Documente Academic
Documente Profesional
Documente Cultură
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Module
Location Construction
Endorsement and Authorisation
For endorsement and authorisation, please refer
to NR/L3/SIG/11303
This document is the property of Network Rail. It shall not be reproduced in whole or part nor disclosed to a third
party without the written permission of Network Rail.
Copyright 2012 Network Rail.
Uncontrolled copy once printed from its electronic source.
Published and Issued by Network Rail, Kings Place, 90 York Way, London. N1 9AG.
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
User information
This Network Rail standard may contain requirements that are colour-coded
according to the following RedAmberGreen classification.
Red Mandatory requirements
Requirements that will be complied with, and achieved under all circumstances.
Accountability for the efficacy of these requirements lies with the Professional
Head/Standard Owner.
These are presented in a red box and with the word shall or a direct instruction.
Requirements that will be complied with unless deviation has been approved.
Accountability for the efficacy of these requirements lies with the Professional
Head/ Standard Owner, or their nominated Delegated Authority.
These are presented with an amber sidebar and with the word shall or a direct
instruction.
Green Guidance
This is presented with a dotted green sidebar and with the word should (usually
in notes).
Page 2 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Issue record
Issue
Date
Comments
August 2000
1st issue
September 2010
March 2011
03/03/2012
Compliance
This Network Rail standard is mandatory and shall be complied with by Network Rail
and its contractors if applicable from 03/03/2012.
When this standard is implemented, it is permissible for all projects that have
formally completed GRIP Stage 3 (Option Selection) to continue to comply with the
issue of any relevant Network Rail standards current when GRIP Stage 3 was
completed and not to comply with requirements contained herein, unless stipulated
otherwise in the scope of this standard.
Disclaimer
In issuing this document for its stated purpose, Network Rail makes no warranties,
express or implied, that compliance with all or any documents it issues is sufficient
on its own to ensure safe systems of work or operation. Users are reminded of their
own duties under health and safety legislation.
Supply
Copies of documents are available electronically, within Network Rails organisation.
Hard copies of this document may be available to Network Rail people on request to
the relevant controlled publication distributor. Other organisations may obtain copies
of this document from IHS. Tel: 01344 328039.
Page 3 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Contents
1 General Lineside Equipment Layout
2 Location Case - General Arrangement
3 Positioning Of Apparatus Cases
4 Method Of Erection
5 Standard Structure Gauge
6 Signal Structures on Lines of 100mph or Less
7 Signal Structures on Lines over 100mph
8 Cant and Curvature
9 Walkways
10 Cable Routes
5
5
5
6
7
7
8
10
12
12
Figure 3 - Layout for Location Cases and Cable Route - Typical Arrangement (1)
Figure 5 - Layout for Location Cases and Cable Route - Typical Arrangement (3)
Figure 6 - Location Case - Typical Arrangement with Retaining Wall
Figure 7 - Location Case - Alternative Guardrail Arrangements
Figure 8 - Location Case - Typical Construction of Guardrail
13
15
16
17
18
Page 4 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Nut, M16.
Base to drawing BRS-SC 32 is used for small cases. The case is bolted down into
tapped holes in the base. This will require four each of the following items:
Filler blocks to drawing BRS-SC-31/3 are used to block off the sides and ends of the
bases that do not have access to cable troughs.
Land ties to drawing BRS-SC-33 may be fixed to the bottom of the base to give
greater stability at windy sites.
Locations may be erected with the inner frames having equipment already mounted
and pre-wired. Take great care that the equipment and wiring is not damaged in any
way during the erection process.
3 Positioning Of Apparatus Cases
An overview of the siting requirements for apparatus housings is given in
NR/GN/SIG/11821, including details of guard rails and platforms.
The preferred position is for locations to be mounted:
so that a person viewing the front side (see below) is facing trains
approaching on the nearest line.
Page 5 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
at least 3.0 metres from the running rail to the face of the case. If this
clearance cannot be obtained, protecting guard rails will be necessary. Where
several cases need protection, the guard rail length should not normally
exceed 2 metres to avoid the rail inhibiting easy exit from the track. If longer
protection is required, rails should be staggered or gapped. Some examples
are given in Figure 4 but other arrangements are possible.
In areas of generally restricted clearances, the guard rail position and length should
be considered in relation to both the protection of persons working at the cases and
the need for someone leaving the track to be able to reach a position of safety.
Some situations with severely limited or variable clearance, or on bridges and
viaducts, or with irregular ground level will require special consideration and
treatment.
All location cases should be at least 2.5 metres from any structure which is bonded
to the traction return as a requirement of overhead line electrification. This is to
prevent someone being able to touch both the location case and the other structure
at the same time. Each may have its own earthing system and a dangerous potential
could exist between the two, creating a safety hazard if they were nearer. For the
same reason, wherever practicable in a.c. electrified areas, guard rails should be at
least 2 metres from the running line and from overhead line structures. If closer, an
insulated barrier should be provided.
If the location case has to be mounted parallel to the track, then it should be
mounted with the front side away from the track. The distance from track and guard
rail rules given above also apply here. See Figure 4.
The front of a location case is the side on which the face of equipment is mounted,
where relay operation or status indications may be observed, and where
adjustments, including gain settings, have to be made.
Extended clearances will be required on new railways and where line speeds exceed
125 mph. In these cases you will be advised accordingly.
4 Method Of Erection
a) Dig a suitable hole approximately 330mm deep. The final ground level should
be 100mm below the top of the troughs.
b) Assemble the bases and troughs. Level up.
c) Fill in the ground around the bases. Firm down and level.
d) Bolt on the case frames. Check that all the frames are level, vertical and
parallel.
e) Fit on all the outer cases and check that the doors fit correctly.
Erect any necessary guard rails. Typical arrangements are shown in Figures 4, 5,
and 7, with the method of construction given in Figure 8. Alternative fixing
arrangements, such as bolting down to pre-cast concrete or other base, may be
used if more suitable.
Page 6 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
The area round the location cases should be made level, and hardstanding provided
if the ground condition warrants it. Gravel or granite chippings are examples of a
suitable non-slip surface.
Platforms around the location (see NR/GN/SIG/11821) will be necessary if:
the ground is not stable.
it would be unsafe to work at (e.g. the ground falls away steeply).
Figure 6 shows an example of how a protective wall has been built round a location
case near banking.
5 Standard Structure Gauge
Signalling equipment shall be located so that it does not encroach on the standard
structure gauge limits shown in both Figures 1, except as permitted below. The
technician must consult the supervisor regarding any new equipment which would be
foul to gauge and report any existing equipment such as stay wires, balance levers
and ground signals which is foul to gauge. All guys or line wires permanently above
the track must be fixed at height not less than 6100mm above rail level. Temporary
wires or ropes over the track must not be lower than 5500mm above rail level or, if
less, no train must be allowed to pass until the wire or rope has been removed.
Supports for carrying temporary wires or ropes shall be fixed securely and, if
necessary, guyed.
6 Signal Structures on Lines of 100mph or Less
Where the maximum permitted speed is 100mph or less, the standard structure
gauge (Figure 1a and 1b) requires the following:
a) no part of any signal structure (post, SPT, ladder, hoops, platform, handrails, or
screening) below 4640mm above rail level shall normally encroach within 1624mm of
the running edge
b) where the above is not achievable, an absolute minimum distance of 1364mm
may be used in case of difficulty, such as where sighting is obstructed by OLE
masts, but only after agreement with the Gauging Engineer Team, Railway System
Engineering for that route.
c) any further reduction (e.g. to take advantage of the curvature of the vehicle gauge)
is subject to individual site assessment by the with the Gauging Engineer Team,
Railway System Engineering for that route.
A straight post shall not be installed between two lines unless there is a minimum
distance of 2728mm, plus the width of the widest part of the structure, between
running edges.
See section 8 or horizontal and vertical increases due to canted and curved track.
Signals must be installed so that they do not infringe the standard structure gauge
unless the sighting form indicates that specific authority has been given by the with
the Gauging Engineer Team, Railway System Engineering for that route.
When sighting signals, the appropriate signal structure drawings shall be consulted
to enable the width of the structure or the position of the signal post centre line to be
calculated. When positioning ground signals, the detailed lower sector structure
gauge in section 7 shall be used.
Page 7 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Page 8 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Page 9 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Page 10 of 18
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Ref:
Issue:
Date:
Compliance date:
CANT
HORIZONTAL
#
VERTICAL
RADIUS OF CURVE m
100
257
10
33
22
200
128
20
65
43
300
85
30
97
64
400
64
40
129
86
500
51
50
161
107
750
34
60
193
128
1000
26
70
225
150
1500
17
80
257
171
2000
13
90
289
192
100
320
214
NOTES:
110
352
235
120
383
256
130
415
277
140
446
299
150
477
320
160
509
342
170
540
363
180
571
385
190
602
406
200
632
427
Page 11 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
9 Walkways
The requirements for walkways given in NR/SP/OHS/069 are illustrated in Figure 1.
This shall be increased to 2406mm adjacent to an unboarded conductor rail, or
2100mm where the maximum permitted speed exceeds 100mph.
NOTE The 2100mm still applies where speed exceeds 125mph even though staff access is
prohibited, since traffic can be temporarily restricted to allowaccess. See section 8 for horizontal
increases on the above figures due to canted and curved track. The width of the walkway is to be
700mm.
10 Cable Routes
The requirements are illustrated in Figure 1. The normal minimum distance of a
cable route is 2000mm from the running edge, passing on the trackside of apparatus
cases, signals, overhead line masts and other obstructions. However, a reduced
clearance of 1250mm from the running edge is permitted in case of difficulty. (If this
is not achievable, the supervisor should be consulted.) Where necessary, a distance
of 2600mm from the running edge shall be provided to minimise interference in
signalling and telecoms cables. No increases on the above figures are required due
to canted and curved track. Where necessary, the cable route may be positioned
beneath the walkway, provided the lids are flush with the surface.
A troughing route shall not be installed between two lines unless there is a minimum
distance of 4100mm between running edges.
Page 12 of 18
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Ref:
Issue:
Date:
Compliance date:
Figure 3 - Layout for Location Cases and Cable Route Typical Arrangement (1)
Page 13 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Figure 4 Layout for Location Cases and Cable Route Typical Arrangement (2)
Page 14 of 18
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Ref:
Issue:
Date:
Compliance date:
Figure 5 - Layout for Location Cases and Cable Route Typical Arrangement (3)
Page 15 of 18
Ref:
Issue:
Date:
Compliance date:
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
NOTE The location identification in this example is not in the preferred position.
Page 16 of 18
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Ref:
Issue:
Date:
Compliance date:
TYPICAL GUARD RAIL ARRANGEMENT WHEN THERE IS LESS THAN 3 METRES TO THE
RUNNING RAIL (Cases at right angles to the track - preferred)
Location Cases
0.5m
Guard Rail
0.5m
0.5m
0.5m
0.5m
0.5m
Less
than
3m
0.25m
Not to scale
2m
2m
Less
than
3m
Guard Rail
0.5m
0.5m
0.5m
Location Cases
TYPICAL GUARD RAIL ARRANGEMENT WHEN THERE IS LESS THAN 3 METRES TO THE
RUNNING RAIL (CasesNEAREST
parallel to the track - non preferred)
Page 17 of 18
NR/L3/SIG/11303/2G05
4
03/03/2012
03/03/2012
Ref:
Issue:
Date:
Compliance date:
GUARD RAIL
1100mm
500mm
Ground Level
600mm
Guard Rails
set in concrete
1000mm
2000mm
Type 25-6
3 off
ELBOW
Type 15-6
2 off
CRUCIFORM BRACKET
Type 26-6
1 off
Heavy Gauge
4.05 mm thick
TOP
1965 mm Long
1 off
CENTRE
965 mm Long
2 off
VERTICAL
1680 mm Long
3 off
Page 18 of 18