Documente Academic
Documente Profesional
Documente Cultură
DELAYED - - - - -
DELAYED 11 11 0.061798 5 5 5
DELAYED - - - - -
DELAYED 19 19 0.106742 9 9 9
DELAYED - - - - -
DELAYED 7 7 0.039326 3 3 3
DELAYED 7 0.039326 3 3 3
DELAYED 7 0.039326 3 3 3
DELAYED - - - - -
DELAYED - - - - -
DELAYED - - - - -
DELAYED 13 13 0.073034 6 6 6
DELAYED - - - - -
DELAYED 10 10 0.05618 5 5 5
DELAYED - - - - -
178 76 104 76
SAGUDAY REVISED SCHEDULE
DELAYED - -
DELAYED 11 11 0.0617978
DELAYED - -
DELAYED 19 19 0.1067416
DELAYED - -
DELAYED 7 7 0.0393258
DELAYED 7 0.0393258
DELAYED 7 0.0393258
DELAYED - -
DELAYED - -
DELAYED - -
DELAYED 13 13 0.0730337
DELAYED - -
DELAYED 10 10 0.0561798
DELAYED - -
178
Thursday, March 23, 2017 Thursday, March 23, 2017 Thursday, March 30, 2017
Monday, January 09, 2017 Monday, January 02, 2017 Monday, January 09, 2017
3 3 3
- - -
2 2 2
- - -
6 6 6
- - -
5 5 5
- - -
4 4 4
- - -
5 5 5
- - -
2 2 2
2 2 2
- - -
- - -
6 6 6
- - -
6 6 6
- - -
7 7 7
- - -
6 6 6
- - -
8 8 8
- - -
8 8 8
- - -
5 5 5
- - -
9 9 9
- - -
3 3 3
3 3 3
3 3 3
- - -
- - -
- - -
6 6 6
- - -
5 5 5
- - -
76 104 76
SAGUDAY REVISED SCHEDULE
BALANCE
Thursday, December 29, 2016 EXCAVATION
Friday, December 30, 2016 EXCAVATION
Saturday, December 31, 2016 SOIL POISONING (FDN)
Friday, December 30, 2016 SOIL POISONING (FDN)
Saturday, December 31, 2016 CONCRETING - FOOTING
Tuesday, January 03, 2017 CONCRETING - FOOTING
Wednesday, January 04, 2017 CONCRETING - TIE BEAM
Thursday, January 05, 2017 CONCRETING - TIE BEAM
Friday, January 06, 2017 CONCRETING - COLUMN FDN TO GF
Saturday, January 07, 2017 CONCRETING - COLUMN FDN TO GF
Monday, January 09, 2017 BACKFILLING (excavated and borrow material)
Friday, January 13, 2017 BACKFILLING (excavated and borrow material)
Saturday, January 14, 2017 GRAVEL FILLING (GF SLAB)
Saturday, January 14, 2017 SOIL POISONING (GF SLAB)
Monday, January 16, 2017 SOIL POISONING (GF SLAB)
Monday, January 16, 2017 GRAVEL FILLING (GF SLAB)
Tuesday, January 17, 2017 CONCRETING - GF SLAB with beams and girders
Monday, January 23, 2017 CONCRETING - GF SLAB with beams and girders
Tuesday, January 24, 2017 CHB LAYING
Tuesday, January 24, 2017 CONCRETING - COLUMN GF to 2F
Monday, January 30, 2017 CONCRETING - COLUMN GF to 2F
Tuesday, January 31, 2017 CONCRETING - 2F SLAB with beams and girders
Tuesday, January 31, 2017 DOORS AND WINDOWS
Tuesday, January 31, 2017 FLOOR FINISHING
Monday, February 06, 2017 CONCRETING - 2F SLAB with beams and girders
Tuesday, February 07, 2017 CONCRETING - COLUMN 2F to 3F
Tuesday, February 07, 2017 PLASTERING
Monday, February 13, 2017 CONCRETING - COLUMN 2F to 3F
Tuesday, February 14, 2017 CONCRETING - 3F SLAB with beams and girders
Tuesday, February 21, 2017 CONCRETING - 3F SLAB with beams and girders
Wednesday, February 22, 2017 CONCRETING - COLUMN 3F to RF
Wednesday, February 22, 2017 CONCRETING - GF SLAB with lintel beams
Wednesday, March 01, 2017 CONCRETING - GF SLAB with lintel beams
Wednesday, March 01, 2017 CONCRETING - COLUMN 3F to RF
Wednesday, March 01, 2017 CHB LAYING
Wednesday, March 01, 2017 DOORS AND WINDOWS
Thursday, March 02, 2017 CONCRETING - RF beams and girders
Thursday, March 02, 2017 CONCRETING - sunbreaker
Thursday, March 02, 2017 CONCRETING - ramp
Thursday, March 02, 2017 CONCRETING - stairs
Thursday, March 02, 2017 G.I. railings
Monday, March 06, 2017 G.I. railings
Monday, March 06, 2017 CONCRETING - stairs
Monday, March 06, 2017 CONCRETING - ramp
Monday, March 06, 2017 CONCRETING - sunbreaker
Monday, March 06, 2017 CONCRETING - RF beams and girders
Tuesday, March 07, 2017 PAINTING (CONCRETE)
Tuesday, March 07, 2017 TRUSSES with painting
Tuesday, March 07, 2017 ELECTRICAL WIRING
Tuesday, March 07, 2017 WATER LINE
Tuesday, March 07, 2017 DRAINAGE LINE
Tuesday, March 07, 2017 PLUMBING FIXTURES
Tuesday, March 07, 2017 TILING
Tuesday, March 07, 2017 EXCAVATION FOR WATER SYSTEM
Wednesday, March 15, 2017 TILING
Wednesday, March 15, 2017 TRUSSES with painting
Wednesday, March 15, 2017 PLASTERING
Wednesday, March 15, 2017 FLOOR FINISHING
Thursday, March 16, 2017 PURLINS with painting
Thursday, March 16, 2017 SAGRODS with painting
Thursday, March 16, 2017 TURNBUCKLE with painting
Saturday, March 18, 2017 TURNBUCKLE with painting
Saturday, March 18, 2017 SAGRODS with painting
Saturday, March 18, 2017 PURLINS with painting
Saturday, March 18, 2017 EXCAVATION FOR WATER SYSTEM
Monday, March 27, 2017 PLUMBING FIXTURES
Monday, March 27, 2017 DRAINAGE LINE
Monday, March 27, 2017 WATER LINE
Saturday, March 18, 2017 ELECTRICAL WIRING
Friday, March 17, 2017 CORRUGATED ROOFING SHEET pre painted
Friday, March 17, 2017 CONSTRUCTION OF WATER SYSTEM
Wednesday, March 22, 2017 CORRUGATED ROOFING SHEET pre painted
Thursday, March 23, 2017 CEILING
Thursday, March 23, 2017 LIGHTING FIXTURES
Thursday, March 23, 2017 PANEL BOARD
Thursday, March 23, 2017 FIRE ALARM
Thursday, March 23, 2017 CEILING FAN
Monday, March 27, 2017 CEILING FAN
Monday, March 27, 2017 FIRE ALARM
Monday, March 27, 2017 PANEL BOARD
Monday, March 27, 2017 LIGHTING FIXTURES
Monday, March 27, 2017 CEILING
Monday, March 27, 2017 CONSTRUCTION OF WATER SYSTEM
Monday, March 27, 2017 PAINTING (CONCRETE)
DURATION
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START NON CRITICAL DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
START NON CRITICAL DELAYED
START NON CRITICAL DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
START NON CRITICAL DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
START NON CRITICAL
END NON CRITICAL
END CRITICAL PATH DELAYED
END NON CRITICAL
END NON CRITICAL
START CRITICAL PATH DELAYED
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END CRITICAL PATH DELAYED
START NON CRITICAL
START CRITICAL PATH DELAYED
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
END NON CRITICAL
END CRITICAL PATH DELAYED
END NON CRITICAL
END NON CRITICAL
START CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
END CRITICAL PATH DELAYED
END NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END NON CRITICAL
START CRITICAL PATH DELAYED
START NON CRITICAL
END CRITICAL PATH DELAYED
START CRITICAL PATH DELAYED
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
START NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END NON CRITICAL
END CRITICAL PATH DELAYED
END NON CRITICAL
END NON CRITICAL
SAGUDAY REVISED SCHEDULE
START NON-CRITICAL 3
START NON-CRITICAL 3
END NON-CRITICAL -
END NON-CRITICAL -
START NON-CRITICAL 29
START NON-CRITICAL 30
START NON-CRITICAL 43
START CRITICAL PATH 8 26.928 5 1
START NON-CRITICAL 37
END CRITICAL PATH -
START CRITICAL PATH 1 82.233 155 12
END CRITICAL PATH -
START CRITICAL PATH 8 19.888 4 1
START CRITICAL PATH 1 93.524 176 14
END CRITICAL PATH -
END CRITICAL PATH -
END NON-CRITICAL -
END NON-CRITICAL -
START CRITICAL PATH 9 29.56875 7 1
START NON-CRITICAL 9
START NON-CRITICAL 2
START NON-CRITICAL 2
START NON-CRITICAL 1
END NON-CRITICAL -
END NON-CRITICAL -
END NON-CRITICAL -
END NON-CRITICAL -
END CRITICAL PATH -
START NON-CRITICAL 26
START CRITICAL PATH 2
START NON-CRITICAL 13
START NON-CRITICAL 13
START NON-CRITICAL 11
START NON-CRITICAL 11
START NON-CRITICAL 1
START NON-CRITICAL 10
END NON-CRITICAL -
END CRITICAL PATH -
END NON-CRITICAL -
END NON-CRITICAL -
START CRITICAL PATH 9
START CRITICAL PATH 9
START CRITICAL PATH 1
END CRITICAL PATH -
END CRITICAL PATH -
END CRITICAL PATH -
END NON-CRITICAL -
END NON-CRITICAL -
END NON-CRITICAL -
END NON-CRITICAL -
END NON-CRITICAL -
START CRITICAL PATH 10
START NON-CRITICAL 5
END CRITICAL PATH -
START CRITICAL PATH -3
START NON-CRITICAL -3
START NON-CRITICAL 6
START NON-CRITICAL 7
START NON-CRITICAL 6
END NON-CRITICAL -
END NON-CRITICAL -
END NON-CRITICAL -
END NON-CRITICAL -
END CRITICAL PATH -
END NON-CRITICAL -
END NON-CRITICAL -
REBAR
PUMPCRETE OPERATOR QUANTITY HAULING FABRICATION INSTALLATION
1 6957.16086 2 8 22
12 9090.66134 16 78 228
1 6562.97141 2 7 21
14 3296.12076 6 29 83
1 3973.85584 1 4 12
FORMWORKS C L T C L T C
QUANTITY FABRICATION INSTALLATION STRIPPING
211.2 9 4 0 15 8 1 3
183.04 8 4 0 13 7 1 3
301.64 124 36 0 231 85 4 26
283.125 13 4 0 25 9 1 3
L T
8 1
176 8
7 1
75 4
8 1