Documente Academic
Documente Profesional
Documente Cultură
R\200060\Commercial\Typing\_GeneralPresentation\doris_pres\PresentationDORISDiapo\PresentationComplte
Slide 1 June 2007
General_Presentation.ppt
INTRODUCTION TO FLOW ASSURANCE
CONTENTS
INTRODUCTION
CONCLUSION
B+C Top
E CL (*)
3120 (DHI) 3125 (N) -
W LOBE 3140 (S)
OUT
A
D
3384 (ODT) -
3463 (DHI-MDT)
W 3463
ODT
E-F
3752
G
2,000 m 2000 m
Reservoir system
(nb of complexes,
stacked sand channel,
lobes)
PVT modelling :
Composition set up,
Heavy cut characteristic definition
Thermodynamic package
600
900 - 1000 - 1000
1200
- 1500
1500 - 1500
1800
- 2000
2100 - 2000
2400
- 2500 - 2500
2700
3000
- 3000 - 3000
3300
3600
- 3500 - 3500
3900
4200 - 4000
- 4000
Reservoir
Burial depth Reservoir burial depth down to 10 000 m
(Metres) Slide 5 June 2007
General_Presentation.ppt
RESERVOIR MODEL
PRODUCTION PROFILES PER WELL
A45_P1
25,000 100
90
20,000
Difficulty to interpret well 80
profiles at late life
70
10,000 40
30
5,000 20
10
0 0
00
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
16
17
18
19
P RESERVOIR
SO4--
ASPHALTENES
WAX
CP
S
ATE
?
RD
HY
VISC CO3--
O ST Y
T
Slide 8 June 2007
General_Presentation.ppt
FOR DIFFERENT FIELD LAYOUTS
Field Architecture :
Well drilling centers
Well target
Subsea Pipeline Network
Topsides facilities location
WATER
PROD
PROD
HYDRATE WAX
ASPHALTENES
NAPHTENATE
SCALES
FLOW
SLUGS ASSURANCE
EROSION
STRATEGIES CORROSION
TOPSIDES
PROCESS EMULSION
Topsides
FLOW
OPERABILITY ACTIVATION
105 m
Process Deck
Topsides
E
Multiphase Pump
GAS LIFT
- Pipe Diameters
VLiquid BUBBLE
- Pipe thermal insulation DOWNWARD SLOPE
(m/s)
SLUGS
- Chemical Requirements UPWARD SLOPE
STRATIFIED VGas
- Production boosting FLOW MAP - HORIZONTAL PIPE (m/s)
1.7e7
15 000 blpd
25 000 blpd
1.65e7
Pa
1.6e7
Pressure (Pa)
1.55e7
20 000 blpd
Time (s)
1.5e7
0 5000 10000 15000 20000
Time [s]
TOPSIDES
SPS
TREE FLOWLINE
SEABED
WELLS
&
DRILLING
RESERVOIR
ENVIRONMENTAL DATA
CONSTRUCTION FLOATER
METHODS EXCURSION
PIPE
DEEPWATER
SIZES RISER INSTALLATION
(FA) DESIGN METHODS
THERMAL RISER
SPECIFICATIONS COMPONENENTS
(FA) SPEC.
GAS LIFT
INJECTION
(FA)
Flexibles jumpers
(dynamic bundles)
Buoyancy tank
(air cans)
Riser bundle
Core pipe (integral/non integral)
(tether)
Flexjoint
(taper joint)
Spools (jumper)
80
Wet Bundle PIP
75 Insulation Insulation Insulation
70
65 36 25 39 19 31
40 32 26 36
60
30 20 32 15 Electrical
26
55
33 26 20 29 Heating
WHFT (C)
50
23 15 16 23 20
45
25 20 25 12
40
35
30
0 5 10 15 20 25 30 35 40 45 50 55 60
Tie Back distance (km)
REQUIRES
TO LOOP THE
PRODUCTION LINE
1 3
2 4
DRY OIL
LIQUID (OIL + WATER)
GAS METHANOL
Slide 18 June 2007
General_Presentation.ppt
FLOW ASSURANCE REQUIRES MONITORING
TO VALIDATE OPERATIONAL PROCEDURES
DEDICATED
TEMPERATURE
SENSORS AT
RISER BASE
55
53
51
r301
49
r302
47
l301
45
l302
43
41
39
37
T (C)
35
33
31
29
27
25
23
21
19
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
t (h)
60.00
50.00
40.00
30.00
Time (hours)
20.00
10.00
T initial
0.00
0 2 4 6 8 10 12 14 16 18
Temperature (C)
P30 shutdown during warm-up P30 test P50 shutdown during warmup P50 test P10 test P10 after 8 days production
T initial
INSULATION PERFORMANCES
Slide 20 June 2007
General_Presentation.ppt
FLOW ASSURANCE REQUIRES CALIBRATION
OF THE MONITORING (2/2)
TEMPERATURE PROBE
FIELD PRODUCTION
TO UPDATE PROCEDURES
TEMPERATURE PROBE
DONT BE
WRONG
OFFSHORE IS
STILL
INNOVATIVE
Slide 24 June 2007
General_Presentation.ppt
FLOW ASSURANCE HUMAN RESSOURCES