Documente Academic
Documente Profesional
Documente Cultură
D R A FT F IN A L R E P O R T
V O L 3 : E N V I R O NM E N T A L SO C I A L I M P A C T
AS S E S S ME N T
(ESI A)
ASSOCIATED CONSULTANTS LTD.
2015
P. O. Box M259,
Accra, Ghana
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
September, 2015
i
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Revision 2
Asscociated Consultants
33 Royalt Castle Road
Kokomlemle
P.O. Box M 259 Accra-Ghana
Tel: +233302237528
ii
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
TABLE OF CONTENTS
ACRONYMS ............................................................................................................................................... ix
LIST OF TABLES ........................................................................................................................................ x
EXECUTIVE SUMMARY ........................................................................................................................ xii
1.0 INTRODUCTION ............................................................................................................................ 1
1.1 Background ................................................................................................................................... 1
1.2 Project Objectives ......................................................................................................................... 1
1.3 ESIA Study Objectives ................................................................................................................. 2
1.4 ESIA Study Scope......................................................................................................................... 2
1.5 ESIA Methodology ....................................................................................................................... 2
1.5.1 Review of Relevant Literature .............................................................................................. 3
1.5.2 Field Work ............................................................................................................................ 3
1.6 Environmental and Social Impact Statement ................................................................................ 3
2.0 ENVIRONMENTAL POLICY AND INSTITUTIONAL FRAMEWORK ..................................... 4
2.1 Ghana Government Environmental Policy ................................................................................... 4
2.2 Legal and Institutional Framework ............................................................................................... 4
2.3 Emission Limit Values .................................................................................................................. 7
2.3.1 Ambient Air Quality ............................................................................................................. 7
2.3.2 Noise ..................................................................................................................................... 7
2.3.3 Water Quality ........................................................................................................................ 8
2.4 Road Policy and Administrative Framework ................................................................................ 9
2.5 Environmental Assessment Regulations and Procedures ............................................................. 9
2.6 Institutional Framework ................................................................................................................ 9
2.6.1 Institutional and Implementation Arrangements ................................................................. 10
3.0 DESCRIPTION OF PROJECT ....................................................................................................... 12
3.1 Project Location and Description ................................................................................................ 12
3.2 Project Components .................................................................................................................... 12
3.2.1 Design Standard .................................................................................................................. 12
3.2.2 Project Works ...................................................................................................................... 13
3.2.3 Horizontal and Vertical Alignments ................................................................................... 13
3.2.4 Pedestrian Facilities ............................................................................................................ 13
3.2.5 Traffic Control Devices ...................................................................................................... 13
iii
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
iv
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
v
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
6.8 Potential Environmental and Social Impacts of Community Development Project ................... 50
6.8.1 Positive Impacts .................................................................................................................. 51
6.8.2 Negative Impacts................................................................................................................. 52
7.0 MITIGATION MEASURES AND COMPLEMENTARY INITIATIVES ................................... 55
7.1 Mitigation Measures Construction Phase ................................................................................ 55
7.1.1 Water Quality ...................................................................................................................... 55
7.1.2 Soil Erosion and Sedimentation .......................................................................................... 55
7.1.3 Air Quality .......................................................................................................................... 55
7.1.4 Noise and Vibration ............................................................................................................ 55
7.1.5 Landscape Modification...................................................................................................... 56
7.1.6 Traffic Congestion .............................................................................................................. 56
7.1.7 Construction Camps ............................................................................................................ 65
7.1.8 Construction Wastes ........................................................................................................... 65
7.1.9 Public Utilities .................................................................................................................... 65
7.1.10 Disturbance to Guako Sacred Grove ................................................................................... 66
7.1.11 Land Acquisitions and Relocations..................................................................................... 66
7.1.12 Alternatives for taxi and tanker drivers............................................................................... 66
7.1.13 Vehicular-Pedestrian Conflicts ........................................................................................... 67
7.1.14 Public and Occupational Health and Safety ........................................................................ 67
7.2 Mitigation measures Operational Phase ................................................................................... 67
7.2.1 Drainage .............................................................................................................................. 67
7.2.2 Land Use Changes .............................................................................................................. 67
7.2.3 Health, Safety and Security ................................................................................................. 68
7.2.4 Interchange may be used as event poster wall / board ........................................................ 68
7.3 COST OF MITIGATION MEASURES ..................................................................................... 68
7.4 Climate Change Mitigation ......................................................................................................... 72
7.5 COMPLEMENTARY INITIATIVES ........................................................................................ 72
7.5.1 Prevention of the Spread of Diseases .................................................................................. 72
7.5.2 Road Safety Education Campaigns ..................................................................................... 72
7.5.3 Tree planting ....................................................................................................................... 72
8.0 EXPECTED RESIDUAL EFFECTS AND ENVIRONMENTAL HAZARD MANAGEMENT . 73
8.1 Residual Impacts ......................................................................................................................... 73
vi
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
vii
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
viii
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
ACRONYMS
AfDB African Development Bank
AIDS - Acquired Immune Deficiency Syndrome
DFR - Department of Feeder Roads
DUR - Department of Urban Roads
ECG - Electricity Company of Ghana
ESIA - Environmental and Social Impact Assessment
ESIS - Environmental and Social Impact Statement
ESMP - Environmental and Social Management Plan
EMU - Environmental Management Unit
EPA - Environmental Protection Agency
ESO - Environmental safety Officer
FC - Forestry Commission
FSD - Forest Services Division
GAMA - Greater Accra Municipal Area
GoG - Government of Ghana
GHA - Ghana Highway Authority
GRIDCo - Ghana Grid Company
GSS - Ghana Statistical Services
GWCL - Ghana Water Company Limited
GWMA - Ga West Municipal Assembly
HSP - Health and Safety Plan
HIV - Human Immune Virus
IFC - International Financial Corporation
ISS - Integrated Safeguard Systems
ISPS - Integrated safeguard Policy System
MRH - Ministry of Roads and Highways
NMT - Non Motorised Traffic
OS - Operational Safeguards
OSH - Occupational Safety and Health
PAP - Project Affected Person
PHC - Population and Housing Census
RFS - Road Fund Secretariat
ROW - Right-Of-Way
RSE - Road Safety & Environment
SME - Small and Medium Enterprise
STI - Sexually Transmitted Infections
TOR - Terms of Reference
WRC - Water Resources Commission
ix
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
LIST OF TABLES
Table 1: Ambient Air Quality Standards ...................................................................................................... 7
Table 2: IFC Noise Limits ............................................................................................................................ 7
Table 3: EPA Noise Limits ........................................................................................................................... 8
Table 4: Ghanaian and IFC Water Quality Discharge Standards ................................................................. 8
Table 5: Design Standards .......................................................................................................................... 12
Table 6: Location of Borrow Pits................................................................................................................ 13
Table 7: Haulage distance of Quarry Pits ................................................................................................... 14
Table 8: Location and Quantity of Sand .................................................................................................... 14
Table 9: Access routes and their lengths ..................................................................................................... 17
Table 10: Water quality of Sunkwa Stream ................................................................................................ 22
Table 11: The PM and TSP levels at ACP Junction were measured .......................................................... 24
Table 12: Ambient Noise levels (dBA) recorded at ACP Junction February 21, 2015 .............................. 24
Table 13: Population of Ga West Municipality .......................................................................................... 25
Table 14: Population size of the studied communities................................................................................ 25
Table 15: Wildlife Species encountered in the sacred groove during field surveys ................................... 28
Table 16: Annual Daily Traffic by Road .................................................................................................... 31
Table 17: Description of Intersection/Interchange Schemes ...................................................................... 34
Table 18: Comparison of 3-Tier with Signal and Rotary (2019-2043) ....................................................... 35
Table 19: Geographical Context and Policy Importance ............................................................................ 45
Table 20: Magnitude Criteria ...................................................................................................................... 45
Table 21 : Evaluation of Significance of Effect .......................................................................................... 46
Table 22: Summary of Environmental and Social Impacts ........................................................................ 46
Table 23: Potential Positive Impacts of Community Development Projects .............................................. 51
Table 24: Potential Negative Impacts of Community Development Projects ............................................ 52
Table 25: Staging of Construction Works and Traffic Diversion ............................................................... 58
Table 26: Mitigation measures and Cost..................................................................................................... 68
Table 27: Health and Safety Incident Recording Procedure ....................................................................... 74
Table 28: Details of Consulted Stakeholders .............................................................................................. 77
Table 29: Summary of Monitoring Responsibilities and Output ................................................................ 81
Table 30: Environmental Management responsibility of the Engineer....................................................... 84
Table 31: Environmental Management Responsibilities of Contractor ...................................................... 85
x
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
LIST OF FIGURES
xi
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
EXECUTIVE SUMMARY
The Government of the Republic of Ghana (GoG) in line with its effort to improve transportation
has implemented Accra Urban Transport Project Phase 1 as a result of a loan received from
African Development Bank (AfDB). As part of this, the GoG acting through the Ministry of
Roads and Highways (MRH) and Department of Urban Roads (DUR) has awarded a contract to
Messrs Associated Consultants Limited in Accra, Ghana to undertake a Detailed Engineering
Design of the Foundation, Traffic Management and Drainage Design of the Pokuase Interchange.
The proposed Pokuase Interchange, at the interchange of the Awoshie Pokuase road and the
Accra-Kumasi Highway at Pokuase has been designed by Messrs Associated Consultants
Limited for the Ministry of Roads and Highways through the Department of Urban Roads which
seeks to improve travel within and between the communities and also to remove the expected
bottleneck at the junction on completion of the main Awoshie Pokuase road project. Under
Ghanas environmental law, construction of roads and highways is classified as environmentally
critical and consequently subject to an Environmental and Social Impact Assessment, an
Environmental and Social Impact Statement has been prepared, which is presented hereunder.
Background
The proposed project involves the design and construction of a three-tier signalised interchange
at Pokuase ACP Junction. The first tier links Accra to Nsawam. It is the existing Accra-
Nsawam-Kumasi Highway. The third tier connects Awoshie road (currently under construction)
to Pokuase ACP-Kwabenya Road. The middle tier can be used to access Awoshie, ACP-
Kwabenya, Accra and Nsawam. The objective of the road project is to enhance urban mobility,
promote efficient, affordable transport services along the Awoshie-Pokuase-Kwabenya Road and
improve livelihoods of people in the project area of influence.
Establish baseline information on both natural and built environment including the socio
economic activities within the corridors of the project road.
Assess and possibly quantify positive and negative impacts.
Propose effective measures to mitigate the negative impacts.
Outline management clauses and enforcement of the mechanisms to be included in the
contract document regarding the implementation of the mitigation measures, and
Prepare a monitoring and management plan indicating parameters to be monitored,
responsibilities and outputs
Methodology
The EIA Study covered an initial review of relevant literature followed by field work in the form
of scoping and gathering of environmental baseline data. During scoping consultations were
held with various stakeholders whose concerns were incorporated into the EIA Terms of
xii
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Reference. Baseline data were assembled through field study. On the basis of information
obtained from the above activities, potential positive and negative impacts of the project were
identified.
Baseline Conditions
Baseline studies enabled the gathering of information on the existing biophysical and socio
economic information. The project is located in the Ga West Municipal Assembly which is
within the coastal savannah ecological zone. This zone is characterised by double maxima
rainfall and high temperature. The project zone is located close to the Guako sacred grove and
also traverses the Sunkwa stream. The population of the Ga West Municipality is estimated
around 262,742 with 49 % being male and 51% female.
Consideration of Alternatives
Alternatives to the project were considered and a conclusion was reached that the net benefits
could only be achieved if the construction went ahead. The construction of the interchange
would considerably ease the traffic congestion anticipated after the construction of the Awoshie
Pokuase road.
The impacts that may be expected are dealt with and are common to most road construction
projects. Negative impacts such as noise, dust, disruption in road use etc., may be expected for
limited duration during the construction period. Considerable increases in traffic flows and
danger to pedestrians and livestock in the communities are also anticipated during the
operational phase. However, the positive impacts will include significant reduction in travel
time, increased travel comfort of travel and increases in economic activities among others.
Mitigation measures have been proposed to address the negative impacts and to enhance the
positive ones. These include operation and maintenance of equipment in accordance to
manufacturers specifications to minimise emission of particulates and noise; appropriate
disposal or reuse of excavated material; implementation of management practices to eliminate
breeding sites of disease vectors and prevent the creation of new ones; implementing appropriate
traffic management measures; and ensuring strict Occupational Safety and Health (OSH)
standards at the base camp.
With the implementation and strict adherence to mitigation measures it is expected that residual
impacts will be of low significance. There are however some positive residual impacts that can
be realised such as improvement in traffic situation and increased awareness of health and safety
issues. Construction of a road involves occupational health and safety risks to road workers,
primarily in the areas of storage and handling of materials, and operation of heavy machinery.
The failure of environmental mitigation can result in serious impacts such as erosion, increased
xiii
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
road accidents and disruption of the community lifestyles. In view of this, an emergency
response plan is proposed to be put in place to deal with environmental /public health
emergencies associated with accidents.
Stakeholder and public consultations is an essential part of the ESIA process. Both EPA (Ghana)
and AfDB require that stakeholders are consulted to seek their views and opinions regarding the
project before they are implemented. Through this process, stakeholders and the public have an
opportunity to contribute to the overall project design by making recommendations and raising
concerns. In addition, the process creates a sense of responsibility, commitment and local
ownership for smooth implementation of the project. This was the objective of these consultation
forums.
Monitoring
This section documents a set of guidelines for implementing and incorporating environmental
management practices to minimise adverse environmental impacts associated with the
construction of the Pokuase Interchange. Its aim is to establish environmental management
standard guidelines for all parties involved in undertaking their various tasks and responsibilities
for the project.
This chapter details the capacity strengthening plans that will be needed to improve or aid the
ability of some key agencies with regard to the implementation of the ESMP. A total cost of
(GH) 1,147,826.94.
Conclusion
Extensive consultations were held with a number of stakeholders and generally, they were of the
view that even though the construction phase of the project will inconvenience them in deferent
ways, the benefit of the rehabilitated road will outweigh the inconveniences, most of which is
temporary. The project is therefore generally accepted and recommended for implementation
assuming the designing and implementation of appropriate environmental management
measures.
xiv
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
1.0 INTRODUCTION
1.1 Background
The GoG acting through the Ministry of Roads and Highways (MRH) and Department of
Urban Roads (DUR) awarded a contract to Messrs Associated Consultants Limited in Accra,
Ghana to undertake a Detailed Engineering Design of the Foundation, Traffic Management
and Drainage Design of the Pokuase Interchange.
However, the road being constructed will intersect the Accra-Kumasi road at the Pokuase
ACP junction and traffic streams are expected to conflict with each other. The Department of
Urban Roads therefore seeks to use the development of the Pokuase interchange to remove
the expected bottleneck at the junction on completion of the main Awoshie Pokuase road
project and to improve travel within and between the communities.
ACP/Kwabenya
Pokuase
Road
Old Awoshie
Road Uncompleted Section of
Awoshie-Pokuase Road
Nsawam
Awoshie- Road
Pokuase Road
1
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
communities and also to remove the expected bottleneck at the junction on completion of the
main Awoshie Pokuase road project. It also ultimately aims to enhance urban mobility,
promote efficient, affordable transport services along the Awoshie-Pokuase-Kwabenya Road
and improve livelihoods of people in the project area of influence.
Establish baseline information on both natural and built environment including the
socio economic activities within the corridors of the project road.
Assess both positive and negative impacts.
Propose effective measures to mitigate the negative impacts.
Outline management clauses and enforcement of the mechanisms to be included in the
contract document regarding the implementation of the mitigation measures, and
Prepare a monitoring and management plan indicating parameters to be monitored,
responsibilities and outputs.
The socio economic effects that the actual works will have on the communities along
the road.
Consulting with government agencies, traditional rulers, community leaders and other
interested members of the public.
Establishing an environmental baseline for the project area.
Assessing environmental and social impacts resulting from the project and their
significance;
Recommending appropriate measures to mitigate potential negative impacts and
enhance positive ones.
Preparing management clauses to be included in the contract document; and
Outlining a monitoring plan, including parameters to be monitored, timelines and
responsibilities for implementation.
2
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The central policy of the ESIA is to provide an opportunity for public participation in the
project design and implementation throughout the entire ESIA process. In this respect,
stakeholders who included Project Affected Persons, Traditional Leaders, Government and
Municipal assembly officials who are likely to be affected directly or indirectly by the
implementation of the proposed project were consulted. These consultations brought to light
peoples views, fears and expectations making it easy to identify major environmental and
socio-economic concerns.
Furthermore, Public consultations provided the study team the opportunity to inform the
community members about the proposed project.
A monitoring programme has been formulated to monitor trends as a result of the project and
thus create the opportunity to minimise adverse effects due to uncertainties in the impact
assessment.
On the basis of the Terms of Reference, this Environmental and Social Impact Statement is
prepared with the following major components:
1. Executive Summary,
2. Introduction
3. Policy, legal and administrative framework,
4. Description of Project
5. Description of Project Environment,
6. Analysis of Alternative Approaches,
7. Potential Environmental and Social Impacts
8. Mitigation of Environmental Impacts and Complementary initiatives
9. Expected residual effects and environmental hazard management
10. Environmental Monitoring Plan,
11. Public Consultations,
12. Environmental and Social Management Plan
13. Institutional Capacities and Strengthening plan
14. Conclusion
15. Annexes
3
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Maintain ecosystems and ecological processes essential for the functioning of the
biosphere;
Ensure sound management of natural resources and the environment;
Adequately protect humans animals and plants, their biological communities and
habitats against harmful impacts and destructive practices and preservation biological
diversity;
Guide development in accordance with quality requirements to prevent, reduce, and
as far as possible, eliminate pollution and nuisances;
Integrate environmental considerations in sectoral, structural and social-economic
planning at the national, regional, district and grassroots levels;
Seek common solutions to environmental problems in West Africa, Africa and the
world at large.
Environmental protection in Ghana is guided by the preventive approach, that is, with the
recognition that socio-economic development must be undertaken in such a way as to avoid
the creation of environmental problems. Creation of awareness, among all sections of the
community, of the environment and its relationship to socio-economic development, and of
the necessity for rational resource use among all sectors of the country is vital part of the
overall objective. Public participation in the environmental decision-making process is an
important element of government policy.
4
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
specifies requirements for the production of an EIA for various proposed works.
Figure 2 below indicates the EIA Procedure.
Criminal Code (Act 29) Section 296-297, 1960 - Prevents the accumulation and
exposure of filth and refuse of all kinds and the prohibition of activities, which may
endanger public health or cause damage to lands, crops, cattle or goods. Any project
activities that will pose danger to health and safety will be infringing on this law.
Water Resources Commission Act 522 (1996) - provides for the preparation of
comprehensive plans for the regulation, utilization, conservation, development and
improvement of water resources and develops policy framework for water resources
management in the country. This Act also grants rights to exploit water resources.
Local Government Act 462, 1994, - District Assemblies will therefore be responsible
for the development, improvement and maintenance of human settlements and
environment in the district and local levels. The Assemblies will therefore be
responsible for the management and maintenance of the roads within their respective
jurisdiction
Town and Country Planning Cap 84, 1951 - Preparation of district layout plans, and
protection and preservation of amenities and public services such as drainage, roads,
refuse disposal, sewerage and water supply.
The Lands Statutory Way Leaves Act 186, 1963-This Land Statutory Way Leaves
Instrument is the most relevant Act with regard to Land acquisition for road
construction. The Act regulates the acquisition of land for road projects. It also allows
for the purposes of construction, installation and maintenance of works of public
utility and for the creation of right-of-way and other rights in respect of such works. It
provides compensation for certain types of loss or damage incurred as a result of those
activities. And once the property owner is served a copy of the Way leaves, he/she has
three months from the date within which to make a compensation claim.
Labour Act No Act 651,2003- Part XV, Section 118 (1) and (2a-h) of the Act enjoins
employers to ensure that every worker employed by him or her works under
satisfactory, safe and healthy conditions, and is further obliged to provide necessary
information, instructions, training and supervision to ensure the health and safety at
work of those other workers engaged in a particular work.
5
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
6
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Industrial 230
24hrs
Total Suspended Residential 150
-
Particulate (TSP) Industrial 75
Annual
Residential 60
Particulate Matter 24hrs - 70 50ug/m3
(PM10) Annual - - 20ug/m3
2.3.2 Noise
International guidelines for ambient noise levels are set out by the IFC in their
Environmental, Health, and Safety Guidelines (2007) and presented in Table 2. In addition,
the EPA provides national guidance on maximum permissible noise levels for prescribed
areas(Table 3). The IFC requires that noise impacts should achieve either the levels given
below in Table 2 or a maximum increase of 3 dB at the nearest receptor location offsite.
7
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Unit of
Characteristics Parameter Measurement *Standard
Turbidity NTU 5
Colour(apparent) Hz 15
Physical Tot. Sus. Sol (SS) mg/l -
Tot. Dis. mg/l 1000
Solids(TDS)
Conductivity S/cm -
Acidity (PH) pH 6.5-8.5
Potassium units
mg/l 30
Sodium mg/l 200
Calcium mg/l 200
Magnesium mg/l 150
Chemical Chloride mg/l 250
Ammonia(NH4- mg/l 0.00-1.5
N) Iron
Total mg/l 0.3
Sulphate (SO4) mg/l 250
Manganese mg/l 0.4
Phosphate (PO4- mg/l -
P)
Nitrate (NO3-N) mg/l 10
Nitrite (NO2 -N) mg/l 1.0
*Faecal Coliform cfu/100ml 0
Biological *Total Coliform cfu/100ml 0
* E.coli cfu/100ml 0
Total Hetero. cfu/100ml 500
Bacteria
8
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The Ministry of Roads and Highways (MRH) is responsible for formulating policies and
overall strategies on roads and vehicular transport. The Ghana Highway Authority (GHA),
Department of Feeder Roads (DFR) and Department of Urban Roads (DUR) are the
organizations under MRH which carry out actual implementation of road policies. Ghana
Highway Authority is responsible for 14,900 km of roads about 65% of which are gravel
roads. The current project falls within the jurisdiction of the Department of Urban Roads.
The MRH has prepared an Environmental and Social Management Framework (ESMF) as
well as a Resettlement Policy Framework (RPF). The purpose of the ESMF and RPF is to
provide corporate environmental, social and resettlement safeguard policy frameworks,
institutional arrangements and capacity available to identify and mitigate potential safeguard
issues and impacts of each sub-project.
During the preparation of the report, these major institutions and/or their documents were
consulted for their technical advice, expert knowledge and concerns as related to the project.
9
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The GHA has an Environmental Management Unit (EMU) that has oversight on
environmental and social issues of the Authoritys mandate. The EMU operates under the
Road Safety and Environment Division (RSED).
10
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
11
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
12
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Road from the Awoshie-Pokuase Road to the ACP-Ashale Botwe Road about 1500 -
2000m of dual Construction Works:
An interchange at the intersection of the ACP-Awoshie /Nsawam Road
Necessary road widening on the Nsawam Road
Provision of necessary ramps and slip roads to make the interchange perform optimally
Necessary traffic management and safety features to address potential safety concerns
of the project
Location (m3)
Pokuase Pit
(535'51.8"N 250,000.00
015'59.3"W)
Agyen Kotoku Pit
(544'19.88"N 60,000.00
022'22.5"W)
Ablekuma/Agape Pit 450,000.00
13
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
(535'51.8"N
019'40.7"W)
Papase Kotoku
(545'35.54"N 89,250 m3
023'12.5"W)
Katapor
300,000 m3
3.2.6.3 Sand
The proposal here is that suitable natural sand would have to be sourced from specifically the
Bator and Akuse areas, since it is extremely difficult to come by such materials in good
quality and quantity within the immediate project environs.
14
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
It is expected that upon project commencement, the Contractor will prepare project activities
schedule to share with the Client. Under the proposed interventions to be undertaken, the
following activities are anticipated.
15
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
also be removed and the Contractor is expected to maintain a record of the number, species
and characteristics of the trees removed for compensation through planting.
3.2.7.3 Earthworks
Earth moving is the removal of the overburden along the alignment to give way for filling
with appropriate materials. This generates significant spoil earth materials to be disposed off
or reused elsewhere. The activities will involve moving fill materials (gravel) to fill and
development of the base on which the road surface will be formed.
Construction of about 15.54km (Fig2) of local roads within the project area to ensure
connectivity within the local community and the main road corridors and to provide
good and all weather access to social services such as schools, health facilities,
markets, etc.
16
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
17
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Support to the Kpobiman Womens Sanitary Service Company through the provision
of water tanks and boreholes to ensure greater water supply to enhance and boost their
activities.
18
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
4.2 Climate
The climatic condition of the project area is characterized to a large extent by temporal and
spatial variation in rainfall. This is principally due to the movement of the inter-tropical
convergence zone (ITCZ). In addition to this primary mechanism, there are other factors that
modulate rainfall amount such as local variation in topography, wind and global factors
giving rise to cyclic climatic variation and possibly longer term climate change. The
movements of the ITCZ are commonly known as South-westerly monsoon which is strictly
the seasonal reversal of the wind accompanied by marked wet and dry seasons. The ITCZ is
formed by vertical motion appearing as convective thunderstorms driven by solar heating,
which effectively draws air in called the trade winds. The duration of the wet season, and
consequently the total amount of rainfall annually, decrease northwards. The greatest rainfall
is generally along the coastline because it has the longest wet season and an inexhaustible
moisture supply from the Gulf of Guinea. It must however be noted, that storm derived from
convective process tend to be of generally low in intensity with long duration. Annual rainfall
in the project catchment ranges from 300mm to 1600mm with a mean annual rainfall of
1000mm. The Trend of total annual rainfall distribution from 1961 to 2011 is as shown in Fig
3.
1600
1400
Total Annual Rainfall (mm)
1200
1000
800
600
400
200
0
1961 1971 1981 1991 2001 2011 2021 19
Year
The collected rainfall data for the project area shows two rainy seasons, the heavy rains start
from March to July and the lesser one from September to October. The dry season falls
within December through to February. The driest month is January followed by February.
The wettest month is June. Fig 4 below shows the average monthly rainfall distribution
within the respective month.
250.0
Rainfall depth (mm)
200.0
150.0
100.0
50.0
0.0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
The mean monthly temperature ranges from 23C to 33C. The lowest monthly temperatures
recorded for the project area occurs during July and August due to cloud cover and December
as a result of cool northeast trade winds. The highest monthly temperatures are recorded
usually in March when the sky is devoid of cloud cover. On annual scale, the maxima
temperature ranges between 30C and 32C and the minima between 23C and 25C.
The mean daily bright sunshine hours varies in excess of 5.0 hours. Wind speeds are
generally light being of order of 6 knots. Strong winds are usually associated with convective
thunderstorm activity during the rainy season and are short in duration.
Temperature, humidity and wind affect rainfall run-off. High temperatures, low relative
humidity and strong winds result in higher evaporation and subsequently reduction in run-off.
20
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Topography
The general topography of the project area is a type that can best be described as undulating
with heights ranging from 70 m up to 210m above mean sea level. There are however, some
few small, sharp undulating as well as flat areas.
Geology
The west of Accra is generally underlain by rocks of the Togo - Akwapim Range which is
now internationally accepted in terminology as the Togo Series. From a source in the sea
around Nyanyano in the Central Region, the Series trends in a northeast direction towards the
western part of Accra and continues in the same direction to the Volta River between Kpong
and Anum and further to the Ghana Togo border near Kpalime and from there in a
northeastern direction where it passes into the Republic of Togo.
The Togo Series originally consisted of alternating argenaceous and argillaceous sediments
which have now been converted into phyllites, schists and quartzites except in few places,
where unaltered shales and sandstones are seen. Quartzite, quartz-schist, sericite-quartz
schist, sericite schist and phyllites are the predominant rocks, but hornstones, jaspers and
hematite quartz-schists some of which were formed after the deposition of the sediments, also
do occur in the Togo series. These series/range are bounded by two major thrust: one, with
the Dahomeyan contact at its eastern margin, and the other at its western contact with the
Cape Coast granitoid complex rocks, the Voltaian and the Buem sediments. The thrust fault
along the western flank has been referred to as the Western Boundary fault and that along the
eastern margin as the Eastern Boundary fault. Both faults separate rocks of different
lithologic facies. It must be noted here that the East Boundary fault is largely tectonic.
The Togo Beds have been subjected to intense directed pressure metamorphism, resulting in
intense folding, fracturing and faulting. Isoclinal folding with the axial planes of the folds
inclined to the east south-east at 30- 60is the rule. Recumbent folds with dips of less than
30 sometimes occur. There is no evidence of the intrusion of igneous rocks into this series in
Ghana. Metamorphism in the Togo series range from green schist to amphibolite faces.
21
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Vegetation type is mainly grass with few shrubs at the marshy areas of the site. There is
Pokuase forest reserve located within the north-eastern section of the project catchment.
Soil Type
The basic soil type within the catchment area is largely silty- clay with some sections
dominated with gravel type soil. Permeability of this type of soil is moderately low resulting
in fairly high surface run-off rates.
Other sources of water in the project area include pipe borne, boreholes and wells. Except for
the communities that enjoy pipe borne water, most of the people depend on borehole water,
hand-dug well water, streams and rivers.
After construction, some portion of the road is expected to disturb the course of the stream
therefore the stream will be re-aligned and engineered to enable it to flow freely.
Unit of
Characteristics Parameter Measurement Side A Side B *Standard
Turbidity NTU 5.00 8.94 5
Colour(apparent) Hz 2.50 2.50 -
Physical Tot. Sus. Sol (SS) mg/l <1.00 <1.00 15-
Tot. Dis. mg/l 407 365 100
Conductivity
Solids(TDS) S/cm 740 664 0-
Acidity (PH) pH 7.29 7.54 6.5-8.5
Potassium mg/l
units 5.20 4.90 30
Sodium mg/l 48.3 33.6 200
Calcium mg/l 41.7 41.6 200
22
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Particulate matter was sampled using MiniVol samplers set to a flow rate of 5 L/min.
Samplers were placed at a minimum height of 5 meters above ground level to prevent the
collection of ground level dust temporarily made airborne by gusting winds.
Pumped air was siphoned through a quartz filter paper, mounted in the sampling unit and
sampling undertaken for 24 hours at each sampling location. The quartz filter paper was
stabilised for a minimum of 24 hours before and after sampling in a desiccator.
The fresh quartz filter paper was weighed before sampling. After the 24-hour sampling
period, post sampling filters were weighed and the difference in weight (W2-W1) was used to
calculate the concentration of the particulate matter in g/m3 using the formula below.
23
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Table 11 shows ambient Particulate matter (PM) and Total Suspended Particles (TSP) in
comparison to the EPA levels. The PM10 and TSP levels measured at the ACP junction were
both lower than EPA standards.
Table 11: The PM and TSP levels at ACP Junction were measured
LOCATION PM10 (g/m3) TSP (g/m3)
Baseline line information for gaseous emissions is not presented but provisions will be made
in the ESMP for additional baseline data.
4.5.2 Noise
A decibel (dB) is the unit for the measurement of noise. The zero on a decibel scale is at the
threshold of hearing, the lowest sound pressure that can be heard on the scale according to
smith: 20 dB is whisper, 40 dB the noise in a quiet office, 60 dB is normal conversation, 80
dB is the level at which sound becomes physically painful.
Noise measurements/recordings were taken with a High Precision 3M Sound Level Meter,
Model Type 1. The sound level meter has an inbuilt calibrator, and was calibrated before
measurement/recordings were taken. The noise meter was calibrated at 114 dB (A) prior to
the measurement.
Ambient noise levels recorded were above the EPA standards (Day) which is consistent with
the high commercial activities and traffic situation observed at the area.
Table 12: Ambient Noise levels (dBA) recorded at ACP Junction February 21, 2015
LOCATION LEQ L10 L50 L90 LMAX EPA
STANDARDS(Commercial
or light industrial areas)
24
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
4.6.1 Population
The population of the Ga West Municipality is estimated around 262,742 with 49 % being
male and 51% female.
Number %
Pokuase 14,223
Ayawaso 5,527
Kwabenya 5,827
4.6.2 Settlement
There are a number of settlements located along the project road. The communities within the
project sphere of influence are predominantly urban and peri-urban. These are located within
the north western/western corridor of Accra. Residential densities in these communities range
between medium to high. Their populations are those to experience the various impacts as a
result of the project; e.g. loss of farms and properties, dust pollution, accidents, etc.
25
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The industrial sector covers varied activities such as the production of mineral water,
aluminium products and also mining and quarrying of large deposits of sandstone, clay and
laterite materials are carried out for the construction industry. In addition, telecommunication,
banking facilities and other infrastructure facilities exist to serve as catalyst for the rapid
development of the Municipality.
The construction sector (estate development) is also fast growing. With the enormous
deposits of natural building materials of high quality coupled with large tracts of undeveloped
lands especially in the rural areas of the municipality, the municipality has become a
favourite area for estate development.
With commerce, the municipality is most characterized by petty trading which involves sale
of food stuffs, provisions, clothing etc.
26
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The land on which the forest is found belongs to the people of Pokuase and all cultural and
religious rituals for the Guako forest is performed by the chief priest of Pokuase. The
Pokuase Traditional Authority is the traditional custodian of the grove however the forest is
under the jurisdiction of the Ga West Municipal Assembly (GWMA) who passed a resolution
that seeks to protect the forest from further degradation (attached in annex).
4.9.2.1 Flora
The area has emergent broken canopy with very thick undergrowth of climbers, `twine and
ropes. The notable vegetation in the grove consists mainly of Onyina (Ceiba pentandra),
Mahogany (Khaya senegalensis), Odum (Melicia eselsa) and Wawa (Triplociton
scleroxylum), Lucina (Leucaena leucocephala), Cassias (Cassia sp), and Teak
(Tectona grandis). Natural regeneration occurs in the forest but at a low rate. The areas close
to and along the Sunkwa stream are predominantly marshy with species such as oil palm
(Elaeis guineensis) and ferns. Poles of Celtis spp also occur within the grove.
4.9.2.2 Fauna
The grove serves as feeding, breeding and roosting grounds for birds of different species
which make up the majority of the wildlife currently occurring in the area. The forest which
once served as home for several species of animal now supports only a small fraction of the
previous animals that existed in the past(Table 15). Both the species diversity and abundance
of wildlife in the area is therefore very low. Although the forest in the grove presented a
suitable habitat for the hinged tortoise (Kinixys sp) and the marsh terrapin (Polemedusa
27
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
subrufa), none of these species were seen during the field surveys. There was no presence of
UICN-red listed species.
Table 15: Wildlife Species encountered in the sacred groove during field surveys
Common Name Scientific Name Mode of
Identification
S H C
Mammals
Giant Gambian Rat Cricetomys gambianus +
Ground Squirrel Euxerus erythropus +
Avifauna
Cattle egret Babulcus ibis +
Black kite Milvus migrans +
Blue-billed malimbe Malimbus nitens +
Little Green Woodpecker Campethera maculosa +
Pied Crow Corvus albus +
Senegal Coucal Cebtropus senegalensis + +
Northern Black Flycatcher Malaenornis edolioides +
Village weaver Ploceus cucullatus +
Velvet-mantled drongo Dicrurus modestus +
Reptiles
Agama lizard Agama agama +
Invertebrates
Praying Mantis Mantis religiosa +
Dragonfly Unidentified +
(S-Sighted/ Seen; H- Hole made by animal for refuge; C- Calls heard from bird)
4.9.3.1 Cultural
The Sacred Grove houses the Guako deity which is known to be the protector of the people of
Pokuase. He is a blacksmith who provides the people with farming and hunting tools when
they request for such. He is celebrated every year, one week after Easter. During this time the
chief priests and people perform rituals to worship the god and ask for favours.
4.9.3.2 Socio-Economic
The socio-economic importance obtained from the sacred grove come in many and diverse
forms. The reservoir from which the tankers siphon water for sale in Pokuase and its environs
is fed by the Sunkwa stream which takes its source from and meanders through the sacred
grove.
28
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Figure 8: Rat hole dug out by humans during hunting of the animal.
Some medicinal leaves can also be found in the sacred grove. These are collected by the chief
priest to cure several diseases that occasionally afflict the local people. The bark of trees such
as Mahogany (Khaya senegalensis) from the sacred grove is also used as medicine by locals.
29
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The forest is currently surrounded by several infrastructures which gradually cause the
degradation and shrinkage of the forest through gradual encroachment.
Majority of the local people in Pokuase now are not very concerned with the management of
the forest and this could be attributed to factors such as:
The infiltration of foreigners (non Pokuase indigenes) who have no regards for the
Guako shrine,
30
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The rise of western religion (e.g. Christianity, Islam) which threatens the traditional
beliefs and practices, and
The lack of education on the history and cultural importance of the Forest.
Consequently it brings about the usurping of the powers of the traditional authorities and
selling of land to private developers.
However, there are some Pokuase locals who still worship the Guako god and so have a
religious interest in the conservation of the sacred grove.
Noise was also very audible within the forest mainly from vehicular movement on the Accra
-Pokuase road. Noise in the area was a source of disturbance to most of the animals in the
forest and could have contributed to the low numbers and diversity of wildlife observed in the
area.
4.10 Traffic
There are several modes of transport within the project area; these include both the motorized
and the non motorized means of transport. Motorized transport includes; cars, buses, trucks,
motorbikes, heavy trucks, while the non-motorized transport include bicycles. Traffic Studies
were done on three sections of road; Accra-Nsawam, Awoshie-Pokuase, ACP junction-
Kwabenya to determine the annual daily traffic. The results are presented below;
Accra-Nsawam 33,774
Awoshie-Pokuase 4,286
Congestion within the project area could be attributed to the fact that the present transport
infrastructure and network system is insufficient to handle the traffic demand.
31
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The design has been made to ensure that one of the proposed ramps Awoshie- Nsawam exit
ramp) can fly over the existing railway line before descending to connect to the middle tier
bridge. A crest curve of 180m is the optimal available length to ensure that there is adequate
vertical clearance between the ramp and the existing railway underpass.
32
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
5.1 Introduction
Projects such as road construction that may have effects on the built and natural environment
always raise issues of concern and alternatives of such projects are always necessary. The
reason is to assess the effects of these alternatives on the environment against expected
benefits. Two main project alternatives have been considered and they are:
This will affect the smooth movement of vehicles to and from the affected area. Travel on
these roads will continue to be slow and commutation times will increase drastically with the
no option alternative.
The topography is such that the Accra-Kumasi Road is in a valley, bordered on both sides by
steep hills. The steepest is the ACP Estate approach (approximately 9%). Vehicular accidents
occurring as a result of the steepness of the ACP Kwabenya road will persist and possibly
increase. Police reports state that a total of 163 accidents have occured on the Accra Pokuase
road from August, 2014 to July, 2015 of which 37 have been fatal.
Pedestrian accidents will occur due to the lack of road safety measures. The health of the
people will be affected because vehicular emissions and noise levels are expected to increase
due to anticipated traffic congestion.
33
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The Client, Department of Urban roads in consultation with key stakeholders and based on
technical, economic, environmental and social factors, opted for the 3-Tier Signalised
interchange.
The Consultants employed two (2) main Models for the economic analysis and evaluation of
the project for the 25 years following its completion, as per the TOR. These models
comprise:
Excel model for the selection of Bridge type, (structure and type of material), and
The Highway Development and Management Investment Model, (HDM-4), for the
selection of the best project functional scheme/option, utilising the traffic operations
on the influence area road network system
34
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
All the project schemes/options were found economically feasible. An Incremental benefit-
cost analysis was then performed to compute the Incremental benefit-cost ratio, (IBCR), to
assess the most feasible project scheme/option.
Based on the results, The Consultants recommended the following interchange options for
consideration based on the results of the Economic evaluation:
3-Tier Rotary interchange
3-Tier Signalised interchange, and
Full Clover Leaf interchange
Environmentally and Socially, The Full Clover leaf option was not selected due to the
following major reasons:
One of the loops would occupy the Sacred Grove, which accommodates the Guako
and therefore could not be touched.
The Clover leaf requires much more space than the 3-Tier Signalised interchange and
needs a lot of appropriation of properties.
Technically, a comparison of performance for the schemes was done in order to access their
level of service. Table 18 shows a comparison between 3-Tier Rotary and 3-Tier Signalized
schemes over the 25years design period (2019-2043 inclusive).
The results reveal that the 3-Tier Signalized scheme would perform better than the 3-Tier
Rotary scheme from the fifth year of operation (2023). The 3-Tier Rotary scheme will
deteriorate to LOS F by the seventh year of operation (2025), while the 3-Tier Signalized
scheme will deteriorate to LOS F five years after (2030). This indicates that the 3-Tier
Signalized scheme would perform at acceptable Level of Service for a relatively longer
period.
35
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The most important benefits that can be derived from the construction of the interchange
include the following among others:
36
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Although construction activities will cause temporary delays in public and private transport,
access to services and facilities should be improved in the long-term through greater
reliability and, possibly increased availability of public transport. Public and private transport
37
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The interchange also has a potential to enhance appreciation of land and property values in
the road section and the immediate neighbourhoods. Among the appreciation will include
value addition to commercial and economic investments, potential for institutional
development and attraction for residential housing development.
The design also seeks to eliminate the steepness or poor vertical alignment that is experienced
at The ACP junction, thereby reducing the occurrence of vehicular accidents at that point.
The road will provide an alternative route for vehicular traffic currently using the Pokuase-
Achimota route to access the western parts of Accra and beyond, and vice versa. This will
make tremendous savings on general fuel consumption and reduction in vehicular emission
pollution, by avoiding the traffic-congested Pokuase-Achimota-La Paz route. It will also
improve the transportation system between the two nodal towns (of Pokuase and Awoshie)
and adjoining settlements, by opening the area up.
38
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
uninterrupted flow of traffic on the Accra-Kumasi road as well as between Pokuase ACP and
Awoshie.
These impacts are considered negative and significant, especially to residential and
commercial establishments located close to project during the construction phase mitigation
measures are required to reduce the impacts on air quality within the project area. Dust
pollution from construction activities will however cease in the operation phase.
During the construction phase of the road, the major sources of noise pollution are vehicles
transporting the construction material to the construction yard and the noise generating
activities at the yard itself. Mixing, casting and material movement are primary noise
generating activities in the yard and will be uniformly distributed over the entire construction
period. Construction activities are anticipated to produce noise levels in the range of 80 - 95
39
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
dB (A). The construction equipment will have high noise levels, which can affect the
personnel operating the machines.
The noise likely to be generated during excavation, loading and transportation of material
will be in the range of 90 to 105 dB (A) and this will occur only when all the equipment
operate together and simultaneously. This however is a remote possibility. The workers in
general are likely to be exposed to an equivalent noise level of 80 to 90 dB (A) in an 8-hour
shift.
40
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Construction activities often lead to the influx of people who will be employed in various
sectors of the construction. This might lead to a profanation of the shrine by workers who
have no regard for the shrine. Local people of Pokuase may take advantage of the intense
activity surrounding the forest to illegally harvest wood for fuel.
There are also a group of mechanics, taxi drivers and water tanker operators within the
project ROW who must be relocated because their activities are incompatible with the
proposed project interventions. This displacement may lead to a loss of business causing
inconvenience.
There are two auto mechanic shops with a total of 6 mechanics situated on the project site.
According to the mechanics they were given temporary permission by the traditional
authority to occupy their current location which is about 0.2 acres.
The Water Tanker drivers who are forty (40) in number c o l l e c t water from the stream to
sell for construction activities and domestic activities aside drinking.
The most visible activity on site is the vehicle operators (taxi drivers) with a membership of
forty-one (41). This group with has been operating from the site for the past 13 years. The
land was allocated to them by the elements within the traditional authority. The taxi rank
covers an area less than 0.3 acres. They ply Haatso, Atomic, West Legon and Madina.
The cut-off date for enumeration of PAPs was on the 31st December 2014. A notice of cut-
off date was re- distributed to the PAPs on the 24th March, 2015(Attached in Annex).
6.4.1 Drainage
The project is in a low lying area which is usually inundated when it rains. The project will
include large sections of paved surfaces which inhibit drainage and will further increase the
risk of flooding.
42
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
43
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Other transport related interventions in the same region include the Awoshie-Pokuase road
and the Bus Rapid Transit (BRT). These interventions are complementary to the project and
may enhance the positive impacts.
An improvement in travel will be observed as travel time will be reduced. This will
especially be beneficial in terms of enhancement of accessibility and commercial
activities thereby facilitating regional economic integration
Efficient vehicular movement arising from an improvement in travel may also lead to
a reduction in emissions, especially CO2. Cumulatively, this will contribute to Climate
Change mitigation,
Safety of the road users also stands to be improved. With the provision of NMT
facilities, additional routes, enhanced signage and information, cases of road accidents
will be significantly reduced.
The ongoing project will have some negative cumulative impacts as well:
Running projects may pose increased social risks with respect to among others
HIV/AIDS, drug trafficking security and other social challenges unless strategic and
appropriate mitigation strategies are formulated to guide all the projects.
The interchange also has a potential to enhance appreciation of land and property
values in the road section and the immediate neighbourhoods. Among the
appreciation will include value addition to commercial and economic investments,
potential for institutional development and attraction for residential housing
development. The situation may not get an immediate back up of necessary amenities
including water supplies, sanitation, access roads, drainage systems and power.
The above are indicators of cumulative impacts associated with the ongoing transportation
related projects in the area. Those associated with future developments cant be determined
because the Municipality assembly lacks an Urban Development Master plan.
Effects are considered to be major, minor or negligible and can be negative or positive.
Where positive impacts are identified mitigation is not required.
45
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
As a guide Table 21 presents a significance evaluation tool which calculates the significance
of the effect by a combination of importance/ sensitivity and magnitude.
Table 21 : Evaluation of Significance of Effect
Magnitude: H i g h
Evaluation: Major
Enhance skills for Local The local artisans will Extent: Local, District, regional
Artisans have the opportunity to
be trained by the Duration: Long Term
contractor enhancing
their skills on the job Magnitude: M e d i u m
and pushing them to a
higher level in their field Evaluation: Minor
or career.
46
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
47
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Evaluation: Major
Air Quality Dust will be generated Extent: Local, District and Regional
during the construction
activities. Duration: Temporary and Short term
Evaluation: Negligible
Land Acquisition and Residential and Extent: Local
Relocation commercial
establishments and Duration: Long term
activities found in the
right of way of the Magnitude: H i g h
project will be destroyed
and relocated Evaluation: Major
Disturbance to Guako The project may utilize Extent: Local
Sacred Grove land adjacent to Guako
Grove. Duration: Long term
48
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
49
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Evaluation: Minor
50
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Magnitude: H i g h
Evaluation: Major
Skills development for Local The local artisans will be Extent: Local, District,
Artisans offered the opportunity to regional, national
have hands on and on the
job training to build and Duration: Long Term
develop their skills.
Magnitude: M e d i u m
Evaluation: Major
Increase revenue for the Revenue can be generated Extent: District
Municipal Assembly by the Ga West Municipal
assembly from traders who Duration: Long Term
sell or trade around the
project site to workers Magnitude: M e d i u m
through ticketing.
Evaluation: Major
OPERATIONAL PHASE
Improved healthcare delivery Construction of new Extent: Local, District,
mortuary and male and regional, national
female surgical wards will
ensure that the
communities receive Duration: Long Term
quality healthcare.
Magnitude: H i g h
Evaluation: Major
Improved education standards Construction of new Extent: Local, District,
schools will serve the regional, national
educational needs of the
communities and its
neighbors, thus increasing Duration: Long Term
literacy rates.
Magnitude: H i g h
Evaluation: Major
Pedestrian and cyclist safety Construction of foot Extent: Local, District,
bridges for pedestrians will regional, national
ensure that safety of
pedestrians and reduce the
incidence of pedestrian Duration: Long Term
51
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Magnitude: H i g h
Evaluation: Major
Improvement in trading and Construction of new Extent: District
markets will provide a
commercial activities permanent place of trade Duration: Long Term
for pavement and street
hawkers thus freeing the Magnitude: M e d i u m
pavements for pedestrian
use. Evaluation: Major
Improved water supply Provision of water tanks Extent: Local, District,
and drilling of boreholes Regional
will provide support to
existing water supply
channels and enable a Duration: Long Term
more extensive potable
water supply within the Magnitude: H i g h
communities.
Evaluation: Major
Enhance Computer Literacy Provision of I.T. Extent: Local, District,
Equipment and training Regional
will lead to:
Duration: Long Term
Increase in computer and
I.T literacy levels among Magnitude: H i g h
young girls in the
communities to receive Evaluation: Major
the support.
52
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
53
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
54
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
55
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The Consultant will ensure that traffic management is done jointly with the relevant road
agencies, the local authorities and the Contractor with a view to keeping inevitable traffic
disturbances and safety hazards to a limited extent.
Recommendations for staging of construction works and the likely traffic diversion routes are
presented in the following sections.
56
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
All traffic management and safety measures will comply with the following standards and
specifications:
i. Standard Details for Signs and Markings for Urban and Trunk Roads (Ministry of
Transportation), 1991
ii. Draft Review of the Ministry of Transportations Signs and Markings Standards
(Ministry of Transportation), April 2007
iii. Guidelines for the Signing at Road Works (Ministry of Transportation) September 2007
iv. Road Reservation Management: Manual for Coordination, June 2001
v. Standard Specification for Road and Bridge Works (Ministry of Transportation) July
2007
vi. Design Guidelines for Traffic Calming Measures (Ministry of Transportation) February
2008
vii. Manual on Uniform Traffic Control Devices, MUTCD (USA Department of
Transportation), 2009
viii. Road Traffic Act-2004, ACT 683.
57
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Stage 1 Ramp 1 and Ramp 2 piers and decks No diversion of traffic on Accra-Kumasi Road
Tier 1 approaches on Awoshie Road and Kwabenya Road piers and Clear routes for Ramp 3 and Ramp 4 and divert traffic to and from Kwabenya
decks onto these routes
Stage 2 Awoshie-Pokuase Road extension Clear routes for Ramp 5, Ramp 6, Ramp 7 and Ramp 8 (along Accra-Kumasi
Tier 3 piers and bridge deck Road) to divert traffic around bridges work zone
Tier 2 columns and bridge deck Cordon off bridges work zone
Earthworks for Tier 1 Divert pedestrian crossing away from work zone
Pedestrian underpass
Stage 3 Awoshie-Pokuase Road extension Re-divert traffic back onto main Accra-Kumasi Road
Ramp 3, Ramp 5, Ramp 6, Ramp 7 and Ramp 8 piers and decks Re-direct traffic to and from Kwabenya Road along Ramp 4 route
Retaining walls and earthworks for approaches to ramps
Stage 4 Awoshie-Pokuase Road extension Divert northbound traffic on Accra-Kumasi road onto southbound lane
Retaining walls and earthworks for Accra-Kumasi Road (northbound) Divert traffic to Kwabenya onto Ramp 3 and Ramp 5.
Connection between Tier 2 bridge deck with Ramp 3 and Ramp 4 Divert traffic from Kwabenya along Ramp 4 and onto the Old Pokuase Road
piers and decks through to join the Accra-Kumasi Road at the Pokuase junction
Widening on main Kwabenya Road Re-direct non-motorized traffic under pedestrian underpass
Stage 5 Awoshie-Pokuase Road extension Divert southbound traffic on Accra-Kumasi road onto northbound lane
Retaining walls and earthworks for Accra-Kumasi Road (southbound) Divert traffic to and from Kwabenya onto Ramp 5, Ramp 3, Ramp 4 and
Widening on main Kwabenya Road Ramp 7
58
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The staging of works and traffic diversions are depicted in Figure 10 through to Figure 14
59
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
60
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
61
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
62
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
63
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Changeable Message Signs - These devices may be used where static sign messages
are not sufficient to accommodate the changing conditions of a work zone (e.g. lane
closures, ramp closures, to advise motorists of conditions for which they will need to
possibly react).
Additional Information Panel Signs - These signs may be used to give the motorists
additional information about a work zone.
Manual Traffic Control Police or authorized personnel would be required to control
traffic at affected intersections, especially during off-peak periods.
Temporary Work Zone Speed Limits - A reduced regulatory speed limit may be
warranted where work activity may constitute a hazard to traffic or workers.
Arrow Boards These may be used to supplement conventional traffic control
devices. They will be warranted where additional warning and directional information
is required to assist in merging and controlling traffic through and around the work
activity.
The construction site will affect the capacity of the existing roads. The extent the roadway is
occupied for work and safety purposes will determine the number of strategies required to
compensate for the loss of capacity. The following, however, include on-site capacity
strategies that would be recommended:
64
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
i. Incident Management Consideration would be given to the use of on-site tow trucks
for work zones with limited or no shoulders available. They would also be considered
where a crash or break-down will seriously impact the roadway and cause significant
backups and delays. Consideration would also be given to the provision of
Turnarounds for access through temporary concrete barrier and for tow trucks and the
Police to park.
ii. Police Patrols for Speed Control - Police patrols in work zones may be required to
ensure vehicular speeds are at or below the posted speed or for other safety reasons.
This typically will require coordination with the MTU of the Police Department.
iii. Pedestrians The project area is characterized by medium to high level of pedestrian
activity. Pedestrian access would also be provided during construction. This will
require providing temporary crossing points, sidewalks, protection from drop-offs,
etc.
65
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
OPTION PROS/CONS
Pros: Cheaper compared to Cement blocks
WIRE MESH Cons: Forest can be broken into as wire
mesh can easily be cut.
Pros: Forest cant easily accessed
CEMENT BLOCKS Cons: More Expensive Compared to wire
mesh.
Based on discussions with the Pokuase Traditional Authority and Amasaman Forestry
Commission it is highly recommended that the cement block option be chosen.
66
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
can still access their water source and find a way to their various destinations through the
network of roads that will be developed.
The Taxi drivers may also operate under the bridges where the proposed pedestrian walkway
across the Accra - Kumasi Highway will be linked through tunnels. These are still being
finalised in the geometric design.
This impact is considered significant since it affects human lives and would therefore require
adequate mitigation measures. The Contractor must also implement a comprehensive
Occupational Health and Safety (OHS) policy.
7.2.1 Drainage
The project design will include an engineered line storm drain of 3.0m x 2.0m to convey all
run-offs to an appropriate outfall. In order to reduce the peak at the outfall section, an
engineered earth storage receptacle has been designed to receive the peak discharge near the
receiving outfall culvert. This storage can also be used by the tanker services.
67
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
68
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Landscape Modification Shrubs and grass will be The cost of which is estimated at
planted in the median GH 383,320.00. Cost to be included in
whilst trees are planted contract documents.
along the sides of the road.
Land Acquisition and Proper and adequate An amount of GH3,963,505.00 is
Relocation compensation promptly estimated for the compensation of
paid to the land and structures based on Consultants
property owners. P roperty Impact assessment.
Payment should take Cost to be included in contract
place before structures are documents
taken over by the project.
The road link between the
Tanker drivers and
Pokuase township will be
developed as part of the
interchange construction
Alternative For Taxi and to pass under the ACP-
Water tanker drivers Kwabenya road
Cost to be included in contract
The Taxi drivers will
documents
operate under the bridges
where we will link the
proposed pedestrian
walkway across the Accra
- Kumasi Highway
through tunnels
Disturbance to Guako Sensitization of workers No separate cost item for clauses in
Sacred Grove on the presence of the contract documents.
shrine and importance of
the grove. Cost included in total GH 62,400 of
EPA compliance monitoring cost
Possible fencing and The replanting of the degraded portion
restoration of Sacred is estimated at GH42,824.00 whilst
Grove. that of the fencing is at GH 67,960.00
(wire mesh) or GH 126,440.00
(cement blocks).
A detailed Traffic
Management Plan should
be drawn up and
implemented by
69
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
contractor.
70
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
An engineered earth
storage receptacle has
been designed to receive
the peak discharge near
the receiving outfall
culvert.
Land Use Changes GWMA should enforce Cost included in GWMA total cost of
land use zoning GH 70,000 for acquisition of
regulations in the orthophotos.
municipality.
Strict monitoring
compliance with traffic
use and speed limits
71
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Trees will be planted along sections of the road and also in the Guako forest. The presence of
these trees will be necessary to capture CO2 from vehicular emissions.
72
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
There are however some positive residual impacts that can be realised:
Economy is expected to grow with the influx of people and the provision of goods
and services.
1. Exposure to excessive dust particles or toxic fumes from bitumen and other chemicals
used in road works;
2. Potential collapse of trenches;
3. Risk of accidents involving passing traffic;
4. Risk of rock falls during blasting;
5. Risk of fuel spills and therefore contaminating water bodies.
73
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The best way to avert any emergency is through prevention. However there are emergencies
which are beyond prevention such as natural disasters. All workers will be given
environmental and safety inductions to enable go about their respective duties in a safe and
environmental sound manner. Appropriate PPEs must be provided to assist in dealing with
environmental, health and safety issues. Individual responsibilities will call for everyone to
be alert when going their duties.
Further training will be given to workers working for instance at a height. Personnel from fire
service will be contacted to give some fire drills, rescue and containment. Specialist first
aider will be contacted to train foremen on administering first aid in the event of emergencies.
All incidents will be recorded and investigated for corrective actions to be put in place to
avert/ prevent future occurrence.
When accidents occurs the person who caused it or finds it will take the following
environmental, Health & Safety Incident Recording Procedure presented below:
Contain the incident or Person causing/ If pipe; close valve, if leak from oil drum;
put mitigation in place finding incident roll drum to produce leaks, if fire; raise
alarm, if accident; inform health personnel,
request for back up from supervisor
Inform Supervisor Isolate area and stop pedestrian and
foreman/supervisor vehicular traffic till further instruction
foreman/supervisor Foreman/ Foreman/ supervisor will follow standard
notifies site manger Supervisor/ Site incident response by contacting traffic
notifies E&S team Manger/ ESO controller. Notify key contacts and
emergency authorities as required
Determine cause of ESO For major incident call for assistance and
74
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
75
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
9.1 Overview
Stakeholder and public consultations is an essential part of the ESIA process. Both EPA
(Ghana) and AfDB require that stakeholders are consulted to seek their views and opinions
regarding the project before they are implemented. Through this process, stakeholders and the
public have an opportunity to contribute to the overall project design by making
recommendations and raising concerns. In addition, the process creates a sense of
responsibility, commitment and local ownership for smooth implementation of the project.
This was the objective of these consultation forums.
9.2 Objectives
The initial stakeholder consultations involved meetings with concerned individuals. The
objective was to inform them of the project as well as discuss the environmental and social
issues of the proposed interchange as well as the mitigation measures that would be
necessary.
The Stakeholders Forum was conducted on the 30th March 2015 at the EPA Conference
Room Amasaman branch. Formal invitations (sample invitation in annex) were sent out to all
the necessary stakeholders informing them of the meeting. The project background, design
concepts and social and environmental issues on the project were presented by the
Consultants to ensure appropriate information and awareness to all the participants.
76
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
(list of attendance in
annex)
Forestry Forestry Commission Mr E.K.
Commission Amasaman Branch Ntiamoah
Amasaman (District and Assistant (0208300985)
Branch District Managers) Mr. Sumaila
Alhassan
Individual
(0244485371)
Meetings/Consultati 8th April,2015
Department of Parks and Gardens Mr Haadi
ons
Parks and (Director) Medjida
Gardens (0245125074)
Amasaman
Branch
Environmental Environmental Health Mr D.K. Opare
77
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
78
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Those concerns that could be addressed immediately were addressed at the meetings but
those that couldnt be addressed were considered in the final designs and also in the ESMP.
Notice of cut-off date was distributed to the PAPs on the 24th March, 2015(Attached in
Annex).
9.5.1 Appreciation
Elimination of envisaged bottlenecks on the road network;
Complementary investment to the Awoshie-Pokuase road
Improved road conditions
Improved safety for users
79
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
9.5.2 Concerns
As much as stakeholders appreciate the project, they also had concerns which are listed
below:
Disruption of livelihood
Prompt payment of adequate compensation;
Alternative provisions for Taxi and Tanker Drivers
Employment opportunities for the locals should be ensured.
Increased dust and noise pollution during the construction phase of the project;
Protection of water quality of Sunkwa Stream
Non-motorized structures to enhance Safety of pedestrians and passengers ;
Profanation of shrine by workers and the general public
80
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
10.0 MONITORING
Environmental monitoring ensures that the impacts have been accurately predicted and that
mitigation measures are being implemented as planned and has the assumed effects. The
monitoring exercise will ensure that the remedial actions recommended in the assessment are
incorporated in the project and maintained throughout the operation life where appropriate. It
will also identify additional remedial measures and corrective measures or redesign remedial
measures if they are not sufficiently effective.
Periodic interviews with the beneficiaries of the projects will also be undertaken to assess
their opinions about the effect of the implementation of the project.
81
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
82
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
11.1 An Overview
The foregoing chapters of this report show that the project poses issues of concern related to
social and economic development as well as environmental conservation and for this reason,
a comprehensive management plan outline would be necessary on the project
implementation. This section documents a set of guidelines for implementing and
incorporating environmental management practices to minimise adverse environmental
impacts associated with the construction of the Pokuase Interchange. Its aim is to establish
environmental management standard guidelines for all parties involved in undertaking their
various tasks and responsibilities for the project.
The ESMP should take into consideration stakeholders desires and interests and be reviewed
continuously for the benefit of acceptability by stakeholders.
83
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
11.4 RESPONSIBILITIES
11.5 Engineer
Table 30: Environmental Management responsibility of the Engineer
PROJECT PHASE No ENGINEERS RESPONSIBILITIES
Design 1 Design the project with the least negative environmental
impact during the operational life of the road
2 Design the project prescribing materials with the least negative
environmental impact
3 Incorporate any feasible traffic safety measures within the
project design.
4 Design environmentally friendly road drainage systems
5 Incorporate all suitable clauses requiring the contractor to
execute his work with due diligence and apply environmentally
friendly methods.
Such requirements must be accompanied by the necessary
methods for monitoring and accompanied by the necessary
methods for monitoring and enforcement. Clauses with
principle contents as minimum requirement.
Implementation 6 The Engineer will supervise and enforce the Contractors
performance on all environmental requirements included in the
Contract Documents.
7 The engineer will monitor the overall environmental impact of
the projects and recommend additional mitigation measures for
implementation when deemed necessary.
84
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
11.6 Contractor
Table 31: Environmental Management Responsibilities of Contractor
PROJECT No CONTRACTORS RESPONSIBILITIES
PHASE
Mobilisation 1 Prepare a detailed Environmental Management Plan be approved
by the Engineer and EPA as stated in the contracts
2 Ensure that the management as well as site managers and foremen
are well informed about all environmental issues of the project.
3 Ensure that all site managers and foremen trained in
environmentally friendly construction methods
4 Ensure that all site managers and foremen are informed about the
cultural importance of the Guako sacred grove.
5 Ensure that all equipment mobilised fulfil the environmental
requirements of the contracts
6 Properly establish, operate and rehabilitate construction camp.
7 Obtain necessary approvals for all borrow pits
8 Establish a waste management plan covering all types of wastes.
Project Execution 9 Apply environmental requirement and construction methods.
10 Ensure occupational health and safety of all workers and visitors to
the site at all times.
11 Fulfil all environmental requirements of the Contract Documents.
12 Inform the Engineer if any unforeseen negative environmental
impact should occur.
13 Provide safe passage around or through the work site for all kinds
of traffic.
14 Ensure that all workers at his camp live responsibly with the
communities along the road corridor
15 Responsible for providing potable water to any community whose
water source is made unwholesome due to the project activities
until the water is made wholesome again.
16 Responsible for management of all types of waste generated from
construction activities, camps, quarries and borrow pits.
Demobilisation 17 Ensure that all affected project areas have been properly cleaned of
waste, graded and re-vegetated.
85
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
11.8 EPA
The EPA is responsible for coordinating environmental issues in Ghana. The Agency is
expected to issue the necessary environmental permits and also to ensure that monitoring and
reporting requirements (as required by the EMSP and detailed management plans in
accordance with EPA standards and guidelines).
86
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Also they have to enforce any actions that may be needed to ensure environmental quality
standards are not breached and permit requirements are maintained.
11.9 DUR/CLIENT
The overall implementation, project supervision and monitoring falls under the purview of
the Environmental Unit of the DUR. It will be in charge of overseeing the implementation of
the ESMP. They also have to issue instructions and guidelines for the additional mitigation
measures to be included during project execution. Additionally they will also liaise with the
local health, road/ traffic and educational Authorities to plan awareness raising campaigns.
11.10 GWMA
The Ga West Municipal assembly can be seen as the general administrator during the
construction and operational phases of the project. The relevant departmental officers in the
Municipal Assembly would be called upon where necessary during the project construction
and operational phases to provide the necessary permits and advisory services to the project
implementers. Some of the areas where they will be required include:
11.12.1 General
The Contractors responsibilities are defined in the following clauses, to be incorporated in
the Contract Document.
87
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
Clause 1:
The Contractor shall be responsible for familiarizing himself with all national and local
legislation relating to his/her activities during the construction phase of the project.
The Contractor shall be responsible for implementing all the mitigation measures proposed
at all sites under his control.
Clause 2:
The Contractor shall take all necessary measures and precautions and otherwise ensure that
the execution of the Works and all associated operations on the Sites or off-site are carried
out in conformity with statutory and regulatory environmental requirements of the
Government of Ghana and the Standard Specifications, where the more stringent shall apply.
The Contractor shall take all measures and precautions to avoid any nuisance or disturbance
arising from the execution of project activities. This shall, wherever possible, be achieved by
suppression of the nuisance at source rather than abatement of the nuisance once generated.
Waste Disposal
Clause 3:
The Contractor shall at all times maintain all sites under his control in a clean and tidy
condition and shall provide appropriate and adequate facilities for the temporary storage so
as to avoid the unnecessary accumulation of waste;
Clause 4:
The Contractor shall be responsible for the safe transportation and disposal of all waste
generated as a result of his activities in such a manner as will not give rise to environmental
pollution in any form, or hazard to human or animal health. In the event of any third party
being employed to dispose of waste, the Contractor shall be considered to have discharged
his responsibilities under this clause only when he has demonstrated that the transportation
and disposal arrangements have not given rise to pollution or will give rise to health hazard;
Clause 5:
The Contractor shall be responsible for the provision of adequate sanitary facilities for his
workforce and that of his sub-contractors. The contractor shall not allow the discharge of
any untreated sanitary waste to groundwater or any surface watercourse. The Contractor
88
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
shall provide details of sanitary arrangements to the Engineer for approval after satisfying
himself that the proposed facilities are adequate and are unlikely to pollute water resources.
Water Resources
Clause 6:
All water and other liquid waste products shall be collected and disposed of at locations on
site or off site and in a manner that shall not cause nuisance or pollution.
Clause 7:
The Contractor shall take all reasonable measures, at all sites under his control, to prevent
spillage and leakage of materials likely to cause pollution of water resources. Such measures
shall include, but not be limited to the provision of bunds around fuel and oil storage
facilities, and oil and grease traps in drainage systems associated with vehicle and plant
washing serving and fuelling areas. Prior to locating of such facilities, the Contractor shall
submit details of pollution prevention measures to the Engineer for approval.
Replanting of trees
Clause 8:
The Contractor shall exercise great effort during the Construction phase to minimize the
number of trees to be felled along the road. Four trees of the same species should be planted
for every tree felled along the road.
Transport of Materials
Clause 9:
The Contractor shall ensure that his vehicles do not cause a safety hazard, noise, dust or
disturbance to local inhabitants.
Clause 10:
The contractor shall provide safe and convenient passage for vehicles, pedestrians and
livestock needing to pass through the works.
Clause 11:
89
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
The Contractor shall provide, erect and maintain on the site and at such positions on the
approaches, traffic signs and traffic control signals necessary for the direction and control of
traffic. The signs shall be reflectorised or adequately illuminated at night in a manner
approved by the Engineer and kept clean and legible at all times. The Contractor shall
reposition, cover or remove signs as required during the various stages of implementation.
Clause 12:
The Contractor shall take reasonable precautions to keep the roads clear of any spillage or
materials from his operation to the satisfaction of the Engineer. The Contractor without delay
shall clear any spillage.
Clause 13:
All vehicles and plant operated by the contractor or his sub-contractors shall at all times be
maintained in accordance with the original manufactures specifications and service
manuals, with particular regard to the control of noise and diesel particulate emissions. The
Engineer shall have the right to require the contractor to replace or rectify any vehicle or
plant, which in his opinion causes excessive noise or emits smoke within 2 days of the
contraction being so notified.
Clause 14:
The Contractor shall consider noise as an environmental concern in his planning and during
execution of the works.
Clause 15:
All vehicles and plant operated by the contractor or his sub-contractors shall at all times be
maintained in accordance with the original manufactures specifications and service
manuals, with particular regard to the control of noise and diesel particulate emissions. The
Engineer shall have the right to require the contractor to replace or rectify any vehicle or
plant, which in his opinion causes excessive noise or emits smoke within 2 days of the
contraction being so notified.
Clause 16:
The Contractor shall take all necessary measures to ensure that operation of all mechanical
equipment and construction processes on and off the site shall not cause any unnecessary or
excessive noise, taking into account all applicable environmental requirements. When
90
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
operating close to residential area sensitive areas such as schools or medical facilities the
Contractors working hours shall be limited to daylight hours.
Clause 17:
The Contractor shall employ dust suppression measures such as watering to minimize dust
pollution.
Clause 18:
The Contractor shall ensure as far as practicable that the health, safety and welfare of
employees and all other persons on site are secured and protected from hazards created by
the Project. The Contractor shall prepare and implement a Health and Safety Plan (HSP),
which shall be approved by the Engineer. The HSP shall address, but shall not be limited to,
the following:
Clause 19:
The Contractor shall take all necessary measures to ensure that such areas shall be
designated no go areas and access to, or work in such areas, shall be prohibited and
carefully controlled. No go and Sensitive Areas shall be clearly designated and
demarcated as such by appropriate signage or markers (not danger tape), provided by the
Contractor.
91
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
No fauna, wild animals or creatures may be deliberately killed, trapped or injured in any
way. The placing of snares, destruction of fences or access to adjoining properties for
purposes of poaching or hunting is regarded as a criminal offence and shall be handled and
treated as such.
92
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
12.1 DUR
The overall implementation, project supervision and monitoring falls under the purview of
the Environmental Unit of the DUR. It will be in charge of overseeing the implementation of
the ESMP.
In order for this to be done successfully, it is necessary that their capacity be strengthened to
improve their function with regards to environmental and social management. An overall cost
of GH106,000.00 has been estimated for this purpose.
Field Activity
1 Marking & Referencing of affected Properties 3,000.00
2 Valuation of Property by Land Valuation Division 5,000.00
3 Survey of Land by Survey and Mapping Division 5,000.00
4 Grievance and Redress Committee 8,000.00
5 Environment and Social Monitoring of Project 10,000.00
6 Sensitization Campaign 75,000.00
TOTAL 106,000.00
12.2 GWMA
The Town and Country Planning department under GWMA will mostly be consulted for this
project. To adequately provide services and perform their duties an amount of GH
453,000.00 is needed to enable them properly undertake their responsibilities.
93
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
4 Acquiring of Orthophotos
Entire Municipality
To check current trend of 70,000
development and provide
base maps.
Ground truthing
5 Procure HP Laptops Computers
7 Procure Plotter
94
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
12.3 EPA
EPA will play a key role in the monitoring of project compliance. To adequately perform its
duties, they request that an amount of GH 588,826.94 be given to aid them.
Table 34: Monitoring Budget
BUDGET
MONITORING ESTIMATES
OBJECTIVES/ITEMS PARAMETERS FREQUENCY RESPONSIBILITY (GH)
To ensure compliance Occupational
to environmental Health and
Safety
standards and enhanced Guako Sacred
environmental quality Grove
Traffic
Management
Borrow Pits 62,400.00
construction
Camp
Management
Construction Weekly EPA/DUR
Waste
Management
Community
Infrastructure
Noise Sampling
80,000.00
and Analysis
Water quality
Sampling and 41,600.00
Analysis
Ambient Air
Quality 201,226.94
Office Equipment and
Stationery 10,000.00
Personal Protective
10,000.00
Equipment
168,000.00
Monitoring Vehicle
15,600.00
Fuel
Office Equipment and
588,826.94
Stationery
95
ACCRA URBAN TRANSPORT PROJECT (AUTP), PHASE 1
ENVIRONMENTAL SOCIAL IMPACT
ASSESSMENT (ESIA)
POKUASE INTERCHANGE
13.0 CONCLUSION
The findings from the Environmental and Social Impact Assessment show that although the
proposed interchange project is expected to have a number of negative impacts most of these
are anticipated to occur during the construction phases and are mitigated in the overall road
design.
However there are sensitive areas in the project area, which if not properly taken care of
could be destroyed. The mitigation measures will require constant information flow and
consultation with the stakeholders to ensure the least adverse social-economic impact from
the project.
The project is therefore being recommended for implementation assuming the incorporation
of the recommended mitigating measures and implementation of the Impact Mitigation
Measures.
96
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ANNEXES
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
CONSULTED DOCUMENTS
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
BASELINE DATA
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
CONSULTATIONS
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ATTENDANCE LIST
No. Name Organisation Position
1 C.H. Clerk GWMA MUNKS ENG.
2 Samuel Asante Pokuase Ayawaso
Taxi Branch
3 Juliana Adubefour GWMA BAC HEAD
4 Daniel Abeo A.C.P. Water Tankers
5 Ferdinand Yali DUR PCU
6 Halimatu Zuban Pokuase
7 Pat Onny DUR RSE
8 Benjamin Adomah- DUR Reg. Dir.
Kusi
9 Nii Ayi Ajama II Ayawaso Asere Stool Stool Elder
10 Nii Gyesi Ankrah Ayawaso Asere Stool Secretary
11 A. Ben-Mahmoud ECG Proj. Eng.
12 Abdoni Justice P.K. Ga Central Mun. Assembly Mun. Eng.
Samuel M. Lawer GWMA Manager
13
14 D.K. Opare GWMA MEHO
15 Nathan Sika ACON Social Dept.
16 David Adonteng NRSC Director
17 Samuel Tackey LVD/AR Chief Valuer
18 Abraham Danquah DUR Snr. Eng.
19 Ebenezer Pinkrah EPA Chief Program Officer
20 George Debrah MRH Snr. Eng.
21 Kwasi Agyeman- MRH Eng.
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
Boakye
22 Gawusu Nuhuo Pokuase-Ayawaso Taxi Union Rep
23 Richard Ayitey Pokuase-Ayawaso Taxi Union Rep
24 Ing. George Lutterodt DUR -
25 Robert Ackabah DUR Quantity Surveyor
26 George Ahram DUR Civil Eng.
27 E.N.K Ashong MRH Director (Civil Eng.)
28 Esther Ayitey NTDA Pokuase Zone Apprentice
Coordinator
29 Edith Ansah Forestry Comm. Reg. Mgr.
30 John Akwasi Nuamah DUR Director
31 Kwabena Bempong ACON Principal Consultant.
32 Charles Doh GRIDCO Mgr.
33 Winefred Agyeman GRIDCO Environmental Officer
34 Nana Akua B. Boateng ACON PC/ Engineer
35 Naki Tetteh-Anowie ACON Environmental
36 Marian Naa Aku ACON Consultant Trainee
Mingle
37 Christiana Danquah Pokuase Haidressers Rep.
Association
38 Lydia Nelson Pokuase Haidressers Rep.
Association
39 Dr. K. Osafo Ampadu DFR Chief Eng.
40 George K. Addison MRH Engineer
41 Ernest Tufuour MRH Snr. Engineer
42 Hon. Comfort Zormelo Manchie Womens Group President
43 Geraldo Charles DUR Quantity Surveyor
44 Ogbordjor Solomon ACP Tankers
45 Akansi Jacob Ebo DUR Quantity Surveyor
46 Gloria Allotey ACON Consultant Trainee
47 Rockson Quarshie Vodafone Rep.
48 Neville Dodoo-Quartey DUR Electrical Eng.
49 Yaw Opoku ACON Vice Pres. Operations
Mensah
50 Selina Avevor Kpobiman Womens Assoc. Chairperson(W.W.)
50 Kodwo Duku Wilson DUR Environmental Officer
51 Dumbah Emmanuella DUR GWMA Mntce. Eng.
53 Henrietta Whyte ACON Trainee Consultant
54 Juliet Adu ACON Traffic Engineer
55 Stephen Mawuli Kweku LVD Valuer
56 Adjei Nyarko Stephen GNTDA Pokuase Rep.
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)
ACRONYMS
Item Discussion
1.0 OPENING
The meeting which was chaired by Ing. John Akwasi Nuamah (DUR) begun at 10:30am
ACCRA URBAN TRANSPORT PROJECT (AUTP), ENVIRONMENTAL SOCIAL
PHASE 1 POKUASE INTERCHANGE IMPACT ASSESSMENT (ESIA)