Documente Academic
Documente Profesional
Documente Cultură
BMS-Istimewa 0
DATE : SHEET :
20 Desember 2016 1 Of 32
REVISION TABLE
Pag Pag
Pag REVISION REVISION REVISION
e e
e
A B 0 1 2 3 A B 0 1 2 3 A B 0 1 2 3
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
1 X
2 X
3 X
4 X
5 X
6 X
7 X
8 X
9 X
10 x
11 X
12 X
13 X
14 X
15 X
16 X
17 X
18 X
19 x
20 X
21 X
22 X
23 X
24 X
25 X
26 X
28 X
DAFTAR ISI
1. TITILE
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
....................................................................................................................................................
5
2. SCOOPE
....................................................................................................................................................
5
3. CODE AND STANDARD
....................................................................................................................................................
5
4. GENERAL
....................................................................................................................................................
6
5. MATERIAL HANDLING
....................................................................................................................................................
6
6. AREA CLASIFICATION
....................................................................................................................................................
7
7. TRANSFORMERS
....................................................................................................................................................
7
8. SWITCHGEAR
....................................................................................................................................................
8
9. MOTOR CONTROL CENTER
....................................................................................................................................................
10
10. PANEL BOARD
....................................................................................................................................................
11
11. UNINTERRUPTIBLE POWER (UPS) SYSTEMS
....................................................................................................................................................
11
12. DC RECTIFIER
....................................................................................................................................................
12
13. MOTORS
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
....................................................................................................................................................
12
14. WIRING METHODE
....................................................................................................................................................
13
15. UNDERGROUND INSTALLATION
....................................................................................................................................................
17
16. TRAY INSTALALTION
....................................................................................................................................................
19
17. ABOVE GROUND CONDUIT INSTALLATION
....................................................................................................................................................
21
18. GROUNDING
....................................................................................................................................................
24
19. PAINTING
....................................................................................................................................................
26
20. TESTING AND INSPECTION
....................................................................................................................................................
1 TITLE :
BMS. ELECTRICAL AND POWER PROCEDURE
2.0. SCOPE :
2.1. This specification defines the minimum requirement governing the
installation of all electrical system. Its proposal is to supplement the
construction drawings and to serve as an installation guide for any activities not
detailed on the drawings.
2.2. In the event that any installation requirement is not fully directed by
the drawings or this specification, the project engineer or his representative will
provide specific guidance.
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
4.0. GENERAL :
4.1. Materials and workmanship shall be the best of their respective
kinds and in full accord with the standard with the standards of
modern electrical construction.
4.2. In the event of conflict between this specification and the drawings,
refer to company for resolution.
4.3. Should conditions develop that render original locations of
equipment, cable ladder routing or termination details unsuitable,
the contractor shall call attention to this fact and obtain approval for
alternate location, mounting or termination method before installing
the work.
4.4. Contractor shall not make any field weld son vessels, tanks, pipes,
or equipment without the prior approval by the company.
4.5. All civil and mechanical works which are a prerequisite for the
installation of electrical equipment shall be performed by the
contractor in accordance with relevant specifications and issued
drawings.
7.0. TRANSFORMERS :
7.1. In general the following type of transformers shall be supplied.
Contracts shall ensure that the transformer to be installed meets
the required specification prior to actual installation.
7.1.1. 3 KVA thru 20KVA
Pad mounted, outdoor, totally enclosed, distribution type,
oil immersed transformers.
Indoor/Outdoor, totally enclosed, substation type, oil
immersed transformers.
7.1.2. 70KVA
Outdoor, totally enclosed, pressurized type, oil immersed
transformers.
Transformers shall be supplied completed and ready for
installation. Contractor shall prepare transformer
foundation pad and install transformer in accordance with
vendors recommendations and the construction drawings.
7.2. Lifting lugs shall be provided for lifting the complete transformer.
The transformer shall never be moved or lifted by placing jacks or
tackle on the radiators, the high voltage and low voltage
compartments or other attachments.
7.3. The contractor shall ground the transformer tank to the system
ground grid, prior to termination of any external electrical
connections.
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
7.4. Line connections must be made in a manner that will not place
undue strain on the bushings and shall use appropriate type and
size of lug. High voltage cable terminations shall be made using
rubber moulded stress cone-type cold shrink terminations kits.
Vendor recommended minimum electrical clearances shall be
maintained.
7.5. Changing transformer tap setting must be made with the
transformer de-energized. The tap changer must not be operated
while the transformer is energized.
7.6. Contractor shall check that the transformer oil level is at the
appropriate ambient temperature gauge level before voltage is
applied to the transformer. For gas filled units confirmation of
positive tank pressure gauge reading shall also be made.
7.7. Pad mounted type transformers shall be vented to the atmosphere
before being placed into service, if they have been pressurized for
leak tests or storage. Before leaving the unit, the cabinet should be
closed utilizing the padlocking provision and any other auxiliary
locking means that may be supplied.
shall be level and smooth. Anchor bolts and hold down clips will be
required only if the motor control center will be installed outdoors.
2 All of the plug in modules and blank panels of the motor control
center shall be removed and a complete inspection shall be made of
the structure after setting in place. All bus, bus support and
structure bolts shall be tasted for tightness. A visual inspection
shall be made for damaged bus supports and busses and for debris
in the area of the busses.
3 All plug in units shall be inspected for tightness of factory cable
connections before reinstallation in the motor control center.
4 All wiring shall be checked for loose connections and to assure wires
are tagged in accordance with the Manufactures final approved As
Built drawings.
5 Circuit Breakers and Fuses.
1 If the plug-in units contain molded case circuit breakers, it
shall be verified that each unit contains the exact circuit
breaker as listed in the Manufactures approval drawings.
2 If the plug in units contain fused disconnect switches or fused
control circuits, it shall be verified that the correct size
switches and correct fuses are installed in each unit as listed
in the manufacturers approved drawings.
3 If the plug-in units contain molded case circuit breakers with
instantaneous magnetic trips, each trip shall be set as shown
on the one line diagram as a preliminary setting. If in
operation the circuit breaker trips due to motor starter inrush,
the trip setting may be adjusted to the next higher setting,
one step at a time, until the circuit breaker does not trip. If
the final trip setting differs from that shown on the one line
diagrams, the new setting shall be recorded on the As-Built
one line diagrams.
6 Magnetic Starters
1 If the plug in unit contains a magnetic motor starter, it shall
be verified that the starter size is the same as listed on 5the
Manufacturers approved drawings, that the correct auxiliary
interlocks are provided, that the starter coil voltage is correct,
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
2 Packing material (tape, cardboard, bracing etc) used inside the UPS
unit to protect the equipment against unusual stresses during
shipping shall only be removed after the equipment has been
installed at its final location.
3 The UPS unit shall not be installed near heat producing devices. A
minimum of 300 mm (12 inches) clearance should be allowed
around louvered panels to provide for adequate air flow.
4 Prior to termination of any external cabling, the UPS units A and
D.C input and output switches and circuit breakers shall be placed in
the OFF position.
5 See paragraph 11.0 for D.C. rectifier and battery
installation/commissioning.
6 Contractor shall confirm proper polarity of battery connections to
the UPS unit prior to energization.
7 With the connection correctly made. Check (measure) the A.C and
D.C input voltages at the terminals for correct magnitude. Position
the UPS unit A.C and D.C. input circuit breakers to the ON
position. Next turn on the A.C. output breaker. Check with meters
for proper output voltage, current and frequency.
For detailed equipment start-up and shout-down procedures and
adjustments refer to Vendor supplied instruction and operating
manual.
allow the cells to standard for at least 24 hours after filling. Adjust
rectifier equalize charge rate and time period in accordance with
battery Vendors operating instructions and fully charge the battery
bank. During charging do not allow the electrolyte temperature to
exceed 45oC (113oF). Check the electrolyte levels after charging
and adjust if necessary before putting the battery into service.
12.0. MOTORS:
12.1. All conduit connections to motor terminal boxes shall be by means
of threaded conduit hubs, with tapered pipe threads to ANSI
standard B2.1, with at least five (5) threads fully engaged. The
conduit assembly must from a weatherproof and dust-tight system
highly resistant to mechanical damage. Co.
12.2. Where armored cables are used in classified areas these shall be
terminated using division 1 approved cable terminations and seals.
These cables shall be PVC sheathed for corrosion protection and the
cable terminators should also be PVC sheathed or taped.
12.3. Flexible conduit connections to fixed motor junction boxes shall be
held to a minimum bending radius established by the particular
manufacturer. For type of flexible conduit to be installed in
classified and unclassified areas refer to section 16.8 and 19 of this
specification.
12.4. For motors equipped with slide rails, (or where adjustment is
available on the machine base plate) sufficient length of flexible
conduit/cable shall be left to permit the full motor travel adjustment
without staring the supply cables.
12.5. For medium voltage motors where motor leads splicing kits are
required, 3M Cold Shrink type 5321 thru 5324 or equal shall be
used. Cable terminations shall be made in accordance with the
issued drawings and instruction supplied by the kit material Vendor.
12.6. Control stations for motor driven equipment shall be mounted
adjacent to the equipment in accordance with issued drawings. The
start/Stop push buttons, manual/off/auto switches, etc., shall be
mounted as detailed on drawings.
13.1. General
13.1.1. The contractor shall install all cable and accessories as
listed on the issued project cable schedule and drawings.
13.1.2. Cable shall be installed in accordance with drawings.
The following segregation will be adhered to throughout the
facility:
a Medium voltage power cabling shall not occupy the
same enclosure, conduit, duct or tray with 600 volt or
less light and power conductors.
b Conductor of 600 volt or less light and power systems
and associated 120 volt A.C. System control cabling
shall be permitted to occupy the same enclosure,
conduit, duct or tray where all co.
c Conductors of A.C. and D.C. low voltage
instrumentation, control and communication system
shall not occupy the same enclosure, conduit, duct or
tray with conductors listed above. For detailed
description of power/instrument cabling segregations
requirements refer to specification VES-7112, section
6.2 thru 6.7.
13.1.3. All medium voltage power cabling within the plan
production area shall be installed underground utilized an
underground duct bank system. For pull boxes and duct bank
construction details refer to standard drawing STD-60-07.
13.1.4. Direct buried cables shall be acceptable for of-plot
services and for non essential plant utilities, where such are
located outside the production facility boundary. For
installation details refer to standard drawing STD-60-06.
13.1.5. In general, 600 volt or less in-plant electrical power
and control distribution shall be installed in overhead cable
tray utilizing tray rated/ armored cables as listed in section
13.2. Cable runs from the tray to the equipment served shall
be installed in rigid conduit or via PVC underground duct or
shall be properly supported armored cable.
13.1.6. For above ground installations, multiples of single
conductor wire, and/or multi-conductor cable run in rigid
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
15.5. For long span installations where there is only one support per cable
tray straight section, the splices should be located at points one-
quarter of the distance between supports where the load stresses
on the said rails will be a minimum. Cable trays shall be spliced
using only Vendor supplied coupling plate and flange fittings.
15.6. Electrical continually (metal of metal contact) shall be maintained at
splices between section of cable tray.
15.7. Site fabrication and cutting of section shall be kept to minimum. For
section that are site fabricated or cut, all sharp edges shall be
smoothed off and made so that no projections remain to damage
the cable. Steel fabricated units and tray shall be permanently
sealed against ingress of moisture by treating with Galvoweld or
equal.
15.8. After the cable tray is assembled and the cables are installed, all
knick, cuts, and other damage to the galvanized coating of steel
tray and support material shall be repaired as described above.
15.9. Cable Spacing, Positioning and Fastening
15.9.1. All cables shall be suitably fastened to the cable tray
every 1.8 m (6 feet) on horizontal runs, every 450 mm (18
inches) on vertical runs and every 450 mm (18 inches) on
turns.
15.9.2. Stainless steel cables ties (Thomas & Betts or company
approved equal) may be used for most fastening applications.
Cable ties in outdoor locations shall be resistant to ultraviolet
radiation.
15.9.3. Single conductor cables shall be fastened in groups
consisting of not more then one conductor per phase or
neutral where circuits are paralleled to prevent current
imbalance in the parallel conductor due to inductive
reactance.
15.9.4. Single conductor shall be securely bonded in circuit
groups are prevent excessive movement due to fault current
magnetic forces.
15.10.Installation of Cable in tray.
15.10.1. Each run of cable tray shall be complete before
installation of cable.
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
17.0. GROUNDING:
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI
18.0. PAINTING:
Surface treatment, primers and finishing shall be suitable for the
environmental conditions specified and as a minimum shall be in
accordance with the requirement of VES-5140, Surface preparation,
painting and Galvanizing.
20 i
Ri =
1000 +
2B
PROSEDURE ELECTRICAL POWER PT. BORNEO MITRA SINERGI