Sunteți pe pagina 1din 37

Drawing Prompt List Template

Project Title Project No.


Customer Date

Objective To ensure that drawings are developed and reviewed with consistent content and level of
detail across all WorleyParsons offices.
Application This Drawing Prompt List will be used during the development of 2D drawings and is to
be used by both engineering and design. It is assumed that any deliverable produced
from a 3D model or intelligent systems will have completed all design reviews, design and
engineering checks and associated actions have been closed out.
This prompt list is for use on all project phases. It is intended for use as a reference tool
for the designer to use throughout the project while producing 2D drawings.
Refer to the 2D Drawing Development Standard (EPP-0406-COR-EN).

Contents
1. GENERAL ALL DRAWINGS.................................................................................................................. 2

2. PIPING AND INSTRUMENTATION DIAGRAMS.......................................................................................3

3. ELECTRICAL DRAWINGS....................................................................................................................... 5

4. INSTRUMENTATION AND CONTROL DRAWINGS...............................................................................11

5. HVAC DRAWINGS.................................................................................................................................. 16

6. SUPPLIER MECHANICAL EQUIPMENT DRAWINGS...........................................................................17

7. EQUIPMENT LAYOUTS......................................................................................................................... 19

8. PLOT PLANS.......................................................................................................................................... 21

9. PIPING GENERAL ARRANGMENTS FROM 3D MODELS.................................................................23

10. PIPING GENERAL ARRANGEMENTS 2D.......................................................................................... 24

11. PIPING ISOMETRICS FROM 3D MODEL........................................................................................... 29

12. PIPING ISOMETRICS 2D.................................................................................................................... 31

13. PIPE SUPPORT DRAWINGS (SPECIAL SUPPORTS)..........................................................................33

14. STRUCTURAL AND ARCHITECTURAL DRAWINGS.............................................................................34

15. CIVIL DRAWINGS................................................................................................................................... 38

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 1 of 37
Drawing Prompt List Template

1. GENERAL ALL DRAWINGS

Item Description Y N NA Comments


GENERAL

1.1 Has all related standards associated with the discipline and
drawing type been read and understood?

1.2 Where there is interaction between HO and SO (GDC) has


the relevant GDP been followed

1.3 Title block (Drawing Title, Drawing No., Revision No.,


Revision Description, Scale, Project No., Signatures, Date,
WorleyParsons logo)

1.4 Reference drawings and documents

1.5 North arrow orientation (where applicable)

1.6 Scale bar shown (where applicable)

1.7 Graphics and text clearly legible

1.8 Dimensions clearly legible

1.9 Standard notes

1.10 Holds list shown (if applicable)

1.11 Drawing Continuation Cross References

1.12 Match line information (drawing no. coordinates, line type,


description)

1.13 Interface with other disciplines

1.14 Drawing modifications, scope or revisions; shown clouded,


revision triangles shown clearly.

1.15 Hold and Demolition clouding showed, revision triangles


shown clearly.

1.16 Design review actions incorporated

1.17 Latest supplier data added

1.18 Design check completed

1.19 Engineering check completed

1.20 HAZOP actions incorporated (where applicable)

1.21 Customer comments incorporated

1.22 Approved change requests incorporated

1.23 Technical queries incorporated

1.24 Stamps have been applied in accordance with Engineering


Checking and stamps Standard (EPP-0035-COR-EN

1.25 Drawing preparation follows the Drawing Checking and


Approval Procedure (EPP-0362-COR-EN).

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 2 of 37
Drawing Prompt List Template

2. PIPING AND INSTRUMENTATION DIAGRAMS

Item Description Y N NA Comments


CONTENT

2.1 Process Drawing Content Standard (EPP-0117-COR-EN)


has been reviewed for preparation of the P&ID

2.2 Safety devices are shown

2.3 Tie-in numbers and interface information

2.4 Equipment, equipment numbers and equipment data as per


database/categories and legend sheets.

2.5 Line size, specification, service and number

2.6 Equipment Trim line number specification service

2.7 Nozzle type, size, number, rating

2.8 Insulation type and thickness

2.9 Drainage and venting requirements

2.10 SP Item tag numbers

2.11 Valve size, tag number, bore type, LO/LC, NO/NC, FO/FC,
CSO/CSC, Interlocking

2.12 Spec breaks

2.13 Sloping lines, no pocket requirements

2.14 Reducers, branches shown correctly

2.15 Hold/notes are clear and concise; align to the component or


symbol they are referenced to.

2.16 Is all input data available, clear and concise (important for
intelligent P&IDs and for extraction of data to produce other
documents such as line lists)

2.17 Self-check comparison between engineering mark-up and


drafted P&ID

2.18
Layout of P&ID is unfussy so that information read cannot be
misinterpreted, lines cross-overs are avoided and kept as
straight as practical
2.19 Instrument tags, symbols, functionality (as per database
when using intelligent P&IDs)

2.20 OPC (Off Page Connector) consistency checks and reports


completed, errors cleared.

2.21 Flow directions on primary and secondary lines

2.22 Equipment symbols are correctly represented and


proportional within the drawing.

2.23 Inconsistency checks: between drawings E.g. line number,


sizes, specs

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 3 of 37
Drawing Prompt List Template

Item Description Y N NA Comments

2.24 Data consistency check between intelligent P&ID and other


databases.

2.25 Check and confirm Supply by, Construction Status


information and Implied components.

2.26 EDE properties check (SPPID only).

2.27 Flag query if there is any doubt on the mark up and


incorporate resolution on the drawing. In case of
intermediate issue highlight pending markup due to query
on the drawing.

Note: For further details on P&ID Content requirements, refer to the Process Drawings Content Standard
(EPP-0017-COR-EN).

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 4 of 37
Drawing Prompt List Template

3. ELECTRICAL DRAWINGS

Item Description Y N NA Comments


CABLE LADDER LAYOUTS

3.1 Sections, details, identifications (including scale)

3.2 Coordinates, dimensions, datum

3.3 Correct identification and service of cable ladders

3.4 Space provision for future cables

3.5 Cable ladder supports located

3.6 References to installation details

3.7 Equipment identified

3.8 Location and correct installation of electrical equipment

3.9 Required separation between electrical and instrument trays


maintained

3.10 Cable entries, termination space and method of termination


considered

3.11 Mechanical, UV and blast/fire protection of cables

3.12 Cable rating for environment and method of installation

3.13 Delineation of scope of work for packaged units


CABLE ROUTING LAYOUTS

3.14 Correct identification of cables

3.15 Alignment with Block Diagrams and Cable Schedules

3.16 Routing conditions determined

3.17 Main loads identified and located

3.18 Routing philosophy determined by


Electrical/Control/Systems

3.19 Cable trench and cable ladder sizes and locations specified

3.20 Required separation between electrical, instrumentation and


HV cables maintained

3.21 Avoided interference with foundations and underground


piping

3.22 Established road crossings, pull pits and stub-up locations


identified
SWITCH ROOM LAYOUT

3.23 Space provision for current and future extensions to


equipment provided (if project requires)

3.24 Fire system/alarms provided

3.25 Location of equipment, access, separations, clearances,


removal etc., considered

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 5 of 37
Drawing Prompt List Template

Item Description Y N NA Comments

3.26 Equipment levelling and fixing requirements specified

3.27 Foundations for power transformers, fire walls included

3.28 Access and escape provision for personnel, equipment


provided

3.29 HVAC, ventilation, air conditioning provisions specified

3.30 Transformer bay provision, oil spill prevention, cable ducts or


conduit interfaces and protection specified

3.31 Pressurization requirements specified

3.32 High voltage system grounding (earthing), neutral earth


resistance, cable sheath grounding etc. considered

3.33 General substation grounding (earthing) provisions, bonding


etc. specified

3.34 Cable access provisions to substation equipment, slots,


holes, multi-cable transits specified

3.35 Lighting provision normal and emergency, internal/external


phase balancing, levels, calculations etc. specified

3.36 Cabling separation, protection, sealing, routing, bending,


supporting etc. specified

3.37 Equipment lifting facilities provided/nominated

3.38 Telephone provisions included

3.39 Security aspects, bolts, latches, fences specified


LIGHTING AND SMALL POWER LAYOUTS

3.40 Light and power legend

3.41 Luminaire elevations (optional)

3.42 GPO/Welding outlet elevations (optional)

3.43 Luminaire identification

3.44 Luminaire circuit number

3.45 GPO/Welding outlet identification and circuit details

3.46 References to relevant installation details

3.47 References to relevant connection diagrams (if applicable)


EARTHING (GROUNDING) SYSTEM LAYOUTS

3.48 Earthing legend

3.49 Earth conductor identification

3.50 Earth electrode identification


Reference to relevant earthing details

3.51 Reference to relevant cable schedules

3.52 Items to be earthed, clearly identified

3.53 Dimensions to earth cable from edge of wall, column line etc.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 6 of 37
Drawing Prompt List Template

Item Description Y N NA Comments

3.54 Notes to include earth conductor depth below ground,


resistance to earth, insulated/non-insulated and connection
types.
SYSTEM (KEY) SINGLE LINE DIAGRAM

3.55 Applicable standards defined and agreed with Customer

3.56 Sources of supply, voltage frequency, busbar ratings and


short circuit ratings shown

3.57 Transformer rating, ratio, impedance, vector grouping and


taps

3.58 Neutral grounding


SINGLE LINE DIAGRAMS

3.59 Data from latest Load List utilized

3.60 Key Single Line Diagram followed

3.61 Voltage and frequency shown

3.62 Switchboard bus continuous rating

3.63 Bus short time short circuit capability

3.64 Circuit breaker trip and frame size

3.65 Fuse types, sizes, current transformer accuracy


class/switches

3.66 Type of starter

3.67 Motor kW rating

3.68 Motor and connectors size designation (NEMA/EEMAC/IEC)

3.69 Load rating

3.70 Neutral grounding method, NGR current rating (or


resistance) and time rating

3.71 Service descriptions

3.72 Equipment tag number

3.73 Shunt trip

3.74 Interlocking logic

3.75 Motor heaters

3.76 Metering details

3.77 Local control stations

3.78 Field control devices (i.e. limit switches, emergency stops)

3.79 Thermistors or Resistance Temperature Devices (RTD)

3.80 Auxiliary supplies

3.81 Current and potential transformer ratios

3.82 Generator size (kW), voltage, power factor and tag number

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 7 of 37
Drawing Prompt List Template

Item Description Y N NA Comments

3.83 Transformer type (ONAF= Oil Natural Air Forced, ONAN=Oil


Natural Air Natural)

3.84 Transformer size (kVA), voltage, impedance and tag number,


ratio, vector grouping, taps

3.85 Generator/transformer protection scheme

3.86 Protection and control relaying for major equipment including


transformers, breakers, motors, transfer schemes and
mechanical interlocks.

3.87 Power factor correction capacitors shown

3.88 Bus duct rating, voltage and current, including continuous


and short time withstand current rating

3.89 Generator metering/control facilities

3.90 Generator driver details

3.91 Switch ratings (load break, isolation, earthing/grounding,


transfer) including voltage, current, tag no.
SCHEMATIC DIAGRAMS

3.92 Control philosophy established and agreed

3.93 Relay/contact grid references shown

3.94 Control devices (switches, relays etc.) are labelled in


accordance with the relevant standards

3.95 Wire numbers are correct and in accordance with the


relevant standards

3.96 Terminations to field equipment shown

3.97 Interfaces to control panel terminations are shown

3.98 Equipment labelled in accordance with relevant standards


TERMINATION DIAGRAMS

3.99 Junction box location identified

3.100 Junction box clearly labelled

3.101 Terminals numbered

3.102 Cables from and to, numbered and identified

3.103 Core numbers/colors identified

3.104 Reference to relevant schematic diagram

3.105 Reference to relevant cable schedule

3.106 Type of junction box including IP and Ex rating (if located in a


hazardous or weatherproof area)

3.107 Reference to relevant installation details


CABLE SCHEDULE

3.108 Cable number

3.109 Origin and Destination (From and To)

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 8 of 37
Drawing Prompt List Template

Item Description Y N NA Comments

3.110 Number of cores

3.111 Conductor size

3.112 Voltage rating shown

3.113 Cable type/construction

3.114 Route length

3.115 Routing nodes in sequential order from origin to destination

3.116 Comments

3.117 Cable gland details


HAZARDOUS AREA CLASSIFICATION DRAWINGS

3.118 Hazardous Area Classifications are defined and modeled as


per the Project Specifications and Codes

3.119 Drawing background is up-to-date and in accordance with


latest Plot Plan or Equipment Layouts

3.120 Prevailing wind direction shown near north arrow.

3.121 Equipment list and hazardous material data received

3.122 Apparatus groups and temperature classes added to


schedule

3.123 Most onerous gas group and temperature class established


for equipment located in each zone, division or other
classification as defined by the applicable
Specification/Code/Standard.

3.124 Hazardous location plans refer to appropriate hazardous


location section and detail drawings.

3.125 Hazardous area envelopes clearly identified and


dimensioned including vertical extent where necessary

3.126 Hazardous Area overlaps shown

3.127 Locations of flammable vent points identified

3.128 Air intakes identified

3.129 Exhaust locations identified

3.130 Hazardous Area Classification design review completed


INSTALLATION DETAILS

3.131 Model numbers of equipment shown

3.132 All dimensions shown

3.133 Sections, details and identification of all equipment including


scale

3.134 All bolts, screws, nuts, washers, thickness of plate sizes and
materials stated

3.135 Bill of materials listed

3.136 Exploded sections (if appropriate)

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 9 of 37
Drawing Prompt List Template

Item Description Y N NA Comments

3.137 Enlarged details (if appropriate)

3.138 Label details shown

3.139 Reference to location identified.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 10 of 37
4. INSTRUMENTATION AND CONTROL DRAWINGS

Item Description Y N NA Comments


INSTRUMENT LOCATION AND LAYOUT DRAWINGS

4.1 All equipment tag numbers identified

4.2 Instrument bubbles shown (to ISA standards) using piping


background layouts

4.3 Alignment with P&IDs

4.4 All instrument junction boxes shown

4.5 Reference to installation details shown

4.6 Instrument equipment and transmitter stands are clear of


access and egress paths

4.7 Conforms with Hazardous Area Classification requirements

4.8 Reference to power supply drawings


INSTRUMENT INDEX

4.9 Tag numbers

4.10 Loop drawing numbers

4.11 P&ID numbers

4.12 Service description

4.13 Manufacturer

4.14 Model number

4.15 Calibration settings

4.16 Termination drawings

4.17 Requisition number

4.18 Purchase Order number


INSTRUMENT I/O LISTS

4.19 Tag numbers

4.20 Loop drawing number

4.21 P&ID numbers

4.22 Service description

4.23 System

4.24 I/O type

4.25 Instrument location

4.26 I/O location

4.27 Intrinsically Safe (IS) or non IS

4.28 Signal type


INSTRUMENT LOGIC DIAGRAMS

4.29 Control system reference

4.30 I/O references

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 11 of 37
Item Description Y N NA Comments

4.31 Plant/Sub section reference

4.32 Service descriptors

4.33 Correct symbols

4.34 Operator function


TERMINATION DRAWINGS

4.35 Panel/junction box and tag numbers clearly identified

4.36 Conductor numbers are shown

4.37 Terminal block numbers are shown

4.38 Control panel terminations are shown

4.39 Supplier interfaces are addressed


INSTRUMENT LOOP DIAGRAMS

4.40 Instrument type

4.41 Field cable number

4.42 Screen terminations

4.43 Junction Box number and terminations

4.44 Marshalling rack number and terminations

4.45 Field Termination Assembly number and terminations

4.46 System cable number

4.47 Processor cabinet number and I/O allocation shown

4.48 Control room reference

4.49 P&ID reference

4.50 Plant location reference

4.51 Power supply reference


FIELD BUS LOOP DIAGRAMS

4.52 Instrument type

4.53 Bus reference number

4.54 Field Cable number

4.55 Screen terminations

4.56 Junction Box number and terminations

4.57 Marshalling rack number and terminations

4.58 Field Termination Assembly number and terminations

4.59 System cable number

4.60 Processor cabinet number and I/O allocation shown

4.61 Control room reference

4.62 P&ID reference

4.63 Plant location reference

4.64 Power supply reference

4.65 Bus loading/entity schedule reference

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 12 of 37
Item Description Y N NA Comments
INSTALLATION HOOK-UP DIAGRAMS

4.66 Interface connections to piping

4.67 Service interface connections

4.68 Bill of materials description and quantities correct. Item


numbers correlate with drawing

4.69 Materials are suitable for application

4.70 Practical installation has been considered

4.71 Notes are comprehensive


References to installation details

4.72 Project design guide and relevant codes have been


considered
INSTRUMENT PANEL GENERAL ARRANGEMENTS

4.73 Cabinet/Console physical shape and profile.

4.74 Panel dimensions

4.75 Location, size and shape of cut-outs

4.76 All tagged items identified

4.77 Model numbers

4.78 Chart or scale ranges

4.79 Nameplates/labels

4.80 Front-of-Panel Instrument locations

4.81 Inside-of-Panel Instrument locations

4.82 Wiring details


CABLE SCHEDULES

4.83 Cable numbers

4.84 Origin and Destination (To/from) designation

4.85 Type of cable

4.86 Number of pairs/cores

4.87 Core size

4.88 Screen arrangement

4.89 Voltage rating

4.90 Cable length

4.91 Intrinsically Safe (IS) / Non IS

4.92 Cable gland type, size and details

4.93 Cable numbers


CABLE BLOCK DIAGRAMS

4.94 All items identified

4.95 Instrument cable numbers shown

4.96 All item locations shown

4.97 WorleyParsons scopes identified

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 13 of 37
Item Description Y N NA Comments
SYSTEM ARCHITECTURE DIAGRAMS

4.98 Systems and protocols identified

4.99 HMI interfaces identified

4.100 Interconnection of new control system tie-ins to existing


control systems identified
CAUSE AND EFFECT DIAGRAMS

4.101 P&IDs are at IFC status

4.102 Narrative descriptions have been received from Process


Engineering

4.103 Format of C&E Diagrams has been agreed with Customer

4.104 C&E Diagrams have been reviewed by Process Engineering

4.105 Notes and P&ID reference drawing numbers are correct

4.106 Equipment numbers are correct

4.107 C&E Diagrams have been through HAZOP


COMMUNICATIONS LAYOUTS

4.108 System scope defined

4.109 System specification approved

4.110 Area classification considered

4.111 Interferences resolved

4.112 Conductor size and type specified

4.113 Cable routing shown

4.114 Telephone locations shown in the model

4.115 Exchange telephone system shown

4.116 Noise map and requirements considered

4.117 Materials identified

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 14 of 37
5. HVAC DRAWINGS

Item Description Y N NA Comments


CONTENT

5.1 Conformance to Ducting and Instrumentation Diagrams


(D&IDs)

5.2 Conformance to engineers design

5.3 Duct sizes identified

5.4 Duct support locations identified

5.5 Duct routing shown in the 3D model

5.6 Identification of ducts and HVAC components

5.7 Clearances between ducts, pipes, equipment and access


ways

5.8 Support locations and symbols

5.9 Insulation shown

5.10 Instrumentation location and identification

5.11 Fresh air intakes located in non-hazardous area

5.12 Exhaust air discharges located to avoid personnel access


ways

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 15 of 37
6. SUPPLIER MECHANICAL EQUIPMENT DRAWINGS

Item Description Y N NA Comments


CONTENT

6.1 Check all nozzle sizes, ratings, orientations

6.2 Packaged equipment dimensions: footprint suits allocated


width, length, height

6.3 Packaged equipment hold-down/mounting details. Bolt hole


sizes and patterns including base thickness or hole sizes
including lengths and patterns.

6.4 Packaged equipment layout acceptable: access to piping,


equipment, manways, inspection openings, sample points,
manual valve operators, regular maintenance items

6.5 Packaged equipment layout is functional, suits process


elevation needs.

6.6 Packaged equipment instrument location and identification:


actuated valves, local read-out instruments, flow meters,
corrosion monitoring devices,

6.7 Packaged equipment personnel and maintenance access

6.8 Packaged equipment Mechanical Handling Report


requirements have been satisfied

6.9 Packaged equipment pipe supports

6.10 Packaged equipment insulation

6.11 Packaged equipment piping tie-in points: sizes, ratings,


orientations, elevation

6.12 Packaged equipment interfaces with power supply, control


systems

6.13 Packaged equipment exhaust air discharges located to avoid


personnel access ways

6.14 Packaged equipment fresh air intakes located in non-


hazardous zone

6.15 Packaged equipment laydown, drop-out areas and


equipment withdrawal areas acceptable

6.16 Vessel dimensions, OD, Tan to Tan length, skirt height

6.17 Vessel/Tower access ladders, platforms; orientation,


elevation, size

6.18 Vessel mounting details: Bolt hole sizes and patterns


including base thickness

6.19 Saddle or mounting bracket locations

6.20 Support legs details

6.21 Fixed and sliding ends

6.22 Internals removal clearance required: tube bundles, coils,


elements, packing, catalyst

6.23 Pipe support mounting clips

6.24 Cable ladder mounting clips

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 16 of 37
Item Description Y N NA Comments

6.25 Instrumentation mounting clips

6.26 Exchanger nozzle locations and orientations, drainage


requirements, tube removal envelope

6.27 Rotating equipment drainage requirements

6.28 Tank stairway location and orientation, sample point location,


roof nozzle arrangement, walkways

6.29 Grouting requirements

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 17 of 37
7. EQUIPMENT LAYOUTS

Item Description Y N NA Comments


CONTENT

7.1 Battery limits

7.2 Sections, details, identifications

7.3 Coordinates

7.4 Equipment list, numbers, descriptions (must match Master


Equipment List)

7.5 Equipment locating dimensions

7.6 Equipment elevations are correctly located by the Elevation


Reference Point

7.7 Equipment dimensions are in accordance with latest supplier


data

7.8 Layout conforms to project Platform Layout Specification (if


applicable)

7.9 Equipment safety requirements have been reviewed by


Safety Group and comments incorporated

7.10 Layout conforms to project HSE & ergonomic guidelines for


safe personnel operation

7.11 Operator personnel routes, unit emergency egress routes,


assembly areas, evacuation routes, drop zones and laydown
areas identified

7.12 Layout satisfies requirements of project environmental data,


wind, tides, currents (if applicable)

7.13 Layout is functional and economic, follows process flow,


suits process elevation needs.

7.14 Equipment is accessible for maintenance and routine


operations

7.15 Mechanical Handling Report requirements have been


incorporated

7.16 Flare radiation zone correct, clearance to other areas OK,


flare drum in optimum location

7.17 Location of electrical equipment considers area


classification, proximity to hazardous equipment (both inside
and outside battery limits).

7.18 Check against hazardous area drawings to see if equipment


can be moved into a safer area

7.19 Constructability issues addressed

7.20 Layout addresses future expansion requirements, allows for


adjacent existing equipment

7.21 Equipment withdrawal areas specified

7.22 All relevant dimensions and levels shown and are correct

7.23 Fire monitor and hydrant locations confirmed acceptable.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 18 of 37
Item Description Y N NA Comments

7.24 Equipment location and drainage design take into account


drainage for normal operation, shutdown and maintenance,
stormwater, firewater and flammable liquid pooling, etc.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 19 of 37
8. PLOT PLANS

Item Description Y N NA Comments


CONTENT

8.1 Pipe rack column/rows shown and numbered

8.2 Outlines of major structures, major civil works, roads,


drainage, slabs etc shown

8.3 Equipment tag numbers and descriptions conform to P&ID.


Cross check with equipment list

8.4 Equipment locating coordinates correct. Equipment


elevations are correctly located by the Elevation Reference
Point

8.5 Plant coordinate & level datum points are shown and are as
agreed with Civil/Structural

8.6 Finished grade elevations have been viewed and agreed to


by the Civil Group

8.7 Equipment dimensions are in accordance with latest supplier


data

8.8 Layout conforms to project specification

8.9 Equipment safety requirements have been reviewed by


Safety Group and comments incorporated

8.10 Layout conforms to project HSE & ergonomic guidelines for


safe personnel operation

8.11 Operator personnel routes, unit emergency egress routes,


assembly areas, evacuation routes, drop zones and layout
areas identified

8.12 Layout satisfies requirements of project environmental data

8.13 Layout accounts for site geographic data (natural elevations,


flood, wind, soil, stormwater, temperatures, tides)

8.14 Layout is functional and economic, follows process flow,


suits process elevation needs.

8.15 Equipment is accessible for maintenance and routine


operations.

8.16 Mechanical Handling Report requirements have been


incorporated

8.17 Flare radiation zone clearances have been reviewed

8.18 Location of electrical equipment considers area


classification, proximity to hazardous equipment (both inside
and outside battery limits).

8.19 Check against hazardous area drawings to see if potential


ignition sources can be moved into a safer area

8.20 Constructability issues addressed: construction traffic


access, laydown, space for major lifts

8.21 Road layout addresses emergency vehicle access to


process plant, tankage, Firefighting Equipment (FFE)

8.22 Road widths checked and correct

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 20 of 37
Item Description Y N NA Comments

8.23 Maintenance crane location and equipment laydown, dropout


and removal areas identified. Safe areas for trailers, huts
and other shutdown facilities are provided.

8.24 Layout addresses future expansion requirements, allows for


adjacent existing equipment

8.25 Existing and future underground services have been


identified and allowed for in layout

8.26 Extent of paving areas shown

8.27 Building placement has considered proximity to hazardous


equipment (both inside and outside battery limits) and local
codes and regulations

8.28 Fire monitor and hydrant locations confirmed acceptable.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 21 of 37
9. PIPING GENERAL ARRANGMENTS FROM 3D MODELS

Item Description Y N NA Comments


CONTENT

9.1 Cable ladders shown

9.2 All structures shown

9.3 Roads and buildings shown

9.4 Ducting and HVAC shown (only where not obscuring piping)

9.5 Civil works shown and reference levels correct

9.6 Underground piping identified

9.7 Sections, details, identifications

9.8 Equipment numbers , Line numbers and Tie-in numbers

9.9 Structural gridlines, numbers and dimensions

9.10 In-line and vessel mounted Instrument numbers

9.11 Clearances between pipes, equipment and access ways

9.12 Pipe support numbers, locations and symbols (if shown on


Piping Plans)

9.13 Pipework locating dimensions only

9.14 Equipment locating dimensions

9.15 Operator and maintenance access

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 22 of 37
10. PIPING GENERAL ARRANGEMENTS 2D

Item Description Y N NA Comments


CONTENT

10.1 Compliance with project safety and ergonomic guidelines

10.2 Compliance with certified equipment drawings

10.3 Compliance with certified in-line instrument drawings

10.4 Pipe routing complies with stress engineers requirements

10.5 Cable Trays shown, not obscuring piping, (break out where
obscuring piping)

10.6 All structures shown

10.7 Access platform elevation and extent correct and clash free

10.8 All buildings shown

10.9 Ducting and HVAC shown (only where not obscuring piping)

10.10 Roads, fences and civil works shown and reference levels
correct

10.11 Extent and level of paved areas

10.12 Underground piping identified correctly

10.13 Existing piping identified correctly

10.14 Future piping identified correctly

10.15 Sections, details, identifications (incl. scale)

10.16 Structural gridlines, numbers and dimensions

10.17 All line numbers identified

10.18 All equipment numbers are shown

10.19 Equipment nozzle numbers, size rating are in accordance


with the suppliers drawings

10.20 Instrument tag numbers are identified

10.21 SP Item numbers are identified

10.22 Tie-in numbers are identified

10.23 SP Item dimensions and ratings

10.24 Control valve dimensions and ratings

10.25 Non-standard valve dimensions and ratings

10.26 Equipment locating dimensions

10.27 Equipment withdrawal and dropout areas

10.28 Equipment fixed and sliding ends shown and are correct

10.29 Equipment insulation thickness

10.30 Vessel trim shown correctly

10.31 In-line and vessel mounted Instrument numbers

10.32 Pipe support numbers, locations and symbols (if shown on


Piping Plans)

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 23 of 37
Item Description Y N NA Comments

10.33 Coordinates, datums

10.34 Insulation extents shown

10.35 Insulation thickness correct

10.36 Grade, TOS and TOC elevations shown and correct

10.37 Operator and maintenance access

10.38 Instrument interfaces are correct

10.39 Compliance with certified SP item drawings

10.40 Piping runs are economical. Unnecessary offsets and


doglegs and elevation changes are avoided

10.41 Rack piping is in accordance with design guidelines, at


correct rack level for economical arrangement, elimination of
pockets and free drainage

10.42 Piping arrangement for Offshore Hook-up spools has been


reviewed and Design Review comments actioned

10.43 Offshore Hook-up spool sizes and welds have been


reviewed and Design Review comments actioned

10.44 Maintenance and operating clearances are adequate

10.45 Pipe supports on critical lines are located in accordance with


stress engineers requirements

10.46 BOP elevations allow for shoes, corrosion strips, saddles,


insulation etc.

10.47 Weld clearances at/around support locations are adequate

10.48 Manual valve accessibility, operability and orientation is


adequate

10.49 Valve top works (operator/hand wheel) sizes and orientation

10.50 Actuated valve accessibility, operability and orientation is


adequate

10.51 Critical valves, unit isolation valves, battery limit valves and
firefighting equipment isolation valves are located in safe
areas and are accessible

10.52 Removable spools specified where shown on P&IDs, and for


removal or dismantling of equipment

10.53 Sufficient clearance is available for use of the removal tool


on corrosion coupon fittings

10.54 Sufficient clearance for bolt installation & removal (e.g. Bfly
& wafer valves)

10.55 Allowance has been made for RTJ spool and fitting
installation/removal

10.56 Adequate clearance allowed for spec blind, spade & spacer
installation & swinging

10.57 Pipe spacings and spans are in accordance with project


span charts

10.58 Adequate pipe clearances to structures, equipment, cable


trays, insulation, grade, platforms, overhead etc.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 24 of 37
Item Description Y N NA Comments

10.59 Pipe spacings allow for installation of insulation and pipe


supports

10.60 Temporary strainers can be removed.

10.61 Clearances for thermowell withdrawal

10.62 Space under Y type and Basket strainers is sufficient to


install and operate blowdown/drain valves

10.63 Pipe routing does not impede the use of gantry and radial
cranes, davits and monorails

10.64 Pump suctions are not pocketed, reducers correct, straight


lengths OK, NPSH requirements satisfied

10.65 Process requirements for non-pocketing, NPSH, slope and


symmetrical piping arrangements are adhered to. Refer to
notes on P&IDs

10.66 Flare & vent, steam & condensate piping are sloping
correctly

10.67 PSVs, bursting discs and blowdown valves are arranged


with minimum length self-draining inlet lines and self-draining
outlets to flare or vent headers

10.68 PSV discharges to atmosphere are located in safe areas

10.69 Drain header slopes are correct. Drain rod-out points are in
correct positions and are accessible

10.70 Drains discharging into an atmospheric drain system are


arranged for safe splash free and visible drainage, into
tundishes or collection boxes

10.71 Centrifugal compressor suctions are not pocketed. Straight


lengths are adequate

10.72 Reciprocating compressor and pump pulsation bottles


positioned correctly

10.73 Fired Heater inlet/outlet piping is symmetrical and


symmetrical branches are of equal length

10.74 Fired Heater fuel gas supply piping to the burner is


symmetrical and the burner fuel isolation valves is in a safe
area

10.75 Instruments are accessible in accordance with project


specifications and job notes

10.76 Instrument requirements for location, orientation, piping


interface and clearance are in accordance with design
guidelines

10.77 ESD and blowdown valves are accessible and located in


safe areas, or in positions approved by the safety group

10.78 Control valves are located in accordance with P&IDs and


design guidelines

10.79 Flow Metering runs are in accordance with up/downstream


requirements

10.80 Piping Tie-in locations and requirements are correct.

10.81 Piping Tie-ins have been site surveyed

10.82 Hydrostatic vents and drains are shown and are sized

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 25 of 37
Item Description Y N NA Comments
correctly

10.83 Process vents and drains are located correctly, in positions


shown on P&IDs

10.84 All branch piping from utility headers such as steam, steam
condensate, instrument air, plant air and nitrogen is taken
from the top of the header

10.85 Utility hose stations are correctly located. Hose couplings


located at correct height and all utilities are in correct and
common sequence

10.86 Steam and Plant Air piping is designed with low point
drains/liquid traps as shown on P&IDs or specified in project
standards

10.87 Steam drip legs and steam traps are located correctly

10.88 Firewater piping is routed in areas and positions where it is


least likely to incur damage from fire and explosion.

10.89 Deluge system piping downstream of the deluge valve is


self-draining

10.90 Firewater monitor, deluge control valves and foam systems


are located outside the area containing the piping system
they are controlling/supplying

10.91 Hydrants, monitors and deluge nozzles are located in


accordance with spray and radius patterns defined by
engineers/consultants recommendations

10.92 Hydrants and manually directed monitors are accessible by


approach from two opposite directions, with adequate
clearance for operation

10.93 Tank farm piping is an economical arrangement, providing


maximum access to tank appurtenances

10.94 Tank access stairs are clear of obstructions with a clear path
to escape routes

10.95 All tank appurtenances with local readouts or requiring


regular attention by operators are supplied with permanent
access

10.96 Tank isolating valves are located on the tank nozzle, or as


close as practicable to tank nozzles.

10.97 Tank pumps, control valves and fire protection systems are
located outside bund walls, in safe areas

10.98 Sample points are located where shown on P&IDs with


permanent access

10.99 Underground piping is located with cover in accordance with


design guidelines

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 26 of 37
11. PIPING ISOMETRICS FROM 3D MODEL

Item Description Y N NA Comments


CONTENT

11.1 Graphics readability, clarity

11.2 NDT, Traceability, painting, testing, insulation, process


conditions etc (note 1)

11.3 Yellow line check for compliance to process MASTER


P&IDs, including all mark-ups & P&ID notes. (P&IDs must be
at IFC status)

11.4 Review the Clash Check Report. All clashes should be


resolved before isometrics are issued for Construction

11.5 Instrument / Equipment tag numbers shown and identified

11.6 Equipment nozzle numbers size & ratings are in accordance


with the suppliers drawings

11.7 Flowstream arrows are shown and correct

11.8 Tie-in numbers correct

11.9 Sloping lines, correct slope and direction

11.10 Spec. break locations

11.11 Underground pipe add note regarding coating and


wrapping

11.12 Hydrostatic vents & drains, size & location

11.13 Thermowell locations & standouts correct

11.14 Flow meter straight runs are correct

11.15 Platform/grade penetrations are shown

11.16 Check compliance with all project specs & standard


drawings & all project job notes

11.17 In-line instrument dimensions and ratings are correct

11.18 SP Item dimensions and ratings are correct

11.19 Orifice flange tapping orientations and details correctly


shown

11.20 HOOK-UP SPOOL noted where applicable

11.21 OPEN END pipe noted where applicable

11.22 Extents/limits of personnel protection and insulation are


correct

11.23 For critical lines, check compliance with final stress isometric

11.24 Pipe support numbers are correct

11.25 Pipe support type is correct

11.26 Pipe support locations & spans are correct

11.27 Correct CL pipe elevation to allow for shoes, pads etc.

11.28 Line is modelled to correct spec

11.29 SP Items listed correctly

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 27 of 37
Item Description Y N NA Comments

11.30 All Instrument numbers correct and instruments listed as BY


INSTR

11.31 Supports listed correctly

11.32 Check for error messages in the BOM (Design Systems


Coordinator to clear)

11.33 Spot check BOM only (1 in 15 isos)

11.34 Check all valve codes

11.35 Wall thickness of nipples

11.36 Check all non-standard bolt lengths, incl thermowells,


insulation gaskets & PSV inlet

11.37 Check bolt withdrawal clearances, including requirements for


bolt tensioning equipment and close fitting valve assemblies
& adjacent branches (if bolt tensioning is required longer
than standard bolt lengths may be required)

11.38 Check bolt hole orientation for any rolled items and provide
detail if non-standard bolt hole orientation is required

11.39 Min weld clearance of 50mm or 4 x WT


ISOMETRIC CONTROL

11.40 Isometric Control sheet has been updated

11.41 Isometric Control P&ID set has been updated for progress
control

Notes:
1. Lines <DN50 are site run. P&ID check only required.
2. Do not show FW or FFW locations, spool numbers, weld numbers or cut lengths.
3. Items not listed are to be checked during Model Reviews

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 28 of 37
12. PIPING ISOMETRICS 2D

Item Description Y N NA Comments


CONTENT

12.1 Graphics readability, clarity

12.2 NDT, Traceability, painting, testing, insulation, process


conditions etc

12.3 Yellow line check for compliance to process MASTER


P&IDs, including all mark-ups and P&ID notes. (P&IDs must
be at IFC status)

12.4 Dimensional check against piping GAs

12.5 Instrument / Equipment tag numbers shown and identified

12.6 Equipment nozzle number, location, size & ratings are in


accordance with the suppliers drawings

12.7 Flowstream arrows are shown & are correct

12.8 Tie-in numbers correct

12.9 Sloping lines, correct slope and direction

12.10 Work Point Elevations

12.11 Spec. break locations

12.12 Underground pipe add note regarding coating and


wrapping

12.13 Hydrostatic vents & drains, size & location

12.14 Thermowell locations & standouts correct

12.15 Platform/grade penetrations are shown

12.16 Check compliance with all project specs, standard drawings


& all project job notes

12.17 In-line instrument dimensions and ratings are correct

12.18 Instrument tapping location, size and type

12.19 Piping/Instrument interfaces

12.20 SP Item dimensions and ratings are correct

12.21 Orifice flange tapping orientations and details correctly


shown

12.22 HOOK-UP SPOOL noted where applicable

12.23 OPEN END pipe noted where applicable

12.24 Type, extents/limits of personnel protection and insulation


are correct

12.25 For critical lines, check compliance with final stress isometric

12.26 Pipe support numbers are correct

12.27 Pipe support type is correct

12.28 Pipe support locations & spans are correct

12.29 Correct CL pipe elevation to allow for shoes, pads etc.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 29 of 37
Item Description Y N NA Comments

12.30 Welded attachment details

12.31 Line is drafted to correct Piping Materials Specification

12.32 SP Items listed correctly

12.33 All Instrument numbers correct and instruments listed as BY


INSTR

12.34 Full check of Bill of Materials against iso and Piping


Materials Spec

12.35 Check all valve codes

12.36 Wall thickness of nipples

12.37 Non-standard bolt lengths

12.38 Check structural column references

12.39 Valve locations

12.40 Valve operator orientation

12.41 Check all non-standard bolt lengths, incl thermowells,


insulation gaskets & PSV inlet

12.42 Check bolt withdrawal clearances, including requirements for


bolt tensioning equipment and close fitting valve assemblies
& adjacent branches (if bolt tensioning is required longer
than standard bolt lengths may be required)

12.43 Check bolt hole orientation for any rolled items and provide
detail if non-standard bolt hole orientation is required

12.44 Min weld clearance of 50mm or 4 x WT


ISOMETRIC CONTROL

12.45 Isometric Control sheet has been updated

12.46 Isometric Control P&ID set has been updated for progress
control

Notes:
1. Do not show FW or FFW locations, spool numbers, weld numbers or cut lengths.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 30 of 37
13.PIPE SUPPORT DRAWINGS (SPECIAL SUPPORTS)

Item Description Y N NA Comments


CONTENT

13.1 Supports requiring structural check have been reviewed by


structural engineer

13.2 Structural requirements incorporated

13.3 Support dimensions correct

13.4 Support spans correct.

13.5 Plastic/fiberglass piping is supported at spans in accordance


with manufactures recommendations

13.6 Shoes sufficient length to allow for axial movement due to


thermal growth

13.7 Shoe heights allow for required insulation thickness

13.8 Support is located to allow for bolt removal on adjacent


flanges

13.9 Material selection is in accordance with selection guidelines

13.10 Weep holes shown in dummy legs, saddles, reinforcement


pads etc.

13.11 Dissimilar metals issues have been addressed

13.12 Gaps on guides and line stops correct

13.13 Selected U-Bolts suitable for purpose

13.14 Support is clash free in the model

13.15 Welding details correct

13.16 Field trim allowance has been shown on field welded


supports

13.17 Supports on rotating equip piping, local to the equip, are


adjustable to permit field alignment.

13.18 Base plates installed where support BOD requires

13.19 Support design allows for stress relieving of piping

13.20 Support does not infringe on personnel access clearance

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 31 of 37
14.STRUCTURAL AND ARCHITECTURAL DRAWINGS

Item Description Y N NA Comments


GENERAL ARRANGEMENT AND LAYOUT DRAWINGS

14.1 Correct dimensions, elevations, coordinates, datum

14.2 Interface with foundations

14.3 Interface with other disciplines

14.4 Arrangements conform to project standards for stairs,


ladders, platforms and handrailing

14.5 Stairs, ladders and platforms for equipment, instrument,


valve access are correct size, elevation etc.

14.6 Clearances to adjacent structures, equipment

14.7 Constructability, simplicity of design

14.8 Accessibility for welding all components

14.9 Weldability (material type, thickness, type of weld)

14.10 Corrosion protection, painting, seal welding

14.11 Non-slip surfaces for stairs, platforms, access ways specified


where necessary

14.12 Passive fire protection specified where necessary

14.13 Weld inspection requirements

14.14 Material specifications

14.15 Framing Plans and Elevations

14.16 Correct member sizes and material grades (check against


engineers specifications)

14.17 Dimensions, TOS elevations

14.18 Match line information (drawing no, coordinates, Line type,


description)

14.19 Beam/column section splices shown

14.20 Orientation of steel sections

14.21 For skids and modules, has center of gravity and weight
been indicated?

14.22 Connections to existing steelwork

14.23 Corrosion protection, painting, seal welding

14.24 Transport options considered. Size and weight limitations

14.25 Design in accordance with project standards

14.26 Connections to existing steelwork shown

14.27 Bolt holes, bolts, bolting procedure, anchor bolts

14.28 Beam/column section splices shown

14.29 Welding symbols

14.30 NDT requirements

14.31 Structural Pipe Support Drawings

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 32 of 37
Item Description Y N NA Comments

14.32 Support locations reflect pipe stressing requirements

14.33 Support elevations and locations match final piping


arrangements
STAIR, LADDER AND HANDRAIL DRAWINGS

14.34 Stair and ladder configuration in compliance with applicable


Code/Standard

14.35 Correct member sizes and material grades (check against


engineers specifications)

14.36 Design in accordance with project standards

14.37 Ladder gates specified

14.38 Ladder cage requirements checked

14.39 Ladder rails and rungs clear of obstructions

14.40 Ladder fixing details specified

14.41 Handrail post adequately supported


GRATING AND PLATING DRAWINGS

14.42 Grating adequately supported

14.43 Grating specified in accordance with manufacturers ordering


requirements

14.44 Plating adequately supported

14.45 Plating and grating sizes specified

14.46 Grating weight is within ergonomic requirements for lifting

14.47 Corrosion protection, painting, seal welding

14.48 Welding symbols correct


LIFTING, RIGGING AND PADEYE DRAWINGS

14.49 Rigging components specified including spreader beams

14.50 Safe working loads of rigging components specified and


consistent with lifted weight

14.51 Lift weight and center of gravity of lifted component specified

14.52 Spreader beams adequately sized

14.53 Padeye details fit specified shackles

14.54 Padeyes are adequately attached to the structure

14.55 NDT requirements specified

14.56 Safe working load of monorails clearly marked on beam


ARCHITECTURAL DETAIL DRAWINGS

14.57 Design in accordance with project standards

14.58 Applicable building codes identified and listed

14.59 Materials specified

14.60 Sections and detail identifications

14.61 Detail orientation correct

14.62 Dimensions legible

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 33 of 37
Item Description Y N NA Comments

14.63 Constructability considered

14.64 Interface with structure and equipment

14.65 Interface with other disciplines (piping, electrical,


mechanical, instruments)

14.66 Corrosion protection, painting, seal welding

14.67 Fire sealing of piping and cable wall/floor penetrations

14.68 Ventilation and air intake points are drawing air from safe
areas

14.69 Building is orientated correctly, is sun shading required

14.70 Safety glass specified for windows where necessary


INSTALLATION DRAWINGS

14.71 Installation sequence

14.72 Temporary access/installation aids

14.73 Check clearances to surrounding structure and equipment

14.74 Check crane lift capacity at pick up and setdown locations

14.75 Check height clearance for rigging and installed component

14.76 Hard points located for rigging and winch locations

14.77 Dimensions legible


FOUNDATION DRAWINGS

14.78 Correct elevation to top of concrete

14.79 Location coordinates defined

14.80 Loads have been established

14.81 Hold down bolt locations match structural / mechanical


details

14.82 Check latest supplier data

14.83 Dimensions legible

14.84 Check clearances from adjacent foundations

14.85 Reinforcing specified

14.86 Earthworks preparation specified

14.87 Concrete grade specified

14.88 Hold down bolt details specified


CONCRETE DETAIL DRAWINGS

14.89 Dimensions legible

14.90 Reinforcing details shown and are as specified by engineer

14.91 Loads have been established

14.92 Sections and detail identifications

14.93 Detail orientation correct

14.94 Constructability considered

14.95 Interface with structure and equipment

14.96 Interface with other disciplines (piping, electrical,

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 34 of 37
Item Description Y N NA Comments
mechanical, instruments)

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 35 of 37
15.CIVIL DRAWINGS

Item Description Y N NA Comments


GENERAL ARRANGEMENT AND LAYOUT DRAWINGS

15.1 Coordinates, dimensions

15.2 Datum specified correctly, (MSL, CD, etc)

15.3 Grid systems specified correctly

15.4 Setout information adequate

15.5 Check latest supplier information

15.6 Materials specifications

15.7 Dimensions and elevations meet design outcomes

15.8 Construction sequencing is possible

15.9 Target fill lines and grades specified clearly

15.10 Target dredge/cut lines and grades specified clearly

15.11 Material zones clearly identified and correlate with


specifications

15.12 Site access clearly identified

15.13 Services locations clearly marked


UNDERGROUND SERVICES PLANS

15.14 North arrow orientation

15.15 Reference locations and matchlines

15.16 Dimensions and datum

15.17 Key plan

15.18 Check clearances from adjacent foundations

15.19 Check clearances from adjacent services

15.20 Interface with above ground services (piping, cable trays,


structures)
CIVIL DETAIL DRAWINGS

15.21 Materials specified

15.22 Sections and detail identifications

15.23 Detail orientation correct

15.24 Dimensions legible

15.25 Earthworks preparation specified

15.26 Location coordinates defined

15.27 Constructability considered

Item Description Y N NA Comments


ROAD DETAIL DRAWINGS

15.28 Materials specified

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 36 of 37
Item Description Y N NA Comments

15.29 Sections and detail identifications

15.30 Detail orientation correct

15.31 Vehicle turning radii addressed

15.32 Dimensions legible

15.33 Road alignment specified in accordance with standards

15.34 Earthworks preparation specified

15.35 Location coordinates defined

15.36 Constructability considered

15.37 Drainage considered


DRAINAGE DETAIL DRAWINGS

15.38 Detail orientation correct

15.39 Dimensions Legible

15.40 Earthworks preparation specified

15.41 Location coordinates defined

15.42 Interface with foundations

15.43 Drainage considers natural fall of land

15.44 Pits and invert levels correctly specified

15.45 Pits labelled

15.46 Drainage design takes into account drainage for normal and
upset operation, shutdown and maintenance, stormwater,
firewater and flammable liquid pooling, etc.

EPF-0121-COR-EN Rev 5 (23-May-16)


Page 37 of 37

S-ar putea să vă placă și