.46 KSI )
0.9(36 KSI )
use
Lecture 10 - Page 5 of 6
20
W14x82 A992
col. centered
on plate
24
7
1 " thick A36 steel base plate
8
Lecture 10 - Page 6 of 6
Bolts used in structural steel fasteners fall within 2 categories see AISC Table
2-5 p. 2-41:
1) Carbon steel bolts These bolts achieve their total strength from shear
(or tension) strength across the diameter of the bolt. They are
relatively low-strength and are used primarily for low-load applications
such as for anchor rods. The typical carbon steel bolt used in
structural steel buildings is ASTM A307 and F1554 for use in anchor
rods.
2) High-strength bolts These bolts are used for high-load connections
and obtain their total strength from the shear strength across the
diameter of the bolt PLUS the friction developed between the nut and
joined steel surfaces. In order to achieve the friction capacity, these
bolts are tensioned to 70% of the ultimate tensile strength of the
material according to the table below. ASTM A325 and A490 bolts are
typically used.
The LRFD references the design of bolted connections in the following:
Lecture 12 - Page 1 of 9
Result
Lecture 12 - Page 2 of 9
2) Edge Tear-Out:
This occurs when the bolt is located too close to the edge of the
plate in the direction of load. A minimum required edge distance, Le, is
dictated in AISC Table J3.4 p. 16.1-107. Possible remedies include
increasing the edge distance or reducing the bolt diameter.
Le
Lecture 12 - Page 3 of 9
3) Bearing Failure:
This type of failure occurs when one of the plates is too thin or not
strong enough for the applied loads. The design bearing strength at
bolt holes is dictated in AISC p. 16.1-111 and AISC Table 7-5 p. 7-28
and AISC Table 7-6 p. 7-30. Possible remedies increasing the plate
thickness, use a higher grade of steel or using larger diameter bolts.
Thin plate
Bearing failure
Lecture 12 - Page 4 of 9
Lecture 12 - Page 5 of 9
Lecture 12 - Page 6 of 9
Rn
ASD
where: Rn = FnAb
= 0.75 LRFD
= 2.00 ASD
Fn = nominal tensile or shear stress of fastener, KSI
= from Table J3.2 p. 16.1-104
Ab = x-sect. nominal area of unthreaded body of bolt, in2
Shear Plane:
The shear plane is the plane in which the various connected parts
are in contact.
Single-shear
Double-shear
Load
Load
Lecture 12 - Page 7 of 9
Example 1 (LRFD)
GIVEN: A diameter ASTM A325-N bolt in single-shear is subjected to a
factored load of 14 KIPS.
REQUIRED: Determine the design shear strength of the bolt considering bolt
shear ONLY, and comment if the bolt is acceptable.
Pu = 14 KIPS
Step 1 Determine design shear strength of bolt:
Design shear strength = Rn
where: = 0.75
Rn = nominal shear strength of fastener
= FnAb
Fn = from Table J3.2 p. 16.1-104
= 48 KSI (threads Not excluded)
Ab = nominal area of unthreaded body of bolt, in2
=
D2
(0.75" ) 2
= 0.44 in2
Design shear strength = (0.75)(48 KSI)(0.44 in2)
Design shear strength = 15.8 KIPS > 14 KIPS Acceptable
Lecture 12 - Page 8 of 9
Example 2 (LRFD)
GIVEN: Same as Example 1
REQUIRED: Determine bolt design shear using AISC Table 7-1 p. 7-22.
Step 1 Refer to Table 7-1:
ASTM A325
Thread condition = N
Design shear strength = 15.9 KIPS
Loading = S (Single shear)
Bolt Diameter, db =
Lecture 12 - Page 9 of 9
Beam
Cope
Lev
S
S
Girder
Connection angles
Angle gage g from AISC p. 1-46
= Leh
where: Cope = cut distance of beam flange necessary to clear girder
flange and K distance, usually 1, 2 or 3
K = distance between top of flange to edge of start of flat web
= from beam properties AISC Part 1
Lev = required minimum vertical edge distance in direction of load
= from AISC Table J3.4 p. 16.1-107
S = bolt center-to-center spacing from AISC J3.3 p. 16.1-106
= 2 times nominal bolt diameter (minimum)
= 3 times bolt diameter (preferred)
= 3 (typical for bolts up to 1 diameter)
Lecture 13 - Page 1 of 5
Example (LRFD)
GIVEN: A W16x40 A992 steel beam A frames into a W18x55 A992 steel girder
B. The applied floor Service DL = 80 PSF and the applied floor Service LL =
100 PSF. Use diameter A325-X bolts with standard bolt holes and doubleangle A36 L3x3x connection angles. The beam is coped at top flange only.
REQUIRED: Design the all-bolted beam-to-girder connection and provide a
summary sketch.
W16x40 Beam A
4 @ 6-0 = 24-0
W18x55 Girder B
30-0
wu L
2
= 24 KIPS
Lecture 13 - Page 2 of 5
These tables incorporate all design considerations for typical allbolted double-angle connections.
Bolts
See Step 3
See Step 9
W16x40
Beam
See Step 5
See Step 7
See Step 5
See Step 8
Lecture 13 - Page 3 of 5
Thread Cond. = X
Angle thickness =
5
" from AISC p. 1-18
16
Use cope = 1
3
" from AISC p. 1-20
16
Lev = 1
The web thickness, tw of a W16x40 = 0.305 from AISC p. 1-20
W16x40 web design strength = 0.305(200 KIPS/inch)
= 61 KIPS > 24 KIPS OK
Lecture 13 - Page 4 of 5
W16x40 Beam
W18x55
Girder
Cope = 1
Lev = 1
S = 3
S = 3
1
Lecture 13 - Page 5 of 5
Welds also have some disadvantages which may preclude their use,
including:
Fillet Welds:
The most common type of weld for structural steel connections is the
fillet weld. This type of weld joins 2 pieces with flat faces at 900 angles.
Some examples of fillet welds and their weld symbols are shown below:
Lecture 14 - Page 1 of 6
Lecture 14 - Page 2 of 6
A closer inspection through the fillet weld itself is shown below to indicate
some of the dimensions of a weld:
The most common type of fillet welding process is Arc welding, or sometime
called stick welding. This process involves running an electric current through a
sacrificial electrode creating an arc of extremely high temperature that fuses the
steel pieces together. The electrode (stick) has a coating called a flux that,
when subject to heat, produces a cloud acting as a barrier to impurities in the air
entering the molten metal. A diagram of arc welding process is below:
Lecture 14 - Page 3 of 6
Lecture 14 - Page 4 of 6
5/16
Lecture 14 - Page 5 of 6
Example (LRFD)
GIVEN: Two thick A36 steel plates fillet welded as shown below. Use
E70XX weld electrodes.
REQUIRED: Determine the maximum factored load, Pu, that can be
applied based on shear strength of the welds.
Pu
3/16
Lecture 14 - Page 6 of 6
W21x44 Girder
Minimum Web
thickness
L=?
W12x58
Column
Weld A
3/16
2X weld
size
L2x2x erection
angle shop-welded to
col. flange
L=?
2 L3x3x3/8
connection angles
Weld B
Lecture 15 - Page 1 of 7
See Step 2
See Step 5
See Step 4
See Step 3
Lecture 15 - Page 2 of 7
Lecture 15 - Page 3 of 7
W12x58
Column
Weld A
3/16
2() =
L2x2x erection
angle shop-welded to
col. flange
12
2 L3x3x3/8
connection angles
Weld B
Lecture 15 - Page 4 of 7
Pu
Pu
Example 2 (LRFD)
GIVEN: A plate is welded to the flange of a column as shown below. This
plate carries a cantilevered factored load of 25 KIPS.
REQUIRED: Determine if the weld is adequate to carry the eccentric loading.
Pu = 25 KIPS
16
Column
flange
L = 8
Plate
Lecture 15 - Page 5 of 7
See Step 3
See Step 2
See Step 4
See Step 3
Lecture 15 - Page 6 of 7
Pu
CC1 D
Pu = LCC1D
where: = 0.75
C = 0.821
C1 = 1.0 (AISC p. 8-65)
D = 4 - 1/16ths
= (8)(0.75)(0.821)(1.0)(4)
Pu = 19.7 KIPS < 25 KIPS UNACCEPTABLE
Lecture 15 - Page 7 of 7
Lecture 16 - Page 1 of 13
1.3 Units
Either U.S. customary or metric units will be used. Each system shall
be independent of the other.
1.4 Design Criteria
The AISC Specification shall be used in the absence of other design
criteria.
1.5 Responsibility for Design
Lecture 16 - Page 2 of 13
Discrepancies between:
Design Drawings
Specifications
Scaled graphic drawings Written info in drawing
Arch., Elect., Mech.
Structural Drawings
Drawings
Which Governs:
Design Drawings
Written info in drawings
Structural Drawings
Lecture 16 - Page 4 of 13
Lecture 16 - Page 5 of 13
Section 5 MATERIALS
5.1 Mill Materials
Fabricator is permitted to order materials upon receipt of Contract
Documents that have been issued for construction.
If mill materials do not meet ASTM A6 tolerances, Fabricator is
permitted to make corrective procedures.
5.2 Stock Materials
Fabricator may use stock materials if they meet with required
ASTM specifications. Certified mill test reports are used as
evidence of record of quality of material.
Section 6 SHOP FABRICATION AND DELIVERY
6.1 Identification of Material
Materials used for special requirements shall be marked by the
supplier as specified by ASTM A6 prior to delivery to Fabricators
shop or point of use.
6.2 Preparation of Material
Thermal cutting of material is permitted. Surfaced specified as
finished shall have a roughness in accordance with ANSI/ASME
B46.1 that is less than or equal to 500.
6.3 Fitting and Fastening
Projecting elements of connection materials need not be
straightened in the connecting plane. Backing bars and runoff tabs
shall be used to produce as required to produce sound welds, and
do not need be removed unless specifically designated in the
Contract Documents.
Lecture 16 - Page 6 of 13
Tolerance Variation:
Length = 1/32
Length = 1/16
Length = 1/8
Straightness < 1/1000 axial length
Camber variation = 0
Camber variation = 0 + 1/8 per
10-0 additional length beyond 50-0
Lecture 16 - Page 7 of 13
Variation in Dimension:
< 1/8
<
< per 100-0
not to exceed a total of 1
Lecture 16 - Page 8 of 13
Lecture 16 - Page 9 of 13
Member:
Column tolerance deviation from plumb
Individual straight piece (other than
column) connecting to column
Adjustable members
Erection Tolerance:
1/500 distance between work points
not to exceed 1 total for first 20 stories
+ 3/16
- 5/16
3/8
Lecture 16 - Page 10 of 13
Lecture 16 - Page 11 of 13
Section 9 CONTRACTS
9.1 Types of Contracts
Lecture 16 - Page 12 of 13
All welds exposed to view shall not project more than 1/16
above the surface.
Lecture 16 - Page 13 of 13
Design Drawings
Specifications
The Design Drawings graphically present the specific design of the structure.
However, they do not indicate the specific requirements relating to:
Materials
Submittals
Job conditions
Testing & inspection
Execution of work
Each division has been further refined into multiple sub-divisions (as
shown for Division 5 above). To obtain samples of specifications, go to
http://www.ogs.state.ny.us/dnc/generalInfo/masterspecdefault.htm
In addition to technical specifications, the CSI MasterFormat is used by
most of the construction industry for purposes of cost estimating,
contractor qualifications, product research and supply ordering.
Lecture 17 - Page 1 of 8
WORK INCLUDED
A. Labor, materials, equipment, services and transportation required to
complete structural steel work on the Drawings, as specified herein or
both. Structural steel work is that work defined in AISC Code of
Standard Practice for Steel Buildings and Bridges, dated March 7,
2005, plus work listed below and shown on structural drawings.
1.
2.
3.
4.
5.
6.
7.
1.2
QUALITY ASSURANCE
A. Comply with latest editions of:
1. American Institute of Steel Construction (AISC) Publications:
a. Manual of Steel Construction: Includes "Specification for
Structural Steel Buildings Load and Resistance Factor Design
(LRFD)", "Code of Standard Practice for Steel Buildings and
Bridges", "Specification for Structural Joints Using ASTM A325
or A490 Bolts".
b. Building Code of New York State by New York State
Department of State Division of Code Enforcement and
Administration.
2. American Welding Society, Inc. (AWS): AWS D1.1 "Structural
Welding Code - Steel".
3. American Hot Dip Galvanizers Association, Inc.; Zinc Institute Inc.:
"Inspection Manual for Hot Dip Galvanized Products".
4. Society for Protective Coatings (SSPC): "Surface Preparation
Specifications".
Lecture 17 - Page 2 of 8
5.
TESTING SERVICES
A. The Contractor shall employ a testing laboratory acceptable to Architect
to perform the following tests:
1. Visual inspection of all welds according to AWS.
2. Magnetic particle inspection according to ASTM E709 for 10
percent of all shop and field welds.
3. Ultrasonic inspection according to ASTM E587 for all shop or field
full penetration welds.
4. Inspection of field-assembled high-strength bolted connections.
5. Inspection of erected columns for plumbness within tolerances
specified.
6. Inspection of headed studs.
7. Visual inspection of all erected steel for damage.
B. Weld Inspector shall be certified in accordance with AWS.
1. Submit resumes of technicians who will perform work showing
evidence of one year minimum experience on similar work.
1.4
SUBMITTALS
A. General: Review of submittals will be for general consideration only.
Compliance with requirements for materials, fabrication, erection and
dimensioning of structural steel shall be Contractor's responsibility.
B. Connections: Submit proposed connection types for review before
preparing detailed shop drawings.
C. Shop Drawings - Submit detailed drawings showing: (NOTE: Design
drawings shall NOT be used as shop drawings)
1. Column layout plans.
2. Floor and roof framing plans.
Lecture 17 - Page 3 of 8
3.
4.
5.
6.
7.
JOB CONDITIONS
A.
B.
C.
D.
PART 2 - PRODUCTS
2.1
MATERIALS
A. Rolled Steel Plates, Angles, Channels, M shapes, HP shapes and Bars:
ASTM A36.
B. W Shapes: ASTM A992.
C. HSS Steel Rectangular, Square and Round: ASTM A500, Grade B.
D. Steel Pipe: ASTM A53 Grade B.
E. Unfinished Bolts, Nuts and Washers: ASTM A307, Grade A.
F. High-strength Bolts, Nuts and Washers: ASTM A325 or A490.
G. Direct Tension Indicating Washers: ASTM F959-85.
H. Headed Studs: ASTM A108, Grades 1015 1020, minimum field = 50
KSI.
I. Anchor Rods, Nuts and Washers: ASTM F1554.
J. Non-Shrink Bedding Mortar for Bearing and Base Plates: CRD-C 621,
Type D Masterflow 713 from Master Builders (or equivalent).
K. Neoprene Bearing Pads: ASTM D412; 70 Durometer Hardness, 2500
PSI Tensile.
L. Weld Electrodes: E70XX and in accordance with AWS.
M. Expansion Bolts: Diameter stainless steel with ultimate capacities in
4000 PSI concrete of 16,000 lbs. in shear and 16,000 lbs. in tension;
minimum embedment of 6 Kwik Bolt II from Hilti Corp. (or equivalent).
Lecture 17 - Page 4 of 8
FABRICATION
A. Fabricate structural steel in strict accordance with reviewed shop
drawings and referenced standards.
B. Fabricate and assemble structural material in shop to greatest extent
possible.
C. Provide camber as indicated on Drawings. Where no camber is
indicated, fabricate steel with mill camber up.
D. Provide holes for securing other work to structural steel framing. Cut,
drill or punch holes perpendicular to metal surfaces. Do not flame cut
holes or enlarge holes by burning. Drill holes in base and bearing
plates.
E. Finish and weld column bases to column base plates.
F. Anchor Rods: Furnish anchor rods, leveling plate and/or other devices
necessary for setting anchoring rods required for securing structural
steel to foundation, concrete or masonry.
G. Hot dip galvanize all lintels in exterior masonry work or as noted on
drawings.
2.3
SHOP PAINTING
A. Shop paint only structural steel work which will be exposed to view and
finish painted. Do not paint steel embedded in concrete or mortar or
receive a spray on fireproofing. Do not paint surfaces which are to be
Lecture 17 - Page 5 of 8
welded, including metal deck. Do not paint contact surfaces of highstrength bolted connections or finished bearing surfaces such as
bearing plates and column base plates.
B. For steel to be shop primed and not exposed to view, remove loose rust
and mill scale by mechanical means in accordance with SSPC-SP3
"Power Tool Cleaning". For steel to be galvanized or primed and finish
painted, remove all dirt, grease, rust and loose mill scale in accordance
with SSPC-SP6 Commercial Blast Cleaning, unless recommended
otherwise by paint manufacturer.
C. Immediately after surface preparation, apply structural steel primer
paint in accordance with manufacturer's instructions but not less than a
uniform dry-film thickness of 2 mils. Use painting methods which will
result in full coverage of joints, corners, edges and exposed surfaces.
D. Apply below grade coating to column bases and columns to be placed
below top of finished floor.
E. Apply two coats of cold galvanizing compound to achieve a minimum
dry-film thickness of 3 mils. in accordance with manufacturers
recommendations.
2.4
CONNECTIONS
A. Weld or bolt shop connections.
B. Bolt field connections as shown on drawings.
C. No one-sided or other eccentric connections will be permitted, unless
shown on Drawings.
D. Minimum Capacity of Beam Connections: For connections not detailed,
provide connection capacity of the nominal full section shear capacity
Vn for the given steel member as dictated in AISC Steel Construction
Manual. A minimum factored shear capacity of 10 kips shall be
provided for all secondary beams. For beam and girders with shear
studs, provide a connection capacity of at least 125 percent of uniform
load values unless indicated otherwise on drawings.
E. Provide snug-tight unfinished threaded fasteners for bolted bearing
connections of secondary framing members to primary members;
including, but not limited to, girts, door framing systems, roof opening
and other framing systems taking only nominal stresses and in no way
reacting in stress on primary members.
F. Provide high-strength fasteners for all principal bolted connections,
unless otherwise indicated.
Lecture 17 - Page 6 of 8
J.
PART 3 - EXECUTION
3.1
INSPECTION
A. Examine conditions under which work shall be erected. Do not proceed
until all unsatisfactory conditions are corrected.
3.2
ERECTION
A. Set structural frames accurately to lines and elevations indicated. Align
and adjust various members forming part of a complete frame or
structure before permanently fastening.
B. Clean bearing surfaces and other surfaces before assembly that will be
in permanent contact after assembly.
C. Perform necessary adjustments to compensate for discrepancies in
elevations and alignment. Level and plumb individual members of
structure within specified tolerances.
D. Splice members only where shown or specified.
E. Maintain work in a stable condition during erection.
F. The use of gas cutting torches in field to correct fabricating errors is
prohibited.
G. Tighten bearing bolt (X) connections to snug-tight condition.
3.3
TOLERANCES
A. Tolerances shall be within limits in AISC "Code of Standard Practice".
B. Fabrication and mill tolerance shall be within limits in AISC Standard
Mill Practice.
Lecture 17 - Page 7 of 8
3.4
TOUCH-UP PAINTING
A. After erection is complete, touch-up paint damaged shop priming coats
and welded areas. Remove weld slag before applying touch-up paint.
B. Touch-up below grade coatings to all portions of structural steel
embedded within concrete slabs on grades.
3.5
3.6
PROTECTION
A. Do not use members for storage or working platforms until permanently
secured.
B. Do not exceed load capacity of members with construction loads.
END OF SECTION
Lecture 17 - Page 8 of 8
Lecture 18 - Page 1 of 10
K-Series Joists
The most commonly-used joist style is the so-called K series. It has a
depth ranging from 8 up to 30 and is used economically to span up to
60-0. A typical K series joist is as shown below:
Lecture 18 - Page 2 of 10
Steel joists are fastened to its supporting members usually by fieldwelding as shown below:
Unlike structural steel beams, steel joists must use bridging placed
perpendicular to the span to obtain its stability. This bridging can be one
of 2 types:
Horizontal Bridging
Diagonal Bridging
Lecture 18 - Page 3 of 10
Lecture 18 - Page 4 of 10
Joist Girders
Joist girders are designed to carry the end reactions from equally-spaced
joists applied to the panel points. Typical depths of joist girders range
from 20 up to 96 with spans of 100-0 or more.
Lecture 18 - Page 5 of 10
Example 1
GIVEN: A roof framing bay is as shown below. The service loads are as follows:
REQUIRED: Design the K series joists assuming the maximum joist spacing =
6-0 (based on metal roof deck). Assume the joist + accessories weighs 10 PLF.
36-0
60-0
Lecture 18 - Page 6 of 10
D
D+L
D + L + (Lr or S or R)
D + (W or 0.7E) + L + (Lr or S or R)
0.6D + W
0.6D + 0.7E
where: D = Dead Load
= 6(16 PSF) + 10 PLF
= 106 PLF
Lr = Roof Live Load
= 6(25 PSF)
= 150 PLF
S = Snow Load
= 6(35 PSF)
= 210 PLF
W = Wind Load
= 6(-12 PSF)
= -72 PLF
Check all 6 load combinations and select worst case total load:
1)
2)
3)
4)
5)
6)
D = 106 PLF
D + L = 106 PLF
D + L + (Lr or S or R) = 106 + 150 = 256 PLF
D + (W or 0.7E) + L + (Lr or S or R) = 106 + 210 = 316 PLF
Lecture 18 - Page 7 of 10
Step 3 Select lightest joist from Vulcraft K series Load Table p. 12:
Total Load = 316 PLF
Live Load = Total Load Dead Load
= 316 PLF 106 PLF
= 210 PLF
Span = 36-0
Possibilities:
Joist Size:
24K8
26K7
28K6
30K7
Total Load:
346
340
330
395
Live Load:
222
240
252
323
Wt/ft:
11.5
10.9
11.4
12.3
Lecture 18 - Page 8 of 10
Use 3 Rows of
Bridging
28K6 @ 6-0
36-0
Lecture 18 - Page 9 of 10
Example 2
GIVEN: The roof framing bay from Example 1.
REQUIRED: Design the lightest weight 60-0 span joist girder.
28K6 @ 6-0
Joist Girder
36-0
wL
2
= 5688 LBS.
= 5.7 KIPS USE 6 KIPS
Step 2 Select joist girder depth from Vulcraft p. 87:
Girder span = 60-0
Joist Spaces = 10N @ 6.00
Load on Each Panel Point = 6 KIPS
Select 72 girder
depth wt. = 35 PLF
Lecture 18 - Page 10 of 10
Top flute
Deck height
Bottom flute
Panel width = 24 36
The Steel Deck Institute, SDI, was established in 1939 in an effort to regulate the
design, manufacture and installation of steel deck. Manufacturers complying with
SDI specifications include Vulcraft, Canam Steel Corp. and United Steel Deck,
Inc.
Types of Steel Deck
There are 3 general types of steel deck roof deck, non-composite floor
deck and composite deck.
1. Roof Deck
Roof deck is used primarily to carry lightweight roof construction. It
is characterized by having relatively narrow bottom flutes so that
there is a wider top flute to maximize the surface contact with rigid
insulation. It comes in heights ranging from 1 up to 3 and in
thicknesses ranging from 24 gage (thinnest) up to 16 gage
(thickest). Depending on the section, roof decking can span as
much as 15-0. Acoustical deck is available to control sound
transmission through the decking. It is used for auditoriums,
schools, etc., and is obtained by adding fiber sound-absorbing batts
between the vertical webs of the decking. In addition, roof deck is
available as cellular deck for use in placing electrical services or
exposed underside. Data relating to roof deck may be found in the
Vulcraft catalog p. 3 18.
Lecture 19 - Page 1 of 8
Lecture 19 - Page 2 of 8
Welded wire
mesh in
concrete slab
Lecture 19 - Page 3 of 8
Lecture 19 - Page 4 of 8
7-0
7-0
7-0
3 spans (min.)
Step 1 Determine maximum unif. load on deck:
Utilizing the 6 allowable stress design load combinations from the
IBC Section 1605.3.1:
1)
2)
3)
4)
5)
6)
D
D+L
D + L + (Lr or S or R)
D + (W or 0.7E) + L + (Lr or S or R)
0.6D + W
0.6D + 0.7E
where: D = Dead Load
= 15 PSF
Lr = Roof Live Load
= 20 PSF
S = Snow Load
= 40 PSF
W = Wind Load
= -8 PSF
Lecture 19 - Page 5 of 8
Check all 6 load combinations and select worst case total load:
1)
2)
3)
4)
5)
6)
D = 15 PSF
D + L = 15 PSF
D + L + (Lr or S or R) = 15 + 20 = 35 PSF
D + (W or 0.7E) + L + (Lr or S or R) = 15 + 40 = 55 PSF
7-0 span
3 span
Lecture 19 - Page 6 of 8
4 @ 6-0 = 24-0
Step 1 Determine the uniform load on the decking:
Utilizing the 6 allowable stress design load combinations from the
IBC Section 1605.3.1:
1)
2)
3)
4)
5)
6)
See Vulcraft
catalog p. 28 for
slab wt.
D
D+L
D + L + (Lr or S or R)
D + (W or 0.7E) + L + (Lr or S or R)
0.6D + W
0.6D + 0.7E
where: D = Dead Load
= Slab wt. + Superimposed Dead Load
= 51 PSF + 38 PSF
= 89 PSF
L= FloorLive Load
= 50 PSF
Step 3 Refer to Reinf. Conc. Slab Allow. Loads table Vulcraft p. 28:
Total Slab Depth = 5
Clear Span = 6-0
Superimposed Unif. Load = Total Load Slab Wt.
= 139 PSF 51 PSF
= 88 PSF
Use 6x6-W2.1xW2.1
W.W.F. Allow. load =
107 PSF > 88 PSF
Lecture 19 - Page 8 of 8
Lecture 2 - Page 1 of 8
Refer to AISC p. 1-10 thru 1-115 for dimensions and structural properties
of the above-noted structural shapes and combination of shapes.
Refer to AISC Table 2-3 (page 2-39) for a list of appropriate structural
steel ASTM designations for various structural shapes. In general, the
following ASTM designations are commonly used:
ASTM
Designation
A36
A572
A992
A53
A500, Gr. B
A500, Gr. B
A588
Fy (KSI)
Fu (KSI)
36
50
50
35
42
46
50
58
65
65
60
58
58
70
High-strength
Excellent quality control, predictability
Ductility
Speed of erection
Lightweight
Can be easily modified
Fireproofing
Corrosion
Need for bracing
Semi-skilled labor (ironworkers, welders)
Subject to vibration
Temperature effects - brittle below -600F
- rapid reduction of E above 7000F
Lecture 2 - Page 2 of 8
Load and Resistance Factor Design (LRFD) see AISC p. 2-6 and 16.1213 thru 217
iQi < Rn
where: I =load factor
Qi = working or service load (see IBC ch. 16)
= reduction factor, see AISC p. 2-10
= 0.90 for limit-states involving yielding
= 0.75 for limit-states involving rupture
Rn = nominal resistance strength of member
If plotted on a probability graph, 2 bell curves would emerge, one being
the probability of loads and the other being the probability of a members
strength being realized.
Probability of
loads, Qi
Probability of
member strength, Rn
Overlap = failure
Lecture 2 - Page 3 of 8
1.4D
1.2D + 1.6L + 0.5(Lr or S or R)
1.2D + 1.6(Lr or S or R) + (0.5L or 0.8W)
1.2D + 1.6W + 0.5L + 0.5(Lr or S or R)
1.2D + 1.0E + 0.5L + 0.2S
0.9D + (1.6W or 1.0E)
W18x40
W18x40
W18x40
wu
24-0
24-0
8-0
Typ.
REQUIRED:
1) Determine the maximum LRFD factored uniform load on the beam, wu.
Lecture 2 - Page 4 of 8
= 39,168 ft-lb
Mu = 39.2 kip-ft
Lecture 2 - Page 5 of 8
Allowable Stress Design (ASD) See AISC p. 2-7 and 16.1-216 thru 217
The Allowable Stress Design (ASD) method is based on the concept that
the stress levels in a component do not exceed established specific
allowable stresses under service loads. For any single component, there
may be several different allowable stress limits that must be checked.
The basic design equation for ASD is as follows:
Qi
Rn
D
D+L
D+(Lr or S or R)
D+0.75L+0.75(Lr or S or R)
D+(W or 0.7E)
D+0.75(W or 0.7E)+0.75L+0.75(Lr or S or R)
0.6D+(W or 0.7E)
Lecture 2 - Page 6 of 8
W18x40
W18x40
W18x40
Example 2
GIVEN: Similar to Example 1, a flat roof is framed with 24-0 long
W18x40 beams spaced 8-0 o.c. The service applied roof dead load is 25
PSF and the applied service roof live load = 20 PSF (per IBC ch. 16). The
service wind load on the flat roof is -8 PSF (uplift).
8-0
24-0
Typ.
REQUIRED:
1) Determine the maximum ASD service uniform load on the beam, w.
2) Determine the maximum ASD service moment on the beam, Mmax.
Step 1 Determine D, Lr and W in terms of PLF:
D = DL(Trib. Width) + Beam wt.
= 25 PSF(8 ft) + 40 PLF
= 240 PLF
Lr = LL(Trib. Width)
= 20 PSF(8 ft)
= 160 PLF
W = -8 PSF(8 ft)
= -64 PLF
Step 2 Determine maximum SERVICE uniform load, w:
1) D
240 PLF
2) D+L
240 PLF + 0 = 240 PLF
3) D+(Lr or S or R)
240 PLF + 160 PLF = 400 PLF USE
Lecture 2 - Page 7 of 8
4) D+0.75L+0.75(Lr or S or R)
240 PLF + 0 + 0.75(160 PLF) = 360 PLF
5) D+(W or 0.7E)
240 PLF + (-64 PLF) = 176 PLF
240 PLF (-64 PLF) = 304 PLF
6) D+0.75(W or 0.7E)+0.75L+0.75(Lr or S or R)
240 PLF + 0.75(-64 PLF) + 0 + 0.75(160 PLF) = 312 PLF
7) 0.6D+(W or 0.7E)
0.6(240 PLF) + (-64 PLF) = 80 PLF
0.6(240 PLF) (-64 PLF) = 208 PLF
Step 3 Determine maximum SERVICE moment on beam, Mmax:
Mmax =
wL2
8
Lecture 2 - Page 8 of 8
Very labor-intensive
Quality control
Formwork
Longer construction schedule due to curing time
Much larger, heavier member sizes (vs. steel-framed)
Poor insulation values
Lecture 21 - Page 1 of 8
Concrete Materials:
Concrete is a mixture of the following materials:
1. Portland Cement The active ingredient that glues the other
materials together, conforming to ASTM C 150-99a. The raw
materials used in portland cement consist mainly of limestone, and
clays & shales. Different types of Portland cement include:
a) Type I General purpose
b) Type II Moderate sulfate protection and lower heat of
hydration
c) Type III High-early strength
d) Type IV Low heat of hydration used for massive concrete
structures such as dams
e) Type V High sulfate resistance
2. Water Water is necessary to create the chemical reaction of
hardening the cement called hydration. It should be clean and free
from any impurities (i.e., potable).
3. Aggregates Fine (sand) and coarse (gravel). Conforming to
ASTM C 33.
4. Admixtures Other ingredients added to enhance properties:
a) Air Entrainment Tiny bubbles used to reduce cracking in
concrete subject to freeze-thaw cycles. Conforming to
ASTM C 260 with an air content of 4% - 8% by volume.
b) Superplasticizers Also called High Range Water
Reducers, used to increase concretes flow (workability)
instead of adding water. Conforming to ASTM C 494 Type F.
c) Retarders Used to slow the hydration process.
Conforming to ASTM C494 Type D.
d) Accelerators Used to speed-up the curing process,
conforming to ASTM C494 Type C or E.
e) Insulating beads Increases the R value, but diminishes
strength.
f) Fly Ash The byproduct of coal-burning electric generating
plants. Used to decrease the amount of portland cement
required. Conforming to ASTM C 618 Class F.
g) Colors Can be mixed to produce any desirable color.
Lecture 21 - Page 2 of 8
Lecture 21 - Page 3 of 8
2) Tensile Strength
Concrete is a brittle material and has very small tensile strength (about
10% of fc). It is usually assumed that concrete has zero tensile
strength.
3) Modulus of Elasticity Determined by formula below:
Econc = 57000
f 'c
f 'c
Lecture 21 - Page 4 of 8
Diameter:
1
1
1
1
Area (in2):
0.11
0.20
0.31
0.44
0.60
0.79
1.00
1.27
1.56
Lecture 21 - Page 5 of 8
Epoxy-coated reinforcing bars are regular bars with a shopapplied coating of epoxy. These bars have exceptional resistance
to corrosion and are used in situations where there is high
water/salt exposure (such as road bridge decks, marine structures,
etc.). They are smooth to the touch and usually green in color.
Codes allow the placement of epoxy-coated bars to be closer to the
surface than regular bars because of the increased resistance to
corrosion. This usually results in a thinner, lighter concrete beam
or slab. Unfortunately, the epoxy coating is often scratched or
damaged during construction, leaving exposed bare steel. This
exposed bare steel is ripe for allowing moisture and salt deposits to
enter and actually INCREASING the propagation of corrosion.
For this reason, many state Departments of Transportation do not
allow epoxy-coated reinforcing bars for use in bridge decks.
Lecture 21 - Page 6 of 8
Required minimum
cover distance
Concrete member
Reinforcing bars
Required minimum
cover distance
Lecture 21 - Page 7 of 8
Minimum cover:
3
2
1
1
Slump:
Maximum
Minimum
3
1
4
1
4
1
3
1
2
1
Lecture 21 - Page 8 of 8
Contents:
PART 1GENERAL
CHAPTER 1GENERAL REQUIREMENTS .................................................318-9
CHAPTER 2DEFINITIONS........................................................................ 318-19
PART 2STANDARDS FOR TESTS AND MATERIALS
CHAPTER 3MATERIALS.......................................................................... 318-27
Lecture 22 - Page 1 of 8
Lecture 22 - Page 2 of 8
1.4(D + F)
1.2(D + F + T) + 1.6(L + H) + 0.5(Lr or S or R)
1.2D + 1.6(Lr or S or R) + (1.0L or 0.8W)
1.2D + 1.6W + 1.0L + 0.5(Lr or S or R)
1.2D + 1.0E + 1.0L + 0.2S
0.9D + 1.6W + 1.6H
0.9D + 1.0E + 1.6H
where: D = service dead loads
L = service live load
Lr = service roof live load
S = snow loads
W = wind loads
R = rainwater loads
E = earthquake loads
F = fluid loads
H = soil loads
T = Temperature, creep, settlement, shrinkage loads
Lecture 22 - Page 3 of 8
0.90
0.70
0.65
0.85
0.75
0.65
Example 1
GIVEN: The interior column of a 2-story concrete-framed building has the
following applied service loads to the 1200 ft2 tributary area as shown:
Roof live load = 20 PSF
Snow load = 45 PSF
Roof superimposed dead load (not including 8 thick slab) = 16 PSF
Roof wind uplift = -8 PSF
Floor live load = 100 PSF
Floor superimposed dead load (not including 10 thick slab) = 42 PSF
REQUIRED: Determine the maximum factored load, Pu, at the bottom of the 20
x 20 square column.
Lecture 22 - Page 4 of 8
20" 20"
3
Column dead load, Dcolumn =
(28 ft ) 150lb / ft
12
12
= 11,667 lbs.
= 11.7 KIPS
Lecture 22 - Page 5 of 8
Lecture 22 - Page 6 of 8
Example 2
GIVEN: The cantilevered floor balcony beam/slab as shown below. The service
superimposed dead load (not including concrete) = 14 PSF and the
superimposed service live load = 75 PSF.
REQUIRED: Determine the maximum factored moment, Mu on the cantilevered
beam.
14-0
18
5 slab
10
Beam
16-0
wu
14-0
Lecture 22 - Page 7 of 8
18
10
8-0
18 5 slab
16-0
10" 13"
150lb
5"
(8' )( ) + ( )( )
3
12 12
12
ft
= 635.4 PLF
Mu = 186.2 KIP-FT
Lecture 22 - Page 8 of 8
Depth to steel d
Hanger bars
(#4 or #5 bars)
Stirrup bars (used
to prevent diag.
tension cracks)
spaced at d/2
apart
Concrete cover
= 2 as
per ACI reqmts.
Height h
Width b
Tension bars As
Section A-A
Lecture 23 - Page 1 of 9
Height h
Min. bar
spacing
Tension bars As
Min. bar
spacing
Lecture 23 - Page 2 of 9
Lecture 23 - Page 3 of 9
Example 1
GIVEN: A rectangular concrete beam is similar to the one shown above.
Use the following:
Height h = 20
Width b = 12
Concrete fc = 4000 PSI
Concrete cover =
All bars are A615 Grade 60 (fy = 60 KSI)
Stirrup bar = #3
4 - #7 Tension bars
REQUIRED:
1) Determine total area of tension bars, As.
2) Determine depth to center of tension bars, d.
A
200
3) Determine actual = s where min =
and state if it is acceptable.
bd
fy
Step 1 Determine area of tension bars, As:
As = 4 bars(0.60 in2 per bar)
As = 2.40 in2
Step 2 Determine depth to tension bars, d:
d = depth to center of tension bars, inches
= h (concrete cover) (stirrup bar dia.) (tension bar dia.)
= 20 ()
d = 18.44
Step 3 Determine actual and min :
actual =
As
bd
min =
2.40in 2
(12" )(18.44" )
200
fy
200
60000 PSI
min = 0.0033
actual = 0.0108
Lecture 23 - Page 4 of 9
Applied loads
Span L
Taking a section through the beam at any place along the length reveals the
following stress distribution about the cross-section of the beam:
Compression
Neutral
Axis
Homogeneous Beam
Tension
Lecture 23 - Page 5 of 9
Compression
Neutral
Axis
C
Neutral
Axis
(a)
0.85fcb
a = 1C
d
Moment arm = Z
T = Asfy
Actual Stress Distribution
T = Asfy
Idealized Stress Distribution
Lecture 23 - Page 6 of 9
As f y
0.85 f ' c b
= 1C
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
fy
87,000
87,000 + f
y
where fy = PSI
max = maximum allowable ratio of tension steel reinforcement per ACI 318
= 0.75bal
Lecture 23 - Page 7 of 9
Example 2
GIVEN: The concrete beam from Example 1 is used to support the loading as
shown below.
REQUIRED:
1. Determine the maximum factored applied moment, Mmax.
2. Determine the usable moment capacity of the beam, Mu, and determine if
it is acceptable based on Mmax.
3. Determine if the beam is acceptable based on max.
20-0
wu L2
8
(3KLF )(20'0" ) 2
8
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.0108)(60 KSI )
= 0.9(2.40 in2)(60 KSI)(18.44)(1 - 0.59
)
4 KSI
= 2161.4 KIP-IN
Mu = 180.1 KIP-FT
Since Mu = 180.1 KIP-FT > Mmax = 150 KIP-FT beam is acceptable
Lecture 23 - Page 8 of 9
max = maximum allowable ratio of tension steel reinforcement per ACI 318
= 0.75bal
bal = balanced ratio of tension steel reinforcement
0.851 f ' c
=
fy
87,000
87,000 + f
y
where fy = PSI
87,000
0.85(0.85)(4 KSI )
=
60 KSI
max = 0.75(0.0285)
max = 0.0214 > act = 0.0108 beam is acceptable
Lecture 23 - Page 9 of 9
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
Designing a beam using the equation above is much more difficult. Assuming the
material properties and dimensions are known, the equation above still has 2
unknown variables As and act. Therefore, design of steel reinforcement for a given
beam is largely one of trial-and-error.
Beam Design
Design of concrete beam members is often one of trial-and-error. Its difficult
to directly solve for all the variables in a reinforced concrete beam. Usually,
material properties are known as well as maximum applied factored moment,
Mmax.
The following Table is useful to get a trial beam size:
Minimum Suggested Thickness h of Concrete Beams & One-Way Slabs
Member:
End Conditions
Simply
One end
Both ends
Cantilever
supported continuous
continuous
Solid one-way slab
L/20
L/24
L/28
L/10
Beam
L/16
L/18.5
L/21
L/8
Span length L = inches
Beams are usually rectangular having the width typically narrower than the
height. The diagram below shows typical beam aspect ratios:
b
h 1.5b 2.5b
Lecture 24 - Page 1 of 9
The design aid shown below is used for design or analysis. Values of
Lecture 24 - Page 2 of 9
Lecture 24 - Page 3 of 9
Example 1
GIVEN: A rectangular concrete beam with dimensions is shown below (stirrup bars
not shown). Use concrete fc = 4000 PSI and grade 60 bars.
REQUIRED:
1) Determine the usable moment capacity Mu of the beam using formula.
2) Determine the usable moment capacity Mu of the beam using Table 2.
b =12
d = 18
3 - # 7 bars
As
bd
act = 0.0083
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.0083)(60 KSI )
= 0.9(1.80 in2)(60 KSI)(18)(1 - 0.59
)
4 KSI
= 1621 KIP-IN
Mu = 135 KIP-FT
Lecture 24 - Page 4 of 9
Step 2 - Determine the usable moment capacity Mu of the beam using Table 2:
From Table 2:
At = 0.0083
Mu
= 461.4 PSI
bd 2
Lecture 24 - Page 5 of 9
Example 2
GIVEN: The concrete beam below. Use the following:
REQUIRED: Design the rectangular beam such that h 1.5b and act (max).
wu = 2 KLF
28-0
wu L2
8
(2 KLF )(28'0" ) 2
8
Lecture 24 - Page 6 of 9
Mu
= 581.2 PSI
bd 2
2352000
= 581.2 PSI
(0.9)(b)(1.5b) 2
Solve for b:
2352000
= 581.2 PSI
(0.9)(2.25b 3 )
b=3
2352000
(0.9)(2.25)(581.2)
b = 12.6 Use b = 12
d = 1.5b
= 1.5(12)
d 18
Lecture 24 - Page 7 of 9
As
bd
As
Area _ of _ one _ bar
2.36in 2
=
0.79in 2 _ per _#8 _ bar
= 2.99 bars USE 3 - #8 bars
Lecture 24 - Page 8 of 9
L
16
L
16
(28'0" )(12" / ft )
16
12
2 - #4 hanger
bars
20
#3 stirrup bars
@ 9 o.c.
concrete cover
3 - #8 main bars
Section A-A
Notes:
1) Concrete fc = 4000 PSI normal-weight
2) All bars ASTM A615 Grade 60
Lecture 24 - Page 9 of 9
Lecture 25 T- Beams
Concrete beams are often poured integrally with the slab, forming a much stronger
T shaped beam. These beams are very efficient because the slab portion
carries the compressive loads and the reinforcing bars placed at the bottom of the
stem carry the tension. A T-beam typically has a narrower stem than an ordinary
rectangular beam. These stems are typically spaced from 4-0 apart to more than
12-0. The slab portion above the stem is designed as a one-way slab spanning
between stems (see Lecture 26).
Slab
Overhang
width
bw
Clear distance
hf = Slab
thickness
bw
Lecture 25 - Page 1 of 9
Assuming T-beams are symmetrical, the following design dimensions are used:
8hf
or
(Clear distance)
(Beam span)
b = smaller
or
(2 x overhang width) + bw
T-Beam Analysis
T-beams are analyzed similarly to rectangular beams, except the
compression area is a narrow strip usually located in the slab.
a = Effective conc.
compressive
thickness
hf
Z = (d Ac = Shaded area
= Effective concrete
compression area
= (a)(b)
bw
Lecture 25 - Page 2 of 9
a
)
2
As = Total area of
main tension bars
a
2
Lecture 25 - Page 3 of 9
Example 1
GIVEN: A commercial building has T-beams spaced 6-6 (center-to-center) with a 4
concrete slab as shown in the framing plan and cross-section views below. Use the
following information:
Superimposed service floor dead load (NOT including conc. wt.) = 40 PSF
Superimposed service floor live load = 100 PSF
Concrete fc = 3000 PSI
ASTM A615 Grade 60 bars
REQUIRED:
1) Determine the maximum factored moment, Mmax, on the T-beam.
2) Determine the usable moment capacity, Mu, for the T-beam.
T-beam
6-6
Perimeter girder
Typ.
Framing Plan
Lecture 25 - Page 4 of 9
Column
6-6
4
16
2 - #9 bars
Section A-A Thru T-Beams
wu L2
8
(1.9 KLF )(20'0" ) 2
8
Mmax = 95 KIP-FT
Lecture 25 - Page 5 of 9
or
(Clear distance) = (78 8) = 35
or
(2 x overhang width) + bw = (2 x 32 + 8) = 72
T
0.85 f ' c
120 KIPS
0.85(3KSI )
= 47.1 in2
Lecture 25 - Page 6 of 9
47.1in 2
60"
a = 0.79
Z = Moment arm distance between center of
compression to center of tension
=d-
a
2
= 16 -
0.79"
2
Z = 15.6
Mu = TZ
= 0.9(120 KIPS)(15.6)
= 1685 KIP-IN
Mu = 140.4 KIP-FT
NOTE: Since Mu = 140.4 KIP-FT > Mmax = 95 KIP-FT, Tbeam is ACCEPTABLE.
Lecture 25 - Page 7 of 9
Heavily-Reinforced T-Beams
T-beams with a lot of tension reinforcement may have a portion of the effective
concrete area located within the stem as shown below:
b
hf
Ac = Shaded area
= Effective concrete
compression area
bw
As
Lecture 25 - Page 8 of 9
Example 2
GIVEN: The T-beam from Example 1.
REQUIRED: Determine the maximum area of tension steel permitted, As max:
Step 1 Determine As max:
From Example 1:
Concrete fc = 3000 PSI
Steel fy = 60 KSI
b = 60
hf = 4
bw = 8
As max = 0.0319[bhf + bw(0.503d hf)]
= 0.0319[(60)(4) + 8(0.503(16) 4)]
As max = 8.7 in2
NOTE: This area of tension steel As = 8.7 in2 is a LOT!! In order
to supply this much steel the beam would require 9 - #9 bars, 15
- #7 bars or 20 - #6 bars! It would be far better to change the
beam dimensions than to try to squeeze this many bars into the
beam.
Lecture 25 - Page 9 of 9
Tension bar
spacing
Slab span
The slab is designed as a series of 1-0 wide beam strips. The analysis
is similar to rectangular beams, except the width b = 12 and the height is
usually on the order of 4 10. The main tension bars are usually #4, #5
or #6 bars. There are no stirrups in slabs, however, additional bars are
placed perpendicular to the main tension bars to prevent cracking during
the curing process. These bars are referred to as shrinkage or
temperature bars and are also usually #4 or #5 bars.
Spacing reqd. for moment
or
3 x slab thickness
or
12
Spacing reqd. by analysis
Lecture 26 - Page 1 of 13
or
5 x slab thickness
or
18
Slab strip
Support
beam
d
Span
b = 12
Tension bars
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
Lecture 26 - Page 2 of 13
Example 1
GIVEN: A one-way slab has a simple span = 8-0 and the following materials
and loads:
REQUIRED: Design the slab, including thickness, main tension bars & shrinkage
bars.
Slab strip
Support
beam
h=?
d
Span = 8-0
b = 12
Tension bars
L
20
8'0" (12" / ft )
20
Lecture 26 - Page 3 of 13
b = 12
Lecture 26 - Page 4 of 13
Step 4 Using Design Aid Table 2 (see Lecture 24), determine As:
Determine the corresponding from
Mu
:
bd 2
Mu
30,720 LB IN
=
2
bd
(0.9)(12" )(4" ) 2
= 177.8 PSI
act =
As
bd
= 12
0.16in 2
= 15 apart
Lecture 26 - Page 5 of 13
= smaller of
= 12
0.12in 2
= 20 apart
Lecture 26 - Page 6 of 13
or
3 x slab thickness
or
12
15 (see prev. page)
or
3 x 5 = 15
or
12 USE
= smaller of
or
5 x slab thickness
or
18
#4 Tension rebar
placed at bottom
of slab
5
#4 Shrinkage bar
spacing = 18 o.c.
Tension bar
spacing = 12 o.c.
Lecture 26 - Page 7 of 13
Bars at top
w
R1
L
M pos =
R3
R2
9
( wL2 )
128
M pos =
9
( wL2 )
128
0.375L
0.375L
1
M neg = ( wL2 )
8
Lecture 26 - Page 8 of 13
Moment
Diagram
R2
R1
R4
R3
Mpos = 0.08(wL2)
Mpos = 0.08(wL2)
Mpos = 0.025(wL )
0.4L
0.4L
0.5L
Mneg = -0.1(wL2)
0.5L
Mneg = -0.1(wL2)
Rebar Placement:
At the transition between the Mpos and Mneg zones, a minimum overlap of
bars is required per ACI 318. These overlaps are required for developing
the full bar strength in tension. The friction developed between the
concrete and the ribs of the rebar must equal the tensile strength of the
bar. The necessary length of the bar embedment to achieve this friction
force is called the Development Length, Ld, and is specified as a multiple
of bar diameters. For example, the Ld for a Grade 60 rebar and concrete
fc = 4000 PSI = 38 x bar diameter.
Tensile Strength
Friction force
Lecture 26 - Page 9 of 13
Lecture 26 - Page 10 of 13
Example 2
GIVEN: A 1-0 wide strip concrete slab that is 6 thick and a 3-span condition
is shown below. All loads shown are already factored and includes slab weight.
Use concrete fc = 4000 PSI and Grade 60 bars. Use d = 5.
REQUIRED: Determine if the slab reinforcing steel is adequate for both the
positive moments and negative moments.
#4 @ 8 o.c.
bars at bottom
of slab
#5 @ 10 o.c.
bars at top of
slab
wu = 1.0 KLF
6
R2
R1
L = 9-0
L = 9-0
Mpos = 0.08(wL2)
0.4L
R3
L = 9-0
Mpos = 0.08(wL2)
Mpos = 0.025(wL )
0.4L
0.5L
Mneg = -0.1(wL2)
0.5L
Mneg = -0.1(wL2)
Lecture 26 - Page 11 of 13
6
8
b = 12
#4 @ 8 o.c. at
BOTTOM of slab
A _ per _ bar
= 12
8"
As
bd
0.30in 2
(12" )(5" )
= 0.005
Determine Mu by formula:
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.005)(60)
= 0.9(0.30 in2)(60 KSI)(5)(1 - 0.59
)
4 KSI
= 77.4 KIP-IN
Mu = 6.45 KIP-FT Mpos = 6.48 KIP-FT ACCEPTABLE
Lecture 26 - Page 12 of 13
d = 5
10
b = 12
#5 @ 10 o.c. at TOP
of slab
A _ per _ bar
= 12
10"
As
bd
0.37in 2
(12" )(5" )
= 0.0061
Determine Mu by formula:
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.0061)(60)
= 0.9(0.37 in2)(60 KSI)(5)(1 - 0.59
)
4 KSI
= 94.5 KIP-IN
Mu = 7.88 KIP-FT < Mneg = 8.1 KIP-FT NOT ACCEPTABLE
Lecture 26 - Page 13 of 13
Lecture 27 - Page 1 of 13
The following Table may be used to determine minimum thickness of various twoway slabs based on deflection:
Easy formwork
Simple bar placement
Low floor-to-floor heights
Lecture 27 - Page 2 of 13
The ACI 318 code allows a direct design method that can be used in most
typical situations. However, the following limitations apply:
1. Must have 3 or more continuous spans in each direction.
2. Slab panels must be rectangular with a ratio of the longer span to
shorter span(measured as centerline-to-centerline of support) not
greater than 2.0.
3. Successive span lengths in each direction must not differ by more than
1/3 of the longer span.
4. Columns must not be offset by more than 10% of the span (in direction
of offset) from either axis between centerlines of successive columns.
5. Loads must be uniformly distributed, with the unfactored live load not
more than 2 times the unfactored dead load (L/D < 2.0).
Design Strips
a) L1 > L2:
L2/4 L2/4
Column
(typ.)
Middle Strip
L2
Middle Strip
L2
L2/4
Lecture 27 - Page 3 of 13
L1
b) L2 > L1:
Middle Strip
L2
Middle Strip
L2
L1
L1/4
L1/4 L1/4
End Span
1
Mo =
wu L2 Ln
8
Interior Span
3
Lecture 27 - Page 5 of 13
Example 1
GIVEN: A two-way flat plate for an office building is shown below. Use the following:
Column dimensions = 20 x 20
Superimposed service floor Dead load = 32 PSF (not including slab weight)
Superimposed service floor Live load = 75 PSF
Concrete fc = 4000 PSI
#4 Grade 60 main tension bars
Concrete cover =
REQUIRED: Use the Direct Design Method to design the two-way slab for the
design strip in the direction shown.
L2 = 16-0
L2 = 16-0
L2 = 16-0
20-0
Ln
20-0
20-0
L2/4 L2/4
Middle strip
= (16 Col. strip)
Col. strip
Middle strip
= (16 Col. strip)
Design Strip = 16
Lecture 27 - Page 6 of 13
Ln
30
Column size
= 220 = 18.33
h=
220"
30
= 7.333
Use 8 thick slab
Step 2 Determine factored uniform load, wu on the slab:
wu = 1.2D + 1.6L
Slab weight
Lecture 27 - Page 7 of 13
wu L2 Ln
8
Mo = 188 KIP-FT
Step 5 Determine distribution of total factored moment into col. & middle strips:
b = 96
8
Lecture 27 - Page 8 of 13
Mu
586,800 LB IN
=
2
bd
(0.9)(96" )(7" ) 2
= 138.6 PSI
From Lecture 24 Table 2:
As
bd
As
As _ per _ bar
2.22in 2
0.20in 2 _ per _#4 _ bar
Lecture 27 - Page 9 of 13
= 165.2 PSI
From Lecture 24 Table 2:
Use = 0.0033
As = 2.22 in2 (see calcs. above)
Use 12 - #4 BOTTOM bars
Lecture 27 - Page 10 of 13
2 :
= 112.0 PSI
From Lecture 24 Table 2:
Use = 0.0033
As = 2.22 in2 (see calcs. above)
Use 12 - #4 BOTTOM bars
Use 6 - #4 Bottom bars at each Middle Strip
Lecture 27 - Page 11 of 13
16-0
16-0
16-0
20-0
20-0
20-0
4-0
Middle strip = 4-0
4-0
Col. strip
16 0
Lecture 27 - Page 12 of 13
Example 2
GIVEN: The two-way slab system from Example 1.
REQUIRED: Design the steel tension bars for design strip shown (perpendicular to
those in Example 1).
16-0
16-0
20-0
20-0
16-0
20-0
20-0
Lecture 27 - Page 13 of 13
Column
(typ.)
Cracking in beams is normal and indicates the tension bars are actually working.
Excessive cracking needs to be controlled by additional bars called stirrups
placed perpendicular to the cracks as shown below:
Lecture 28 - Page 1 of 9
Vu Vc
Lecture 28 - Page 2 of 9
d
2
If Vs < 4 f ' c bw d
then Max. stirrup spacing smax = smaller of
or
24
d
4
or
12
Av f y d
Vs
< Smax
Lecture 28 - Page 3 of 9
Example
GIVEN: A simply-supported concrete beam having the following: (Assume the
beam is adequate based on flexure)
wu = 5.6 KLF
(includes beam wt.)
Conc.
column
12 x 20 concrete
beam
20-0
12
#3 U-shaped
stirrup bars
d = 18
Beam Cross-Section
Lecture 28 - Page 4 of 9
h = 20
wu L
2
= 56 KIPS
d = 18
= 1.5
wu = 5.6 KLF
Vu = 47.6 KIPS
56 KIPS
0
d = 1.5
Vc = 0.75( 2 f ' c bw d )
= 0.75( 2 4000 PSI (12" )(18" )
= 20,492 Lbs.
= 20.5 KIPS
Lecture 28 - Page 5 of 9
Shear
Diagram
Vu = 47.6 KIPS
56 KIPS
-47.6 KIPS
-10.25 KIPS
Stirrups
required
d = 1.5
Stirrups
required
Vu Vc
Vs = 36.1 KIPS
Lecture 28 - Page 6 of 9
d = 1.5
d
18"
=
= 9
2
2
Then:
Max. stirrup spacing smax = smaller of
or
24
b) Check spacing requirement:
Av f y d
s=
Vs
Assumed shear
crack
< Smax
#3 U-shaped
stirrup bars
2 - #3 bars
spanning crack
Lecture 28 - Page 7 of 9
Vu = 47.6 KIPS
56 KIPS
-47.6 KIPS
-10.25 KIPS
d = 1.5
Stirrups
required
Stirrups
required
d = 1.5
12" / ft
5.6 KLF
+1
=
6" o.c.
Lecture 28 - Page 8 of 9
20-0
15 - #3 U-shaped stirrups
at ea. end of beam
Stirrup bar spacing = 6 o.c.
12
20
Beam Cross-Section
Lecture 28 - Page 9 of 9
REQUIRED: Determine the stirrup bar requirements. Assume only one spacing
for the beam.
25 KIPS
25 KIPS
25 KIPS
25 KIPS
wu = 1.2 KLF
Conc.
column
8-0
8-0
8-0
8-0
8-0
40-0
20
d = 32
#3 U-shaped
stirrup bars
Beam Cross-Section
Lecture 29 - Page 1 of 6
h = 34
25 KIPS
25 KIPS
25 KIPS
wu = 1.2 KLF
Conc.
column
8-0
8-0
8-0
8-0
8-0
40-0
74
64.4
29.8
39.4
4.8
NOTE: All
loads are in
Kips
-4.8
-29.8
-29.8
-39.4
32"
(1.2 KLF )
12" / ft
= 70.8 KIPS
Step 3 Determine shear capacity of concrete Vc:
Vc = 0.75( 2 f ' c bw d )
= 0.75( 2 4000 PSI (20" )(32" ))
= 60,716 Lbs.
Vc = 60.7 KIPS
Lecture 29 - Page 2 of 6
-74
25 KIPS
25 KIPS
25 KIPS
25 KIPS
wu = 1.2 KLF
8-0
8-0
8-0
8-0
8-0
Vu = 70.8
74
64.4
39.4
(Vc) = 30.4
29.8
4.8
Shear Diagram
-4.8
-29.8
32
-29.8
-39.4
-74
Stirrups reqd.
39.4kips 30.4kips
1.2kips _ per _ foot
= 7.5 feet
= 90
Lecture 29 - Page 3 of 6
Vu Vc
Vs = 13.5 KIPS
Step 6 Determine stirrup spacing, s:
a) Check if Vs < 4 f ' c bw d
13.5 KIPS < 4 4000 PSI (20" )(32" )
13.5 KIPS < 161,900 Lbs. YES
d
32"
=
= 16
2
2
Then:
Max. stirrup spacing smax = smaller of
or
24
Use
Lecture 29 - Page 4 of 6
Av f y d
s=
Vs
Assumed shear
crack
< Smax
2 - #3 bars
spanning crack
#3 U-shaped
stirrup bars
= 31.3 > 16
Use #3 Stirrup bars spaced 16 o.c.
Step 7 Determine number of stirrups required:
(96"32" ) + 90"
=
+1
16" o.c.
See shear
diagram
Lecture 29 - Page 5 of 6
40-0
11 - #3 U-shaped stirrups
at ea. end of beam
Stirrup bar spacing = 16 o.c.
20
34
Beam Cross-Section
Lecture 29 - Page 6 of 6
Trusses
Bracing
Hangers
The design of steel tension members is found in the following locations in the
LRFD Manual:
AISC Part 5
AISC SPEC Chapter D p. 16.1-26
AISC SPEC Chapter D p. 16.1-249
There are 2 types of failure mechanisms for tension members. The first is
yielding on the gross area and the second is fracture on the net section.
Yielding on Gross Area
Yielding on the gross area refers to stretching of the gross crosssectional area of the member:
The LRFD design strength for yielding on gross section in tension = tPn
P
The ASD allowable strength for yielding on gross section in tension = n
Lecture 3 - Page 1 of 7
Bolt holes
Material
thickness
The LRFD design strength for fracture on net section in tension = tPn
P
The ASD allowable strength for fracture on net section in tension = n
Lecture 3 - Page 2 of 7
Example 1 (LRFD)
GIVEN: The double-angle L4x4x A36 bracing member as shown below is
under a FACTORED tensile load of 54 kips. The angles are bolted to the steel
gusset plate using 2 diameter bolts.
REQUIRED:
1) Determine if the angles are acceptable based on yielding on gross area.
2) Determine if the angles are acceptable based on fracture on net area.
l = 3
FACTORED
Step 1 Determine LRFD design strength of member considering yielding:
Lecture 3 - Page 3 of 7
N.A.
N.A.
x
x
U = 1
l
where x = 1.08 see properties AISC p. 1-43
l = Connection length
= 3 (see sketch above)
1.08"
= 1
3"
= 0.64
Ae = AnU
= 3.47 in2(0.64)
= 2.22 in2
Design strength = 0.75(58 KSI)(2.22 in2)
= 96.6 KIPS
Since 96.6 KIPS > 54 KIPS member is acceptable
Lecture 3 - Page 4 of 7
W8 Bottom chord
15-0
22-0
22-0
L
rmin
300
264"
rmin
300
Required rmin > 0.88 in. looking at AISC p. 1-27, the smallest
W8 that will work is W8x18 with ry = 1.23 in. > rmin of 0.88 in.
Lecture 3 - Page 5 of 7
VertForce
HorzForce
=
VertLength HorzLength
100 KIPS HorzForce
=
15'0"
22'0"
Horz Force = 146.7 KIPS
Step 3 Design lightest W8 member considering yielding on gross area:
ASD Allowable strength for yielding =
Fy Ag
where: = 1.67
Fy = 50 KSI (see AISC p. 2-39)
Solve for Ag:
Ag >
>
146.7 kips()
Fy
146.7kips(1.67)
50 KSI
AISC p. 1-26
Fy Ag
Lecture 3 - Page 6 of 7
Step 5 Determine the allowable tensile yielding load on W8x18 using AISC Table 5-1:
ASD
W8x18
Allowable yielding
SERVICE tensile
load = 157 Kips
Lecture 3 - Page 7 of 7
Concrete
Rebar
T = Asfy
Ld
The development length is based upon the BOND between the rebar and the
concrete. Factors affecting this bond include the following:
Lecture 30 - Page 1 of 9
d b f y
25 f ' c
d b f y
20 f ' c
where:
db = diameter of bar
fy = yield strength of bar, PSI
fc = specified concrete compressive strength, PSI
= alpha
= Bar location factor
= 1.3 for top reinforcement
= 1.0 for all other locations
= beta
= Coating factor
= 1.5 for epoxy coated bars
= 1.0 for uncoated bars
= lambda
= Lightweight aggregate factor
= 1.3 for lightweight aggregate
= 1.0 for normal weight aggregate
Lecture 30 - Page 2 of 9
Example 1
GIVEN: A #6 rebar under tension force. Assume the following conditions:
d b f y
25 f ' c
6
(60,000 PSI )(1.0)(1.0)(1.0)
8
Ld =
25 4000 PSI
Ld = 28.5
Concrete
#6 Rebar
Ld = 28.5
Lecture 30 - Page 3 of 9
Condition
Clear spacing of
bars > db, clear
cover > db
Concrete fc
3000 PSI
4000 PSI
5000 PSI
3000 PSI
4000 PSI
5000 PSI
Example 2
GIVEN: The same information as Example 1.
REQUIRED: Using the table above, determine the Ld for a #6 bar.
Step 1 Use table above to determine Ld:
Concrete fc = 4000 PSI
Clear spacing of bars > db, clear cover > db
Lecture 30 - Page 4 of 9
Ld = 38db
= 38(6/8)
Ld = 28.5
db f y
f 'c
or
Ldc = 0.0003dbfy
Example 3
GIVEN: A #6 bar in compression. Use fc = 4000 PSI and Grade 60 bars.
REQUIRED: Determine the Ldc for the bar.
Ldc = Development length in compression
Ldc = 0.02
= larger of
db f y
f 'c
6
(60,000 PSI )
8
= 0.02
= 14.2 Use
4000 PSI
or
Ldc = 0.0003dbfy = 0.0003(6/8)(60,000 PSI) = 13.5
Ldc = 14.2
Lecture 30 - Page 5 of 9
Concrete
Ls
Lecture 30 - Page 6 of 9
Ldh = Lhb
Lecture 30 - Page 7 of 9
db
f 'c
Re quired _ As
Pr ovided _ As
Example 4
GIVEN: A #5 Grade 40 bar is in tension as shown below. Use LIGHTWEIGHT
concrete with fc = 4000 PSI.
REQUIRED: Determine the min. required hook dimensions X, Y and Z.
Z = Ldh
Side cover = 1
End cover = 1
Critical section
Lecture 30 - Page 8 of 9
db
f 'c
5
8"
= 1200
4000 PSI
= 11.9
Step 4 Determine total development length, Z = Ldh:
Ldh = Lhb
Where: = 1.0 since side cover = 1 < 2
= 1.3 since lightweight concrete
=
fy
60000 PSI
40000 PSI
= 0.67
60000 PSI
Ldh = Lhb
= 11.9(1.0)(1.3)(0.67)
Ldh = 10.4
Lecture 30 - Page 9 of 9
Lecture 31 Serviceability
Serviceability refers to the structural performance of the finished building under
service loads.
Beam deflection
Lateral drift
Vibration
We will be focusing our discussion on beam deflection. The ACI 318-02 Code
dictates that the deflections be checked on the basis of effective moment of
inertia, Ie, under service loads. Before we can determine the value of the
effective moment of inertia, we must first have an understanding of the gross
moment of inertia, Ig, and the cracked moment of inertia, Icr.
Gross Moment of Inertia Ig:
The gross moment of inertia is not appropriate for reinforced concrete
beams because the concrete under the neutral axis is in tension and is
ineffective. Since tension is carried by the steel rebar, the beam becomes
composite and therefore must be analyzed as such (See AECT 210
Lecture 6). The calculated value of gross moment of inertia is higher than
what is actually present.
b
bh 3
12
Lecture 31 - Page 1 of 7
y
N.A.
nAs
Icr =
by 3
+ nAs (d y ) 2
3
bd
nAs 1 + 2
1
nAs
y=
b
Lecture 31 - Page 2 of 7
M
Ie = cr
M a
3
M
I g + 1 cr
M a
I cr I g
h
2
Lecture 31 - Page 3 of 7
Example 1
GIVEN: A simply-supported rectangular beam is shown below. The loads
indicated are SERVICE loads. Use concrete fc = 4000 PSI and grade 60 bars.
REQUIRED:
1) Determine the gross moment of inertia Ig of the beam.
2) Determine the cracked moment of inertia Icr of the beam.
3) Determine the maximum allowable mid-span deflection of the beam
assuming allow = L/360.
4) Determine the actual mid-span deflection of the beam using Ie.
25-0
12
2 - #4 hanger
bars
20
#3 stirrup bars
@ 9 o.c.
concrete cover
3 - #8 main bars
Section A-A
Lecture 31 - Page 4 of 7
bh 3
Ig =
12
=
(12" )(20) 3
12
Ig =8000 in4
Step 2 Determine cracked moment of inertia Icr:
Icr =
by 3
+ nAs (d y ) 2
3
Where: n = Modular ratio
E
29,000,000 PSI
29,000,000 PSI
=
= steel =
E conc
57,000 f ' c
57,000 4000 PSI
= 8.04
As = Area of steel rebar in tension, in2
= 3 bars(0.79 in2 per #8 bar)
= 2.37 in2
bd
nAs 1 + 2
1
nAs
y=
b
(12" )(18.375" )
1
(8.04)(2.37in 2 ) 1 + 2
2
(8.04)(2.37in )
=
12"
= 6.2
Lecture 31 - Page 5 of 7
Icr =
by 3
+ nAs (d y ) 2
3
(12" )(6.2" ) 3
+ 8.04(2.37in 2 )(18.375"6.2" ) 2
3
allow =
L
360
(25'0" )12" / ft
360
allow = 0.83
Step 4 - Determine the effective moment of inertia Ie:
fr = modulus of rupture for the concrete
= 7.5 f ' c
= 7.5 4000 PSI
= 474.3 PSI
Mcr = moment that would initially crack the section
fr I g
=
yt
=
= 379,473 Lb-In
= 379.4 KIP-In
= 31.6 KIP-FT
Lecture 31 - Page 6 of 7
wL2
8
(1.5KLF )(25'0" ) 2
8
Ma = 117.2 KIP-FT
M
Ie = cr
M a
3
M
I g + 1 cr
M a
I cr
31.6 3
31.6 3
4
4
=
(
8000
in
)
+
(2904in ) I g
1
117.2
117.2
Ie = 3004 in4
Step 5 Determine actual mid-span deflection using Ie:
5wL4
act =
384 E conc I e
1500 PLF
4
5
(25'0" x12" / ft )
12
=
384(57000 4000 PSI )(3004in 4 )
act = 1.22
Since act = 1.22 > allow = 0.83 member is NOT acceptable
Lecture 31 - Page 7 of 7
Lecture 33 Columns
Concrete Columns:
Concrete is good at resisting compression but poor in resisting tension.
So, it might make sense that concrete would be the material of choice for
columns. It is true that concrete IS used for compression members such
as columns, piers, bearing walls and pedestals. Members under pure
compression could then (theoretically) be unreinforced. These members
are often subject to additional forces such as moment that would put some
tensile forces into the member and would thus necessitate the addition of
tension reinforcement.
Most columns have combined compression and bending. They are
essentially a beam-column. The compression capacity of a reinforced
column is reduced by the bending stresses on the column and vice-versa.
A graph of the axial load capacity of a column vs. the moment capacity of
a typical column is shown below:
Pure compression
Pure bending
Bending moment capacity
Lecture 33 - Page 1 of 14
Unconfined core
Insufficient ties
Lecture 33 - Page 2 of 14
A confined concrete core will carry substantially more load and will NOT
explode outward like the unconfined concrete section will.
Load
Load
Minor concrete
spalling, core
remains intact
Confined core
Tied Column:
A Tied concrete column is one in which individual rebar ties are used to
wrap completely around the vertical bars to confine the interior core.
These ties are usually #3 or #4 bars spaced per ACI requirements:
Least column dimension
Tie Spacing = smaller of
Lecture 33 - Page 3 of 14
Vertical bars (4
minimum)
Tie bars
Tie spacing
Concrete
Lecture 33 - Page 4 of 14
Spiral Column:
A spiral column has a single rebar wrapped around the vertical bars in a
spiral and is stronger than a comparable tied column. It is more laborintensive to build than a tied column. The ACI requires a minimum of 6
vertical bars, with the same minimum and maximum areas of steel as a
tied column.
Concrete
Pitch =
1 3
Spiral rebar
Spiral columns have greater ductility than a tied column. This means that
a spiral column is capable of sustaining larger strain before failure than a
tied column. For this reason, spiral columns are used in areas with
high seismicity to prevent brittle failures. The stress-strain curve below
shows the relative yield strength of a tied column and a spiral column are
similar, however the strain capacity of the spiral column is much greater
than that of a tied column.
Spiral column
Yield
Stress
Fracture
Fracture
Tied column
Strain
Lecture 33 - Page 5 of 14
Pu
Side view of
column
= Small
= Large
Lecture 33 - Page 6 of 14
e
0.10
h
e
0.10
h
Lecture 33 - Page 7 of 14
Spiral requirements:
Ag
f'
1 c
Ac
fy
s = 0.45
s=
4 As (d c d b )
sdc2
where: s = ratio of spiral bar to gross area
s = spacing of spiral bends (pitch), in
Ag = gross area of column, in2
Ac = area of core, in2
= area measured out-to-out of spiral
As = area of spiral bar, in2
dc = diameter of core measured out-to-out of spiral
db = diameter of spiral bar
Lecture 33 - Page 8 of 14
Example 1
GIVEN: A 16 x 16 square tied concrete column has an applied factored axial
load Pu = 300 KIPS and an applied factored moment Mu = 35 KIP-FT. In
addition, use the following:
REQUIRED:
1) Determine the eccentricity e and state whether or not it is considered to
be small eccentricity.
2) Determine the required tie spacing.
3) Determine if the vertical bars are acceptable based on ACI requirements.
4) Determine the usable axial strength of the tied column, Pn, and state
whether or not it is acceptable.
16
16
8 - #7 vertical bars
Step 1 Determine eccentricity and whether it is small.
Eccentricity e =
M u (12" / ft )
Pu
35 KIP FT (12" / ft )
300 KIPS
e = 1.4
Small eccentricity if e/h < 0.10
e/h = 1.4/(16)
e/h = 0.0875 it is small eccentricity
Lecture 33 - Page 9 of 14
Pn = 594 KIPS
Since Pn = 594 KIPS > 300 KIPS column is acceptable
Lecture 33 - Page 10 of 14
Example 2
GIVEN: A 14 diameter spiral column has a factored axial load Pu = 400 KIPS
and a factored moment = 45 KIP-FT. In addition, use the following:
REQUIRED:
1) Determine the eccentricity e and state whether or not it is considered to
be small eccentricity.
2) Determine the required spiral pitch.
3) Determine the usable axial strength of the spiral column, Pn, and state
whether or not it is acceptable.
Lecture 33 - Page 11 of 14
M u (12" / ft )
Pu
45 KIP FT (12" / ft )
400 KIPS
e = 1.35
e
< 0.10
h
Small eccentricity if
e
1.35"
=
h
14"
e/h = 0.096 it is small eccentricity
Step 2 Determine the required spiral pitch s:
f'
Ag
1 c
fy
Ac
s = 0.45
where: Ag =
(Outside _ Dia ) 2
Pitch
(14" ) 2
Ag = 153.9 in2
Ac =
(Core _ Dia ) 2
(11" ) 2
Ac = 95.0 in2
Lecture 33 - Page 12 of 14
f'
Ag
1 c
fy
Ac
s = 0.45
4 KSI
153.9in 2
1
2
60 KSI
95.0in
s = 0.45
s = 0.0186
Pitch = s
s=
4 As (d c d b )
sdc2
3
4(0.11in 2 )(11" " )
8
s=
(0.0186)(11" ) 2
Pitch s = 2.08
Use pitch = 2
Lecture 33 - Page 13 of 14
Step 3 - Determine the usable axial strength of the spiral column, Pn:
Since e/h < 0.10 then the formula can be used:
Pn = 513 KIPS
Since Pn = 513 KIPS > 400 KIPS column is acceptable
Lecture 33 - Page 14 of 14
The analysis of such a frame is usually quite complex and requires computer
software such as STAAD or approximate analysis methods such as the Portal
Method and others discussed in AECT 210 Structural Theory Lecture 17.
Lecture 34 - Page 1 of 12
Determining points along the curve is quite laborious and typically not done using
hand calculations. Instead, computer programs or design guides are used to
perform column analysis and design.
Below are some Column Interaction Diagrams that are used for column
analysis and design.
Lecture 34 - Page 2 of 12
Lecture 34 - Page 3 of 12
Lecture 34 - Page 4 of 12
KL
22
rmin
Lecture 34 - Page 5 of 12
Example
GIVEN: A 20 x 20 square interior tied column is shown below. Use concrete fc
= 4000 PSI and 8 - #8 grade 60 vertical bars and #3 ties. Concrete cover = 1.
All loads are factored and includes beam weight. Assume the moment from the
2
w L
beams acting on the column is u n where Ln = clear span of attached beam,
12
and wu = factored unif. load.
REQUIRED:
1) Determine the applied factored axial load, Pu on the middle column. Be
sure to add column weight. Assume the loads from the roof above are
75% of the floor load.
KL
2) Determine the slenderness ratio
using K = 0.7 and determine if
rmin
column qualifies as short.
3) Determine total factored moments Mtotal applied to the column.
4) Determine if the column is acceptable based on Column Interaction
Diagram.
22-0
46 K
46 K
wu = 2.5 KLF
wu = 1.7 KLF
14-0
30-0
Beam 1
Beam 2
20 x 20 Middle
column
Lecture 34 - Page 6 of 12
Step 1 Determine the total factored axial load, Pu on the middle column:
a) Beam 1:
End reaction = (46 K + 46 K + 1.7 KLF(22-0))
= 64.7 KIPS
b) Beam 2:
End reaction = (2.5 KLF(30-0))
= 37.5 KIPS
c) Column weight:
Weight =
20" x 20"
(14'0" )(150 PCF )
144in 2 / ft 2
= 5833 Lbs.
= 5.8 KIPS
Total Pu = 1.75(64.7 KIPS + 37.5 KIPS + 5.8 KIPS)
Total Pu = 189 KIPS
Step 2 - Determine the slenderness ratio
KL
using K = 0.7:
rmin
(0.7)(14'0" x12" / ft )
KL
=
rmin
0.3(20" )
KL
= 19.6
rmin
Since KL/rmin < 22 it is a short column
Lecture 34 - Page 7 of 12
46 K
wu = 1.7 KLF
Ln = 20.33
w L
To determine Mmax = u n we must convert point loads into
12
equivalent uniform load wu. From AISC LRFD Manual p. 5160:
Lecture 34 - Page 8 of 12
wu = wuniform + wpoint
= 1.7 KLF +
fP
L
= 1.7 KLF +
2.667(46 KIPS )
22'0"
= 7.3 KLF
Lecture 34 - Page 9 of 12
Mmax =
wu Ln
12
7.3KLF (20.33' ) 2
12
30-0
wu = 2.5 KLF
Ln = 28.33
w L
Mmax = u n
12
=
2.5KLF (28.33' ) 2
12
Lecture 34 - Page 10 of 12
M total (12" / ft )
Pu
84 KIP FT (12" / ft )
189 KIPS
e = 5.33
e 5.33"
=
h
20"
e
= 0.27 > 0.10 CANNOT use small eccentricity formula
h
b) Determine :
h = 20
X
20
8 - #8 vertical bars
X = concrete cover + stirrup dia. + (vert. bar dia.)
= 1 + + (8/8)
= 2.375
h = 20 (X + X)
= 20 (2.375 + 2.375)
= 15.25
(20) = 15.25
= 0.76 USE = 0.75
Lecture 34 - Page 11 of 12
Pn
Ag
Pn
Ag
Pn
Ag
Pu
Ag
189 KIPS
20" x 20"
= 0.47 KSI
e Pu e
x
=
h Ag h
= (0.47 KSI)(0.27)
Pn
Ag
e
= 0.13 KSI
h
g =
As
Ag
2
= 8 _ bars (0.79in _ per _#8 _ bar )
20" x 20"
Lecture 35 - Page 1 of 9
Soil Type:
Bedrock
Sedimentary and foliated rock
Sandy gravel and/or gravel
12,000 PSF
4,000 PSF
3,000 PSF
Sand, silty sand, clayey sand, silty gravel, clayey gravel
2,000 PSF
Clay, sandy clay, silty clay, clayey silt, silt, sandy silt
1,500 PSF
Organics, peat, top soil
NOT Recommended for use
as footing bearing
* = An increase of one-third is permitted when using alternate load combinations in
IBC Section 1605.3.2 that include wind or earthquake loads.
Example
GIVEN: An 8 wide load-bearing poured-in-place concrete wall is to bear on a
wall footing with the following:
Lecture 35 - Page 2 of 9
2-0
1-0
Finished grade
qe
qe = qa (ftg. wt.) (soil wt.)
= 3000 PSF (1-0 thick(150 lb/ft3)) + ((2-0 thick(110 lb/ft3))
= 3000 PSF 150 PSF 220 PSF
qe = 2630 PSF
Lecture 35 - Page 3 of 9
qe = 2630 PSF
Footing width = wf
Footing width = wf =
wf =
Ptotal
qe
14000 PLF
2630 PSF
wf = 5.32 feet
USE footing width = 5-6
Lecture 35 - Page 4 of 9
qu = 3490 PSF
Step 5 Determine minimum depth of footing, dmin based on shear:
Footing
thickness
#5 bar
d = footing thickness concrete cover (Bar dia.)
= 12 3 (5/8)
= 8.69
w f Wall _ Width d
Vu = qu
2
2
2
8.69"
8"
2
2
2
Vu = 7170 Lbs.
Lecture 35 - Page 5 of 9
Vu
(0.85)2 f ' c (12" )
7170 Lbs.
(0.85)2 3000 PSI (12" )
Point A
qu = 3490 PSF
Isolate footing
overhang and treat
as if it were a
cantilevered beam
MA = Moment at point A
Footing _ overhang
= qu(Footing overhang)
2.42'
= 3490 PSF(2.42)
2
MA = 10,219 FT-LB
Lecture 35 - Page 6 of 9
Lecture 35 - Page 7 of 9
Spacing = 12" s
As
= 12"
0.34in 2
= 10.9
Use #5 bars spacing = 10 o.c.
Step 9 Determine longitudinal shrinkage/temperature bars:
h = 12
As temp = 0.0018bh
= 0.0018(5.5 x 12/ft)(12)
= 1.43 in2
Number of bars =
As
As _ per _ bar
1.43in 2
0.20in 2 _ per _#4 _ bar
= 7.15 bars
Use 8 - #4 longitudinal temperature/shrinkage bars
Lecture 35 - Page 8 of 9
3-0 minimum
8 poured-in-place
conc. wall centered
over footing
8 - #4 longitudinal bars
3 conc. cover
12
#5 bars @ 10 o.c.
NOTES:
1)
2)
3)
4)
Finished grade
5-6
Lecture 35 - Page 9 of 9
Lecture 36 - Page 1 of 8
Example
GIVEN: A steel column rests on a 12 x 12 base plate and has the following:
REQUIRED: Design the square concrete footing, including all dimensions and
bars. Provide a Summary Sketch showing all information necessary to build it.
Step 1 Determine Trial footing thickness:
Assume footing thickness 1(Column Width OR Base Plate Width)
1(12)
TRY Footing Thickness = 15
Step 2 Determine effective soil bearing qe:
qe = effective soil bearing pressure
= reduced soil bearing due to wt. of footing & soil above footing
= qa (wt. of footing) (wt. of soil)
Soil overburden
2-9
1-3
Finished grade
qe
qe = 4000 PSF (1.25(150 PCF)) (2.75(100 PCF))
= 3538 PSF
= 3.5 KSF
Lecture 36 - Page 2 of 8
Ptotal
qe
PDEAD + PLIVE
qe
= 62.9 ft2
Length x Width = 62.9 ft2
Since Length = Width
(Length)2 = 62.9 ft2
Length = 7.93 feet
Use 8-0 x 8-0 square footing Area = 64 ft2 > 62.9 ft2
Step 4 Determine bearing pressure for strength design, qu:
qu =
qu = 4.75 kips/ft2
Lecture 36 - Page 3 of 8
Footing
thickness = 15
#7 bar
d = Footing thickness (concrete cover) (bar diameter)
= 15 3 (7/8)
= 11.56
Step 6 Determine d required to resist 2-way punching shear:
Footing
thickness = 15
d
2
Col.
width
bo
4
bo
d
= col. width + 2( )
4
2
= 12 + 2(
11.56"
)
2
Lecture 36 - Page 4 of 8
d
2
b
= qu(Footing area - o )
4
= 285.8 KIPS
= 285,800 Lbs.
dreqd = required depth to tension steel for shear
=
Vu 2
(0.85)4 f ' c bo
285,800 Lbs.
(0.85)4 3000 PSI (94.24" )
dreqd = 16.3
Since dreqd = 16.3 > 11.56 must increase footing
thickness
Revised footing thickness = h = dreqd + 3 + (7/8)
= 16.3 + 3 + (7/8)
= 19.73
Revised footing thickness = 20
Lecture 36 - Page 5 of 8
Column
baseplate
8-0
12
3-6
3-6
8-0
Mu = (Footing width)(qu)
= (8-0)(4.75KSF)
( Footing _ Overhang ) 2
2
(3.5' ) 2
2
= 232.8 Kip-Ft
Lecture 36 - Page 6 of 8
Mu
=
bd 2
232.8Kip Ft (12000
Lb Inch
)
Kip Ft
d
= 117.9 PSI
From Lecture 24 Table at fc = 3000 PSI use min = 0.0033
since 117.9 PSI < 190.3 PSI.
As = bd
= (0.0033)(8-0 x 12/ft)(16.56)
As = 5.25 in2
Step 9 Determine tension bar layout:
Number of bars =
As
As _ per _ bar
5.25in 2
=
0.60in 2 _ per _#7bar
= 8.75 bars
Use 9 - #7 bars both ways at bottom of footing
Lecture 36 - Page 7 of 8
4-0 minimum
Steel column on 12 x 12
base plate centered over
footing
3 conc. cover
20
NOTES:
1)
2)
3)
4)
5)
Finished grade
8-0
Lecture 36 - Page 8 of 8
Load-bearing Wall
Lecture 37 - Page 1 of 7
tw
6
or
18
where: = 0.70
fc = specified concrete strength, PSI
K = end fixity of walls
= 1.0 for pinned-pinned
= 0.70 for fixed-pinned
Ag = Gross effective area of wall section, in2
= Leff x tw
Lu = unbraced height of wall, inches
tw = thickness of wall, inches
Lecture 37 - Page 2 of 7
Example
GIVEN: A poured-in-place concrete wall supports W18x35 steel beams spaced
6-0 apart and rests on 10 wide steel bearing plates. Use the following:
Beam end reaction = 22 KIPS Service Dead Load (Not incl. wall wt.)
= 15 KIPS Service Live Load
Wall
Lu = 13-0
10 bearing
plate
Wind = 25 PSF
Steel beam
Fin. Grade
Slab on grade
Lecture 37 - Page 3 of 7
4
7 Largest
wL2
8
(25PSFx1'0" )(13' ) 2
=
8
Mwind = 528 Ft-Lb per 1-0 length of wall
= 528 Ft-Lb(6-0) for beam spacing
= 3168 Ft-Lb per 6-0 length of wall
Step 3 Determine the maximum SERVICE vertical load on wall Ptotal:
Ptotal = PDEAD + PLIVE
= (PDEAD + wall weight) + PLIVE
8"
Lecture 37 - Page 4 of 7
M
P
3.168Kip Ft (12" / ft )
44.8KIPS
= 0.85 inches
The empirical design method dictates that e <
tw
8"
=
6
6
tw
6
Wall thickness
tw
= 1.33 > 0.85 OK to use Empirical Design Method
6
Lecture 37 - Page 5 of 7
(1.0)(13' x12" / ft ) 2
= 0.55(0.70)(4000 PSI )(336in ) 1
32(8" )
2
spacing = 12
0.115in 2
= 32.3
3tw = 3(8) = 24
Maximum bar spacing = smaller of
or
18 USE
Lecture 37 - Page 6 of 7
spacing = 12
0.192in 2
= 19.4
3tw = 3(8) = 24
or
18 USE
USE #5 horizontal bars @ 18 o.c.
Step 9 Draw Summary Sketch:
18
Lu = 13-0
#5 @ 18 ea.
way
Slab on grade
NOTES:
Fin. Grade
Lecture 37 - Page 7 of 7
Lecture 39 - Page 1 of 12
Dead end
Casting bed
Live end
Prestress
force Ps
Step 1
Step 2
Hardened concrete
Prestress
force Ps
Tendons released at Live end
and Dead end creating an
axial force along length of
precast member
Lecture 39 - Page 2 of 12
Step 3
Tendons tensioned
between bulkheads
Prestress
force Ps
Dead end
Live end
Step 1
Tendons creating an
upward force along
length of member
Tendons anchored at
Live end
Dead end
Step 2
Lecture 39 - Page 3 of 12
Ps Ps ey
Ag
Ig
Mu = 0.9Apsfps(dp -
a
)
2
p
f pu
fps = f pu 1 p
'
f
c
1
fpu = ultimate tensile strength of prestressing tendon
A ps
bd p
Lecture 39 - Page 4 of 12
a=
A ps f ps
0.85 f ' c b
b
yt
h
dp
N.A.
e
yb
Aps
Rectangular Prestressed Beam
Lecture 39 - Page 5 of 12
Example
GIVEN: The rectangular prestressed concrete beam as shown below. Use the
following:
REQUIRED:
1) Determine the location of the neutral axis and prestress eccentricity e.
2) Determine the moment of inertia about the neutral axis, Ig.
3) Determine the stresses during prestressing.
4) Determine the stresses during initial applied service beam weight.
5) Determine the stresses due to service applied dead load + live load.
6) Determine the final stresses due to all service loads and prestressing.
7) Determine the maximum actual factored moment on the beam Mmax.
8) Determine the factored usable moment capacity Mu of the beam.
22-0
10
yt
18
16
N.A.
e
yb
Datum
18/2 = 9
yt
dp =16
h = 18
e
Yb
n=
E steel
E conc
29,000,000 PSI
57,000 f ' c
= 7.2
nAps = 7.2(0.459 in2)
= 3.30 in2
Lecture 39 - Page 7 of 12
Step 2 - Determine the moment of inertia about the neutral axis, Ig:
2
bh 3
h
+ bh y t + nA ps (e) 2
Ig =
12
2
(10" )(18" ) 3
18"
2
2
+ (10" )(18" ) 9.13"
+ (3.30in )(6.87" )
12
2
Ps Ps ey
Ag
Ig
where: Ps = prestress force
= 70%(fpu)(Aps)
= 0.70(270 KSI)(0.459 in2)
= 86.8 KIPS
y = yt for tensile stresses at top of beam
= yb for compressive stresses at bottom of beam
Ps Ps ey t
+
Ag
Ig
Lecture 39 - Page 8 of 12
Ps Ps eyb
Ag
Ig
(10" x18" )
5018.7in 4
M beam ( y )
Ig
where: Mbeam = maximum unfactored moment due to beam wt.
=
wbeam ( L) 2
8
(188PLF )(22'0" ) 2
8
= 11,374 Lb-Ft
= 11.4 KIP-FT
y = yt for compression in top
= yb for tension in bottom
a) Check stresses at TOP:
ftop =
M beam ( y t )
Ig
(11.4 KIP FT (12" / ft ))(9.13" )
5018.7in 4
ftop = -0.25 KSI Compression
Lecture 39 - Page 9 of 12
b)
= +
M beam ( y b )
Ig
Step 5 - Determine the stresses due to service applied dead load + live load:
f=
M DL + LL ( y )
Ig
where: MDL+LL = maximum unfactored moment due to DL+LL
=
wDL + LL ( L) 2
8
M DL + LL ( y t )
Ig
Lecture 39 - Page 10 of 12
= +
M DL + LL ( y b )
Ig
Step 6 - Determine the final stresses due to all service loads and prestressing:
-0.48C
18
+1.08T
-0.48C
Ps
Ag
-0.25C
-1.05C
+ Ps ey
Ig
+0.35T
+0.24T
Beam Wt.
-2.51C
-2.16C
-1.29C
+2.44T
+1.15T
Transfer
DL + LL
Final
Initial Prestress
wu L2
Mmax =
8
wu = 1.2D + 1.6L
= 1.2(400 PLF + 188 PLF) + 1.6(1500 PLF)
= 3106 PLF
= 3.1 KLF
Mmax =
3.1(22'0) 2
8
f
'
c
1
fpu = ultimate tensile strength of prestressing tendon
= 270 KSI
A ps
bd p
0.453in 2
(10" )(16" )
= 0.00283
0.40
270 KSI
fps = 270 KSI 1
(0.00283)
5KSI
0.80
= 249.4 KSI
a=
A ps f ps
0.85 f ' c b
(0.453in 2 )(249.4 KSI )
0.85(5 KSI )(10" )
= 2.66
Mu = 0.9Apsfps(dp -
a
)
2
2.66"
)
2
= 1492 Kip-In
Mu = 124.3 KIP-FT < Mmax = 188 KIP-FT NOT ACCEPTABLE
Lecture 39 - Page 12 of 12
AISC Part 3
AISC Spec Chapter F p. 16.1-44
Concrete slab
over metal
decking
Lecture 4 - Page 1 of 12
Mn
b
Where: b = 1.67
Mn = nominal flexural moment
= Mp = Plastic moment
= FyZx
Zx = plastic section modulus
= from properties
Example 1 (LRFD)
GIVEN: A W16x26 steel beam using A992 steel is continuously laterally
braced, and experiences a FACTORED moment = 104 KIP-FT.
REQUIRED:
1) Determine the design flexural moment, bMn for the beam.
2) Determine if the beam is adequate.
Step 1 Determine bMn for the beam:
bMn = 0.90(FyZx) since it is continuously laterally braced
= 0.90(50 KSI)(44.2 in3)
= 1989 KIP-IN
From properties,
bMn = 165.8 KIP-FT
AISC p. 1-21
Step 2 Determine if the beam is adequate:
Since bMn = 165.8 KIP-FT > 104 KIP-FT beam is adequate
Example 2 (LRFD)
GIVEN: The W16x26 beam from Example 1.
REQUIRED: Determine the design flexural moment, bMn for the beam
using the LRFD Zx Table 3-2 (see AISC p. 3-11 thru 3-19)
Step 1 Refer to AISC p. 3-18 for W16x26:
Look in the LRFD column bMpx = 166 KIP-FT
Lecture 4 - Page 2 of 12
Example 3 (ASD)
GIVEN: An A992 steel beam A is continuously laterally braced and
carries a superimposed SERVICE (i.e., not factored) floor live load = 100
PSF and a superimposed SERVICE dead load = 85 PSF. Assume initially
the beam weighs 30 PLF and check your results.
REQUIRED:
1) Design the lightest weight steel beam using the Zx Table 3-2.
2) Design the lightest weight W14 steel beam using the Maximum Total
Uniform Load Table 3-6 (see AISC p. 3-33 thru 3-95).
Beam A
3@7-0 = 21-0
Girder A
32-0
Lecture 4 - Page 3 of 12
Assumed
beam wt.
R2 = 21.2 KIPS
32-0
wL2
Ma =
8
=
Ma = 169.6 KIP-FT
Step 3 Select lightest weight beam from Table 3-2:
From AISC p. 3-17 look under ASD column
M px
to find a
b
BOLD moment that is equal or larger than the calculated Ma:
Use W16x40
M px
b
Lecture 4 - Page 4 of 12
Lecture 4 - Page 5 of 12
Moment capacity
Distance between
lateral supports
Lecture 4 - Page 6 of 12
The AISC has developed graphs of LRFD and ASD beam design
Mn
moments, bMn, and
respectively, for beam shapes that has been
b
mathematically altered from the graph above (for simplicity), and looks like
the following: (See AISC p. 5-7 and AISC p. 16.1-33)
Moment capacity
bMp and
bMr and
Real curve
Mp
b
AISC curve
Mr
b
Lp
Lr
Distance between
lateral supports
Where: b = 0.90 (LRFD)
b = 1.67 (ASD)
E
Fy
AISC p. 16.1-48
E
0.7 Fy
AISC p. 16.1-48
Lp = 1.76ry
Lr = rts
E = 29000 KSI
Fy = yield stress, KSI
Mp = (FyZx)
AISC p. 16.1-47
Mr = 0.7(FySx)
AISC p. 16.1-269
Lecture 4 - Page 7 of 12
Example 4 (LRFD)
GIVEN: A W14x43 steel girder using A992 steel. It is laterally braced at
Lb = 8-0 increments by beams framing into the side. It experiences a
maximum FACTORED moment, Mu = 250 KIP-FT.
REQUIRED:
1) Draw the graph of design moments vs. unbraced length.
2) Determine the design moment, bMn for an actual unbraced length Lb =
10-0 using formula F2-2 from AISC p. 16.1-47.
3) Determine the design moment using the Beam Available Moments vs.
Unbraced Length graphs on AISC p. 3-125.
Step 1 Draw graph of design moments vs. unbraced length:
From AISC p. 3-17, pick values of Lp, Lr, bMp, and bMr
Real curve
AISC curve
bMn = ????
bMrx = 164 KIP-FT
Lp = 6.68 ft.
Lr = 20.0 ft.
Lb = 10-0
Lb L p
Mn = C b M p ( M p 0.7 Fy S x )
L L
r
p
Lecture 4 - Page 8 of 12
10'6.68'
Mn = 1.0 3480 Kip In ((3480 0.7(50 KSI )(62.6in 3 )
)
20'6.68'
= 3159 Kip-In
= 263.3 Kip-Ft
Therefore, since = 0.9:
Mn = 0.9(263.3 Kip-Ft)
Mn = 237 Kip-Ft
Since Mn = 237 Kip-Ft < Mu = 250 Kip-Ft, beam is
UNACCEPTABLE
Lecture 4 - Page 9 of 12
Mn 237 Kip-Ft
Lb = 10-0
Lecture 4 - Page 10 of 12
30-0
Lecture 4 - Page 11 of 12
LRFD:
Mn
316 Kip ft
Lecture 4 - Page 12 of 12
Design Drawings
Specifications
The Design Drawings graphically present the specific design of the structure. However, they do not
indicate the specific requirements relating to:
Materials
Submittals
Job conditions
Testing & inspection
Execution of work
Each division has been further refined into multiple sub-divisions (as shown for Division 3 above).
To obtain samples of specifications, go to http://www.ogs.state.ny.us/dnc/masterspec/default.htm
In addition to technical specifications, the CSI MasterFormat is used by most of the construction
industry for purposes of cost estimating, contractor qualifications, product research and supply
ordering.
Lecture 40 - Page 1 of 14
SUMMARY
A. Work Included: Cast-in-place concrete.
1.2
QUALITY ASSURANCE
A. Comply with the latest edition of the following:
1. ACI 301 "Specifications for Structural Concrete for Buildings"
2. ACI 302 "Guide for Concrete Floor and Slab Construction"
3. ACI 304 "Recommended Practice for Measuring, Mixing, Transporting, Placing
Concrete"
4. ACI 305 "Hot Weather Concreting"
5. ACI 306 "Cold Weather Concreting"
6. ACI 311 "Recommended Practice for Concrete Inspection"
7. ACI 315 "Details and Detailing of Concrete Reinforcement"
8. ACI 318 "Building Code Requirements for Reinforced Concrete"
9. ACI 347 "Recommended Practice for Concrete Formwork"
10. ACI SP-15 Field Reference Manual
11. CRSI
"Manual of Standard Practice"
1.3
SUBMITTALS
A. Shop Drawings: Submit Shop Drawings for fabrication, bending and placement of
concrete reinforcement. Show bar schedules, stirrup spacing, diagrams of bent bars,
arrangements of concrete reinforcement. Include special reinforcement required for
openings through concrete. Show elevations of reinforcement for all members at
minimum 1/4 inch = 1'-0" scale. Show locations all construction and control joints.
B. Mix Design: Submit proposed mix designs for concrete at least 15 days before start of
concreting. Submittal shall include: cement content and type, admixture content and
type, aggregate source and gradation, water content, air content, slump, and
documentation of average strength by field experience or laboratory prepared trial
mixtures in accordance with ACI 318 Article 4.3.
C. Product Data: Submit data and installation instructions for proprietary material.
D. Material Certificates: Submit materials certificates certifying that each material
complies with Specifications.
1.4
TESTING SERVICES
A. Employ, at Contractor's expense, a testing laboratory acceptable to Architect to
perform material evaluation tests and for quality control during placement.
Lecture 40 - Page 2 of 14
B. Sample and test concrete for quality control during placement as follows:
1. Sampling Fresh Concrete: ASTM C172 except modified for slump to comply
with ASTM C94.
2. Slump: ASTM C143 - one for each concrete truck, measured at point of
discharge.
3. Air Content: ASTM C231 pressure method - one for each truck load of readymixed air-entrained concrete.
4. Temperature: Test concrete temperature hourly when ambient temperature is
40oF and below, and when 80oF and above.
5. Compressive Test Specimen: ASTM C31, one set of six standard cylinders for
each compressive strength test. Store undisturbed and in an insulated box during
cold weather. Deliver cylinders to lab between 24 and 48 hours after making.
6. Compressive Strength Tests: ASTM C39, one set of six cylinders for each 50
cubic yards or fraction thereof, of each concrete class placed in any one day, two
lab specimens tested at 7 days, two lab specimens tested at 28 days and two
specimens retained in reserve for later testing if required.
C. Test Reports
1. Forward results to Architect, Engineer and Contractor on same day that tests are
made.
2. Reports of compressive strength tests shall contain the general information of
project identification name and number, date of concrete placement, name of
Contractor, name of concrete supplier, truck number and delivery ticket number,
name of concrete testing service, concrete type and class, name of individual
making specimen, location of concrete batch in structure, design compressive
strength at 28 days, concrete mix proportions and materials; and the specific
information of slump, air content, temperature, compressive strength and type of
break for both 7-day and 28-day tests.
3. Field reports of concrete inspection shall contain general information noted
above, plus ambient temperature, concrete temperature, weather, slump, air
content and cylinder numbers.
D. Additional Testing
1. Testing service shall make additional tests of in-place concrete when test results
indicate specified concrete strengths and other characteristics have not been
attained in structure.
2. Testing service shall conduct tests to determine adequacy of concrete by cored
cylinders complying with ASTM C42 or by other methods acceptable to
Architect.
3. Contractor shall pay for such tests conducted, and any other additional testing
required, if concrete testing confirms specified strengths have not been met.
1.5
JOB CONDITIONS
Lecture 40 - Page 3 of 14
A. Store materials so as to ensure preservation of their quality and fitness for the Work.
Store reinforcement and formwork in a manner to prevent damage and accumulation
of dirt.
B. Contractor shall be responsible for correction of concrete work which does not
conform to specified requirements, including strength, tolerances and finishes.
Correct deficient concrete as directed by Architect.
PART 2 - PRODUCTS
2.1
MATERIALS
A. Formwork
1. Exposed Concrete: Unless otherwise shown or specified, construct formwork for
concrete surfaces, which will be exposed to view in the completed project, with
form plywood, metal or other acceptable panel-type material, to provide
continuous, straight, smooth exposed surfaces. Furnish in largest practicable
sizes to minimize number of joints and to conform to joint system shown on
Drawings. Provide form material with sufficient thickness to withstand pressure
of newly-placed concrete without bow or deflection.
2. Unexposed Concrete: Form concrete surfaces which will be unexposed to view in
the completed Project with plywood, lumber, metal or other acceptable material.
Provide lumber dressed on at least 2 edges and 1 side for tight fit.
B. Form Ties
1. Exposed Concrete: Plastic cone snaptie, Type 3M by Superior or accepted equal.
2. Unexposed Concrete: Snap-off metal ties, designed to prevent form deflection
and prevent spalling surfaces upon removal. Portion remaining after removal
shall be at least 1" from concrete surface.
C. Form Coatings: Commercial formulation form-coating compounds shall not bond
with, stain, nor adversely affect concrete surfaces, and shall not impair subsequent
treatments of concrete surfaces requiring bond or adhesion, nor impede wetting of
surfaces to be cured with water or curing compound.
D. Reinforcement
1. Deformed bars: ASTM A615, Grade 60.
2. Welded Wire Fabric: ASTM A185. Flat sheets only.
3. All chairs, spacers, clips, wire anchors and related items necessary to accurately
space and secure reinforcement.
4. Additional bars, if required, to anchor or space reinforcement.
5. Chairs shall be plastic booted at points of bearing on forms for exposed concrete.
6. Minimum 16-gage annealed tie wire, ASTM A82.
E. Cement: ASTM C150, Type I or Type II.
F. Aggregates: ASTM C33 and as herein specified.
Lecture 40 - Page 4 of 14
1.
2.
Fine Aggregate: Clean, sharp, natural sand free from loam, clay, lumps or other
deleterious substances with less than 10% passing the #100 sieve and less than
3% passing the #200 sieve.
Coarse Aggregate: Clean, uncoated, processed aggregate containing no clay,
mud, loam or foreign matter, as follows:
a. Crushed stone: Processed from natural rock or stone for concrete slabs
meeting NYSDOT 703-0201.
b. Clean, sharp, natural or processed gravel, or crushed stone, free from loam,
clay, lumps, or other deleterious substances for footings and miscellaneous
concrete.
c. Maximum Aggregate Size: Footings and walls size 467. Slabs size 57 with
minimum of 1800 pounds per cubic yard.
J.
Lecture 40 - Page 5 of 14
U. Dowel Bars: 1-inch square steel bars with -inch compressible foam on vertical
faces; or 1-inch-diameter steel bars, greased.
V. Non-shrink Grout: Sonogrout 14 by Sonneborn, or accepted equal.
W. Water Stop: Volclay Waterstop RX, 1" x 3/4" by American Colloid Co. or accepted
equal.
X. Dovetail Slot: Standard Dovetail Slot #180, 26 gauge galvanized steel with foam
filler by Heckmann Building Products or accepted equal.
2.2
Maximum
day
Water
Compressive
Cement Ratio
Air Content
Weight
3,000
0.55
4% - 6%
3,500
0.50
0%
4,000
0.45
5% - 7%
4,000
0.45
4% - 6%
Strength
Footings, foundation walls and all other
below grade concrete, miscellaneous
concrete.
Interior slabs on grade and suspended
slabs.
Exterior concrete subjected to freezing
and thawing, exterior slab on grade.
Interior light weight suspended slab.
D. Slump
1. Footings and Foundation Walls: 3" to 5".
2. Slabs: 4" maximum.
E. Ready Mix Concrete: ASTM C94.
Lecture 40 - Page 6 of 14
F. The quantity of coarse aggregate in pounds must be in the range of 1.25 to 1.5 times
the quantity of fine aggregate in pounds.
G. Fly ash may be substituted for cement for interior slabs only, at a maximum rate of 15
percent by weight. Submittals shall include actual mix design, including percentage
of fly ash and test results showing that mix meets specified compressive strength, and
air content. Fly ash is not permitted in cold weather concreting unless extended
protection is provided. Protection and heat shall be maintained until 70 percent of
specified design strength is achieved.
H. Pumping of concrete is permitted only if mix designs specifically prepared and used
previously for pumping are submitted. Pumpline shall have a 5-inch minimum inside
diameter and shall be used with 5-inch pumps.
2.3
REINFORCING FABRICATION
A. Fabricate bars to required lengths, shapes and bends. Do not rebend or straighten
reinforcement in a manner that shall weaken the material.
2.4
FORMWORK
A. Design formwork to support vertical and lateral loads that might be applied until such
loads can be supported by concrete structure.
PART 3 - EXECUTION
3.1
INSPECTION
A. Examine conditions under which concrete shall be placed. Do not proceed with work
until all unsatisfactory conditions are corrected.
3.2
NOTIFICATION
A. Notify Architect 24 hours before anticipated time of completion of reinforcement in
any section.
B. Do not place concrete until reinforcement has been observed and corrections, if any,
made.
3.3
FORMWORK INSTALLATION
A. Erect, brace, and maintain formwork to support vertical and lateral loads.
B. Construct forms to sizes, lines and dimensions shown to obtain accurate alignment,
location, grades, level and plumb work in finished structure.
Lecture 40 - Page 7 of 14
C. Provide for openings, offsets, keys and other features required in work. Accurately
position and support items.
D. Solidly butt joints and provide backup at joints to prevent leakage of cement paste.
E. Provide crush plates or wrecking plates where stripping may damage cast concrete
surfaces.
F. Kerf wood inserts for forming keys and the like to prevent swelling and for easy
removal.
G. Provide openings in concrete form to accommodate work of other trades. Determine
size and location of openings, recesses and chases from trades providing such.
H. Cleaning and Tightening: Thoroughly clean forms and adjacent surfaces to receive
concrete. Remove chips, wood, sawdust, dirt or other debris just before concrete is
placed. Retighten forms after concrete placement if required to eliminate concrete
leaks.
I.
3.4
Reuse of Forms: Clean and repair surfaces of forms to be reused in the work. Split,
frayed, delaminated, or otherwise damaged form facing material is not acceptable.
Apply new form coating compound material. When forms are reused for successive
concrete placement, thoroughly clean surfaces, remove fins and laitance, and tighten
forms to close all joints. Align and secure joints to avoid offsets.
REINFORCEMENT PLACING
A. Clean reinforcement of loose rust, mill scale, earth, ice and other materials which
reduce or destroy bond with concrete.
B. Accurately position, support and secure reinforcement against displacement by
formwork, construction or concrete placement operations. Locate and support
reinforcement by metal chairs, runners, bolsters, spacers and hangers as required. Do
not use brick.
C. Place reinforcement to obtain at least the minimum coverages for concrete protection.
D. Arrange, space and securely tie bars and bar supports to hold reinforcement in position
during concrete placement. Set wire ties so ends are directed into concrete, not toward
exposed concrete surfaces.
E. Lap bar splices as indicated. Stagger splices in adjacent bars. Wire tie all splices.
3.5
Lecture 40 - Page 8 of 14
B. Place flat sheets in as long lengths as practical. Lap adjoining sheets at least one full
mesh. Offset laps to prevent continuous laps in either direction.
C. Do not continue welded wire fabric through any control joints or construction joints
for slabs on grade.
3.6
CONCRETE PLACEMENT
A. Before placing concrete, inspect and complete formwork installation, reinforcing steel
and items to be embedded or cast in.
B. Notify other trades to permit installation of their work. Cooperate with other trades in
setting such work as required.
C. Install anchor bolts and sleeves.
D. Deposit concrete continuously or in layers of such thickness that no concrete shall be
placed on concrete which has hardened sufficiently to cause formation of seams or
planes of weakness within section. Provide construction joints if section cannot be
placed continuously.
E. Deposit concrete as nearly as practicable to its final location to avoid segregation
caused by rehandling or flowing.
F. Keep excavations free of water. Do not deposit concrete in water, mud, snow or on
frozen ground.
G. Maximum drop of concrete shall not exceed 5 feet. Use hopper and trunk for greater
drops.
H. Contractor shall be responsible for controlling the proper placing of all embedded
pipe, conduit and other embedded items.
I.
3.7
Contractor shall be responsible for finishing of all concrete slabs to proper elevations
to insure that all surface moisture will drain freely to floor drains, and that no puddle
areas exist. During finishing operation, Contractor shall pay particular attention to
this criterion, and shall make all efforts to obtain this. Any cost of corrections to
provide for this positive drainage will be the responsibility of Contractor.
CONSOLIDATION
A. Consolidate placed concrete by mechanical vibrating equipment supplemented by
hand spading, rodding or tamping.
B. Do not use vibrators to transport concrete inside formwork.
Lecture 40 - Page 9 of 14
SURFACE FINISHES
A. Finish of Formed Surfaces
1. Rough Form Finish: For formed concrete surfaces not exposed-to-view in the
finish work or concealed by other construction unless otherwise indicated. This is
the concrete surface having texture imparted by form facing material used, with
tie holes and defective areas repaired and patched and fins and other projections
exceeding 1/4" in height removed.
2. Smooth Form Finish: For formed concrete surfaces exposed-to-view. This is ascast concrete surface obtained with selected form facing material, arranged
orderly and symmetrically with a minimum of seams. Repair and patch defective
areas with fins or other projections completely removed and smoothed. Lightly
rub all exposed surfaces to achieve a uniform appearance.
or
Lightly sandblast to expose fine aggregate with occasional exposure of coarse
aggregate and to make the color uniform.
B. Monolithic Slab Finishes
1. Scratch Finish: Apply scratch finish to monolithic slab surfaces to receive
concrete floor topping or mortar setting beds for tile, and other bonded applied
cementitious finish flooring material. After placing slabs, roughen surface before
final set with stiff brushes, brooms or rakes.
2. Trowel Finish: Apply trowel finish to monolithic slab surfaces to be exposed-toview, and slab surfaces to be covered with carpet, resilient flooring, paint or other
thin film finish coating system. After floating, begin first trowel finish operation
using a power-driven trowel. Begin final troweling when surface produces a
ringing sound as trowel is moved over surface. Consolidate concrete surface by
final hand-trowel operation, free of trowel marks.
3. Non-Slip Broom Finish: Apply non-slip broom finish to exterior concrete
platforms, steps and ramps, and elsewhere as indicated. Immediately after trowel
finishing, slightly roughen concrete surface by brooming with fiber bristle broom
perpendicular to main traffic route.
3.9
Lecture 40 - Page 10 of 14
Lecture 40 - Page 11 of 14
For other surfaces (footing, walls, etc.) curing shall be by one of the accepted curing
treatments listed above.
Restore curing protection on all freshly cut joint edges and faces when sawing joints
or removing forms.
D. Concrete placed under cold weather conditions shall be cured by completely covering
exposed surface of concrete with curing sheet materials with sheeting completely
sealed around edges. All concrete shall be cured for a minimum of 14 days with
temperatures at or above 40oF or for a minimum of 7 days with temperatures at or
above 70oF.
3.11 COLD WEATHER CONCRETING
A. Place concrete during cold weather in accordance with ACI 306.
B. For cold weather concreting, (defined as a period when for more than three successive
days the mean daily temperature drops below 40oF) concrete temperature shall be
maintained in accordance with ACI 306.
3.12 HOT WEATHER CONCRETING
A. Place concrete in accordance with ACI 305.
B. Cool ingredients before mixing to maintain concrete temperature below 90oF at time
of placement.
C. Cover reinforcing steel with water-soaked burlap if temperature of reinforcing steel
exceeds ambient air temperature.
D. Wet forms thoroughly before placing concrete.
3.13 WALL JOINTS
A. Construction Joints: Locate and install construction joints as shown on Drawings.
Where construction joints are not shown, locate joints at masonry control joints.
Install joints maximum of 60 feet on center in locations acceptable to Architect.
3.14 INTERIOR SLAB JOINTS
A. Construction Joints: Locate and form construction joints as shown on Drawings.
Where construction joints are not shown place in locations acceptable to Architect.
B. Contraction Joints: Sawcut joints as soon as possible after finishing, generally within
4 to 16 hours. Make sample cut to determine if concrete surface is firm enough so that
it is not torn or damaged by the blade.
Lecture 40 - Page 12 of 14
C. Isolation Joints: Construction isolation in slabs on grade at all points of contact with
vertical surfaces and elsewhere as indicated.
3.15 EXTERIOR SLAB JOINTS
A. Expansion Joints: Locate and install expansion joints as shown on Drawings. Where
expansion joints are not shown, locate and install joints a maximum of 20 feet on
center in either direction.
B. Contraction Joints: Tool joints during final finishing with edging tool.
C. Isolation Joints: Construct isolation joints in slabs on grade at all points of contact
with vertical surfaces and elsewhere as indicated.
3.16 TOLERANCES
A. Footings
1. Variation of dimensions in plan: plus 2" or minus 1/2".
2. Variation of center from specified center in plan: 2 percent of footing width in
direction of variation, plus or minus 2" maximum variation.
3. Variation of bearing surface from specified elevation: plus or minus 1/2".
B. Anchor Bolts and Sleeves
1. Variation from specified location in plan: plus or minus 1/4".
2. Variation from specified elevation: plus or minus 1/2".
C. Slab on Grade
1. Surface Flatness: FF20 or greater.
2. Surface Levelness: FL17 or greater.
3. Variation from specified elevation: plus or minus 1/4".
D. Stairs
1. Variation in riser: 1/8".
2. Variation in tread: 1/8".
3.17 SLAB SEALERS
A. Interior Exposed Slabs: Apply two coats of hardener after slabs have cured a
minimum of 28 days at a rate of 100 square feet/gallon; in accordance with
manufacturers recommendations.
B. Exterior Exposed Slabs: Apply two coats of Penetrating Exterior Anti-Spalling Sealer
after slabs have cured a minimum of 28 days in accordance with manufacturers
recommendations.
3.18 REPAIR OF SURFACES
Lecture 40 - Page 13 of 14
END OF SECTION
Lecture 40 - Page 14 of 14
Lecture 41 Metric
Metric units are used everywhere in the world EXCEPT the USA. It is based on
scientific measurements, not the length of a kings foot or the weight of a chicken.
Area
Volume
Weight
Force
Multiply:
inches
inches
feet
feet
yards
in2
ft2
ft2
yd2
in3
ft3
ft3
gallons
gallons
pounds
pounds
kips
pounds per foot (PLF)
Moment
Unit weight
Stress (pressure)
Lb-In
Lb-Ft
Kip-Ft
Kip-Ft
Kip-In
Lb per ft3 (PCF)
Lb per in2 (PSI)
Lb per in2 (PSI)
Lb per in2 (PSI)
Kips per in2 (KSI)
Kips per in2 (KSI)
Lb per ft2 (PSF)
Lb per ft2 (PSF)
Kips per ft2 (KSF)
Kips per ft2 (KSF)
By:
25.4
0.0254
304.8
304.8
0.9144
645.2
92,909
0.0929
0.836
16,387
28,317,000
0.0283
0.003785
3.785
0.454
4.448
4448
14.594
0.11299
1.3559
1355.9
1.3559
112.99
0.1571
6895
6.895
0.0006895
6895
6.895
47.88
0.04788
47.88
0.04788
Lecture 41 - Page 1 of 11
To Obtain:
millimeters (mm)
meters (m)
millimeters (mm)
meters (m)
meters (m)
mm2
mm2
m2
m2
mm3
mm3
m3
m3 = 1000 liters
liters
kilograms (kg)
Newtons (N)
Newtons (N)
Newtons per meter (N/m)
N-m
N-m
N-m
kN-m
N-m
kN/m3
Pascals = Pa = N/m2
kPa = kilopascals = 1000 Pa
mPa = megapascals = N/mm2
kPa
mPa
Pa
kPa
kPa
mPa
Example 1
GIVEN: All road construction projects in New York State have drawings
with metric measurements. All metric drawings always use units of mm
for everything. (Reminder: 1 m = 1000 mm)
REQUIRED: Convert 1500 mm as shown on the drawings into
feet/inch/sixteenths.
Use the conversion 1 inch = 25.4 mm
Number of inches =
1500mm
25.4mm _ per _ inch
= 59.055118 inches
= 48 + 11.055118
= 4 + 11.055118
= 4 + 11 + (0.055118 x 16th)
= 4 + 11 +
1500 mm = 4-11
0.88
16ths
1
"
16
Example 2
GIVEN: The x-sectional area of a W30x211 steel beam = 62.0 in2.
REQUIRED: Determine the area of the beam in units of mm2.
Use the conversion 1 inch = 25.4 mm
1 inch x 1 inch = 25.4 mm x 25.4 mm
1 in2 = 645.2 mm2
Number of mm2 = 62.0 in2 x 645.2 mm2 per in2
Area = 40,002 mm2
Lecture 41 - Page 2 of 11
Example 3
GIVEN: The tank below.
REQUIRED: How many liters are in the tank?
7-0
Dia. = 18-0
Vol. =
(18' ) 2 (7' )
= 1781 ft3
= 1781 ft3(7.48 gals per ft3)
Vol. = 13324 gal.
Use the conversion 1 ft3 = 0.0283 m3
Volume = 1781 ft3(0.0283 m3 per ft3)
= 50.4 m3
Volume = 50.4 m3(1000 liters per m3)
Volume = 50,400 liters
Lecture 41 - Page 3 of 11
Example 4
GIVEN: An ASTM A325 steel bolt is capable of resisting an allowable
shear stress of 30 kips per square inch (KSI)
REQUIRED: What is the allowable shear stress for the bolt in units of
KPa?
Use the conversions of 1 inch = 25.4 mm
1 Pa = 1 N/m2
1 kPa = 1000 Pa
1 lb = 4.448 N
30 KSI =
30000lb
1in 2
30 KSI =
30 KSI =
(133440 N )
(0.00064516mm 2 )
Lecture 41 - Page 4 of 11
Metric Loads
All metric loads, forces and derivatives of those are in units of Newtons.
Below is a sampling of typical minimum design live loads for buildings:
2.87
4.79
2.87
3.59
4.79
4.79
2.87
1.92
2.87
7.18
2.40
1.92
1.92
4.79
4.79
Material Properties
Material:
Steel A36
Steel A992
Aluminum
Concrete (4000 psi)
Wood - SYP
Earth sandy
Water
Unit Weight:
Lb/ft3 kN/m3
490
77.2
490
77.2
170
26.7
150
23.6
37
5.8
100
15.7
62.4
9.8
Kips/in2
29,000
29,000
10,000
3,600
1,600
-
kN/mm2
205
205
70
25.4
11.3
-
Lecture 41 - Page 5 of 11
Metric Dimensions
All metric dimensions are in units of millimeters. Below are a few
examples of architectural drawings in metric dimensions:
Lecture 41 - Page 6 of 11
Lecture 41 - Page 7 of 11
11 m
wu L2
Mmax =
8
=
(3kN / m)(11m) 2
8
in
in
in
Zx = 1,089,742 mm3
Lecture 41 - Page 8 of 11
Step 3 - Determine the LRFD design moment of the beam Mn in units of kN-m:
From LRFD:
See table above
Mn = 0.9FyZx
where: Fy = 345 N/mm2
Zx = 1,089,742 mm3
m
kN
x
= 338,360,000 N-mm x
1000 N 1000mm
Mn = 338.4 kN-m
Step 4 - Determine if the beam is adequate in moment:
Since Mn = 338.4 kN-m > Mmax = 45.4 kN-m beam is OK
Lecture 41 - Page 9 of 11
350
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(20mm) 2
where: As = 3 bars
4
2
= 942.5 mm
act =
As
bd
942.5mm 2
(250mm)(350mm)
= 0.0108
Lecture 41 - Page 10 of 11
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.0108)(400 N / mm 2
= 0.9(942.5 mm2)(400 N/mm2)(350 mm)(1 - 0.59
25 N / mm 2
= 106,640,000 N-mm
m
kN
x
= 106,640,000 N-mm x
1000 N 1000mm
Mu = 106.6 kN-m
Step 2 Det. moment capacity Mu in units of Kip-Feet:
Kip Feet
Mu = 106.6 kN-m x
1.3559kN m
Mu = 78.6 Kip-Feet
Lecture 41 - Page 11 of 11
See conversion
table above
Shear plane
Normal beam
Coped beam
Short span
Lecture 5 - Page 1 of 9
tw
Beam X-Sect
Aw = Shear area
in normal beam
(shaded)
Aw = Shear area
in coped beam
(shaded)
Vn
v
Lecture 5 - Page 2 of 9
Example 1 (LRFD)
GIVEN: A W14x26 A992 steel beam.
REQUIRED: Determine the FACTORED design shear strength, vVn for
the beam.
Step 1 Determine area of web, Aw:
Aw = twd
tw
Lecture 5 - Page 3 of 9
Example 2 (ASD)
GIVEN: The W12x30 A992 steel beam has a 4 cope and has the
SERVICE load as shown below. Disregard beam weight.
REQUIRED:
1) Determine if the beam is acceptable on the basis of shear at the coped
end.
2) Determine if the beam is acceptable on the basis of shear at the
location of the point load.
W12x30
R2
R1
Lecture 5 - Page 4 of 9
120KIPS (7' )
10'
= 84 KIPS
Step 2 Determine ALLOWABLE shear strength in coped web at R1:
0.6 Fy Aw C v
Vn
=
v
1.50
Aw = Area of web
= twh
h = d - cope
tw
Lecture 5 - Page 5 of 9
(Note: This example looks ONLY at shear. Very high loads also require a
detailed look at connections, which will be investigated later)
Lecture 5 - Page 6 of 9
The following allowable deflection limits for steel construction are used by
the IBC:
Construction
Roof member supporting plaster ceiling
Roof member supporting nonplaster ceiling
Roof member supporting no ceiling
Floor members
Live Load
L/360
L/240
L/180
L/360
Snow or Wind
L/360
L/240
L/180
-
Lecture 5 - Page 7 of 9
Example 3
GIVEN: The floor framing plan below. The total superimposed service
dead load = 86 PSF (not including beam weight) and the service live load
= 125 PSF.
REQUIRED: Determine the maximum actual mid-span deflection and
compare with a Live load limit = L/480 and a Dead load + Live load limit =
L/240 on the W18x35 steel beam.
do
do
W18x35 beam
W24x62 girder
25-0
4@8-0 = 32-0
Step 1 Determine the actual max. deflection considering Live load only:
1000 PLF
4
5
(25' x12" / ft )
12
max =
384(29000000 PSI )(510in 4 )
= 0.59 in.
Lecture 5 - Page 8 of 9
L
480
allow =
25'0" (12" / ft )
480
= 0.625 in.
Since allow = 0.625 > 0.59 beam is acceptable
Step 3 Determine max. defl. considering Deal load + Live load:
5wL4
384 EI
max =
1723PLF
4
5
(25' x12" / ft )
12
max =
384(29000000 PSI )(510in 4 )
= 1.02 in.
Step 4 Determine allowable deflection of L/240 for LL + DL:
allow =
L
240
25'0" (12" / ft )
240
= 1.25 in.
Since allow = 1.25 > 1.02 beam is acceptable
Lecture 5 - Page 9 of 9
R2
R1
75-0
(10KLF )(75' ) 2
8
wu L
2
(10KLF )(75' )
2
Vu = 375 KIPS
Step 2 Determine preliminary depth of girder:
Assume depth =
Span
10
75'0" (12" / ft )
10
depth
= 90
h = web ht.
E
h
<
260 then design shear = v Vn
Fy t w
4.52 E
Vn = Aw
2
h
t
w
tw =
h
260 :
tw
87"
260
= 0.33
Try tw = 3/8:
Aw = Area of web
4.52 E
Vn = Aw
2
h
t
w
4.52(29000 KSI )
= (87 x 3/8)
2
87"
3 / 8"
Try tw = :
Use 87 x web
Area of flange = A f
7031KIP FT (12" / ft )
(50 KSI )(87")
19.4 in2
TRY 1 x 14 flange (Area of flange = 21 in2 > 19.4 in2)
Step 6 Check tension (bottom) flange for yield strength (AISC 16.1-107:
Design strength for tension flange = bMn
where: b = 0.90
Mn = S xtReFy
I total
yb
Sxt =
Yt
t wh3
+ 2( A f )( y b ) 2
12
Itotal =
87
yb
=
Af = Area of
flange
0.75" (87) 3
+ 2(21in 2 )( 44.25") 2
12
= 123,395 in4
Sxt =
123395in 4
44.25"
= 2788.6 in3
Re = Hybrid girder factor
= 1.0 if web & flange steel F y are the same
bMn = 0.9SxtReFy
= 0.9(2788.6 in3)(1.0)(50 KSI)
= 125,487 KIP -IN
= 10,457 KIP -FT > Mu = 7031 KIP -FT OK
ar
1200 + 300a r
hc
5.70 E 1.0
tw
Fy
Aw
Af
(87" )(0.75" )
21in 2
= 3.1
hc =
h
2
87"
2
= 43.5
43.5"
3 .1
29000
1 .0
RPG = 1
5
.
70
1200 + 300(3.1) 0.75"
50
= 1.11 use 1.0
Re = 1.0
bMn = 0.9Sxc RPGReFy
= 0.9(2788.6 in3)(1.0)(1.0)(50 KSI)
= 125,487 KIP -IN
= 10,457 KIP -FT > Mu = 7031 KIP -FT OK
1 Plate
90
Plate
1 Plate
14
Non-Composite Construction
The word composite means 2 or more different materials. In composite
construction, the slab is adequately bonded to the steel beam by means of
headed shear studs resulting in a composite beam. The concrete acts like a
large flange in compression, while a much greater portion of the steel beam
acts in tension. The result is a VERY efficient beam as much as 40% to 60%
lighter weight steel than non-composite.
Headed shear studs
welded thru metal deck to
beam flange
Composite Construction
Lecture 7 - Page 1 of 10
Comp.
Comp.
N.A
N.A
Ten.
Ten.
Composite Section
Non-Composite Section
Notice that the neutral axis (N.A.) in the non-composite beam is located in the
middle of the section. This indicates that half of the beam section is in tension
and half is in compression.
In the composite section, the compression is carried ENTIRELY by the concrete,
while the tension is carried by the beam.
Composite Design per LRFD
Metal Deck
Shear stud
Ycon
Beam
Lecture 7 - Page 2 of 10
a
Y2
BeamSpan
8
= smaller of
BeamSpacing
2
Distance to edge of slab
As Fy
0.85 f ' c b
As = Cross-sectional area of beam
= from properties
fc = Specified concrete compressive strength
= 4 KSI (usually)
Y2 = Ycon -
a
2
Lecture 7 - Page 3 of 10
Ycon
The best way to see how the design of a composite beam is accomplished is thru
an example problem:
Example 1 (LRFD)
GIVEN: A floor structure using A992 steel beams and the following
superimposed SERVICE loads:
3@8-0 = 24-0
30-0
Beam A
wu = 1.2D + 1.6L
= 1.2[8(63 PSF + 30 PLF)] + 1.6[8(75 PSF)]
= 1601 PLF
= 1.6 KLF
Mu =
wu L2
8
= 180 KIP-FT
Lecture 7 - Page 4 of 10
M u (12" / ft )
0.85Fy 2 + Ycon 2
= 17.28 PLF
From AISC Table 3-19 p. 3-184 TRY W14x22
Step 3 Determine concrete flange force, Qn:
Qn = AsFy
where: As = Area of beam
= 6.49 in2 (from properties for W14x22)
Lecture 7 - Page 5 of 10
BeamSpan
30' (12" / ft )
=
= 45 USE
8
8
BeamSpacing
8' (12" / ft )
=
= 48
2
2
b = smaller of
a
2
where a =
As Fy
0.85 f ' c b
325KIPS
0.85(4 KSI )(45" )
= 2.12
Y2 = 4 -
2.12"
2
= 2.94
Use Y2 = 3
Step 6 Determine required beam size from AISC Table 3-19:
W14x22
Y2 = 3
Qn = 325 KIPS
Lecture 7 - Page 6 of 10
Page 3-184
Lecture 7 - Page 7 of 10
2Qn
Qn ( stud )
where: Qn = AsFy
= 325 KIPS
Qn(stud) = Nominal horz. shear strength of stud
= From AISC Table 3-21 p. 3-207
= 17.2 KIPS
2(325KIPS )
17.2 KIPS _ per _ stud
= 37.8 studs
Use 38 dia. studs
Step 8 Check beam shear at coped end:
Assume beam is coped 1
1
13.7
W14x22 beam
Girder
Factored beam end reaction =
= 24 KIPS
Lecture 7 - Page 8 of 10
Set up a ratio of vVn for the full W14x22 beam section to the
reduced beam section:
vV n
Full _ depth
vV n
Re duced _ depth
vV n
94.8KIPS
=
13.7"
(13.7"1.5" )
vVn = 84.4 KIPS > 24 KIPS for reduced section OK
Step 9 Draw summary sketch:
38 Dia. shear studs welded
thru metal deck along center of
beam spaced evenly along length
of beam
Lecture 7 - Page 9 of 10
Example 2
GIVEN: The beam from Example 1. All loads and other conditions are
the same.
REQUIRED: Design lightest weight W14 Beam A using NONCOMPOSITE construction.
Step 1 Determine Mu:
Mu = 180 KIP-FT
Step 2 Design lightest weight W14 beam:
From AISC Zx Table p. 3-18:
Use W14x34 bMpx = 205 KIP-FT > 180 KIP-FT
(Note: The W14x34 non-composite beam is 55% heavier
than a W14x22 beam that is used as a composite beam.)
Lecture 7 - Page 10 of 10
Axial Load
Lecture 8 - Page 1 of 9
Pn
ASD
c
where: c = 0.90
c = 1.67
Pn = nominal compressive strength
= AgFcr
Ag = Gross cross-sectional area, in2
= From properties
Fcr = Elastic critical buckling stress
Fy
KL
E
4.71
= 0.658 Fe Fy IF
rmin
Fy
= 0.877Fe
IF
KL
E
> 4.71
rmin
Fy
2E
KL
rmin
Lecture 8 - Page 2 of 9
KL
200
rmin
Example 1 (LRFD)
GIVEN: A W12x50 using A992 is used as a column in a building. It is
laterally braced at 14-0 about both the X axis and Y axis. Use K = 1.0.
REQUIRED: Determine the design axial compressive strength, cPn for
the column.
KL
E
Step 1 Determine if
4.71
:
rmin
Fy
KL (1.0)(14'0" X 12" / ft )
=
rmin
1.96in
= 85.7
4.71
29000 KSI
E
= 4.71
Fy
50 KSI
= 113.4
KL
E
4.71
rmin
Fy
Therefore,
2E
KL
rmin
2 (29000 KSI )
(85.7 )2
= 38.97 KSI
Lecture 8 - Page 3 of 9
Fcr = 0.658 Fe Fy
50 ksi
= 29.2 KSI
cPn = 0.90(AgFcr)
= 0.90(14.6 in2)(29.2 KSI)
Lecture 8 - Page 4 of 9
Example 2 (LRFD)
GIVEN: The truss shown below uses single A36 steel L6x4x angle for
all members. All loads shown are factored.
REQUIRED: Determine if the truss member A is adequate based on
axial compression.
L6x4x
Member A
6-0
10-0
10-0
30 KIPS
Step 1 Determine force in Member A:
Length of member A = (10' ) 2 + (6' ) 2
= 11.66 feet
= 139.9 inches
11.66'
Force in member A = 15 KIPS
6'
= 29.2 KIPS
Step 2 Determine slenderness factor (KL/rmin):
KL 1.0(139.9" )
=
rmin
0.864"
= 161.9 < 200 OK
Lecture 8 - Page 5 of 9
KL
= 161
rmin
At Fy = 36 KSI and
KL
= 162
rmin
Page 4-322
Lecture 8 - Page 6 of 9
KL
= 161.9 cFcr = 8.62 KSI
rmin
cPn = c (AgFcr)
= Ag(cFcr)
= 4.75 in2(8.62 KSI)
Lecture 8 - Page 7 of 9
Example 3 (LRFD)
GIVEN: A column has an unbraced length = 12-0 and is subject to a
factored axial load = 450 KIPS. Use K = 1.0.
REQUIRED:
1) Design the lightest weight A992 W shape using AISC Table 4-1.
2) Design the lightest weight Square HSS shape using AISC Table 4-4.
3) Design the lightest weight Round HSS shape using AISC Table 4-5.
Step 1 Design lightest W shape:
From AISC Table 4-1, the following possibilities may be used:
Shape
W8x58
W10x49
W12x53
W14x53
Weight (PLF)
58
49
53
53
KL
12
12
12
12
Weight (PLF)
48.7
47.8
48.8
KL
12
12
12
Weight (PLF)
50.8
54.8
49.6
KL
12
12
12
Lecture 8 - Page 8 of 9
Example 4 (LRFD)
GIVEN: Same as Example 1. A W12x50 using A992 is used as a column
in a building. It is laterally braced at 14-0 about both the X axis and Y
axis. Use K = 1.0.
REQUIRED: Determine the design axial compressive strength, cPn for
the column using AISC Table 4-1.
Lecture 8 - Page 9 of 9
M=0
M = Pe
32 K
20 K
32 K
20 K
32 K
20 K
Lecture 9 - Page 1 of 11
In particular, AISC Spec H1 (p. 16.1-70) dictates the following interaction formulas:
a) For
Pr
0 .2
Pc
Pr 8 M rx M ry
+
+
1.0
Pc 9 M cx M cy
b) For
Pr
< 0 .2
Pc
Pr M rx M ry
+
+
1.0
2 Pc M cx M cy
Lecture 9 - Page 2 of 11
As an alternative to the above equations, AISC Table 6-1 (p. 6-5 thru 6-95) can be
used. In particular the interaction formulas from above may be re-written as:
a) For
Pr
0 .2
Pc
Pr
< 0 .2
Pc
1
9
pPr + (bxMrx + byMry) < 1.0
2
8
where: bx
by
p
Example 1 (LRFD)
GIVEN: A W14x68 A992 steel corner column for a two-story building has an
unbraced height = 12-0 and is subjected to the FACTORED loads applied from
beam end reactions as shown in plan view below.
REQUIRED: Determine if the column section is adequate under combined
compression and bending.
146 K
180 K
Lecture 9 - Page 3 of 11
Beam
146 K
is equivalent to
W14x68 col.
L4x4x connection
angle
d = 14+
8
4
3
3
7
4
2
3
6
3
2
2
5
3
2
1
4
2
3
2
3
1
2
1
g
g1
g2
Lecture 9 - Page 4 of 11
2
1
1
1
Mrx = Pe
where: P = Beam end reaction
From AISC p. 1-46 and above
e = eccentricity
= (d) + angle gage
= (14) + 2
= 9
9.5"
Beam
is equivalent to
Column web tw
L4x4x connection
angle
Mry = Pe
where: P = Beam end reaction
e = eccentricity
= (tw) + angle gage
= ()+ 2
= 2
2.75"
Lecture 9 - Page 5 of 11
Pr
0 .2
Pc
Pr
326 KIPS
=
Pc
700 KIPS
Lecture 9 - Page 6 of 11
See Below
Lecture 9 - Page 7 of 11
Check:
pPr + bxMrx + byMry < 1.0
1.43 x 10-3(326 KIPS) + 2.19 x 10-3(115.6 KIP-FT) + 6.42 x 10-3(41.2 KIP-FT) < 1.0
Lecture 9 - Page 8 of 11
18 K
Example 2 (LRFD)
GIVEN: A 5-story interior column with non-symmetric loads as shown
typically below. Use KL = 14-0. Connection angles are L3x3x.
REQUIRED: Design the lightest weight W12 column for the lowest level.
28 K
34 K
14 K
7.75"
Mrx = 16 KIPS
12" / ft
= 10.3 KIP-FT
Lecture 9 - Page 9 of 11
2"
Mry = 14 KIPS
12" / ft
= 2.3 KIP-FT
Step 4 Select Trial W12 column size:
Referring to AISC Table 4-1 p. 4-18:
@ KL = 14 Try W12x50 cPn = Pc = 443 KIPS > 376 KIPS
Step 5 Determine column adequacy using interaction formula:
Check
Pr
0 .2
Pc
Pr
376 KIPS
=
Pc
443KIPS
Lecture 9 - Page 10 of 11
Lecture 9 - Page 11 of 11
Depth to steel d
Hanger bars
(usually #4 or
#5 bars)
Stirrup bars (used
to prevent diag.
tension cracks)
spaced at d/2+
apart
Concrete cover
= 2 as
per ACI reqmts.
Height h
Width b
Tension bars As
Section A-A
Lecture 3 Page 1 of 10
Height h
Min. bar
spacing
Tension bars As
Min. bar
spacing
Lecture 3 Page 2 of 10
Lecture 3 Page 3 of 10
Example 1
GIVEN: A rectangular concrete beam is similar to the one shown above.
Use the following:
Height h = 20
Width b = 12
Concrete fc = 4000 PSI
Concrete cover =
All bars are A615 Grade 60 (fy = 60 KSI)
Stirrup bar = #3
4 - #7 Tension bars
#3 Stirrup
bars
Height h = 20
Depth to steel d
Width b = 12
4 - #7 tension bars
REQUIRED:
1) Determine total area of tension bars, As.
2) Determine depth to center of tension bars, d.
A
200
and state if it is acceptable.
3) Determine actual = s where min =
bd
fy
Step 1 Determine area of tension bars, As:
As = 4 bars(0.60 in2 per #7 bar)
As = 2.40 in2
Lecture 3 Page 4 of 10
As
bd
min =
2.40in 2
(12" )(18.44" )
200
fy
200
60000 PSI
min = 0.0033
actual = 0.0108
Lecture 3 Page 5 of 10
Applied loads
Span L
Taking a section through the beam at any place along the length reveals the
following stress distribution about the cross-section of the beam:
Compression
Neutral
Axis
Homogeneous Beam
Tension
Lecture 3 Page 6 of 10
Compression
Neutral
Axis
C
Neutral
Axis
(a)
0.85fcb
a = 1C
d
Moment arm = Z
T = Asfy
Actual Stress Distribution
T = Asfy
Idealized Stress Distribution
Lecture 3 Page 7 of 10
As f y
0.85 f ' c b
Beta
= 1C
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
fy
87,000
87,000 f
y
where fy = PSI
max = maximum allowable ratio of tension steel reinforcement per ACI 318
= 0.75bal
Lecture 3 Page 8 of 10
Example 2
GIVEN: The concrete beam from Example 1 is used to support the loading as
shown below.
REQUIRED:
1. Determine the maximum factored applied moment, Mmax.
2. Determine the usable moment capacity of the beam, Mu, and determine if
it is acceptable based on Mmax.
3. Determine if the beam is acceptable based on max.
20-0
wu L2
8
(3KLF )(20'0" ) 2
8
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.0108)(60 KSI )
= 0.9(2.40 in2)(60 KSI)(18.44)(1 - 0.59
)
4 KSI
= 2161.4 KIP-IN
Mu = 180.1 KIP-FT
Since Mu = 180.1 KIP-FT > Mmax = 150 KIP-FT beam is acceptable
Lecture 3 Page 9 of 10
max = maximum allowable ratio of tension steel reinforcement per ACI 318
= 0.75bal
bal = balanced ratio of tension steel reinforcement
0.851 f ' c
=
fy
87,000
87,000 f
y
where fy = PSI
87,000
0.85(0.85)(4 KSI )
=
60 KSI
max = 0.75(0.0285)
max = 0.0214 > act = 0.0108 beam is acceptable
Lecture 3 Page 10 of 10
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
Designing a beam using the equation above is much more difficult. Assuming the
material properties and dimensions are known, the equation above still has 2
unknown variables As and act. Therefore, design of steel reinforcement for a given
beam is largely one of trial-and-error.
Beam Design
Design of concrete beam members is often one of trial-and-error. Its
impossible to directly solve for all the variables in a reinforced concrete beam.
Usually, material properties are known as well as maximum applied factored
moment, Mmax.
L
The following Table is useful to get a trial beam size:
h 1.5b 2.5b
Lecture 4 Page 1 of 13
The design aid shown below is used for design or analysis. Values of
Lecture 4 Page 2 of 13
Lecture 4 Page 3 of 13
Example 1
GIVEN: A rectangular concrete beam with dimensions is shown below (stirrup bars
not shown). Use concrete fc = 4000 PSI and grade 60 bars.
REQUIRED:
1) Determine the usable moment capacity Mu of the beam using formula.
2) Determine the usable moment capacity Mu of the beam using Table 2.
b =12
d = 18
3 - # 7 bars
act =
As
bd
act = 0.0083
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.0083)(60 KSI )
= 0.9(1.80 in2)(60 KSI)(18)(1 - 0.59
)
4 KSI
= 1621 KIP-IN
Mu = 135 KIP-FT
Lecture 4 Page 4 of 13
Step 2 - Determine the usable moment capacity Mu of the beam using Table 2:
Mu
461.4 PSI
bd 2
Lecture 4 Page 5 of 13
Example 2
GIVEN: The concrete beam below. Use the following:
REQUIRED: Design the rectangular beam such that h 1.5b and act (max).
wu = 2 KLF (includes anticipated beam weight = 300 PLF)
28-0
(2 KLF )(28'0" ) 2
8
Lecture 4 Page 6 of 13
Mu
= 581.2 PSI
bd 2
Mu
= 581.2 PSI
bd 2
2352000 Lb in
581.2 PSI
(0.9)(b)(1.5b) 2
Solve for b:
2352000
581.2 PSI
(0.9)(2.25b 3 )
b3
2352000
(0.9)(2.25)(581.2)
b = 12.6 Use b = 12
d = 1.5b
= 1.5(12)
d 18
Lecture 4 Page 7 of 13
As
bd
As
Area _ of _ one _ bar
2.36in 2
0.79in 2 _ per _#8 _ bar
Lecture 4 Page 8 of 13
L
16
L
16
(28'0" )(12" / ft )
16
20
12
Recall: UnitWt
Weight
Rearranging:
Volume
(1'0" )
Lecture 4 Page 9 of 13
Step 9 Draw Summary Sketch labeling all information necessary to build it:
12
2 - #4 hanger
bars
20
#3 stirrup bars
@ 9 o.c.
concrete cover
all around
3 - #8 main bars
Section A-A
Notes:
1) Concrete fc = 4000 PSI normal-weight
2) All bars ASTM A615 Grade 60
Lecture 4 Page 10 of 13
Example 3
GIVEN: A continuous 10 x 16 concrete beam is shown below. Assume the
following:
REQUIRED:
1) Determine the magnitude of the maximum positive and negative moments
(Refer to Structural Theory notes)
2) Determine if the beam is adequate based upon flexure only. Check positive &
negative moments.
wu = 2400 PLF (incl. beam wt.)
R1
R2
L = 20-0
Mpos = 0.08(wL2)
0.4L
R4
R3
L = 20-0
L = 20-0
Mpos = 0.025(wL )
0.5L
Mpos = 0.08(wL2)
0.5L
Mneg = -0.1(wL2)
Mneg = -0.1(wL2)
R1 = 0.4wL
R2 = 1.1wL
R3 = 1.1wL
R4 = 0.4wL
Lecture 4 Page 11 of 13
0.4L
#3 stirrup bars
@ 9 o.c.
concrete cover
all around
16
2 - #4 hanger
bars
2 - #9 main bars
Beam cross-section in Mpos region
(upside-down in Mneg region)
9
= 16 - - 3/8 - "
8
d = 14.3125
Lecture 4 Page 12 of 13
act =
As
bd
2(1.00in 2 _ per _ bar )
(10" )(14.3125" )
act = 0.01397 which is > min = 0.0033 and < max = 0.0214 OK
act f y
Mu = 0.9Asfyd(1 - 0.59
f 'c
(0.01397)(60 KSI )
= 0.9(2.00 in2)(60 KSI)(14.3125)(1 - 0.59
)
4 KSI
= 1354.6 KIP-IN
Mu = 112.9 KIP-FT
Step 4 Check if beam is adequate based upon flexure only:
a) Maximum positive moment, Mpos:
As
From above, the largest Mpos = 76.8 Kip-Ft < 112.9 Kip-Ft
ACCEPTABLE
As
Lecture 4 Page 13 of 13