Documente Academic
Documente Profesional
Documente Cultură
1 PRELIMINARIES
Code
1.0
1.1
Description
Rupiah
TENDERING
Preparation and Submission of the Tender
The tenderer will be provided with:
(a) One (1) copy of the Tender Booklet which comprises:
1.00 Form of Tender and Annexures.
2.00 Contract Agreement.
3.00 Conditions of Contract.
4.00 Method of Measurement.
5.00 Specification.
6.00 Bill of Quantities.
7.00 Final Summary.
8.00 List of Tender Drawings.
9.00 Project Directory.
(b) One (1) copy of the Specification
(c) One (1) set of Tender Drawings
These documents and drawings are referred to collectively as the Tender Documents.
The Tender Booklet shall be filled in and returned in a sealed envelope as directed in the
invitation to tender
The tenderer is to note that the Employer reserves the right not to accept the lowest
or any tender, and in no case will expenses incurred by the tenderer in the
preparation of his tender be reimbursed.
The tenderer's priced Bill of Quantities will be checked for arithmetical errors and for
consistency by PT. Arcadis Indonesia. The tenderer is to ensure that all extensions,
casts and transfers are carefully checked and that the unit rates are consistent
before finalising the Bill of Quantities for inclusion in the tender submission.
To Collection Rp
6/6
25.000.000,00
1.3
Description
Operating Licence
The tenderer should note that he is required to submit with his tender a
copy of his Surat Izin Usaha Jasa Konstruksi (SIUJK) or his Surat Tanda
Daftar Rekanan (STDR), whichever is applicable. The validity of the SIUJK
or STDR shall be maintained throughout the course of the Contract. The
Contractor shall indemnify the Employer against any loss or damage which
he may suffer through the Contractor's failure to ensure that the SIUJK or
STDR is valid. If the tender is returned without an accompanying copy of
the SIUJK or STDR it may be disqualified.
Tenderer to Visit the Site
The tenderer is advised to visit the Site and fully acquaint himself with the nature,
extent, characteristics and practicability of the Works. The tenderer shall include in
his tender for all costs in respect of the availability or lack of access, restrictions on
storage and working space, the nature of the ground, the proximity of adjoining
structures and roads, the local regulations affecting use of the Site and any other
limitation imposed by the Site and its surroundings. No claim resulting from failure
to do so will be admitted.
The Contractor shall accept the Site as found on the Commencement Date and at
his own expense shall clear the Site of any debris or rubbish.
1.4
500.000,00
600.000,00
1.5
Rupiah
Alterations to Text
The tenderer shall not make any alteration to the Tender Documents (other than as
specifically allowed by the Tender Documents themselves) except on the written
instructions of the Project Manager or of PT. Arcadis Indonesia. Unauthorised
amendments will be ignored and may lead to the disqualification of the tender.
To Collection Rp.
6/7
1.000.000,00
2.100.000,00
Description
Rupiah
1.6
Tendered Amount
All pricing shall be in Rupiahs.
The unit rates set down by the tenderer against each item in the Bill of Quantities,
unless expressly provided to the contrary, shall be held to include for the supply of
all Materials, Plant, labour, equipment, supervision, all overhead costs, profit, and
any other expense necessary to complete the Works to the full requirements of the
Tender Documents.
1.7
1.8
Type of Tender
The tenderer is required to submit a fixed price lump sum tender.
The quantities incorporated into the Tender Booklet are for guidance only and are at
the sole risk and responsibility of the tenderer. The quantities themselves will not
form part of the Contract.
To Collection Rp.
6/8
5.000.000,00
Description
Rupiah
PROJECT PARTICULARS
Description of the Works
The Works included in this Contract comprise, in general terms only, the road and
drainage works of River Mookervart Bridge to the proposed Daan Mogot City.
The Contractor shall satisfy himself as to the full extent, character and nature of the
Works.
2.2
2.3
2.4
50.000.000,00
Description
2.4
2.5
Rupiah
The Contractor shall comply with all requirements of the Estate Regulations
Governing Construction Activities, a copy of which is attached as an appendix to
these Preliminaries, and shall allow for all costs associated therewith.
For the purposes of this Contract, the term Building Block Owner as used in the
Estate Regulations Governing Construction Activities shall mean the Contractor. All
obligations and liabilities ascribed to the Building Block Owner shall be carried out or
borne by the Contractor at his sole cost and responsibility.
To Collection Rp.
5.000.000,00
6/10
BILL NO.1 PRELIMINARIES
Code
Description
3.0
CONTRACT PARTICULARS
3.1
Conditions of Contract
The Contractor will be required to enter into a formal contract with the Employer
executed under hand and based on the conditions incorporated as Section 3.00
Conditions of Contract.
Rupiah
A list of the clauses contained in the Conditions of Contract is set out hereunder. If
the tenderer considers that any of the clauses in the Conditions involves expense
which has not been allowed for elsewhere in the tender, he shall set against those
clauses the money value for complying with the requirements of the clause.
1. Definitions.
2. Interpretation.
3. Obligations of the Contractor.
4. Assignment and Subletting.
5. Commencement, Completion and Sectional Completion.
6. Defects Liability.
7. Payment.
8. Project Managers Instructions.
9. Increase or Decrease in Costs.
10. Type of Contract and Quantities.
11. Statutory Obligations, Notices, Fees and Charges.
12. Contractors Superintendence.
13. Insurance Against Injury to Persons and Property.
14. Insurance of the Works.
15. Termination by the Employer due to default by Contractor.
16. Termination by the Employer for Convenience.
To Collection Rp.
6/11
8.000.000,00
Description
Rupiah
5.000.000,00
Description
Rupiah
(a)
The Works, or Sections or parts thereof, are in the opinion of the Project
Manager ready for occupation and/or use.
(b)
All services are tested and operating satisfactorily as specified and all
specified guarantees, indemnities and/or warranties have been handed over
to the Project Manager.
(c)
(d)
15.000.000,00
Description
Rupiah
3.4
Approval of Programme
The submission to and approval by the Project Manager of the Programme (and any
revisions thereto) shall not relieve the Contractor of any of his duties,
responsibilities, liabilities or obligations under the Contract.
To Collection Rp.
6/14
26.000.000,00
Description
Rupiah
3.5
3.6
3.7
Discrepancies
All items shown or described in the Drawings or Specification are to be taken to be
included in both.
All existing levels and dimensions shown on the Drawings are believed to be
correct, but the Contractor shall verify the same at the Site.
Any discrepancy which occurs in either the Drawings or the Specification or in the
existing levels and dimensions shall immediately be brought to the attention of the
Project Manager.
3.8
25.000.000,00
Description
Rupiah
3.9
Pricing of Preliminaries
The Contractor shall be deemed to have priced these Preliminaries to include for
the cost of Preliminaries expended in the carrying out of work for which Provisional
Sums have been included in the Accepted Contract Amount. No adjustment will be
made to the total of the Preliminaries whether Provisional Sums are omitted or
expended.
3.10
Method of Measurement
The Bill of Quantities are measured in accordance with the principles of the
Standard Method of Measurement of Construction Works in Indonesia (the ISMM)
prepared by PT. Arcadis Indonesia. A copy of this document can be obtained from
the office of PT. Arcadis Indonesia by prior appointment.
3.11
Overtime
The Contractor shall be deemed to have allowed in the Accepted Contract Amount
for all overtime necessary to be worked in order to complete the Works within the
Time for Completion.
3.12
25.000.000,00
Description
Rupiah
Provisional Quantities
Items marked Provisional indicates the quantity of that item could not be calculated
with any accuracy at the time of tender.
In the Final Statement, the value of any item marked Provisional shall be omitted
in full and replaced with the value of the items calculated from the contractual unit
rate applied to the actual quantity measured in accordance with the Standard
Method of Measurement of Construction Works in Indonesia.
3.14
3.15
Minimum Wages
The Contractor must ensure that all workpeople employed on the Works, including
those employed by his subcontractors, are paid at least the minimum wage as
decreed by the Government from time to time.
The Contractor must confirm this in writing should the Employer so request.
To Collection Rp.
6/17
5.000.000,00
Description
Rupiah
INSURANCES
Insurance of the Works and Third Party Insurance
The Employer has placed insurances for the project and will be responsible for the
payment of the premiums. A copy of the policy can be examined by the Contractor
upon request.
The Contractor is hereby reminded that he shall be liable for and has indemnified
the Employer against any expense, liability, loss, claim or proceedings arising out of
the Contract and it is his sole responsibility to inform the Employer of any additional
or supplemental cover with he believes is required. The premium payable to the
insurers in respect of any additional or supplemental cover placed by the Employer
at the behest of the Contractor shall be borne by the Contractor.
The insurance policy is subject to certain excesses or deductibles which shall be
borne by the Contractor and, if not paid by him, may be deducted by the Employer
from any sums due or to become due to the Contractor or be recovered as a debt
due from the Contractor.
Any reduction in the level of these excesses requested by the Contractor will be
arranged by the Employer, but all additional premiums which may thereupon
become due shall be borne by the Contractor.
Contractors Equipment and Temporary Works shall be at the sole risk of the
Contractor or his subcontractors or any nominated Subcontractor or Direct
Contractor and are not covered by the Employers insurances. Any insurances in
respect of risks to Contractors Equipment and Temporary Works shall be arranged
by the Contractor or his subcontractors or any nominated Subcontractor or Direct
Contractor as the case may be.
4.2
8.000.000,00
Description
Rupiah
4.3
4.4
4.5
12.500.000,00
Description
Rupiah
GENERAL CONDITIONS
Site Management and Establishment Costs
The Contractor shall allow for all on and off site management and establishment
costs.
The Contractor shall provide an organisation chart showing a full and detailed list of
his site supervisory staff for the Works for the approval of the Project Manager. The
list shall include all relevant details of each member of staff including his/her
function, position, duties, qualifications, experience, age and length of employment
with the Contractor. The organisation chart shall also indicate the site supervisory
staff responsible for remedial works during the Defects Liability Period. The
provision of the organisation chart and the Project Manager's approval thereof shall
not limit the Contractor's responsibility and obligations in respect of adequate
staffing and in the event additional staff are considered necessary to properly and
effectively supervise the execution of the Works, the Contractor shall provide such
additional staff at no extra cost to the Employer.
The Contractors project manager and assistant project managers shall be capable
of receiving verbal and written instructions in Indonesian and English. Any
instruction given to the Contractors project manager by the Project Manager shall
be deemed to have been issued to the Contractor.
All senior site supervisory staff shall be to the approval of the Project Manager who
shall have the absolute right and authority to withdraw his approval as and when he
deems it to be necessary and proper without assigning any reason thereto.
None of the senior site supervisory staff may be changed without the prior approval
of the Project Manager.
5.2
Contractors Equipment
The Contractor shall allow for all Contractors Equipment necessary for the proper
execution of the Works.
The Contractor shall note that payment for Contractors Equipment in monthly
progress payments shall be made progressively throughout the construction period
with due regard for periods during which it is in use. Full or majority payment at the
commencement of the Works on the grounds that the equipment is purchased,
imported or mobilised will not be considered.
To Collection Rp.
6/20
25.000.000,00
5.3
Description
Rupiah
Contractor's Labour
The Contractor shall allow for all labour necessary for the proper execution of
the Works.
The Contractor shall be entirely responsible for all labour employed on the Works.
The Contractor shall allow for complying with all Government legislation and
regulations in respect of labour currently in force and accept the risk of any
impending or future legislation or regulation or other condition which alters any
existing obligation or imposes new obligations.
The Contractor shall allow for all costs in respect of labour, including but not limited
to:
(a) annual and public holidays.
b) travelling time, expenses, fares and transport.
(c) non-productive time and other expenses in connection with overtime.
(d) incentive and bonus payments.
(e) any other payments and charges arising from the employment of
5.4
Contractors Employees
The Contractor shall provide and employ in connection with the execution of the
Works:
(a) only such technical staff as are skilled and experienced in their respective
trades and such foremen and leading hands as are competent to give proper
supervision to the work they are required to supervise.
(b) such skilled and semi-skilled labour as is necessary for the proper and timely
execution of the Works.
The Contractor shall, if required by the Project Manager, deliver to the Project
Manager daily reports in such form as the Project Manager may prescribe showing
in detail the site supervisory staff and the members of the various classes of labour
employed by the Contractor on the Works.
5.5
15.000.000,00
Description
5.5
5.6
5.7
Rupiah
The Contractor shall, within 14 days after the date of the Letter of Award present, for
the approval of the Project Manager, a comprehensive Site Safety Programme and
the name of the designated Site Safety Officer. Approval of this programme and the
officer shall not relieve the Contractor of any of his responsibilities in respect of site
safety.
The Site Safety Officer shall meet with his counterpart from the Project Managers
staff on a weekly basis to review the Site Safety Programme.
As a minimum the following safety requirements will be enforced:
(a) Hard hats and work shoes or boots are to be worn at all times whilst on Site.
(b) Use of protective devices, such as safety goggles, face shields, respirators,
gloves, safety lines and belts, hearing protection, dust and fume masks and
the like, is mandatory.
(c) No alcohol use is allowed at any time immediately before or during work
hours.
(d) The Site is to be kept clean. All debris is to be placed in designated locations
and removed on a daily basis.
(e) Provision of a first aid post.
5.8
Visitors
The Contractor shall not allow any unauthorised visitors into the Site. He shall keep
a visitors book for persons authorised to visit the Site and shall provide for their use
hard hats, protective clothing and boots.
To Collection Rp.
6/22
15.000.000,00
Description
5.9
5.10
Rupiah
In cases where no particular standard is named for any material or item of plant to
be used in the Works, the relevant ASTM, ANSI, ASHRAE, BS, DIN, JIS or other
equivalent international standard, where one exists, shall apply. However, provided
that the Contractor satisfies the Project Manager as to their equivalence, materials
or plant may be suplied to national standards other than those specified. The
Project Manager shall be the sole judge of equivalence.
5.11
Methods of Working
Methods of working may be varied by the Contractor to suit the actual conditions
encountered provided the design intent is fulfilled and the quality of the end product
complies encountered provided the design intent is fulfilled and the quality of the
end product complies with the Contract. Such alternative methods of working shall
be agreed with and approved by the Project Manager before implementation.
5.12
5.13
25.000.000,00
Description
Rupiah
5.14
Testing of Materials
The Contractor shall carry out tests on all materials and plant required by the Project
Manager to be tested at his own expense and shall pay all charges in connection
with tests ordered by the Project Manager to be carried out by others.
The establishment of a testing laboratory on the Site and/or the use of an
independent testing facility is at the option of the Contractor, provided always that
the Project Manager shall have the right to instruct testing to be carried out at an
independent testing facility at no extra cost to the Employer on a case-by-case
basis.
The bench marks must be properly protected. Should any bench mark be displaced
or lost it shall be replaced immediately at the Contractors expense.
15.000.000,00
To Collection Rp.
6/24
15.000.000,00
Description
Rupiah
To Collection Rp.
5.15
5.16
Dimensions
Figured dimensions are to be taken in preference to scaled in all cases. Before
commencing any work or ordering any materials the Contractor must verify all
dimensions. If any discrepancies are found they must immediately be brought to the
notice of the Project Manager. No claim for loss arising out of discrepancies will be
allowed which in the opinion of the Project Manager would have been discovered
had reasonable care been taken by the Contractor.
The Contractor shall not use any quantities contained in these documents for the
purposes of ordering materials.
To Collection Rp.
6/25
20.000.000,00
Description
Rupiah
5.18
5.19
14.000.000,00
Description
Rupiah
5.20
5.21
5.22
5.22
5.23
Advertisements
The Contractor, his subcontractors or any nominated Subcontractor shall not,
without the consent of the Project Manager, affix or exhibit or place upon any part of
the Site or the Works, signboards, placards, posters, banners, or any other
advertising material.
Publicity releases related to the Works shall first be submitted to the Employer and
the Project Manager for approval.
5.24
10.000.000,00
Description
Rupiah
Delivery of Materials to the Site and Removal of Spoil and Surplus Materials from
the Site
The Contractor shall comply with the requirements of the Estate Manager, the local
authority and the police in respect of the use of motor vehicles delivering materials
to or removing spoil or surplus materials from the Site and shall allow for all costs in
connection therewith.
5.26
Materials to be New
All materials used in the Works shall be new. No materials to be used in the
Permanent Works shall be used in the Temporary Works prior to their incorporation
in the Permanent Works.
5.27
5.28
Temporary Easements
The Contractor shall obtain the consent of adjoining property owners should there
be a need for temporary easements or any other manner of physical encroachment
on their property.
5.29
80.000.000,00
Description
Rupiah
6.0
SPECIFIC CONDITIONS
6.1
6.2
Bending Schedules
The Contractor shall prepare bending schedules for all steel bar
reinforcement shown on the Drawings. The format of bending schedules shall
be as specified in BS 8666. All bending schedules shall be submitted to the
Project Manager for comment.
Should the Contract provide for the remeasurement of steel bar reinforcement, a
copy of the bending schedules shall be provided to PT. Langdon & Seah Indonesia.
The Contractor shall allow for all costs in connection with the preparation and
submission of bending schedules.
6.3
Shop Drawings
The Contractor shall, at his own expense, prepare and submit for the approval of the
Project Manager copies in duplicate (in the first instance) of detailed shop drawings
of the Works in order to facilitate fabrication and construction. The drawings shall
be submitted a minimum of 30 days prior to the required approval date.
The shop drawings prepared by the Contractor shall additionally include
coordinated, multi-service shop drawings and builders work drawings for the
mechanical, electrical and plumbing installations (even if those installations are
carried out by nominated Subcontractors or Direct Contractors). Coordinated, multiservice
shop drawings shall be overlaid on the structural shop drawings to ensure
there is no conflict between the various elements of the building.
To Collection Rp.
6/29
50.000.000,00
Description
Rupiah
6.4
As-built Drawings
Throughout the construction period the Contractor shall maintain an up-to-date set
of as-built drawings for the various parts of the Works which have been completed
in accordance with the Contract. The Contractor shall provide the Project Manager
with as-built drawings in the form of one electronic copy, two sets of prints and one
set of transparencies as a pre-condition to the issue of the Taking-Over Certificate.
6.5
Avoidance of Nuisance
The Contractor shall take all reasonable measures to avoid nuisance to residents of
and visitors to adjoining properties and to the public.
All Contractors Equipment shall be fitted with radio and TV.
interference suppressors.
The Contractor shall endeavour to minimise noise pollution and prevent dust from
arising as a result of his activities. The Contractor shall regularly spray with water
those locations or operations which produce dust so as to reduce or eliminate this
potential nuisance.
All consequential claims for damages or compensation arising from the failure
of the Contractor to take or implement such measures shall be borne by the
Contractor.
To Collection Rp.
6/30
7.000.000,00
Description
Rupiah
To Collection Rp.
6.6
Pest Control
The Contractor shall ensure the Works remains free of pests such as rodents,
mosquitoes and the like and shall allow for the employment of a pest control
specialist if such is required.
6.7
6.8
5.000.000,00
Description
Rupiah
To Collection Rp.
6.8
6.9
6.10
50.000.000,00
Description
Rupiah
6.11
6.12
Identification Badges
All of the site based employees of the Contractor and his subcontractors, and of any
nominated Subcontractor shall be provided with approved identification badges
incorporating a photograph, which are to be worn continuously whilst they are on the
Site, and by which they may be identified by contractor and grade of employee.
Any employee who does not wear their identification badge will be prevented from
entering the Site.
6.13
5.000.000,00
Description
Rupiah
TEMPORARY WORKS
Temporary Access
The Contractor shall allow for providing and maintaining temporary roads,
hardstandings, working platforms, bridges, crossings, and the like necessary for
carrying out the Works and shall clear away on completion of the Works and make
good all damage done.
The alignment of the temporary roads, hardstandings, bridges, crossings and the
like shall be decided in agreement with the Project Manager who will require them to
follow the lines of the permanent roads and paths wherever possible.
7.2
Temporary Buildings
All temporary buildings are to be the approval of the Project Manager and are to
meet the requirements of the relevant authorities.
7.3
7.4
7.5
5.000.000,00
Description
Rupiah
7.6
Temporary Site Accommodation for the Employer and the Project Manager
Temporary site accommodation for the Employer and the Project Manager will be
provided by the Employer.
7.7
Signboard
The marketing signboard will be provided by the Employer. Construction signboard
shall be provided by the Contractor.
7.8
Site Fencing
The Contractor shall provide, erect and maintain temporary fencing and gates
to secure the site and shall clear away on completion of the Works. The
Contractor shall alter, shift and adapt from time to time as required by the
7.9
Telephones
The Contractor shall provide sufficient telephones for his own use and for the use of
his subcontractors.
The Contractor shall allow for the payment of all charges for telephones provided for
his own use or the use of his subcontractors.
The Employer will make his own arrangements for telephones for his own use and
for the use of the Project Manager.
7.10
Water
The Contractor shall provide all necessary clean, fresh water for use in the Works,
including that required for the use of his subcontractors, any nominated
Subcontractors and any Direct Contractors, and including that needed for testing
and commissioning.
The Contractor shall provide all temporary meters, mains, storage tanks and
distribution pipework as necessary to provide water wherever required.
The Contractor shall maintain and adapt whenever and wherever necessary
throughout the construction period, pay all costs and charges in connection
therewith and clear away on completion.
To Collection Rp.
6/35
5.000.000,00
Description
Rupiah
To Collection Rp.
7.11
7.12
7.13
5.000.000,00
Description
Rupiah
To Collection Rp.
Removal of Water
The Contractor shall allow for providing all pumping that may be required to keep
the Works dry down to the level of the bottom of the excavations whether from rain,
springs, or any other source. No accumulation of water will be permitted at any time
during the progress of the Works.
Disposal of water shall be in accordance with the regulations and requirements of
the appropriate authority.
7.15
Temporary Drainage
The Contractor shall allow for providing all necessary temporary channels and
temporary drainage works which may be necessary to drain off water from the Site
and to prevent nuisance due to run-off on to adjacent land. The Contractor shall
remove the temporary drainage as necessary as it is replaced by the permanent
surface drainage work.
7.16
Fire Protection
The Contractor shall allow for keeping the Site safe from fire hazard. The Contractor
shall take all necessary precautions including those specified by the insurer of the
Works and shall provide all necessary fire fighting equipment to the satisfaction of
the Project Manager.
In particular, a water supply of adequate pressure shall be installed to the
highest point of the structure at all times with sufficient hoses to reach all
parts of the building.
The Contractor shall properly train designated staff in the operation of the fire
fighting equipment and in the implementation of fire evacuation procedures. Such
training shall include regular fire drills throughout the construction period.
No inflammable goods such as fuel oils, oil based paints, kerosene, thinners,
cellulose lacquers, bitumen, bitumen based products and the like shall be stored in
the building under construction.
7.17
Lightning Protection
The Contractor shall provide and maintain an effective temporary lightning
protection system for the structure under construction and for all hoists and cranes.
The lightning protection system is to be of the type that conveys any lightning
discharge directly and safely to the ground.
To Collection Rp.
6/37
5.000.000,00
7.19
7.20
Description
Rupiah
To Collection Rp.
Protection of the Works
The Contractor shall provide for covering up and protecting the Works from
inclement weather.
The Contractor shall provide full and adequate protection for all finished surfaces
and for all materials and plant which may be subject to damage and shall be
responsible for making good all damage to such finished surfaces, materials and
plant occurring before the date of issue of the Taking-Over Certificate.
Protection must be applied or provided as soon as a surface is finished and/or
materials and plant arrive on the Site or as may be otherwise desirable and such
protection shall be maintained in effective condition throughout the construction
period.
Where the product supplied includes a protective covering or coating the Contractor
shall repair, replace or otherwise maintain such covering or coating in an effective
state.
Removal of Rubbish
All rubbish, packing material, surplus materials and the like are to be removed from
the Site or surrounding areas as soon as is possible and at least once daily during
the construction period so as to maintain unhindered access to and easy inspection
of all work.
The Contractor shall provide and maintain for as long as required for the
construction of the Works all necessary temporary external rubbish chutes.
No burning of rubbish on the Site will be allowed.
Cleaning-up
The Contractor, shall upon completion leave the whole of the Works and the
surrounding area in a clean and tidy state, to the satisfaction of the Project
Manager.
To Collection Rp.
6/38
5.000.000,00
Description
Rupiah
To Collection Rp.
8.0
8.1
Direct Contractors
The term Direct Contractor shall mean a contractor executing any works not
forming part of the Works which has entered into a separate contract with the
Employer and is under the coordination of the Contractor.
The Conditions of Contract applicable to the employment of Direct Contractors can
be viewed at the offices of PT. Langdon & Seah Indonesia by prior appointment.
8.2
8.3
(a)
(b)
(c)
(d)
(e)
Provision of power, lighting and water specifically required for the work
executed by Direct Contractors including for the testing and commissioning
thereof (excepting that power for the Direct Contractors' own welding works
shall be provided by the Direct Contractor).
(f)
5.000.000,00
Description
Rupiah
To Collection Rp.
8.3
8.4
5.000.000,00
Description
Rupiah
To Collection Rp.
COLLECTION
Page No.6/6
Page No.6/7
Page No.6/8
Page No.6/9
Page No.6/10
Page No.6/11
Page No.6/12
Page No.6/13
Page No.6/14
Page No.6/15
Page No.6/16
Page No.6/17
Page No.6/18
Page No.6/19
Page No.6/20
Page No.6/21
Page No.6/22
Page No.6/23
Page No.6/24
Page No.6/25
Page No.6/26
Page No.6/27
Page No.6/28
Page No.6/29
Page No.6/30
Page No.6/31
25.000.000,00
2.100.000,00
5.000.000,00
50.000.000,00
5.000.000,00
8.000.000,00
5.000.000,00
15.000.000,00
26.000.000,00
25.000.000,00
25.000.000,00
5.000.000,00
8.000.000,00
12.500.000,00
25.000.000,00
15.000.000,00
15.000.000,00
25.000.000,00
15.000.000,00
20.000.000,00
14.000.000,00
10.000.000,00
80.000.000,00
50.000.000,00
7.000.000,00
5.000.000,00
To Collection Rp.
497.600.000,00
6/41
BILL NO.1 PRELIMINARIES
Code
Description
Rupiah
To Final Summary Rp
6/42
497.600.000,00
50.000.000,00
5.000.000,00
5.000.000,00
5.000.000,00
5.000.000,00
5.000.000,00
5.000.000,00
5.000.000,00
5.000.000,00
5.000.000,00
592.600.000,00