Sunteți pe pagina 1din 107

PROGRAM SUPPLY PLAN

During the pre-FEED Phase, the Program Procurement Management Team (PPMT) in cooperation with the
Envelope Management Teams and other Company stakeholders, developed an overall Program Supply
Plan, which was further developed during the FEED Phase.
The driving force behind the plan is to establish the Vendor selection and management process and
determine the level of Company engagement preceding and during the EPC Phase by addressing the
following areas:

(a) Optimum number of Vendors available, or required, to address the extensive and diverse RTIP scope
of supply.
(b) Procurement strategies for key commodities based upon the overall RTIP contracting strategy and
schedule considerations, available supply sources, technology requirements, potential risks and rewards,
local content, total cost of ownership and similar requirements.
(c) Need to negotiate and award Program Leveraged Agreements (PLAs) to support standardization
initiatives, and to reduce cost and schedule.
(d) Optimum level of consolidation of Vendors, and equipment / material models and types to enable
effective site standardization, including spare parts, and operations and maintenance requirements.
(e) Optimum levels of expediting and inspection to be imposed upon the individual Contractors.

The Program Supply Plan can be thought of as the repository for the "Program Approved Vendors List" and
all procurement strategies developed during FEED as part of the following independent activities:
Program Contracting Strategy
Equipment and Materials Standardization Plan
Procurement Market Studies and Selected Sourcing Strategies
Local Content Plan
Main elements of the finalized plan include estimated quantities and cost by equipment / material groupings
(on the project level - see Project Supply Plan), approved Vendors, negotiation elements, timing, expediting
and inspection requirements, and procurement strategies and their implementation elements, etc. A
classification for Equipment and Bulk materials will identify the approach for obtaining market pricing to
support the estimate.

PROJECT SUPPLY PLANS


Specific Project Supply Plans for each unit were developed by the responsible FEED / PMC Contractors in
cooperation with the Envelope Management Teams by incorporating relevant elements from the Program
Supply Plan and increasing the level of detail to include item specific requirements / strategies. In addition,
the Project Supply Plans will include all Licensor mandated proprietary Vendors to comply with performance
and warranty obligations. These plans will be the controlling document for the supply of all equipment and
materials, related services and standardization by the Contractors, and issued as part of the EPC Invitation to
Bid (ITB). Company Project Procurement Leads (PPLs) will provide required direction and oversight for the
Project Supply Plans with final approval by the PPMT.

Doc. No: A554-K-PRG-PU-LIS-DOC-009 Contains Confidential Information of Date: 29 July 2011


(Introduction) Both Dow and Saudi Aramco Revision: 04
EQUIPMENT AND MATERIAL CLASSIFICATIONS
For the FEED Estimate, Company has directed the FEED / PMC Contractors to obtain Vendor
budget quotations for eighty percent (80%) of the Total Equipment Cost per unit. Equipment
being defined as all "tagged" process equipment (mainly mechanical and process containing
equipment - PCE). The bulk materials are addressed differently (a mix of market data and
statistical modeling).
Recommendation:
The budget quotes should cover more than just the Process Equipment, as many other major
equipment items may have a very high value and therefore an impact on the estimate accuracy.
Request:
The FEED / PMC Contractor is requested to review the attached list of equipment and materials
categories and comment on the selected classification: Bulk or Equipment. An Equipment
identifier ("E") indicates that item will be added to the equipment list, and consequently covered
by budget quotes, provided the cost is of sufficient magnitude to influence the eighty percent
(80%) requirement. An identifier "B" means it has been classified as a Bulk item. Note that
some "Critical Equipment" may require a "purchase quality" inquiry perhaps - to be indentified in
the Estimating Plan.

Doc. No: A554-K-PRG-LIS-DOC-009 Contains Confidential Information of Date: 29 July 2011


(Classifications) Both Dow and Armaco Revision: 04
STANDARDIZATION CATEGORY DEFINITIONS
Depending on the final selection of the product categories to be standardized
(outcome of the workshops, benefit / cost evaluations) Company will use the
following means of achieving standardization / variability minimization.

Category A - PLAs: Where functionality of the whole Complex or safety is


concerned, or a significant impact on total cost of ownership is identified, one (1) or
a limited number of Vendors will be selected by Company to supply Program-wide
equipment and/or materials. Alternatively, such Vendors may be selected by
Company to supply a given site area or envelope. During the Design Phase,
Company will competitively bid and enter into Program-wide PLAs with Category A
Vendors.

Category B - Company Directed Materials: Where Company wishes to direct


Vendor selection due to total cost of ownership considerations or any other reason,
Company may request Contractor to utilize a Vendor other than the one selected by
Contractor from the Project Supply Plan. Such Company direction may give rise to
a Change Order under paragraph 10 of Schedule A.

Category C - Matching Vendor Materials: Where Company does not wish to


influence Vendor selection, Contractor shall conduct the procurement process in
accordance with the Vendor selection requirements set out in Schedule G. Once a
Vendor has been selected, Contractor must source items within its scope of Work
from the same Vendor to achieve a level of standardization.

Category D - Commodity Materials: For certain high volume, low impact materials
and low unit cost items (including components of a larger item or package typically
purchased by the main Equipment manufacturer) where standardization is required
but it is not economically advantageous to develop a PLA, Contractor must procure
only from Vendors listed in the Project Supply Plan or designated within the
technical package (datasheets/specifications contained in the Project Design Basis).

Category E - Critical Equipment: For Critical Equipment that requires special


attention in the procurement process. In some cases the Company may have
started the formal requisition process prior to the Effective Date. Contractor shall
assume responsibility for completing the procurement whether or not already
initiated by Company.

Category F - Licensor Directed Materials: For Equipment that must be procured


from a specific Vendor as required by a License Agreement.

Doc. No: A554-K-PRG-PU-LIS-DOC-009 Contains Confidential Information of Date: 29 July 2011


(Standardization) Both Dow and Saudi Aramaco Revision: 04
EXPEDITING LEVEL GUIDELINES

Typical Organization and Reporting Structure

An Expediting Coordinator shall be assigned to each individual Engineering, Procurement


and Construction (EPC) project by the EPC contractor and have responsibility for providing
oversight, supervision and coordination of all expediting activities both in the EPCs home
office and in the field, including all worldwide support locations and 3rd Party Agencies. The
Expediting Coordinator shall also be responsible for establishing and maintaining all project
expediting plans, procedures, work processes and related documentation for implementation
across the project to ensure maximum standardization of approach, reporting and control.
During EPC execution the Expediting Coordinator, working within the parameters as
established by these Expediting Level Guidelines, will determine the level and type (Home
Office and / or Field) of expediting required depending upon the complexity of the equipment
/ material, delivery criticality (interdependency, high impact on the project construction
schedule), field required date and / or previous history with the vendor, subject to
reassessment as circumstances dictate and Owner approval. After the appropriate level of
expediting has been established, the order is then assigned to the responsible Home Office
Expediter.
Home Office Expediters, reporting to the Expediting Coordinator, will be assigned to perform
desk expediting as outlined below and to provide oversight, supervision and coordination of
all expediting activities performed by Field Expediters, where required.

If field expediting is required, the assigned Home Office Expediter shall be responsible for
completing and forwarding all assignment details to the Field Expediter. The Home Office
Expediter shall determine which Field Expediter is best suited for a particular assignment
(considering cost, availability and experience).
Upon completion of each expediting visit, the Field Expediter shall complete the appropriate
expediting report and forward to the Home Office Expediter for further action and / or
distribution. Any back-up documents referred to in the report, such as production schedules,
photographs, etc. may be forwarded separately.

Home Office (Desk) Expediting


Home Office Expediters responsibilities and duties include: Verify receipt of order and
request return of signed order acknowledgement; confirm order has been entered into
vendor's system; confirm primary point of contact; review and confirm documentation
requirements; and establish a contact schedule to monitor the progress of milestones,
manufacturing schedules, sub-vendor orders, inspection witness points, and delivery.

Contains Confidential Information of Date: 29 July 2011


A554-K-PRG-PU-LIS-DOC-009 (Expediting) Both Dow and Aramco Revision: 04
Field Expediting
The Field Expediters responsibilities and duties shall be parallel to the duties of the Home
Office Expediter, regarding established level of communication with the manufacturer;
maintaining the timely submittal of drawings; confirming receipt of suborder equipment and
materials; and measuring the progress in the shop against the fabrication schedule.
Expediting Levels
The Expediting Levels outlined below (and incorporated within the Program Supply Plan) are
established based upon the complexity and criticality of equipment and materials as defined
herein. These levels reflect the minimum criteria for expediting coverage.
Level 1: Refers to industry standard equipment and materials purchased from vendors who
have demonstrated reliability in meeting standard delivery schedules. Usually no Field
Expediting is required. Home Office Expediting by telephone and email is required once a
month, as a minimum.
Level 2: This refers to equipment or materials with limited sources, large quantities and / or
schedule sensitive. Field Expediting is required and coverage ranges from once a month to
twice a month, or more frequently as required. Home Office Expediting is still required by
telephone and email twice a month, as a minimum.

Level 3: This refers to equipment and materials involving complex manufacturing steps, large
quantities, exotic materials, and / or is schedule critical. Field Expediting is required and
coverage normally ranges from twice a month to weekly visits. Home Office Expediting is still
required by telephone and email twice a month, as a minimum.
Level 4: This refers to equipment or materials with the highest priority considering delivery
time, vendor performance, the overall construction schedule and / or on the critical path.
These items are considered to be of prime importance to the successful and timely execution
of the project. Field Expediting coverage ranges from weekly visits to resident expediter.
Home Office Expediting is still required by telephone and email as required.
NOTE: Owner reserves the right to change the Expediting Levels (to a higher or lower level
or frequency based upon current performance and conditions) and also reserves the right to
accompany field expediters on visits to vendors and sub-vendors offices and manufacturing
facilities as Owner deems necessary.

Contains Confidential Information of Date: 29 July 2011


A554-K-PRG-PU-LIS-DOC-009 (Expediting) Both Dow and Aramco Revision: 04
INSPECTION LEVEL GUIDELINES

Level 0 Documentation requirements only; no equipment vendor inspection required

Level 1 Only final inspection is required prior to shipping


Includes as a minimum, pre-inspection meetings, one or more unspecified in
Level 2 progress surveillance visits, all witness and hold points, final inspection, and
release for shipment.
Same as level 2, except that in progress surveillance inspections shall be on a
Level 3
regular basis ( daily, weekly or bi-weekly)
Level 4 Resident inspector continually monitoring the work.

Contains Confidential Information of Date: 29 July 2011


A554-K-PRG-PU-LIS-009 (Inspection) Both Dow and Saudi Aramco Revision: 04
Program Supply Plan
Revision Record - Rev. 04
4 GEN ALL APPLICABLE CATEGORIES Indicated PLA Categories and Vendors where applicable
4 GEN ALL APPLICABLE CATEGORIES Deleted Spacing and Formatted where necessary
4 LABORATORY ALL CATEGORIES Revised entire section with the most recent changes
4 A4.7 ANALYZER, INFRARED (IR) - GAS CORRELATION Perkin-Elmer Deleted
ANALYZER, TOTAL ORGANIC CARBON (TOC) - ONLY FOR PROCESS WATER
4 A1.12 CONDENSATE STREAMS WITHOUT PARTICLES (CLEAN STREAM) "Pollution Control Systems (Biotector)" changed to "Biotector Analytical Systems Ltd."
ANALYZER, TOTAL ORGANIC CARBON (TOC) - ONLY FOR PROCESS WATER
4 A1.12 CONDENSATE STREAMS WITHOUT PARTICLES (CLEAN STREAM) Vendor Changed from Shimadzu to Biotector Analytical Systems Ltd.
ANALYZER, TOTAL ORGANIC CARBON (TOC) - ALL APPLICATIONS EXCEPT
FOR CLEAN PROCESS WATER CONDENSATE AND WATER WITH
4 A1.13 MONOMERS (DIRTY STREAM) "Pollution Control Systems (Biotector)" changed to "Biotector Analytical Systems Ltd."
4 A8.15 ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION VALVES (BELLOWS) Circo Instrumentation Technologies (HOKE) Deleted
4 A8.16 ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION VALVES (BALL) Circo Instrumentation Technologies (HOKE) Deleted
4 A8.19 ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION VALVES (O-RING) Circo Instrumentation Technologies (HOKE) Deleted
ANALYZER, SAMPLE SYSTEMS - ANALYZER SYSTEM PACKAGER Computer System Protection Chambers and Integrated Communications Co LTD (CPIC)
4 A8.23 (INTEGRATION) (SA) Added
4 A8.38 ANALYZER, SAMPLE SYSTEMS - TUBING FITTINGS Circo Instrumentation Technologies (HOKE) Deleted
Category Description Revised to Read "ANALYZER, SAMPLE SYSTEMS - HEAT
4 A8.39 ANALYZER, SAMPLE SYSTEMS - HEAT TRACED BUNDLES TRACED, PRE-INSULATED AND/OR JACKETED TUBING OR TUBING BUNDLES"
4 A8.43 ANALYZER, PROCESS SAMPLING Biar Inc. Added
4 A8.43 ANALYZER, PROCESS SAMPLING Phoenix Precision Added
4 B1.1 BATTERY, CHARGERS Special Considerations Added
4 B1.2 BATTERY, FLOODED ELECTROLYTE STA. STORAGE BATTERY Special Considerations Added
4 B2.0 BUS DUCT Category Deleted
4 B2.1 BUS DUCT, 18 kV ISO-PHASE Category and Vendors Deleted in their entirety
4 B4.1 CABLE, POWER, 1KV THROUGH 35 KV Gulf International Electric Distribution Apparatuses Co LTD (SA) Deleted
4 B4.1
B4 1 CABLE POWER
CABLE, POWER, 1KV THROUGH 35 KV Ne ans Deleted
Nexans
4 B4.1 CABLE, POWER, 1KV THROUGH 35 KV Oman Cables Industry (SA) Deleted
4 B4.1 CABLE, POWER, 1KV THROUGH 35 KV Prysmian Cables & Systems SRL Deleted
4 B4.1 CABLE, POWER, 1KV THROUGH 35 KV "Riyadh Cable" Added to Saudi Modern Company for Cable (SA)
4 B4.1 CABLE, POWER, 1KV THROUGH 35 KV The Okonite Company Deleted
4 B4.1 CABLE, POWER, 1KV THROUGH 35 KV Gulf Cable & Electrical Industries Co KSC Added
4 B4.2 CABLE, < 1000 V "Power" Added to Category Description
4 B4.2 CABLE, POWER, < 1000 V Draka Cableteq Deleted
4 B4.2 CABLE, POWER, < 1000 V Gulf International Electric Distribution Apparatuses Co LTD (SA) Deleted
4 B4.2 CABLE, POWER, < 1000 V Oman Cables Industry (SA) Deleted
4 B4.2 CABLE, POWER, < 1000 V Prysmian Cables & Systems SRL Deleted
4 B4.2 CABLE, POWER, < 1000 V "Riyadh Cable" Added to Saudi Modern Company for Cable (SA)
4 B4.2 CABLE, POWER, < 1000 V "Gulf Cable - Kuwait" changed to "Gulf Cable & Electrical Industries Co KSC"
4 B4.3 CABLE, INSTRUMENTATION & CONTROL Special Considerations Added to Belden Wire & Cable
4 B4.3 CABLE, INSTRUMENTATION & CONTROL Special Considerations Added to Kerpenwerk GMBH
4 B4.3 CABLE, INSTRUMENTATION & CONTROL Okazaki Manufacturing Company Deleted
4 B4.3 CABLE, INSTRUMENTATION & CONTROL TE Wire and Cable Company Deleted
4 B4.3 CABLE, INSTRUMENTATION & CONTROL Special Consideration Added to the Okonite Company
4 B4.3 CABLE, INSTRUMENTATION & CONTROL Special Considerations Added to Northwire

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Program Supply Plan
Revision Record - Rev. 04
Moved Saudi Cable Company (SA) from B4.4 to B4.3 and combined Category B4.4 with
B4.3, since vendors are identical for both categories. Equipment Description of B4.3 now
4 B4.3 CABLE, INSTRUMENTATION, CONTROL , & THERMOCOUPLE reads "Cable, Instrumentation, Control, & Thermocouple"
4 B4.5 CABLE, COMMUNICATIONS, FIBER OPTIC Standardization Category C Added
4 B4.12 CABLE, HV (230kV) New Category Added - Vendors not yet approved
4 B5.1 CABLE TRAY, CHANNEL, ALUMINUM Cooper B-Line Deleted
4 B5.1 CABLE TRAY, CHANNEL, ALUMINUM M.P. Husky Deleted
4 B5.1 CABLE TRAY, CHANNEL, ALUMINUM Wahah Electric Supply Company of Saudi Arabia (SA) Deleted
4 B5.1 CABLE TRAY, CHANNEL, ALUMINUM Adhwa Al Rawafid Electric Industries Added
4 B5.2 CABLE TRAY, TYPE FRP M.P. Husky Deleted
4 B5.2 CABLE TRAY, TYPE FRP Abahsain-Cope Saudi Arabia Limited (SA) Added
4 B5.2 CABLE TRAY, TYPE FRP Adhwa Al Rawafid Electric Industries Added
4 B8.3 ENGINE, STANDBY DIESEL, FOR STANDBY GENERATORS Doosan Added
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW Rockwell Automation (Allen Bradley) Added
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW ABB Deleted
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW Arabia Electric Limited (SA) Deleted
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW Arabian Point Eight Power Company (SA) Deleted
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW Electrical Power Distribution Deleted
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW General Electric Deleted
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW Gulf International Electric Distribution Apparatuses Co LTD (SA) Deleted
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW Siemens Energy & Automation Deleted
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW Square D Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V ABB Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V Arabia Electric Limited (SA) Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V Arabian Point Eight Power Company (SA) Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V Electrical Power Distribution Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V Gulf International Electric Distribution Apparatuses Co LTD (SA) Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V Siemens Power Transmission & Distribution Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V Square D Deleted
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V Eaton / Cuttler Hammer Added
4 B13.2 MOTOR, FORM-WOUND IND., ABOVE 250 HP, HORIZONTAL Schorch Deleted
4 B14.2 PANELBOARD, ELECTRICAL, LOW VOLTAGE Kinney Electrical Manufacturing Company Deleted
4 B14.2 PANELBOARD, ELECTRICAL, LOW VOLTAGE Eaton (Cutler Hammer) Added
4 B14.3 PANELBOARD, FUSED, ELECTRICAL, LOW VOLTAGE New Category Added
4 B14.3 PANELBOARD, FUSED, ELECTRICAL, LOW VOLTAGE Kinney Electrical Manufacturing Company Added
4 B14.3 PANELBOARD, FUSED, ELECTRICAL, LOW VOLTAGE Eaton / Cuttler Hammer Added
4 B14.3 PANELBOARD, FUSED, ELECTRICAL, LOW VOLTAGE Cooper Bussman Added
4 B16.3 POWER SYSTEM, FUSES, < 1000 V Electromec Deleted
4 B16.3 POWER SYSTEM, FUSES, < 1000 V Changed Shawmut to Ferraz Shawmut (Mersen)
4 B16.3 POWER SYSTEM, FUSES, < 1000 V Siemens Energy & Automation Deleted
4 B16.4 POWER SYSTEM, FUSES, 1000 V AND ABOVE Electromec Deleted
4 B16.4 POWER SYSTEM, FUSES, 1000 V AND ABOVE GEC Deleted
4 B16.4 POWER SYSTEM, FUSES, 1000 V AND ABOVE Changed Shawmut to Ferraz Shawmut (Mersen)
4 B16.4 POWER SYSTEM, FUSES, 1000 V AND ABOVE Inepar Deleted
4 B18.2 GROUNDING, HARDWARE & CONNECTIONS "Use In-Kingdom Suppliers Approved by Owner" Comment Deleted
4 B22.1 MOTOR CONTROL STATION, NON CLASSIFIED, DIVISION 2, ZONE 2 "Use In-Kingdom Suppliers Approved by Owner" Comment Deleted
4 B22.1 MOTOR CONTROL STATION, NON CLASSIFIED, DIVISION 2, ZONE 2 CEAG Deleted
4 B22.1 MOTOR CONTROL STATION, NON CLASSIFIED, DIVISION 2, ZONE 2 Crouse Hinds Added
4 B22.1 MOTOR CONTROL STATION, NON CLASSIFIED, DIVISION 2, ZONE 2 Appleton Added

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Program Supply Plan
Revision Record - Rev. 04
4 B22.2 MOTOR CONTROL STATION, HAZARDOUS AREA, DIVISION 1, ZONE 1 CAEG Deleted
4 B22.2 MOTOR CONTROL STATION, HAZARDOUS AREA, DIVISION 1, ZONE 1 "Use In-Kingdom Suppliers Approved by Owner" Comment Deleted
4 B24.1 SWITCHGEAR, METAL-CLAD, LV, INDOOR Arabian Point Eight Power Company (SA) Deleted
4 B24.1 SWITCHGEAR, METAL-CLAD, LV, INDOOR Electrical Power Distribution Deleted
4 B24.1 SWITCHGEAR, METAL-CLAD, LV, INDOOR Gulf International Electric Distribution Apparatuses Co LTD (SA) Deleted
4 B24.1 SWITCHGEAR, METAL-CLAD, LV, INDOOR Siemens Energy & Automation Deleted
4 B24.1 SWITCHGEAR, METAL-CLAD, LV, INDOOR Eaton Added
4 B24.2 SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR INSULATED ABB Deleted
4 B24.2 SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR INSULATED Arabia Electric Limited (SA) Deleted
4 B24.2 SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR INSULATED Arabian Point Eight Power Company (SA) Deleted
4 B24.2 SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR INSULATED Electrical Power Distribution Deleted
4 B24.2 SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR INSULATED Gulf International Electric Distribution Apparatuses Co LTD (SA) Deleted
4 B24.2 SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR INSULATED Siemens Energy & Automation Deleted
4 B24.2 SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR INSULATED Eaton Added
4 B24.5 SWITCHGEAR, (GAS INSULATED) - 230K New Category Added - Vendors not yet approved
4 B27.1 TRANSFORMER, POWER DRY TYPE 150 KVA AND LARGER Areva Deleted
4 B27.1 TRANSFORMER, POWER DRY TYPE 150 KVA AND LARGER Square D Added
4 B27.2 TRANSFORMER, POWER, LIQUID 250 KVA - 50 MVA Saudi Transformers Company (SA) Deleted
4 B29.2 UPS SYSTEM, INDUSTRIAL, ABOVE 10 TO 200KVA Amatek Deleted
4 B30.0 & B30.1 POWER FACTOR CORRECTION CAPACITORS New Category Added - Vendors not yet approved
4 B31.0 & B31.1 ELECTRICAL POWER MANAGEMENT SYSTEM New Category Added - Vendors not yet approved
4 B32.0 & B32.1 CABLE MANAGEMENT New Category Added - Vendors not yet approved
INSTRUMENT TUBE FITTINGS, SMALL VALVES (TUBING AND THREADED
4 C2.8 ENDS) Circo Instrumentation Technologies (HOKE) Deleted
INSTRUMENT TUBE FITTINGS, SMALL VALVES (TUBING AND THREADED
4 C2.8 ENDS) Hy-Lok Deleted
4 C5.1 MONITORING VIBRATION, TRANSMITTERS -NON-CRITICAL SKF Deleted
4 C5.1 MONITORING VIBRATION, TRANSMITTERS -NON-CRITICAL GE Energ
Energyy (Bently
(Bently Nevada)
Nevada) Added
4 C6.2 PRESSURE MEASUREMENT, MANIFOLDS Hy-Lok Deleted
4 C6.2 PRESSURE MEASUREMENT, MANIFOLDS Circo Instrumentation Technologies (HOKE) Deleted
4 C6.15 FIBERGLASS FLUSH RINGS Brazosport Plastics, Inc. Added
4 C6.15 FIBERGLASS FLUSH RINGS Pfeiffer Chemie-Armatureb GmbH (a member of The Samson Group) Added
ALL CATEGORIES BELOW WERE DELETED FROM GENERAL TRANSMITTER
CATEGORY(C9.0) AND RE-CATEGORIZED FOR SPECIFIC PROCESS
FUNCTIONS (PRESSURE, LEVEL AND TEMPERATURE)
TRANSMITTER, TEMPERATURE ELECTRONIC - FIELD MOUNTED -
4 C9.1 STANDARD ACCURACY Re-categorized to C8.6
TRANSMITTER, TEMPERATURE ELECTRONIC - FIELD MOUNTED - HIGH
4 C9.2 PRECISION Re-categorized to C8.7
4 C9.3 TRANSMITTER TEMPERATURE ELECTRONIC - DIFFERENTIAL Re-categorized to C8.8
4 C9.4 TRANSMITTER, PRESSURE - PRESSURE AND DIFFERENTIAL PRESSURE Re-categorized to 6.16
4 C9.5 TRANSMITTER, FLOW - PRESSURE AND DIFFERENTIAL PRESSURE Re-categorized to 6.17
4 C9.6 TRANSMITTER, ABSOLUTE OR GAUGE - EXTRUDER MELT (PLASTICS) Re-categorized to 6.18
4 C9.7 TRANSMITTER, STANDARD P AND D/P CELL Deleted in its entirety
4 C9.8 TRANSMITTER, REMOTE OR DIRECT MOUNT SEAL SYSTEM Re-categorized to 6.19
4 C9.9 TRANSMITTER - SUBMERGE ELEMENT (POND) - LEVEL MEASUREMENT Re-categorized to 4.21
4 C9.11 TRANSMITTER, SERVO DISPLACER (CUSTODY TRANSFER / ACCOUNTING) Re-categorized to 4.22
4 C9.12 TRANSMITTER, CAPACITANCE (RADIO FREQUENCY) Re-categorized to 4.23

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Program Supply Plan
Revision Record - Rev. 04
4 C9.13 TRANSMITTER, LEVEL - RADAR Re-categorized to 4.24
4 C9.14 TRANSMITTER, FREE SPACE RADAR (CUSTODY TRANSFER/ACCOUNTING) Re-categorized to 4.25
4 C9.15 TRANSMITTER, GUIDED WAVE RADAR (TDR) (PROCESS CONTROL) Re-categorized to 4.26
4 C9.16 TRANSMITTER, INDUCTIVE / MAGNETOSTRICTIVE FLOAT Re-categorized to 4.27
4 C9.17 TRANSMITTER, ULTRASONIC Re-categorized to 4.28
4 C9.18 TRANSMITTER, NUCLEAR Re-categorized to 4.29
4 C9.19 TRANSMITTER, LIQUID LEVEL; DISPLACER Re-categorized to 4.30
4 C10.6 VALVE, CONTROL, ROTARY, BALL, CERAMIC BALL Changed Model in Special Considerations to 300CL to 300ZL
4 C11.18 FIELDBUS INDICATORS New Category Added and Vendors ABB, Rosemount, and Yokogawa Added
4 Various ALL APPLICABLE CATEGORIES Name Change from Bumwoo to BHI
4 D1.6 MIXERS, REACTION MIXERS Category Added
4 D1.6 MIXERS, REACTION MIXERS Sebewaing Tool & Engineering Added
4 D8.1 COMPRESSOR, API - 617 CENTRIFUGAL Inspection Level Changed from 4 to 3
4 D8.12 COMPRESSOR, FLOODED SCREW - PROCESS & REFRIGERATION GEA Added
4 D10.1 COOLING TOWER, WATER SPIG Added
Revised Category Description to read "Desuperheaters, Eductors, Steam Ejectors, and
4 D16.0 DESUPERHEATERS Venturis"
4 D16.1 DESUPERHEATER Tyco (Narvik Yarway) Added
4 D16.1 DESUPERHEATERS, GENERAL Revised Category Description to read "Desuperheaters"
4 D16.2 DESUPERHEATERS, EDUCTORS Revised Category Description to read "Eductors"
4 D16.3 DESUPERHEATERS, STEAM EJECTORS Revised Category Description to read "Steam Ejectors"
4 D16.4 DESUPERHEATERS, VENTURIS Revised Category Description to read "Venturis"
4 D17.1 DRYER, SKID INSTRUMENT AIR & COMPRESSED Van Air Inc Added
4 D17.1 DRYER, SKID INSTRUMENT AIR & COMPRESSED Ingersoll Rand Added
4 D23.4 FILTER, LIQUIDE SERVICE (BAG / BASKET / CARTRIDGE) Calgon Carbon Corporation Added
FLARES, COMBUSTION CONTROLS INCLUDING IGNITERS AND FLAME
4 D24.1 FRONT GENERATORS Calgon Carbon Corporation Added
4 D25.1 FURNACE, CRACKING Maritime Industrial Service Added
4 D25.2 FURNACE, TUBE SUPPORTS Faser Added
4 D25.2 FURNACE, TUBE SUPPORTS Fias Added
4 D35.1 LUBRICATION, API - 614 OIL SYSTEMS Changed Category Description to "Lubrication, Special Purpose Oil System"
PUMP, CENTRIFUGAL: API-610, OVERHUNG, SINGLE STAGE HORIZONTAL
4 D39.1 (TYPE OH) Flowserve Al Rushaid (SA) Added
PUMP, CENTRIFUGAL: API-610, SINGLE STAGE VERTICAL IN-LINE (TYPE
4 D39.4 OH3) Flowserve Al Rushaid (SA) Added
PUMP, CENTRIFUGAL: BETWEEN BEARING DOUBLE SUCTION, SINGLE
4 D39.9 STAGE CENTRIFUGAL (API-610) (TYPE BB1/BB2) Flowserve Al Rushaid (SA) Added
PUMP, CENTRIFUGAL: BETWEEN BEARING DOUBLE SUCTION
4 D39.8 CENTRIFUGAL (NON-API COOLING TOWER) Flowserve Al Rushaid (SA) Added
PUMP, CENTRIFUGAL: BETWEEN BEARING DOUBLE SUCTION
4 D39.8 CENTRIFUGAL (NON-API COOLING TOWER) ITT Saudi Company Added
PUMP, CENTRIFUGAL: BETWEEN BEARING DOUBLE SUCTION
4 D39.8 CENTRIFUGAL (NON-API COOLING TOWER) Sulzer Pumps Added
4 D39.10 PUMP, CENTRIFUGAL; MAGNETIC DRIVE; HORIZONTAL (ASME B73.3) Flowserve Al Rushaid (SA) Added
4 D39.10 PUMP, CENTRIFUGAL; MAGNETIC DRIVE; HORIZONTAL (ASME B73.3) (Goulds)
PUMP, CENTRIFUGAL: NON-API SEALED HORIZONTAL END SUCTION
4 D39.13 (ASME B73.1 AND PULP AND PAPER) Flowserve Al Rushaid (SA) Added
4 D39.14 PUMP, CENTRIFUGAL: NON-API SEALED VERTICAL INLINE; ASME B73.2 Flowserve Al Rushaid (SA) Added

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Program Supply Plan
Revision Record - Rev. 04
4 D39.16 PUMP, CENTRIFUGAL: INTEGRALLY GEARED (TYPE OH6) Removed Comment "Not Anticipated For RTIP - Sole Source" and "Nikkiso"
4 D39.25 PUMP, ROTARY POS. DISPLACEMENT - SCREW TYPE API-676 Imo Pumps Added
4 D40.4 REFRIGERATION UNIT, SAFETY SHOWER WATER SKIDS Category Added
4 D40.4 REFRIGERATION UNIT, SAFETY SHOWER WATER SKIDS HydroThrift Corporation Added
SEALS AND PACKING, MECHANICAL SEALS FOR PUMPS (LIQUID AND DRY
4 D42.1 GAS) Flowserve Abahsain (SA) Added
4 D42.2 SEALS AND PACKING, SEAL POTS Flowserve Abahsain (SA) Added
SEALS AND PACKING, MECHANICAL SEALS FOR PUMPS (LIQUID AND DRY
4 D42.1 GAS) John Crane Saudi Arabia Added
4 D42.2 SEALS AND PACKING, SEAL POTS John Crane Saudi Arabia Added
4 D45.5 TURBINE, SPECIAL PURPOSE STEAM (API - 612) GE Oil & Gas Added
WATER TREATMENT SYSTEM, SANITARY WASTEWATER MEMBRANE BIO
4 D48.11 REACTOR GE Power and Water Added
WATER TREATMENT SYSTEM, SANITARY WASTEWATER MEMBRANE BIO
4 D48.11 REACTOR Koch Membrane Added
COUPLINGS, GENERAL PURPOSE, ELASTOMERIC FLEXIBLE SLEEVE
4 D50.1 SPACER OR FLEXIBLE PIN John Crane Deleted
4 D50.2 COUPLING, GENERAL PURPOSE, METALLIC FLEXIBLE ELEMENT John Crane Deleted
4 D50.3 COUPLING, FLEXIBLE API-671 John Crane Deleted
4 D52.0 & 52.1 MAN LIFT, ARIEL WORK PLATFORM New Category Added and Genie JLG Added
4 D53.0 & 53.1 SEPARATORS, VENDOR DESIGNED CARBON STEEL New Category Added and Peerless Added
4 E1.1 VESSELS, PRES.; CS; MAX. WALL THK OF 19 MM Aguilar & Salas Added
4 E1.1 VESSELS, PRES.; CS; MAX. WALL THK OF 19 MM Maritime Industrial Service Added
4 E1.1 VESSELS, PRES.; CS; MAX. WALL THK OF 19 MM Sungjin Geotec Deleted
4 E1.2 VESSELS, PRES.; CS; WALL THK OF 38 MM Sungjin Geotec Deleted
4 E1.3 VESSELS, PRES.; CS; WALL THK FROM 38 TO 76MM Aguilar & Salas Added
4 E1.3 VESSELS, PRES.; CS; WALL THK FROM 38 TO 76MM Maritime Industrial Service Added
4 E1.3 VESSELS,, PRES.;; CS;; WALL THK FROM 38 TO 76MM gj Geotec Deleted
Sungjin
4 E1.4 VESSELS, PRES.; CS; WALL THK MORE THAN 76 MM Maritime Industrial Service Added
Al Zamil Heavy Industries Ltd.; Zamil Steel Industries Structural Steel Division; Al Saghyir
Boilers and Pressure Vessel; Geyad Factory for Pressure Vessels and Steel Buildings
Limited; Hidada Limited; Yanbu Steel Company, Saudi Arabian Fabricated Metals
4 E1.4 VESSELS, PRES.; CS; WALL THK MORE THAN 76 MM Industry Company Limited - Added
4 E1.5 VESSELS, CARBON STEEL (SMALL UP TO 24" DIAMETER) CBC Industrias Pesadas SA Deleted
4 E1.5 VESSELS, CARBON STEEL (SMALL UP TO 24" DIAMETER) Dacro Industries Deleted
4 E1.6 VESSELS, CARBON STEEL (SMALL UP TO 60" DIAMETER) Dacro Industries Deleted
4 E1.6 VESSELS, CARBON STEEL (SMALL UP TO 60" DIAMETER) Zhangjiagang Furui Boiler & Pressure Vessel Mfg. Added
4 E1.7 VESSELS, CARBON STEEL (LARGE OVER 60" DIAMETER) CBC Industrias Pesadas SA Deleted
4 E1.7 VESSELS, CARBON STEEL (LARGE OVER 60" DIAMETER) Sungjin Geotec Deleted
4 E1.7 VESSELS, CARBON STEEL (LARGE OVER 60" DIAMETER) Dacro Industries Deleted
4 E1.7 VESSELS, CARBON STEEL (LARGE OVER 60" DIAMETER) Zhangjiagang Furui Boiler & Pressure Vessel Mfg. Added
4 E1.8 VESSELS, STAINLESS STEEL Zhangjiagang Furui Boiler & Pressure Vessel Mfg. Added
4 E1.8 VESSELS, STAINLESS STEEL Sungjin Geotec Deleted
4 E1.8 VESSELS, STAINLESS STEEL Maritime Industrial Service Added
4 E1.8 VESSELS, STAINLESS STEEL CBC Industrias Pesadas SA Deleted
4 E1.8 VESSELS, STAINLESS STEEL Dacro Industries Deleted
4 E1.8 VESSELS, STAINLESS STEEL Sewon Cellontech Co. Ltd. Added
4 E1.8 VESSELS, STAINLESS STEEL Shanghai Morimatsu Pressure Vessel Co. Ltd. Added
4 E1.8 VESSELS, STAINLESS STEEL Shanghai Tonghua Added

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Program Supply Plan
Revision Record - Rev. 04
4 E1.9 VESSELS, ALLOY & CLAD (NICKEL BASED) Dacro Industries Deleted
4 E1.9 VESSELS, ALLOY & CLAD (NICKEL BASED) CBC Industrias Pesadas SA Deleted
4 E1.9 VESSELS, ALLOY & CLAD (NICKEL BASED) Maritime Industrial Service Added
4 E1.9 VESSELS, ALLOY & CLAD (NICKEL BASED) Al-Zamil Company for Heavy Steel Added
4 E1.9 VESSELS, ALLOY & CLAD (NICKEL BASED) Biffal Heavy Industries Added
4 E1.9 VESSELS, ALLOY & CLAD (NICKEL BASED) Gulf Heavy Industries Added
4 E1.10 VESSELS, TITANIUM AND SUPER ALLOY CBC Industrias Pesadas SA Deleted
4 E2.2 TANKS, SHOP; ATMOSPHERIC PRESSURE; CS & SS, (API-620 and API-650) CBC Industrias Pesadas SA Deleted
4 E2.3 TANKS, FIELD, ATMOSPHERIC PRESSURE; CS, (API-620 and API-650) CBC Industrias Pesadas SA Deleted
4 E2.4 TANKS, FIELD, ATMOSPHERIC PRESSURE; SS, (API-620 and API-650) CBC Industrias Pesadas SA Deleted
4 E2.5 TANKS, LOW TEMPERATURE; (API-620) Biffal Heavy Industries Added
4 E4.1 BLENDERS, STATIC - SILO CBC Industrias Pesadas SA Deleted
HEAT EXCHANGERS, SHELL & TUBE; CS (Small and Medium up to 60"
4 E5.1 Diameter) CBC Industrias Pesadas SA Deleted
HEAT EXCHANGERS, SHELL & TUBE; CS (Small and Medium up to 60"
4 E5.1 Diameter) Maritime Industrial Service Added
HEAT EXCHANGERS, SHELL & TUBE; CS (Small and Medium up to 60"
4 E5.1 Diameter) Sungjin Geotec Deleted
4 E5.2 HEAT EXCHANGERS, SHELL & TUBE; CS (Large over 60" Diameter) Maritime Industrial Service Added
4 E5.2 HEAT EXCHANGERS, SHELL & TUBE; CS (Large over 60" Diameter) Sungjin Geotec Deleted
4 E5.2 HEAT EXCHANGERS, SHELL & TUBE; CS (Large over 60" Diameter) CBC Industrias Pesadas SA Deleted
HEAT EXCHANGERS, SHELL & TUBE; STAINLESS AND ALLOY STEEL (Small
4 E5.3 up to 24" Diameter) CBC Industrias Pesadas SA Deleted
HEAT EXCHANGERS, SHELL & TUBE; STAINLESS AND ALLOY STEEL
4 E5.4 (Medium up to 60" Diameter) CBC Industrias Pesadas SA Deleted
HEAT EXCHANGERS, SHELL & TUBE; STAINLESS AND ALLOY STEEL
4 E5.4 (Medium up to 60" Diameter) Gulf Heavy Industries Added
HEAT EXCHANGERS,, SHELL & TUBE;; STAINLESS AND ALLOY STEEL ((Large
g
4 E5.5 over 60" Diameter) CBC Industrias Pesadas SA Deleted
HEAT EXCHANGERS, SHELL & TUBE; STAINLESS AND ALLOY STEEL (Large
4 E5.5 over 60" Diameter) Shanghai Tonghua Added
4 E5.6 HEAT EXCHANGERS, SHELL & TUBE; HIGH ALLOY CBC Industrias Pesadas SA Deleted
4 E5.8 HEAT EXCHANGERS, SURFACE CONDENSERS CBC Industrias Pesadas SA Deleted
4 E5.8 HEAT EXCHANGERS, SURFACE CONDENSERS Ilsung Added
4 E5.9 HEAT EXCHANGERS, MULTI-PIPE; DOUBLE-PIPE; HAIRPIN CBC Industrias Pesadas SA Deleted
4 E5.9 HEAT EXCHANGERS, MULTI-PIPE; DOUBLE-PIPE; HAIRPIN Sungjin Geotec Deleted
4 E5.14 HEAT EXCHANGERS, AIR COOLED Deleted Category in its entirety
4 E5.16 HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OVER 139.4 New Category Added with Purchasing Strategy B
4 E5.16 HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OVER 139.4 Jord International PTE (Malaysia Only) Added
4 E5.16 HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OVER 139.4 FMB-KNM FZCO Remained from Category E5.14
4 E5.16 HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OVER 139.4 Hudson Products Remained from Category E5.14
4 E5.16 HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OVER 139.4 GEA BTT (France and Qatar Only) Added
4 E5.16 HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OVER 139.4 Zamil Hudson (SA) Added
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW New Category Added with Purchasing Strategy B
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW Hamon D'Hondt (SA) Added

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Program Supply Plan
Revision Record - Rev. 04
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW Abahsain Specialized Industrial Co (ASIC) (SA) Added
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW GEA BTT (France and Qatar Only) Added
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW FMB-KNM FZCO Added
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW Hudson Products Added
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW Jord International PTE (Malaysia Only) Added
AIR COOLED HEAT EXCHANGERS, BARE TUBE AREA OF 139.4 SQ.M AND
4 E5.17 BELOW Zamil Hudson (SA) Added
4 E7.1 TRANSFER LINE EXCHANGERS, PRIMARY Olmi SPA Added
4 E7.2 TRANSFER LINE EXCHANGERS, SECONDARY CBC Industrias Pesadas SA Deleted
4 E8.1 REACTORS, CUSTOM CBC Industrias Pesadas SA Deleted
4 E8.1 REACTORS, CUSTOM Dacro Industries Deleted
4 E8.1 REACTORS, CUSTOM Mitternight Boiler Works Inc Deleted
4 E15.1 SPHERES, ASME Sungjin Geotec Deleted
4 E15.1 SPHERES, ASME Maritime Industrial Service Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Special Considerations Added to entire section
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS ArcelorMittal Stainless Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Butting Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS North American Stainless Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Jindal Group Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Rolled Alloys Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Taiyuan Iron and Steel Group Co Ltd (TISCO) Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Shanghai Baosteel (No. 3 Mill) Added
4 E16.1
E16 1 ALLOY APPROVED MILLS
ALLOY MILLS, AUSTENITIC & DUPLEX STAINLESS
STAINLESS STEELS Kunshan Daekyung Steel Co Ltd (KDKC)
(KDKC) Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Changshu Walsin Specialty Steel Co Ltd Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS RathGibson Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Bruck Group Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Creusot Forge Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS POSCO E&C, Korea Added
4 E16.1 ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX STAINLESS STEELS Salzgitter Mannesmann International GmbH Added
4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS Special Considerations Added to entire section
4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS ArcelorMittal Stainless Added
4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS Butting Added
4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS Rolled Alloys Added
4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS RathGibson Added
4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS Bruck Group Added
4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS G.O. Carlson Added
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) Special Considerations Added to entire section
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) Butting Added
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) Rolled Alloys Added
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) Loterios Added
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) TIMET Added
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) Listed UNITI and TICO seperately
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) Sandvik Added

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Program Supply Plan
Revision Record - Rev. 04
4 E16.3 ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA, NB, ALLOYS) ATI Alleggheny Ludlum Added
4 E16.4 EXPLOSION CLADDING MATERIAL Special Considerations Added to entire section
4 E16.4 EXPLOSION CLADDING MATERIAL SMT Shockwave Metalworking Technologies Added
4 E16.5 ROLL BONDED CLAD PLATE AND SHEET Special Considerations Added to entire section
4 E16.5 ROLL BONDED CLAD PLATE AND SHEET New Category Added
4 E16.5 ROLL BONDED CLAD PLATE AND SHEET Voestalpine Grobblech GmbH Added
4 F1.2 PIPE, CARBON STEEL - WELDED AZIZ European Pipe Company (SA) Added
4 F1.4 PIPE, STAINLESS STEEL - SEAMLESS Jubail Energy Services (JESCO) Added
4 F1.4 PIPE, STAINLESS STEEL - SEAMLESS Davis Pipe Deleted
4 F1.4 PIPE, STAINLESS STEEL - SEAMLESS Pusan Pipe Deleted
4 F3.1 PIPE SPOOL FABRICATION - METALLIC Aasia Steel Factory Co Ltd (SA). Added

Al-Rashed Fasteners and Engineering (SA), Al-Rashid Fasteners and Engineering (SA),
Arabian Fasteners and Engineering (SA), and Saudi BEA Fasteners Manufacturing (SA)
4 H8.1 FASTENERS Added
4 H8.2 FLUROPOLYMER COATED FASTENERS New Category Added
Al-Rashed Fasteners and Engineering (SA), Al-Rashid Fasteners and Engineering (SA),
Arabian Fasteners and Engineering (SA), BEA SRL, Lone Star Fasteners LP, OME,
4 H8.2 FLUROPOLYMER COATED FASTENERS Takenaka Seisakusho Co Ltd, Triplefast Middle East Ltd Added
4 H16.0 & H16.1 PIPELINE SCRAPER TRAPS TO ASME B3.4/B31.B (Inlet Area Only) New Category Added
4 H16.1 PIPELINE SCRAPER TRAPS TO ASME B3.4/B31.B (Inlet Area Only) Glapwell Contracting Services, FAI Carvico, and Pipeline Engineering Services Added
4 H17.0 & H17.1 DISMANTLING JOINTS New Category Added
4 H17.1 DISMANTLING JOINTS Klamex Pipe Couplings and Viking Johnson Added
4 I1.3 PIPING VALVES, BUTTERFLY Saudi Valve Manufacturing Co Ltd Deleted
4 I1.4 PIPING VALVES, CHECK Saudi Valve Manufacturing Co Ltd Deleted
4 I1.7 PIPING VALVES, GATE Saudi Valve Manufacturing Co Ltd Deleted
4 I1.8 PIPING VALVES, GLOBE Saudi Valve Manufacturing Co Ltd Deleted
4 I1.12 PIPING VALVES, PLUG Fluroseal Added
4 J6.1 POST INDICATING VALVES American Flow Control Added
4 J9.0 FIRE PROTECTION SYSTEMS INTEGRATOR New Category Added
REDA Fire, Saudi Factory for Fire Equipment, Tyco Fire & Integrated Solutions, and
4 J9.1 FIRE PROTECTION SYSTEMS INTEGRATOR Williams Fire & Hazard Control Added
4 K1.1 STRUCTURE, STEEL Aasia Steel Factory Co Ltd.(SA) Added

Date: 29 July 2011


Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Analytical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE E= Suffix US$ Strategy Level Level Weight Volume Date Date Date Time (weeks) Time (weeks)
Requirements
Equipment
ELECTROCHEMICAL MEASUREMENT: Ph,
2 A 1.0 CONDUCTIVITY, OXIDATION REDUCTION POTENTIAL
(ORP)
Standardization -
2 A1.1 ANALYZER, LOWER EXPLOSIVE LIMIT (LEL) - PORTABLE B DRAEGERWERK AG 1 0
Category B
INDUSTRIAL SCIENTIFIC CORP
A1.1
(MSA)
Standardization -
2 A1.2 ANALYZER, LOWER EXPLOSIVE LIMIT (LEL) - FIXED B DRAEGERWERK AG 1 0
Category B
A1.2 GENERAL MONITORS
Standardization -
2 A1.3 ANALYZER, CONDUCTIVITY B ENDRESS+HAUSER 1 0
Category B
EMERSON PROCESS
A1.3 MANAGEMENT (ROSEMOUNT
ANALYTICAL)
YOKOGAWA CORPORATION
A1.3
OF AMERICA
YOKOGAWA CORPORATION
2 A1.4 ANALYZER, OXIDATION REDUCTION POTENTIAL (ORP) B 1 0
OF AMERICA
Standardization -
2 A1.5 ANALYZER, pH ELECTRODES - CL2 APPLICATIONS B METTLER - TOLEDO (INGOLD) 1 0
Category B
EMERSON PROCESS
Standardization -
2 A1.6 ANALYZER,, pH
p ELECTRODES - ALL OTHER APPLICATIONS B MANAGEMENT
G ((ROSEMOUNT
OS OU 1 0
Category B
ANALYTICAL)
A1.6 ENDRESS+HAUSER
YOKOGAWA ELECTRIC
A1.6
CORPORATION
EMERSON PROCESS
Standardization -
2 A1.7 ANALYZER, pH TRANSMITTERS B MANAGEMENT (ROSEMOUNT 1 0
Category B
ANALYTICAL)
A1.7 ENDRESS+HAUSER
YOKOGAWA ELECTRIC
A1.7
CORPORATION
2 A1.8 ANALYZER, SPECIFIC ION - ELECTRODES B METTLER - TOLEDO (INGOLD) 1 0
A1.8 THERMO SCIENTIFIC (ORION)
YOKOGAWA CORPORATION
A1.8
OF AMERICA

2 A1.9 ANALYZER, SPECIFIC ION - TRANSMITTERS B METTLER - TOLEDO (INGOLD) 1 0

A1.9 THERMO SCIENTIFIC (ORION)


YOKOGAWA CORPORATION
A1.9
OF AMERICA
ANALYZER, PHOTO-IONIZATION DETECTOR (PID) -
2 A1.10 B PHOTOVAC 1 0
PORTABLE
A1.10 PID ANALYZERS (HNU)
2 A1.11 ANALYZER, TAPE TYPE B GASTRONICS (GMD 1 0
A1.11 HONEYWELL
Standardization -
ANALYZER, TOTAL ORGANIC CARBON (TOC) - ONLY FOR Category A,
BIOTECTOR ANALYTICAL
4 A1.12 PROCESS WATER CONDENSATE STREAMS WITHOUT E Biotector is the 1 0
SYSTEMS LTD.
PARTICLES (CLEAN STREAM) selected PLA
Vendor
Standardization -
ANALYZER, TOTAL ORGANIC CARBON (TOC) - ALL
ANALYZER
Category A,
APPLICATIONS EXCEPT FOR CLEAN PROCESS WATER BIOTECTOR ANALYTICAL
4 A1.13 E Biotector is the 1 0
CONDENSATE AND WATER WITH MONOMERS (DIRTY SYSTEMS LTD.
selected PLA
STREAM)
Vendor
A1.14 ANALYZER, BIOLOGICAL OXYGEN DEMAND (BOD) 1 1
A1.15 ANALYZER, CHEMICAL OXYGEN DEMAND (COD) B 1 1

2 A1.16 ANALYZER, TOTAL HYDROCARBON (THC) B ABB INC 1 0

ANLYZER, TOTOAL HYDROCARBON (THC) - TUEV


A1.17 B SICK MAIHAK
APPROVED
ANALYZER, NITROGEN OXIDES (NOX) -
2 A1.18 B 1 0
CHEMILUMINESCENCE
Standardization -
2 A1.19 ANALYZER, TOXIC DETECTORS (ALL) B DRAEGERWERK AG (FIXED) 1 0
Category B
A1.19 GENERAL MONITORS
A1.20 ANALYZER, TITRATOR - WET CHEMISTRY B APPLIKON 1 1

A1.21 ANALYZER, AMMONIA OR PHOSPHATE IN WASTE WATER APPLIKON 1 1

2 A2.0 CHROMATOGRAPH
Standardization -
Category A,
SIEMENS ENERGY &
4 A2.1 ANALYZER, GAS CHROMATOGRAPHY (GC) - GENERAL E Siemens is the 1 1
AUTOMATION
selected PLA
Vendor
A2.2 ANALYZER, GAS CHROMATOGRAPHY (GC) - MICRO E 1 1
A2.3 ANALYZER, ION CHROMATOGRAPHY E DIONEX 1 1
A2.4 ANALYZER, SUPER CRITICAL FLUID CHROMATOGRAPHY E ABB INC 1 1
THERMO SCIENTIFIC ((FLUID
2 A2.5
A2 5 ANALYZER,
ANALYZER HYDROCARBON SPILL DETECTOR E 1 0
DATA)
2 A3.0 MOISTURE, HUMIDITY, DEWPOINT
GE SENSING (GENERAL
2 A3.1 ANALYZER, ELECTRONIC / CHEMICAL - ALUMINUM OXIDE B 1 0
EASTERN)

A3.1 GE SENSING (PANAMETRICS)

ANALYZER, ELECTRONIC / CHEMICAL - P250 - FIXED AND DUMAT ANALYTICAL


2 A3.2 B 1 0
PORTABLE ENGINEERING GMBH
A3.2 MEECO
ANALYZER, ELECTRONIC / CHEMICAL - PHYSICAL - OSC. Standardization -
2 A3.3 B AMETEK 1 0
CRYSTAL Category B
ANALYZER, ELECTRONIC / CHEMICAL - PHYSICAL - CHILLED
2 A3.4 B 1 0
MIRROR
OPTICAL: INFRARED, ULTRA-VIOLET,
2 A4.0 SPECTROSCOPIC, REFRACTOMETER, PHOTOCELL, X-
RAY, TDL
2 A4.1 ANALYZER, CHEMICAL FLUORESCENCE B 1 0

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Analytical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Analytical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE E= Suffix US$ Strategy Level Level Weight Volume Date Date Date Time (weeks) Time (weeks)
Requirements
Equipment
2 A4.2 ANALYZER, SPECTROSCOPY OPTICAL FIBER B OFS 1 0
2 A4.3 ANALYZER, COLORIMETER, EXTRACTIVE SAMPLE B ENDRESS+HAUSER 1 0
A4.3 SIGRIST - PHOTOMETER AG
ANALYZER, FOURIER TRANSFORM INFRARED (FTIR) / Standardization -
3 A4.4 B ABB INC 1 2
FOURIER TRANSFORM NEAR INFRARED (FTNIR) Category B
HAMILTON SUNDSTRAND
A4.4 (APPLIED INSTRUMENT
TECHNOLOGIES
ANALYZER, FILTER PHOTOMETER - INFRARED (IR) / NEAR Standardization -
3 A4.5 B ABB INC 1 1
INFRARED (NIR) Category B
A4.5 SERVOMEX
A4.6 ANALYZER, INFRARED (IR) - LUFT DETECTOR B ABB INC 1 1
SIEMENS ENERGY &
A4.6
AUTOMATION
A4.7 ANALYZER, INFRARED (IR) - GAS CORRELATION B SERVOMEX 1 1
ANALYZER, ULTRA-VIOLET (UV) / VISIBLE - SINGLE
A4.8 B ABB INC 1 1
COMPONENT, FILTER, EXTRACTIVE SAMPLE
A4.8 SERVOMEX
ANALYZER, ULTRA-VIOLET (UV) / VISIBLE - SINGLE
GALVANIC APPLIED
A4.9 COMPONENT, FILTER, IN-LINE MEASUREMENT (INCLUDING B 1 1
SCIENCES (MONITEK)
COLORIMETERS)
A4.9 OPTEK
A4.10 ANALYZER - ULTRA-VIOLET (UV) - DIODE ARRAY B 1 1
Standardization -
Category A,
YOKOGAWA CORPORATION
4 A4.11 ANALYZER, TUNED DIODE LASER (TDL) B Yokogawa is the 1 1
OF AMERICA
selected PLA
Vendor
Standardization -
Category A,
ANALYZER, INTEGRATED CAVITY OUTPUT SPECTROMETER YOKOGAWA CORPORATION
4 A4.12 B Yokogawa is the
(ICOS) OF AMERICA
selected PLA
Vendor
GUIDED WAVE
ANALYZER, FILTER PHOTOMETER - INFRARED (IR) / NEAR Standardization -
3 A4.13 (APPLICATIONS USING FIBER
INFRARED (NIR), MULTIWAVE Category B
OPTIC PROBES ONLY)
2 A5.0 OXYGEN (O2)
EMERSON PROCESS
2 A5.1 ANALYZER, DISSOLVED OXYGEN (O2) - FIXED B MANAGEMENT (ROSEMOUNT 1 0
ANALYTICAL)
A5.1 METTLER-TOLEDO (IN-GOLD)
ANALYZER, DISSOLVED OXYGEN (02) - EFFLUENT/WASTE
2 A5.2 B HACH COMPANY 1 0
WATER APPLICATIONS
ANALYZER, OXYGEN (O2) FUEL CELL - INCLUDES
2 A5.3 B DELTA F 1 0
PORTABLES
TELEDYNE ANALYTICAL
A5.3
INSTRUMENTS
ANALYZER, OXYGEN (O2) DEFICIENCY - ENCLOSED AREA Standardization -
2 A5.4 B DRAEGERWERK AG 1 0
MONITORS Category B
SIEMENS ENERGY &
2 A5.5 ANALYZER, OXYGEN (O2) - PARAMAGNETIC B 1 0
AUTOMATION
ANALYZER, OXYGEN (O2) - POLARAGRAPHIC/ELECTRO- EMERSON PROCESS
2 A5.6 B 1 0
CHEMICAL MANAGEMENT
A5.6 TELEDYNE
Standardization -
2 A5.7 ANALYZER, ZIRCONIA OXIDE (ZR O2) B AMETEK 1 0
Category B
EMERSON PROCESS
A5.7 MANAGEMENT (ROSEMOUNT
ANALYTICAL)
A5.7 SERVOMEX
2 A6.0 CONTINUOUS EMISSION MONITORS (CEMs)
Standardization -
ANALYZER, CEMs - EXTRACTIVE SYSTEMS - CO/O2/NOX - Category A, ABB
4 A6.1 B ABB INC 1 2
COLD/DRY SAMPLE is the selected
PLA Vendor
ANALYZER, CEMs - EXTRACTIVE SYSTEMS - CO/O2/NOX -
A6.2 B 1 1
HOT/WET SAMPLE
2 A7.0 PHYSICAL PROPERTIES
2 A7.1 ANALYZER, CALORIMETER (BTU OR WOBBE INDEX) B 1 0
OPTICAL CONTROL SYSTEMS
2 A7.2 ANALYZER, CAST FILM B 1 2
(OCS)
EMERSON PROCESS
2 A7.3 ANALYZER, OPACITY - EXTRACTIVE B MANAGEMENT (ROSEMOUNT 1 0
ANALYTICAL)
A7.3 ENDRESS+HAUSER
A7.3 SIGRIST - PHOTOMETER AG
2 A7.4 ANALYZER, OPACITY - IN LINE/STACK B DURAG GMBH 1 0
A7.4 SICK MAIHAK
2 A7.5
A7 5 ANALYZER,
ANALYZER PARTICLE SIZE B 1 0

2 A7.6 ANALYZER, REFRACTOMETER (IN LINE & DIFFERENTIAL) B 1 0


MESA LABORATORIES
2 A7.7 ANALYZER, SONIC VELOCITY B 1 0
(NUSONICS DIVISION)
ANALYZER, TURBIDITY (TOTAL SUSPENDED SOLIDS) - NON- GALVANIC APPLIED
2 A7.8 B 1 0
WASTE WATER APPLICATIONS SCIENCES (MONITEK)
A7.8 OPTEK
ANALYZER, TURBIDITY (TOTAL SUSPENDED SOLIDS) -
2 A7.9 B ENDRESS+HAUSER 1 0
WASTE WATER APPLICATIONS
A7.9 HACH
2 A7.10 ANALYZER, SLUDGE LEVEL MONITORING B ENDRESS+HAUSER 1 0

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Analytical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Analytical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE E= Suffix US$ Strategy Level Level Weight Volume Date Date Date Time (weeks) Time (weeks)
Requirements
Equipment
2 A7.11 ANALYZER, THERMAL CONDUCTIVITY B ABB INC 1 0
A7.11 LFE
TELEDYNE ANALYTICAL
A7.11
INSTRUMENTS
2 A7.12 ANALYZER, RHEOMETER B THERMO SCIENTIFIC 1 2
2 A7.13 ANALYZER, VAPOR PRESSURE B 1 0
2 A7.14 ANALYZER, DUST B DURAG GMBH 1 0
A7.14 SIGRIST - PHOTMETER AG

2 A7.15 ANALYZER, FLAME IONISATION DETECTORS (FIDs) B 1 0

2 A7.16 ANALYZER, VISCOSITY - VIBRATION METHOD B HYDRAMOTION 1 0


2 A7.17 ANALYZER, VISCOSITY - ROTATING CUP METHOD B 1 0
2 A8.0 AUXILIARY SYSTEMS
Standardization -
2 A8.1 ANALYZER, DATA ACQUISITION - CLASSIFIED AREAS B DAISY DATA 1 0
Category B
SHI (PANASONIC Standardization -
2 A8.2 ANALYZER, DATA ACQUISITION - NON-CLASSIFIED AREAS B 1 0
TOUGHBOOK) Category B
HEADLINE FILTERS
2 A8.3 ANALYZER, SAMPLE SYSTEMS - FILTERS (GAS) B 1 0
(PROCESS ANAYLYTICAL)
M&C PRODUCTS
A8.3
ANALYSENTECHNIK GMBH
A8.3 PARKER HANNIFIN (BALSTON)
ANALYZER, SAMPLE SYSTEMS - FILTERS (LIQUID/GAS
2 A8.4 B A+ CORPORATION (GENIE) 1 0
SEPARATION)
A8.4 PERMA PURE PRODUCTS
2 A8.5 ANALYZER, SAMPLE SYSTEMS - FILTERS (LIQUID) B A+ CORPORATION 1 0
M&C PRODUCTS
A8.5
ANALYSENTECHNIK GMBH
ANALYZER, SAMPLE SYSTEMS - PRESSURE REGULATORS
2 A8.6 B BOC 1 0
(CYLINDERS)
A8.6 DRUVA
A8.6 MATHESON/TESCOM
A8.6 PARKER (VERIFLO)
A8.6 PRAXAIR
A8.6 SCOTT
ANALYZER, SAMPLE SYSTEMS - PRESSURE REGULATORS
2 A8.7 B DRUVA 1 0
(CARRIER GAS)
EMERSON PROCESS
A8.7 MANAGEMENT (BROOKS
PROCESS ANALYTICAL)
A8.7 PORTER INSTRUMENT
A8.7 PRAXAIR
ANALYZER, SAMPLE SYSTEMS - PRESSURE REGULATORS
2 A8.8 B DRUVA 1 0
(PROCESS)
A8.8 PARKER HANNIFAN (VERIFLO)
EMERSON PROCESS
A8.8
MANAGEMENT (TESCOM)
2 A8.9 ANALYZER,, SAMPLE SYSTEMS - ROTOMETERS (ALL)
( ) B 1 0

2 A8.10 ANALYZER, SAMPLE SYSTEMS - ENCLOSURE HEATERS B INTERTEC 1 0


A8.10 O'BRIEN
ANALYZER, SAMPLE SYSTEMS - SAMPLE COOLERS (AIR
2 A8.11 B EXAIR 1 0
OPERATED)
ITW AIR MANAGEMENT
A8.11
VORTEC
ANALYZER, SAMPLE SYSTEMS - SAMPLE COOLERS (SOLID M&C PRODUCTS
2 A8.12 B 1 0
STATE) ANALYSENTECHNIK GMBH
A8.12 PERMA PURE (BALDWIN)
A8.12 UNIVERSAL ANALYZERS
ANALYZER, SAMPLE SYSTEMS - SAMPLE COOLERS-
2 A8.13 B LYTRON 1 0
REFRIG, LIQUID SAMPLE
ANALYZER, SAMPLE SYSTEMS - SAMPLE COOLERS- HEAT
2 A8.14 B ALFA LAVAL 1 0
EXCHANGERS
A8.14 SENTRY
ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION
4 A8.15 B SWAGELOK 1 0
VALVES (BELLOWS)
ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION
4 A8.16 B SWAGELOK 1 0
VALVES (BALL)
ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION EM - TECHNIK GMBH
2 A8.17 B 1 0
VALVES, DIAPHRAGM, NON - METALLIC ARMATURENBAU
SAINT-GOBAIN
A8.17 PERFORMANCE PLASTICS
MICROELECTRONICS
(FURON)
A8.17 ENTEGRIS
ANALYZER, SAMPLE SYSTEMS - STREAM SELECT,
2 A8.18 B PARKER HANNIFAN (VERIFLO) 1 0
DIAPHRAGM, METALLIC
A8.18 SWAGELOK

ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION


4 A8.19 B SWAGELOK 1 0
VALVES (O-RING)

ANALYZER, SAMPLE SYSTEMS - MULTIPLE STREAM


A8.20 B PARKER HANNIFAN 1 0
SELECTION VALVE SWITCHING ASSEMBLY
A8.20 SWAGELOK

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Analytical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Analytical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE E= Suffix US$ Strategy Level Level Weight Volume Date Date Date Time (weeks) Time (weeks)
Requirements
Equipment
ANALYZER, SAMPLE SYSTEMS - STREAM SELECTION
2 A8.21 B ASCO 1 0
VALVES, SOLENOID
A8.21 BURKERT
PARKER HANNIFIN
A8.21 CORPORATION (FLUID
CONTROL DIVISION)
ANALYZER, PROCESS ANALYTICAL ENGINEERING
2 A8.22 B ABB INC 1 3
CONTRACTOR (PAEC)
SIEMENS ENERGY &
A8.22
AUTOMATION
YOKOGAWA CORPORATION
A8.22
OF AMERICA
ANALYZER, SAMPLE SYSTEMS - ANALYZER SYSTEM
2 A8.23 B ABB INC (SHANGHIA) 1 3
PACKAGER (INTEGRATION)
COMPUTER SYSTEM Must have Sample
PROTECTION CHAMBERS Systems Fabrication by
4 A8.23 AND ITEGRATED 1 3
an external source
COMMUNICATIONS CO LTD acceptable to RTIP
(CPIC) (SA)
A8.23 SIEMENS AG (KARLSRUHE)
SIEMENS PROCESS
A8.23
ANALYTICS (SHANGHAI)
SIEMENS PTE LTD - PASI
A8 23
A8.23
(SINGAPORE)
SIEMENS ENERGY &
A8.23
AUTOMATION (HOUSTON)
YOKOGAWA CORPORATION
A8.23
OF AMERICA
See Analyzer - sample systems -
ANALYZER, SAMPLE SYSTEMS - ANALYZER SYSTEM
2 A8.24 B analyzer system packager 1 3
FABRICATOR
(Integration)
A8.24
See Analyzer - sample systems -
2 A8.25 ANALYZER, SAMPLE SYSTEMS - ENCLOSURES B analyzer system packager 1 0
(Integration)
2 A8.26 ANALYZER, SAMPLE SYSTEMS - PUMPS (LIQUIDS - PISTON) B FLUID METERING INC (FMI) 1 0

ANALYZER, SAMPLE SYSTEMS - PUMPS (LIQUIDS -


2 A8.27 B ISMATEC SA 1 0
PERISTALTIC)
A8.27 MASTERFLEX
A8.27 WATSON-MARLOW BREDEL
2 A8.28 ANALYZER, SAMPLE SYSTEMS - PUMPS (GASES) B AIR DIMENSIONS INC (ACI) 1 0
A8.28 KNF NEUBERGER
M&C PRODUCTS
A8.28
ANALYSENTECHNIK GMBH
ANALYZER, SAMPLE SYSTEMS - PUMPS (HIGH
2 A8.29 B BUEHLER TECHNOLOGIES 1 0
TEMPERATURE, >150 DEG C)
A8.29 KNF NEUBERGER
M&C PRODUCTS
A8.29
ANALYSENTECHNIK GMBH
ANALYZER, SAMPLE SYSTEMS - PUMP, LIQUID, SUNDYNE CORPORATION
2 A8.30 B 1 0
MAGNETICALLY COUPLED (CASTER)
ANALYZER, SAMPLE SYSTEMS - VACUUM PUMPS, ALCATEL VACUUM
2 A8.31 B 1 0
ROUGHING PRODUCTS
A8.31 EDWARDS
2 A8.32 ANALYZER, SAMPLE SYSTEMS - VACUUM PUMPS, TURBO B EDWARDS 1 0

PFEIFFER VACUUM GMBH


A8.32
(BALZERS)
ANALYZER, SAMPLE SYSTEMS - VACUUM PUMPS, HIGH GARDNER DENVER (ELMO
2 A8.33 B 1 0
FLOW, NON - CORROSIVE REITCHER)
ANALYZER, SAMPLE SYSTEMS - VACUUM PUMPS, MEDIUM
2 A8.34 B METAL BELLOWS 1 0
FLOW, NON - CORROSIVE
ANALYZER, SAMPLE SYSTEMS - VACUUM PUMPS, HIGH
2 A8.35 B AIR DIMENSIONS 1 0
TEMP, CORROSIVE
BRONKHORST HIGH-TECH
2 A8.36 ANALYZER, SAMPLE SYSTEMS - FLOW CONTROLLERS B 1 0
B.V.
EMERSON PROCESS
A8.36 MANAGEMENT (BROOKS
PROCESS ANALYTICAL)
ANALYZER, SAMPLE SYSTEMS - FLOW CONTROLLERS BRONKHORST HIGH-TECH
2 A8.37 B 1 0
(THERMAL) B.V. (PROCESS ANALYTICAL)
EMERSON (BROOKS
A8.37
PROCESS ANALYTICAL)
Standardization -
Category A,
4 A8.38 ANALYZER, SAMPLE SYSTEMS - TUBING FITTINGS B SWAGELOK Swagelok is the 1 0
selected PLA
Vendor
ANALYZER, SAMPLE SYSTEMS - HEAT TRACED, PRE-
Standardization -
4 A8.39 INSULATED AND/OR JACKETED TUBING OR TUBING B O'BRIEN 1 0
Category B
BUNDLES
A8.39 THERMON
SIEMENS ENERGY & Standardization -
2 A8.40 ANALYZER, PAMC MONITOR SYSTEM B 1 0
AUTOMATION (AWC) Category D
ANALYZER, SAMPLE SYSTEMS - PUMPS (LIQUID - PROMINENT FLUID
2 A8.41 1 0
DIAPHRAM) CONTROLS
A8.41 PULSAFEEDERS
ANALYZER, SAMPLE SYSTEMS - FILTER (WASTEWATER -
2 A8.42 HACH ENVIRONMENTAL 1 0
BLOWBACK)
4 A8.43 ANALYZER, PROCESS SAMPLING BIAR, INC 1 0
4 A8.43 PHOENIX PRECISION
2 A9.0 BOILING RANGE AND FREEZING POINT
2 A9.1 ANALYZER, FLASH POINT B 1 0
2 A9.2 ANALYZER, BOILING POINT B ABB INC 1 0

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Analytical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Electrical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Field Need Date
CODE Suffix US$ Strategy Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
E= Equipment Requirements

2 B 1.0 BATTERIES & CHARGERS


Standardization - AEG Power Solutions is
Category A, AEG the PLA Vendor and
4 B1.1 BATTERY, CHARGERS B AEG POWER SOLUTIONS Power Solutions is 1 0 single point of contact for
the selected PLA chargers, batteries, and
Vendor UPS Systems.
AMETEK SOLIDSTATE
B1.1
CONTROLS
2 B1.1 C&D TECHNOLOGIES
2 B1.1 ENERSYS
2 B1.1 HINDEL
B1.1 SAFT POWER SYSTEMS
Standardization - AEG Power Solutions is
Category A, AEG the PLA Vendor and
BATTERY, FLOODED ELECTROLYTE STA. STORAGE
4 B1.2 B AEG POWER SOLUTIONS Power Solutions is 1 0 single point of contact for
BATTERY
the selected PLA chargers, batteries, and
Vendor UPS Systems.
2 B1.2 C & D TECHNOLOGIES
2 B1.2 ENERSYS
HOPPECKE BATTERIEN GMBH
B1.2
& CO. KG
2 B1.3 O USED
NOT S
2 B1.4 NOT USED
4 B2.0 NOT USED
4 B2.1 NOT USED 2 N/A

2 B3.0 LARGE DC SYSTEMS (FOR CHLORINE UNIT ONLY)


Standardization -
B3.1 LARGE DC SYSTEM, RECTIFIERS E FUJI ELECTRIC 2 2
Category E
B3.2 LARGE DC SYSTEM, RECTIFIERS - POLARIZATION E NOT A TECHNOLOGY DRIVEN SINGLE SOURCE RAPID POWER 2 2

Standardization -
B3.3 LARGE DC SYSTEM, BUS BAR - INSULATORS B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE INTREPID INDUSTRIES 1 2
Category D
LARGE DC SYTEM, BUS BAR - DESIGN, FABRICATION & AMEC SPIE ZUIDWEST
2 B3.4 E 2 2
TURNKEY INSTALLATION (ELECTRON)
B3.4 FLOHE GMBH
B3.4 VISION ELECTRIC
B3.4 W.D. WHINERY
AMEC SPIE ZUIDWEST
3 B3.5 LARGE DC SYTEM, DC BUSSES - FLEXES (COPPER) B 1 2
(ELECTRON)
B3.5 FLOHE GMBH
B3.5 VISION ELECTRIC
B3.5 WATEREDGE
LARGE DC SYSTEM, BUSSES - TRANSITIONS - EXPLOSION DYNAMIC MATERIAL
3 B3.6 B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE 1 2
BONDED ALUMINUM TO COPPER CORPORATION
LARGE DC SYSTEM, BUSSES - ALUMINUM FLEXES & AMEC SPIE ZUIDWEST
3 B3.7 1 2
SPLICE PLATES (ELECTRON)
B3.7 FLOHE GMBH
B3.7 Q GROUP
B3.7 VISION ELECTRIC
B3.7 W.D. WHINERY
3 B3.8 LARGE DC SYSTEM, SWITCHES B FERRAZ 1 2
B3.8 RITTER
3 B3.9 LARGE DC SYSTEM, METERING E ABB INC 2 2

B3.9 DYNAMP LLC (HALMAR/LEM)

2 B4.0 CABLE & ACCESSORIES


Technically acceptable
for Medium Voltage Multi-
Core cables per RT7D-
0447-00.
Technically Acceptable
for Medium Voltage
Single Core cables per
RT7D-0450-00 with the
following voltage ratings:
U0/U (Um) = 6/10 (12)
GULF CABLE & ELECTRICAL kV
4 B4.1 CABLE, POWER, 1KV THROUGH 35 KV B 1 1
INDUSTRIES CO KSC U0/U (Um) = 8.7/15
(17.5) kV
NOT technically
acceptable for Medium
Voltage Single Core
cables per RT7D-0450-
00 with the following
voltage ratings:
U0/U (Um) = 26/45 (52)
kV
U0/U (Um) = 20/35 (40)
4 B4.1 ( )
SAUDI CABLE COMPANY (SA)
SAUDI MODERN COMPANY
4 B4.1
FOR CABLE (RIYADH CABLE)
GULF CABLE & ELECTRICAL
4 B4.2 CABLE, POWER, < 1000 V B 1 1
INDUSTRIES CO KSC
B4.2 SAUDI CABLE COMPANY (SA)

SAUDI MODERN COMPANY


4 B4.2 FOR CABLE (RIYADH CABLE)
(SA)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Electrical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Electrical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Field Need Date
CODE Suffix US$ Strategy Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
E= Equipment Requirements

Technically acceptable
ONLY for the following
RTIP instrumentation
cable:
specification RT7D-0461-
02 (ITC)
4 B4.3 CABLE, INSTRUMENTATION, CONTROL , & THERMOCOUPLE B BELDEN WIRE & CABLE 1 1
specification RT7D-0461-
04 (non-jacketed)
specification RT7D-0462-
01 (ITC)
specification RT7D-0468-
01 (TC)
B4.3 DEKORON WIRE AND CABLE

Technically acceptable
for instrumentation cable
EXCEPT for the
following RTIP
instrumentation cable:
4 B4.3 KERPENWERK GMBH specification RT7D-0461-
01 (ITC-ER)
specification RT7D-0461-
06 (Fieldbus ITC ER)
ITC-ER)
specification RT7D-0463-
01 (ITC-ER)

Technically acceptable
ONLY for the following
MIDDLE EAST SPECIALIZED RTIP instrumentation
4 B4.3
CABLES COMPANY (SA) cable (one type):
specification RT7D-0468-
01 (TC)
Technically acceptable
for instrumentation cable
EXCEPT for the
following RTIP
instrumentation cable:
4 B4.3 NORTHWIRE specification RT7D-0466-
01 (single pair
thermocouple extension)
specification RT7D-0466-
02 (multi-pair
thermocouple extension)
Technically acceptable
for instrumentation cable
EXCEPT for the
following RTIP
instrumentation cable:
4 B4.3 THE OKONITE COMPANY specification RT7D-0461-
01 (ITC-ER)
specification RT7D-0461-
06 (Fieldbus ITC-ER)
specification RT7D-0463-
01 (ITC-ER)

Technically acceptable
for instrumentation cable
EXCEPT for the
following RTIP
instrumentation cable:
4 B4.3 SAUDI CABLE COMPANY (SA) specification RT7D-0461-
01 (ITC-ER)
specification RT7D-0461-
06 (Fieldbus ITC-ER)
specification RT7D-0463-
01 (ITC-ER)

4 B4.4 COMBINED WITH B4.3 B 1 1


Standardization -
4 B4.5 CABLE, COMMUNICATIONS, FIBER OPTIC B CORNING CABLE SYSTEMS 1 1
Category C
B4.5 DRAKA COMTEQ
MIDDLE EAST FIBER CABLE
B4.5
(SA)
OMAN FIBER OPTIC COMPANY
B4.5
(SA)
B4.5 SAUDI CABLE COMPANY (SA)
SAUDI MODERN COMPANY
B4.5
FOR CABLE (SA)
CABLE, ELECTRICAL, CATHODIC PROTECTION TURNKEY CATHODIC PROTECTION Standardization -
3 B4.6 E 1 1
SYSTEMS COMPANY Category C
CORRPRO ARABIA GROUND
B4.6
(SA)

B4.6 THREE LIONS FACTORY (SA)


3 B4.7 NOT USED B
Standardization -
3 B4.8 CABLE, GLANDS B CEAG 0 0
Category C
B4.8 CROUSE-HINDS
B4.8 HAWKE
B4.8 HUMMEL
THOMAS & BETTS (T&B
B4.8
CONDUIT FITTINGS)
Standardization -
3 B4.9 CABLE, LUGS & SPLICING SLEEVES B FCI BURNDY 0 0
Category C
B4.9 KLAUKE
B4.9 PFISTERER
B4.9 THOMAS & BETTS
B4.9 TYCO (RAYCHEM)
Standardization -
3 B4.10 CABLE, TERMINATIONS & SPLICES B 3M 0 0
Category C
PRYSMIAN CABLES &
B4.10
SYSTEMS SRL

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Electrical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Electrical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Field Need Date
CODE Suffix US$ Strategy Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
E= Equipment Requirements

SIEMENS ENERGY &


B4.10
AUTOMATION
B4.10 TYCO (RAYCHEM)
EGS ELECTRICAL GROUP Standardization -
3 B4.11 CABLE, FIRE BARRIER B 0 0
(NELSON FIRESTOP) Category B
B4.11 ROXTEC (FRAME & BLOCKS)

4 B4.12 CABLE, HV (230kV) B

2.0 B5.0 CABLE TRAY


Standardization -
Category A,
ABAHSAIN-COPE SAUDI
4 B5.1 CABLE TRAY, CHANNEL, ALUMINUM B Abahsain-Cope is 1 2 1
ARABIA LIMITED (SA)
of 2 selected PLA
Vendors
ADHWA AL RAWAFID
4 B5.1
ELECTRIC INDUSTRIES
ALLIED TUBE & CONDUIT (T. J.
COPE)
Standardization -
Category A, Saudi
SAUDI ELECTRIC INDUSTRIES
4 B5.1 Electric is 1 of 2
COMPANY (SA)
selected PLA
Vendors

ALLIED TUBE & CONDUIT (T. J. Standardization -


4 B5.2 CABLE TRAY, TYPE FRP B 2 1
COPE) Category A

ABAHSAIN-COPE SAUDI
4 B5.2
ARABIA LIMITED (SA)
ADHWA AL RAWAFID
4 B5.2
ELECTRIC INDUSTRIES
Standardization -
ENDURO SYSTEMS Category A, Enduro
4 B5.2
INCORPORATED (ESI) is the selected PLA
Vendor

CIRCUIT BREAKERS (SEE SWITCHGEAR SEE SWITCHGEAR


B6.0
CATEGORIES FOR VENDORS) CATEGORIES FOR VENDORS

2 B7.0 DRIVES

Standardization -
DRIVE, VARIABLE (ADJUSTABLE) FREQUENCY LESS THAN Category A, ABB is
4 B7.1 E ABB INC 2 0
1KV the selected PLA
Vendor
ROCKWELL AUTOMATION
B7.1
(ALLEN BRADLEY)
SIEMENS ENERGY &
B7.1
AUTOMATION
WEG EQUIPAMENTOS
B7.1
ELETRICOS S.A.
DRIVE, VARIABLE (ADJUSTABLE) FREQUENCY 1KV AND Standardization -
4 B7.2 E ABB INC 2 1
ABOVE Category A
Standardization -
Category A,
SIEMENS ENERGY &
4 B7.2 Siemens is the
AUTOMATION (ROBICON)
selected PLA
Vendor
WEG EQUIPAMENTOS
B7.2
ELETRICOS S.A.
DRIVE, VERY LARGE MOTOR / VFD COMBINATIONS (>10 Standardization -
3 B7.3 E ABB INC 3 2
MW) Category B
B7.3 AREVA
SIEMENS ENERGY &
B7.3
AUTOMATION (ROBICON)
2 B8.0 GENERATORS
Standardization -
3 B8.1 GENERATOR, SYNCHRONOUS E ALSTOM ELECRIC 3 3
Category E
2 B8.1 BRUSH TURBOGENERATORS
B8.1 GE
SIEMENS ENERGY &
B8.1
AUTOMATION
ATLAS INDUSTRIAL Standardization -
4 B8.2 GENERATOR, STANDBY DIESEL E 3 1
EQUIPMENT Category A
B8.2 CATERPILLAR - ELECTRICAL
B8.2 CUMMINS (ONAN)
B8.2 F G WILSON (ENGINEERING)
B8.2 INTERGEN SRL
B8.2 KOHLER COMPANY
B8.2 MUSTANG
Standardization
Standardi ation -
Category A, SAB is
4 B8.2 S.A.B.
the selected PLA
Vendor
SAUDI DIESEL GENERATORS
3 B8.2
COMPANY
ZAHID TRACTOR
3 B8.2
(CATERPILLAR)
3 B8.3 ENGINE, STANDBY DIESEL, FOR STANDBY GENERATORS E CATERPILLAR 3 1
3 B8.3 CUMMINS
3 B8.3 DEUTZ
3 B8.3 DETROIT DIESEL/MTU
4 B8.3 DOOSAN
3 B8.3 PERKINS
2 B9.0 HEAT TRACING
Standardization -
2 B9.1 HEAT TRACING, DESIGN AND TURNKEY PROJECTS E THERMON ELECTRIC 2 1
Category C

B9.1 TYCO THERMAL CONTROLS

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Electrical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Electrical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Field Need Date
CODE Suffix US$ Strategy Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
E= Equipment Requirements

B10.0 HEATERS
Standardization -
3 B10.1 HEATER, RESISTANCE B CHROMALOX 1 0
Category B
B10.1 GAUMER PROCESS HEATERS
B10.1 THERMON ELECTRIC
B10.1 TYCO (RAYCHEM)
B10.1 WATLOW
B11.0 LIGHTING
Standardization -
B11.1 LIGHTING, EMERGENCY FIXTURES B CROUSE-HINDS 1 0
Category B
B11.1 THOMAS & BETTS
Standardization -
3 B11.2 LIGHTING, LAMPS B OSRAM SYLVANIA 1 0
Category C
B11.2 PHILIPS
Standardization -
B11.3 LIGHTING, PROCESS AREA FIXTURES B CROUSE-HINDS 1 0
Category B
EGS ELECTRICAL GROUP
B11.3
(APPLETON)
B11.3 THOMAS & BETTS (HAZLUX)
Standardization -
B11.4 LIGHTING, HIGH BAY / LOW BAY B CROUSE-HINDS 1 0
Category B
EGS ELECTRICAL GROUP
B11 4
B11.4
(APPLETON)
B11.4 HOLOPHANE
B11.4 THOMAS & BETTS (HAZLUX)
GENLYTE THOMAS (DAY- Standardization -
3 B11.5 LIGHTING, CONTROL ROOM / OFFICE FIXTURES B 1 0
BRITE) Category C
B11.5 LITHONIA
B11.5 METALUX
B11.5 OSRAM SYLVANIA
B11.5 PHILIPS
2 B12.0 MOTOR CONTROL CENTERS
Standardization -
Category A, Eaton is
4 B12.1 MOTOR CONTROL CENTERS, 1000 V AND BELOW E EATON / CUTTLER HAMMER 2 2
the selected PLA
vendor
ROCKWELL AUTOMATION
4 B12.1
(ALLEN BRADLEY)
WAHAH ELECTRIC SUPPLY
4 B12.1 COMPANY OF SAUDI ARABIA
(SA)
Standardization -
Category A, Eaton is
4 B12.2 MOTOR CONTROL CENTERS, > 1000 V E EATON / CUTTLER HAMMER 2 2
the selected PLA
vendor
ROCKWELL AUTOMATION
B12.2
(ALLEN BRADLEY)
WAHAH ELECTRIC SUPPLY
4 B12.2 COMPANY OF SAUDI ARABIA
(SA)
2 B13.0 MOTORS
Standardization -
3 B13 1
B13.1 MOTOR FORM-WOUND BRUSHLESS SYNCH
MOTOR, E ABB INC 2 2
Category B
CONVERTEAM MOTORS SA
2 B13.1 (ELECTRIC MACHINERY)
ENGINE TYPE APLLICATIONS
ONLY
B13.1 GENERAL ELECTRIC
SIEMENS ENERGY &
2 B13.1
AUTOMATION
WEG EQUIPAMENTOS
B13.1
ELETRICOS S.A.
Standardization -
4 B13.2 MOTOR, FORM-WOUND IND., ABOVE 250 HP, HORIZONTAL E GENERAL ELECTRIC 2 2
Category A
SIEMENS ENERGY &
2 B13.2
AUTOMATION
B13.2 TECO WESTINGHOUSE
Standardization -
Category A, Teco
WEG EQUIPAMENTOS
4 B13.2 Westinghouse is the
ELETRICOS S.A.
selected PLA
Vendor
MOTOR, LOW VOLTAGE RANDOM-WOUND INDUCTION, UP Standardization -
4 B13.3 E GENERAL ELECTRIC 2 0
TO 250 HP Category A
SIEMENS ENERGY &
B13.3
AUTOMATION
Standardization -
TECO ELECTRIC & Category A, Teco
4 B13.3 Westinghouse is the
MACHINERY
selected PLA
Vendor
WEG EQUIPAMENTOS
B13.3
ELETRICOS S.A.
SIEMENS ENERGY &
3 B13.4
B13 4 MOTOR, IND., ABOVE 250 HP; VERTICAL
MOTOR FORM WOUND IND E 2 2
AUTOMATION
TECO ELECTRIC &
B13.4
MACHINERY
WEG EQUIPAMENTOS
B13.4
ELETRICOS S.A.
2 B14.0 PANELBOARDS
Standardization -
3 B14.1 PANELBOARD, LOW VOLTAGE, EXPLOSION PROOF B CROUSE-HINDS DIVISON 2 0
Category C
EATON ELECTRICAL (CUTLER-
B14.1
HAMMER)
B14.1 EGS APPLETON
ALFANAR ELECTRICAL Standardization -
3 B14.2 PANELBOARD, ELECTRICAL, LOW VOLTAGE B 2 0
SYSTEMS (SA) Category C
ARABIA ELECTRIC LIMITED
B14.2
(SA)
EATON ELECTRICAL (CUTLER-
4 B14.2
HAMMER)
ELECTRICAL POWER
B14.2
DISTRIBUTION

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Electrical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Electrical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Field Need Date
CODE Suffix US$ Strategy Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
E= Equipment Requirements

GULF INTERNATIONAL
ELECTRIC DISTRIBUTION
3 B14.2
APPARATUSES ASSEMBLIES
CO. LTD. (GEDAC) (SA)
REMAL FACTORY FOR
B14.2
ELECTRIC PANEL (SA)
B14.2 SQUARE D
WAHAH ELECTRIC SUPPLY
B14.2 COMPANY OF SAUDI ARABIA
(SA)
KINNEY ELECTRICAL Standardization -
4 B14.3 PANELBOARD, FUSED, ELECTRICAL, LOW VOLTAGE B 1 0
MANUFACTURING COMPANY Category C
EATON ELECTRICAL (CUTLER-
4 B14.3
HAMMER)
4 B14.3 COOPER BUSSMAN
B15.0 NOT USED
B15.1 NOT USED

B15.2 NOT USED


2 B16.0 POWER SYSTEM METERING & PROTECTION
2 B16.1 POWER SYSTEM, METERING B ABB INC 1 0
AMETEK POWER
B16.1 INSTRUMENTS (ROCHESTER
SCIENTIFIC COLUMBUS)
B16.1 COMPTON
B16.1 GE (MULTILIN)
B16.1 POWER MEASUREMENT
ROCKWELL AUTOMATION
B16.1
(ALLEN BRADLEY)
SIEMENS ENERGY &
B16.1
AUTOMATION
B16.1 SQUARE D
B16.1 TOSHIBA
2 B16.2 POWER SYSTEM, PROTECTIVE RELAYS B ABB INC 1 0
B16.2 BECKWITH ELECTRIC
EATON ELECTRICAL (CUTLER-
B16.2
HAMMER)

3 B16.2 GE MULTILIN Models 369 and 469 only

B16.2 SEL
SIEMENS ENERGY &
B16.2
AUTOMATION
Standardization -
3 B16.3 POWER SYSTEM, FUSES, < 1000 V B BUSSMANN 1 0
Category B
4 B16.3 FERRAZ SHAWMUT (MERSEN)
4 B16.3 LITTELFUSE
2 B16.4 POWER SYSTEM, FUSES, 1000 V AND ABOVE B ABB INC 1 0
B16.4 BUSSMANN
B16.4 GE
4 B16 4
B16.4 FERRAZ SHAWMUT (MERSEN)

B16.4 S&C ELECTRIC


SIEMENS ENERGY &
B16.4
AUTOMATION
2 B17.0 RECTIFIERS - CATHODIC PROTECTION
RECTIFIER - CATHODIC PROTECTION, IMPRESSED Standardization -
2 B17.1 B ABDULLA FOUAD IMPALLOY 1 0
CURRENT Category C
CATHODIC PROTECTION
B17.1
COMPANY
CORRPRO ARABIA GROUND
B17.1
(SA)
B17.1 J. A. ELECTRONICS
B17.1 THREE LIONS FACTORY (SA)

RECTIFIER - CATHODIC PROTECTION, POWER SUPPLY, Standardization -


2 B17.2 B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE KYOCERA SOLAR 1 0
ELECTRICAL Category C
B18.0 GROUNDING
Standardization -
3 B18.1 GROUNDING, MONITORING UNITS B BOND-RITE 1 0
Category C
B18.1 CROUSE-HINDS
EGS ELECTRICAL GROUP
B18.1
(APPLETON)
B18.1 ENRAF
B18.1 SCULLY
THOMAS & BETTS
B18.1
(RUSSELLSTOLL)
B18.1 TIMM-ELECTRONIC
Standardization -
3 B18.2 GROUNDING, HARDWARE & CONNECTIONS B CLIPSAL 1 0
Category C
B18.2 ERICO
B18.2 FCI BURNDY
THOMAS & BETTS
B18.2
(BLACKBURN)
2 B19.0 PROGRAMMABLE LOGIC CONTROLLERS
ROCKWELL AUTOMATION
2 B19.1 PROGRAMMABLE LOGIC CONTROLLERS E 1 0
(ALLEN BRADLEY)
SIEMENS ENERGY &
B19.1
AUTOMATION
TELEMECANIQUE (GROUP
B19.1
SCHNEIDER)
B20.0 PREFABRICATED SWITCH ROOMS
Standardization -
3 B20.1 PREFABRICATED SWITCH ROOMS E CONTROL ROOMS OF TEXAS 2 2
Category B
B20.1 GFRC SHELTERS
B20.1 METAL SYSTEMS
B20.1 POWELL INDUSTRIES
B21.0 PROCESS AREA PLUGS & RECEPTACLES (460 V)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Electrical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Electrical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Field Need Date
CODE Suffix US$ Strategy Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
E= Equipment Requirements

Standardization -
3 B21.1 PROCESS AREA PLUGS & RECEPTACLES (460 V) B CROUSE-HINDS 1 0
Category C
B21.1 RALCO
B21.1 THOMAS & BETTS (HAZLUX)
2 B22.0 MOTOR CONTROL STATIONS
MOTOR CONTROL STATION, NON CLASSIFIED, DIVISION 2, Standardization -
4 B22.1 E APPELTON 2 0
ZONE 2 Category B
4 B22.1 CROUSE-HINDS
ROCKWELL AUTOMATION
B22.1
(ALLEN BRADLEY)
MOTOR CONTROL STATION, HAZARDOUS AREA, DIVISION Standardization -
4 B22.2 E CROUSE-HINDS 2 0
1, ZONE 1 Category B
EGS ELECTRICAL GROUP
B22.2
(APPLETON)
B23.0 JUNCTION BOXES
ARABIAN FIBERGLASS Standardization -
3 B23.1 JUNCTION BOXES B 1 0
PRODUCTS Category C
B23.1 CEAG
HAWA ELECTRIC PANEL
B23.1
BOARD FACTORY
B23.1 HOFFMAN
REMAL FACTORY FOR
B23.1
ELECTRIC PANEL (SA)
B23.1 RITTAL ELECTRICAL
B23.1 ROBROY INDUSTRIES
SAFETY AND PROTECTION
B23.1
FACTORY
B23.1 STAHL ELECTRICAL
B24.0 SWITCHGEAR
Standardization -
4 B24.1 SWITCHGEAR, METAL-CLAD, LV, INDOOR E EATON 2 2
Category A
B24.1 POWELL INDUSTRIES
Standardization -
WAHAH ELECTRIC SUPPLY
Category A,
4 B24.1 COMPANY OF SAUDI ARABIA
WAHAH is the
(SA)
selected PLA
SWITCHGEAR, METAL-CLAD, INDOOR 1-38 KV AIR Standardization -
4 B24.2 E EATON 2 2
INSULATED Category A
Standardization -
Category A, Powell
4 B24.2 POWELL INDUSTRIES
is the selected PLA
Vendor
WAHAH ELECTRIC SUPPLY
4 B24.2 COMPANY OF SAUDI ARABIA
(SA)

B24.3 SWITCHGEAR, HV CONTROLGEAR, FIREWATER E AUTOMATIC SWITCH (ASCO) 2 2

B24.3 JOSLYN CLARK CONTROLS


Standardization -
3 B24.4 SWITCHGEAR, GIS, METAL ENCLOSED E ABB INC 2 2
Category B
B24.4 AREVA
SIEMENS ENERGY &
B24.4
AUTOMATION
4 B24.5 SWITCHGEAR, (GAS INSULATED) - 230K E
CONTROL AND PROTECTIVE RELAY PANEL
B25.0
(FABRICATORS)
Standardization -
3 B25.1 CONTROL AND PROTECTIVE RELAY PANEL (FABRICATORS) B ABB INC 1 1
Category B
ARABIA ELECTRIC LIMITED
B25.1
(SA)
B25.1 POINT EIGHT POWER
REMAL FACTORY FOR
B25.1
ELECTRIC PANEL (SA)
WAHAH ELECTRIC SUPPLY
B25.1 COMPANY OF SAUDI ARABIA
(SA)
2 B26.0 SWITCHES
ARABIA ELECTRIC LIMITED Standardization -
B26.1 SWITCH, DISCONNECT, HIGH VOLTAGE B 1 1
(SA) Category C
B26.1 PASCOR ATLANTIC
B26.1 S & C ELECTRIC
WAHAH ELECTRIC SUPPLY
B26.1 COMPANY OF SAUDI ARABIA
(SA)
SWITCH, DISCONNECT 600 V, HEAVY DUTY, FUSED/NON- Standardization -
B26.2 B ABB INC 1 1
FUSED Category C
B26.2 AREVA
EATON ELECTRICAL (CUTLER-
B26.2
HAMMER)
ROCKWELL AUTOMATION
B26.2
(ALLEN BRADLEY)
SIEMENS ENERGY &
B26.2
AUTOMATION
B26.2 SQUARE D
Standardization -
3 B26.3 SWITCH, TRANSFER, AUTOMATIC, INDOOR, LV B AUTOMATIC SWITCH (ASCO) 1 0
Category B
B26.3 EATON ELECTRICAL
GE ZENITH
B26.3 CONTROLS/GENERAL
ELECTRIC
B26.3 KOHLER
B26.3 RUSSELL ELECTRIC
2 B27.0 TRANSFORMERS
Standardization -
3 B27.1 TRANSFORMER, POWER DRY TYPE 150 KVA AND LARGER E ABB INC 2 1
Category C
4 B27.1 SQUARE D
WAHAH ELECTRIC SUPPLY
4 B27.1 COMPANY OF SAUDI ARABIA
(SA)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Electrical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Electrical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Field Need Date
CODE Suffix US$ Strategy Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
E= Equipment Requirements

WEG EQUIPAMENTOS
B27.1
ELETRICOS S.A.
Standardization -
Category A, ABB is
the selected PLA
4 B27.2 TRANSFORMER, POWER, LIQUID 250 KVA - 50 MVA E ABB INC 2 1
Vendor for Oil Filled
Units up to 3 MVA
and above
2 B27.2 AREVA
SIEMENS ENERGY &
B27.2
AUTOMATION
Standardization -
Category A,
WAHAH ELECTRIC SUPPLY
WAHAH is the
4 B27.2 COMPANY OF SAUDI ARABIA
selected PLA
(SA)
Vendor for Oil Filled
Units up to 2.5 MVA
Standardization -
TRANSFORMER, LARGE POWER REGULATING Category A, ABB is
4 B27.3 E ABB INC 3 2
TRANSFORMERS, LIQUID ABOVE 50 MVA the selected PLA
V d
Vendor
B27.3 AREVA
FUJI ELECTRIC/JAPAN AE
B27.3
POWER
SIEMENS ENERGY &
B27.3
AUTOMATION
WEG EQUIPAMENTOS
B27.3
ELETRICOS S.A.
B28.0 REACTORS
Standardization -
3 B28.1 REACTORS - CURRENT LIMITING B ABB INC 1 1
Category B
B28.1 AREVA
SIEMENS ENERGY &
B28.1
AUTOMATION
B28.1 TRENCH ELECTRIC (SIEMENS)
2 B29.0 UPS SYSTEM
Standardization -
Category A, AEG
4 B29.1 UPS SYSTEM, ABOVE 200KVA E AEG POWER SYSTEMS Power Solutions is 2 1
the selected PLA
Vendor
EMERSON NETWORK POWER
2 B29.1
(LIEBERT CORPORATION)
B29.1 MGE UPS SYSTEMS
Standardization - AEG Power Solutions is
Category A, AEG the PLA Vendor and
4 B29.2 UPS SYSTEM, INDUSTRIAL, ABOVE 10 TO 200KVA E AEG POWER SYSTEMS Power Solutions is 2 1 single point of contact for
the selected PLA chargers, batteries, and
Vendor UPS Systems.
B29.2 GUTOR ELECTRONIC
4 B30.0 POWER FACTOR CORRECTION CAPACITORS
4 30.1 POWER FACTOR CORRECTION CAPACITORS E 2 1
4 B31.0 ELECTICAL POWER MANAGEMENT SYSTEM
4 31.1 ELECTICAL POWER MANAGEMENT SYSTEM E 2 1
4 B32.0 CABLE MANAGEMENT
Standardization -
4 B32.1 CABLE MANAGEMENT E 2 1
Category A

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Electrical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

2 C 1.0 FLOW MEASUREMENT


EMERSON PROCESS Diamond II (DFF) (No.
Standardization -
C1.1 FLOW MEASUREMENT, ANNUBARS B MANAGEMENT (DIETERICH 1 0 3095 transmitters) (No. 485
Category B
STANDARD) annubar)
C1.1 EUROMISURE SRL Flotec
All that meet spec
C1.1 INTRA AUTOMATION
requirements
SOLARTRON MOBREY (KDG Low Flow, High Flow, KB
C1.1
INSTRUMENTS) Series (High accuracy)
MERIAM PROCESS Accutube Series 24D/25D
C1.1
TECHNOLOGIES (flange mount)
All that meet spec
2 C1.2 FLOW MEASUREMENT, ORIFICE PLATE/METER RUNS B BAIMONTE 1 0
requirements
All that meet spec
C1.2 BARTHEL
requirements
All that meet spec
C1.2 CRANE MANUFACTURING
requirements
All that meet spec
C1.2 DANIEL EUROPE
requirements
EIPSA - ESPANOLA DE All that meet spec
C1.2
INSTRUMENTACIO requirements
EMERSON PROCESS
All that meet spec
C1.2 MANAGEMENT ((DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.2 EUROMISURE SRL
requirements
All that meet spec
C1.2 HIMPE
requirements
OFFICINE NICOLA GALPERTI & All that meet spec
C1.2
FIGLIOS requirements
All that meet spec
C1.2 SOLARTRON ISA
requirements
All that meet spec
C1.2 TM TECNOMATIC SPA
requirements
All that meet spec
C1.2 WYATT ENGINEERING
requirements
All that meet spec
2 C1.3 FLOW MEASUREMENT, ORIFICE; PLATE; ASTM A 182/A 240 B CRANE MANUFACTURING 1 0
requirements
EMERSON PROCESS
All that meet spec
C1.3 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
EIPSA - ESPANOLA DE All that meet spec
C1.3
INSTRUMENTACIO requirements
All that meet spec
C1.3 EUROMISURE SRL
requirements
All that meet spec
C1.3 SOLARTRON ISA
requirements
All that meet spec
C1.3 TM TECNOMATIC SPA
requirements
FLOW MEASUREMENT, METER RUNS - PREFABRICATED All that meet spec
2 C1.4 B ALDERLEY FZE 1 0
GAS requirements
All that meet spec
C1.4 ALDERLEY SYSTEMS
requirements
EMERSON PROCESS
All that meet spec
C1.4 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.4 EUROMISURE SRL
requirements
All that meet spec
C1.4 KROHNE ALTOMETER
requirements
All that meet spec
C1.4 ODS BV
requirements
All that meet spec
C1.4 SOLARTRON ISA
requirements
FLOW MEASUREMENT, METER RUNS - PREFABRICATED All that meet spec
2 C1.5 B ALDERLEY FZE 1 0
LIQUID requirements
All that meet spec
C1.5 ALDERLEY SYSTEMS
requirements
EMERSON PROCESS
All that meet spec
C1.5 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)

C1.5 EUROMISURE SRL All that meet spec


requirements
All that meet spec
C1.5 KROHNE ALTOMETER
requirements
All that meet spec
C1.5 ODS BV
requirements
All that meet spec
C1.5 SOLARTRON ISA
requirements
FLOW MEASUREMENT, ORIFICE PLATE - SPECIAL All that meet spec
2 C1.6 B BARTHEL 1 0
MATERIAL OF CONSTRUCTION requirements
COLLINS INSTRUMENT All that meet spec
C1.6
COMPANY requirements
FLOW MEASUREMENT, INTEGRAL ORIFICE - FLOW EMERSON PROCESS
2 C1.7 B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE 1 0 Model/Series 1195
MEASUREMENT MANAGEMENT (ROSEMOUNT)

NOT ANTICIPATED FOR RTIP - SOLE SOURCE Use of V-Cones must be


C1.8 FLOW MEASUREMENT, V-CONES B MCCROMETER 1 0
approved by Owner
All that meet spec
C1.9 FLOW MEASUREMENT, VENTURI TUBES B ABB INC 1 0
requirements
All that meet spec
C1.9 BARTHEL
requirements
EMERSON PROCESS
All that meet spec
C1.9 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
EIPSA - ESPANOLA DE All that meet spec
C1.9
INSTRUMENTACIO requirements
All that meet spec
C1.9 EUROMISURE SRL
requirements
All that meet spec
C1.9 HIMPE
requirements
All that meet spec
C1.9 SOLARTRON ISA
requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

All that meet spec


C1.9 TM TECNOMATIC SPA
requirements
All that meet spec
C1.9 WYATT ENGINEERING
requirements
All that meet spec
C1.10 FLOW MEASUREMENT, WEDGE METER B ABB INC 1 0
requirements
All that meet spec
C1.10 SOLARTRON ISA
requirements
All that meet spec
C1.11 FLOW MEASUREMENT, FLOW NOZZLE B CRANE MANUFACTURING 1 0
requirements
EMERSON PROCESS
All that meet spec
C1.11 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.11 EUROMISURE SRL
requirements
Rosemount transmitter
EMERSON PROCESS Standardization - 8732; Rosemount - sensor -
C1.12 FLOW MEASUREMENT, MAGNETIC METER B 1 0
MANAGEMENT (ROSEMOUNT) Category B 8705 series flanged,
transmitter - 8712 smart
Krohne Optiflux 4000
sensor, Krohne IFC 300
C1.12 KROHNE
transmitter; IFM 6080
(small sizes)
YOKOGAWA ELECTRIC
C1.12 ADMAG AXF
CORPORATION
EMERSON PROCESS Standardization -
C1.13 FLOW MEASUREMENT, VORTEX B 1 0 Model / Series 8800C
MANAGEMENT (ROSEMOUNT) Category B
C1.13 ENDRESS+HAUSER Prowirl 72
EMERSON PROCESS Sensors CMF025 to
Standardization -
C1.14 FLOW MEASUREMENT, CORIOLIS METER - DUAL TUBE B MANAGEMENT (MICRO 1 0 CMF300, with 2700
Category B
MOTION) electronics
Promas F and M meters
with 80 series electronics
C1.14 ENDRESS+HAUSER standard. Series 83
electronics used only if
special functionality is
required
EMERSON PROCESS
Standardization - Tseries with 2700
C1.15 FLOW MEASUREMENT, CORIOLIS METER, STRAIGHT TUBE B MANAGMENT (MICRO 1 0
Category B electronics
MOTION)
Promas I meters with 80
series electronics standard.
C1.15 ENDRESS+HAUSER Series 83 electronics used
only if special functionality is
required.
C1.15 KROHNE Optimas 7000
EMERSON PROCESS
FLOW MEASUREMENT, CORIOLIS METER - LOW FLOW CMF 10 with series 2700
C1.16 B MANAGEMENT (MICRO 1 0
METERS (BELOW 1/4" TUBES) electronics
MOTION)
Promass A with series 80
electronics standard. Series
C1.16 ENDRESS+HAUSER 83 electronics used only if
special functionality is
required.
FLOW MEASUREMENT, CORIOLIS - SPECIAL METERS NOT A TECHNOLOGY DRIVEN SINGLE SOURCE All that meet spec
C1.17 B RHEONIK 1 0
(LARGE SIZES) requirements
FLOW MEASUREMENT, POSITIVE DISPLACEMENT - GAS All that meet spec
C1.18 B AMERICAN METER 1 1
TYPE requirements
All that meet spec
C1.18 BADGER METER
requirements
BARTON INSTRUMENT All that meet spec
C1.18
SYSTEMS requirements
All that meet spec
C1.18 BRODIE METER
requirements
DRESSER INC (ROOTS All that meet spec
C1.18
METERS & INSTRUMENTS) requirements
All that meet spec
C1.18 ROMET
requirements
FLOW MEASUREMENT, POSITIVE DISPLACEMENT - GEAR BOPP AND REUTHER All that meet spec
2 C1.19 B 1 1
OR HELICAL TYPE MESSTECHNIK requirements
All that meet spec
C1.19 BRODIE METER
requirements
All that meet spec
C1.19 FLOW DATA
requirements
All that meet spec
C1.19 MAX MACHINERY
requirements
All that meet spec
C1.19 SMITH METER
requirements
All that meet spec
C1.20 FLOW MEASUREMENT, THERMAL - INSERTION B FLUID COMPONENTS 1 0
requirements
All that meet spec
C1.20 KURZ INSTRUMENTS
requirements
AMERICAN INDUSTRIAL
All that meet spec
C1.21 FLOW MEASUREMENT, THERMAL - SPOOL PIECE B PARTNERS (BROOKS 1 0
requirements
INSTRUMENTS)
All that meet spec
C1.21 BRONKHORST
requirements
All that meet spec
C1.21 FLUID COMPONENTS
requirements
All that meet spec
C1.21 KURZ INSTRUMENTS
requirements
AMERICAN INDUSTRIAL
FLOW MEASUREMENT, VARIABLE AREA (ROTAMETERS) - Standardization - All that meet spec
3 C1.22 B PARTNERS (BROOKS
GLASS TUBE (METAL OR PLASTIC BLOCKS) Category C requirements
INSTRUMENTS)
KROHNE-MESSTECHNIK All that meet spec
C1.22
GMBH & CO requirements
ROTA YOKOGAWA GMBH & All that meet spec
C1.22
CO requirements
All that meet spec
C1.22 WALLACE AND TIERNAN
requirements
FLOW MEASUREMENT, VARIABLE AREA (ROTAMETERS) - Standardization - All that meet spec
C1.23 B ABB INC 1 0
ARMORED (STAINLESS STEEL) Category C requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

AMERICAN INDUSTRIAL
All that meet spec
C1.23 PARTNERS (BROOKS
requirements
INSTRUMENTS)
KROHNE-MESSTECHNIK All that meet spec
C1.23
GMBH & CO requirements
ROTA YOKOGAWA GMBH & All that meet spec
C1.23
CO requirements
FLOW MEASUREMENT, ULTRASONIC - LIQUID TYPE - GE INDUSTRIAL SENSING Standardization -
C1.24 B 1 0 DF868, XMT868
CLAMP-ON (PANAMETRICS) Category B
ADM Series. Portable
C1.24 FLEXIM Clamp-On Series is not
Acceptable.
FLOW MEASUREMENT, ULTRASONIC - LIQUID TYPE - GE INDUSTRIAL SENSING Standardization - All that meet spec
C1.25 B 1 0
PORTABLE, CLAMP-ON (PANAMETRICS) Category B requirements
3 C1.25
EMERSON PROCESS
FLOW MEASUREMENT, ULTRASONIC - LIQUID TYPE - Standardization -
2 C1.26 B MANAGEMENT (DANIEL 1 0 Daniel Model 3804
SPOOL PIECE Category B
MEASUREMENT & CONTROL)
GE INDUSTRIAL SENSING
C1.26 DF868, XMT868
(PANAMETRICS)
C1.26 KROHNE UFM3030, normal use
Standardization - All that meet spec
C1.27 FLOW MEASUREMENT,, ULTRASONIC,, FLARE B ELSTER-INSTROMET NV 1 0
C t
Category B i
requirementst
All that meet spec
C1.27 PANAMETRICS
requirements
EMERSON PROCESS
FLOW MEASUREMENT, ULTRASONIC - GAS TYPE - SPOOL Standardization -
2 C1.28 B MANAGEMENT (DANIEL 1 0 Daniel SeniorSonic
PIECE Category B
MEASUREMENT & CONTROL)
Q.Sonic
C1.28 ELSTER-INSTROMET NV
FlareSonic
GE INDUSTRIAL SENSING GF868, GM868, GM868,
C1.28
(PANAMETRICS) GS868
All that meet spec
C1.28 KROHNE
requirements
2 C1.28 SICK ENGINEERING GMBH FlowSIC600

EMERSON PROCESS
FLOW MEASUREMENT, MULTIPATH ULTRASONIC; GAS Standardization - All that meet spec
C1.29 B MANAGEMENT (DANIEL 1 0
SERVICE Category B requirements
MEASUREMENT & CONTROL)

All that meet spec


C1.29 ELSTER-INSTROMET NV
requirements
All that meet spec
C1.29 KROHNE
requirements
All that meet spec
C1.29 SICK ENGINEERING GMBH
requirements
CANADA PIPELINE All that meet spec
C1.30 FLOW MEASUREMENT, STRAIGHTENING DEVICES B 1 0
ACCESSORIES requirements
EMERSON PROCESS
All that meet spec
C1.30 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.30 ODS
requirements
All that meet spec
C1.30 SAVANT
requirements
All that meet spec
C1.30 VORTAB
requirements
EMERSON PROCESS
Standardization - All that meet spec
C1.31 FLOW MEASUREMENT, DENSITY - VIBRATING CYLINDER B MANAGEMENT (MOBREY 1 0
Category C requirements
MEASUREMENT)
THERMO ELECTRON All that meet spec
C1.31
(SARASOTA) requirements
YOKOGAWA ELECTRIC All that meet spec
C1.31
CORPORATION requirements
All that meet spec
C1.32 FLOW MEASUREMENT, DENSITY - NUCLEAR B BERTHOLD 1 0
requirements
THERMO ELECTRON (TEXAS All that meet spec
C1.32
NUCLEAR) requirements
All that meet spec
C1.33 FLOW MEASUREMENT, METERING SKID B ALDERLEY FZE 3 3
requirements
All that meet spec
C1.33 ALDERLEY SYSTEMS
requirements
All that meet spec
C1.33 FMC TECHNOLOGIES
requirements
KROHNE-MESSTECHNIK All that meet spec
C1.33
GMBH & CO requirements
All that meet spec
C1.33 ODS BV
requirements
FLOW MEASUREMENT, CUSTODY AUTOMATIC SAMPLING, All that meet spec
2 C1.34 B ABB INC 1 0
GAS requirements
EMERSON PROCESS
All that meet spec
C1.34 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.34 DOEDIJNS CONTROLS BV
requirements
FLOW MEASUREMENT, CUSTODY AUTOMATIC SAMPLING, All that meet spec
2 C1.35 B DOEDIJNS CONTROLS BV 1 0
LIQUID requirements
All that meet spec
C1.35 JISKOOT
requirements
EMERSON PROCESS
FLOW MEASUREMENT, CUSTODY CHROMATOGRAPH, GAS All that meet spec
2 C1.36 B MANAGEMENT (DANIEL 1 0
OR LIQUID requirements
MEASUREMENT & CONTROL)
SOLARTRON MOBREY (KDG All that meet spec
2 C1.37 FLOW MEASUREMENT, CUSTODY DENSITY METER, LIQUID B 1 0
INSTRUMENTS) requirements
All that meet spec
C1.37 THERMO FISHER SCIENTIFIC
requirements
FLOW MEASUREMENT, CUSTODY FLOW COMPUTER, GAS, All that meet spec
2 C1.38 B DYNAMIC FLOW COMPUTERS 1 0
FIELD MOUNTED requirements
All that meet spec
C1.38 OMNI FLOW COMPUTERS
requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

EMERSON PROCESS
FLOW MEASUREMENT, CUSTODY FLOW COMPUTER, GAS, All that meet spec
2 C1.39 B MANAGEMENT (DANIEL 1 0
PANEL-MNTD requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.39 OMNI FLOW COMPUTERS
requirements
EMERSON PROCESS
FLOW MEASUREMENT, CUSTODY FLOW COMPUTER, All that meet spec
2 C1.40 B MANAGEMENT (DANIEL 1 0
LIQUID, PANEL-MNT requirements
MEASUREMENT & CONTROL)

All that meet spec


C1.40 OMNI FLOW COMPUTERS
requirements

EMERSON PROCESS
FLOW MEASUREMENT, CUSTODY METER, MULTI-PATH, All that meet spec
2 C1.41 B MANAGEMENT (DANIEL 1 0
ULTRASONIC requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.41 ELSTER-INSTROMET NV
requirements
All that meet spec
C1.41 KROHNE
requirements
All that meet spec
C1 41
C1.41 SICK ENGINEERING GMBH
requirements
All that meet spec
C1.41 SMITH METER (FMC)
requirements
EMERSON PROCESS
All that meet spec
2 C1.42 FLOW MEASUREMENT, CUSTODY METER, ORIFICE PLATE B MANAGEMENT (DANIEL 1 0
requirements
MEASUREMENT & CONTROL)
EMERSON PROCESS
FLOW MEASUREMENT, CUSTODY METER, ORIFICE, DUAL All that meet spec
2 C1.43 B MANAGEMENT (DANIEL 1 0
CHAMBER requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.43 SMITH METER
requirements
All that meet spec
C1.43 PIETRO FIORENTINI
requirements
EMERSON PROCESS
FLOW MEASUREMENT, CUSTODY METER, ORIFICE, SINGLE All that meet spec
2 C1.44 B MANAGEMENT (DANIEL 1 0
CHAMBER requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.44 SMITH METER
requirements
All that meet spec
C1.44 PIETRO FIORENTINI
requirements
FLOW MEASUREMENT, CUSTODY METER, POS DISPL , All that meet spec
C1.45 B SMITH METER 1 1
LIQUID requirements
All that meet spec
C1.45 BRODIE METER
requirements
EMERSON PROCESS
All that meet spec
C1.46 FLOW MEASUREMENT, CUSTODY METER, TURBINE, LIQUID B MANAGEMENT (DANIEL 1 1
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.46 SMITH METER
requirements
q
FLOW MEASUREMENT, CUSTODY METERING CONTROL All that meet spec
C1.47 E ALDERLEY SYSTEMS 2 2
SYSTEM, GAS requirements

EMERSON PROCESS
All that meet spec
C1.47 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)

All that meet spec


C1.47 ODS BV
requirements
STEPHEN GILLESPIE All that meet spec
C1.47
CONSULTANTS requirements
All that meet spec
C1.47 SWINTON TECHNOLOGY
requirements
FLOW MEASUREMENT, CUSTODY METERING CONTROL All that meet spec
C1.48 E ALDERLEY SYSTEMS 2 2
SYSTEM, LIQUID requirements
EMERSON PROCESS
All that meet spec
C1.48 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.48 ODS BV
requirements
STEPHEN GILLESPIE All that meet spec
C1.48
CONSULTANTS requirements
All that meet spec
C1.48 SWINTON TECHNOLOGY
requirements
STEPHEN GILLESPIE All that meet spec
C1.48
CONSULTANTS LTD requirements
FLOW MEASUREMENT, CUSTODY PRESET CONTROLLER All that meet spec
2 C1.49 B SMITH METER 1 0
TRUCK UNLOADNG requirements
EMERSON PROCESS
All that meet spec
C1.49 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
FLOW MEASUREMENT, CUSTODY PRESET CONTROLLER, All that meet spec
2 C1.50 B SMITH METER 1 0
TRUCK LOADING requirements
EMERSON PROCESS
All that meet spec
C1.50 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
FLOW MEASUREMENT, CUSTODY PROVER, BI- All that meet spec
C1.51 E ALDERLEY SYSTEMS 3 3
DIRECTIONAL requirements
All that meet spec
C1.51 ALDERLEY FZE
requirements
All that meet spec
C1.51 ODS BV
requirements
FLOW MEASUREMENT, CUSTODY PROVER, SMALL All that meet spec
2 C1.52 B ALDERLEY FZE 2 2
VOLUME requirements
All that meet spec
C1.52 CALIBRON SYSTEMS
requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

EMERSON PROCESS
All that meet spec
C1.52 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
FLOW MEASUREMENT, CUSTODY PROVER, UNI- All that meet spec
2 C1.53 B FMC TECHNOLOGIES 3 3
DIRECTIONAL requirements
All that meet spec
C1.53 SMITH METER
requirements
FLOW MEASUREMENT, CUSTODY SYS TRUCK All that meet spec
2 C1.54 B ALDERLEY FZE 1 0
UNLOADING, POS DISP requirements
All that meet spec
C1.54 ALDERLEY SYSTEMS
requirements
All that meet spec
C1.54 FMC TECHNOLOGIES
requirements
FLOW MEASUREMENT, CUSTODY SYS, LIQUID PIPELINE, All that meet spec
2 C1.55 B ALDERLEY FZE 1 0
TURBINE/PD requirements
All that meet spec
C1.55 ALDERLEY SYSTEMS
requirements
EMERSON PROCESS
All that meet spec
C1.55 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.55 FMC TECHNOLOGIES
requirements
All that meet spec
C1.55 ODS BV
requirements
FLOW MEASUREMENT, CUSTODY SYSTEM GAS PIPELINE, All that meet spec
C1.56 B ALDERLEY FZE 1 1
ORIFICE requirements
All that meet spec
C1.56 ALDERLEY SYSTEMS
requirements
EMERSON PROCESS
All that meet spec
C1.56 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.56 ELSTER-INSTROMET NV
requirements
All that meet spec
C1.56 FMC TECHNOLOGIES
requirements
All that meet spec
C1.56 ODS BV
requirements
FLOW MEASUREMENT, CUSTODY SYSTEM GAS PIPELINE, All that meet spec
C1.57 B ALDERLEY FZE 1 1
ULTRASONIC requirements
All that meet spec
C1.57 ALDERLEY SYSTEMS
requirements
All that meet spec
C1.57 ELSTER-INSTROMET NV
requirements
All that meet spec
C1.57 FMC TECHNOLOGIES
requirements
All that meet spec
C1.57 KROHNE OIL AND GAS
requirements
All that meet spec
C1.57 ODS BV
requirements
All that meet spec
C1.57 PIETRO FIORENTINI
requirements
FLOW MEASUREMENT, CUSTODY SYSTEM, TRUCK All that meet spec
C1.58 B ALDERLEY FZE 1 1
LOADING, POS DISP requirements
All that meet spec
C1.58 ALDERLEY SYSTEMS
requirements
All that meet spec
C1.58 FMC TECHNOLOGIES
requirements
FLOW MEASUREMENT, CUSTODY AUTOMATIC SAMPLING, All that meet spec
2 C1.59 B ABB INC 1 0
GAS requirements
EMERSON PROCESS
All that meet spec
C1.59 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
2 C1.59 SERVOMEX
requirements
All that meet spec
C1.60 FLOW MEASUREMENT, REMOTE TERMINAL UNIT TYPE B ARABIA ELECTRICAL 1 0
requirements
All that meet spec
C1.60 BRISTOL BABCOCK
requirements
All that meet spec
C1.60 ELSAG DATAMAT SPA
requirements
All that meet spec
C1.60 GE ENERGY SERVICES
requirements
All that meet spec
C1.60 INVENSYS MIDDLE EAST FZE
requirements
INVENSYS PROCESS All that meet spec
C1.60
SYSTEMS requirements
REMOTE AUTOMATION All that meet spec
C1.60
SOLUTIONS requirements
C1.60 SIEMENS AG All that meet spec
requirements
YOKOGAWA CORPORATION All that meet spec
C1.60
OF AMERICA requirements
YOKOGAWA ENGINEERING All that meet spec
C1.60
ASIA (YEA) requirements
All that meet spec
C1.60 YOKOGAWA MIDDLE EAST
requirements
YOKOGAWA SYSTEMS All that meet spec
C1.60
CENTER EUROPE B.V. requirements
FLOW MEASUREMENT, METER; PROVER; BI-DIRECTIONAL All that meet spec
C1.61 E ALDERLEY FZE 2 2
C/W ACCESS requirements
All that meet spec
C1.61 ALDERLEY SYSTEMS
requirements
EMERSON PROCESS
All that meet spec
C1.61 MANAGEMENT (DANIEL
requirements
MEASUREMENT & CONTROL)
All that meet spec
C1.61 FMC TECHNOLOGIES
requirements
All that meet spec
C1.62 FLOW MEASURMENT, FLOW SIGHT GLASSES B ABB INC 1 0
requirements
CLARKE RELIANCE JACOBY All that meet spec
C1.62
TARBOX CORP requirements
All that meet spec
C1.62 ERNST GAGE
requirements
TYCO FLOW CONTROL All that meet spec
C1.62
(PENBERTHY) requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

2 C2.0 INSTRUMENT AIR SUPPLY & TUBING


3 C2.1 INSTRUMENT AIR SUPPLY, FILTERS B SIEMENS (MOORE) Model 2306
3R30 Series Hose w/ 3904
C2.2 INSTRUMENT AIR SUPPLY, HOSES B EATON CORPORATION 1 0
fittings
S007.51.212.35 (Schneider
ARMATURENFABRIK FRANZ
C2.3 INSTRUMENT AIR SUPPLY, AIR SUPPLY MANIFOLDS B NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC 1 0 part number) per G6D-
SCHNEIDER
0102-00
C2.4 INSTRUMENT AIR SUPPLY, FUSIBLE LINKS / PLUGS B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE ELSIE MANUFACTURING 1 0 Pipe Plug 212 deg.F

ASSOCIATED TUBE All that meet spec


C2.5 INSTRUMENT TUBING, METALLIC B 1 0
INDUSTRIES requirements
All that meet spec
C2.5 AVEST SANDVIK TUBE
requirements
AVESTA POLARIT STAINLESS All that meet spec
C2.5
TUBE requirements
All that meet spec
C2.5 HANDY HARMANN
requirements
SANDVIK MATERIALS All that meet spec
C2.5
TECHNOLOGY requirements
SANDVIK TUBULAR All that meet spec
C2.5
PRODUCTS requirements
All that meet spec
C2.5 SCHOELLER-BLECKMANN
requirements
All that meet spec
C2.5 SUMITOMO METAL
requirements
THE INDIAN SEAMLESS All that meet spec
C2.5
METAL TUBE requirements
Standardization -
2 C2.6 INSTRUMENT TUBE FITTINGS, METALLIC B SEE ANALYTICAL 8.38 1 0
Category A

Standardization -
2 C2.7 INSTRUMENT TUBE FITTINGS, AIR PIPING B SEE ANALYTICAL 8.38 1 0
Category A
INSTRUMENT TUBE FITTINGS, SMALL VALVES (TUBING AND All that meet spec
4 C2.8 B MERWEDE VALVES
THREADED ENDS) requirements
All that meet spec
4 C2.8 OLIVER VALVES
requirements
All that meet spec
C2.8 PARKER HANNIFIN
requirements
All that meet spec
C2.8 SWAGELOK
requirements
TYCO ANDERSON All that meet spec
C2.8
GREENWOOD requirements
INSTRUMENT AIR SUPPLY, FILTERS/REGULATORS (AIR
3 C2.9 B 1 0
SETS)
2 C3.0 JUNCTION BOXES
Standardization - All that meet spec
C3.1 JUNCTION BOX, FIELD B CEAG / CROUSE HINDS 1 0
Category D requirements
All that meet spec
C3.1 HOFFMAN
requirements
All that meet spec
C3.1 RITTAL
requirements
JUNCTION BOX, CONTROL PANELS/EQUIPMENT All that meet spec
C3.2 B AMOT CONTROLS 1 0
ENCLOSURE INTEGRATORS requirements
All that meet spec
3 C3 2
C3.2 BENTLY NEVADA
requirements
COMPUTER SYSTEM All that meet spec
3 C3.2
PROTECTION requirements
All that meet spec
3 C3.2 CONTROLS & ELECTRICS PTE
requirements
All that meet spec
C3.2 ELECTROMACH BV
requirements
GULF INT'L ELECTRICAL All that meet spec
3 C3.2
DISTRIBUTION requirements
All that meet spec
C3.2 HIMA SELLA
requirements
INDUSTRIAL CONTROL All that meet spec
3 C3.2
SERVICES requirements
PANELMATIC TEXAS All that meet spec
C3.2
INCORPORATED requirements
REMAL FACTORY FOR All that meet spec
C3.2
ELECTRIC PANEL requirements
SWITCHGEAR & All that meet spec
C3.2
INSTRUMENTATION requirements
TOTAL ENGINEERING All that meet spec
C3.2
SERVICES TEAM requirements
C3.3 COMBINED WITH 3.2 0
All that meet spec
2 C3.4 JUNCTION BOX, FREE STANDING ENCLOSURES B CROUSE HINDS 1 0
requirements
All that meet spec
C3.4 HOFFMAN
requirements
C3.4 RITTAL TS
C3.5 COMBINED WITH 3.4 0
All that meet spec
C3.6 JUNCTION BOX, TERMINAL BLOCKS B PHOENIX CONTACT 1 0
requirements
C3.6 WEIDMUELLER W Series
Use ISOLATING barriers
C3.7 JUNCTION BOX,, BARRIERS - INSTRINSIC SAFETY B MTL INSTRUMENTS GROUP 1 0
only
l
Use ISOLATING barriers
C3.7 PEPPERL+FUCHS GMBH
only
All that meet spec
2 C3.8 JUNCTION BOX, SIGNAL CONDITIONING B MTL INSTRUMENTS GROUP 1 0
requirements
All that meet spec
C3.8 PEPPERL+FUCHS GMBH
requirements
All that meet spec
2 C3.9 JUNCTION BOX, SIGNAL ISOLATORS B MTL INSTRUMENTS GROUP 1 0
requirements
All that meet spec
C3.9 PEPPERL+FUCHS GMBH
requirements
JUNCTION BOX, SEPARATION AMPLIFIERS (ISOLATORS) - All that meet spec
2 C3.10 B MTL INSTRUMENTS GROUP 1 0
INSTRINSIC SAFETY requirements
All that meet spec
C3.10 PEPPERL+FUCHS GMBH
requirements
All that meet spec
C3.11 JUNCTION BOX, SURGE ARRESTERS (SUPRESSION) B MTL INSTRUMENTS GROUP 1 0
requirements
All that meet spec
C3.11 PHOENIX CONTACT
requirements
All that meet spec
C3.12 JUNCTION BOX, TERMINAL STRIPS / BLOCKS B PHOENIX CONTACT 1 0
requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

All that meet spec


C3.12 WEIDMUELLER
requirements
ACOPIAN TECHNICAL All that meet spec
2 C3.13 JUNCTION BOX, POWER SUPPLIES - DC B 1 0
COMPANY requirements
220VAC LZS-1500-3
C3.13 LAMBDA
115VAC SE-1500-3
MODEL - Mean Well SP-
750-27, Mean Well Stock
C3.13 MEAN WELL Number 11205. Supplier of
power supplies for non-
certified MODTM 5 CANs
C3.13 PHOENIX CONTACT QUINT Series
All that meet spec
C3.14 JUNCTON BOX, RELAYS - INTERPOSING - GENERAL B CUTLER HAMMER 1 0
requirements
All that meet spec
C3.14 OMRON
requirements
See EMETL practice G7D-
C3.14 PHOENIX CONTACTS
1735-01
ROCKWELL AUTOMATION All that meet spec
C3.14
(ALLEN BRADLEY) requirements
All that meet spec
C3.14 TYCO POTTER BRUMSFIELD
requirements
PHOENIX CONTACT See EMETL practice G7D-
3 C3.15 JUNCTON BOX, RELAYS - INTERPOSING - SAFETY 1 0
(INSTRUMENTATION) 1735 01
1735-01
2 C4.0 LEVEL MEASUREMENT
All that meet spec
2 C4.1 LEVEL MEASUREMENT, GAUGE - LEVEL GLASS B JERGUSON GAGE & VALVE 1 0
requirements
All that meet spec
C4.1 K-TEK
requirements
All that meet spec
C4.1 TYCO (PENBERTHY)
requirements
All that meet spec
C4.1 TYCO (YARWAY)
requirements
2 C4.2 LEVEL MEASUREMENT, GAUGE - LEVEL MAGNETIC B CESARE BONETTI SPA 1 0 BONT
C4.2 K-TEK KM 26
Maglink Mag 3 - Mag 16
C4.2 MAGNETROL (10-14-08) SIL: DO NOT
use in SIL
FTL 50 and 70 series
LEVEL MEASUREMENT, SWITCHES - VIBRATING - LIQUID "Liquiphant"(10-14-08) SIL:
2 C4.3 B ENDRESS+HAUSER 1 0
(PROCESS APPLICATIONS) Evaluated by Exida for use
in SIS
Optiswitch 4000, 5000 C
C4.3 KROHNE
series
C4.3 VEGA Vegaswing 51, 61, 63
FTL 50 & 70 Series with
LEVEL MEASUREMENT, SWITCHES - VIBRATING - LIQUID FEL 57 & FTL 325P or FDL
2 C4.4 B ENDRESS+HAUSER 1 0 60 Series w/FTL 670 (10-
(SIS APPLICATIONS)
14-08) SIL: Certified by
TUEV for use in SIS
C4.4 KROHNE Optiswitch 5000
C4.4 VEGA Vegaswing 61, 63
LEVEL MEASUREMENT, SWITCHES - FLOAT/DISPLACER -
2 C4.5 B K-TEK 1 0 LS 20
CAGED
B 24, C 24, B 40, B 60, B
C4 5
C4.5 MAGNETROL 73 H & N (10
73, (10-14-08)
14 08) SIL
SIL:
DO NOT use in SIL
C4.5 SOLARTRON MOBREY Vertical Float
100 Series 741-743, 200
C4.5 SOR
Series 740-803, 801, 802
LEVEL MEASUREMENT, SWITCHES - FLOAT - DIRECT All that meet spec
2 C4.6 B K-TEK 1 0
INSERTION requirements
All that meet spec
C4.6 MAGNETROL
requirements
All that meet spec
C4.6 TOKYO KEISO
requirements
All that meet spec
C4.6 SOLARTRON MOBREY
requirements
All that meet spec
C4.6 SOR
requirements
All that meet spec
2 C4.7 LEVEL MEASUREMENT, SWITCHES - NUCLEAR B BERTHOLD 1 0
requirements
All that meet spec
C4.7 ENDRESS+HAUSER requirements (10-14-08)
SIL: Evaluated by Exida for
use in SIS
All that meet spec
C4.7 OHMART VEGA requirements (10-14-08)
SIL: DO NOT use in SIL
All that meet spec
2 C4.8 LEVEL MEASUREMENT, SWITCHES - CONDUCTIVITY B DWYER 1 0
requirements
All that meet spec
C4.8 ENDRESS+HAUSER requirements (10-14-08)
SIL: DO NOT use in SIL
All that meet spec
C4.8 VEGA
requirements
LEVEL MEASUREMENT, SWTICHES - CONDUCTIVITY All that meet spec
2 C4.9 B DWYER 1 0
(S U )
(STEAM DRUM) equ e e ts
requirements
All that meet spec
C4.9 FLOWSERVE (GESTRA)
requirements
All that meet spec
C4.9 TYCO (YARWAY)
requirements
All that meet spec
C4.9 VEGA
requirements
All that meet spec
2 C4.10 LEVEL MEASUREMETN, SWITCHES - THERMAL B K-TEK 1 0
requirements
All that meet spec
C4.10 MAGNETROL
requirements
LEVEL MEASUREMENT, SWITCHES - ULTRASONIC
2 C4.11 B AMETEK DREXELBROOK 1 0 VeriGAP 504 Series
(WETTED GAP)
Echotel 915, 961 and 962
C4.11 MAGNETROL (10-14-08) SIL: Evaluated
by Exida for use in SIS
THERMO ELECTRON
C4.11 Sapphire
(SENSALL)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

Liquicap M FTI51, FTI52,


LEVEL MEASUREMENT, SWITCHES - CAPACITANCE (RADIO Multicap DC 11, 12, 16 or
2 C4.12 B ENDRESS+HAUSER 1 0 21 Ceramic 11500 (10-14-
FREQUENCY)
08) SIL: DO NOT use in
SIL
KCAP300, KCAP400, A02,
C4.12 K-TEK
A77, A75
All that meet spec
C4.12 MAGNETROL requirements (10-14-08)
SIL: DO NOT use in SIL
LEVEL MEASUREMENT, SOLIDS (SILO / HOPPERS) - All that meet spec
2 C4.13 B AMETEK 1 0
CAPACITANCE requirements
All that meet spec
C4.13 ENDRESS+HAUSER
requirements
All that meet spec
C4.13 MAGNETROL
requirements
Single Probe (10-16-08)
LEVEL MEASUREMENT, SOLIDS (SILO / HOPPERS) - AUTOMATION PRODUCTS ACCEPTABLE for MRO
2 C4.14 B 1 0
VIBRATING SWITCH (DYNATROL) only. SIL: DO NOT use in
SIL
Soliphant II FTM 50, 51 or
52 (10-15-08) SIL:
C4.14 ENDRESS+HAUSER
Evaluated by Exida for use
in SIS
Silopilot FMM 760 (10-15-
LEVEL MEASUREMENT, SOLIDS (SILO / HOPPERS) -
2 C4.15 B ENDRESS+HAUSER 1 0 08) SIL: DO NOT use in
ELECTRO MECHANICAL (YO-YO)
SIL
FMU 41, FMU 43, FMY 860
LEVEL MEASUREMENT, SOLIDS (SILO / HOPPERS) - with Sensors FDU 80 to 86
2 C4.16 B ENDRESS+HAUSER 1 0
ULTRASONIC (10-15-08) SIL: DO NOT
use in SIL
C4.16 OHMART VEGA Vegason 51 - 56
FRM (10-16-08) SIL:
LEVEL MEASUREMENT, FLUSH RINGS - METAL AND
3 C4.17 B 1 0 Qualified for use in SIS
INSTALLATION DETAILS
loops as Proven-in use.
All that meet spec
3 C4.18 LEVEL MEASUREMENT, FLUSH RINGS - LINED requirements (10-16-08)
SIL: Qualified for use in SIS
loops as Proven-in-use.
LEVEL MEASUREMENT, TANK GAUGING EQUIPMENT - ENRAF TERMINAL 854 (10-15-08) SIL: DO
2 C4.19 B 1 0
SERVO AND FLOAT AUTOMATION NOT use in SIL
C4.19 L & J TECHNOLOGIES MCG 1500SFI
C4.19 VAREC 6005 STG
All that meet spec
BRAZOSPORT PLASTICS, INC. requirements (10-16-08)
3 C4.20 LEVEL MEASUREMENT, FLUSH RINGS - FRP 1 0
(INSTRUMENTATION) SIL: Qualified for use in SIS
loops as Proven-in-use.
CRANE (PSI LINED PIPING All that meet spec
3 C4.20
SYSTEM) requirements
TRANSMITTER - SUBMERGE ELEMENT (POND) - LEVEL All that meet spec
4 C4.21 B AMETEK
MEASUREMENT requirements
TRANSMITTER, SERVO DISPLACER (CUSTODY TRANSFER / DELFT INSTRUMENTS 854 (10-15-08) SIL: DO
4 C4.22 B 1 0
ACCOUNTING) (ENRAF) NOT use in SIL
All that meet spec
4 C4.23 TRANSMITTER, CAPACITANCE (RADIO FREQUENCY) B AMETEK 1 0
requirements
Multicap DC 11, 12, 16 or
4 C4.23 ENDRESS+HAUSER 21 with FECC 12. CCeramic
11500 (10-15-08) SIL: DO
NOT use in SIL
4 C4.24 TRANSMITTER, LEVEL - RADAR B EMERSON RADAR 1 0 5400
Vegapuls 60, 68 Series (10-
4 C4.24 OHMART VEGA 15-08) SIL: Evaluated by
exida for use in SIS
FMR 230, FMR 231, FMR
240, FMR 244, FMR 245,
4 C4.24 ENDRESS + HAUSER FMR 250 (10-15-08) SIL:
Evaluated by Exida for use
in SIS
EMERSON PROCESS
TRANSMITTER, FREE SPACE RADAR (CUSTODY (10-15-08) SIL: DO NOT
4 C4.25 B MANAGEMENT (ROSEMOUNT 1 0
TRANSFER/ACCOUNTING) use in SIL
TANK GAUGING)
4 C4.25 ENDRESS + HAUSER Micropilot S
ENRAF TERMINAL
4 C4.25 SmartRadar series
AUTOMATION
Levelflex FMP 40, 41C, 45
TRANSMITTER, GUIDED WAVE RADAR (TDR) (PROCESS
4 C4.26 B ENDRESS + HAUSER 1 0 (10-15-08) SIL: Evaluated
CONTROL)
by Exida for use in SIS
Vegaflex 60 Series SIL:
4 C4.26 OHMART VEGA Evaluated by exida for use
in SIS
Elite Series. SIL: Not
4 C4.26 MAGNETROL INTERNATIONAL
approved for SIS
EMERSON PROCESS
4 C4.27 TRANSMITTER, INDUCTIVE / MAGNETOSTRICTIVE FLOAT B MANAGEMENT (FISHER 1 0 Fisher DL3
CONTROLS)
4 C4.27 K-TEK AT (Accutrak) Series
All that meet spec
4 C4.27 MAGNETROL requirements (10-14-08)
SIL: Evaluated by Exida for
use in SIS
FMU 41, FMU 43, FMU
4 C4.28 TRANSMITTER, ULTRASONIC B ENDRESS+HAUSER 1 0 860 with Sensors FDU 80 &
86 (10-15-08) SIL: DO NOT
use in SIL
4 C4.28 OHMART VEGA Vegason 51 - 56
All that meet spec
4 C4.29 TRANSMITTER, NUCLEAR B BERTHOLD 1 0
requirements
All that meet spec
4 C4.29 ENDRESS+HAUSER
requirements
All that meet spec
4 C4.29 OHMART VEGA
requirements
All that meet spec
4 C4.29 THERMO FISHER SCIENTIFIC
requirements
All that meet spec
4 C4.30 TRANSMITTER, LIQUID LEVEL; DISPLACER; B MAGNETROL INTERNATIONAL requirements (10-14-08)
SIL: DO NOT use in SIL
2 C5.0 MONITORING

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

Standardization -
GE ENERGY (BENTLY Category A, Bently
4 C5.1 MONITORING VIBRATION, TRANSMITTERS -NON-CRITICAL B Nevada is the 1 0
NEVADA)
selected PLA
Vendor
PC420V and PC420A
Series Loop Powered
Sensors. ("V" Series are
C5.1 WILCOXON RESEARCH velocity transmitters. "A"
series are accelerometers.
Typically velocity is used for
machine condition
monitoring )
LP202 (Velocity); LP302
(Acceleration); LP800
3 C5.1 CTC series (Intrinsically Safe
Velocity), LP900 series
(Intrinsically Safe
Acceleration)
MONITORING VIBRATION, MONITORING SYSTEMS - EMERSON PROCESS Standardization - All that meet spec
4 C5.2 E 2 2
CRITICAL MANAGEMENT Category A requirements
Standardization -
GE ENERGY (BENTLY Category A, Bently
4 C5.2 Nevada
e ada iss tthe
e Series 3500 monitors
NEVADA)
selected PLA
Vendor
All that meet spec
C5.2 ROCKWELL AUTOMATION
requirements
All that meet spec
C5.2 SKF CONDITION MONITORING
requirements
2 C6.0 PRESSURE MEASUREMENT
PRESSURE MEASUREMENT, DIAPHRAGM SEALS - DRESSER AL-RUSHAID VALVE All that meet spec
2 C6.1 B 1 0
PRESSURE AND VACUUM APPLICATIONS & INSTRUMENT requirements
All that meet spec
C6.1 DRESSER INC
requirements
EMERSON PROCESS 1199 with Rosemount
C6.1
MANAGEMENT (ROSEMOUNT) SEALS
All that meet spec
C6.1 WIKA
requirements
990.27 or 990.29 or 990.39
with WIKA SEALS; (5-19-
10) Yokogawa pressure
transmitters should not be
YOKOGAWA ELECTRIC used in vacuum services
C6.1 less than 200 mmHga
CORPORATION
when used with Wika
remote or direct seals, (10-
21-08) SIL: Qualified for
use in SIS loops as Proven-
in use
ARMATURENFABRIK FRANZ All that meet spec
2 C6.2 PRESSURE MEASUREMENT, MANIFOLDS B 1 0
SCHNEIDER requirements
All that meet spec
C6.2 OLIVER VALVES
requirements
All that meet spec
C6 2
C6.2 PARKER HANNIFIN
requirements
TYCO (ANDERSON All that meet spec
C6.2
GREENWOOD) requirements
All that meet spec
C6.2 VESTA PGI MANUFACTURING
requirements
All that meet spec
PRESSURE MEASUREMENT, INSTALLATION HARDWARE - ARMATURENFABRIK FRANZ requirements (10-20-08)
2 C6.3 B 1 0
TRANSMITTER / PRESSURE GAUGE SCHNEIDER SIL: Qualified for use in SIS
loops as Proven-in-use.
All that meet spec
COOPER CAMERON VALVES requirements (10-20-08)
C6.3
(TBV) SIL: Qualified for use in SIS
loops as Proven-in-use.
PRESSURE MEASUREMENT, CONTROLLER - LOCAL SELF All that meet spec
2 C6.4 B ABB INC 1 0
CONTAINED TYPE requirements
EMERSON PROCESS
All that meet spec
C6.4 MANAGEMENT (FISHER
requirements
CONTROLS)
YOKOGAWA ELECTRIC All that meet spec
C6.4
CORPORATION requirements
FRM (10-20-08) SIL:
ARMATURENFABRIK FRANZ
3 C6.5 FLUSH RINGS - METAL AND INSTALLATION HARDWARE B 1 0 Qualified for use in SIS
SCHNEIDER
loops as Proven-in-use.
FRM (10-20-08) SIL:
COOPER CAMERON VALVES
C6.5 Qualified for use in SIS
(TBV)
loops as Proven-in-use.
CRANE (PSI LINED PIPING All that meet spec
3 C6.6 FLUSH RINGS - LINED B
SYSTEM) care of EPSCO requirements
PFEIFFER CHEMIE- All that meet spec
3 C6.6
ARMATUREN GMBH requirements
(Equivalent to G6D-5201-
PRESSURE MEASUREMENT
MEASUREMENT, GAUGES - WITH & WITHOUT 00.)) ((10-21-08)) SIL: Not
3 C6.7 B ASHCROFT used in SIL loops.
SEAL AND INSTRUMENT AIR GAUGE
Compliance with SIS
requirements not needed.
Models: 232, 233, 111 (10-
C6.7 WIKA 21-08) SIL: Not used in SIL
loops. Compliance with SIS
requirements not needed
(10-21-08) SIL: Not used in
PRESSURE MEASUREMENT, GAUGES - HIGH PRESSURE SIL loops. Compliance with
2 C6.8 B ASHCROFT 1 0
(10 - 60 KSI) (AUTOCLAVE PROCESS CONNECTION) SIS requirements not
needed
All that meet spec
C6.8 WIKA MIDDLE EAST
requirements
PRESSURE MEASUREMENT, GAUGES - DRAFT RANGE (TO All that meet spec
2 C6.9 B AMETEK 1 0
2.5" H2O (0.5KPA)) requirements
All that meet spec
C6.9 ASHCROFT
requirements
(10-21-08) SIL: Not used in
C6.9 DWYER SIL loops. Compliance with
SIS requirements not
needed.

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

PRESSURE MEASUREMENT, GAUGES - DRAFT RANGE (> 2" All that meet spec
2 C6.10 B AMETEK 1 0
H2O (0.5KPA)) requirements
All that meet spec
C6.10 ASHCROFT
requirements
All that meet spec
C6.10 DWYER
requirements
GENERAL ELECTRIC (DRUCK- All that meet spec
2 C6.11 PRESSURE MEASUREMENT, GAUGES - TEST B 1 0
RUSKA) requirements
PRESSURE MEASUREMENT, GAUGES, DIFFERENTIAL All that meet spec
2 C6.12 B AMETEK 1 0
PRESSURE INDICATOR requirements
All that meet spec
C6.12 ASHCROFT
requirements
All that meet spec
C6.12 DWYER
requirements
All that meet spec
C6.12 WIKA
requirements
BARTON INSTRUMENT All that meet spec
2 C6.13 PRESSURE MEASUREMENT, SWITCH B 1 0
SYSTEMS requirements
All that meet spec
C6.13 CUSTOM CONTROL SENSORS
requirements
All that meet spec
C6.13 DRESSER INC
requirements
All that meet spec
C6 13
C6.13 MERCOID
requirements
All that meet spec
C6.13 SOR
requirements
All that meet spec
C6.13 UNITED ELECTRIC CONTROLS
requirements
All that meet spec
C6.13 WIKA
requirements
All that meet spec
C6.13 WIKA MIDDLE EAST
requirements
All that meet spec
BRAZOSPORT PLASTICS, INC. requirements (10-21-08)
3 C6.14 FLUSH RINGS - FRP 1 0
(INSTRUMENTATION) SIL: Qualified for use in SIS
loops as Proven-in-use.
BRAZOSPORT PLASTICS, INC. All that meet spec
4 C6.15 FLUSH RINGS - FIBERGLASS 1 0
(INSTRUMENTATION) requirements
PHEIFFER CHEMIE-
All that meet spec
4 C6.15 ARMATUREB GmbH (A Member
requirements
of the the Samson Group)

Standardization -
Category A,
TRANSMITTER, PRESSURE - PRESSURE AND EMERSON PROCESS
4 C6.16 B Rosemount is the 1 0 3051T or 3051C, 3051CD
DIFFERENTIAL PRESSURE MANAGEMENT (ROSEMOUNT)
selected PLA
Vendor
EJA 110AE, 120AE,
YOKOGAWA ELECTRIC 310AE, 430AE, 440AE and
4 C6.16 EJX 530AE, (10-21-08)
CORPORATION
SIL: Evaluated by Exida for
use in SIS
TRANSMITTER, FLOW - PRESSURE AND DIFFERENTIAL EMERSON PROCESS Standardization -
4 C6 17
C6.17 B 1 0 3051CD
PRESSURE MANAGEMENT (ROSEMOUNT) Category B
YOKOGAWA ELECTRIC
4 C6.17 EJA 110AE, 120AE
CORPORATION
TRANSMITTER, ABSOLUTE OR GAUGE - EXTRUDER MELT Selection requires Owner
4 C6.18 B DYNISCO 1 0
(PLASTICS) approval.
3051C or 3051T with 1199
EMERSON PROCESS Standardization - Rosemount Seals (10-14-
4 C6.19 TRANSMITTER, REMOTE OR DIRECT MOUNT SEAL SYSTEM B 1 0
MANAGEMENT (ROSEMOUNT) Category B 08) SIL: Evaluated by Exida
for use in SIS
EJA 110AE with 990.27 or
YOKOGAWA ELECTRIC 990.29 or 990.39 with
4 C6.19 WIKA Seals (10-14-08)
CORPORATION
SIL: Evaluated by Exida for
use in SIS
2 C7.0 SYSTEMS
3 C7.1 NOT USED E
3 C7.2 NOT USED B
3 C7.3 NOT USED B
SYSTEM, CONTROL ROOM EQUIPMENT - CONSOLES All that meet spec
2 C7.4 B HIMA 1 0
COMPONENTS (SWITCHES) requirements
All that meet spec
C7.4 HONEYWELL
requirements
ROCKWELL AUTOMATION All that meet spec
C7.4
(ALLEN BRADLEY) requirements
All that meet spec
2 C7.4 TRICONEX
requirements
SYSTEM, CONTROL ROOM EQUIPMENT - SMALL AMETEK (ROCHESTER
2 C7.5 B 1 0
ANNUNCIATOR PANELS INSTRUMENT)

C7.5 HIMA
All that meet spec
C7.5 RONAN ENGINEERING
requirements
C7.5 RTK ENGINEERING

C7.5 TRICONEX
3 C7.6 NOT USED B
3 C7.7 NOT USED E
3 C7.8 NOT USED B
3 C7.9 NOT USED B
3 C7.10 NOT USED B
All that meet spec
2 C7.11 SPEED SYSTEMS, NON-CRITICAL (TACHOMETER) B AIRPAX HOLDINGS 1 0
requirements
GE ENERGY (BENTLY All that meet spec
C7.11
NEVADA) requirements
All that meet spec
C7.11 IRD UK
requirements
All that meet spec
C7.11 PEPPERL+FUCHS GMBH
requirements
All that meet spec
C7.11 ROCKWELL AUTOMATION
requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

2 C8.0 TEMPERATURE MEASUREMENT


All specified in G6D-7000-
TEMPERATURE MEASUREMENT, RESISTANCE xx series. 10-22-08 SIL:
2 C8.1 B ABB INC 1 0
TEMPERATURE DEVICES (RTDs) Qualified for use in SIS
loops as Proven-in-use.
All specified in G6D-7000-
EMERSON PROCESS xx series. 10-22-08 SIL:
C8.1
MANAGEMENT Qualified for use in SIS
loops as Proven-inuse.
All specified in G6D-7000-
xx series. 10-22-08 SIL:
C8.1 WIKA
Qualified for use in SIS
loops as Proven-in-use.
All specified in G6D-7000-
xx series. 10-22-08 SIL:
2 C8.2 TEMPERATURE MEASUREMENT, THERMOCOUPLES (T/Cs) B ABB INC 1 0
Qualified for use in SIS
loops as Proven-in-use.
All specified in G6D-7000-
EMERSON PROCESS xx series. 10-22-08 SIL:
C8.2
MANAGEMENT Qualified for use in SIS
loops as Proven-in-use.
MegopaK; Must comply
C8.2 HONEYWELL
with G6D-7100-02.
Must complyp y with G6D-
C8 2
C8.2 THERMO ELECTRIC
7100-02.
All specified in G6D-7000-
xx series. 10-22-08 SIL:
C8.2 WIKA
Qualified for use in SIS
loops as Proven-in-use.
All specified in G6D-7000-
2 C8.3 TEMPERATURE MEASUREMENT, THERMOWELLS B ABB INC 1 0 xx series. 10-22-08 SIL:
Qualified for use in SIS
loops as Proven-in-use.
All specified in G6D-7000-
EMERSON PROCESS xx series. 10-22-08 SIL:
C8.3
MANAGEMENT Qualified for use in SIS
loops as Proven-in-use.
All specified in G6D-7000-
C8.3 WIKA xx series. 10-22-08 SIL:
Qualified for use in SIS
loops as Proven-in-use.
All that meet spec
2 C8.4 TEMPERATURE MEASUREMENT, SWITCHES B CUSTOM CONTROL SENSORS 1 0
requirements
All that meet spec
C8.4 BARTON INSTRUMENTS
requirements
All that meet spec
C8.4 DRESSER INC (ASHCROFT)
requirements
All that meet spec
C8.4 MERICOID CORP
requirements
All that meet spec
C8.4 SOR
requirements
All that meet spec
C8.4 UNITED ELECTRIC
requirements
All that meet spec
C8.4 WIKA
requirements
All that meet spec
C8.4 WIKA MIDDLE EAST
requirements
TEMPERATURE MANAGEMENT, INDICATOR TEMPERATURE All that meet spec
2 C8.5 B ABB INC 1 0
- BIMETALLIC AND EXPANSION TYPES requirements
All that meet spec
C8.5 AMETEK (US GAUGE)
requirements
DRESSER AL-RUSHAID VALVE All that meet spec
C8.5
& INSTRUMENTATION requirements
All that meet spec
C8.5 DRESSER INC
requirements
All that meet spec
C8.5 RUEGER SA
requirements
All that meet spec
C8.5 WIKA
requirements
TH02, 10-22-08 SIL:
TEMPERATURE TRANSMITTER, ELECTRONIC - FIELD Standardization -
4 C8.6 B ABB INC 1 0 Evaluated by Exida for use
MOUNTED - STANDARD ACCURACY Category A
in SIS
Standardization -
Fieldbus: 644, 4-20mA: 248
Category A,
EMERSON PROCESS (10-22-08) SIL: 248
4 C8.6 Rosemount is the
MANAGEMENT (ROSEMOUNT) evaluated by Exida for use
selected PLA
in SIS
Vendor
T31-11, 10-22-08 SIL:
4 C8.6 WIKA Evaluated by Exida for use
in SIS
TH202, 10-22-08 SIL:
TEMPERATURE TRANSMITTER - ELECTRONIC - FIELD Standardization -
4 C8.7 B ABB INC 1 0 Evaluated by Exida for use
MOUNTED - HIGH PRECISION Category A
in SIS
Standardization -
Category A,
EMERSON PROCESS
4 C8.7 Rosemount is the 3144
MANAGEMENT
selected PLA
Vendor
4 C8.7 WIKA T53.10
TH202, 10-22-08 SIL:
TEMPERATURE TRANSMITTER - ELECTRONIC -
4 C8.8 B ABB INC 1 0 Evaluated by Exida for use
DIFFERENTIAL
in SIS
EMERSON PROCESS
4 C8.8 3144P
MANAGEMENT (ROSEMOUNT)

2 C9.0 TRANSMITTERS
4 C9.1 NOT USED B
4 C9.2 NOT USED B
4 C9.3 NOT USED B

4 C9.4 NOT USED B

4 C9.5 NOT USED B

4 C9.6 NOT USED B


4 C9.7 NOT USED B

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

4 C9.8 NOT USED B


4 C9.9 NOT USED B
TRANSMITTER, SUBMERGE ELEMENT (DEEP WELL All that meet spec
2 C9.10 B NOT ANTICIPATED FOR RTIP - NOT TECNOLOGY SPECIFIC ABB INC 1 0
INSERTION PROBE) requirements
4 C9.11 NOT USED B
4 C9.12 NOT USED B
4 C9.13 NOT USED B

4 C9.14 NOT USED B

4 C9.15 NOT USED B

4 C9.16 NOT USED B

4 C9.17 NOT USED B


4 C9.18 NOT USED B

4 C9.19 NOT USED B

EMERSON PROCESS All that meet spec


2 C9.20 TRANSMITTER, MULTIVARIABLE B 1 0
MANAGEMENT requirements
All that meet spec
C9.20 HONEYWELL
requirements
YOKOGAWA ELECTRIC KOFU All that meet spec
C9.20
PLANT requirements
Standardization -
Category A,
TRANSMITTER, LEVEL / FLOW / PRESSURE - INSTALLATION ARMATURENFABRIK FRANZ Armaturenfabrik All that meet spec
4 C9.21 B 1 0
TBV KITS SCHNEIDER GmbH Franz Schneider is requirements
the selected PLA
Vendor
COOPER CAMERON VALVES All that meet spec
C9.21
(TBV) requirements
2 C10.0 VALVES
VALVE, CONTROL, SEVERE SERVICE, HIGH PRESSURE CONTROL COMPONENTS (CCI Standardization - Drag Series (CCI) BTG
C10.1 E 3 3
AND HIGH PRESSURE DROP & BTG) Category B models
All that meet spec
C10.1 DRESSER MASONEILAN requirements. Owner must
approve 77000 series.
EMERSON PROCESS
Easy E Series, HP;
C10.1 MANAGEMENT (FISHER
Whisperflo for gas only
CONTROLS)
C10.1 FLOWSERVE Mark I & II
Globe: 21000, 41000;
Standardization -
4 C10.2 VALVE, CONTROL, LINEAR MOTION (GLOBE/ANGLE) B DRESSER MASONEILAN 2 1 Adjustable CV: 28000
Category A
Varipak
Standardization -
EMERSON PROCESS Category A, Fisher Globe: E Series; Miniature:
4 C10.2 MANAGEMENT (FISHER Controls is the Fisher Baumann 24000,
CONTROLS) selected PLA 51000 Series
Vendor
FLOWSERVE (VALTEK & Globe: Mark I; Miniature:
C10.2
KAMMER) 800000 185000 Series
800000,
EMERSON PROCESS
3 C10.3 VALVE, CONTROL, LINEAR MOTION, LINED PTFE/PFA B MANAGEMENT (FISHER 2 1 RSS
CONTROLS)
PFEIFFER CHEMIE
C10.3 MODEL - 1A/Model 1b
ARMATUREN
Standardization - Type A&KB with actuator
2 C10.4 VALVES, CONTROL, PINCH TYPE/DIAPHRAGM B CRANE (SAUNDERS) 2 1
Category B type ES
C10.4 LAROX PVE Series
C10.4 RED VALVE 5200
All that meet spec
3 C10.5 VALVES, CONTROL, ROTARY, BALL B DRESSER MASONEILAN 2 1
requirements
EMERSON PROCESS
V-260C, V-260B, V-
C10.5 MANAGEMENT (FISHER
260A+Attenuator
CONTROLS)
All that meet spec
C10.5 FLOWSERVE
requirements
D, QLM, QD, T25, T4/T5,
3 C10.5 METSO AUTOMATION
QT5/QT4
3 C10.6 VALVE, CONTROL, ROTARY, BALL, CERAMIC BALL B DRESSER NILCOR 2 1 300ZL
EMERSON PROCESS
4 C10.6 MANAGEMENT (FISHER V150S, V500
CONTROLS)

C10.6 METSO AUTOMATION E2 / E6 Series

Standardization - All that meet spec


4 C10.7 VALVE, CONTROL, ROTARY, SEGMENT BALL B DRESSER MASONEILAN 2 1
Category A requirements
Standardization -
EMERSON PROCESS Category A, Fisher
V-150, V-250, V-300, CV-
4 C10.7 MANAGEMENT (FISHER Controls is the
500, V300+Attenuator
CONTROLS) selected PLA
Vendor
All that meet spec
C10.7 FLOWSERVE
requirements
C10.7 METSO AUTOMATION R21 Series , QR21 Series
All that meet spec
3 C10.8 VALVE, CONTROL, ROTARY, BUTTERFLY B DRESSER MASONEILAN 2 1
requirements
EMERSON PROCESS
C10.8 MANAGEMENT (FISHER 8560/ 8532
CONTROLS)
All that meet spec
C10.8 FLOWSERVE
requirements
C10.8 METSO AUTOMATION L2, L6, SL2, SL6 Series
C10.8 TYCO (VANESSA) 32500, 33000 Series
VALVE, CONTROL, ROTARY, BUTTERFLY, LINED (RUBBER, All that meet spec
3 C10.9 B AMRI 2 1
PTFE/PFA) requirements
ENPRO INDUSTRIES 100L (Lugged), 100F
C10.9
(GARLOCK) (Flanged)
PFEIFFER CHEMIE
C10.9 10A
ARMATUREN
C10.9 TYCO (KEYSTONE) Fig. 16-17
3 C10.10 VALVE, CONTROL, ROTARY, ECCENTRIC PLUG/GLOBE B DRESSER MASONEILAN 2 1 Camflex II ; 35000

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

EMERSON PROCESS
All that meet spec
C10.10 MANAGEMENT (FISHER
requirements
CONTROLS)
All that meet spec
C10.10 FLOWSERVE
requirements
FC/FG Finetrol, QAFI/QFI
C10.10 METSO AUTOMATION
Series, FC/FG-Q
3 C10.11 VALVE, CONTROL, ROTARY, ECCENTRIC PLUG, LINED B DRESSER MASONEILAN 2 1 31000 Lined
EMERSON PROCESS
All that meet spec
C10.11 MANAGEMENT (FISHER
requirements
CONTROLS)
All that meet spec
C10.11 FLOWSERVE
requirements
Standardization -
2 C10.12 VALVE, CONTROL, ROTARY, PLUG B CRANE (XOMO TUFLINE) 2 1 067, 0367
Category B
All that meet spec
C10.12 DRESSER MASONEILAN
requirements
EMERSON PROCESS
All that meet spec
C10.12 MANAGEMENT (FISHER
requirements
CONTROLS)
G4 with standard on-off
C10.12 FLOWSERVE (DURCO)
port, EG4 V-port
Standardization -
2 C10.13 VALVE, CONTROL, ROTARY, PLUG LINED B CRANE (XOMO TUFLINE) 2 1 061, 0361
Category
g yB
All that meet spec
C10.13 DRESSER MASONEILAN
requirements
EMERSON PROCESS
All that meet spec
C10.13 MANAGEMENT (FISHER
requirements
CONTROLS)
T4 with standard on-off
C10.13 FLOWSERVE (DURCO)
port, ET4 V-port
2 C10.14 VALVE, BLOCK & BLEED COMBINATION B FLOWSERVE (MCCANNA) 2 1 See appropriate pipe spec
C10.14 KUEHME ARMATUREN KVH / F
CONTROL COMPONENTS (CCI All that meet spec
2 C10.15 VALVE, DESUPERHEATER B 2 1
& BTG) requirements
C10.15 DRESSER MASONEILAN 84000 SteamForm
EMERSON PROCESS
CONTEK: All that meet
C10.15 MANAGEMENT (FISHER
spec requirements.
CONTROLS)
Standardization - 92/692, 50/650; Must
2 C10.16 VALVE, REGULATOR, PRESSURE, BACK PRESSURE B CLA-VAL COMPANY 1 0
Category B comply with G6C-8051-00.
170, 173, 174, 500, 526;
C10.16 DRESSER ITALIA SPA Must comply with G6C-
8051-00.
170, 173, 174, 500, 526;
C10.16 DRESSER MASONEILAN Must comply with G6C-
8051-00.
Instr. Air: 399A / 627 /67
CFR / 98 / 64; Natural Gas:
EMERSON PROCESS 1098H-EGR (up to 6") and
C10.16 MANAGEMENT (FISHER 95 (up to 2"); Nitrogen:
CONTROLS) 399A-161 / 627 / Y690 / 98/
64; Process Fluids:
95/1301/925; Steam: 95
L08,L45,L50; Must comply
C10.16 THOMPSON VALVES
with G6C-8051-00.
170 171
170, 171, 172
172, 174
174, 500
500,
Standardization -
2 C10.17 VALVE, REGULATOR, PRESSURE, PRESSURE REDUCING B DRESSER MASONEILAN 1 0 525; Must comply with G6C-
Category B
8051-00.
Instr. Air: 399A / 627 /67
CFR / 98 / 64; Natural Gas:
EMERSON PROCESS 1098H-EGR (up to 6") and
C10.17 MANAGEMENT (FISHER 95 (up to 2"); Nitrogen:
CONTROLS) 399A-161 / 627 / Y690 / 98/
64; Process Fluids:
95/1301/925; Steam: 95
170, 171, 172, 174, 500,
Standardization -
2 C10.18 VALVE, REGULATOR, PRESSURE OR FLOW B DRESSER AL-RUSHAID VALVE 1 0 525; Must comply with G6C-
Category B
8051-00.
170, 171, 172, 174, 500,
MASONEILAN DIVISION
C10.18 525; Must comply with G6C-
DRESSER IND
8051-00.
Instr. Air: 399A / 627 /67
CFR / 98 / 64; Natural Gas:
1098H-EGR (up to 6") and
C10.18 FISHER CONTROLS 95 (up to 2"); Nitrogen:
399A-161 / 627 / Y690 / 98/
64; Process Fluids:
95/1301/925; Steam: 95
Instr. Air: 399A / 627 /67
CFR / 98 / 64; Natural Gas:
1098H-EGR (up to 6") and
C10.18 FISHER PROCESS SRL 95 (up to 2"); Nitrogen:
399A-161 / 627 / Y690 / 98/
64; Process Fluids:
95/1301/925; Steam: 95
EMERSON PROCESS
Standardization -
2 C10.19 VALVE, REGULATOR, TANK BLANKETING B MANAGEMENT (FISHER 1 0 Fisher Ace Models: 95 / 97
Category B
CONTROLS)
TYCO (ANDERSON
C10.19 GREENWOOD Type RA, BV-1, Y1
INSTRUMENTATION)
C10.19 VALVE CONCEPTS 1078 / 1088
Standardization -
3 C10.20 VALVE, REGULATOR, BACK FLOW PROTECTION B SAMSON AG 1 0 42-20
Category B
EMERSON PROCESS Standardization - See "EMETL# G6D-8404-
2 C10.21 VALVE, SOLENOID, AIR SUPPLY SWITCHING B 1 0
MANAGEMENT (ASCO) Category D xx Series"
PARKER (FLUID CONTROL See EMETL practice G6D-
C10.21
DIVISION) 8401-02
VALVE, SOLENOID, REDUNDANT COIL, AIR SUPPLY EMERSON PROCESS Standardization - See "EMETL# G6D-8405-
2 C10.22 B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE 1 0
SWITCHING MANAGEMENT (ASCO) Category D xx Series"
VALVE, SOLENOID, NON-PNEUMATIC APPLICATIONS EMERSON PROCESS Standardization - All that meet spec
2 C10.23 B 1 0
(PROCESS APPLICATIONS) MANAGEMENT (ASCO) Category D requirements
All that meet spec
C10.23 NORGREN (HERION)
requirements
PARKER (FLUID CONTROL All that meet spec
C10.23
DIVISION) requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

VALVE, SOLENOID, IN-LINE BLOCKING SOLENOIDS - TURBO Standardization -


2 C10.24 B MUELLER 1 0 MK20 Series
MACHINERY PROTECTION Category D
2 C10.25 VALVE, ACTUATOR, ELECTRICAL ON/OFF E.I.M. COMPANY 1 0 TEC2000
C10.25 LIMITORQUE MX
C10.25 ROTORK CONTROLS IQ Series II
2 C10.26 VALVE, ACTUATOR, ELECTRICAL CONTROL B E.I.M. COMPANY 1 0 TEC2000
C10.26 LIMITORQUE MX
C10.26 ROTORK CONTROLS IQM series II
All that meet spec
2 C10.27 VALVE, ACTUATOR, ELECTRICAL FAIL SAFE B BIFFI ITALIA SRL 1 0
requirements
All that meet spec
C10.27 CAMERON WILLIS
requirements
All that meet spec
C10.27 ROTORK CONTROLS
requirements
All that meet spec
2 C10.28 VALVE, ACTUATOR, HYDRAULIC & ELECTRICAL ROTARY B BIFFI ITALIA SRL 1 0
requirements
All that meet spec
C10.28 CAMERON ITALY SRL
requirements
EMERSON PROCESS All that meet spec
C10.28
MANAGEMENT (BETTIS) requirements
All that meet spec
C10 28
C10.28 EPM BETTIS FRANCE
requirements
All that meet spec
C10.28 KOSO AMERICA
requirements
All that meet spec
C10.28 ROTORK CONTROLS
requirements
All that meet spec
C10.28 ROTORK FLUID SYSTEM SRL
requirements
All that meet spec
C10.28 SHAFER VALVE COMPANY
requirements
All that meet spec
C10.28 VALVITALIA SPA
requirements
Standardization -
4 C10.29 VALVE, ACTUATOR, PNEUMATIC, RACK & PINION B AIR TORQUE 1 0 PT series
Category A
Standardization -
Category A,
EMERSON PROCESS Emerson E12 to E1600 & P2500-
4 C10.29
MANAGEMENT (EL-O-MATIC) (Elomatic) is the P4000
selected PLA
Vendor
Standardization -
Category A,
EMERSON PROCESS
4 C10.29 Emerson (Hytork) XL Series
MANAGEMENT (HYTORK)
is the selected
PLA Vendor
EMERSON PROCESS
2 C10.30 VALVE, ACTUATOR, PNEUMATIC, SCOTCH YOKE B 1 0 G Series
MANAGEMENT (BETTIS)
EMERSON PROCESS
All that meet spec
C10.30 MANAGEMENT (SHAFER
requirements
VALVE COMPANY)
All that meet spec
C10.30 METSO AUTOMATION
requirements
All that meet spec
C10.30 ROTORK CONTROLS
requirements
Series ALGA ALGA S Fig.
C10.30 TYCO (BIFFI)
79 A
All that meet spec
2 C10.31 VALVE, ACTUATOR, PNEUMATIC, DIAPHRAGM LINEAR B BIFFI ITALIA SRL 1 0
requirements
COOPER CAMERON VALVES All that meet spec
C10.31
ITALY SRL requirements
C10.31 DRESSER MASONEILAN Series 87/88
EMERSON PROCESS
C10.31 MANAGEMENT (FISHER Series 657/667
CONTROLS)
EMERSON PROCESS All that meet spec
C10.31
MANAGEMENT (BETTIS) requirements
EMERSON PROCESS
All that meet spec
C10.31 MANAGEMENT (SHAFER
requirements
VALVE COMPANY)
All that meet spec
C10.31 EPM BETTIS FRANCE
requirements
All that meet spec
C10.31 METSO AUTOMATION
requirements
All that meet spec
C10.31 ROTORK CONTROLS
requirements
All that meet spec
C10.31 ROTORK FLUID SYSTEM SRL
requirements
All that meet spec
C10.31 SAMSON
requirements
All that meet spec
C10.31 VALVITALIA SPA
requirements
All that meet spec
2 C10.32 VALVE.ACTUATOR, PNEUMATIC, DIAPHRAGM ROTARY B BIFFI ITALIA SRL 1 0
requirements
All that meet spec
C10.32 CAMERON ITALY SRL
requirements
Series 33 (diaphragm)
C10.32 DRESSER MASONEILAN Series 35 (rolling
diaphragm)
EMERSON PROCESS All that meet spec
C10.32
MANAGEMENT (BETTIS) requirements
EMERSON PROCESS
C10.32 MANAGEMENT (FISHER Series 1051/1052
CONTROLS)
EMERSON PROCESS
All that meet spec
C10.32 MANAGEMENT (SHAFER
requirements
VALVE COMPANY)
All that meet spec
C10.32 EPM BETTIS FRANCE
requirements
Quadra-Powr (rolling
C10.32 METSO AUTOMATION
diaphragm) Series QP
All that meet spec
C10.32 PFEIFFER
requirements
All that meet spec
C10.32 ROTORK CONTROLS
requirements

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

All that meet spec


C10.32 VALVITALIA SPA
requirements
All that meet spec
2 C10.33 VALVE, ACTUATOR, PNEUMATIC, PISTON LINEAR B BIFFI ITALIA SRL 1 0
requirements
COOPER CAMERON VALVES All that meet spec
C10.33
ITALY SRL requirements
DRESSER PRODUITS All that meet spec
C10.33
INDUSTRIELS requirements
EMERSON PROCESS
C10.33 Series GVO
MANAGEMENT (BETTIS)
All that meet spec
C10.33 FLOWSERVE
requirements
FLOWSERVE (VALTEK /
C10.33 Square 25 to 600 Inch
KAMMER)
All that meet spec
C10.33 ROTORK CONTROLS
requirements
SPX CORPORATION
C10.33 CY-PC
(DEZURIK)
All that meet spec
2 C10.34 VALVE, ACTUATOR, PNEUMATIC, PISTON ROTARY B BIFFI ITALIA SRL 1 0
requirements
COOPER CAMERON VALVES All that meet spec
C10.34
ITALY SRL requirements
DRESSER PRODUITS All that meet spec
p
C10 34
C10.34
INDUSTRIELS requirements
EMERSON PROCESS All that meet spec
C10.34
MANAGEMENT (BETTIS) requirements
EMERSON PROCESS
All that meet spec
C10.34 MANAGEMENT (SHAFER
requirements
VALVE COMPANY)
All that meet spec
C10.34 FLOWSERVE
requirements
All that meet spec
C10.34 METSO AUTOMATION
requirements
All that meet spec
C10.34 ROTORK CONTROLS
requirements
All that meet spec
C10.34 VALVITALIA SPA
requirements
EMERSON PROCESS RV Series. Not preferred
2 C10.35 VALVE, ACTUATOR, PNEUMATIC, VANE B MANAGEMENT (SHAFER 1 0 for valve automation.
VALVE COMPANY) Requires Owner approval.
Model 01 to Model 20;
Restricted Use to be used
C10.35 KINETROL only for high cycling
applications (greater than 1
cycle per minute)
Series 167 Series LS124D
Series LS205D Series
2 C10.36 VALVE, ACTUATOR, PNEUMATIC, ROTARY/RISING STEM B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE ORBIT 1 0 LS269D; Restricted Use to
be used only with Orbit ball
valves with linear stem
travel
EMERSON PROCESS
VALVE, SMART CONTROLLER ESD (SIS) SERVICE - PARTIAL
2 C10.37 B MANAGEMENT (FISHER 2 0 DVC6000_ESD
STROKE TEST DEVICES
CONTROLS)
C10.37 METSO AUTOMATION VG800 series
Standardi ation -
Standardization All that meet spec
3 C10.38 VALVES, PIPING, RELIEF B CONTROL COMPONENTS 2 2
Category B requirements
All that meet spec
2 C10.38 M&J VALVE OPERATIONS
requirements
MACHINEFABRIEK MOKVELD All that meet spec
2 C10.38
BV requirements
MOTOYAMA ENGINEERING All that meet spec
2 C10.38
WORKS requirements
All that meet spec
2 C10.38 NAKAKITA SEISAKUSHO
requirements
All that meet spec
2 C10.38 SAFETY SYSTEMS
requirements
TYCO FLOW CONTROL Standardization - All that meet spec
4 C10.39 VALVES, PIPING, PILOT OPERATED RELIEF B 2 2
(ANDERSON GREENWOOD) Category A requirements
*NOTE - TYCO KTM PLANT
2 C10.39
NOT ACCEPTABLE
Standardization -
Category A,
DRESSER AL-RUSHAID VALVE Dresser Al- All that meet spec
4 C10.39
& INSTRUMENT CO Rushaid is the requirements
selected PLA
Vendor
All that meet spec
3 C10.39 DRESSER, INC.
requirements
Standardization - All that meet spec
4 C10.40 VALVES, PIPING, SPRING OPERATED RELIEF B DRESSER CONSOLIDATED 2 2
Category A requirements
All that meet spec
2 C10.40 LESLER GMBH & CO KG
requirements
TYCO FLOW CONTROL All that meet spec
2 C10.40
(ANDERSON GREENWOOD) requirements
TYCO FLOW CONTROL All that meet spec
2 C10.40
(CROSBY) requirements
TYCO FLOW CONTROL All that meet spec
2 C10.40
(SAPAGE) requirements
TYCO FLOW CONTROL All that meet spec
2 C10.40
(SEMPELL) requirements
*NOTE - TYCO KTM PLANT
2 C10.40
NOT ACCEPTABLE
All that meet spec
3 C10.40 DRESSER
requirements
All that meet spec
3 C10.40 LESER GMBH & CO
requirements
Standardization -
Category A,
DRESSER AL-RUSHAID VALVE Dresser Al- All that meet spec
4 C10.40
& INSTRUMENT CO Rushaid is the requirements
selected PLA
Vendor
TYCO FLOW CONTROL All that meet spec
2 C10.41 VALVES, PIPING, TRANSFLO RELIEF DEVICES B 2 2
(ANDERSON GREENWOOD) requirements
*NOTE - TYCO KTM PLANT
2 C10.41
NOT ACCEPTABLE

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

21000, 41000, Varipak


3 C10.42 VALVE, CONTROL, LINEAR MOTION, BELLOWS SEAL DRESSER MASONEILAN 1 1
(28000)
EMERSON PROCESS
3 C10.42 MANAGEMENT (FISHER E Series
CONTROLS)
Mark I shroudless,
Guardian 2; Note:
FLOWSERVE (VALTEK & KAMMER TECHNOLOGY
3 C10.42 PREFERRED OVER
KAMMER)
VALTEK TECHNOLOGY.
USE KAMMER WHERE
AVAILABLE
EMERSON PROCESS
VALVE, CONTROL, ROTARY, SEGMENT BALL, CERAMIC
3 C10.43 MANAGEMENT (FISHER 1 1 V-150/V-300 Micronotch
BALL
CONTROLS)
3 C10.44 VALVES, POSITION SWITCHES FLOWSERVE (ACCORD) 1 0 Phazer II BRS
3 C10.45 VALVES, POSITION TRANSMITTER - ROTARY FLOWSERVE (PMV) 1 0 F5
TYCO (WESTLOCK
3 C10.45 9479 DT, 420
CONTROLS CORPORATION)
EP-5 Series with Namur
VALVES, POSITIONERS, FOR RACK AND PINION
3 C10.46 FLOWSERVE (PMV) 1 0 shaft; with VDI/VDE 3845
ACTUATORS
shaft design
EMERSON PROCESS
Fieldbus: DVC6000f-AD; 4-
3 C10.47 VALVES, POSITIONERS MANAGEMENT ((FISHER 1 0
20mA: DVC6000 AD
DVC6000-AD
CONTROLS)
Fieldbus: 3731-5; 4-20mA:
3731-3 (use Samson
3 C10.47 SAMSON positioners for valves by
Samson, Pfeiffer, Kammer,
and non-specified control
valve packages)
Fieldbus: ND9000 series; 4-
3 C10.47 METSO 20mA: ND9000 series (Use
ND9000 series for Metso
rotary valves only)
MASONEILAN DIVISION Fieldbus: FVP; 4-20mA:
3 C10.47
DRESSER IND SVI-IIAP-2
FLOWSERVE (VALTEK & Fieldbus: Logix 3400 series;
3 C10.47
KAMMER) 4-20mA: Logix 3210MD-AD
3 C10.48 VALVES, PART TURN LOCK OUT DEVICES - MECHANICAL DYNATORQUE, INC. 1 0 D-Lock
Automax LOM (not suitable
3 C10.48 FLOWSERVE
for torque-seated valves)
2 C11.0 MISC. INSTRUMENTS
All that meet spec
2 C11.1 INSTRUMENT WIRE AND CABLE B BELDEN WIRE & CABLE 1 0
requirements
All that meet spec
C11.1 DEKORON WIRE & CABLE
requirements
All that meet spec
C11.1 KERPENWERK GMBH AND CO
requirements
MIDDLE EAST SPECIALIZED All that meet spec
C11.1
CABLES requirements
All that meet spec
C11.1 OKAZAKI MANUFACTURING
requirements
All that meet spec
C11.1 SAUDI CABLE COMPANY
requirements
All that meet spec
C11.1 THE OKONITE COMPANY
requirements
All that meet spec
C11.2 WEIGH CELLS FOR ADDITIVE FEEDER SYSTEMS B K-TRON 1 0
requirements
METTLER - TOLEDO All that meet spec
2 C11.3 PLATFORM SCALES FOR PACKAGING B 1 0
(MASSTRON) requirements
All that meet spec
C11.3 VELCON
requirements
ELECTRONIC INTERFACE COMPONENTS, COMMUNICATOR, EMERSON PROCESS
2 C11.4 B 1 0 375
HAND HELD MANAGEMENT
C11.4 FOXBORO HT991
SFC Smart Field
C11.4 HONEYWELL
Communicator
YOKOGAWA CORPORATION YHC4150X (HART); BT200
C11.4
OF AMERICA (BRAIN)
3 C11.4 BEAMEX MC5 Fieldbus
3 C11.4 ENDRESS+HAUSER Field Xpert
ELECTRONIC INTERFACE COMPONENTS, CALIBRATOR, All that meet spec
2 C11.5 B DAVIS INSTRUMENTS (FLUKE) 1 0
HAND HELD requirements
MERIAM PROCESS
C11.5 MFT
TECHNOLOGIES
All that meet spec
C11.5 OMEGA
requirements
3 C11.5 BEAMEX MC5 Fieldbus
ELECTRONIC INTERFACE COMPONENT CONTROLLER; All that meet spec
2 C11.6 B ARCOM CONTROL SYSTEMS 1 0
ELECTRONIC; SUPERVISORY COTR requirements
All that meet spec
C11.6 CEGELEC GMBH & CO KG
requirements
FOXBORO COMPANY All that meet spec
C11.6
(INVENSYS) requirements
All that meet spec
C11.6
C11 6 HONEYWELL
requirements
All that meet spec
C11.6 INVENSYS MIDDLE EAST FZE
requirements
REMOTE AUTOMATION All that meet spec
C11.6
SOLUTIONS requirements
All that meet spec
C11.6 SIEMENS AG - A&D I&S
requirements
All that meet spec
C11.6 TELVENT
requirements
YOKOGAWA CORPORATION All that meet spec
C11.6
OF AMERICA requirements
YOKOGAWA SYSTEMS All that meet spec
C11.6
CENTER EUROPE B.V. requirements
2 C11.7 FOUNDATION FIELDBUS, POWER SUPPLIES B MTL/RELCOM 1 0 See G6C-910-01
All that meet spec
C11.7 PEPPERL & FUCHS
requirements
Standardization -
3 C11.8 FOUNDATION FIELDBUS, WIRING BLOCKS B MTL/RELCOM 1 0 FCS-MB*-SG
Category D

C11.8 PEPPERL & FUCHS R2-SP-N**

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Instrumentation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
Tag Number / Estimate 1000 Purchasing Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision PAVL CODE Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Expediting Level Inspection Level Transportation Time Level Planned PO Date Field Need Date Special Considerations
Suffix US$ Strategy Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

FOUNDATION FIELDBUS, MULTI-INPUT TEMPERATURE EMERSON PROCESS


2 C11.9 B 1 0 848T
TRANSMITTER MANAGEMENT (ROSEMOUNT)
C11.9 MTL/RELCOM 9331-TI
C11.9 PEPPERL & FUCHS *-TI-Ex8.FF.*
3 C11.10 WEIGH CELLS / SYSTEMS FOR PROCESS VESSELS HBM (HOTTINGER) 1 0 C2 and C16
METTLER - TOLEDO All that meet spec
3 C11.10 (INSTRUMENTATION) requirements
All that meet spec
VISHAY (BLH)
3 C11.10 requirements
All that meet spec
SWITCHES, PROXIMITY SWITCH CUSTOM SWITCH 1 0
3 C11.11 requirements
All that meet spec
PEPPERL+FUCHS GMBH
3 C11.11 requirements
WIRING, SIL RATED REPEATER POWER SUPPLY (SIGNAL MTL INSTRUMENTS GROUP
1 0 MTLx544D
3 C11.12 SPLITTER) PLC
3 C11.12 PEPPERL+FUCHS GMBH KFD2-STC4
3 C11.13 FLAME IGNITORS - BURNER MANAGEMENT FORNEY CORPORATION 1 0 Series 90
Durag DLX200-XXX-10/30;
D-LX 100<; D-LE 600; D-
DURAG GMBH UG 660; For SIL
1 0
(INSTRUMENTATION) applications, only Durag
3 C11.14 FLAME SCANNERS - BURNER MANAGEMENT and Fireye are approved

951IR / 95UV / 95DS; For


FIREYE, INC. SIL applications, only Durag
3 C11.14 and Fireye are approved
BABCO EPS - All that meet spec
X, Y OR Z PURGE UNITS 1 0
3 C11.15 PEPPERL=FUCHS, INC. requirements
All that meet spec
SITEK
3 C11.15 requirements
All that meet spec
3 C11.16 DISCS, RUPTURE - GRAPHITE B BS&B 1 0
requirements
All that meet spec
3 C11.16 SGL
requirements
All that meet spec
3 C11.16 STRIKO
requirements
All that meet spec
3 C11.16 ZOOK
requirements
Standardization - All that meet spec
4 C11.17 DISCS, RUPTURE - METAL B BS&B 1 0
Category A requirements
All that meet spec
3 C11.17 CONTINENTAL DISC
requirements
All that meet spec
3 C11.17 FIKE METAL PRODUCTS
requirements
Standardization -
Category A ,
All that meet spec
4 C11.17 OSECO Oseco is the
requirements
selected PLA
Vendor
All that meet spec
4 C11.18 FIELDBUS INDICATORS ABB
requirements
ROSEMONT (EMERSON
4 C11.18
PROCESS MANAGEMENT)
4 C11.18 YOKOGAWA

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Instrumentation) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D 1.0 AGITATORS & MIXERS


Standardization -
D1.1 AGITATORS, GENERAL E CHEMINEER 2 1
Category B
CHEMA PROCESS AND
D1.1
SYSTEM ENGINEERING GMBH

D1.1 EKATO
D1.1 HITACHI LTD
LIGHTNIN (SPX PROCESS
D1.1
EQUIPMENT)
Standardization -
D1.2 AGITATORS, GLASS LINED E DE DIETRICH 2 1
Category B
D1.2 PFAUDLER
D1.2 TYCON TECHNOGLASS
LIGHTNIN (SPX PROCESS Standardization -
D1.3 AGITATORS, MAGNETIC DRIVES E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC 2 1
EQUIPMENT) Category B

D1.4 MIXERS, CONTINUOUS - PLASTIC MIXING & COMPOUNDING E FARREL 1 1

D1.4 KOBE STEEL WORKS


D1.4 POMINI
Standardization -
D1.5 MIXERS, STATIC B CHEMINEER (KENICS MIXERS) 1 1
Category C
D1.5 KOMAX SYSTEMS
D1.5 SULZER CHEMTECH
SEBEWAING TOOL & Standardization -
4 D1.6 MIXERS, REACTION B 1 1
ENGINEERING Category C
EMERSON POWER
Standardization -
D2.1 BEARINGS, SINGLE SYTEM ONLY B TRANSMISSION (BROWNING 1 0
Category C
MANUFACTURING)

EMERSON POWER
D2.1
TRANSMISSION (ROLLWAY)
EMERSON POWER
D2.1 TRANSMISSION
(SEALMASTER)
D2.1 FAG KUGELFISCHER AG
D2.1 NSK LTD
D2.1 NTN
D2.1 REXNORD (LINK-BELT)
ROCKWELL AUTOMATION
D2.1
(DODGE)
D2.1 SKF
THE TIMKEN COMPANY -
D2.1
TORRINGTON-FAFNIR
D3.0 BOILERS
3 D3.1 BOILER, STEAM - PACKAGE WATERTUBE E ALSTOM 2 3
D3.1 BABCOCK & WILCOX
D3.1 BABCOCK-HITACHI
D3.1 C-B NEBRASKA BOILER
DAEKYUNG MACHINERY &
D3.1
ENGINEERING
D3.1 FOSTER WHEELER
D3.1 G.C. BROACH
D3.1 MACCHI
MITSUI BABCOCK ENERGY
D3.1
SERVICES
MITSUI ENGINEERING &
D3.1
SHIPBUILDING
D3.1 TECHNOTHERM
D3.2 BOILER, STEAM - PACKAGE FIRETUBE E BABCOCK-HITACHI 2 3
D3.2 CLEAVER-BROOKS
DAEKYUNG MACHINERY &
D3.2
ENGINEERING
D3.2 FULTON
D3.2 G.C. BROACH
D3.2 JOHNSTON BOILER
MITSUI BABCOCK ENERGY
D3.2
SERVICES
D3.2 TECHNOTHERM
D3.3 BOILER, STEAM - PACKAGE / THROX E LOOS INTERNATIONAL 2 3
D3.3 STANDARD-KESSEL
D3.4 BOILER, STEAM - PACKAGE / THROX - FIRETUBE E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC JOHNSTON BOILER 2 3
D3.5 BOILER, STEAM - PACKAGE / THROX - WATERTUBE E BABCOCK & WILCOX 2 3
D3.5 C-B NEBRASKA BOILER
D3.5 MAN TURBO
3 D3.6 BOILER, STEAM - FIELD ERECTED E ALSTOM 2 3
D3.6 BABCOCK & WILCOX
D3.6 FOSTER WHEELER
MITSUI BABCOCK ENERGY
D3.6
D3 6
SERVICES
MITSUI ENGINEERING &
D3.6
SHIPBUILDING
D4.0 BURNERS
D4.1 BURNER, LONOX E CALLIDUS TECHNOLOGIES 2 2
D4.1 COEN
D4.1 JOHN ZINK
T-THERMAL COMPANY
D4.1
(SELAS)
D4.1 ZEECO
D5.0 CASTING MACHINES
D5.1 CASTING MACHINES E NOT ANTICIPATED FOR RTIP - AUTOMOTIVE INDUSTRY WEBEX 1 1
D6.0 CENTRIFUGES
Standardization -
D6.1 CENTRIFUGE, DECANTER SOLID BOWL SEDIMENTATION E ALFA LAVAL 2 2
Category B
D6.1 ANDRITZ BIRD
D6.1 EIMCO

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

GEA WESTFALIA SEPARATOR


D6.1
AG
D6.1 MITSUBISHI KAKOKI KAISHA
D6.1 TEMA (SIEBTECHNIK)
Standardization -
D6.2 CENTRIFUGE, INVERTING CLOTH FILTERING E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC HEINKEL 2 2
Category B
Standardization -
D6.3 CENTRIFUGE, PEELER FILTERING E ANDRITZ BIRD 2 2
Category B
D6.3 KRAUSS-MAFFEI
Standardization -
D6.4 CENTRIFUGE, PERFORATED BOWL FILTERING E AMETEK 2 2
Category B
D6.4 ANDRITZ BIRD

COMI CONDOR SEPARATION


D6.4
TECHNOLOGIES
D6.4 FERRUM

D6.4 WESTERN STATES MACHINE

NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC Standardization -


D6.5 CENTRIFUGE, PODBEALIC E BAKER PERKINS 2 2
Category B
Standardization -
D6.6 CENTRIFUGE, PUSHER FILTERING E B&P PROCESS EQUIPMENT 2 2
Category B
D6.6 ESCHER-WYSS (MAN TURBO)

D6.6 FERRUM
D6.6 KRAUSS-MAFFEI
D6.6 TEMA (SIEBTECHNIK)
Standardization -
D6.7 CENTRIFUGE, STACK DISK SEDIMENTATION E ALFA LAVAL 2 2
Category B
D6.7 EIMCO
GEA WESTFALIA SEPARATOR
D6.7
AG
D6.7 MITSUBISHI KAKOKI KAISHA
Standardization -
D6.8 CENTRIFUGE, WORM SCREEN FILTERING E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC TEMA (SIEBTECHNIK) 2 2
Category B
D7.0 CHEMICAL INJECTION UNITS
Standardization -
D7.1 CHEMICAL INJECTION UNIT, SKID E AES ARABIA LIMITED (SA) 2 2
Category B
BRAN & LUEBBE
D7.1
INCORPORATED (SPX)
D7.1 DOSAPRO MILTON ROY
D7.1 IMC GMBH
D7.1 JOHNSON MARCH SYSTEMS
D7.1 LEWA GMBH
PROMINENT DOSIERTECHNIK
D7.1
GMBH
D7.1 SPX PROCESS EQUIPMENT
2 D8.0 COMPRESSORS
*GE/AC COMPRESSOR
(OSHKOSH, WI LOCATION IS Standardization -
4 D8.1 COMPRESSOR, API - 617 CENTRIFUGAL E ONLY ACCEPTABLE FOR 3 3
Category E
SINGLE STAGE OVERHUNG
UNITS
D8.1 DRESSER-RAND
D8.1 ELLIOTT/EBARA
GE OIL & GAS (NUOVO
3 D8.1
PIGNONE)
D8.1 MAN TURBO
MITSUBISHI HEAVY
D8.1
INDUSTRIES
D8.1 SIEMENS / DEMAG / DELAVAL

2 D8.2 COMPRESSOR, API - 617 INT GEAR PROCESS E ATLAS COPCO 3 3


D8.2 MAN TURBO

D8.2 SIEMENS / DEMAG / DELAVAL

D8.2 SUNDYNE
Standardization -
2 D8.3 COMPRESSOR, API - 618 RECIPROCATING - HORIZONTAL E BURCKHARDT COMPRESSION 2 3
Category E
D8.3 DRESSER-RAND
D8.3 NEUMAN & ESSER (NEA)
GE OIL & GAS (NUOVO
3 D8.3
PIGNONE)
Standardization -
2 D8.4 COMPRESSOR, API - 618 RECIPROCATING - VERTICAL E BURCKHARDT COMPRESSION 2 3
Category E
D8.4 NEUMAN & ESSER (NEA)
GE OIL & GAS (NUOVO
3 D8.4
PIGNONE)
2 D8.5 COMPRESSOR, API - 619 DRY SCREW (PROCESS) E MAN TURBO 3 3
D8.5 KOLBECO
2 86
D8.6 CO SSO , API - 672
COMPRESSOR, 6 INT GEAR
G C
CENTRIF AIR E S CO
ATLAS CO
COPCO 2 3
CAMERON COMPRESSION
D8.6
SYSTEMS
D8.6 FS-ELLIOTT COMPANY

D8.6 SIEMENS / DEMAG / DELAVAL

2 D8.7 COMPRESSOR, AXIAL E DRESSER-RAND 2 3


D8.7 ELLIOTT
D8.7 MAN TURBO
D8.8 COMPRESSOR, DIAPHRAGM E ANDREAS HOFER 2 2
D8.8 HOWDEN BC COMPRESSORS
COMPRESSOR, DRY SCREW - PNEUMATIC CONVEYING
D8.9 E AERZENER 2 2
SYSTEM
D8.9 ATLAS COPCO
D8.9 KOLBECO
2 D8.10 COMPRESSOR, DRY SCREW - NON API E AERZENER 2 2
D8.10 ATLAS COPCO
D8.10 KOLBECO
2 D8.11 COMPRESSOR, FLOODED SCREW - INSTRUMENT AIR E ATLAS COPCO 2 1

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D8.11 INGERSOLL-RAND
D8.11 SULLAIR
COMPRESSOR, FLOODED SCREW - PROCESS &
4 D8.12 E AERZENER 4 2
REFRIGERATION
3 D8.12 FRICK
4 D8.12 GEA
HOWDEN BC COMPRESSORS
D8.12
(ARAMCO CAUTION)
D8.12 MYCOM
2 D8.13 COMPRESSORS, HYPER E BURCKHARDT COMPRESSION 2 4
GE OIL & GAS (NUOVO
3 D8.13
PIGNONE)
D8.14 COMPRESSOR, NON-API RECIPROCATING - AIR E COMPAIR UK 2 1
D8.14 GARDNER DENVER
D8.14 INGERSOLL-RAND
D8.14 SIAD MACCHINE IMPIANTI SPA
D8.15 COMPRESSOR, NON-API RECIPROCATING - PROCESS E CORKEN 2 1

HOWDEN BC COMPRESSORS
D8.15
(ARAMCO CAUTION)

D8 15
D8.15 NEUMAN & ESSER (NEA)
2 D8.16 COMPRESSOR, SLIDING VANE E BUSCH 2 2
D8.17 COMPRESSOR, VACUUM - DRY SCREWS E BUSCH 2 2
D8.17 SIHI
GARDNER DENVER (GARO
D8.18 COMPRESSOR, VACUUM - LIQUID RING E 2 2
DESIGNS ONLY)
D8.18 GARO SPA
D8.18 SIHI
D8.19 COMPRESSOR, VACUUM - PD LOBE BLOWER E AERZENER 2 2

DRESSER (ROOTS BLOWERS


D8.19
& COMPRESSORS)

GARDNER DENVER
D8.19
(SUTORBUILT)
D8.19 M-D PNEUMATICS
COMPRESSOR, MAGNETIC DRIVE LIQUID RING VACUUM
D8.20 E HERMETIC 2 2
PUMP
D8.20 SIHI
2 D9.0 CONDENSERS
2 D9.1 CONDENSER, SURFACE STEAM SYSTEM; 32-SAMS E GRAHAM MANUFACTURING 3 2
D9.1 TECHNOTHERM
2 D10.0 COOLING TOWERS
Standardization -
4 D10.1 COOLING TOWER, WATER E HAMON THERMAL EUROPE 2 0
Category A
Standardization -
Category A, SPIG
4 D10.1 SPIG
is the selected
PLA Vendor
SPX COOLING
D10.1
TECHNOLOGIES
2 D11.0 CRANES AND LIFTS
Standardization -
D11.1 CRANE, BRIDGE E ABUS KRANSYSTEME GMBH 2 2
Category C
AMERICAN CRANE AND
D11.1
EQUIPMENT
DEMAG CRANES &
D11.1
COMPONENTS GMBH
EASTERN MORRIS CRANES
D11.1
(SA)
D11.1 KCI KONECRANES
D11.1 OMI CRANE & MONORAIL
PROSERVANCHOR CRANE
D11.1
GROUP
D11.1 R&M SYSTEMS (RM HOIST)
SAUDI CRANES AND STEEL
D11.1
WORKS (SA)
STAHL CRANE SYSTEMS
3 D11.1
ADDED
AMERICAN CRANE AND Standardization -
D11.2 LIFT, JIB BOOM W/ TROLLEY & HOIST E 2 1
EQUIPMENT Category C
DEMAG CRANES &
D11.2
COMPONENTS GMBH
EASTERN MORRIS CRANES
D11.2
(SA)
D11.2 GENERAL CRANE SERVICE
D11.2 HYDRAMARINE AS
INDUSTRIAL HOIST SERVICES
D11.2
(IHS)
D11.2 KITO
D11.2 MORRIS MATERIAL HANDLING
PROSERVANCHOR CRANE
D11.2
GROUP
STAHL CRANE SYSTEMS
3 D11.2
ADDED
Standardization -
2 D11.3 LIFT, MONORAIL W/ TROLLEY & HOIST E FORVIS 2 1
Category C
D11.3 GENERAL CRANE SERVICE
INDUSTRIAL HOIST SERVICES
D11.3
(IHS)
PROSERVANCHOR CRANE
D11.3
GROUP
STAHL CRANE SYSTEMS
3 D11.3
ADDED
D11.3 TEGA
Standardization -
D11.4 LIFT, TROLLEY ABUS KRANSYSTEME GMBH 2 1
Category C
D11.4 CHESTER
D11.4 COFFING

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D11.4 COLUMBUS MCKINNON


D11.4 J. D. NEUHAUS (JDN)
D11.4 SHAWBOX
STAHL CRANE SYSTEMS
3 D11.4
ADDED
D11.4 YALE
2 D12.0 CRUSHERS
2 D12.1 CRUSHER, HAMMER MILL E FULLER-KOVAKO 2 2

METSO MINERALS (SVEDALA -


D12.1
ALLIS MINERAL SYSTEMS)

2 D12.2 CRUSHER, JAW E FULLER-KOVAKO 2 2

METSO MINERALS (SVEDALA -


D12.2
ALLIS MINERAL SYSTEMS)

2 D12.3 CRUSHER, ROD E ATLANTIC COAST CRUSHERS 2 2

D12.3 FRANKLIN MILLER


D12.3 FULLER-KOVAKO

METSO MINERALS (SVEDALA -


D12.3
ALLIS MINERAL SYSTEMS)

2 D13.0 CUTTERS / PELLETIZERS / DIES


2 D13.1 CUTTERS / PELLETIZERS / DIES E BERSTORFF 2 2
D13.1 CONAIR
D13.1 CONDUX
COPERION WERNER &
D13.1
PFLEIDERER
CUMBERLAND ENGINEERING
D13.1
CORPORATION
DAVIS-STANDARD (KILLION,
D13.1 EGAN, NRM, STERLING, ER-
WE-PA)
D13.1 FARREL
D13.1 FITZPATRICK
D13.1 GENCO
HOSOKAWA ALPINE
D13.1
AKTIENGESELLSCHAFT
D13.1 IHI
D13.1 JSW (JAPAN STEEL WORKS)
D13.1 PALLMANN
D13.1 POMINI
D13.1 PRECISION CUTTERS
D13.1 PREVIERO
D13.1 REINECKE
D13.1 RIETER (AUTOMATIK)
D13.1 ROGERS TOOL WORKS
D13.1 SCHEER BAY
SEBEWAING TOOL &
D13.1
ENGINEERING
D13.1 WENHOENER
XALOY (FORMERLY
D13.1 BERINGER/DYNISCO
EXTRUSION)
D14.0 CYCLONES
D14.1 CYCLONE, SEPARATOR E ABT 2 1
AKW (AMBERGER
D14.1
KAOLINWERKE)
D14.1 ALFA LAVAL
D14.1 DELTA/DUCON
D14.1 EIMCO
D14.1 FISHER-KLOSTERMAN
D14.1 KREBS ENGINEERS
D15.0 DESALINATION

D15.1 DESALINATION, THERMAL - VAPOR COMPRESSION E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC AQUATECH INTERNATIONAL 3 3

D15.2 DESALINATION, THERMAL - VERTICAL TUBE E AQUATECH INTERNATIONAL 3 3

MITSUBISHI HEAVY
D15.2
INDUSTRIES
D15.3 DESALINATION, REVERSE OSMOSIS SYSTEM AND ACCESS E AES ARABIA LIMTED (SA) 3 3

D15.3 AQUATECH INTERNATIONAL

D15.3 CAIRD & RAYNER CLARK


HOH WATER TECHNOLOGY
D15.3
A/S
D15.3 IONICS (GE)
D15.3 MECHANICAL EQUIPMENT
D15.3 SASAKURA ENGINEERING
SAUDI BERKEFELD FILTER
D15.3
(SA)
DESUPERHEATERS, EDUCTORS, STEAM EJECTORS,
4 D16.0
AND VENTURIS

4 D16.1 DESUPERHEATERS B BABCOCK-HITACHI 2 1

D16.1 BELLELI ENERGY SRL


CONTROL COMPONENTS
D16.1
INCORPORATED (CCI)
D16.1 DRESSER ITALIA SPA
EMERSON PROCESS
D16.1 MANAGEMENT (FISHER
REGULATORS - CON-TEK
INC.)
D16.1 GRAHAM MANUFACTURING

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

MASONEILAN DIVISION
D16.1
DRESSER
MITSUBISHI HEAVY
D16.1
INDUSTRIES
D16.1 NIPPON FISHER
SAMSON AG - MESS- UND
D16.1
REGELTECHNIK
D16.1 SCHUTTE & KOERTING
4 D16.1 TYCO (NARVIK YARWAY)
4 D16.2 EDUCTORS B GEA WIEGAND 2 1
D16.2 NU-CON
D16.2 QUICKDRAFT
D16.2 SCHUTTE & KOERTING
D16.2 TYCO (PENBERTHY)
Standardization -
4 D16.3 STEAM EJECTORS E CROLL-REYNOLDS 2 1
Category C
D16.3 GEA WIEGAND

D16.3 GRAHAM MANUFACTURING

D16.3 KOERTING
D16.3 C
NITECH
SAMHWA MIXING
D16.3
TECHNOLOGY
D16.3 SCHUTTE & KOERTING
D16.3 TYCO (PENBERTHY)
4 D16.4 VENTURIS B AMETEK 2 1
D16.4 CROLL REYNOLDS
D16.4 GEA WIEGAND
2 D17.0 DRYERS
Standardization -
D17.1 DRYER, SKID INSTRUMENT AIR & COMPRESSED E DELAIR B.V. 2 2
Category C
4 D17.1 INGERSOLL-RAND
D17.1 PNEUMATIC PRODUCTS
D17.1 SPX KEMP
D17.1 SULLAIR
4 D17.1 VAN AIR INC
Standardization -
2 D17.2 DRYER, CENTRIFUGAL PELLET E DEC-E-TECH 2 1
Category C
D17.2 GALA INDUSTRIES
D17.2 KRAUSS-MAFFEI
D17.2 LITTLEFORD DAY
D17.2 SULZER PUMPS
Standardization -
2 D17.3 DRYER, CONVECTION BELT / CONVEYER E AEROGLIDE CORPORATION 2 1
Category C
D17.3 COMESSA
Standardization -
2 D17.4 DRYER, FLUID BED - TYPE 1 VIBRATORY E ANHYDRO A/S 2 1
Category C
D17.4 CARMAN INDUSTRIES
D17.4 CARRIER
D17.4 GEA BARR-ROSIN
Standardization -
2 D17.5 DRYER, FLUID BED - TYPE 2 NON VIBRATORY E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC GEA NIRO 2 1
Category C
Standardization -
2 D17.6 DRYER, NAUTA STYLE E DEC-E-TECH 2 1
Category C
HOSOKAWA MICRON
D17.6
CORPORATION
D17.6 HOSOKAWA-BEPEX
D17.6 KRAUSS-MAFFEI
D17.6 LITTLEFORD DAY
Standardization -
2 D17.7 DRYER, ROTATING TUMBLE E COMESSA 2 1
Category C
D17.7 GRENZEBACH BSH
D17.7 LITTLEFORD DAY
Standardization -
2 D17.8 DRYER, SPECIALTY PRODUCT - TYPE 1 PADDEL E GEA BARR-ROSIN 2 1
Category C
D17.8 GEA NIRO
D17.8 GRENZEBACH BSH
D17.8 HOSOKAWA-BEPEX
D17.8 KRAUSS-MAFFEI
D17.8 LIST AG
D17.8 LOEDIGE
D17.8 PROCEDYNE
DRYER, SPECIALTY PRODUCT - TYPE 2 NARA PADDEL GOUDSCHE Standardization -
2 D17.9 E 2 1
PROCESSOR MACHINEFABRIEK BV Category C
D17.9
D17 9 KOMLINE SANDERSON
KOMLINE-SANDERSON
Standardization -
2 D17.10 DRYER, SPRAY ATOMIZER E ANHYDRO A/S 2 1
Category C
CARLISLE PROCESS
D17.10
SYSTEMS
D17.10 GEA NIRO
D17.10 HOSOKAWA-BEPEX
D18.0 DUST COLLECTORS
BECKERT & HIESTER Standardization -
D18.1 DUST COLLECTOR, BIN TOP E 1 1
INCORPORATED Category C
D18.1 DYNAMIC AIR
Standardization -
D18.2 DUST COLLECTOR, DISPOSABLE ELEMENT E DONALDSON COMPANY 1 1
Category C
D18.2 GE ENERGY (BHA GROUP)
D18.2 INTENSIVE FILTER
D18.2 MAC EQUIPMENT
DUST COLLECTOR, MECH SHAKER - SELF CLEANING Standardization -
D18.3 E FULLER-KOVAKO 1 1
ELEMENT Category C
D18.3 GE ENERGY (BHA GROUP)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

DUST COLLECTOR, PNEUMATIC JET PULSE - SELF Standardization -


D18.4 E BECKERT & HIESTER 1 1
CLEANING ELEMENT Category C
CEILCOTE AIR POLLUTION
D18.4
CONTROL
D18.4 DONALDSON COMPANY
D18.4 FLEX-KLEEN
D18.4 FULLER-KOVAKO
D18.4 GE ENERGY (BHA GROUP)
D18.4 LUEHR FILTER GMBH & CO
D18.4 MAC EQUIPMENT
D18.4 MIKROPUL
2 D19.0 ELEVATORS
Standardization -
D19.1 ELEVATOR, PERSONNEL - CABLE E OTIS 2 0
Category C
D19.1 THYSSEN
Standardization -
2 D19.2 ELEVATOR, PERSONNEL - HYDRAULIC E OTIS 2 0
Category C
2 D19.2 THYSSEN
Standardization -
2 D19.3 ELEVATORS, PERSONNEL - MATERIAL LIFT E OTIS 2 0
Category C
D19.3 THYSSEN
D20 0
D20.0 ENGINES
D20.1 ENGINE, STATIONARY - DIESEL E CATERPILLAR 2 0
D20.1 CUMMINS
D20.1 DETROIT DIESEL
D20.1 STEWART & STEVENSON
2 D21.0 EXTRUDERS
EXTRUDER, SINGLE SCREW - NON OEM SCREWS -
D21.1 E BARR 1 1
GENERAL
D21.1 GLYCON
D21.1 MIGRANDY
D21.1 PRECISION FEEDSCREWS
D21.1 SPIREX
XALOY INCORPORATED
(FORMERLY
D21.1
BERINGER/DYNISCO
EXTRUSION)
EXTRUDER, SINGLE SCREW - NON OEM SCREWS -
D21.2 E BARR 1 0
LABORATORY EQUIPMENT
D21.2 GLYCON
D21.2 MIGRANDY
D21.2 PRECISION FEEDSCREWS
D21.2 SPIREX CORPORATION
XALOY (FORMERLY
D21.2 BERINGER/DYNISCO
EXTRUSION)
EXTRUDER, TWIN SCREW - NON OEM SCREWS AND
D21.3 E B&P PROCESS EQUIPMENT 1 1
SCREW ELEMENTS
D21.3 CANTERBURY
D21.3 CENTURY SPECIALTIES

EXTRICOM GMBH BLACH


D21 3
D21.3
EXTRUDER & COMPONENTS

D21.3 MARION MOLD & TOOL

EXTRUDER, SINGLE SCREW (LESS THAN 200HP / 150KW) - GLOUCESTER (BATTENFELD


D21.4 E 2 2
BLOWN FILM / FOAM SHEET GLOUCESTER)

D21.4 NEW CASTLE INDUSTRIES


EXTRUDER, SINGLE SCREW (LESS THAN 200HP / 150KW) -
D21.5 E BERSTORFF 2 2
EXTRUSION COATING
BLACK-CLAWSON
D21.5
CONVERTING MACHINERY
D21.5 HAAKE (THERMO ELECTRON)
DAVIS-STANDARD (KILLION,
EXTRUDER, SINGLE SCREW (LESS THAN 200HP / 150KW) -
D21.6 E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC EGAN, NRM, STERLING, ER- 2 2
GENERAL
WE-PA)
EXTRUDER, SINGLE SCREW (LESS THAN 200HP / 150KW) - NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC
D21.7 E REIFENHAUSER 2 2
GROOVED BARREL / BLOWN FILM
EXTRUDER, SINGLE SCREW (LESS THAN 200HP / 150KW) -
2 D21.8 E AMERICAN KUHNE 2 0
LABORATORY EQUIPMENT
RANDCASTLE
EXTRUDER, SINGLE SCREW (LESS THAN 200HP / 150KW) - NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC
D21.9 E HPM 2 2
SHEET > 10 MILS THICK
EXTRUDER, SINGLE SCREW (GREATER THAN 200HP /
D21.10 E BERSTORFF 2 2
150KW) - GENERAL
DAVIS-STANDARD (KILLION,
D21.10 EGAN, NRM, STERLING, ER-
WE-PA)
D21.10 NEW CASTLE INDUSTRIES
EXTRUDER, TWIN SCREW (GREATER THAN 200HP / 150KW)
D21.11 E BERSTORFF 2 2
- GENERAL
COPERION WERNER &
D21.11
PFLEIDERER
D21.11 JSW (JAPAN STEEL WORKS)
D21.11 WEATHERFORD ALS (KOBE)
EXTRUDER, TWIN SCREW (LESS THAN 200HP / 150KW) - NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC
D21.12 E WELDING ENGINEERS 2 2
DEVOLATIZATION
EXTRUDER, TWIN SCREW (LESS THAN 200HP / 150KW) -
D21.13 E BERSTORFF 2 2
GENERAL
COPERION WERNER &
D21.13
PFLEIDERER
DAVIS-STANDARD (KILLION,
D21.13 EGAN, NRM, STERLING, ER-
WE-PA)
D21.13 JSW (JAPAN STEEL WORKS)
EXTRUDER, TWIN SCREW (LESS THAN 200HP / 150KW) -
2 D21.14 E CENTURY SPECIALTIES 1 0
LABORATORY EQUIPMENT
HAAKE (THERMO ELECTRON
D21.14
CORPORATION)
D21.14 LEISTRITZ CORPORATION
2 D22.0 FANS AND BLOWERS

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

Standardization -
D22.1 BLOWER; CENTRIFUGAL, 31-SAMSS-001 E DMW 2 3
Category B
MITSUBISHI HEAVY
D22.1
INDUSTRIES
DRESSER (ROOTS BLOWERS
D22.1
& COMPRESSORS)

Standardization -
D22.2 BLOWER; CENTRIFUGAL - OVER 5000HP, 31-SAM E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC DMW CORPORATION 2 3
Category B
Standardization -
D22.3 BLOWER, HIGH PRESSURE E FIMA 2 3
Category B
HOWDEN (BUF. FORGE,
D22.3
NOVENCO)
D22.3 SPENCER TURBINE
BLOWER, - HOT GAS TAIL - HIGHLY CORROSIVE HOWDEN (BUF. FORGE, Standardization -
D22.4 E 2 3
APPLICATIONS NOVENCO) Category B
D22.4 ROBINSON
Standardization -
D22.5 BLOWER, POSITIVE DISPLACEMENT (PD) LOBE E AERZENER 2 2
Category B
DRESSER (ROOTS BLOWERS
D22.5
& COMPRESSORS)

GARDNER DENVER
D22.5
(SUTORBUILT)

D22.5 M-D PNEUMATICS (TUTHILL)

D22.5 PEDRO GIL S.A.


RKR GEBLAESE UND
D22.5
VERDICHTER GMBH
Standardization -
D22.6 FAN, CENTRIFUGAL API - 673 E BOLDROCCHI 2 2
Category B
D22.6 FIMA
HOWDEN (BUF. FORGE,
D22.6
NOVENCO)
D22.6 ROBINSON
FAN AND BLOWER, AXIAL FLOW - HEAVY DUTY MARINE / Standardization -
D22.7 E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC HARTZELL 2 2
MINE AND LIGHT DUTY Category B
Standardization -
2 D22.8 FAN AND BLOWER, CENTRIFUGAL - GEN PURPOSE E AIR CURE (FRP ONLY) 2 2
Category B
D22.8 CHICAGO BLOWER
D22.8 FIMA
HOWDEN (BUF. FORGE,
D22.8
NOVENCO)
NEW YORK BLOWER
D22.8
COMPANY
D22.8 ROBINSON
D22.8 SCHIELE
2 D23.0 FILTERS
Standardization -
D23.1 FILTER, INTAKE AIR E KOCH FILTER 2 2
Category C
D23.1 DOLLINGER
D23.1 DOLLINGER IRELAND
RASHED AL RASHED AND
D23.1
SONS DONALDSON (SA)
Standardization -
D23.2 FILTER, BELT PRESS E ANDRITZ-RUTHNER 2 1
Category C
D23.2 ASHBROOK SIMON-HARTLEY
D23.2 KLEIN
Standardization -
D23.3 FILTER, CANDLE / BACKWASH E AMERICAN FILTERS 2 1
Category C
D23.3 DR. MULLER AG, DRM
D23.3 MOTT INDUSTRIAL
D23.3 PALL CORPORATION
D23.3 PALL SCHUMACHER
D23.3 W. L. GORE & ASSOCIATES
Standardization -
D23.4 FILTER, LIQUIDE SERVICE (BAG / BASKET / CARTRIDGE) E AMAFILTER 2 1
Category C
CALGON CARBON
4 D23.4
CORPORATION
D23.4 CUNO
EATON FILTRATION
D23.4
(HAYWARD)

D23.4 FSI (FILTER SPECIALISTS INC)

D23.4 GORA
3 D23.4 JOHN CRANE INDUFUL
D23.4 PALL CORPORATION
D23.4 PARKER FILTRATION
Standardization -
D23.5 FILTER, PRESS - TYPE 1 HORIZONTAL E EIMCO 2 1
Category C
D23.5 JWI (SIEMENS/US FILTERS)
D23.5 NETZSCH INCORPORATED
PALL SCHENK FILTER
D23.5
SYSTEMS
PERRIN (SIEMENS/US
D23.5
FILTERS)
Standardization -
D23.6 FILTER, PRESS - TYPE 2 VERTICAL E HYDROMATION 2 1
Category C
D23.6 LAROX
Standardization -
D23.7 FILTER, LEAF - NO PRECOAT SYSTEM E AMAFILTER 2 1
Category C
D23.7 EIMCO
D23.7 SPARKLER FILTERS
Standardization -
D23.8 FILTER, LEAF - PRECOAT SYSTEM E EIMCO 2 1
Category C
PALL SCHENK FILTER
D23.8
SYSTEMS
D23.8 PALL SCHUMACHER
GNEUSS Standardization -
D23.9 FILTER, POLYMER SCREEN E 2 1
KUNSTSTOFFTECHNIK GMBH Category C

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D23.9 KREYENBORG
XALOY (FORMERLY
D23.9 BERINGER/DYNISCO
EXTRUSION)
Standardization -
D23.10 FILTER, ROTARY DRUM PRESSURE E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC BHS - SONTHOFEN GMBH 2 1
Category C
Standardization -
2 D23.11 FILTER, SAND - GENERAL E EIMCO 2 2
Category C
D23.11 METSO MINERALS (SALA) AB

D23.11 PASSAVANT
US FILTER / SIEMENS
D23.11
(PERMUTIT)
D23.11 VORTISAND
D23.11 YARDNEY
Standardization -
2 D23.12 FILTER, SAND - MOVING BED E AXEL JOHNSON 2 2
Category C

D23.12 METSO MINERALS (SALA) AB

Standardization -
D23.13 FILTER, VACUUM - BELT TYPE E BHS - SONTHOFEN GMBH 2 1
Category C
D23.13 EIMCO
D23.13 PANNEVIS
Standardization -
D23.14 FILTER, VACCUM - ROTARY DRUM TYPE E BHS - SONTHOFEN GMBH 2 1
Category C
D23.14 KHD (ANDRITZ BIRD INC)
Standardization -
D23.15 FILTER, VACUUM - TILING / HORIZONTAL PAN TYPE E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC EIMCO 2 1
Category C
METITO ARABIA INDUSTRIES Standardization -
2 D23.16 FILTER, MEDIA - SAND, ANTHRACITE, SEA WATER B 1 0
(SA) Category C
SAUDI BERKEFELD FILTER
D23.16
(SA)
SIEMENS WATER
D23.16
TECHNOLOGIES
2 D24.0 FLARES AND CONTROLS
FLARES, COMBUSTION CONTROLS INCLUDING IGNITERS CALGON CARBON
4 D24.1 E 3 2
AND FLAME FRONT GENERATORS CORPORATION
2 D24.1 'CALLIDUS TECHNOLOGIES
D24.1 FIREYE ELECTRONICS
D24.1 FORNEY INTERNATIONAL
D24.1 JOHN ZINK
D24.1 POWERTROL
D24.1 ZEECO
FLARE, GROUND AND ELEVATED, INCLUDING FLARE TIPS
2 D24.2 E CALLIDUS TECHNOLOGIES 3 2
AND STACKS
D24.2 JOHN ZINK
D24.2 ZEECO
2 D25.0 FURNACES
D25.1 FURNACE, CRACKING E FOSTER WHEELER 3 3
D25.1 LUMMUS
MARITIME INDUSTRIAL
4 D25 1
D25.1
SERVICE
D25.1 PETROCHEM
D25.1 SELAS FLUID PROCESSING
D25.1 STONE & WEBSTER
D25.1 TECHNIP (KTI)
2 D25.2 FURNACE, TUBE SUPPORTS E DURALOY TECHNOLOGIES 2 0
4 D25.2 FASER
4 D25.2 FIAS
KUBOTA METAL
D25.2
CORPORATION
D25.2 MANOIR

METALTEK INTERNATIONAL
D25.2 (CARONDELET
CORPORATION)

D25.2 PARALLOY
SCHMIDT & CLEMENS GMBH &
D25.2
CO
KUBOTA METAL
2 D25.3 FURNACE, TUBES - ETHYLENE E 2 0
CORPORATION
D25.3 MANOIR
SCHMIDT & CLEMENS GMBH &
D25.3
CO. KG
KUBOTA METAL
D25.4 FURNACE, TUBES - VINYL E 2 0
CORPORATION
D25.4 MANOIR
D25.4 PARALLOY
SCHMIDT & CLEMENS GMBH &
D25.4
CO
D25.5 FURNACE,, BLOWE - SOOT 32-SAMSS-029 E CLYDE BERGEMANN 2 0
MITSUBISHI HEAVY
D25.5
INDUSTRIES
2 D26.0 GEARS
FLENDER GRAFFENSTADEN Standardization -
3 D26.1 GEAR, API 613 B 2 3
SA Category B
3 D26.1 HITACHI NICO TRANSMISSION
3 D26.1 LUFKIN INDUSTRIES
3 D26.1 RENK-MAAG
VOITH TURBO BHS GETRIEBE
3 D26.1
GMBH
VOITH TURBO BHS GETRIEBE
2 D26.2 GEAR, EPICYCLIC / PLANETARY B 1 3
GMBH
GEAR, BOX - NON-API GEN. PURP. PARALLEL SHAFT SMALL
D26.3 B FLENDER-GRAFFENSTADEN 1 1
SIZE STANDARD < 500 HP
D26.3 PIV
D26.3 REXNORD (FALK)
D26.3 REXNORD (LINK-BELT)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

SEW-EURODRIVE GMBH & CO


D26.3
KG
VOITH TURBO BHS GETRIEBE
D26.4 GEAR, HYDRAULIC / FLUID COUPLING B NOT ANTICIPATED FOR RTIP - SOLE SOURCE 2 2
GMBH
2 D26.5 GEAR, BOX - VARIABLE SPEED COUPLING, API 613 B EAGLE INDUSTRY NIIGATA 2 3
D26.5 GOODRICH
D26.5 KOP-FLEX
D26.5 REXNORD (FALK)
D26.5 TWIN DISC
FLENDER GRAFFENSTADEN Standardization -
3 D26.6 GEAR, API 677 B 2 3
SA Category B
3 D26.6 HITACHI NICO TRANSMISSION
3 D26.6 LUFKIN INDUSTRIES
3 D26.6 NIPPON GEAR
3 D26.6 PHILADELPHIA GEAR
3 D26.6 SEISA GEAR
STORK GEARS & SERVICES
3 D26.6
B.V.
D27.0 GRANULATOR
D27.1 GRANULATOR, ROTARY DRUM E BERSTORFF 2 1
D27.1 BUSS SMS-CANZLER GMBH

CARTER DAY INTERNATIONAL


D27.1
(JACOBSON)

COPERION WERNER &


D27.1
PFLEIDERER
D27.1 LITTLEFORD DAY
D27.1 MITTS & MERRILL (JORDAN)
D28.0 GRINDERS
ANDRITZ (SPROUT-BAUER
D28.1 GRINDER, PRODUCT E 2 1
EQUIPMENT)
BAUERMEISTER
D28.1 ZERKLEINERUNGSTECHNIK
GMBH
D28.1 BEPEX INTERNATIONAL

D28.1 CONDUX
CUMBERLAND ENGINEERING
D28.1
CORPORATION
FOREMOST MACHINE
D28.1
BUILDERS
KILIA FLEISCHEREI- UND
D28.1 SPEZIAL-MASCHINEN FABRIK
GMBH
D28.1 NEUHAUS-NEOTECH
D28.1 PALLMANN
D29.0 HEAT RECOVERY UNIT
FOSTER WHEELER IBERIA
D29.1 HRU, HEAT RECOVERY STEAM GENERATOR E 3 3
S.A.
S A
D29.1 BORSIG GMBH
D29.1 CCT SRL
D29.1 G.C. BROACH COMPANY
D29.1 MACCHI
THERMAX BABCOCK AND
D29.1
WILCOX
2 D30.0 HEATERS
2 D30.1 HEATER, HEAT TRANSFER FLUIDS E BORN CANADA 2 2
D30.1 G. C. BROACH COMPANY 3
D30.1 GEKAKONUS GMBH
TEI STRUTHERS WELLS
D30.1
(BABCOCK POWER)
D30.1 TULSA HEATERS INC (THI)
VOGT POWER
2 D30.2 HEATER, HEAT TRANSFER FLUID VAPORIZER E NOT ANTICIPATED FOR RTIP - SOLE SOURCE INTERNATIONAL (BABCOCK 2 3
POWER)
2 D31.0 HVAC
AWAL GULF Standardization -
D31.1 HVAC, AIR CONDITIONING UNIT - SELF CONTAINED E 2 0
MANUFACTURING Category B
D31.1 BARD MANUFACTURING
HEATING AND AIR
D31.1
CONDITIONING (SA)
D31.1 LG ELECTRONIC
PETRA ENGINEERING
D31.1
INDUSTRIES
SHARJAH AND KUWAIT
D31.1
MANUFACTURING
ZAMIL AIR CONDITIONERS
D31.1
(SA)
HVAC, AIR CONDITIONING UNIT - PACKAGED UNIT TRAILER AL SALEM YORK Standardization -
2 D31.2 E 2 0
MOUNTED MANFUCATURING (SA) Category B
AWAL GULF
D31.2
MANUFACTURING
PETRA ENGINEERING
D31.2
INDUSTRIES
SHARJAH AND KUWAIT
D31.2
MANUFACTURING
D31.2 SPECIFIC SYSTEMS
ZAMIL AIR CONDITIONERS
D31.2
(SA)
HVAC, CHILLER WATER - PACKAGED WATER COOLED FOR Standardization -
D31.3 E TRANE 2 2
UTILITY APPLICATIONS Category B
D31.3 YORK PROCESS SYSTEMS
Standardization -
D31.4 HVAC, AIR HANDLING EQUIPMENT E CARRIER 2 0
Category B
D31.4 TRANE
D31.4 YORK PROCESS SYSTEMS

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

Standardization -
D31.5 HVAC, CHILLER UNITS E CARRIER 2 2
Category B
D31.5 TRANE
D31.5 YORK PROCESS SYSTEMS
Standardization -
D31.6 HVAC, HEATING EQUIPMENT - GENERAL E CARRIER 2 0
Category B
D31.6 TRANE
D31.6 YORK PROCESS SYSTEMS
Standardization -
D31.7 HVAC, HVAC EQUIPMENT - GENERAL E CARRIER 2 0
Category B
D31.7 TRANE
D31.7 YORK PROCESS SYSTEMS
Standardization -
2 D31.8 HVAC, PACKAGE UNIT - EXPLOSION PROOF E CARRIER (IN KINGDOM) 2 0
Category B
D31.8 MARC CLIMATIC
D31.8 TRANE (IN KINGDOM)
YORK PROCESS SYSTEMS (IN
D31.8
KINGDOM)
Standardization -
D31.9 HVAC, PACKAGE UNIT - GENERAL E CARRIER 2 0
Category B
D31.9 TRANE
D31.9 YORK PROCESS SYSTEMS

2 D32.0 HYDRAULICS

HYDRAULICS, DRIVE SYSTEMS - PUMPS / CONTROLS / Standardization -


2 D32.1 B BOSCH REXROTH AG 1 2
MOTORS Category C
D32.1 FLODRAULIC
D32.1 HAGGLUNDS
D32.1 OIL GEAR COMPANY
Standardization -
D32.2 HYDRAULICS, HYDRAULIC CONTROLS - ACTUATORS B NOT ANTICIPATED FOR RTIP - SOLE SOURCE BAFCO 1 1
Category C
HYDRAULICS, HYDRAULIC CONTROLS - CONTROLS, BOSCH REXROTH Standardization -
D32.3 B 1 1
VALVES CORPORATION Category C
D32.3 EATON (VICKERS)
D32.3 HAGGLUNDS
Standardization -
D32.4 HYDRAULICS, HYDRAULIC MOTORS - GENERAL B FLODRAULIC 1 1
Category C
D32.4 OIL GEAR COMPANY
D32.4 REXNORD (FALK)
HYDRAULICS, HYDRAULIC MOTORS - HIGH SPEED, LOW Standardization -
D32.5 B BOSCH REXROTH AG 1 1
TORQUE Category C
D32.5 LINDE HYDRAULICS
HYDRAULICS, HYDRAULIC MOTORS - HIGH SPEED, LOW NOT ANTICIPATED FOR RTIP - SOLE SOURCE
Standardization -
D32.6 B DENISON HYDRAULICS 1 1
TORQUE & MEDIUM DUTY Category C
HYDRAULICS, HYDRAULIC MOTORS - LOW SPEED, HIGH Standardization -
D32.7 B FLENDER 1 1
TORQUE Category C
D32.7 HAGGLUNDS
Standardization -
D32.8 HYDRAULICS, HYDRAULIC MOTORS - MEDIUM DUTY B NOT ANTICIPATED FOR RTIP - SOLE SOURCE EATON (VICKERS) 1 1
Category C
Standardization -
D32.9 HYDRAULICS, HYDRAULIC PRODUCT PRESSES B NOT ANTICIPATED FOR RTIP - SOLE SOURCE DIEFFENBACHER N.A. 1 1
Category C
Standardization -
2 D32.10 HYDRAULICS, HYDRAULIC PUMPS B BOSCH REXROTH AG 1 1
Category C
BOSCH REXROTH
D32.10
CORPORATION
D32.10 DENISON HYDRAULICS
D32.10 EATON (VICKERS)
D32.10 HYDAC INTERNATIONAL
D32.10 LINDE HYDRAULICS
D32.10 OIL GEAR COMPANY
D32.10 REXNORD (FALK)
D33.0 INCINERATORS
D33.1 INCINERATOR E CALLIDUS TECHNOLOGIES 2 2
D33.1 CALORIC ANLAGENBAU
D33.1 JOHN ZINK
D33.1 KEU
D33.1 SELAS-KIRCHNER GMBH
D33.1 TSK
D33.1 T-THERMAL COMPANY
D33.2 INCINERATOR, FLUIDIZED BED E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC EIMCO 2 2
D33.3 INCINERATOR, SMALL SOLIDS INCINERATOR E CONSERTHERM 2 2
D33.3 CONSUMAT
D33.3 CORECO
METSO MINERALS (KENNEDY
D33.3
VAN SAUN)
THERMAL ENGINEERING
D33.3
CORPORATION (TEC)
D33.3 VOLUND
CALORIC ANLAGENBAU
D33.4 INCINERATOR, TOX BURNER & CHAMBER E 2 2
GMBH
D33.4 COEN COMPANY
D33.4 DURR ENVIRONMENTAL
EISENMANN CORPORATION
D33.4
USA
EPCON INDUSTRIAL SYSTEMS
D33.4
NV
D33.4 HALDOR-TOPSOE
D33.4 JOHN ZINK
D33.4 LURGI GMBH
D33.4 SELAS-KIRCHNER GMBH
D33.4 SMITH ENGINEERING
D33.4 THERMATRIX
D33.4 T-THERMAL
WHEELABRATOR AIR
D33.4
POLLUTION CONTROL
D33.5 INCINERATOR, TOX CATALYTIC OXIDIZERS E HALDOR-TOPSOE 2 2
D33.5 JOHN ZINK
D33.5 JOHNSON MATTHEY

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D33.5 SALEM ENGELHARD


D33.5 T-THERMAL COMPANY
WHEELABRATOR AIR
D33.5
POLLUTION CONTROL
D33.6 INCINERATOR, TOX GENERAL E CALLIDUS TECHNOLOGIES 2 2
D33.6 CALORIC ANLAGENBAU
D33.6 JOHN ZINK
D33.6 KEU
D33.6 NITTETSU
D33.6 T-THERMAL COMPANY
INCINERATOR, TOX REGENERATIVE / RECUPERATIVE
D33.7 E CALLIDUS TECHNOLOGIES 2 2
OXIDIZERS
D33.7 CALORIC ANLAGENBAU
D33.7 JOHN ZINK
D33.7 KEU
D33.7 NITTETSU
D33.7 T-THERMAL
2 D34.0 LOADING EQUIPMENT
GARDNER DENVER (EMCO- Standardization -
2 D34.1 LOADING EQUIPMENT, MARINE - LOAD / UNLOADING ARMS E 2 2
WHEATON) Category C
3D4.1 CONNEX (SVT)
LOADING EQUIPMENT, TRUCK AND RAIL - LOADING / Standardization -
D34.2 E CONNEX (SVT) 1 2
UNLOADING ARMS Category C
D34.2 FMC TECHNOLOGIES
GARDNER DENVER (EMCO-
D34.2
WHEATON)
D34.2 OPW ENGINEERED SYSTEMS
Standardization -
D34.3 LOADING EQUIPMENT, LOADING / UNLOADING PLATFORMS E CARBIS 1 2
Category C
D34.3 GREEN MANUFACTURING
SAFE HARBOR ACCESS
D34.3
SYSTEMS
2 D35.0 LUBRICATION
Standardization -
4 D35.1 LUBRICATION, SPECIAL PURPOSE OIL SYSTEMS B BARIC 2 3
Category B
D35.1 COBEY
ELLIOTT EBARA
D35.1
TURBOMACHINERY
D35.1 G. J. OLIVER
D35.1 LUBE POWER
MIDDLE EAST POWER
D35.1
COMPANY (SA)
MITSUBISHI HEAVY
D35.1
INDUSTRIES
D35.1 OELTECHNIK
LUBRICATION, GENERAL PURPOSE OIL SYSTEMS AND Standardization -
2 D35.2 B BARIC 1 2
FLUIDS SYSTEMS Category B
D35.2 COBEY
D35.2 FLUID SYSTEMS
D35.2 G. J. OLIVER
D35.2 LUBE POWER
D35.2 OELTECHNIK
D36.0 MIST ELIMINATORS - SCRUBBERS
D36.1 MIST ELIMINATOR - SCRUBBER, AERATORS E ATLAS COPCO 2 1
D36.1 LANDUSTRIE SNEEK BV
D36.2 MIST ELIMINATOR - SCRUBBER, BAG HOUSE TYPE E AMEREX INDUSTRIES 2 1
D36.2 SOLIOS ENVIRONNEMENT
WHEELABRATOR AIR
D36.2
POLLUTION CONTROL
MIST ELIMINATOR - SCRUBBER, - SCRUBBER, IONIZING
D36.3 E 2 1
WET
MIST ELIMINATOR - SCRUBBER, MISCELLANEOUS GAS NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC
D36.4 E BUEHLER (MIAG) 2 1
(VAPOR) SEPARATION EQUIPMENT
MIST ELIMINATOR - SCRUBBER, MISCELLANEOUS LIQUIDS /
D36.5 E 2 1
LIQUIDS SEPARATION EQUIPMENT
MIST ELIMINATOR - SCRUBBER, MISCELLANEOUS LIQUIDS /
D36.6 LIQUIDS SEPARATION EQUIPMENT - CL2 OR HCL JET E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC GEA WIEGAND 2 1
SPRAY SCRUBBER
CEILCOTE AIR POLLUTION
D36.7 MIST ELIMINATOR - SCRUBBER, DEGASIFIER E 2 1
CONTROL
D36.7 KIMRE
D36.7 KOCH INDUSTRIES
MONSANTO ENVIRO-CHEM
D36.7
SYSTEMS
MUNTERS EUROFORM GMBH
D36.7
& CO KG
D36.7 PEERLESS MANUFACTURING
D36.7 VFF
(KOCH
YORK (OTTO H) (KOCH-
D36.7
D36 7
GLITSCH)
MIST ELIMINATOR - SCRUBBER, DEGASIFIERS - VANE NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC
D36.8 E BURGESS-MANNING INC. 2 1
IMPINGEMENT ELEMENTS
AMETEK (SCHUTTE &
D36.9 MIST ELIMINATOR - SCRUBBER, VENTURI SCRUBBER E 2 1
KOERTING)
D36.9 CROLL REYNOLDS
D36.9 FISHER-KLOSTERMAN
D36.9 GEA WIEGAND
D36.9 TYCO (PENBERTHY)
MIST ELIMINATOR - SCRUBBER, WET SCRUBBER / SPRAY DUCON ENVIRONMENTAL
D36.10 E 2 1
TOWERS SYSTEMS
D36.10 RICHARD STIHLER GMBH
3 D37.0 NITROGEN PLANTS
D37.1 NITROGEN PLANT, GENERATOR E AIR LIQUIDE 3 2
D37.1 CARBO-TRADE
D37.1 LINDE AG

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

2 D38.0 PACKAGING AND WEIGHING

PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - Standardization -


D38.1 E HAVER & BOECKER 2 0
ALL TYPES Category B
PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - CUSTOM EQUIPMENT DESIGN Standardization -
D38.2 E 2 0
BULK BAGS LOADING (CED) Category B
D38.2 DELAERE
D38.2 FLEXICON
D38.2 PREMIER TECH CHRONOS
D38.2 SMURFIT-STONE CONTAINER
D38.2 SPIROFLOW SYSTEMS
PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - Standardization -
D38.3 E ACCURATE 2 0
BULK BAGS UNLOADING Category B
D38.3 SPIROFLOW SYSTEMS
D38.3 YOUNG INDUSTRIES
PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - Standardization -
D38.4 E BEMIS COMPANY 2 0
BULK BOXES / DRUMS Category B
CUSTOM EQUIPMENT DESIGN
D38.4
(CED)
D38.4 DELAERE
D38.4 PREMIER TECH CHRONOS
PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - Standardization -
D38.5 E HAVER & BOECKER 2 0
FORM, FILL & SEAL (25 KG / 50 LB) Category B
WINDMOELLER &
D38.5
HOELSCHER
PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - HAYSSEN PACKAGING Standardization -
D38.6 E 2 0
FORM, FILL & SEAL (SMALL POUCHES) TECHNOLOGIES Category B
D38.6 ROVEMA
PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - Standardization -
D38.7 E NEWLONG 2 0
OPEN MOUTH SYSTEMS Category B
D38.7 PREMIER TECH CHRONOS
PACKAGING & WEIGHING, BAGS / BULK BAGS EQUIPMENT - Standardization -
D38.8 E BEMIS COMPANY 2 0
VALVE BAGS Category B
SMURFIT-STONE CONTAINER
D38.8
CORPORATION
Standardization -
D38.9 PACKAGING & WEIGHING, BOTTLES FILLING / HANDLING E FEIGE 2 0
Category B
D38.9 NEUPAK
D38.9 OCME S.R.L.
D38.9 PACK REALIZATION
D38.9 SERAC
PACKAGING & WEIGHING, CASES / CARTONS ERECTORS Standardization -
D38.10 E CERMEX 2 0
AND CLOSERS - AUTOMATIC HOT MELT Category B
D38.10 COMBI
D38.10 KRONES
D38.10 LOVESHAW
D38.10 WAYNE AUTOMATION
PACKAGING & WEIGHING, CASES / CARTONS ERECTORS Standardization -
D38.11 E 3M PACKAGING 2 0
AND CLOSERS - TAPING UNIT Category B
D38.11 LOVESHAW
D38.11 SIAT S.P.A.
St d di ti -
Standardization
D38.12 PACKAGING & WEIGHING, CASES LOADING EQUIPMENT E ACMI 2 0
Category B
D38.12 CERMEX
D38.12 COMBI
D38.12 KRONES
D38.12 OCME S.R.L.
PACKAGING & WEIGHING, CODING / PRINTING EQUIPMENT - Standardization -
D38.13 E BOPACK 2 0
BARCODE LABELS Category B
D38.13 PEAK TECHNOLOGIES
PACKAGING & WEIGHING, CODING / PRINTING EQUIPMENT - Standardization -
D38.14 E DIGITAL DESIGN (GENESIS) 2 0
LARGE CHARACTER Category B
D38.14 IMAJE
D38.14 VIDEO JET TECHNOLOGIES
PACKAGING & WEIGHING, CODING / PRINTING EQUIPMENT - Standardization -
D38.15 E DOMINO PRINTING SCIENCES 2 0
LASER CODING Category B
PACKAGING & WEIGHING, CODING / PRINTING EQUIPMENT - Standardization -
D38.16 E IMAJE 2 0
SMALL CHARACTER Category B
MARKEM SOLUTIONS CENTER
D38.16
N.V.
D38.16 VIDEO JET TECHNOLOGIES
Standardization -
D38.17 PACKAGING & WEIGHING, CONVEYORS - ACCUMULATION E HARTNESS INTERNATIONAL 2 0
Category B
D38.17 PORTEC
Standardization -
D38.18 PACKAGING & WEIGHING, CONVEYORS - BAGS E BEUMER 2 0
Category B
CONTROL DESIGN &
D38.18
MANUFACTURING
D38.18 MOELLERS
ARROWHEAD CONVEYOR Standardization -
D38.19 PACKAGING & WEIGHING, CONVEYORS - CASES / BOTTLES E 2 0
CORPORATION Category B
D38.19 HYTROL
D38.19 SIDEL
FKI LOGISTEX AUTOMATION Standardization -
D38.20 PACKAGING & WEIGHING, CONVEYORS - DRUMS E 2 0
DIVISION Category B
D38.20 HYTROL
D38.20 SIEMENS DEMATIC
D38.20 SPECIALTY EQUIPMENT
Standardization -
D38.21 PACKAGING & WEIGHING, CONVEYORS - PALLETS E BEUMER 2 0
Category B
CONTROL DESIGN &
D38.21
MANUFACTURING
FKI LOGISTEX AUTOMATION
D38.21
DIVISION
D38.21 MOELLERS
D38.21 SIEMENS DEMATIC
D38.21 SPECIALTY EQUIPMENT
PACKAGING & WEIGHING, CONVEYORS - TELESCOPING NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC Standardization -
D38.22 E STEWART GLAPAT 2 0
(BELTS) Category B
Standardization -
D38.23 PACKAGING & WEIGHING, DEPALLETIZERS - BOTTLES E ACMI 2 0
Category B

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D38.23 KRONES
D38.23 OCME S.R.L.
Standardization -
D38.24 PACKAGING & WEIGHING, EQUIPMENT - CHECK SCALES E METTLER - TOLEDO
Category B
D38.24 MOELLERS
D38.24 THOMPSON SCALE
PACKAGING & WEIGHING, EQUIPMENT - DRUMS / IBC / Standardization -
D38.25 E CARDINAL SCALE 2 0
PLATFORM SCALES Category B
D38.25 FAIRBANKS SCALES
D38.25 METTLER - TOLEDO
D38.25 THOMPSON SCALE
PACKAGING & WEIGHING, EQUIPMENT - NET WEIGH Standardization -
D38.26 E HAVER & BOECKER 2 0
SCALES Category B
LIBRAWERK
D38.26
MASCHINENFABRIK GMBH
D38.26 PREMIER TECH CHRONOS
D38.26 WEBER MARKING SYSTEMS
PACKAGING & WEIGHING, GLUE APPLICATION EQUIPMENT - NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC Standardization -
D38.27 E NORDSON 2 0
HOT GLUE SYSTEM Category B
PACKAGING & WEIGHING, GLUE APPLICATION EQUIPMENT - NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC Standardization -
D38.28 E LOCK N' POP 2 0
PALLET STABILIZATION / UNITIZING Category B
PACKAGING & WEIGHING, IBC / DRUMS / PAILS FILLING & Standardization -
D38 29
D38.29 E FEIGE 2 0
HANDLING Category B
D38.29 FULLER-KOVAKO
D38.29 OCME S.R.L.
D38.29 SPECIALTY EQUIPMENT
D38.29 UNI.MAC
D38.29 VELCON
PACKAGING & WEIGHING, IBC / DRUMS / PAILS FILLING & Standardization -
D38.30 E FEIGE 2 0
HANDLING - PAIL / JERRYCAN FILLING Category B
D38.30 NEUPAK
D38.30 PACK REALIZATION
Standardization -
D38.31 PACKAGING & WEIGHING, INSPECTION SYSTEMS E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC DVT CORPORATION 2 0
Category B
Standardization -
D38.32 PACKAGING & WEIGHING, LABELING EQUIPMENT E AVERY-DENNISON 2 0
Category B
D38.32 BOPACK
D38.32 CCL (ACCRAPLY)
D38.32 GEOSTICK
MARKEM SOLUTIONS CENTER
D38.32
N.V.
D38.32 PAGO
D38.32 QUADREL LABELING
SCHLEUTER MASCHINENBAU
D38.32
GMBH
D38.32 WEBER MARKING SYSTEMS
Standardization -
D38.33 PACKAGING & WEIGHING, PALLETIZERS - BAGS E BEMIS COMPANY 2 0
Category B
D38.33 BEUMER
CONTROL DESIGN &
D38.33
MANUFACTURING
D38.33 MOELLERS
Standardization -
D38.34 PACKAGING & WEIGHING, PALLETIZERS - CARTONS E OCME S.R.L. 2 0
Category B
D38.34 VON GAL
Standardization -
D38.35 PACKAGING & WEIGHING, PALLETIZERS - DRUMS E FEIGE 2 0
Category B
D38.35 PASCO
D38.35 SPECIALTY EQUIPMENT
D38.35 UNI.MAC
PACKAGING & WEIGHING, ROBOTIC EQUIPMENT / Standardization -
D38.36 E ABB 2 0
SYSTEMS Category B
D38.36 BEUMER
D38.36 C & D ROBOTICS
D38.36 COSTI
D38.36 FANUC
D38.36 GE
D38.36 MOELLERS
D38.36 OCME S.R.L.
PACKAGING & WEIGHING, ROBOTIC MANULIPULATORS / Standardization -
2 D38.37 E COLUMBIA / OKURA 2 0
LIFTS ASSISTS - ALL PACKAGE TYPES Category B
DALMEC INDUSTRIAL
D38.37
MANIPULATORS
D38.37 PALAMATIC
D38.37 TAWI
D38.37 VACU-HOIST
PACKAGING & WEIGHING, ROBOTIC MANULIPULATORS / Standardization -
2 D38.38 E EASY LIFT EQUIPMENT 2 0
LIFTS ASSISTS - DRUMS HANDLING / DUMPING Category B
D38.38 INTERTHOR
D38.38 M. O . INDUSTRIES
MATERIAL TRANSFER AND
D38.38
STORAGE
PACKAGING & WEIGHING, ROBOTIC MANULIPULATORS / Standardization -
2 D38.39 E ADVANCE LIFTS 2 0
LIFTS ASSISTS - LIFT TABLES Category B
D38.39 AUTOQUIP
D38.39 BISHAMON
D38.39 ECONOLIFT
D38.39 HYMO
PACKAGING & WEIGHING, SEALING - BAGS SEWING Standardization -
D38.40 E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC UNION SPECIAL MACHINE 2 0
EQUIPMENT Category B
PACKAGING & WEIGHING, SEALING EQUIPMENT - BAGS
D38.41 E FISCHBEIN
HEAT - ALL TYPES
D38.41 NEWLONG
D38.41 SIG DOBOY
PACKAGING & WEIGHING, SEALING EQUIPMENT - FILM Standardization -
D38.42 E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC VERTROD / TECHNASEAL 2 0
BAGS Category B
PACKAGING & WEIGHING, SEALING EQUIPMENT -
D38.43 E ENERCON INDUSTRIES 2 0
INDUCTION SEALING (BOTTLES)
D38.43 LEPEL
D38.43 PILLAR INDUCTION

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC OPTIMA FILLING AND Standardization -
D38.44 PACKAGING & WEIGHING, SHRINKWRAPPERS E 2 0
PACKAGING MACHINES GMBH Category B
D38.45 PACKAGING & WEIGHING, STRETCHHOODER E BEUMER 2 0
D38.45 MOELLERS
Standardization -
D38.46 PACKAGING & WEIGHING, STRETCHWRAPPERS E BORDEN/MATCO 2 0
Category B
BORST PACKAGING SYSTEMS
D38.46
BV
D38.46 ITW
D38.46 LANTECH
Standardization -
D38.47 PACKAGING & WEIGHING, TRUCK WEIGH SCALES E AVERY WEIGH-TRONIX 2 0
Category B
D38.47 EMERY WINSLOW SCALE
D38.47 EWB
D38.47 METTLER - TOLEDO
D38.47 MOLEN
D38.47 SCHENCK
PACKAGING & WEIGHING, UNLOAD / DUMP STATION - BAG Standardization -
D38.48 E LUXME 2 0
DUMP STATION Category B
D38.48 PALAMATIC
D38.48 YOUNG INDUSTRIES
PACKAGING & WEIGHING, UNLOAD / DUMP STATIONS - Standardization -
D38 49
D38.49 E M O . INDUSTRIES
M. 2 0
DRUMS / PACK DUMP STATIONS Category B
MATERIAL TRANSFER AND
D38.49
STORAGE
PACKAGING & WEIGHING, MAGNETS, METAL DETECTION Standardization -
D38.50 E ARGENMAT 2 0
AND METAL REMOVAL Category B
D38.50 ERIEZ MAGNETICS
D38.50 FJI
GOUDSMIT MAGNETIC
D38.50
SYSTEMS B.V.
D38.50 MAGNETIC PRODUCTS
D38.50 MOFFAT
D38.50 S+S
SARTORIUS AACHEN GMBH &
D38.50
CO
2 D39.0 PUMPS
PUMP, CENTRIFUGAL: API-610, OVERHUNG, SINGLE STAGE Standardization -
4 D39.1 E EBARA 2 2
HORIZONTAL (TYPE OH) Category A
FLOWSERVE (BWIP/BYRON
D39.1
JACKSON/WILSON SNYDER)
4 D39.1 FLOWSERVE AL-RUSHAID
Standardization -
Category A, ITT
4 D39.1 ITT (GOULDS PUMPS) Goulds is the
selected PLA
Vendor
D39.1 KSB
D39.1 SAUDI PUMP FACTORY (SA)
D39.1 SULZER PUMPS
PUMP, CENTRIFUGAL: API-610, MULTI-STAGE HORIZONTAL,
3 D39.2 E EBARA 3 3
AXIALLY OR RADIALLY SPLIT (TYPE BB)
FLOWSERVE (BWIP/BYRON
D39.2
JACKSON/WILSON SNYDER)
D39.2 ITT (GOULDS PUMPS)
2 D39.2 SAUDI PUMP FACTORY (SA)
D39.2 SULZER PUMPS
2 D39.3 NOT USED
PUMP, CENTRIFUGAL: API-610, SINGLE STAGE VERTICAL IN- EBARA CORPORATION Standardization -
4 D39.4 E 2 2
LINE (TYPE OH3) FUJISAWA PLANT Category A
FLOWSERVE (BWIP/BYRON
D39.4
JACKSON/WILSON SNYDER)
FLOWSERVE AL-RUSHAID
4 D39.4
(SA)
Standardization -
Category A, ITT
4 D39.4 ITT (GOULDS PUMPS) Goulds is the
selected PLA
Vendor
D39.4 SAUDI PUMP FACTORY (SA)
D39.4 SULZER PUMPS
PUMP, CENTRIFUGAL: VERTICAL SINGLE STAGE, VOLUTE
D39.5 E FLOWSERVE (STORK) 2 1
TYPE (SUMP)
D39.5 ITT (FLYGT)
SAUDI MECHANICAL
D39.5
INDUSTRIES (SA)
D39.5 SAUDI PUMP FACTORY (SA)
D39.5 SULZER PUMPS
EBARA CORPORATION
3 D39.6 PUMP, CENTRIFUGAL: MULTI-STAGE VERTICAL (API-610) E 2 3
FUJISAWA PLANT
FLOWSERVE (BWIP/BYRON
D39.6
JACKSON/WILSON SNYDER)
D39.6 ITT (GOULDS PUMPS)
D39.6 SAUDI PUMP FACTORY (SA)
D39.6 SULZER PUMPS
D39.7 PUMP, CENTRIFUGAL: VERTICAL MOLTON SULFUR E CHARLES S. LEWIS PUMP 2 1
FRIATEC - RHEINHUETTE
D39.7
GMBH & CO
D39.7 ITT (GOULDS PUMPS)
D39.7 WEIR GABBIONETA SRL
Standardization -
PUMP, CENTRIFUGAL: BETWEEN BEARING DOUBLE Category A, DMW
4 D39.8 E DMW CORPORATION 2 3
SUCTION CENTRIFUGAL (NON-API COOLING TOWER) is the selected
PLA Vendor
D39.8 EBARA
D39.8 FLOWSERVE
FLOWSERVE AL-RUSHAID
4 D39.8
(SA)
D39.8 ITT (GOULDS PUMPS)
4 D39.8 ITT SAUDI COMPANY (SA)
D39.8 KSB

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D39.8 SAUDI PUMP FACTORY (SA)


4 D39.8 SULZER PUMPS
PUMP, CENTRIFUGAL: BETWEEN BEARING DOUBLE
Standardization -
4 D39.9 SUCTION, SINGLE STAGE CENTRIFUGAL (API-610) (TYPE E EBARA 2 3
Category A
BB1/BB2)
D39.9 FLOWSERVE
FLOWSERVE AL-RUSHAID
4 D39.9
(SA)
Standardization -
Category A, ITT
4 D39.9 ITT (GOULDS PUMPS) Goulds is the
selected PLA
Vendor
D39.9 KSB
D39.9 SAUDI PUMP FACTORY (SA)
D39.9 SULZER
PUMP, CENTRIFUGAL; MAGNETIC DRIVE; HORIZONTAL Standardization -
4 D39.10 E ANSIMAG 2 1 Lined Pumps Only
(ASME B73.3) Category A
D39.10 DICKOW PUMP COMPANY
Retrofit of existing sealed
4 D39.10 FLOWSERVE (DURCO)
pumps only
FLOWSERVE AL-RUSHAID
4 D39 10
D39.10
(SA)
D39.10 HERMETIC PUMPEN GMBH
Standardization -
Category A, HMD
4 D39.10 HMD/KONTRO (SUNDYNE) Kontro is the
selected PLA
Vendor
4 D39.10 INNOMAG Lined Pumps Only.
Retrofit of existing sealed
4 D39.10 ITT (GOULDS PUMPS)
pumps only
D39.10 KLAUS-UNION
2 D39.11 NOT USED
D39.12 PUMP, CENTRIFUGAL; AXIAL FLOW E ITT (GOULDS PUMPS) 2 1
D39.12 KSB
D39.12 LAWRENCE PUMPS
D39.12 SULZER PUMPS
WEIR CLEAR LIQUID DIVISION
D39.12
(BEGEMANN PUMPS)
Standardization -
PUMP, CENTRIFUGAL: NON-API SEALED HORIZONTAL END Category A,
4 D39.13 E FLOWSERVE (DURCO) Flowserve is the 2 1
SUCTION (ASME B73.1 AND PULP AND PAPER)
selected PLA
Vendor
FLOWSERVE AL-RUSHAID
4 D39.13
(SA)
D39.13 ITT (GOULDS PUMPS)
D39.13 SAUDI PUMP FACTORY (SA)
Standardization -
PUMP CENTRIFUGAL: NON-API
PUMP, NON API SEALED VERTICAL INLINE; Category
Catego y A,,
4 D39.14 E FLOWSERVE (DURCO) Flowserve is the 2 1
ASME B73.2
selected PLA
Vendor
FLOWSERVE AL-RUSHAID
4 D39.14
(SA)

D39.14 ITT (GOULDS PUMPS)


Standardization -
4 D39.15 PUMP, CENTRIFUGAL: CANNED MOTOR; Type ASME B73.3M E HERMETIC 2 1
Category A
Standardization -
SUNDYNE / NIKKISO (EX- Category A,
4 D39.15 SUNDYNE DESIGNS AND SGM Nikisso is the
SERIES) selected PLA
Vendor
D39.15 TEIKOKU / CHEMPUMP
4 D39.16 PUMP, CENTRIFUGAL: INTEGRALLY GEARED (TYPE OH6) E SUNDYNE 2 1
CAVITRON V. HAGEN &
D39.17 PUMP, CENTRIFUGAL CHOPPING E 2 1
FUNKE GMBH
D39.17 CP PUMPEN AG
D39.17 HOELSCHER
D39.17 SIEFER
D39.17 VAUGHAN CO
FRIATEC - RHEINHUETTE
D39.18 PUMP, CENTRIFUGAL, HORIZONTAL, MOLTEN SULFUR E 2 1
GMBH & CO
D39.18 WEIR GABBIONETA SRL
PUMP, CENTRIFUGAL: LOW FLOW HIGH HEAD
2 D39.19 E DICKOW PUMP COMPANY 2 2
CENTRIFUGAL (SINGLE & MULTI STAGE)
D39.19 FLOWSERVE (IDP)
D39.19 HERMETIC
D39.19 ITT ((FLYGT))
D39.19 ITT (GOULDS PUMPS)
D39.19 REIHANSL GMBH
D39.19 SULZER PUMPS
D39.19 SUNDYNE
WEIR SPECIALTY PUMPS
D39.19
(ROTO-JET PUMP)
PUMP, RECIPROCATING, DIRECT ACTING, GEAR DRIVEN
D39.20 E FLOWSERVE (IDP) 2 1
(API - 674)
D39.20 PERONI POMPE SPA
D39.20 RAM PUMPS LTD
PUMP, RECIPROCATING, POSITIVE DISPLACEMENT,
2 D39.21 E FLOWSERVE (IDP) 2 2
SLURRY
FLOWSERVE (WILSON
D39.21
SNYDER)
MCCARTNEY
D39.21
MANUFACTURING
D39.21 MILTON ROY (WILLIAMS)
D39.21 URACA
D39.21 WEATHERFORD ALS (KOBE)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D39.22 PUMP, ROTARY POS. DISPLACEMENT - GEAR TYPE E FLOWSERVE 2 0


COLFAX AMERICAS (IMO
D39.22
PUMP)
D39.22 LEWA (LCI)
D39.22 MAAG PUMP SYSTEMS
D39.22 TUTHILL
D39.22 VIKING PUMP

2 D39.23 PUMP, ROTARY POS. DISPLACEMENT - POLYMER GEAR E MAAG PUMP SYSTEMS 2 3

SEBEWAING TOOL &


D39.23
ENGINEERING COMPANY
D39.23 VANICO
D39.23 WITTE
PUMP, ROTARY; POS. DISPLACEMENT - PROGRESSIVE COLFAX AMERICAS
2 D39.24 E 2 1
CAVITY (ALLWEILER)
JOH. HEINR. BORNEMANN
D39.24
GMBH
D39.24 MOYNO
PUMP, ROTARY POS. DISPLACEMENT - SCREW TYPE API- FLOWSERVE/'IDP (SIER-BATH)
2 D39.25 E 2 2
676 (WORTHINGTON)
COLFAX AMERICAS (WARREN
D39.25
PUMPS)
4 D39.25 IMO PUMPS
D39.25 LEISTRITZ
2 D39.26 PUMP, SUBMERSIBLE E AURORA HYDROMATIC 2 1
D39.26 EBARA
D39.26 ENVIRONMENT ONE
D39.26 ITT (FLYGT)
D39.26 ITT (GOULDS PUMPS)
D39.26 KSB
D39.26 MYERS

D39.26 PEERLESS PUMP COMPANY


WEIR SPECIALTY PUMPS
D39.26
(WEMCO PUMP)
2 D39.27 PUMP, DIAPHRAGM (AIR OPERATED) E ALFA LAVAL 2 1
D39.27 FLOTRONIC PUMPS
D39.27 IR ARO
D39.27 VERDER
D39.27 VERSA-MATIC (DOMINATOR)
WANNER ENGINEERING
D39.27
(HYDRA-CELL)
D39.27 WARREN RUPP (SANDPIPER)
WILDEN PUMP &
D39.27
ENGINEERING
D39.27 YAMADA
PUMP, METERING (INCLUDING API - 675 CONTROL Standardization -
2 D39.28 E BRAN-LUEBBE 2 0
VOLUME) Category B
D39.28 LEWA
D39 28
D39.28 MILTON ROY (GEAR TYPE)
D39.28 MILTON ROY (LINC) (LMI)
D39.28 NIKKISO HYDROFLO
D39.28 PASCAL (GEAR TYPE)
D39.28 PROMINENT (ORLITA)
PULSAFEEDER (ECO) (GEAR
D39.28
TYPE)
COLFAX AMERICAS (ZENITH
2 D39.28
PUMPS -GEAR TYPE)
D39.29 PUMP, PERISTALIC E ALFA LAVAL 2 0
D39.29 COLE-PARMER INSTRUMENT
CRANE PROCESS FLOW
D39.29
TECHNOLOGIES
D39.29 MASTERFLEX
D39.29 WATSON-MARLOW BREDEL
D39.30 PUMP, REGENERATIVE TURBINE E DICKOW PUMP 2 1
D39.30 FLOWSERVE (IDP)
D39.30 KSB
D39.30 PEERLESS PUMP
D39.30 ROTH PUMP
D39.30 SUNDYNE
2 D39.31 PUMP, ROTARY POSITIVE DISPLACEMENT - SEALLESS E HERMETIC 2 1
COLFAX AMERICAS (IMO
D39.31
PUMP)
D39.31 PULSAFEEDER (ISOCHEM)
D39.31 VIKING PUMP
2 D39.32 PUMP, ROTARY, VANE, API 676 E BLACKMER 2 0
D39.32 EBS-RAY PUMPS PTY
D39.32 SPX PROCESS EQUIPMENT
D39.33 PUMP,, SELF PRIMING E FLOWSERVE ((DURCO)) 2 0
D39.33 ITT (GOULDS PUMPS)
3 D39.34 PUMP, SELF PRIMING HORIZONTAL SUMP PUMP E FLOWSERVE 2 0
FLOWSERVE AL-RUSHAID -
KSA
ITT (GOULDS PUMPS)
SAUDI PUMP FACTORY (SA)
2 D40.0 REFRIGERATION UNITS
REFRIGERATION UNIT, ABSORPTION REFRIGERATION Standardization -
D40.1 E TRANE 3 2
UNITS (ARU) Category E
D40.1 YORK PROCESS SYSTEMS
REFRIGERATION UNIT, MECHANICAL REFRIGERATION
Standardization -
D40.2 UNITS (MRU) - LIGHT DUTY PROCESS REFRIGERATION E GEA / FES SYSTEMS 3 2
Category E
EQUIPMENT
D40.2 TRANE
D40.2 YORK PROCESS SYSTEMS
REFRIGERATION UNIT, MECHANICAL REFRIGERATION Standardization -
2 D40.3 E GEA / FES SYSTEMS 3 3
UNITS (MRU) - PROCESS REFRIGERATION Category E

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

GEA INDUSTRIE
D40.3 TECHNOFRIGO DELL'ORTO
S.P.A.
3 D40.3 ENERFLEX LTD
D40.3 YORK PROCESS SYSTEMS
Standardization -
4 D40.4 REFRIGERATION UNIT, SAFETY SHOWER WATER SKIDS E HYDROTHRIFT CORPORATION 1 2
Category A
D41.0 ROTARY KILNS
D41.1 ROTARY KILNS E ABB INC 3 0
D41.1 MAN TURBO
D41.1 VON ROLL
2 D42.0 SEALS AND PACKING
Standardization -
Category A, Eagle
SEALS AND PACKING, MECHANICAL SEALS FOR PUMPS
4 D42.1 E EAGLE BURGMANN Burgmann is 1 of 2 1 0
(LIQUID AND DRY GAS)
selected PLA
Vendors
Standardization -
FLOWSERVE FSD (SEAL
Category A,
GROUP) - INCLUDING
4 D42.1 Flowserve is 1 of 2
DURAMETALLIC/ BWIP/
selected PLA
PACIFIC
Vendors
4 D42.1 FLOWSERVE ABAHSAIN
JOHN CRANE (INCLUDING
FLEXIBOX & SEALOL)
JOHN CRANE SAUDI ARABIA
4 D42.1
(SA)
Standardization -
FLOWSERVE FSD (SEAL
Category A,
GROUP) - INCLUDING
4 D42.2 SEALS AND PACKING, SEAL POTS B Flowserve is the 1 0
DURAMETALLIC/ BWIP/
selected PLA
PACIFIC
Vendor
4 D42.2 FLOWSERVE ABAHSAIN
JOHN CRANE SAUDI ARABIA
4 D42.2
(SA)
D42.2 K-TEK
Standardization -
Category A, Eagle
4 D42.3 MECHANICAL SEALS FOR COMPRESSORS - DRY GAS E EAGLE BURGMANN Burgmann is the 1 0
selected PLA
Vendor
FLOWSERVE FSD (SEAL
D42.3 GROUP)-INCLUDING
DURAMETALLIC/BWIP/PACIFIC

JOHN CRANE (INCLUDING


D42.3
FLEXIBOX & SEALOL)

2 D43.0 SILENCERS
Standardization -
2 D43.1 SILENCERS B BURGESS-MANNING 1 0
Category C
GARDNER DENVER
D43.1
(HOFFMAN)
D43.1 MAXIM SILENCERS
D43.1 STODDARD SILENCERS
UNIVERSAL SILENCER
D43.1
(NELSON INDUSTRIES)
Standardization -
2 D44.0 SOLIDS HANDLING SYSTEMS
Category B
D44.1 SOLID HANDLING SYSTEM, BELT CONVEYORS E DINNISSEN BV 2 1
D44.1 FMC TECHNOLOGIES
D44.1 J. ENGELSMANN AG
D44.1 MICHELOTTI
D44.1 REXNORD (LINK-BELT)
D44.1 SEGLER

D44.1 SHAUANGLONG (SINGAPORE)

SIEMENS DEMATIC
D44.1
(RAPISTAN)
NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC NICOR INTERNATIONAL
D44.2 SOLID HANDLING SYSTEM, BELTED PRODUCT THROWERS E 2 1
HOLLAND
D44.3 SOLID HANDLING SYSTEM, BUCKET ELEVATORS E BUCK-EL 2 1
D44.3 DRESSER INDUSTRIES
D44.3 J. ENGELSMANN AG
D44.3 MITSUBISHI
D44.3 REXNORD
D44.3 SENGLER
D44.4 SOLID HANDLING SYTEM, DIVERTER VALVES E COPERION WAESCHLE 2 1
D44.4 FULLER-KOVAKO
D44.4 MOTAN
D44.4 SALINA VORTEX
D44.4 YOUNG INDUSTRIES
D44.4 ZEPPELIN

D44.5 SOLID HANDLING SYSTEM, ELUTRIATORS - CLEAN E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC PELLETRON CORPORATION 2 1

D44.6 SOLID HANDLING SYSTEM, ELUTRIATORS - GENERAL E CARTER DAY INTERNATIONAL 2 1


D44.6 COPERION WAESCHLE
D44.6 KICE INDUSTRIES
D44.6 ZEPPELIN
AGRICHEMA
D44.7 SOLID HANDLING SYSTEM, LIVE BINS BOTTOMS E MATERIALFLUSSTECHNIK 2 1
GMBH & CO
D44.7 BRABENDER TECHNOLOGIE

D44.7 CARMAN INDUSTRIES


D44.7 MATCON
D44.7 METALFAB

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D44.7 VIBRA SCREW


SOLID HANDLING SYSTEM, MECHANICAL AGITATORS
2 D44.8 E BEPEX INTERNATIONAL 2 1
BLENDERS

D44.8 FORBERG INTERNATIONAL AS

D44.8 GERICKE AG
HENSCHEL MIXING
D44.8
TECHNOLOGY SERVICE
D44.8 J. ENGELSMANN AG
D44.8 LITTLEFORD DAY
D44.8 LOEDIGE (DIVISION DRAIS)
D44.8 MAGUIRE BLENDERS
D44.8 RUBERG
D44.8 YOUNG INDUSTRIES
SOLID HANDLING SYSTEM, MECHANICAL TUMBLE
D44.9 E HITACHI LTD 2 1
BLENDERS
D44.9 KREYENBORG
D44.9 LITTLEFORD DAY
D44.9 LOEDIGE
D44.9 PATTERSON-KELLEY
D44 10
D44.10 SOLID HANDLING SYSTEM
SYSTEM, PNEUMATIC BLENDERS E 2 1
SOLID HANDLING SYSTEM, PNEUMATIC CONVEY - DENSE
D44.11 E COPERION WAESCHLE 2 1
PHASE
D44.11 DYNAMIC AIR
D44.11 GERICKE AG
D44.11 MAC EQUIPMENT
D44.11 NEU INTERNATIONAL
D44.11 ZEPPELIN
SOLID HANDLING SYSTEM, PNEUMATIC CONVEY - DILUTE AVITEQ VIBRATIONSTECHNIK
D44.12 E 2 1
PHASE GMBH
COPERION MACHINERY &
D44.12
SYSTEMS (SHANGHAI)
D44.12 COPERION WAESCHLE
FOREMOST MACHINE
D44.12
BUILDERS
D44.12 GERICKE AG
GOVONI SIM BIANCA IMPIANTI
D44.12
S.P.A.
D44.12 J. ENGELSMANN AG
D44.12 JOEST GMBH & CO KG
D44.12 NEU INTERNATIONAL
SHANGHAI BLOOM POWER
D44.12
ENGINEERING
D44.12 YOUNG INDUSTRIES
D44.12 ZEPPELIN
ANDRITZ (SPROUT-BAUER
D44.13 SOLID HANDLING SYSTEM, ROTARY VALVES E 2 1
EQUIPMENT)
D44.13 COPERION WAESCHLE
D44.13 FULLER-KOVAKO
D44 13
D44.13 HOWDEN
D44.13 JAUDT
D44.13 MAC EQUIPMENT
D44.13 MOTAN
D44.13 YOUNG INDUSTRIES
D44.13 ZEPPELIN
D44.14 SOLID HANDLING SYSTEM, SAMPLERS (SOLIDS) E COPERION WAESCHLE 2 1
D44.14 GUSTAFSON
D44.14 INTER SYSTEMS
D44.14 J. ENGELSMANN AG
D44.14 MOTAN
D44.14 SCHUETTEMEYER
D44.14 SICON
D44.14 ZEPPELIN
D44.15 SOLID HANDLING SYSTEM, SCREW CONVEYORS E ACOTEC 2 1
D44.15 BORRACHAS DA PENHA
CONTINENTAL SCREW
D44.15
CONVEYOR
D44.15 FLEXICON
D44.15 HI-LINE
D44.15 J. ENGELSMANN AG
D44.15 KOMAR INDUSTRIES

D44.15 MARTIN SPROCKET & GEAR

D44.15 MASTERBOR
D44.15 SENGLER
D44.15 THERMA-FLITE
D44.15 THOMAS CONVEYOR
SOLID HANDLING SYSTEM,
SYSTEM SCREW FEEDERS - CUSTOM NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC
D44.16
D44 16 E JENIKE & JOHANSON,
JOHANSON INC 2 1
ENGINEERED MASS FLOW
D44.17 SOLID HANDLING SYSTEM, SCREW FEEDERS - GENERAL E ACCURATE 2 1
D44.17 ACRISON
D44.17 BRABENDER TECHNOLOGIE
D44.17 CONAIR
D44.17 GERICKE AG
D44.17 J. ENGELSMANN AG
D44.17 K-TRON
D44.17 SCHENCK-ACCURATE
D44.17 SENGLER
D44.17 SEWON HEAVY INDUSTRIES
D44.17 VIBRA SCREW
D44.18 SOLID HANDLING SYSTEM, SHAKER SCREENERS E ABB CELLIER S.A. 2 1
D44.18 ALLGAIER WERKE GMBH
D44.18 FRIEDBURG
D44.18 J. ENGELSMANN AG
D44.18 JOEST GMBH & CO KG

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

D44.18 KASON
D44.18 MOGENSEN
D44.18 ROTEX
D44.18 SWECO
D44.18 WITTE
D44.19 SOLID HANDLING SYSTEM, SILO BLENDERS - DYNAMIC E COPERION WAESCHLE 2 1
D44.19 FULLER-KOVAKO
D44.19 ZEPPELIN
D44.20 SOLID HANDLING SYSTEM, SILO BLENDERS - STATIC E AVERY MASCHINEN GMBH 2 1
D44.20 COLUMBIAN TECTANK
D44.20 CONAIR
D44.20 COPERION WAESCHLE
D44.20 MOELLERS
D44.20 YOUNG INDUSTRIES
D44.20 ZEPPELIN
D44.21 SOLID HANDLING SYSTEM, SLIDE GATE VALVES E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC MAC EQUIPMENT 2 1
SOLID HANDLING SYSTEM, STORAGE / HANDLING VALVES -
D44.22 E COPERION WAESCHLE 2 1
GENERAL
D44.22 DEZURIK
D44.22 J. ENGELSMANN AG
D44.22 MAC EQUIPMENT
D44.22 SALINA VORTEX
D44.22 SCHUTTE-MEYER
D44.23 SOLID HANDLING SYSTEM, VALVED AIRLOCKS E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC MAC EQUIPMENT 2 1

AVITEQ VIBRATIONSTECHNIK
D44.24 SOLID HANDLING SYSTEM, VIBRATING CONVEYORS E 2 1
GMBH

D44.24 CARMAN INDUSTRIES


D44.24 CARRIER
D44.24 FMC TECHNOLOGIES
D44.24 FRIEDBURG
D44.24 GENERAL KINEMATICS
D44.24 JOEST GMBH & CO KG
D44.24 SCHENCK
D44.24 VIBRA SCREW
D44.25 SOLID HANDLING SYSTEM, WEIGH FEEDERS E ACCURATE 2 1
D44.25 ACRISON
D44.25 AZO GMBH & CO. KG
D44.25 BRABENDER TECHNOLOGIE
D44.25 ERIEZ MAGNETICS
FOREMOST MACHINE
D44.25
BUILDERS
D44.25 GERICKE AG
D44.25 K-TRON
D44.25 SCHENCK-ACCURATE
D44.25 SEISHIN ENTERPRISE
D44.25 VIBRA SCREW
2 D45.0 TURBINES
ALSTOM POWER
D45.1 TURBINE, GAS - INDUSTRIAL TYPES (API - 616) E 3 3
GENERATION AG
D45.1 ALSTOM POWER LIMITED
GENERAL ELECTRIC
D45.1
INDUSTRIAL
HITACHI LTD POWER
D45.1
SYSTEMS
MIDDLE EAST POWER
D45.1
COMPANY (SA)
MITSUBISHI HEAVY
D45.1
INDUSTRIES
NUOVO PIGNONE SPA -
D45.1
TURBOMACHINERY
D45.1 SIEMENS CANADA
SIEMENS INDUSTRIAL
D45.1
TURBOMACHINERY
D45.2 TURBINE, GAS - AERODERIVIATIVE TYPES E GE ENGINE SERVICES 3 3
MITSUBISHI HEAVY
D45.2
INDUSTRIES
NUOVO PIGNONE SPA -
D45.2
TURBOMACHINERY
D45.2 PRATT AND WHITNEY
D45.2 ROLLS ROYCE
D45.2 ROLLS-ROYCE CANADA
D45.2 SOLAR TURBINES
D45.3 TURBINE, GAS - GENERATORS SETS E GE ENGINE SERVICES 3 3
MITSUBISHI HEAVY
D45.3
INDUSTRIES
NUOVO PIGNONE SPA -
D45.3
TURBOMACHINERY
D45.3 PRATT AND WHITNEY
D45.3 ROLLS ROYCE
D45.3 ROLLS-ROYCE CANADA
D45.3 SOLAR TURBINES

DEMAG (SIEMENS) DELAVAL Standardization -


2 D45.4 TURBINE, GENERAL PURPOSE STEAM (API - 611) E 2 1
TURBOMACHINERY B.V. Category B

D45.4 DRESSER RAND SA


ELLIOTT EBARA
D45.4
TURBOMACHINERY
D45.4 MAN TURBO
MITSUBISHI HEAVY
D45.4
INDUSTRIES
DEMAG (SIEMENS) DELAVAL Standardization -
2 D45.5 TURBINE, SPECIAL PURPOSE STEAM (API - 612) E 2 3
TURBOMACHINERY B.V. Category E

D45.5 DRESSER RAND SA


ELLIOTT EBARA
D45.5
TURBOMACHINERY

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

4 D45.5 GE OIL & GAS


MITSUBISHI HEAVY
D45.5
INDUSTRIES
D45.5 MAN TURBO
D45.6 TURBINE, STEAM GENERATORS SETS E DRESSER-RAND 3 3
D45.6 ELLIOTT
D45.6 GE
D45.6 SIEMENS
2 D45.7 TURBINE, HYDRAULIC E NOT ANTICIPATED FOR RTIP - NOT TECHNOLOGY SPECIFIC 2 3
D46.0 TURBO EXPANDERS
ATLAS COPCO MAFI TRENCH Standardization -
D46.1 TURBO EXPANDER, CRYOGENIC APPLICATIONS E 3 3
COMPANY Category B
D46.1 CRYOSTAR SAS
Standardization -
D46.2 TURBO EXPANDER, GAS EXPANSION E DRESSER RAND SA 3 3
Category B
ELLIOTT EBARA
D46.2
TURBOMACHINERY
D47.0 VAPORIZERS
ARMSTRONG ENGINEERING
D47.1 VAPORIZER, CRYOGENIC E 3 2
ASSOCIATES
D47.1 CHEMTEC PTE
D47 1
D47.1 CHEMTEC UK
D47.1 LINDE AG
MITSUBISHI HEAVY
D47.1
INDUSTRIES
D48.0 WATER TREATMENT SYSTEMS
D48.1 WATER TREATMENT SYSTEM, CLARIFIERS - THICKENERS E EMICO PROCESS EQUIPMENT 2 2

D48.1 METSO MINERALS (SALA) AB

D48.1 PARKSON
D48.1 PASSAVANT
GE INFRASTRUCTURE WATER
D48.2 WATER TREATMENT SYSTEM, LIQUID INJECTION SYSTEMS E 2 2
& PROCESS TECHNOLOGIES
D48.2 NALCO
WATER TREATMENT SYSTEM, SANITARY WASTEWATER
D48.3 E AES ARABIA LIMITED (SA) 2 2
PACKAGE TREAT PLNT
METITO ARABIA INDUSTRIES
D48.3
(SA)
SAUDI BERKEFELD FILTER
D48.3
(SA)
SIEMENS WATER
D48.3
TECHNOLOGIES
WATER TREATMENT SYSTEM, OILY WASTEWATER SIEMENS WATER
D48.4 E 3RD PARTY SUPPLY 2 2
CENTRIFUGAL TECHNOLOGIES
WATER TREATMENT SYSTEM, SANITARY WASTEWATER
D48.5 E AES ARABIA LIMITED (SA) 2 2
FILTERS
METITO ARABIA INDUSTRIES
D48.5
(SA)
NATCO GROUP/DIV OF
D48.5
NATIONAL TANK
SIEMENS WATER
D48.5
TECHNOLOGIES
WATER TREATMENT SYSTEM, UNIT, WASTEWATER
D48.6 E AES ARABIA LIMITED (SA) 2 2
PRELIMINARY TREATMENT
METITO ARABIA INDUSTRIES
D48.6
(SA)
D48.6 METITO OVERSEAS
SAUDI BERKEFELD FILTER
D48.6
(SA)
WATER TREATMENT SYSTEM, UNIT, WASTEWATER METITO ARABIA INDUSTRIES
D48.7 E 2 2
AERATION (MECHANICAL, (SA)
D48.7 METITO OVERSEAS
SAUDI BERKEFELD FILTER
D48.7
(SA)
WATER TREATMENT SYSTEM, WASTEWATER
D48.8 E AES ARABIA LIMITED (SA) 2 2
DISINFECTION-CHLORINATION
D48.8 EXCELTEC INTERNATIONAL
METITO ARABIA INDUSTRIES
D48.8
(SA)
D48.8 METITO OVERSEAS
SAUDI BERKEFELD FILTER
D48.8
(SA)
WATER TREATMENT SYSTEM,, TANK, WASTEWATER ALL
D48.9 E AES ARABIA LIMITED (SA) 2 2
WASTEWATER
METITO ARABIA INDUSTRIES
D48.9
(SA)
D48.9 METITO OVERSEAS
SAUDI BERKEFELD FILTER
D48.9
(SA)
SIEMENS WATER
D48.9
TECHNOLOGIES
WATER TREATMENT SYSTEM,, CONTROL,WASTEWATER
D48.10 E AES ARABIA LIMITED (SA) 2 0
ODOR (ACTIVATED CARBO
D48.10 CALGON CARBON
SIEMENS WATER
D48.10
TECHNOLOGIES
WATER TREATMENT SYSTEM, SANITARY WASTEWATER 3RD PARTY SIEMENS WATER
D48.11 E 3 3
MEMBRANE BIO REACTOR SUPPLY TECHNOLOGIES
4 D48.11 KOCH MEMBRANE
4 D48.11 GE POWER & WATER
WATER TREATMENT SYSTEM, OIL/WATER SEPARATION-
D48.12 E MONARCH SEPARATORS 2 2
API&CPI
NATCO GROUP / DIV OF
D48.12
NATIONAL TANK
SIEMENS WATER
D48.12
TECHNOLOGIES
WATER TREATMENT SYSTEM, OILY/WATER SEPARATION- 3RD PARTY SUPPLY SIEMENS WATER
D48.13 E 2 2
DAF&IAF TECHNOLOGIES

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Mechanical

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

WATER TREATMENT SYSTEM, OILY WASTEWATER 3RD PARTY SUPPLY SIEMENS WATER
D48.14 E 2 2
FILTERS-SAND & MULTI MED TECHNOLOGIES
WATER TREATMENT SYSTEM, OILY WASTEWATER SIEMENS WATER
D48.15 E 3RD PARTY SUPPLY 3 3
FILTERS-WALNUT&SHELL MED TECHNOLOGIES
WATER TREATMENT SYSTEM, OILY/WATER SEPARATION- SIEMENS WATER
D48.16 E 3RD PARTY SUPPLY 2 2
OIL SKIMMERS TECHNOLOGIES
WATER TREATMENT SYSTEM, SANITARY SLUDGE 3RD PARTY SUPPLY SIEMENS WATER
D48.17 E 2 2
DEWATERING TECHNOLOGIES
D48.18 WATER TREATMENT SYSTEM, AERATOR E 3RD PARTY SUPPLY LANDUSTRIE SNEEK BV 2 2
2 D49.0 DREDGERS
ELLICOTT DREDGERS
2 D49.1 DREDGERS E 2 2
(MARKEL VENTURES)
D49.1 IHC MERWEDE
D49.1 VOSTA LMG
2 D50.0 COUPLINGS
COUPLINGS, GENERAL PURPOSE, ELASTOMERIC FLEXIBLE EMERSON POWER Standardization -
4 D50.1 B 1 0
SLEEVE SPACER OR FLEXIBLE PIN TRANSMISSION (KOP-FLEX) Category A,
3 D50.1 FLENDER SIEMENS (N-
Standardization -
Category A, T.B.
Woods (Altra
4 D50.1 T.B. WOODS ((SURE-FLEX))
Industrial Motion) is
the selected PLA
Vendor
Standardization -
Category A, T.B.
COUPLING, GENERAL PURPOSE, METALLIC FLEXIBLE Woods (Altra
4 D50.2 B AMERIDRIVES 1 0
ELEMENT Industrial Motion) is
the selected PLA
Vendor
EMERSON POWER
2 D50.2
TRANSMISSION (KOP-FLEX)
3 D50.2 FLENDER SIEMENS (ARPEX)
THOMAS / REXNORD (SERIES
2 D50.2
71)
Standardization -
Category A, T.B.
Woods (Altra
4 D50.3 COUPLING, FLEXIBLE API-671 B AMERIDRIVES 1 0
Industrial Motion) is
the selected PLA
Vendor
EMERSON POWER
2 D50.3
TRANSMISSION (KOP-FLEX)
2 D50.3 GOODRICH
3 D50.3 REXNORD/THOMAS
2 D51.0 ELECTROLYZER
2 D51.1 ELECTROLYZER E ASAHI KASAI 1 0
4 D52.0 MAN LIFT
4 D52.1 MAN LIFT, ARIEL WORK PLATFORM E GENIE, JLG 1 0
4 D53.0 SEPARATORS
4 D53.1 SEPARATORS, VENDOR DESIGNED CARBON STEEL E PEERLESS 1 0

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Mechanical) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
2 E 1.0 VESSELS

4 E1.1 VESSELS, PRES.; CS; MAX. WALL THK OF 19 MM E AGUILAR & SALAS 2 2

AL-SAGHYIR STEAM BOILERS


2 E1.1
(SA)
AL-ZAMIL COMPANY FOR
E1.1
HEAVY STEEL (SA)
ARABIAN CBI TANK
E1.1
MANUFACTURING (SA)
BILFAL HEAVY INDUSTRIES
E1.1
(SA)
CIMTAS CELIK IMALAT
E1.1
MONTEJ VE TESIS
DAEKYUNG MACHINERY &
E1.1
ENGINEERING
E1.1 DOOSAN MECATEC
3 E1.1 ELLIMETAL N.V.
E1.1 G & G INTERNATIONAL NV
GEYAD FACTORY FOR
E1.1
PRESSURE VESSELS (SA)
GULF HEAVY INDUSTRIES
E1.1
(SA)
E1.1 GULF STEEL WORKS (SA)
E1.1 HIDADA COMPANY (SA)

E1.1 HITACHI ZOSEN MECHANICAL

E1.1 HYUNDAI HEAVY INDUSTRIES

E1.1 ISGEC / YAMUNA NAGER


KNM PROCESS SYSTEMS
E1.1
SDN BHD
E1.1 LARSEN AND TOUBRO
MARITIME INDUSTRIAL
4 E1.1
SERVICE
MITSUBISHI HEAVY
E1.1
INDUSTRIES
OLAYAN DESCON
E1.1
ENGINEERING (SA)
SAUDI ARABIAN FABRICATED
E1.1
METALS (SA)
3 E1.1 SCHELDE EXOTECH B.V
E1.1 SCHWARTZ HAUMONT CMSA
STAHL-UND APPARATEBAU
E1.1
HANS LEFFER
E1.1 YANBU STEEL (SA)
ZAMIL STEEL INDUSTRIES
E1.1
(SA)
4 E1.2 VESSELS, PRES.; CS; WALL THK OF 38 MM E AGUILAR & SALAS 3 2
AL-ZAMIL COMPANY FOR
2 E1.2 E
HEAVY STEEL (SA)
ARABIAN CBI TANK
E1.2
MANUFACTURING (SA)
BILFAL HEAVY INDUSTRIES
E1.2
(SA)
CIMTAS CELIK IMALAT
E1.2
MONTEJ VE TESIS
DAEKYUNG MACHINERY &
E1.2
ENGINEERING
E1.2 DOOSAN MECATEC
3 E1.2 ELLIMETAL N.V.
E1.2 G & G INTERNATIONAL NV
GULF HEAVY INDUSTRIES
E1.2
(SA)

E1.2 HITACHI ZOSEN MECHANICAL

E1.2 HYUNDAI HEAVY INDUSTRIES

E1.2 ISGEC / YAMUNA NAGER


E1.2 ISHIKAWAJIMA-HARIMA
KNM PROCESS SYSTEMS
E1.2
SDN BHD
E1.2 KOBE STEEL
E1.2 LARSEN AND TOUBRO
MARITIME INDUSTRIAL
4 E1.2
SERVICE
MITSUBISHI HEAVY
E1.2
INDUSTRIES
OLAYAN DESCON
E1.2
ENGINEERING (SA)
SAUDI ARABIAN FABRICATED
E1.2
E1 2
METALS (SA)
3 E1.2 SCHELDE EXOTECH B.V
E1.2 SCHWARTZ HAUMONT CMSA
STAHL-UND APPARATEBAU
E1.2
HANS LEFFER
E1.2 YANBU STEEL (SA)
ZAMIL STEEL INDUSTRIES
E1.2
(SA)
4 E1.3 VESSELS, PRES.; CS; WALL THK FROM 38 TO 76MM E AGUILAR & SALAS 3 2
AL-ZAMIL COMPANY FOR
2 E1.3 E
HEAVY STEEL (SA)
ARABIAN CBI TANK
E1.3
MANUFACTURING (SA)
BILFAL HEAVY INDUSTRIES
E1.3
(SA)
CIMTAS CELIK IMALAT
E1.3
MONTEJ VE TESIS
E1.3 DOOSAN MECATEC
E1.3 G & G INTERNATIONAL NV

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
GULF HEAVY INDUSTRIES
E1.3
(SA)

E1.3 HITACHI ZOSEN MECHANICAL

E1.3 HYUNDAI HEAVY INDUSTRIES

E1.3 ISGEC / YAMUNA NAGER


ISHIKAWAJIMA-HARIMA
E1.3
HEAVY
E1.3 KAWASAKI HEAVY
KNM PROCESS SYSTEMS
E1.3
SDN BHD
E1.3 KOBE STEEL
E1.3 LARSEN AND TOUBRO
MARITIME INDUSTRIAL
4 E1.3
SERVICE
MITSUBISHI HEAVY
E1.3
INDUSTRIES
OLAYAN DESCON
E1.3
ENGINEERING (SA)
3 E1.3 SCHELDE EXOTECH B.V
E1 3
E1.3 SCHWARTZ HAUMONT CMSA
3 E1.3 SEWON CELLONTECH
STAHL-UND APPARATEBAU
E1.3
HANS LEFFER
AL-ZAMIL COMPANY FOR
4 E1.4 VESSELS, PRES.; CS; WALL THK MORE THAN 76 MM E 3 2
HEAVY STEEL (SA)
AL SAGHYIR BOILERS AND
4 E1.4
PRESSURE VESSEL (SA)
ARABIAN CBI TANK
2 E1.4 E
MANUFACTURING (SA)
BILFAL HEAVY INDUSTRIES
E1.4
(SA)
CIMTAS CELIK IMALAT
E1.4
MONTEJ VE TESIS
E1.4 DOOSAN MECATEC
E1.4 G & G INTERNATIONAL NV
GEYAD FACTORY FOR
4 E1.4 PRESSURE VESSELS AND
STEEL BUILDINGS (SA)
GULF HEAVY INDUSTRIES
2 E1.4
(SA)
4 E1.4 HIDADA LIMITED (SA)

E1.4 HITACHI ZOSEN MECHANICAL

E1.4 HYUNDAI HEAVY INDUSTRIES

E1.4 ISGEC / YAMUNA NAGER


ISHIKAWAJIMA-HARIMA
E1.4
HEAVY
KAWASAKI HEAVY
E1.4
INDUSTRIES
KNM PROCESS SYSTEMS
E1.4
SDN BHD
E1.4 KOBE STEEL
E1.4 LARSEN AND TOUBRO
MARITIME INDUSTRIAL
4 E1.4
SERVICE
MITSUBISHI HEAVY
E1.4
INDUSTRIES

SAUDI ARABIAN FABRICATED


4 E1.4 METALS INDUSTRY COMPANY
LIMITED (SA)

E1.4 SCHWARTZ HAUMONT CMSA

STAHL-UND APPARATEBAU
E1.4
HANS LEFFER

4 E1.4 YANBU STEEL COMPANY (SA)

ZAMIL STEEL INDUSTRIES


4 E1.4 STRUCTURAL STEEL DIVISION
(SA)
AL-ZAMIL COMPANY FOR
2 E1.5 VESSELS, CARBON STEEL (SMALL UP TO 24" DIAMETER) E 2 2
HEAVY STEEL (SA)
AMALGAMATED METAL
E1.5
CORPORATION (AMC)
APPARATEBAU GMBH
E1.5
CRIMMITSCHAU
ARABIAN CBI TANK
2 E1.5
MANUFACTURING (SA)
E1.5 ASTRA EVANGELISTA S.A.
BENICIA FABRICATION &
E1.5
MACHINE
BILFAL HEAVY INDUSTRIES
2 E1.5
(SA)
E1.5 CEMBELL INDUSTRIES
E1.5 CHEM FABRICATION
E1.5 COEK ENGINEERING N.V.
E1.5 CONFAB INDUSTRIAL S/A
E1.5 ELLIMETAL N.V.
E1.5 FABEX
FREEPORT WELDING &
E1.5
FABRICATING
E1.5 G & G INTERNATIONAL NV
GEYAD FACTORY FOR
2 E1.5
PRESSURE VESSELS (SA)
E1.5 GTI NV

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
2 E1.5 GULF HEAVY INDUSTRIES
2 E1.5 HIDADA COMPANY (SA)
E1.5 HYUNDAI HEAVY INDUSTRIES
JARAGUA EQUIPAMENTOS
E1.5
INDUSTRIAIS LTDA.
E1.5 KOPETZ MFG
NORTHWEST COPPER
E1.5
WORKS
OLAYAN DESCON
2 E1.5
ENGINEERING (SA)
SAUDI ARABIAN FABRICATED
2 E1.5 METALS (SA) (LIMITED TO WT
>38mm)
SCHWARTZ-HAUTMONT
E1.5 CONSTRUCCIONES
METALICAS S.A.
E1.5 SEWON CELLONTECH
VEROLME SPECIAL
E1.5
EQUIPMENT B.V. (VSE)
YANBU STEEL (SA) (LIMITED
2 E1.5
TO WT >38mm)
ZAMIL STEEL INDUSTRIES
2 E1 5
E1.5
(SA) (LIMITED TO WT >38mm)
AL-ZAMIL COMPANY FOR
2 E1.6 VESSELS, CARBON STEEL (SMALL UP TO 60" DIAMETER) E 2 2
HEAVY STEEL (SA)
AMALGAMATED METAL
E1.6
CORPORATION (AMC)
APPARATEBAU GMBH
E1.6
CRIMMITSCHAU
ARABIAN CBI TANK
2 E1.6
MANUFACTURING (SA)
E1.6 ASTRA EVANGELISTA S.A.
BENICIA FABRICATION &
E1.6
MACHINE
BILFAL HEAVY INDUSTRIES
2 E1.6
(SA)
E1.6 CEMBELL INDUSTRIES
E1.6 CHEM FABRICATION
E1.6 COEK ENGINEERING N.V.
E1.6 CONFAB INDUSTRIAL S/A
E1.6 ELLIMETAL N.V.
E1.6 FABEX
FREEPORT WELDING &
E1.6
FABRICATING
E1.6 G & G INTERNATIONAL NV
GEYAD FACTORY FOR
2 E1.6
PRESSURE VESSELS (SA)
E1.6 GTI NV
GULF HEAVY INDUSTRIES
2 E1.6
(SA)
2 E1.6 GULF STEEL WORKS (SA)
2 E1.6 HIDADA COMPANY (SA)

E1.6 HYUNDAI HEAVY INDUSTRIES


JARAGUA EQUIPAMENTOS
E1.6
INDUSTRIAIS
KNM SPECIAL PROCESS
2 E1.6
EQUIPMENT
E1.6 KOPETZ MFG
NORTHWEST COPPER
E1.6
WORKS
OLAYAN DESCON
2 E1.6
ENGINEERING (SA)
SAUDI ARABIAN FABRICATED
2 E1.6 METALS (SA) (LIMITED TO WT
>38mm)
SCHWARTZ-HAUTMONT
E1.6 CONSTRUCCIONES
METALICAS S.A.
E1.6 SEWON CELLONTECH
VEROLME SPECIAL
E1.6
EQUIPMENT B.V. (VSE)
YANBU STEEL (SA) (LIMITED
2 E1.6
TO WT >38mm)
ZAMIL STEEL INDUSTRIES
2 E1.6
(SA) (LIMITED TO WT >38mm)
ZHANGJIAGANG FURUI
4 E1.6
BOILER & PRESSURE VESSEL
AL-ZAMIL COMPANY FOR
2 E1.7 VESSELS, CARBON STEEL (LARGE OVER 60" DIAMETER) E 3 2
HEAVY STEEL (SA)
AMALGAMATED METAL
E1.7
CORPORATION (AMC)
APPARATEBAU GMBH
E1.7
CRIMMITSCHAU
ARABIAN CBI TANK
2 E1.7
MANUFACTURING (SA)
E1.7 ASTRA EVANGELISTA S.A.
BENICIA FABRICATION &
E1.7
MACHINE
BILFAL HEAVY INDUSTRIES
2 E1.7
(SA)
E1.7 CEMBELL INDUSTRIES
E1.7 CHEM FABRICATION
E1.7 COEK ENGINEERING N.V.
E1.7 CONFAB INDUSTRIAL S/A
E1.7 ELLIMETAL N.V.
E1.7 FABEX
FREEPORT WELDING &
E1.7
FABRICATING
E1.7 G & G INTERNATIONAL NV
GEYAD FACTORY FOR
2 E1.7
PRESSURE VESSELS (SA)
E1.7 GTI NV

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
GULF HEAVY INDUSTRIES
2 E1.7
(SA)
2 E1.7 GULF STEEL WORKS (SA)
2 E1.7 HIDADA COMPANY (SA)

2 E1.7 HITACHI ZOSEN MECHANICAL

E1.7 HYUNDAI HEAVY INDUSTRIES

JARAGUA EQUIPAMENTOS
E1.7
INDUSTRIAIS
KNM SPECIAL PROCESS
2 E1.7
EQUIPMENT
E1.7 KOPETZ MFG
2 E1.7 LARSEN AND TOUBRO
NORTHWEST COPPER
E1.7
WORKS
OLAYAN DESCON
2 E1.7
ENGINEERING (SA)
SAUDI ARABIAN FABRICATED
2 E1.7 METALS (SA) (LIMITED TO WT
>38mm)
SCHWARTZ-HAUTMONT
SCHWARTZ HAUTMONT
E1.7 CONSTRUCCIONES
METALICAS S.A.
E1.7 SEWON CELLONTECH
STAHL-UND APPARATEBAU
2 E1.7
HANS LEFFER
VEROLME SPECIAL
E1.7
EQUIPMENT B.V. (VSE)
YANBU STEEL (SA) (LIMITED
2 E1.7
TO WT >38mm)
ZAMIL STEEL INDUSTRIES
2 E1.7
(SA) (LIMITED TO WT >38mm)
ZHANGJIAGANG FURUI
4 E1.7
BOILER & PRESSURE VESSEL
A & A MACHINE AND
2 E1.8 VESSELS, STAINLESS STEEL E 2 2
FABRICATION
AL-ZAMIL COMPANY FOR
E1.8
HEAVY STEEL (SA)
AMALGAMATED METAL
E1.8
CORPORATION (AMC)
APPARATEBAU GMBH
E1.8
CRIMMITSCHAU
E1.8 ASTRA EVANGELISTA S.A.
BENICIA FABRICATION &
E1.8
MACHINE
BILFAL HEAVY INDUSTRIES
E1.8
(SA)
E1.8 CEMBELL INDUSTRIES
E1.8 CHEM FABRICATION
CIMTAS CELIK IMALAT
E1.8
MONTEJ VE TESIS
E1.8 COEK ENGINEERING N.V.
E1 8
E1.8 CONFAB INDUSTRIAL S/A
DAEKYUNG MACHINERY &
E1.8
ENGINEERING
E1.8 DOOSAN MECATEC
E1.8 ELLETT INDUSTRIES
E1.8 ELLIMETAL N.V.
E1.8 FABEX
FREEPORT WELDING &
E1.8
FABRICATING
E1.8 G & G INTERNATIONAL NV
GLADWIN TANK
E1.8
MANUFACTURING
E1.8 GTI NV
E1.8 HIDADA COMPANY (SA)

E1.8 HITACHI ZOSEN MECHANICAL

E1.8 HYUNDAI HEAVY INDUSTRIES

E1.8 IL SUNG
ISHIKAWAJIMA-HARIMA
E1.8
HEAVY
JARAGUA EQUIPAMENTOS
E1.8
INDUSTRIAIS
E1.8 KAWASAKI HEAVY
KNM PROCESS SYSTEMS
E1.8
SDN BHD
E1.8 KOBE STEEL
E1.8 KOPETZ MFG
E1.8 KTI BELGIUM
E1.8
E1 8 LARSEN AND TOUBRO
MARITIME INDUSTRIAL
4 E1.8
SERVICE
MITSUBISHI HEAVY
E1.8
INDUSTRIES
NORTHWEST COPPER
E1.8
WORKS
R.C. TECHNICAL WELDING &
E1.8
FABRICATION
E1.8 SCHELDE EXOTECH B. V.
SCHILLER APPARATEBAU
3 E1.8
GMBH
E1.8 SCHWARTZ HAUMONT CMSA
SEWON CELLONTECH CO
4 E1.8
LTD
SHANGHAI MORIMATSU
4 E1.8
PRESSURE VESSEL CO LTD
4 E1.8 SHANGHAI TONGHUA

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
STAHL-UND APPARATEBAU
E1.8
HANS LEFFER
VEROLME SPECIAL
E1.8
EQUIPMENT B.V. (VSE)
2 E1.8 ZAMIL STEEL INDUSTRIES
ZHANGJIAGANG FURUI
4 E1.8 BOILER & PRESSURE VESSEL
MFG
AL-ZAMIL COMPANY FOR
4 E1.9 VESSELS, ALLOY & CLAD (NICKEL BASED) E 2 2
HEAVY STEEL (SA)
BENICIA FABRICATION &
4 E1.9
MACHINE
BIFFAL HEABY INDUSTRIES
4 E1.9
(SA)
E1.9 CEMBELL INDUSTRIES
E1.9 COEK ENGINEERING N.V.
E1.9 CONFAB INDUSTRIAL S/A
E1.9 ELLETT INDUSTRIES
E1.9 GTI NV
GULF HEAVY INDUSTRIES
4 E1.9
(SA)
E1.9 KOPETZ MFG
MARITIME INDUSTRIAL
4 E1.9
SERVICES
NORTHWEST COPPER
E1.9
WORKS
R.C. TECHNICAL WELDING &
E1.9
FABRICATION
E1.9 SCHELDE EXOTECH B. V.
SCHWARTZ-HAUTMONT
E1.9 CONSTRUCCIONES
METALICAS S.A.
E1.9 SEWON CELLONTECH
VEROLME SPECIAL
E1.9
EQUIPMENT B.V. (VSE)
4 E1.10 VESSELS, TITANIUM AND SUPER ALLOY E COEK ENGINEERING N.V. 2 2
E1.10 ELLETT INDUSTRIES
E1.10 SCHELDE EXOTECH B. V.
SCHILLER APPARATEBAU
E1.10
GMBH
BENICIA FABRICATION &
E1.11 VESSELS, ALUMINUM (INCLUDES HOPPERS, SILOS, ETC.) E 2 2
MACHINE
R.C. TECHNICAL WELDING &
E1.11
FABRICATION
SHANGHAI MORIMATSU
E1.11
PRESSURE VESSEL
2 E2.0 TANKS
ARABIAN CBI TANK
E2.1 TANKS, ROOF; FLOATING;EXTERNAL, (API-620 and API-650) E 2 1
MANUFACTURING (SA)
E2.1 YANBU STEEL (SA)
TANKS, SHOP
TANKS SHOP; ATMOSPHERIC PRESSURE;
PRESSURE CS & SS
SS, (API
(API- AL KHODARI HEAVY
AL-KHODARI
2 E2.2 E 2 2
620 and API-650) INDUSTRIES (KHI)
AL-ZAMIL COMPANY FOR
E2.2
HEAVY STEEL (SA)
APPARATEBAU GMBH
E2.2
CRIMMITSCHAU
ARABIAN CBI TANK
E2.2
MANUFACTURING (SA)
E2.2 ASTRA EVANGELISTA S.A.
BENICIA FABRICATION &
E2.2
MACHINE
BILFAL HEAVY INDUSTRIES
E2.2
(SA)
E2.2 CEMBELL INDUSTRIES
E2.2 CHICAGO BRIDGE INDONESIA
E2.2 CONFAB INDUSTRIAL S/A
E2.2 ELLIMETAL N.V.
E2.2 FABEX
FREEPORT WELDING &
E2.2
FABRICATING
GEYAD FACTORY FOR
E2.2
PRESSURE VESSELS (SA)
GLADWIN TANK
E2.2
MANUFACTURING
E2.2 GLM TANK
E2.2 GTI NV
E2.2 GULF HEAVY INDUSTRIES
E2.2 GULF STEEL WORKS (SA)
E2.2 HIDADA COMPANY (SA)
E2.2 INCASE
JARAGUA EQUIPAMENTOS
E2.2
E2 2
INDUSTRIAIS
JPM INGENIEURTECHNIK
E2.2
GMBH
KNM SPECIAL PROCESS
2 E2.2
EQUIPMENT
E2.2 METSCCO STEEL
MITSUBISHI HEAVY
E2.2
INDUSTRIES
MOHAMMAD AL-MOJIL GROUP
E2.2
STEEL
OLAYAN DESCON
E2.2
ENGINEERING (SA)
SCHWARTZ-HAUTMONT
E2.2 CONSTRUCCIONES
METALICAS S.A.
E2.2 YANBU STEEL (SA)
ZAMIL COMPANY (SA) (SOME
E2.2
LIMITATIONS APPLY)
TANKS, FIELD, ATMOSPHERIC PRESSURE; CS, (API-620 and AL-KHODARI HEAVY
2 E2.3 E 2 2
API-650) INDUSTRIES (KHI)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
AL-ZAMIL COMPANY FOR
E2.3
HEAVY STEEL (SA)
ARABIAN CBI TANK
E2.3
MANUFACTURING (SA)
E2.3 ASTRA EVANGELISTA S.A.
BILFAL HEAVY INDUSTRIES
E2.3
(SA)
E2.3 CHICAGO BRIDGE INDONESIA
E2.3 CONFAB INDUSTRIAL S/A
GEYAD FACTORY FOR
E2.3
PRESSURE VESSELS (SA)
3 E2.3 GULF HEAVY INDUSTRIES
E2.3 GULF STEEL WORKS (SA)
E2.3 HIDADA COMPANY (SA)
JARAGUA EQUIPAMENTOS
E2.3
INDUSTRIAIS
E2.3 METSCCO STEEL
MITSUBISHI HEAVY
E2.3
INDUSTRIES
E2.3 YANBU STEEL (SA)
TANKS, FIELD, ATMOSPHERIC PRESSURE; SS, (API-620 and
E2.4 E ASTRA EVANGELISTA S.A. 2 2
API-650)
E2.4 CHICAGO BRIDGE INDONESIA
E2.4 CONFAB INDUSTRIAL S/A
3 E2.4 GULF HEAVY INDUSTRIES
JARAGUA EQUIPAMENTOS
E2.4
INDUSTRIAIS
ARABIAN CBI TANK
E2.5 TANKS, LOW TEMPERATURE; (API-620) E 2 2
MANUFACTURING (SA)
E2.5 BELLELI ENERGY SRL
E2.5 BELLELI ENERGY UAE
BIFFAL HEAVY INDUSTRIES
4 E2.5
(SA)
E2.6 TANKS, DOME ROOF, ALUMINUM E CONSERVATEK INDUSTRIES 2 1
E2.6 TEMCOR
TANKS AND NON-ASME VESSELS, FRP - FIBER AMIANTIT FIBERGLASS
E2.7 E 2 2
REINFORCED PLASTIC INDUSTRIES
AN-COR INDUSTRIAL
E2.7
PLASTICS
CHRISTEN & LAUDON
E2.7
STAFFELSTEIN
ENDURO SYSTEMS (VESCA
E2.7
DIVISION)
KUROTEC-KTS
E2.7 KUNSTSTOFFTECHNIK STADE
GMBH
E2.7 PROSKE PLASTIC PRODUCTS

E2.7 RL INDUSTRIES

E2.7 TRIPLE M FIBERGLASS MFG

TROY MANUFACTURING
E2.7
CANADA
2 E3.0 HOPPERS, SILOS & BINS
HOPPERS, SILOS & BINS, STAINLESS STEEL
2 E3.1 E ELLIMETAL N.V. 2 2
CONSTRUCTION
GEA - TECHNOLOGY
E3.1
EQUIPMENT
E3.1 JANSENS & DIEPERINK B.V.
R.C. TECHNICAL WELDING &
E3.1
FABRICATION
E3.1 ZEPPELIN
2 E4.0 BLENDERS
4 E4.1 BLENDERS, STATIC - SILO E CONFAB INDUSTRIAL S/A 2 1
E4.1 COPERION WAESCHLE
JARAGUA EQUIPAMENTOS
E4.1
INDUSTRIAIS
KNM SPECIAL PROCESS
E4.1
EQUIPMENT
2 E5.0 HEAT EXCHANGERS
HEAT EXCHANGERS, SHELL & TUBE; CS (Small and Medium
4 E5.1 AGUILAR & SALAS 2 2
up to 60" Diameter)
APPARATEBAU GMBH
2 E5.1 E
CRIMMITSCHAU
E5.1 ASTRA EVANGELISTA S.A.
E5.1 BELLELI ENERGY SRL
BENICIA FABRICATION &
E5.1
MACHINE
BILFAL HEAVY INDUSTRIES
E5.1
(SA)
BREMBANA COSTRUZIONI
5
E5.1
INDUSTRIALI
S SR
S
BRONSWERK HEAT
3 E5.1
TRANSFER B.V.
4 E5.1 BHI
E5.1 CEMBELL INDUSTRIES
E5.1 CHEM FABRICATION
E5.1 COEK ENGINEERING N.V.
DAEKYUNG MACHINERY &
E5.1
ENGINEERING
E5.1 DOOSAN MECATEC
E5.1 DUNN HEAT EXCHANGERS
E5.1 ELLETT INDUSTRIES
E5.1 EXCHANGER INDUSTRIES
E5.1 GEO
GODREJ AND BOYCE
E5.1
MANUFACTURING.
E5.1 GTI NV
GULF HEAVY INDUSTRIES
E5.1
(SA)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
E5.1 GULF STEEL WORKS (SA)
E5.1 HITACHI ZOSEN MECHANICAL
E5.1 HUGHES-ANDERSON HEAT
E5.1 HYUNDAI HEAVY INDUSTRIES
E5.1 ILSUNG
E5.1 ISGEC / YAMUNA NAGER
JARAGUA EQUIPAMENTOS
E5.1
INDUSTRIAIS
E5.1 KAWASAKI HEAVY
KNM SPECIAL PROCESS
2 E5.1
EQUIPMENT
KOCH HEAT TRANSFER
2 E5.1
COMPANY SRL
E5.1 KOPETZ MFG
E5.1 LARSEN AND TOUBRO
MARITIME IINDUSTRIAL
4 E5.1
SERVICE
E5.1 MAYR & WILHELM GMBH & CO

MITSUBISHI HEAVY
E5 1
E5.1
INDUSTRIES
NORTHWEST COPPER
E5.1
WORKS
OLAYAN DESCON
E5.1
ENGINEERING (SA)
E5.1 SCHELDE EXOTECH B. V.
E5.1 SEWON CELLONTECH
STAHL-UND APPARATEBAU
E5.1
HANS LEFFER
E5.1 SWECOMEX S.A. DE C.V.
VEROLME SPECIAL
E5.1
EQUIPMENT B.V. (VSE)
HEAT EXCHANGERS, SHELL & TUBE; CS (Large over 60"
4 E5.2 E AGUILAR & SALAS 2 2
Diameter)
APPARATEBAU GMBH
2 E5.2 E
CRIMMITSCHAU
E5.2 ASTRA EVANGELISTA S.A.
E5.2 BELLELI ENERGY SRL
BENICIA FABRICATION &
E5.2
MACHINE
BILFAL HEAVY INDUSTRIES
E5.2
(SA)
BREMBANA COSTRUZIONI
E5.2
INDUSTRIALI SR
BRONSWERK HEAT
E5.2
TRANSFER B.V.
4 E5.2 BHI
E5.2 CEMBELL INDUSTRIES
E5.2 CHEM FABRICATION
E5.2 COEK ENGINEERING N.V.
DAEKYUNG MACHINERY &
E5 2
E5.2
ENGINEERING
E5.2 DOOSAN MECATEC
E5.2 DUNN HEAT EXCHANGERS
E5.2 ELLETT INDUSTRIES
E5.2 EXCHANGER INDUSTRIES
E5.2 GEO
GODREJ AND BOYCE
E5.2
MANUFACTURING.
E5.2 GTI NV
GULF HEAVY INDUSTRIES
E5.2
(SA)
E5.2 GULF STEEL WORKS (SA)
HITACHI LIMITED KASADO
E5.2
WORKS

E5.2 HITACHI ZOSEN MECHANICAL

E5.2 HUGHES ANDERSON HEAT

E5.2 HYUNDAI HEAVY INDUSTRIES

E5.2 ILSUNG
E5.2 ISGEC / YAMUNA NAGER
JARAGUA EQUIPAMENTOS
E5.2
INDUSTRIAIS
KAWASAKI HEAVY
E5.2
INDUSTRIES
KNM SPECIAL PROCESS
2 E5.2
EQUIPMENT
KOCH HEAT TRANSFER
E5.2
COMPANY SRL
E5.2 KOPETZ
E5.2 LARSEN AND TOUBRO
MARITIME IINDUSTRIAL
4 E5.2
SERVICE
E5.2 MAYR & WILHELM GMBH & CO

MITSUBISHI HEAVY
E5.2
INDUSTRIES
NORTHWEST COPPER
E5.2
WORKS
OLAYAN DESCON
E5.2
ENGINEERING (SA)
E5.2 SCHELDE EXOTECH B. V.
E5.2 SEWON CELLONTECH
STAHL-UND APPARATEBAU
E5.2
HANS LEFFER
E5.2 SWECOMEX S.A. DE C.V.
VEROLME SPECIAL
E5.2
EQUIPMENT B.V. (VSE)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
HEAT EXCHANGERS, SHELL & TUBE; STAINLESS AND APPARATEBAU GMBH
2 E5.3 E 2 2
ALLOY STEEL (Small up to 24" Diameter) CRIMMITSCHAU
E5.3 ASTRA EVANGELISTA S.A.
E5.3 BELLELI ENERGY SRL
BENICIA FABRICATION &
E5.3
MACHINE
BILFAL HEAVY INDUSTRIES
E5.3
(SA)
BREMBANA COSTRUZIONI
E5.3
INDUSTRIALI SR
BRONSWERK HEAT
E5.3
TRANSFER B.V.
4 E5.3 BHI
E5.3 CEMBELL INDUSTRIES
E5.3 CHEM FABRICATION
E5.3 COEK ENGINEERING N.V.
DAEKYUNG MACHINERY &
E5.3
ENGINEERING
E5.3 DOOSAN MECATEC
E5.3 DUNN HEAT EXCHANGERS
E5.3 ELLETT INDUSTRIES
E5.3 EXCHANGER INDUSTRIES
E5.3 GEO
E5.3 GTI NV

E5.3 HITACHI ZOSEN MECHANICAL

E5.3 HYUNDAI HEAVY INDUSTRIES

ISHIKAWAJIMA-HARIMA
E5.3
HEAVY
JARAGUA EQUIPAMENTOS
E5.3
INDUSTRIAIS
E5.3 KAWASAKI HEAVY
KNM SPECIAL PROCESS
2 E5.3
EQUIPMENT
E5.3 KOBE STEEL
KOCH HEAT TRANSFER
E5.3
COMPANY
E5.3 KOPETZ MFG
E5.3 LARSEN AND TOUBRO

E5.3 MAYR & WILHELM GMBH & CO

MITSUBISHI HEAVY
E5.3
INDUSTRIES
NORTHWEST COPPER
E5.3
WORKS
E5.3 SCHELDE EXOTECH B. V.
E5.3 SEWON CELLONTECH
STAHL-UND APPARATEBAU
E5.3
HANS LEFFER
E5.3 SWECOMEX S.A. DE C.V.
VEROLME SPECIAL
E5.3
EQUIPMENT B.V. (VSE)
HEAT EXCHANGERS, SHELL & TUBE; STAINLESS AND APPARATEBAU GMBH
2 E5.4 E 2 2
ALLOY STEEL (Medium up to 60" Diameter) CRIMMITSCHAU
E5.4 ASTRA EVANGELISTA S.A.
E5.4 BELLELI ENERGY SRL
BENICIA FABRICATION &
E5.4
MACHINE
BILFAL HEAVY INDUSTRIES
E5.4
(SA)
BREMBANA COSTRUZIONI
E5.4
INDUSTRIALI SR
BRONSWERK HEAT
E5.4
TRANSFER B.V.
4 E5.4 BHI
E5.4 CEMBELL INDUSTRIES
E5.4 CHEM FABRICATION
E5.4 COEK ENGINEERING N.V.
DAEKYUNG MACHINERY &
E5.4
ENGINEERING
E5.4 DOOSAN MECATEC
E5.4 DUNN HEAT EXCHANGERS
E5.4 ELLETT INDUSTRIES
E5.4 EXCHANGER INDUSTRIES
E5.4 GEO
E5.4 GTI NV
4 E5.4 GULF HEAVY INDUSTRIES

E5.4 HITACHI ZOSEN MECHANICAL

E5.4
E5 4 HYUNDAI HEAVY INDUSTRIES

ISHIKAWAJIMA-HARIMA
E5.4
HEAVY
JARAGUA EQUIPAMENTOS
E5.4
INDUSTRIAIS
E5.4 KAWASAKI HEAVY
KNM SPECIAL PROCESS
2 E5.4
EQUIPMENT
E5.4 KOBE STEEL
KOCH HEAT TRANSFER
E5.4
COMPANY SRL
E5.4 KOPETZ MFG
E5.4 LARSEN AND TOUBRO

E5.4 MAYR & WILHELM GMBH & CO

MITSUBISHI HEAVY
E5.4
INDUSTRIES
NORTHWEST COPPER
E5.4
WORKS

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
E5.4 SCHELDE EXOTECH B. V.
SCHILLER APPARATEBAU
3 E5.4
GMBH
E5.4 SEWON CELLONTECH
STAHL-UND APPARATEBAU
E5.4
HANS LEFFER
E5.4 SWECOMEX S.A. DE C.V.
VEROLME SPECIAL
E5.4
EQUIPMENT B.V. (VSE)
HEAT EXCHANGERS, SHELL & TUBE; STAINLESS AND APPARATEBAU GMBH
2 E5.5 E 3 3
ALLOY STEEL (Large over 60" Diameter) CRIMMITSCHAU
E5.5 ASTRA EVANGELISTA S.A.
E5.5 BELLELI ENERGY SRL
BENICIA FABRICATION &
E5.5
MACHINE
BILFAL HEAVY INDUSTRIES
E5.5
(SA)
BREMBANA COSTRUZIONI
E5.5
INDUSTRIALI SR
BRONSWERK HEAT
E5.5
TRANSFER B.V.
4 E5.5 BHI
E5 5
E5.5 CEMBELL INDUSTRIES
E5.5 CHEM FABRICATION
E5.5 COEK ENGINEERING N.V.
DAEKYUNG MACHINERY &
E5.5
ENGINEERING
E5.5 DOOSAN MECATEC
E5.5 DUNN HEAT EXCHANGERS
E5.5 ELLETT INDUSTRIES
E5.5 EXCHANGER INDUSTRIES
E5.5 GEO
E5.5 GTI NV

E5.5 HITACHI ZOSEN MECHANICAL

E5.5 HYUNDAI HEAVY INDUSTRIES

ISHIKAWAJIMA-HARIMA
E5.5
HEAVY
JARAGUA EQUIPAMENTOS
E5.5
INDUSTRIAIS
E5.5 KAWASAKI HEAVY
KNM SPECIAL PROCESS
2 E5.5
EQUIPMENT
E5.5 KOBE STEEL
KOCH HEAT TRANSFER
E5.5
COMPANY SRL
E5.5 KOPETZ MFG
E5.5 LARSEN AND TOUBRO

E5.5 MAYR & WILHELM GMBH & CO


MITSUBISHI HEAVY
E5 5
E5.5
INDUSTRIES
NORTHWEST COPPER
E5.5
WORKS
E5.5 SCHELDE EXOTECH B. V.
E5.5 SEWON CELLONTECH
4 E5.5 SHANGHAI TONGHUA
STAHL-UND APPARATEBAU
E5.5
HANS LEFFER
E5.5 SWECOMEX S.A. DE C.V.
'VEROLME SPECIAL
E5.5
EQUIPMENT B.V. (VSE)
ZHANGJIAGANG FURUI
4 E5.5 BOILER & PRESSURE VESSEL
MFG
APPARATEBAU GMBH
2 E5.6 HEAT EXCHANGERS, SHELL & TUBE; HIGH ALLOY E 2 2
CRIMMITSCHAU
BENICIA FABRICATION &
E5.6
MACHINE
E5.6 COEK ENGINEERING N.V.
DAEKYUNG MACHINERY &
E5.6
ENGINEERING
E5.6 ELLETT INDUSTRIES
E5.6 EXCHANGER INDUSTRIES
E5.6 GTI NV
E5.6 HYUNDAI HEAVY INDUSTRIES
KNM SPECIAL PROCESS
2 E5.6
EQUIPMENT
KOCH HEAT TRANSFER
E5.6 CANADA (KOCH
ENGINEERING LTD)
E5.6 KOPETZ MFG
E5.6 MAYR & WILHELM GMBH
NANJING SPECIAL METAL
E5.6
EQUIPMENT
NORTHWEST COPPER
E5.6
WORKS
E5.6 SEWON CELLONTECH
VEROLME SPECIAL
E5.6
EQUIPMENT B.V. (VSE)
E5.7 HEAT EXCHANGERS, SHELL AND TUBE - OFF-THE-SHELF E ALTEX INDUSTRIES 1 1
3 E5.7 API BASCO
DOYLE & ROTH
E5.7
MANUFACTURING
E5.7 ITT STANDARD
ALSTOM POWER (HEAT
E5.8 HEAT EXCHANGERS, SURFACE CONDENSERS E 3 3
EXCHANGE DIVISION)
APPARATEBAU GMBH
E5.8
CRIMMITSCHAU
E5.8 ASTRA EVANGELISTA S.A.

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
E5.8 COEK ENGINEERING N.V.
E5.8 CONFAB INDUSTRIAL S/A
E5.8 GRAHAM MANUFACTURING
E5.8 GTI NV
4 E5.8 ILSUNG
E5.8 MAYR & WILHELM GMBH & CO
E5.8 SCHELDE EXOTECH B. V.
VEROLME SPECIAL
E5.8
EQUIPMENT B.V. (VSE)
E5.9 HEAT EXCHANGERS, MULTI-PIPE; DOUBLE-PIPE; HAIRPIN E ALCO PRODUCTS 2 2
APPARATEBAU GMBH
E5.9
CRIMMITSCHAU
BROWN FINTUBE FRANCE SA
E5.9
HAMON
E5.9 BURGESS-MANNING INC.
E5.9 COEK ENGINEERING N.V.
E5.9 CONFAB INDUSTRIAL S/A
DAEKYUNG MACHINERY &
E5.9
ENGINEERING
E5.9 GTI NV
E5.9 GULF HEAVY INDUSTRIES
E5.9 KOCH HEAT TRANSFER
E5.9 MAYR & WILHELM GMBH & CO
E5.9 R. W. HOLLAND
SCHILLER APPARATEBAU
3 E5.9
GMBH
E5.9 SCHELDE EXOTECH B. V.
E5.9 SEWON CELLONTECH
E5.9 UHDE GMBH
VEROLME SPECIAL
E5.9
EQUIPMENT B.V. (VSE)
2 E5.10 HEAT EXCHANGERS, PLATE AND FRAME E ALFA LAVAL 2 2
E5.10 APV NORTH AMERICA
3 E5.10 GEA ECOFLEX
E5.10 TRANTER
HEAT EXCHANGERS, GRAPHITE TUBE AND CARBON
E5.11 E CARBONE LORRAINE 3 2
BLOCK TYPE
E5.11 SGL ACOTEC
E5.11 SGL CARBON TECHNIC
ARMSTRONG ENGINEERING
E5.12 HEAT EXCHANGERS, ELECTRIC E 2 3
ASSOCIATES
E5.12 ELTRON CHROMALOX
E5.12 EXHEAT
E5.13 HEAT EXCHANGERS, SPIRAL E ALFA LAVAL 3 2
E5.13 GEA - CANZLER
4 E5.14 NOT USED E
HEAT EXCHANGERS, COLD BOX INCLUDING BRAZED
E5.15 E CHART INDUSTRIES 3 3
ALUMINUM
E5.15
E5 15 LINDE AG
E5.15 NORDON INDUSTRIES
SUMITOMO PRECISION
E5.15
PRODUCTS
HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OVER Standardization -
4 E5.16 E FBM-KNM FZCO 3 3
139.4 Category B
GEA-BTT (FRANCE AND
4 E5.16 E
QATAR ONLY)
4 E5.16 HUDSON PRODUCTS
JORD INTERNATIONAL
4 E5.16
(MALASIA ONLY)
4 E5.16 ZAMIL HUDSON (SA)
HEAT EXCHANGERS, AIR COOLED, BARE TUBE AREA OF ABASAIN SPECIALIZED Standardization -
4 E5.17 3 3
139.4 SQ.M AND BELOW INDUSTRIAL CO (ASIC) (SA) Category C
4 E5.17 FMB-KNM FZCO
GEA-BTT (FRANCE AND
4 E5.17
QATAR ONLY)
4 E5.17 HAMON D'HONDT
4 E5.17 HUDSON PRODUCTS
JORD INTERNATIONAL
4 E5.17
(MALASIA ONLY)
4 E5.17 ZAMIL HUDSON (SA)
E6.0 HEATERS
ALSTOM POWER ENERGY
E6.1 HEATERS, FLAT PLATE E 2 2
RECOVERY GMBH
E6.1 EBCO INDUSTRIES
E6.1 KOPETZ MFG
E6.1 NORDON INDUSTRIES
E6.1 SCHELDE EXOTECH B. V.
2 E7.0 TRANSFER LINE EXCHANGERS
S O POWER
ALSTOM O G
ENERGY
E7.1
E7 1 TRANSFER LINE EXCHANGERS
EXCHANGERS, PRIMARY E 2 2
RECOVERY GMBH
E7.1 BABCOCK - BORSIG
4 E7.1 OLMI SPA
E7.1 SHG - SCHACK (SCHMIDTKE)
ALSTOM POWER ENERGY
E7.2 TRANSFER LINE EXCHANGERS, SECONDARY E 2 2
RECOVERY GMBH
E7.2 ALTEX INDUSTRIES
AMALGAMATED METAL
E7.2
CORPORATION (AMC)
APPARATEBAU GMBH
E7.2
CRIMMITSCHAU
E7.2 ASTRA EVANGELISTA S.A.
E7.2 BABCOCK - BORSIG
E7.2 CEMBELL INDUSTRIES
E7.2 COEK ENGINEERING N.V.
DEDINI S/A INDUSTRIAS DE
E7.2
BASE
E7.2 DUNN HEAT EXCHANGERS
E7.2 ELLETT INDUSTRIES

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
E7.2 EXCHANGER INDUSTRIES
E7.2 GEO
E7.2 GTI NV
E7.2 HYUNDAI HEAVY INDUSTRIES
JARAGUA EQUIPAMENTOS
E7.2
INDUSTRIAIS
KOCH HEAT TRANSFER
E7.2 CANADA LP (KOCH
ENGINEERING LTD)
E7.2 KOPETZ MFG

E7.2 MAYR & WILHELM GMBH & CO


NORTHWEST COPPER
E7.2
WORKS
E7.2 OLMI S.P.A.
E7.2 SCHELDE EXOTECH B. V.
E7.2 SEWON CELLONTECH
E7.2 SWECOMEX S.A. DE C.V.
VEROLME SPECIAL
E7.2
EQUIPMENT B.V. (VSE)
E7.3 TRANSFER LINE EXCHANGERS, TERTIARY E ALTEX INDUSTRIES 2 2
AMALGAMATED METAL
E7.3
CORPORATION (AMC)
APPARATEBAU GMBH
E7.3
CRIMMITSCHAU
E7.3 ASTRA EVANGELISTA S.A.
E7.3 BABCOCK - BORSIG
CBC INDUSTRIAS PESADAS
E7.3
S.A.
E7.3 CEMBELL INDUSTRIES
E7.3 CHENG CHEN MACHINERY
E7.3 COEK ENGINEERING N.V.
DAEKYUNG MACHINERY &
E7.3
ENGINEERING
DEDINI S/A INDUSTRIAS DE
E7.3
BASE
E7.3 DUNN HEAT EXCHANGERS
E7.3 ELLETT INDUSTRIES
E7.3 EXCHANGER INDUSTRIES
E7.3 GEO
E7.3 GTI NV

E7.3 HYUNDAI HEAVY INDUSTRIES

JARAGUA EQUIPAMENTOS
E7.3
INDUSTRIAIS
KOCH HEAT TRANSFER
E7.3 CANADA LP (KOCH
ENGINEERING LTD)
E7.3 KOPETZ MFG

E7.3 MAYR & WILHELM GMBH & CO

NORTHWEST COPPER
E7.3
WORKS, INC.
E7.3 OLMI S.P.A.
E7.3 SCHELDE EXOTECH B. V.
E7.3 SEWON CELLONTECH
E7.3 SWECOMEX S.A. DE C.V.
VEROLME SPECIAL
E7.3
EQUIPMENT B.V. (VSE)
2 E8.0 REACTORS
3 E8.1 REACTORS, CUSTOM E G&G INTERNATIONAL 3 3
3 E8.1 HYUNDAI HEAVY INDUSTRIES
E8.1 KOPETZ MFG
3 E8.1 LARSEN & TOUBRO
MITSUBISHI HEAVY
3 E8.1
INDUSTRIES

4 E8.1 SHANGHI MORIMATSU

VEROLME SPECIAL
E8.1
EQUIPMENT B.V. (VSE)
E9.0 EVAPORATORS
E9.1 EVAPORATORS, THIN FILM E BALCKE DUERR 2 2
E9.1 CHEMA BALCKE DUERR
E9.1 GEA
E10.0 LINED EQUIPMENT
E10.1 LINED EQUIPMENT, GLASS E DE DIETRICH 3 2
E10.1 PFAUDLER
E10.1 TYCON TECHNOGLASS
2 E11.0 FIBER REINFORCED PLASTIC MATERIAL
AN-COR INDUSTRIAL
2 E11.1 O C
FRP - FIBER REINFORCED S C - SC
PLASTIC U S
SCRUBBERS E 2 2
PLASTICS
S CS
CHRISTEN & LAUDON
E11.1
STAFFELSTEIN
KUROTEC-KTS
E11.1 KUNSTSTOFFTECHNIK STADE
GMBH
E11.1 PROSKE PLASTIC PRODUCTS

E11.1 RL INDUSTRIES
E11.1 TRI-CLOR
TROY MANUFACTURING
E11.1
CANADA
FRP - FIBER REINFORCED PLASTIC - STACKS AND DUCTS - AN-COR INDUSTRIAL
E11.2 E 2 2
GENERAL PLASTICS
CHRISTEN & LAUDON
E11.2
STAFFELSTEIN
E11.2 EDO SPECIALTY PLASTICS
ENDURO SYSTEMS (VESCA
E11.2
DIVISION)
E11.2 FIBREX CORPORATION

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
KUROTEC-KTS
E11.2 KUNSTSTOFFTECHNIK STADE
GMBH
E11.2 PROSKE PLASTIC PRODUCTS
E11.2 RL INDUSTRIES
E11.2 TRI-CLOR
TROY MANUFACTURING
E11.2
CANADA
3 E11.3 FRP - FIBER REINFORCED PLASTIC - FURAN E AN-COR 2 3
ENDURO SYSTEMS (VESCA
2 3
DIVISION)
KUROTEC - KTS
3 E11.3 KUNSTSTOFFTECHNIK STADE
GMBH
E11.3 PROSKE PLASTIC PRODUCTS

E11.3 TRI-CLOR
FRP - FIBER REINFORCED PLASTIC - EQUIPMENT - DUAL CHRISTEN & LAUDON
2 E11.4 E 2 3
LAMINATE STAFFELSTEIN
3 E11.4 CPF DUALAM
ENDURO SYSTEMS (VESCA
E11.4
DIVISION)
KUROTEC-KTS
E11.4 KUNSTSTOFFTECHNIK STADE
GMBH
3 E11.4 PLASTICON EUROPE BV
E11.4 RL INDUSTRIES
E11.4 TRI-CLOR
FRP - FIBER REINFORCED PLASTIC - FIELD FABRICATED - AN-COR INDUSTRIAL
2 E11.5 E 2 3
LARGE DIAMETER PLASTICS
CHRISTEN & LAUDON
E11.5
STAFFELSTEIN
KUROTEC-KTS
E11.5 KUNSTSTOFFTECHNIK STADE
GMBH
E11.5 RL INDUSTRIES
AN-COR INDUSTRIAL
E11.6 FRP - FIBER REINFORCED PLASTIC - ASME RTP-1 E 2 2
PLASTICS
E11.6 RL INDUSTRIES
E12.0 INTERNALS
E12.1 INTERNALS, SCREENS E JOHNSON SCREENS 2 1
E12.1 NAGAOKA INTERNATIONAL
E12.2 INTERNALS, PACKING - TOWER E CENTURY PLASTICS 2 0
E12.2 HETP
E12.2 KOCH GLITSCH
E12.2 MONTZ
E12.2 RASCHIG GMBH
E12.2 RAUSCHERT GMBH
E12.2 SULZER CHEMTECH
E12.2 VFF
E12.3 INTERNALS (TOWER), TRAYS E KOCH GLITSCH ITALIA SRL 2 1
KOCH-GLITSCH MASS
E12.3
TRANSFER (NORTON)
E12.3 MONTZ
E12.3 RAUSCHERT GMBH
E12.3 SULZER CHEMTECH
E12.3 UOP
13.0 VAPORIZERS

E13.1 VAPORIZER; CRYOGENIC E ARMSTRONG ENGINEERING 2 2


ASSOCIATES
E13.1
LINDE AG

E13.1 MITSUBISHI HEAVY


INDUSTRIES
E13.1 CHEMTEC PTE
E14.0 PANELS
E14.1 PANELS, HEAT TRANSFER E CENTURY PLASTICS 2 2
E14.1 HETP
KOCH-GLITSCH MASS
E14.1
TRANSFER (NORTON)
E14.1 MONTZ
E14.1 RASCHIG GMBH
E14.1 RAUSCHERT GMBH
E14.1 SENIOR PLATE COIL
E14.1 SULZER CHEMTECH
E14.1 TRANTER PHE
E14.1 VFF
E15.0 SPHERES
AL-ZAMIL COMPANY FOR
E15.1 SPHERES, ASME E 3 3
HEAVY STEEL (SA)
ARABIAN CBI TANK
E15.1
MANUFACTURING (SA)
BILFAL HEAVY INDUSTRIES
E15.1
(SA)
CIMTAS CELIK IMALAT
E15.1
MONTEJ VE TESIS
E15.1 DOOSAN MECATEC
E15.1 G & G INTERNATIONAL NV
E15.1 GULF HEAVY INDUSTRIES

E15.1 HITACHI ZOSEN MECHANICAL

E15.1 HYUNDAI HEAVY INDUSTRIES


E15.1 ISGEC / YAMUNA NAGER
ISHIKAWAJIMA-HARIMA
E15.1
HEAVY

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
E15.1 KAWASAKI HEAVY
KNM PROCESS SYSTEMS
E15.1
SDN BHD
E15.1 KOBE STEEL
E15.1 LARSEN AND TOUBRO
MARITIME INDUSTRIAL
4 E15.1
SERVICE
MITSUBISHI HEAVY
E15.1
INDUSTRIES
OLAYAN DESCON
E15.1
ENGINEERING (SA)
E15.1 SCHWARTZ HAUMONT CMSA
STAHL-UND APPARATEBAU
E15.1
HANS LEFFER
4 E15.1
2 E16.0 ALLOY APPROVED MILLS
ALLOY APPROVED MILLS, AUSTENITIC & DUPLEX Austenitic stainless plate,
4 E16.1 B ARCELORMITTAL STAINLESS 1 1
STAINLESS STEELS flat/ring forgings
Austenitic and duplex
stainless plate, sheet,
4 E16.1 ATI ALLEGHENY LUDLUM
pipe, tube, flat/ring
forgings
g g
Austenitic and duplex
4 E16.1 BUTTING stainless plate, sheet,
pipe, tube
Austenitic and duplex
4 E16.1 BRUCK GROUP
stainless flat/ring forgings

Austenitic and duplex


CARPENTER SPECIALTY
4 E16.1 stainless plate, sheet,
ALLOYS
pipe, tube
CHANGSHU WALSIN Duplex stainless
4 E16.1
SPECIALTY STEED CO LTD seamless tubes
Austenitic stainless
4 E16.1 CREUSOT FORGE
flat/ring forgings
Austenitic stainless plate,
4 E16.1 JINDAL GROUP
sheet
KUNSHAN SAEKYUNG STEEL Austenitic stainless plate,
4 E16.1
CO LTD (KDKC) sheet
NORTH AMERICAN Austenitic stainless plate,
4 E16.1
STAINLESS sheet
Austenitic and duplex
4 E16.1 OUTOKUMPU STAINLESS INC stainless plate, sheet,
pipe, tube
Austenitic stainless plate,
4 E16.1 POSCO, E&C KOREA
sheet
Austenitic and duplex
4 E16.1 RATHGIBSON
stainless tube
Austenitic stainless plate,
4 E16.1 ROLLED ALLOYS
sheet
SALZGITTER MANNESMANN Austenitic and duplex
4 E16.1
INTERNATIONAL GMBH stainless plate, sheet
Austenitic and duplex
4 E16.1 SANDVIK stainless plate, sheet,
pipe, tube
SHANGHAI BAOSTEEL (NO. 3 Austenitic stainless plate,
4 E16.1
MILL) sheet
TAIYUAN IRON AND STEEL Austenitic stainless plate,
4 E16.1
GROUP CO LTD (TISCO) duplex stainless plate,

4 E16.2 ALLOY APPROVED MILLS, NI-BASE ALLOYS B ARCELORMITTAL STAINLESS 1 1 Plate, Sheet

Plate, sheet, pipe, tube,


4 E16.2 ATI ALLEGHENY LUDLUM
flat/ring forgings
4 E16.2 ATI ALLVAC Plate, sheet, pipe, tube
4 E16.2 BUTTING Plate, sheet, pipe, tube
Plate, sheet, pipe, tube,
4 E16.2 BRUCK GROUP
flat/ring forgings
Plate, sheet, pipe, tube,
4 E16.2 G.O. CARLSON
flat/ring forgings
4 E16.2 HAYNES INTERNATIONAL Plate, sheet, pipe, tube
4 E16.2 RATHGIBSON Tube
4 E16.2 ROLLED ALLOYS Plate, sheet, pipe, tube
4 E16.2 SANDVIK Plate, sheet, pipe, tube
4 E16.2 SPECIAL METALS Plate, sheet, pipe, tube
4 E16.2 THYSSEN KRUPP Plate, sheet, pipe, tube

ALLOY APPROVED MILLS, REACTIVE METALS (ZR, TI, TA,


4 E16.3 B ATI ALLEGHENY LUDLUM 1 1 Ti flat/ring forgings
NB, ALLOYS)
1. Zr, Ti, Ta, Nb Plate,
4 E16.3 ATI WAH CHANG 1 1 sheet, pipe, tube 2. Zr
flat/ring forgings
4 E16.3 BUTTING Ti plate, sheet, pipe, tube

4 E16.3 LOTERIOS Ti tube


Zr, Ti, Ta, Nb plate,
4 E16.3 ROLLED ALLOYS
sheet, pipe, tube
Ti, Zr plate, sheet, pipe,
4 E16.3 SANDVIK
tube
4 E16.3 TIMET Ti plate, sheet, pipe, tube

4 E16.3 TITANIUM INDUSTRIES Plate, sheet, pipe, tube


4 E16.3 TICO Ti flat/ring forgings
Zr, Ti, Ta, Nb plate,
4 E16.3 UNITI
sheet, pipe, tube
ASAHI KASEI CHEMICAL
4 E16.4 EXPLOSION CLADDING MATERIAL B 1 1 Plate, sheet
CORPORATION
DYNAMIC MATERIALS
E16.4
4 CORPORATION Plate, sheet

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Containing Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Time
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix Design US$ Strategy Level Level Weight Volume Date Date (weeks) (weeks)
Requirements
Equipment
REGAL TECHNOLOGY
E16.4
4 CORPORATON Plate, sheet
SMT SHOCKWAVE
4 E16.4 METALWORKING
TECHNOLOGIES Plate, sheet
VOELSTALPINE
4 E16.5 ROLL BONDED CLAD PLATE AND SHEET B
GROBBLECH GMBH 1 1 Plate, sheet

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (PCE) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Location Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment Requirements

2 F 1.0 PIPE
BENTERLER STAHL/ROHR Standardization -
4 F1.1 PIPE, CARBON STEEL - SEAMLESS B DE 2 2
(WERK 41) (PADERBORN) Category A
BENTERLER STAHL/ROHR
F1.1 DE
(WERK 65) (DINSLAKEN)
F1.1 JFE STEEL (HANDA) JP
MANNESMANN FUCHS IPE
F1.1 DE
GMBH ROHR (HAMM)
MANNESMANNROHREN-
F1.1 DE
WERKE A.G. (BOUS)
MITTAL STEEL SOUTH AFRICA
F1.1 ZA
(VEREENIGING)
F1.1 NIPPON STEEL (TOKYO) JP
F1.1 NKK TUBES (KAWASAKI) JP
SAUDI STEEL PIPE COMPANY
F1.1 SA
(DAMMAM)
F1.1 SIDERCA S.A.I.C. (CAMPANA) AR
SUMITOMO METAL IND.
F1.1 JP
(KAINAN)
SUMITOMO METAL
F1.1 JP
IND.(AMAGASAKI-SHI)
SUMITOMO METAL IND
F1 1
F1.1 JP
(WAKAYAMA)
F1.1 TENARIS DALMINE (DALMINE) IT
TIANJIN PIPE (GROUP)
F1.1 CN
CORPORATION LT (TIANJIN)
TUBOS DE ACERO DE
F1.1 MX
MEXICO (VERACRUZ )
TUBOS REUNIDOS S.A.
F1.1 ES
(AMURRIO)
U.S. STEEL TUBULAR
F1.1 US
(FARFIELD)
V & M STAR LP
F1.1 US
(YOUNGSTOWN)
VALLOUREC & MANNESMANN
F1.1 FR
(AULNOYE)
VALLOUREC & MANNESMANN
F1.1 FR
(SAINT SAULVE)
VALLOUREC & MANNESMANN
F1.1 DE
TUBES GMBH (MULHEIM)
VALLOUREC AND
F1.1 MANNESMANN (BELO BR
HOROZONTE 30000)
VOESTALPINE TUBULARS
F1.1 AT
GMBH & CO KG (KINDBERG)
VOLZHSKY PIPE PLANT
F1.1 RU
(VOLZHSKY)
ARABIAN PIPES COMPANY Standardization -
4 F1.2 PIPE, CARBON STEEL - WELDED B SA 3 2
(APC) (RIYADH) Category A
AZIZ EUROPEAN PIPE
4 F1.2 SA
COMPANY
BERG STEEL PIPE (PANAMA
F1.2 US
CITY))
BERGROHR GMBH SIEGEN
F1.2 DE
(SIEGEN)
CONFAB TUBOS, S.A.
F1.2 BR
(PINDOMONHANGABA)
CORINTH PIPEWORKS
F1.2 GB
(CORINTH)
CORUS TUBES 20" MILL
F1.2 GB
(HARTLEPOOL)
CORUS TUBES 42" MILL
F1.2 GB
(HARTLEPOOL)
CORUS TUBES 84" MILL
F1.2 GB
(HARTLEPOOL)
EISENBAU KRAEMER M.B.H
F1.2 DE
(HILCHENBACH-DAHLBRUCH)
ERNDTEBRUCKER
F1.2 DE
EISENWERK (ERNDTEBRUCK)
EUROPIPE GMBH (MULHEIM
F1.2 DE
AD RUHR)
GROUP FIVE PIPE SAUDI
F1.2 SA
(DAMMAM)
F1.2 HUSTEEL (CHOLLANAM-DO) KR
F1.2 HYUNDAI HYSCO (ULSAN) KR
ILVA LAMIERE E TUBI
F1.2 IT
(TARANTO)
MANNESMANN FUCHS ROHR
F1.2 DE
(HAMM)
NATIONAL PIPE COMPANY
F1.2 SA
LIMITED (AL KHOBAR)
NIPPON STEEL
F1.2 JP
CORPORATION (KIMITSU)
NIPPON STEEL
F1.2 JP
CORPORATION (TOKAI)
NIPPON STEEL
F1.2 JP
CORPORATION (HIKARI)
F1.2 NKK TUBES (KAWASAKI-SH) JP
SAUDI STEEL PIPE CO.
F1.2 SA
(DAMMAM)
SEAH STEEL CO. (POHANG
F1.2 KR
CITY)
SUMITOMO METAL
F1.2 JP
INDUSTRIES (KASHIMA)
SUMITOMO METAL
F1.2 JP
INDUSTRIES (WAKAYAMA)
BENTELER STAHL/ROHR
F1.3 PIPE, LOW ALLOY CS - SEAMLESS B DE 2 2
(WERK 41) (PADERBORN)
BENTERLER STAHL/ROHR
F1.3 DE
(WERK 65) (DINSLAKEN)
JFE STEEL CORPORATION
F1.3 JP
(HANDA)
F1.3 NKK TUBES (KAWASAKI) JP
PRODUCTOS TUBULARES
F1.3 ES
S.A.(VALLE DE TRAPAGA)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Location Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment Requirements

SUMITOMO METAL IND.


F1.3 JP
(KAINAN)
SUMITOMO METAL IND.
F1.3 JP
(AMAGASAKI-SHI)
V&M DEUTSCHLAND GMBH
F1.3 DE
(ZEITHAIN)
VALLOUREC & MANNESMANN
F1.3 FR
(DEVILLE LES ROUEN)
VALLOUREC & MANNESMANN
F1.3 FR
(SAINT SAULVE)
VALLOUREC & MANNESMANN
F1.3 FR
(AULNOYE)
VALLOUREC & MANNESMANN
F1.3 DE
TUBES GMBH (MULHEIM)
Standardization -
4 F1.4 PIPE, STAINLESS STEEL - SEAMLESS B ALTECH 2 2
Category A
F1.4 ALTHAMMER DE
F1.4 ARCUS STAHL DE
F1.4 AVESTA POLARIT SW
F1.4 B.S.L. TUBES ET RACCORDS FR
F1 4
F1.4 BARLOWORLD SA
F1.4 BORUSAN BIRLESIK TK
F1.4 BUTTING DE
F1.4 CONSULTEX IT
F1.4 DALMINE IT
F1.4 DMV STAINLESS ITALIA IT
F1.4 DST TUBELARS CA
F1.4 EISENBAU KRAMER DE
F1.4 ESTA ROHR DE
F1.4 HAYNES
F1.4 IBF IT
F1.4 ILTA INOX IT
F1.4 INOTECH IT
F1.4 JARO FN
F1.4 JARO OY FN
F1.4 JAUN YUANG TA
F1.4 JFE (KAWASAKI) JP
F1.4 JIULI CN
4 F1.4 JUBAIL ENERGY SERVICES SA
F1.4 KANZEN TETSU MA
F1.4 KAWASAKI JP
F1.4 KOBE JP
F1.4 KUZE JP
F1.4 MACH
MANNESMANN DMV (COSTA
F1.4 IT
VOLPINO)
MANNESMANN DMV
F1.4 DE
(REMSCHEID)
MANNESMANN DMV
F1 4
F1.4 FR
(MONTBARD)
MANNESMANN DMV
F1.4 US
(HOUSTON, TX)
F1.4 MARCEGALIA US
F1.4 MOIZIEUX-GAUCHON IND FR
NANTONG SPECIAL STEEL
F1.4 CN
(NANTONG)
F1.4 NIKOPOL RU
F1.4 NIPPON STEEL JP
F1.4 NKK JP
OUTOKUMPU (AVESTA
F1.4 US
POLARIT)
F1.4 PEXCO (CLARKS SUMMIT, PA) US
F1.4 PRODUCTOS TUBULARES SP
PRZEDSIEBIORSTWO
F1.4 CZ
WALCOWNIA
F1.4 RED POINT ALLOYS NL
F1.4 RFF ROHR FLANCHE FITTING DE
F1.4 ROCKWELL COLLINS (IRVINE, C US
SALEM TUBE (GREENVILLE,
F1.4 US
PA)
F1.4 SANDVIK (SANDVIKEN) SW
F1.4 SANDVIK US
F1.4 SANDVIK IN
F1.4 SANDVIK (AMPRIOR) CA
F1.4 SANYO JP
SCHOELLER-BLECKMANN
F1.4 AU
(TERNITZ)
SHANGHAI JINCHANG
F1.4 CN
STAINLESS
F1.4 SIDERCA
S C ARGENTINA
G AR
F1.4 SITAI-INOX IT
F1.4 SOSTA DE
F1.4 SUMITOMO METALS JP
F1.4 SURAJ STAINLESS IN
F1.4 TC
F1.4 TRENT
F1.4 TUBACEX (LIODIO) SP
F1.4 TUBOS REUNIDOS S.A. SP
VALLOUREC &
F1.4 DE
MANNESSMANN
VALLOUREC &
F1.4 FR
MANNESSMANN FRANCE
F1.4 WALSIN SPECIALTY STEEL CN
WEBCO INDUSTRIES
F1.4 US
(MANNFORD, OK)
F1.4 WYMAN GORDON (IXP) US
F1.4 YEUN CHYANG INDUSTRIAL TA
F1.4 YUEN CHYANG CN

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Location Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment Requirements

ALTHAMMER GMBH U. CO.KG Standardization -


4 F1.5 PIPE, STAINLESS STEEL - WELDED B DE 2 2
(HEIDENHEIM) Category A
AVESTA SANDVIK TUBE AB
F1.5 SE
(TORSHALLA)
DMV STAINLESS FRANCE
F1.5 FR
(MONTBARD)
DMV STAINLESS ITALIA SRL
F1.5 IT
(COSTA VLOPINA)
DMV STAINLESS STEEL
F1.5 DE
(REMSCHEID)
ERNDTEBRUCKER
F1.5 DE
EISENWERK (ERNDTEBRUCK)
INOX TECH SPA - RONDA
F1.5 IT
GROUP (LENDINARA)
OUTOKUMPU STAINLESS
F1.5 US
(WILDWOOD)
OUTOKUMPU STAINLESS
F1.5 TUBULAR PRODUCT SE
(STORFORS)
PRODUCTOS TUBULARES
F1.5 ES
S.A. (VALLE DE TRAPAGA)
SANDVIK MATERIALS
F1.5 TECHNOLOGY AB SE
(SANDVIKEN)
SANDVIK TUBULAR
F1.5 US
PRODUCTS (CLARKS SUMMIT)
SOSTA
F1.5 EDELSTAHLROHRWERK DE
GMBH (KONNERN)
SUMITOMO METAL IND.
F1.5 JP
(AMAGASAKI-SHI)
DMV STAINLESS FRANCE
3 F1.6 PIPE, DUPLEX STAINLESS STEEL - SEAMLESS B FR 3 3
(MONTBARD)
DMV STAINLESS ITALIA SRL
F1.6 IT
(COSTA VLOPINA)
DMV STAINLESS STEEL
F1.6 DE
(REMSCHEID)
ERNDTEBRUCKER
F1.6 DE
EISENWERK (ERNDTEBRUCK)
H BUTTING GMBH & CO
F1.6 DE
(KNESEBECK)
MANNESMANN DMV
F1.6 US
STAINLESS (HOUSTON, TX)
OUTOKUMPU STAINLESS
F1.6 US
(WILDWOOD)
OUTOKUMPU STAINLESS
F1.6 TUBULAR PRODUCT SE
(STORFORS)
PRODUCTOS TUBULARES
F1.6 ES
S.A. (VALLE DE TRAPAGA)
SANDVIK MATERIALS
F1.6 TECHNOLOGY AB SE
(SANDVIKEN)
SANDVIK TUBULAR
F1.6 US
PRODUCTS (CLARKS SUMMIT)
SCHOELLER-BLECKMANN
F1.6 AT
(TERNITZ)
SOSTA
F1.6 EDELSTAHLROHRWERK DE
GMBH (KONNERN)
SUMITOMO METAL IND.
F1.6 JP
(AMAGASAKI-SHI)
TTI - TUBACEX TUBOS
F1.6 ES
INOXIDABLES SA (LLODIO)
3 F1.7 PIPE, DUPLEX STAINLESS STEEL - WELDED B ALTECH 3 3
F1.7 BRISTOL METALS US
F1.7 BUTTING DE
F1.7 DAVIS
F1.7 DMV
ERNDTEBRUCKER
F1.7 DE
EISENWERK (EEW)
F1.7 HAYNES
F1.7 KAWASAKI
F1.7 KOBE
F1.7 MACH
F1.7 MACH CORPORATION US
F1.7 MANNESMANN DMV IT
F1.7 MANNESMANN DMV DE
F1.7 NIPPON
OUTOKUMPU (AVESTA
F1.7 SW
POLARIT)
OUTOKUMPU (AVESTA
F1.7 US
POLARIT)
F1.7 PRODUCTOS TUBULARES
F1.7
F1 7 PUSAN PIPE
F1.7 RIVIT IT
F1.7 SANDVIK SW
F1.7 SANDVIK US
F1.7 SCHOELLER BLECKMANN AU
F1.7 SOSTA DE
F1.7 SUMITOMO
F1.7 SWEPCO US
F1.7 TC
F1.7 TRENT
F1.7 TUBACEX SP
F1.7 WYMAN GORDON
DMV STAINLESS FRANCE
3 F1.8 PIPE, NICKEL/NICKEL ALLOY - SEAMLESS B FR 2 2
(MONTBARD)
DMV STAINLESS STEEL
F1.8 DE
(REMSCHEID)
SANDVIK TUBULAR
F1.8 US
PRODUCTS (CLARKS SUMMIT)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Location Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment Requirements

SPECIAL METALS
F1.8 HUNTINGTON PLANT US
(HUNTINGTON)
SUMITOMO METAL IND.
F1.8 JP
(AMAGASAKI-SHI)
DMV STAINLESS FRANCE
3 F1.9 PIPE, NICKEL/NICKEL ALLOY - WELDED B FR 3 3
(MONTBARD)
DMV STAINLESS STEEL
F1.9 DE
(REMSCHEID)
SANDVIK TUBULAR
F1.9 US
PRODUCTS (CLARKS SUMMIT)
SPECIAL METALS
F1.9 HUNTINGTON PLANT US
(HUNTINGTON)
SUMITOMO METAL IND
F1.9 JP
(AMAGASAKI-SHI)
ALTHAMMER GMBH
3 F1.10 PIPE, TITANIUM B DE 3 3
(HEIDENHEIM)
F1.10 ATI WAH CHANG (USA) US
AVESTA SANDVIK TUBE AB
F1.10 SE
(TORSHALLA)
BENTELER STAHL/ROHR
F1.10 DE
(WERK 41) (PADERBORN)
BENTERLER STAHL/ROHR
F1.10 DE
(WERK 65) (DINSLAKE)
F1.10 CETAB UK
DMV STAINLESS FRANCE
F1.10 FR
(MONTBARO)
DMV STAINLESS STEEL
F1.10 DE
(REMSCHEID)
F1.10 FAE AR
F1.10 FLOMAC
F1.10 LOTERIOS IT
F1.10 MACH PIPE
F1.10 PENN
F1.10 PRECISION METAL SPIN
PRODUCTOS TUBULARES
F1.10 ES
S.A. (VALLE DE TRAPAGA)
F1.10 RMI TITANIUM (USA) US
SANDVIK TUBULAR
F1.10 US
PRODUCTS (CLARKS SUMMIT)
SPECIAL METALS
F1.10 US
(HUNTINGTON) PLANT
SUMITOMO METAL IND
F1.10 JP
(AMAGASAKI-SHI)
F1.10 TICO TITANIUM
F1.10 TIFAB
F1.10 TIMET US
TITANIUM FABRICATION
F1.10 US
(FAIRFIELD, NJ)
F1.10 TRICOR US
TUBOS REUNIDOS S.A.
F1.10 ES
(AMURRIO)
F1.10 UNITI US
V&M DEUTSCHLAND GMBH
F1.10 DE
(ZEITHAIN)
VALLOUREC & MANNESMANN
F1.10 FR
(DEVILLE LES ROUEN)
VALLOUREC & MANNESMANN
F1.10 FR
(SAINT SAULVE)
VALLOUREC & MANNESMANN
F1.10 DE
(AULNOYE)
F1.11 PIPE, ALUMINUM B 2 2
F1.12 PIPE, LIMITED STRENGTH ALLOYS - COPPER B 2 2
AMIANTIT OMAN (MUSCAT,
F1.13 PIPE, HDPE B SA 2 2
OMAN)
INDEPENDENT PIPE
F1.13
PRODUCTS, INC.
F1.13 POLYPIPE
F1.13 POLYTUBES
F1.13 US POLY COMPANY
F1.13 WL PLASTICS
NEW PRODUCTS INDUSTRIES
F1.14 PIPE, PVC B SA 2 2
(NEPRO) (JEDDAH)
SAUDI INDUSTRIES FOR
F1.14 SA
PIPES COMPANY (JEDDAH)
SAUDI PLASTIC PRODUCTS
F1.14 SA
COMPANY (RIYADH)
Standardization -
FUTURE PIPE INDUSTRIES Category A, Future
4 F1.15 PIPE, FRP - CUSTOM FABRICATION (VINYLESTER) B SA 3 3
(DAMMAM) Pipe is the selected
PLA Vendor
F1.15 AMERON PTE (SINGAPORE) SG
NKT FLEXIBLES I/S
F1.15 DK
(KALUNDBORG)
PIPELIFE NETHERLANDS B.V.
F1.15 NL
(ENKHUIZEN)
WELLSTREAM INT'L
F1.15 GB
(NEWCASTLE)
AN-COR INDUSTRIAL
F1.15 US
PLASTICS - PIPING
EDO SPECIALTY PLASTICS -
F1.15 US
PIPING
ENDURO SYSTEMS (VESCA
F1.15 US
DIVISION) - PIPING
F1.15 FIBREX CA
KUROTEC-KTS
F1.15 KUNSTSTOFFTECHNIK STADE DE
GMBH
F1.15 OLLEARIS S.A. SP
F1.15 PLASTILON OY FI

F1.15 PROSKE PLASTIC PRODUCTS US

REINFORCED PLASTIC
F1.15 CA
SYSTEMS (RPS)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Location Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment Requirements

TROY MANUFACTURING
F1.15 US/CA
CANADA
F1.15 RL INDUSTRIES US
F1.15 TRI-CLOR US
BONDSTRAND LIMITED Standardization -
4 F1.16 PIPE, FRP - LIGHT DUTY - COMMODITY (EPOXY) B SA 2 3
(DAMMAM) Category A
Standardization -
FUTURE PIPE INDUSTRIES Category A, Future
4 F1.16 SA
(DAMMAM) Pipe is the selected
PLA Vendor
AMERON B.V.
F1.16 NL
(GELDERMALSEN)
F1.16 AMERON PTE (SINGAPORE) SG
NKT FLEXIBLES I/S
F1.16 DK
(KALUNDBORG)
PIPELIFE NETHERLANDS B.V.
F1.16 NL
(ENKHUIZEN)
WELLSTREAM INT'L
F1.16 GB
(NEWCASTLE)
F1.16 AMERON (BONDSTRAND)

F1.16 COMPOSITE PIPES INDUSTRY OMAN

GULF ETERNIT / FUTURE PIPE


F1.16 UAE
INDUSTRIES
FIBERGLASS SYSTEM
F1.16 US
(SMITH/STAR/FIBERCAST)
AMIANTIT EPOXY PIPE Standardization -
4 F1.17 PIPE, FRP - LIGHT DUTY - COMMODITY (VINYLESTER) B SA 2 3
PRODUCTION (DAMMAM) Category A
BONDSTRAND LIMITED
F1.17 SA
(DAMMAM)
Standardization -
FUTURE PIPE INDUSTRIES Category A, Future
4 F1.17 SA
(DAMMAM) Pipe is the selected
PLA Vendor
F1.18 PIPE, GLASS LINED B DE DIETRICH US 2 2
F1.18 PFLAUDER US
F1.18 TYCON TECHNOGLASS US
F1.19 PIPE, FRP - PIPING - DUAL LAMINATE B CPF DUALAM CA 3 3
ENDURO SYSTEMS (VESCA
F1.19 US
DIVISION)
KUROTEC-KTS
F1.19 KUNSTSTOFFTECHNIK STADE DE
GMBH
F1.19 PLASTILON OY FI
H BUTTING GMBH & CO
F1.20 PIPE, STEEL; CLAD INTERNAL; EXTERNAL WIT B DE 3 3
(KNESEBECK)
KLAD MANUFACTURING
F1.20 US
(HOUSTON, TX)
PROCLAD INTERNATIONAL
F1.20 GB
(GLENROTHES)
NKT FLEXIBLES I/S
F1.21 PIPE, METALLIC; FLEXIBLE; NYLON AND POLY B DK 2 2
(KALUNDBORG)
AMERON SAUDI ARABIA LTD
F1.22 PIPE, METALLIC; STEEL; CEMENT LINED; PLA B SA 2 2
(DAMMAM)
GEYAD FACTORY FOR
F1.22 PRESSURE VESSELS SA
(ALKHOBAR)
MOHAMMAD AL-MOJIL GROUP
F1.22 SA
STEEL (DAMMAM)
AL-QAHTANI PIPE COATING
F1.23 PIPE, METALLIC; STEEL; CONCRETE; B SA 2 2
TERMINAL (DAMMAM)
SUMITOMO METAL
F1.23 JP
INDUSTRIES (WAKAYAMA)
F1.24 PIPE, METALLIC; STEEL; GALVANIZED; B SAUDI STEEL PIPE (DAMMAM) SA 2 2
SUMITOMO METAL
F1.24 JP
INDUSTRIES (WAKAYAMA)
WHEATLAND TUBE COMPA
F1.24 US
(WHEATLAND)
Standardization -
F1.25 PIPE, PLASTIC LINED PIPING - PTFE/PP/PVDF B CRANE RESISTOFLEX US 2 2
Category C
F2.0 PIPE BENDING
ALASKAN COPPER WORKS
F2.1 PIPE BENDING B US 3 3
(SEATTLE)
BASSI LUIGI & C. S.P.A. (SAN
F2.1 IT
ROCA AL PORTO)
BENEX CORPORATION (KIRYU-
F2.1 JP
SHI, GUNMA-KEN)
BENEX CORPORATION
F2.1 JP
(AMAGASAKI-SHI)
BENEX CORPORATION (YUUKI-
F2.1 JP
SHI)
BILFAL HEAVY INDUSTRIES
F2.1
F2 1 SA
LTD. (JUBAIL)
CUSTOM ALLOY
F2.1 CORPORATION (HIGH US
BRIDGE)
DAI-ICHI HIGH FREQUENCY
F2.1 JP
(KISARAZU-SHI, CHIBA-KEN)
DYNAMIC PRODUCTS
F2.1 US
(HOUSTON, TX)
ERNE FITTINGS GMBH
F2.1 AT
(SCHLINS)
FABRICOM GTI
F2.1 BE
(GRIMBERGEN)
LADISH DIVISION/TRINITY
F2.1 US
(RUSSELLVILLE)
LINVIC ENGINEERING
F2.1 GB
(WOLVERHAMPTON)
MITSUI BABCOCK ENERGY
F2.1 GB
SERVICES (RENFREW)
F2.1 NIPPON BEND (TOKYO) JP

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Location Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment Requirements

NIPPON STEEL
F2.1 JP
CORPORATION (KIMITSU)
PETROL RACCORD SPA
F2.1 IT
(CALENDASCO)
F2.1 PIANA SPA (STRADELLA) IT
F2.1 PSL LIMITED (NANI CHIRAI) IN
SAUDI STEEL PIPE COMPANY
F2.1 SA
LIMITED (DAMMAM)
SHAW NASS MIDDLE EAST
F2.1 BH
W.L.L (MANAMA)
SHAW SUNLAND
F2.1 US
FABRICATORS, INC.
SIMAS SPA (PREZZATE DI
F2.1 IT
MAPELLO)
SPIE ENERTRANS (CERGY
F2.1 FR
PONTOISE CEDEX)
F2.1 SUNGJIN GEOTEC (ULSAN) KR
SUNGKWANG BEND
F2.1 KR
(GANGSEO-KU, BUSAN)
TECNOFORGE SPA (CASTEL
F2.1 IT
SAN GIOVANNI)
F2.1 TECNOFORGE SPA (ARENO) IT
TECTUBI
C U RACCORDI
CCO SPA
S
F2 1
F2.1 IT
(PODENZANO)
F2.1 TK CORPORATION (PUSAN) KR
TUBACEX TAYLOR
F2.1 ACCESORIOS SA ES
(ARCENIEGA)
TUBE FORGINGS OF AMERICA
F2.1 US
(PORTLAND)
WESTER PIJPLEIDINGEN
F2.1 NL
(STRIJEN)
WILHELM GELDBACH
F2.1 INDUSTRIE GMBH DE
(GELSENKIRCHEN)
F3.0 PIPE SPOOL FABRICATION - METALLIC
ABDULLAH AL-HAMOUD AL-
F3.1 PIPE SPOOL FABRICATION - METALLIC B SA 3 3
SHUWAYER (DH. AIRPORT)
ALASKAN COPPER WORKS
F3.1 US
(SEATTLE)
AL-QAHTANI PIPE COATING
F3.1 SA
TERMINAL (DAMMAM)
AL-ZAMIL COMPANY FOR
F3.1 SA
HEAVY STEEL (JEDDAH)
ASIA STEEL FACTORY CO
4 F3.1 TH
LTD.
AVESTA SANDVIK TUBE AB
F3.1 SE
(TORSHALLA)
BASSI LUIGI & C. S.P.A. (SAN
F3.1 IT
ROCA AL PORTO)
BILFAL HEAVY INDUSTRIES
F3.1 SA
(JUBAIL)
CHICAGO BRIDGE &
F3.1 US
IRON/HOWE-BAKER (TYLER)
DAE HAN PRECISION &
F3 1
F3.1 KR
INDUSTRIES (GYEONGJU)
FABRICOM GTI
F3.1 BE
(GRIMBERGEN)
FAI OFFICINE DI CARVICO SPA
F3.1 IT
(CARVICO)
GEYAD FACTORY FOR
F3.1 PRESSURE VESSELS SA
(ALKHOBAR)
H BUTTING GMBH & CO
F3.1 DE
(KNESEBECK)
HYUNDAI HEAVY INDUSTRIES
F3.1 KR
(ULSAN KYUNGNAM)
IODS (EAST KILBRIDE,
F3.1 GB
GLASGOW)
KLAD MANUFACTURING
F3.1 US
(HOUSTON, TX)
L.P. S.P.A. (VENEGONO-
F3.1 IT
SUPERIORE)
MARITIME INDUSTRIAL
F3.1 SA
SERVICES (JUBAIL)
F3.1 MC DERMOTT (DUBAI) AE
MITSUI BABCOCK ENERGY
F3.1 GB
SERVICES LTD (RENFREW)
MOHAMMAD AL-MOJIL GROUP
F3.1 SA
STEEL (DAMMAM)
NIPPON STEEL
F3.1 JP
CORPORATION (KIMITSU)
PROCLAD INTERNATIONAL
F3.1 GB
(GLENROTHES)
SAUDI ARABIAN FABRICATED
F3.1 SA
METALS (ALKHOBAR)
SHAW NASS MIDDLE EAST
F3.1 BH
W.L.L (MANAMA)
SHAW SUNLAND
F3.1 US
FABRICATORS (WALKER)
SPIE ENERTRANS (CERGY
F3.1 FR
PONTOISE CEDEX)
F3.1 SUNG IL (BUSAN) KR
SWECO FAB PIPING
F3.1 TECHNOLOGIES (HOUSTON, US
TX)
VALLOUREC & MANNESMANN
F3.1 FR
(DEVILLE LES ROUEN)
YANBU STEEL COMPANY
F3.1 SA
(YANBU)
F4.0 PIPE COATING
AL-QAHTANI PIPE COATING
F4.1 PIPE COATING B SA 3 3
TERMINAL (DAMMAM)
ARABIAN PIPE COATING
F4.1 SA
COMPANY (JUBAIL)
ARABIAN PIPES COMPANY
F4.1 SA
(APC) (RIYADH)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Model / Design Manufacturers Location Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment Requirements

BREDERO SHAW
F4.1 GB
(EDINBURGH)
BSR PIPELINE SERVICES
F4.1 GB
(HARTLEPOOL)
GLOBAL ANTI CORROSION
F4.1 SA
TECHNIQUES (JUBAIL)
JFE STEEL CORPORATION
F4.1 JP
(FUKUYAMA)
MANNESMANN FUCHS IPE
F4.1 DE
GMBH ROHR (HAMM)
SUMITOMO METAL
F4.1 JP
INDUSTRIES (WAKAYAMA)
UMRAN STEEL PIPE
F4.1 TR
(UMRANIYE)
UMRAN STEEL PIPE
F4.1 TR
(AKCAKOCA)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
2 G 1.0 FITTINGS
Standardization -
4 G1.1 FITTINGS, CS & LOW ALLOY- SW &THRD B BONNEY FORGE (MT. UNION) US 2 0
Category A
G1.1 DELCORTE SA (MAUBEUGE) FR
I.M.L. INDUSTRIA MECCANICA
G1.1 IT
(CASARZA LIGURE)
MEGA SPA
G1.1 IT
(SCANZOROSCIATE)
SUNGKWANG BEND
G1.1 KR
(GANGSEO-KU, BUSAN)
G1.1 ULMA FORJA (ONATI) ES
WFI BONNEY FORGE
G1.1 US
(HOUSTON, TX)
BASSI LUIGI & C. SPA (SAN Standardization -
4 G1.2 FITTINGS, CS & LOW ALLOY- BW & SMLS B IT 2 2
ROCA AL PORTO Category A
BENEX CORPORATION (KIRYU-
G1.2 JP
SHI, GUNMA-KEN)
CANADOIL FORGE LTD./LTEE
G1.2 CA
(BECANCOUR, PQ)
CUSTOM ALLOY (SPECIAL
G1.2 SIZES AND WALLS) (HIGH US
BRIDGE)
DYNAMIC PRODUCTS
G1 2
G1.2 US
(HOUSTON, TX)
G1.2 ERNE (MUERZZUSCHLAG) AT
G1.2 ERNE FITTINGS (SCHLINS) AT
INTERFIT SA GROUP
G1.2 FR
VALLOUREC (MAUBEUGE)
PETROL RACCORD SPA
G1.2 IT
(CALENDASCO)
SHAW ALLOY PIPING
G1.2 PRODUCTS (SHREVEPORT, US
LA)
STEEL FORGINGS (SADDLES,
G1.2 REDUCERS) (SHREVEPORT, US
LA)
SUNGKWANG BEND CO. LTD
G1.2 KR
(GANGSEO-KU, BUSAN)
G1.2 TECHNOFORGE (ARENO) IT
TECNOFORGE SPA (CASTEL
G1.2 IT
SAN GIOVANNI)
TECTUBI RACCORDI (Large
G1.2 IT
OD) (PODENZANO)
TFA (TUBE FORGING OF
G1.2 US
AMERICA) (PORTLAND, OR)
G1.2 TK CORPORATION (PUSAN) KR
TUBACEX TAYLOR
G1.2 ACCESORIOS SA ES
(ARCENIEGA)
VILMAR SA (RAMNICU
G1.2 RO
VALCEA)
G1.2 WELDBEND (ARGO) US
WILLHELM GELDBACH
G1.2 INDUSTRIE GMBH DE
(GELSENKIRCHEN)
SAUDI ARABIAN FABRICATED
G1.2 SA
METALS (ALKHOBAR)
BASSI LUIGI & C. S.P.A. (SAN Standardization -
4 G1.3 FITTINGS, CS & LOW ALLOY- BW WELDED B IT 2 2
ROCA AL PORTO) Category A
BENEX CORPORATION (KIRYU-
G1.3 JP
SHI, GUNMA-KEN)
G1.3 BENKAN (BENEX)
CANADOIL FORGE LTD./LTEE
G1.3 CA
(BECANCOUR, PQ)
CUSTOM ALLOY (SPECIAL
G1.3 SIZES AND WALLS) (HIGH US
BRIDGE)
DYNAMIC PRODUCTS
G1.3 US
(HOUSTON, TX)
G1.3 ERNE (MUERZZUSCHLAG) AT
G1.3 ERNE FITTINGS (SCHLINS) AT
INTERFIT SA GROUP
G1.3 FR
VALLOUREC (MAUBEUGE)
PETROL RACCORD SPA
G1.3 IT
(CALENDASCO)
SHAW ALLOY PIPING
G1.3 PRODUCTS (SHREVEPORT, US
LA)
STEEL FORGINGS (SADDLES,
G1.3 REDUCERS) (SHREVEPORT, US
LA)
SUNGKWANG BEND
G1.3 KR
(GANGSEO-KU, BUSAN)
G1.3 TECHNOFORGE (ARENO) IT
TECNOFORGE SPA (CASTEL
G1.3 IT
SAN GIOVANNI)
TECTUBI RACCORDI (LARGE
G1.3 IT
OD) (PODENZANO)
TFA (TUBE FORGING OF
G1.3 US
AMERICA) (PORTLAND, OR)
G1.3 TK CORPORATION (PUSAN) KR
TUBACEX TAYLOR
G1.3 ACCESORIOS SA ES
(ARCENIEGA)
G1.3 VILMAR SA (RAMNICU RO
G1.3 WELDBEND (ARGO) US
WILLHELM GELDBACH
G1.3 INDUSTRIE GMBH DE
(GELSENKIRCHEN)
SAUDI ARABIAN FABRICATED
G1.3 SA
METALS (ALKHOBAR)
BONDSTRAND LIMITED
2 G1.4 FITTINGS, NON-METALIC, ANY TYPE; ANY SIZE B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE SA 2 0
(DAMMAM)
AMIANTIT FIBERGLASS
2 G1.5 FITTINGS, NON-METALIC; GASKET JOINTS B SA 2 0
INDUSTRIES (DAMMAM)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
FUTURE PIPE INDUSTRIES
G1.5 SA
(DAMMAM)
ALLOY STAINLESS Standardization -
4 G1.6 FITTINGS, SSTL - SOCKET WELD AND THREADED B US 2 1
PRODUCTS Category A
G1.6 BONNEY FORGE (MT. UNION) US
G1.6 CAMCO
CAPITOL/CAMCO/PHOENIX
G1.6 US
FORGE
G1.6 CHERO PIPING SPA
CORROSION MATLS
G1.6
(HASTELLOY ONLY)
G1.6 DELCORTE FR
G1.6 EZEFLOW US/CA
G1.6 GIBSON
G1.6 IML IT
G1.6 ISE JP
G1.6 J&J
KINGDOM PRECISION
G1.6 CN
CASTING
G1.6 LAME IT
G1.6 LAME SRL
G1 6
G1.6 MEGA IT
G1.6 OMC RACCORDI IT
G1.6 PENN MACHINE US
G1.6 PENN MACHINE- TEXAS PMW US
G1.6 PHOENIX - CAMCO US
G1.6 SUNGKWANY KR
G1.6 TC
G1.6 TK
G1.6 VIAR MECCANICA SRL IT
G1.6 WELDING OUTLETS US
G1.6 WESTBROOK US
G1.6 WFI
WFI (BONNEY FORGE)
G1.6 US
(HOUSTON, TX)
Standardization -
4 G1.7 FITTINGS, SSTL - BUTT WELD - SEAMLESS B APP (SHAW) US 2 2
Category A
G1.7 AWAJI (ASK) TH
G1.7 BENKAN (BENEX) JP
G1.7 BUTTING DE
G1.7 CLOSEBEND US
CORE PRODUCTS (GERLIN
G1.7 US
TUBETECH)
G1.7 CUSTOM ALLOY US
DYNAMIC PRODUCTS
G1.7 US
(HOUSTON, TX)
G1.7 ERNE AU
G1.7 ERNE FR
G1.7 EZEFLOW CA
G1.7 FILMAG ITALIA IT
G1 7
G1.7 FLOMAC US
G1.7 FLOWLINE US
G1.7 FORMWELD US
G1.7 GAM RACCORDI IT
G1.7 GIBSON
G1.7 J&J
G1.7 JARO OY FN
G1.7 JERO US
G1.7 KANZEN TETSU SDN BHD MY
G1.7 KREMO DE
G1.7 MACH US
G1.7 MARDALE UK
G1.7 NAUTIC STEELS UK
G1.7 NIROBO DE
O.M.R. (OFFICINE
G1.7 IT
MECCANICHE RIGHI)
G1.7 OUTOKUMPO ABE CA
G1.7 OUTOKUMPO STAINLESS FN
G1.7 PETROL RACCORD IT
G1.7 PICOR (CORE PIPE) US
G1.7 RACCORTUBI/TECHNINOX IT
SANDVIK MATERIAL
G1.7 UK
TECHNOLOGY UK
G1.7 SCHULZ, KREFELD DE
SHAW - ALLOY PIPING
G1.7 US
PRODUCTS
G1.7 SSE PIPE FITTINGS UK
G1.7 SUNGKWANG BEND KR
G1.7 T.T.U./T.T.C. TH
G1.7
G1 7 TA CHEN TA
G1.7 TAYLOR FORGE
G1.7 TC
G1.7 TECHNOBEND IT
G1.7 TECHNOFORGE IT
G1.7 TECTUBI RACCORDI IT
G1.7 TK CORP KR
G1.7 VALEN UK
G1.7 WEIR MATERIALS LIMITED UK
G1.7 WFI BONNEY FORGE US
G1.7 WILHELM SCHULTZ DE
G1.7 WILHELM SCHULTZ BR
Standardization -
4 G1.8 FITTINGS, SSTL - BUTT WELD - WELDED B APP (SHAW) US 2 2
Category A
G1.8 AWAJI (ASK) TH
G1.8 BENKAN (BENEX) JP
G1.8 BUTTING DE
G1.8 CLOSE BEND

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
CORE PRODUCTS
G1.8 US
(GERLINTUBETECH)
G1.8 CUSTOM ALLOY US
G1.8 DYNAMIC PRODUCTS US
G1.8 ERNE AU
G1.8 ERNE FR
G1.8 EZEFLOW CA
G1.8 FILMAG ITALIA IT
G1.8 FLOMAC US
G1.8 FLOWLINE US
G1.8 FORMWELD FITTINGS US
G1.8 GAM RACCORDI IT
G1.8 GIBSON
G1.8 J&J
G1.8 JARO OY FN
G1.8 JERO US
G1.8 KANZEN TETSU SDN BHD MY
G1.8 KREMO DE
G1.8 MACH US
G1.8 MARDALE UK
G1 8
G1.8 NAUTIC STEELS UK
G1.8 NIROBO DE
O.M.R. (OFFICINE
G1.8 IT
MECCANICHE RIGHI)
G1.8 OUTOKUMPU ABE CA
G1.8 OUTOKUMPU STAINLESS FN
G1.8 PETROL RACCORD IT
G1.8 PICOR (CORE PIPE) US
G1.8 RACCORTUBI/TECHNINOX IT
SANDVIK MATERIAL
G1.8 UK
TECHNOLOGY
G1.8 SCHULTZ (KREFELD) DE
G1.8 SHAW ALLOY PRODUCTS US
G1.8 SSE PIPE FITTINGS UK
G1.8 SUNGKWANG BEND KR
G1.8 T.T.U./T.T.C. TH
G1.8 TA CHEN TA
G1.8 TAYLOR FORGE
G1.8 TC
G1.8 TECHNOBEND SPA IT
G1.8 TECHNOFORGE IT
G1.8 TECTUBI RACCORDI IT
G1.8 TK CORP KR
G1.8 VALEN UK
G1.8 WEIR MATERIALS LIMITED UK
G1.8 WFI BONNEY FORGE US
G1.8 WILHELM SCHULTZ BR
G1.8 WILHELM SCHULTZ DE
2 G1.9 FITTINGS, DUPLEX SSTL - SMLS AND WELDED B APP (SHAW) US 2 2
G1.9 AWAJI (ASK) TH
G1.9 BENKAN (BENEX) JP
G1.9 CLOSE BEND
CORE PRODUCTS
G1.9 US
(GERLINTUBETECH)
G1.9 CUSTOM ALLOY US
G1.9 DYNAMIC PRODUCTS
G1.9 ERNE AU
G1.9 EZEFLOW CA
G1.9 FILMAG ITALIA IT
G1.9 FLOMAC
G1.9 FLOWLINE US
G1.9 FORMWELD
G1.9 GAM RACCORDI IT
G1.9 GIBSON
G1.9 J&J
G1.9 KANZEN TETSU SDN BHD MY
G1.9 MACH US
G1.9 MARDALE UK
O.M.R. (OFFICINE
G1.9 IT
MECCANICHE RIGHI)
G1.9 OUTOKUMPO ABE CA
G1.9 PETROL RACCORD IT
SANDVIK MATERIAL
G1.9 UK
TECHNOLOGY UK
G1.9 SCHULTZ DE
G1.9 SHAW ALLOY PRODUCTS US
G1.9 SSE PIPE FITTINGS UK
G1.9 SUNGKWANG BEND KR
G1.9 T.T.U./T.T.C. TH
G1.9 TAYLOR FORGE
G1.9 TC
G1.9 TECHNOBEND SPA IT
G1.9 TECTUBI RACCORDI IT
G1.9 VALEN UK
G1.9 WEIR MATERIALS LIMITED UK
G1.9 WFI BONNEY FORGE US
G1.9 WILHELM SCHULTZ DE
2 G1.10 FITTINGS, NICKEL/NICKEL ALLOY - SMLS & WELDED B APP 2 2
BESTWELD (SEAMLESS
G1.10 US
ONLY)
G1.10 CUSTOM ALLOY US
G1.10 DYNAMIC PRODUCTS US
G1.10 ERNE AU
G1.10 EZEFLOW CA
G1.10 FILMAG-ITALIA IT
G1.10 FLOMAC US

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
G1.10 FLOWLINE US
G1.10 FORMWELD
G1.10 GIBSON
G1.10 J & J MACHINE US
G1.10 JERO
G1.10 MACH US
G1.10 PENN MACHINE US
G1.10 SCHULTZ
SHAW - ALLOY PIPING
G1.10 US
PRODUCTS
G1.10 TAYLOR FORGE
G1.10 WFI
G1.10 WILHELM SCHULTZ DE
2 G1.11 FITTINGS, TITANIUM B ATI 2 2
G1.11 ERNE AU
EZ-FLOW - BUTTWELD
G1.11
FITTINGS
G1.11 FLO MAC US
FORMWELD - BUTTWELD
G1.11
FITTINGS
G1.11 LOTERIOS IT
G1.11 MACH US
TICO TITANIUM INC OF TEXAS
G1.11
PIPE
G1.11 TIFAB
G1.11 TIMET
G1.11 TRICOR US
G1.11 UNITED TITANIUM US
G1.11 UNITI
G1.11 WFI
G1.11 PENN

2 G1.12 FITTINGS, POLYETHYLENE B 2 2

2 G1.13 FITTINGS, CPVC B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE SPEARS MANUFACTURING INT 2 0
AMIANTIT OMAN (MUSCAT,
2 G1.14 FITTINGS, FABRICATED - 'HDPE B 2 2
OMAN)
G1.14 HIGH COUNTRY FUSION
INDEPENDENT PIPE
G1.14
PRODUCTS
CENTRAL PLASTICS
2 G1.15 FITTINGS, MOLDED - 'HDPE B 2 2
COMPANY
G1.15 US POLY COMPANY
2 G1.16 FITTINGS, PVC B SPEARS MANUFACTURING INT 2 0
2 G1.17 FITTINGS, PFA B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE 2 0
2 G1.18 FITTINGS, GLASS LINED DE DIETRICH 1 2
G1.18 PFLAUDER
G1.18 TYCON TECHNOGLASS
2 G2.0 FLANGES
METALFAR PRODOTTI
Standardization -
4 G2.1 FLANGES, CS & LOW ALLOY - SW, THRD & LAP JOINT B INDUSTRIALI SPA (CESANA IT 2 1
Category A
BRIANZA)
NATIONAL FLANGE AND
G2.1 US
FITTING (HOUSTON, TX)
PRECISION FORGINGS
G2.1 SA
FACTORY (ALKHOBAR)
G2.1 ULMA FORJA (ONATI) ES
ARABIAN METALS COMPANY Standardization -
4 G2.2 FLANGES, CS AND LOW ALLOY - WELD NECK B SA 2 2
DAMMAM Category A
G2.2 GALPERTI (HOUSTON, TX) US
METALFAR PRODOTTI
G2.2 INDUSTRIALI SPA (CESANA IT
BRIANZA)
NATIONAL FLANGE AND
G2.2 US
FITTING (HOUSTON, TX)
OFFICINE A. MELESI .
G2.2 IT
(CORTENOVA)
PRECISION FORGINGS
G2.2 SA
(ALKHOBAR)
G2.2 ULMA FORJA (ONATI) ES
WILHELM GELDBACH
G2.2 DE
(GELSENKIRCHEN)
Standardization -
4 G2.3 FLANGES, SS - SW, THREADED AND LAP JOINT B AMERIFORGE SW 2 1
Category A
G2.3 BO & AKE EGBERGS
G2.3 CARLSON
CORE PRODUCTS (GERLINE
G2.3 US
TUBE-LINE)
CORROSION MATERIALS
G2.3 US
(HASTELLOY GRADES)
F.A.D. FLANG ACCIANO &
G2.3 IT
DERIVATI SPA
FLANSCHENWERK BEBITZ
G2.3 DE
GMBH
G2.3 FRIULANA FLANGE IT
GALPERTI GROUP (NOT
G2.3 US
GALPERTI S.R.L.)
G2.3 GELBACH
G2.3 GIBSON
HAYNES INTERNATION
G2.3 US
(HASTELLOY GRADES)
G2.3 J & J MACHINE US
JIANGYIN HENGYOU
G2.3 CH
HARDWARE
G2.3 JMD VIRAJ IN
G2.3 KERKAU US
G2.3 KOFCO KR
G2.3 KOREA FLANGE KR
M.G.I (MOIZIEUX-GACHON
G2.3 FR
INDUSTRIE)
G2.3 MAASS FLANGE UA

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
G2.3 MAASS MX
G2.3 MARDALE UK
G2.3 METALFAR IT
G2.3 NEWMANS
G2.3 OFFICINE AMBROGIO MELESI IT
G2.3 OFFICINE SANTAFEDED SRI
G2.3 SPECIAL FLANGE SERVICES UK
TEXAS METAL WORKS
G2.3 US
(AMERIFORGE)
TUBELINE (CORE PIPE)
G2.3 US
(STAINLESS ONLY)
G2.3 VIRAJ (STAINLESS ONLY) IN
W. GELDBACH PIPING
G2.3 DE
EQUIPMENT
G2.3 WAFFENSCHMIDT DE
G2.3 WEIR MATERIALS UK
G2.3 WELDING UNITS UK
G2.3 WESTBROOK US
G2.3 WESTERN FORGE & FLANGE US
WFI (BONNEY FORGE)
G2.3 US
(SPECIAL ONLY)
G2 3
G2.3 WUXI HUAAN FLANGES CH
G2.3 ZAPP DE
ZHANGJIAGANG SANLIN
G2.3 CH
FLANGE
OFFICINE A. MELESI AND Standardization -
4 G2.4 FLANGES, STAINLESS STEEL - WELD NECK B IT 2 2
(CORTENOVA) Category A
G2.4 VIRAJ FORGINGS IN
G2.4 AMERIFORGE INT
G2.4 BO & AKE EDBERGS SW
G2.4 CARLSON INT
CORE PRODUCTS (GERLINE
G2.4 US
TUBE-LINE)
CORROSION MATERIALS
G2.4 US
(HASTELLOY GRADES)
F.A.D. (FLANGE ACCIANO &
G2.4 IT
DERIVATI SPA)
FLANSCHENWERK BEBITZ
G2.4 DE
GMBH
G2.4 FRIULANA FLANGE IT
GALPERTI GROUP (NOT
G2.4 US
GALPERTI S.R.L.)
G2.4 GELBACH INT
G2.4 GIBSON INT
HAYNES INTERNATIONAL
G2.4 US
(HASTELLOY GRADES)
G2.4 J & J MACHINE US
JIANGYIN HENGYOU
G2.4 CH
HARDWARE
G2.4 JMD VIRAJ IN
G2.4 KERKAU US
G2.4 KOFCO KR
G2.4 KOREA FLANGE KR
LINVIC ENGINEERING
G2.4 GB
(WOLVERHAMPTON)
M.G.I (MOIZIEUX-GAUCHON
G2.4 FR
INDUSTRIE)
G2.4 MAASS FLANGE US
G2.4 MAASS MX
G2.4 MARDALE UK
G2.4 METALFAR IT
G2.4 NEWMANS INT
OFFICINE NICOLA GALPERTI &
G2.4 IT
FIGLIO (DERIVO)
G2.4 OFFICINE SANTAFEDE SRI INT
G2.4 RINGROLLERS (SPRINGS) ZA
SBS- SPECIAL BRIDES
G2.4 FR
SERVICE (BOEN SURLIGNON)
SPECIAL FLANGE SERVICES
G2.4 UK
LTD.
TEXAS METAL WORKS
G2.4 US
(AMERIFORGE)
TUBELINE (CORE PIPE)
G2.4 US
(STAINLESS ONLY)
G2.4 VILMAR SA (RAMNICU RO
W. GELDBACH PIPING
G2.4 DE
EQUIPMENT
G2.4 WAFFENSCHMIDT DE
G2.4 WEIR MATERIALS UK
G2.4 WELDING UNITS UK
G2.4 WESTBROOK US
G2.4 WESTERN FORGE & FLANGE US
WFI (BONNEY FORGE)
G2.4 US
(SPECIAL ONLY)
G2.4 WUXI HUAAN FLANGES CH
G2.4 ZAPP DE
ZHANGJIAGANG SANLIN
G2.4 CH
FLANGE
BRUCK GMBH ENSHEIM
2 G2.5 FLANGES, SWIVEL B DE 2 2
(SAARBRUECKEN)
FORGEROSSI S.A.S.
G2.5 IT
(ARSIERO)
GALPERTI INCORPORATED
G2.5 US
(HOUSTON, TX)
LINVIC ENGINEERING LIMITED
G2.5 GB
(WOLVERHAMPTON)
MEGA SPA
G2.5 IT
(SCANZOROSCIATE)
OFFICINE A. MELESI AND CO.
G2.5 IT
(CORTENOVA)
OFFICINE NICOLA GALPERTI &
G2.5 IT
FIGLIO (DERIVO)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
OIL STATES INDUSTRIES
G2.5 US
(HOUSTON, TX)
AMIANTIT FIBERGLASS
2 G2.6 FLANGES, RTRP B SA 2 0
INDUSTRIES (DAMMAM)
BONDSTRAND LIMITED
G2.6 SA
(DAMMAM)
FUTURE PIPE INDUSTRIES
G2.6 SA
(DAMMAM)
2 G2.7 FLANGES, DUPLEX - SW, THR AND LAP JOINT B AMERIFORGE 2 1
G2.7 BO & AKE EGBERGS SW
G2.7 CARLSON
CORE PRODUCTS (GERLINE
G2.7 US
TUBE-LINE)
CORRISION MATERIALS
G2.7 US
(HASTELLOY GRADES)
F.A.D. (FLANGE ACCIANO &
G2.7 IT
DERIVATI SPA)
FLANSCHENWERK BEBITZ
G2.7 DE
GMBH
G2.7 FRIULANA FLANGE IT
GALPERTI GROUP (NOT
G2.7 US
GALPERTI S.R.L.)
G2.7 GELBACH
G2.7 GIBSON
HAYNES INTERNATIONAL
G2.7 US
(HASTELLOY GRADES)
G2.7 J & J MACHINE US
JIANGYIN HENGYOU
G2.7 CH
HARDWARE
G2.7 JMD VIRAJ IN
G2.7 KERKAU US
G2.7 KOFCO KR
G2.7 KOREA FLANGE KR
M.G.I (MOIZIEUX-GAUCHON
G2.7 FR
INDUSTRIE)
G2.7 MAASS FLANGE US
G2.7 MAASS MX
G2.7 MARDALE UK
G2.7 METALFAR IT
G2.7 NEWMANS
G2.7 OFFICINE AMBROGIO MELESI IT
G2.7 OFFICINE SANTAFEDED SRI
G2.7 SPECIAL FLANGE SERVICES UK
TEXAS METAL WORKS
G2.7 US
(AMERIFORGE)
TUBELINE (CORE PIPE)
G2.7 US
(STAINLESS ONLY)
G2.7 VIRAJ (STAINLESS ONLY) IN
W. GELDBACH PIPING
G2.7 DE
EQUIPMENT
G2.7 WAFFENSCHMIDT DE
G2.7 WEIR MATERIALS LIMITED UK
G2 7
G2.7 WELDING UNITS UK
G2.7 WESTBROOK US
G2.7 WESTERN FORGE & FLANGE US
WFI (BONNEY FORGE)
G2.7 US
(SPECIALS ONLY)
G2.7 WUXI HUAAN FLANGES CH
G2.7 ZAPP DE
ZHANGJIAGANG SANLIN
G2.7 CH
FLANGE
2 G2.8 FLANGES, DUPLEX - WELD NECK B AMERIFORGE 2 2
G2.8 BO & AKE EDBERGS SW
G2.8 CARLSON
CORE PRODUCTS (GERLINE
G2.8 US
TUBE-LINE)
CORRISION MATERIALS
G2.8 US
(HASTELLOY GRADES)
F.A.D. (FLANGE ACCIANO &
G2.8 IT
DERIVATI SPA)
G2.8 FLANSCHENWERK BEBITZ DE
G2.8 FRIULANA FLANGE IT
GALPERTI GROUP (NOT
G2.8 US
GALPERTI S.R.L.)
G2.8 GELBACH
G2.8 GIBSON
HAYNES INTERNATIONAL
G2.8 US
(HASTELLOY GRADES)
G2.8 J & J MACHINE US
JIANGYIN HENGYOU
G2.8 CH
HARDWARE
G2.8 JMD VIRAJ IN
G2.8
G2 8 KERKAU US
G2.8 KOFCO KR
G2.8 KOREA FLANGE CO. LTD. KR
M.G.I (MOIZIEUX-GAUCHON
G2.8 FR
INDUSTRIE)
G2.8 MAASS FLANGE US
G2.8 MAASS MX
G2.8 MARDALE UK
G2.8 METALFAR IT
G2.8 NEWMANS
G2.8 OFFICINE AMBROGIO MELESI IT
G2.8 OFFICINE SANTAFEDED SRI
G2.8 SPECIAL FLANGE SERVICES UK
TEXAS METAL WORKS
G2.8 US
(AMERIFORGE)
TUBELINE (CORE PIPE)
G2.8 US
(STAINLESS ONLY)
G2.8 VIRAJ (STAINLESS ONLY) IN
W. GELDBACH PIPING
G2.8 DE
EQUIPMENT

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
G2.8 WAFFENSCHMIDT DE
G2.8 WEIR MATERIALS LIMITED UK
G2.8 WELDING UNITS UK
G2.8 WESTBROOK US
G2.8 WESTERN FORGE & FLANGE US
WFI (BONNEY FORGE)
G2.8 US
(SPECIALS ONLY)
G2.8 WUXI HUAAN FLANGES CH
G2.8 ZAPP DE
ZHANGJIAGANG SANLIN
G2.8 CH
FLANGE
2 G2.9 FLANGES, NI / NI ALLOY SW, THRD AND LAP JOINT B BO & AKE EDBERGS 2 2
G2.9 CARLSON
CORRISION MATERIALS
G2.9 US
(HASTELLOY GRADES)
G2.9 FLANSCHENWERK BEBITZ DE
GALPERTI GROUP (NOT
G2.9 US
GALPERTI S.R.L.)
G2.9 GELBACH
G2.9 GIBSON
HAYNES INTERNATIONAL
G2.9 US
(HASTELLOY GRADES)
G2.9 J & J MACHINE US
JIANGYIN HENGYOU
G2.9 CH
HARDWARE
G2.9 KERKAU US
G2.9 KOFCO KR
G2.9 MAASS FLANGE US
G2.9 METALFAR IT
G2.9 NEWMANS
TEXAS METAL WORKS
G2.9 US
(AMERIFORGE)
TUBELINE (CORE PIPE)
G2.9 US
(STAINLESS ONLY)
G2.9 VIRAJ (STAINLESS ONLY) IN
W. GELDBACH PIPING
G2.9 DE
EQUIPMENT
G2.9 WAFFENSCHMIDT DE
G2.9 WESTBROOK US
G2.9 WESTERN FORGE & FLANGE US
WFI (BONNEY FORGE)
G2.9 US
(SPECIALS ONLY)
G2.9 WUXI HUAAN FLANGES CH
G2.9 ZAPP DE
ZHANGJIAGANG SANLIN
G2.9 CH
FLANGE
2 G2.10 FLANGES, NI / NI ALLOY - WELD NECK B CARLSON 2 2
CORRISION MATERIALS
G2.10 US
(HASTELLOY GRADES)
FLANSCHENWERK BEBITZ
G2.10 DE
GMBH
GALPERTI GROUP ((NOT
G2 10
G2.10 US
GALPERTI S.R.L.)
G2.10 GELBACH
G2.10 GIBSON
HAYNES INTERNATIONAL
G2.10 US
(HASTELLOY GRADES)
G2.10 J & J MACHINE US
G2.10 KERKAU US
G2.10 KOFCO KR
G2.10 MAASS FLANGE US
G2.10 METALFAR IT
G2.10 NEWMANS
TEXAS METAL WORKS
G2.10 US
(AMERIFORGE)
TUBELINE (CORE PIPE)
G2.10 US
(STAINLESS ONLY)
G2.10 VIRAJ (STAINLESS ONLY) IN
G2.10 WESTBROOK US
G2.10 WESTERN FORGE & FLANGE US
WFI (BONNEY FORGE)
G2.10 US
(SPECIALS ONLY)
2 G2.11 FLANGES, TITANIUM - SW, THRD AND LAP JOINT B ATI 2 2
EZ-FLOW - BUTTWELD
G2.11
FITTINGS
G2.11 FLOMAC
FORMWELD - BUTTWELL
G2.11
FITTINGS
G2.11 GALPERTI GROUP US
G2.11 GALPERTI GROUP IT
G2.11 MACH
G2.11 PENN
G2.11 PRECISION METAL SPIN

G2.11 TICO TITANIUM INC OF TEXAS

G2.11 TIFAB
G2.11 TIMET
G2.11 TRICOR US
G2.11 UNITI
G2.11 WESTERN FORGE US
G2.11 WFI
2 G2.12 FLANGES, TITANIUM - WELD NECK B ATI 1 2
EZ-FLOW - BUTTWELD
G2.12
FITTINGS
G2.12 FLOMAC
FORMWELD - BUTTWELL
G2.12
FITTINGS
G2.12 GALPERTI GROUP US
G2.12 GALPERTI GROUP IT
G2.12 MACH

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Fittings and Flanges

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Special
Classification
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Transportatio Estimated Estmated Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Location Negotiator Time Level Special Considerations
CODE Suffix Design US$ Strategy Level Level n Total Weight Total Volume Inquiry Date Date Date Time (weeks) Time (weeks)
E= Equipment
Requirements
G2.12 PENN
G2.12 PRECISION METAL SPIN
G2.12 TICO TITANIUM INC OF TEXAS
G2.12 TIFAB
G2.12 TIMET
G2.12 TRICOR US
G2.12 UNITI
G2.12 WESTERN FORGE US
G2.12 WFI
2 G2.13 FLANGES, POLYETHYLENE B 2 2

2 G2.14 FLANGES, CPVC B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE SPEARS MANUFACTURING 2 0

2 G2.15 FLANGES, HDPE B 2 2

2 G2.16 FLANGES, PVC B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE SPEARS MANUFACTURING 2 0

2 G2.17 FLANGES, PFA B 2 0

2 G3.0 BRANCH OUTLETS


BASSI LUIGI S.P.A. (SAN ROCA Standardization -
4 G3 1
G3.1 BRANCH OUTLETS - METALLIC - ALL MATERIALS B IT 1 0
AL PORTO) Category A
G3.1 BONNEY FORGE (MT. UNION) US

G3.1 DELCORTE SA (MAUBEUGE) FR


I.M.L. INDUSTRIA MECCANICA
G3.1 IT
(CASARZA LIGURE)
LINVIC ENGINEERING
G3.1 GB
(WOLVERHAMPTON)
MEGA SPA
G3.1 IT
(SCANZOROSCIATE)
MERWEDE VALVES BV
G3.1 NL
(HARDINZVELD-GIESSENDAM)
PENNSYLVANIA MACHINE
G3.1 US
WORKS (ASTON, PA)
PETROL RACCORD SPA
G3.1 IT
(CASTELLANZA)
G3.1 PIANA SPA (STRADELLA) IT
G3.1 PROMAT BD LTD (WALSAL) GB
W F I INTERNATIONAL
G3.1 US
(HOUSTON,TX)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Fittings Flanges) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Specialty

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE E= Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
Requirements
Equipment
2 H 1.0 SUPPORTS
Standardization -
2 H1.1 SUPPORTS, MODULAR SUPPORTS B HALFEN GMBH & CO KG 2 0
Category C
PIPING TECHNOLOGY &
2 H1.1
PRODUCTS
H1.2 SUPPORTS, INSULATED SUPPORTS - HOT B PIPE SHIELDS 2 0
H1.3 SUPPORTS, ROLLER SUPPORTS B NOT A TECHNOLOGY DRIVEN SINGLE SOURCE HILMAN ROLLERS 2 1
H2.0 GASKETS
AL-IMAN FACTORIES Standardization -
H2.1 GASKETS, FOR FLANGE - KAMMPROFILE / GROOVED B 1 0
ESTABLISHMENT (SA) Category C
H2.1 FLEXITALLIC
H2.1 GULF GASKET FACTORY (SA)

H2.1 JAMES WALKER & COMPANY


LAMONS METAL GASKET
H2.1
COMPANY
AL-IMAN FACTORIES Standardization -
H2.2 GASKETS, FOR FLANGE - SPIRAL WOUND B 1 0
ESTABLISHMENT (SA) Category C
DELMON INDUSTRIAL and
H2.2
MECHANICAL (SA)
H2.2 FLEXITALLIC

H2.2 GULF GASKET FACTORY (SA)

H2.2 SAUDI GASKET FACTORY (SA)

H2.2 LAMONS METAL GASKET


AL-IMAN FACTORIES Standardization -
H2.3 GASKETS, SOLID METAL, RING TYPE B 1 0
ESTABLISHMENT (SA) Category C
AMIANTIT RUBBER
H2.3
INDUSTRIES
H2.3 FLEXITALLIC
H2.3 GULF GASKET FACTORY (SA)
H2.3 LAMONS METAL GASKET
Standardization -
H2.4 GASKETS, GASKET KIT; INSULATING; WASHERS, SLEEVES B FLEXITALLIC 1 0
Category C
H2.4 LAMONS METAL GASKET
H2.4 PIKOTEK
GASKETS, SHEET MAT'L (RUBBER, POLYMERIC, GRAPHITE, AL-IMAN FACTORIES Standardization -
H2.5 B 1 0
ETC.) ESTABLISHMENT (SA) Category C
AMIANTIT RUBBER
H2.5
INDUSTRIES
DELMON INDUSTRIAL and
H2.5
MECHANICAL (SA)
H2.5 FLEXITALLIC
H2.5 GULF GASKET FACTORY (SA)

H2.5 JAMES WALKER & COMPANY


H2.5 LAMONS METAL GASKET
H2.5 SAUDI GASKET FACTORY (SA)
( )
H3.0 STEAM TRAPS
Standardization -
H3.1 STEAM TRAPS B ARMSTRONG INTERNATIONAL 1 1
Category C
H3.1 FLOWSERVE (GESTRA)
H3.1 GESTRA AG
H3.1 SPIRAX SARCO
H4.0 SMALL INLINE FILTER - Y TYPE
Standardization -
H4.1 SMALL INLINE FILTER - Y TYPE B SPIRAX SARCO 1 0
Category C
2 H5.0 STRAINERS
Standardization -
H5.1 STRAINERS, FABRICATED B FILTER FAB 1 1
Category C
H5.1 HAYWARD STRAINERS
H5.1 MACK IRON WORKS
H5.1 PLENTY
Standardization -
H5.2 STRAINERS, SMALL INLINE FILTER - BSKT TP B HAYWARD STRAINERS 1 1
Category C
H5.2 PLENTY
Standardization -
2 H5.3 STRAINERS, STARTUP B FILTER FAB 1 0
Category C
H5.3 HAYWARD STRAINERS
H5.3 MACK IRON WORKS
2 H6.0 EXPANSION JOINTS
2 H6.1 EXPANSION JOINTS, METAL B FLEXIDER SRL 2 2
H6.1 HANWEL EUROPE
HYSPAN PRECISION
H6.1
PRODUCTS
H6.1 JAMES WALKER TOWNSON
H6.1 OFFICINE A. MELESI AND CO
H6.1 SENIOR FLEXONICS
H6.1 SUNGJIN GEOTEC
H6.1 SWECO FAB
H6.1 WITZENMANN GMBH
GARLOCK SEALING
2 H6.2 EXPANSION JOINTS, RUBBER B 2 2
TECHNOLOGIES
H6.2 GENERAL RUBBER
H6.2 PROCO
2 H6.3 EXPANSION JOINTS, SLEEVE B COLTEC 2 2
GARLOCK SEALING
H6.3
TECHNOLOGIES
2 H7.0 TUBING
2 H7.1 TUBINE, PROCESS TUBE - FITTINGS B HOKE 1 0
H7.1 SWAGELOCK
2 H7.2 TUBING, METALLIC; ALL SIZES; ALL MATERIAL B ACCLES AND POLLOCK 1 0
H7.2 BRISTOL METALS

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Specialty) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Specialty

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE E= Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
Requirements
Equipment
H7.2 BUTTING
CAMDEL METALS DIV./HANDY
H7.2
& HARMAN
H7.2 CARTECH
H7.2 DMV
H7.2 GEA RAINEY
H7.2 GREENVILLE
H7.2 HANDY & HARMAN
H7.2 HAYNES
H7.2 IPSCO (KOPPEL STEEL)
H7.2 JFE STEEL CORPORATION
H7.2 KAINAN WORKS
H7.2 KANZEN TETSU SDN BHD
H7.2 KOBE SPECIAL TUBE
KUBOTA CORPORTATION
H7.2
OSAKA PLANT
H7.2 LAKESIDE STEEL
H7.2 MACH
H7.2 MANNESMANN DMV
H7.2 MANNESMANN DMV
H7.2 MARCEGAGLIA

H7.2 METALTEK INTERNATIONAL


H7.2 MITSUBISHI
H7.2 NANTONG SPECIAL STEEL
H7.2 NIPPON
H7.2 NKK TUBES KEIHIN WORKS
H7.2 OUTOKUMPU
OUTOKUMPU STAINLESS
H7.2
TUBULAR PRODUCT
H7.2 PEXCO
H7.2 PROFINS
H7.2 RATH GIBSON (GIBSON TUBE)
H7.2 ROCKWELL COLLINS
H7.2 SALEM
SALZGITTER MANNESMANN
H7.2
STAINLESS TUBES
H7.2 SANDVIK
H7.2 SCHMIDT-CLEMENS
H7.2 SCHOELLER-BLECKMANN
H7.2 SHARON TUBE
H7.2 SHINKO METAL PRODUCTS
H7.2 SMC
H7.2 STAINLESS KUZE
H7.2 SUMIKIN STAINLESS TUBE
H7.2 SUMITOMO
H7.2 SWEPCO
H7.2 TANARIS
TIANJIN PIPE COMPANY
H7.2
(TPCO)
H7.2 TITANIUM FABRICATION
TPS TECHNITUBE
H7.2
ROEHRWERKE
H7.2 TRENT
H7.2 TUBACEX
H7.2 TUBOS REUNIDOS S.A.
H7.2 U.S. STEEL
H7.2 V&M (MANNESMANN)
H7.2 V&M (VALLOUREC)
H7.2 V&M STAR
H7.2 VDM
H7.2 VOEST-ALPINE
H7.2 WEBCO INDUSTRIES
H8.0 FASTENERS
AL-RASHED FASTENERS AND
4 H8.1 FASTENERS B 1 0
ENGINEERING (SA)
AL-RASHID FASTENERS AND
4 H8.1
ENGINEERING (SA)
ARABIAN FASTENERS AND
4 H8.1
ENGINEERING (SA)
H8.1 BECK CRESPEL
EUROFAST
H8.1
PETROCHEMICALS SUPPLY
H8.1 LAMONS GASKET
O.M.E. METALLURGICA
H8.1
ERBESES
H8.1 PROSPER ENGINEERING
H8.1 QUALITY BOLT & SCREW
H8.1 ROLLSTUD
SAUDI BEA FASTENERS
4 H8.1
MANUFACTURING (SA)
AL-RASHED FASTENERS AND
4 H8.2 FLUROPOLYMER COATED FASTENERS B 1 0
ENGINEERING (SA)
AL-RASHID FASTENERS AND
4 H8.2
ENGINEERING (SA)
ARABIAN FASTENERS AND
4 H8.2
ENGINEERING (SA)
4 H8.2 BEA SRL
4 H8.2 LONE STAR FASTENERS, LP
4 H8.2 OME
TAKENAKA SEISAKUSHO CO
4 H8.2
LTD
TRIPLEFAST MIDDLE EAST
4 H8.2
LTD
H9.0 PLASTIC LINED PIPE
H9.1 LINERS, PLASTIC - PTFE, PVDF, PP B SEE PIPE AVL 2 0

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Specialty) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Pipe Specialty

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE E= Suffix US$ Strategy Level Level Weight Volume Inquiry Date Date Date Time (weeks) Time (weeks)
Requirements
Equipment

H9.2 LINERS, HDPE - SLIP LINE B UNITED PIPELINE SYSTEMS 2 0

2 H10.0 SPRING HANGERS


Standardization -
2 H10.1 SPRING HANGERS B AMBER/BOOTH 1 1
Category C
H10.1 LISEGA AG
PIPING TECHNOLOGY &
H10.1
PRODUCTS
H11.0 DEVICES
H11.1 DEVICES, BACK FLOW PREVENTION B CONBRACO INDUSTRIES 1 0
H11.1 FEBCO
H11.1 WATTS
H11.2 DEVICES, RELIEF - LOW PRESSURE API B GROTH 1 0
J. KOCH ASSOCIATES
H11.2
(TORNADO)
L & G TECHNOLOGIES
H11.2
(SHAND & JURS)
H11.2 PROTECTOSEAL
PROTEGO
H11.2 (BRAUNSCHWEIGER
FLAMMENFILTER)
H11 2
H11.2 SHAND & JURS
H11.2 TORNADO
H11.2 VAREC
H11.2 WHESSOE VAREC
3 H12.0 DISCS - MOVED TO INSTRUMENTATION
3 H12.1 DISCS, RUPTURE - GRAPHITE
3 H12.2 DISCS, RUPTURE - METAL
2 H13.0 FLAME ARRESTORS
BRAUNSCHWEIGER
2 H13.1 FLAME ARRESTORS, METAL B 1 0
FLAMMENFILTER (PROTEGO)
H13.1 GROTH
H13.1 PROTECTOSEAL
H13.1 WESTECH
2 H14.0 SPOOL, PIPE
2 H14.1 SPOOL, PIPE JOINT INSULATING B RMA KEHL GMBH & CO 1 0
H14.1 T.D. WILLIAMSON
H15.0 FLANGE, PIPE
H15.1 FLANGE, PIPE, SPECTACLE PLATE; ANY STEEL B BD PROFILES 1 0
H15.1 BRUCK GMBH ENSHEIM
H15.1 CRANE MANUFACTURING
H15.1 INMA STEEL FABRICATORS
H15.1 LINVIC ENGINEERING
MARITIME INDUSTRIAL
H15.1
SERVICES
METALFAR PRODOTTI
H15.1
INDUSTRIALI SPA
H15.1 OFFICINE A. MELESI AND CO
OFFICINE NICOLA GALPERTI &
H15.1
FIGLIO
SAUDI ARABIAN FABRICATED
H15.1
METALS
4 H16.0 SCRAPER TRAPS
PIPELINE SCRAPER TRAPS TO ASME B3.4/B31.B (INLET GLAPWELL CONTRACTING
4 H16.1 B 1 0
AREA ONLY) SERVICES
4 H16.1 FAI CARVICO
PIPELINE ENGINEERING
4 H16.1
SERVICES
4 H17.0 DISMANTLING JOINTS
4 H17.1 DISMANTLING JOINTS B KLAMFLEX PIPE COUPLINGS 1 0
4 H17.1 VIKING JOHNSON

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Pipe Specialty) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Piping Valves

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

2.0 I 1.0 PIPING VALVES


3 I1.1 PIPING VALVES, ANGLE B FRICK 2 2
HANSEN TECHNOLOGIES
I1.1
CORPORATION
I1.1 HENRY (HERL)
Standardization -
Category A,
4 I1.2 PIPING VALVES, BALL B ATOMAC (FLOWSERVE) Automac is 1 of 4 2 2
selected PLA
Vendors
Standardization -
Category A, BAC is
4 I1.2 BAC
1 of 4 selected PLA
Vendors
I1.2 CHEMTROL
I1.2 COOPER
I1.2 DRESSER NIL-COR
I1.2 GEORGE FISCHER
I1.2 HOKE
I1.2 ITT
I1.2 JC/TL
I1.2 KF CONTRA
I1.2 KITZ
I1.2 KROMBACH
Standardization -
4 I1.2 KTM Category A, KTM is
1 of 4 selected PLA
Vendors
I1.2 MCCANNA (FLOWSERVE)
I1.2 METSO N-J
I1.2 MOGAS
NIBCO (WATCH ZINC
I1.2
CONTENT)
I1.2 ORBIT (CAMERON)
I1.2 SAWGELOK-WHITEY
I1.2 TBV
TUFLINE/XOMOX
I1.2
INTERNATIONAL GMBH
I1.2 VALVTECH
I1.2 VALVTRON
I1.2 VELAN
I1.2 WKM (CAMERON)
Standardization -
WORCESTER Category A, PLA
4 I1.2
(FLOWSERVE) pending with
Worcester
Standardization -
4 I1.3 PIPING VALVES, BUTTERFLY B ADAMS 2 2
Category A
I1.3 AMRI
I1.3 BRAY (API 609 ONLY)
I1.3 DEMCO
Standardization -
4 I1.3 DEZURIK Category A, Dezurik
is 1 of 3 selected
PLA Vendors
I1.3 DRESSER NIL-COR
I1.3 DURCO
I1.3 FMC (WECO)
I1.3 GARLOCK
I1.3 GRINNELL (TYCO)
I1.3 KEYSTONE (TYCO)
I1.3 MOSITES
NELES-JAMESBURY
I1.3
(METSO AUTOMATION)
Standardization -
Category A,
4 I1.3 NEOTECHA (TYCO) Neotecha is 1 of 3
selected PLA
Vendors
NORRIS (NORRISEAL
I1.3 CONTROLS/ DOVER) (API
609 ONLY)
I1.3 ORTON SRL
I1.3 PRATT
Standardization -
Category A,
4 I1.3 VANESSA (TYCO) Vanessa is 1 of 3
selected PLA
Vendors
I1.3 VELAN
I1.3 XOMOX
I1.3
I1 3 ZWICK GMBH & CO
Standardization -
4 I1.4 PIPING VALVES, CHECK B ATOMAC 2 2
Category A
ADAMS ARAMATUREN
I1.4
GMBH
I1.4 AUTOCLAVE ENGINEERS
I1.4 BFE SPA
I1.4 BONNEY FORGE
I1.4 CHECK-ALL
I1.4 CHEMTROL
I1.4 COOPER
I1.4 CRANE RESISTOFLEX
DANIEL (M&J VALVE
I1.4
OPERATIONS)
I1.4 DOUGLAS CHERO
DRESSER AL-RUSHAID
I1.4
VALVE AND
I1.4 DSI
I1.4 DUO-CHECK

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Piping Valves) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Piping Valves

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

I1.4 EDLON-PSI
I1.4 EDWARD (FLOWSERVE)
I1.4 GEORGE FISCHER
I1.4 GESTRA AG (FLOWSERVE)
I1.4 GOODWIN INT
I1.4 GULF
I1.4 HOKE / CIRCOR
Standardization -
INDUSTRIAL VALVES Category A, IVM-
4 I1.4 OMB is 1 of 3 2 inch & Smaller, Forged
MANUFACTURER
selected PLA
Vendors
I1.4 KITZ
I1.4 LADISH
LARSEN & TOUBRO
I1.4
(AUDCO INDIA LIMITED)

Standardization -
NEWAY (ABAHSAIN NEWAY
4 I1.4 Category A, PLA 2 inch & Smaller, Forged
INDUSTRIAL)
pending with Neway

I1.4 NEWCO
NIBCO (WATCH ZINC
I1.4 CONTECT IN BRONZE
VALVES)
I1.4 OMB
I1.4 PROQUIP (VELAN)
I1.4 SWAGELOK-NUPRO

Standardization -
Category A, SWI is
4 I1.4 SWI 2 inch & Smaller, Forged
1 of 3 selected PLA
Vendors

I1.4 TOM WHEATLEY


I1.4 TUFLINE
I1.4 TY VALVE
I1.4 VELAN
I1.4 VOGT (FLOWSERVE)
3 I1.5 PIPING VALVES, DIAPHRAGM B ITT 2 1
I1.5 MCCANNA
2 I1.6 NOT USED
AMERICAN FLOW Standardization -
4 I1.7 PIPING VALVES, GATE B 2 2
CONTROL Category A
I1.7 AVK INTERNATIONAL
I1.7 BFE SPA
I1.7 BONNEY FORGE
I1.7 COOPER
DANIEL (M&J VALVE
I1.7
OPERATIONS)
I1.7 DESCOTE
I1.7 DOUGLAS CHERO
I1.7 DRESSER
I1.7 DSI
I1.7 EAGLE
I1.7 EDWARD (FLOWSERVE)
I1.7 FAIRBANKS
I1.7 FRICK
I1.7 HANSEN TECH
I1.7 HENRY (HERL)
Standardization -
Category A, IVM-
INDUSTRIAL VALVES
4 I1.7 OMB is 1 of 3 2 inch & Smaller, Forged
MANUFACTURER
selected PLA
Vendors
I1.7 KITZ
I1.7 LADISH
LARSEN & TOUBRO AIL
I1.7
(AUDCO INDIA LIMITED)
I1.7 MERWEDE VALVES BV
I1.7 MUELLER

Standardization -
NEWAY (ABAHSAIN NEWAY
4 I1.7 Category A, PLA 2 inch & Smaller, Forged
INDUSTRIAL)
pending with Neway

I1.7 NEWCO
NIBCO (WATCH CONTENT
I1.7
IN BRONZE VALVES)
I1.7 OMB
I1.7 SHIPHAM VALVES
I1.7
I1 7 SMITH
Standardization -
4 I1.7 SWI Category A, SWI is 2 inch & Smaller, Forged
1 of 3 selected PLA
Vendors
I1.7 TY VALVE
I1.7 VELAN
I1.7 VOGT (FLOWSERVE)
I1.7 WKM
Standardization -
4 I1.8 PIPING VALVES, GLOBE B BFE SPA 2 2
Category A
I1.8 BONNEY FORGE
I1.8 CONVAL
I1.8 COOPER
I1.8 DESCOTE
I1.8 DOUGLAS CHERO
I1.8 DRESSER
I1.8 DSI
I1.8 EAGLE (FLOWSERVE)

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Piping Valves) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Piping Valves

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Classification Special
PAVL Tag Number / Model / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description B= Bulk Item Tag- Type Quantity Material Size Manufacturers Negotiator Transportation Time Level Planned PO Date Field Need Date Special Considerations
CODE Suffix Design US$ Strategy Level Level Weight Volume Date (weeks) Time (weeks)
E= Equipment Requirements

I1.8 EDWARD
I1.8 FRICK
I1.8 HANSEN TECH
I1.8 HENRY (HERL)
I1.8 HP VALVES
Standardization -
INDUSTRIAL VALVES Category A, IVM-
4 I1.8 OMB is 1 of 3 2 inch & Smaller, Forged
MANUFACTURER
selected PLA
Vendors
I1.8 KITZ
I1.8 LADISH
LARSEN & TOUBRO AIL
I1.8
(AUDCO INDIA LIMITED)
I1.8 MERWEDE VALVES BV

Standardization -
NEWAY (ABAHSAIN NEWAY
4 I1.8 Category A, PLA 2 inch & Smaller, Forged
INDUSTRIAL)
pending with Neway

I1.8 NEWCO
NIBCO (WATCH CONTENT
I1.8
IN BRONZE VALVES)
I1.8 OMB
I1.8 PHONIX
I1.8 RAIMONDI
I1.8 SHIPHAM VALVES

Standardization -
Category A, SWI is
4 I1.8 SWI 2 inch & Smaller, Forged
1 of 3 selected PLA
Vendors

I1.8 VELAN
I1.8 VOGT
I1.8 VOGT (FLOWSERVE)
ANDERSON GREENWOOD
3 I1.9 PIPING VALVES, NEEDLE B 2 0
& COMPANY
AUTOCLAVE ENGINEERS
I1.9
INCORPORATED
I1.9 HOKE
KEROTEST
I1.9
MANUFACTURING
I1.9 MERWEDE VALVES BV
I1.9 OLIVER VALVES LTD
I1.9 PARKER-HANNIFIN
I1.9 SWAGELOK-WHITEY
ANDERSON GREENWOOD
3 I1.10 PIPING VALVES, INSTRUMENT B 2 0
& COMPANY
AUTOCLAVE ENGINEERS
I1.10
INCORPORATED
I1.10 HOKE
KEROTEST
I1.10
MANUFACTURING
I1.10 MERWEDE VALVES BV
I1.10 OLIVER VALVES LTD
I1.10 PARKER-HANNIFIN
I1.10 SWAGELOK-WHITEY
3 I1.11 PIPING VALVES, KNIFEGATE B FABRI-VALVE 2 2
I1.11 VELAN
COOPER CAMERON / Standardization -
4 I1.12 PIPING VALVES, PLUG B 2 2
ORBIT VALVE Category A
I1.12 DURCO (FLOWSERVE)
4 I1.12 FLUROSEAL
I1.12 GALLI E CASSINA SPA
I1.12 GENERAL VALVE
Standardization -
NORDSTROM Category A, PLA
4 I1.12
(FLOWSERVE) pending with
Nordstrom
SERCK AUDCO VALVES
I1.12
(FLOWSERVE)
I1.12 TUFLINE (XOMOX)
2 I1.13 NOT USED
Dow will add the complete
PIPING VALVES, RAIL ROAD APPLICATIONS - SAMPLING -
2 I1.14 B spring operated relief valve list 2 2
RAM / PISTON
to this spreadsheet.
2 I1.15 NOT USED
2 I1.16 NOT USED
2 I1.17 NOT USED

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Piping Valves) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Fire Protection Equipment

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Classification Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Date Date Date Time (weeks) Time (weeks)
Requirements

J1.0 FIRE PROTECTION EQUIPMENT


Standardization -
KENNEDY (TYPE K-81A OR Category A, REDA
4 J1.1 HYDRANTS- 6" DRY BARREL B 1 0
EQUIVALENT) is the selected PLA
Vendor (Distributor)
MUELLER SUPER CENTURION
J1.1
SPL
J1.1 AVK
J1.1 JAMES JONES

Standardization -
Category A, REDA
4 J1.2 MONITORS B ELKHART 1 0
is the selected PLA
Vendor (Distributor)

Standardization -
J1.3 HOSE REELS B REDA (SA) 1 1
Category B
J1.3 SFFECO (SA)
J1.3 SHUWAYER (SA)
Standardization -
J1.4 HOSE CABINETS (UL/FM APPROVED UNITS) B REDA (SA) 1 1
Category B
J1 4
J1.4 SFFECO (SA)
J1.4 SHUWAYER (SA)
J2.0 SAFETY EQUIPMENT
ANSUL (CO2, I-K-30-G DRY Standardization -
J2.1 PORTABLE FIRE EXTINGUISHERS B 1 0
CHEM) Category B
Standardization -
J2.2 WHEELED EXTINGUISHERS B ANSUL 31009 1 0
Category B
Standardization -
J2.3 BREATHING AIR DEVICES (SA) B SCOTT 1 0
Category B

Standardization -
SAFETY SHOWER / EYEWASH UNITS IN COMPLIANCE WITH Category A, REDA
J2.4 B ENCON SAFETY PRODUCTS 1 0
(ANSI Z358.1) is the selected PLA
Vendor (Distributor)

J2.4 HAWS
J3.0 WATER SPRAY / DELUGE
Standardization -
J3.1 DELUGE VALVES B INBAL DELUGE VALVE 1 0
Category B
J3.1 TYCO
J3.1 VIKING
Standardization -
J3.2 SPRAY NOZZLES B GRINNEL 1 0
Category B
J3.2 TYCO
J3.2 VIKING
Standardization -
J3.3 FUSIBLE PLUGS B GRINNEL 1 0
Category B
J3.3 TYCO
J3.3 VIKING
Standardization -
J3.4 FUSIBLE PLUG CONTROL PANELS B GRINNEL 1 1
Category B
J3.4 TYCO
A. O. SMITH WATER Standardization -
J3.5 BASKET STRAINERS B 1 0
PRODUCTS Category B
J3.5 TYCO
J4.0 FIXED FIRE SYSTEMS
Standardization -
J4.1 DRY CHEMICAL B ANSUL 1 0
Category B
Standardization -
J4.2 FOAM SYSTEMS B ANSUL (AFFF-AR 1-3%) 1 1
Category B
J4.2 WILLIAMS
Standardization -
J4.3 FOAM LIQUID B ANSUL 1 0
Category B
J4.3 SOLBERG
J4.3 WILLIAMS
Standardization -
J4.4 CO2 SYSTEMS B TYCO 1 0
Category B
Standardization -
J4.5 CLEAN AGENT B FM-200 1 0
Category B
J4.5 INERGEN
J4.5 NOVEC 1230
J4.5 TYCO
Standardization -
J4.6 BUILDING SPRINKLER SYSTEMS B TYCO 1 0
Category B
J4.7 WATER SPRAY SYSTEMS B TYCO 1 0
Standardization -
J4.8 FOAM STORAGE TANKS (BLADDER) B ANSUL 1 0
Category B
J4.8 SKUM TYPE MTB
J4.8 WILLIAMS
Standardization -
J4.9 WIDE RANGE PROPORTIONERS B ANSUL 1 0
Category B
J4.9
J4 9 SKUM TYPE TPW
J4.9 WILLIAMS
Standardization -
J4.10 COUPLINGS / FITTINGS B GRINNEL 1 0
Category B
Standardization -
J4.11 CONTROL & STOP VALVES B GRINNEL 1 0
Category B
Standardization -
J4.12 PRESSURE SWITCHES B STATIC-O-RING 1 0
Category B
2 J5.0 FIRE PUMPS
Standardization -
2 J5.1 HORIZONTAL FIRE PUMPS B AURORA PUMP 2 1
Category B
J5.1 ITT GOULDS
J5.1 NIJHUIS
2 J5.1 PEERLESS PUMPS
2 J5.1 SAUDI PUMP COMPNAY
Standardization -
2 J5.2 VERTICAL FIRE PUMPS B AURORA PUMP 2 1
Category B
J5.2 ITT GOULDS
J5.2 NIJHUIS
2 J5.2 PEERLESS PUMPS

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Fire Protection Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Fire Protection Equipment

Special
PAVL Tag Number / Estimate 1000 Purchasing Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Field Need Dwg Lead Delivery Lead
Pkg. No. Revision Equipment Description Classification Tag- Type Quantity Material Size Model / Design Manufacturers Negotiator Transportation Time Level Special Considerations
CODE Suffix US$ Strategy Level Level Weight Volume Date Date Date Time (weeks) Time (weeks)
Requirements

2 J5.2 SAUDI PUMP COMPNAY


Standardization -
2 J5.3 JOCKEY PUMPS B AURORA PUMP 2 1
Category B
J5.3 ITT GOULDS
J5.3 NIJHUIS
2 J5.3 PEERLESS PUMPS
2 J5.3 SAUDI PUMP COMPNAY
J6.0 POST INDICATORS
Standardization -
Category A, REDA
4 J6.1 POST INDICATING VALVES B AMERICAN FLOW CONTROL 1 0
is the selected PLA
Vendor (Distributor)
J6.1 AVK
J6.1 BRAY
J6.1 MULLER
J6.1 NEWMANS
J6.1 PRATT
J7.0 GAS & FLAME DETECTION
3 J7.1 GAS DETECTORS Moved to Analytical PAVL Code A1.2
Standardization -
J7.2 FLAME DETECTORS B DETRONICS 1 0
Category B
J7.2 DRAEGER
J7.2 GENERAL MONITORS
J8.0 FIRE DETECTION & NOTIFICATION
Standardization -
J8.1 SMOKE DETECTORS B EST 1 0
Category B
J8.1 HONEYWELL
J8.1 SIEMENS
J8.1 TYCO
J8.1 NOTIFIER (HONEYWELL)
Standardization -
J8.2 HEAT DETECTORS B EST 1 0
Category B
J8.2 HONEYWELL
J8.2 NOTIFIER (HONEYWELL)
J8.2 SIEMENS
J8.2 TYCO
Standardization -
J8.3 MANUAL ALARM CALL POINTS B EST 1 0
Category B
J8.3 HONEYWELL
J8.3 NOTIFIER (HONEYWELL)
J8.3 SIEMENS
J8.3 TYCO
Standardization -
J8.4 VISUAL NOTIFICATION DEVICES B EST 1 0
Category B
J8.4 HONEYWELL
J8.4 NOTIFIER (HONEYWELL)
J8.4 SIEMENS
J8.4 TYCO
Standardization -
J8.5 AUDIBLE NOTIFICATION DEVICES B HONEYWELL 1 0
Category B
J8.5 SIEMENS
Standardization -
J8.6 ADDRESSABLE FIRE ALARM SYSTEMS B EST 1 0
Category B
J8.6
J8 6 HONEYWELL
J8.6 NOTIFIER (HONEYWELL)
J8.6 SIEMENS
J8.6 TYCO
Standardization -
J8.7 FIRE & SECURITY SYSTEMS B GE SECURITY 1 0
Category B
J8.7 NOTIFIER (HONEYWELL)
J8.7 SIEMENS
4 J9.0 FIRE PROTECTION SYSTEMS INTEGRATOR
4 J9.1 FIRE PROTECTION SYSTEMS INTEGRATOR B REDA FIRE (SA) 1 0
SAUDI FACTORY FOR FIRE
4 J9.1
EQUIPMENT
TYCO FIRE & INTEGRATED
4 J9.1
SOLUTIONS
WILLIAMS FIRE & HAZARD
4 J9.1
CONTROL

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Fire Protection Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Structural Steel

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE

Special
PAVL Tag Number Model / Estimate Expediting Inspection Estimated Total Estmated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead Special
Pkg. No. Revision Equipment Description Classification Tag- Type Quantity Material Size Manufacturers Location Purchasing Strategy Negotiator Transportation Time Level Field Need Date
CODE / Suffix Design 1000 US$ Level Level Weight Volume Date Date (weeks) Time (weeks) Considerations
Requirements

2 K1.0 STRUCTURE, STEEL

Standardization -
Category A
(Fabricated Piperack
ABDULLAH AL-HAMOUD AL- DH. AIRPORT,
4 K1.1 STRUCTURE, STEEL B Steel and Raw 2 2
SHUWAYER SA
Materials - Not
Fabricated Steel for
Process Units)

K1.1 AL-ZAMIL FOR HEAVY STEEL JEDDAH, SA

Standardization -
Category A
(Fabricated Piperack
Steel and Raw
JEDDAH,
ARABIAN INTERNATIONAL Materials - Not
4 K1.1 SAUDI
COMPANY FOR Fabricated Steel for
ARABIA
Process Units),
Arabian International is
1 of 2 selected PLA
Vendors

ASIA STEEL FACTORY CO


4 K1.1 THAILAND
LTD.
CLEVELAND BRIDGE AND
2 K1.1 DUBAI, AE
ENGINEERING
2 K1.1 EMIRATES BUILDING SYSTEM DUBAI, AE

Standardization -
Category A
(Fabricated Piperack
Steel and Raw
FACTORY ABDULLA B. AL- Materials - Not
4 K1.1 JUBAIL, SA
KHALIFA Fabricated Steel for
Process Units),
Factory Abdulla is 1
of 2 selected PLA
Vendors
GEYAD FACTORY FOR ALKHOBAR,
K1.1
PRESSURE VESSELS SA
JUBAIL
K1.1 GULF STEEL WORKS INDUSTRIAL
CITY, SA
K1.1 HIDADA COMPANY LIMITED JEDDAH, SA
INTERNATIONAL BUILDING
K1.1 RIYADH, SA
SYSTEM
MARITIME INDUSTRIAL
K1.1 JUBAIL, SA
SERVICES
2 K1.1 MC DERMOTT DUBAI, AE
MOHAMMAD AL-MOJIL GROUP
K1.1 DAMMAM, SA
STEEL
SHANGHAI MATSUO STEEL
2 K1.1 CHINA
STRUCTURE CO. LTD.
2 K1.1 TRINITY USA
UNITED STEEL STRUCTURES
2 K1.1 CHINA
LIMITED
K1.1 YANBU STEEL COMPANY YANBU, SA

K1.1 ZAMIL STEEL INDUSTRIES DAMMAM, SA

2 K2.0 CIVIL, WATERSTOP


Standardization -
Category A,
2 K2.1 WATERSTOP MATERIAL FOR CONCRETE (TPER) GREENSTREAK GROUP INC US Greenstreak Group is
the selected PLA
Vendor

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Structural Steel) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)

Program Supply Plan


Laboratory Equipment (Pending)

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Expediting Inspection Estimated Total Estimated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Purchasing Strategy Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix US$ Level Level Weight Volume Date Date (weeks) Time (weeks)
Requirements
Equipment
L1.0 ANALYZERS

ANALYZERS, BIOLOGICAL OXYGEN DEMAND (BOD) AND


L1.1 B HACH 1 0 SS Justification Rec'd
INCUBATOR

L1.2 ANALYZERS, CHEMICAL OXYGEN DEMAND(COD) B HACH 1 0 SS Justification Rec'd


L1.3 ANALYZERS, COLOR B HUNTERLAB 1 0 SS Justification Rec'd

L1.4 ANALYZERS, COLOR GARDNER B BYK-GARDNER 1 0 SS Justification Rec'd

L1.5 ANALYZERS, DIGESTOR (P, COD) B HACH 1 0


PRECISION SCIENTIFIC
L1.6 ANALYZER, DIGITAL SALT-IN-CRUDE B 1 0
PETROLEUM INSTRUMENTS

L1.7 ANALYZERS, DISSOLVED OXYGEN B HACH 1 0 SS Justification Rec'd

L1.8 ANALYZERS, FLASH POINT B PETROTEST 1 0


L1.8 KOEHLER

L1 9
L1.9 ANALYZERS HEADSPACE
ANALYZERS, B AGILENT 1 0 SS Justification Rec'd
Rec d

L1.10 ANALYZERS, INFRACAL IR PLATFORM B WILKS 1 0

L1.11 ANALYZERS, MOISTURE, LOSS ON DRYING B BRINKMANN-METROHM 1 0


L1.11 METTLER-TOLEDO
L1.12 ANALYZERS, PORTABEL DISSOLVED OXYGEN B FISHER SCIENTIFIC 1 0
L1.12 HACH
L1.12 MARTEK
L1.13 ANALYZERS, PORTABLE OXYGEN B AMATEK 1 0
L1.13 TELEDYNE
L1.14 ANALYZERS, PORTABLE NATURAL GAS MOISTURE B GE PANAMETRICS (SA) 1 0
L1.15 ANALYZERS, RESIDUAL GAS B AC ANALYZER 1 0
GRABNER INSTRUMENTS
L1.16 ANALYZERS, RVP, MINIVAP VPSH B 1 0 SS Justification Rec'd
GmbH
L1.17 ANALYZERS, SAYBOLT COLOR B KOEHLER INSTRUMENT CO. 1 0 SS Justification Rec'd
L1.18 ANALYZERS, THERMO GRAVMETRIC (TGA) B TA INSTRUMENTS 1 0 SS Justification Rec'd
L1.19 ANALYZERS, THERMOMECHANICAL (TMA) B TA INSTRUMENTS 1 0 SS Justification Rec'd
L1.20 NOT USED B

L1.21 ANALYZERS, TOTAL NITROGEN B ANTEK 1 0 SS Justification Rec'd

ANALYZERS, TOTAL ORGANIC CARBON (TOC) and Nitrogen


L1.22 B SHIMADZU TOC-V 1 0 SS Justification Rec'd
modulator
L2.0 BALANCES

L2.1 BALANCES, ANALYTICAL B METTLER TOLEDO 1 0


L2.1 SARTORIUS
L3.0 CHROMATOGRAPHY
L3.1 CHROMATOGRAPHY, GAS B AGILENT 1 0 SS Justification Rec'd

L3.2 CHROMATOGRAPHY, GAS - SPECIAL APPLICATIONS B WASSON ECE 1 0 SS Justification Rec'd

CHROMATOGRAPHY, GAS AND MASS SPECTROMETRY


L3.3 B AGILENT 1 0 SS Justification Rec'd
(GC/MS) - Routine analysis
CHROMATOGRAPHY, GAS AND MASS SPECTROMETRY
L3.4 B FINNIGAN 1 0
(GC/MS) - Problem solving
L3.4 JOEL (SA)
L3.5 NOT USED
L3.5 CHROMATOGRAPH, GEL PERMEATION B AGILENT 1 0 SS Justification Rec'd

L3.6 CHROMATOGRAPH, GEL PERMEATION B AGILENT 1 0 SS Justification Rec'd

L3.7 CHROMATOGRAPHY, ION B DIONEX 0 SS Justification Rec'd

L3.8 CHROMATOGRAPHY, HPLC B AGILENT 1 0 SS Justification Rec'd


CHROMATOGRAPHY, LIQUID AND MASS SPECTROMETRY
L3.9 B AGILENT 1 0 SS Justification Rec'd
(LC/MS)
L4.0 LAB DATA SYSTEMS
L4.1 LAB DATA SYSTEMS (LIT) B AGILENT 1 0
L4.1 ATLAS CDS
L4.1 EZCHROM CDS

L5.0
L5 0 METERS
Equivalent is acceptable
L5.1 METERS, ASTM THERMOMETER B FISHER SCIENTIFIC 1 0
upon Company Approval
METERS, CHLORINE (FREE & TOTAL), POCKET
L5.2 B HACH 1 0 SS Justification Rec'd
COLORIMETER II TEST KIT
METERS, CONDUCTOMER W/MAGNETIC STIRRER AND 5 Equivalent is acceptable
L5.3 B METROHM 1 0
SPARE CONDUCTIVITY ELECTRODE upon Company Approval

L5.4 METERS, DENSITY (GENERAL LIQUIDS) B ANTON PAAR 1 0 SS Justification Rec'd

L5.5 METERS, DENSITY MEASUREMENT FOR PE B TOYOSEIKI 1 0


L5.5 METTLER

L5.6 METERS, DIFFERENTIAL SCANNING CALORIMETER, (DSC) B TA INSTRUMENTS 1 0 SS Justification Rec'd

Equivalent is acceptable
L5.7 METERS, DS CONDUCTIVITY B MYRON L 1 0
upon Company Approval
Standardization -
L5.8 METERS, pH B BRINKMANN 1 0
Category B
L5.8 DENVER INSTRUMENTS

Doc. No. A554-K-PRG-PU-LIS-DOC-009 Date: 29 July 2011


(Laboratory Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Ras Tanura Integrated Project (RTIP)

Program Supply Plan


Laboratory Equipment (Pending)

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Expediting Inspection Estimated Total Estimated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Purchasing Strategy Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix US$ Level Level Weight Volume Date Date (weeks) Time (weeks)
Requirements
Equipment
L5.8 FISHER SCIENTIFIC
L5.8 METROHM
L5.8 METTLER TOLEDO
Equivalent is acceptable
L5.9 METERS, REFRACTOMETER B FISHER SCIENTIFIC 1 0
upon Company Approval
L5.10 METERS, RHEOMETERS (CAPILLARY) B GOTFFERT 1 0
L5.10 TINIUS OLSEN

L5.11 METERS, RHEOTENS (MELT STRENGTH) B GOTFFERT 1 0


L5.11 TINIUS OLSEN

L5.12 METERS, MELT FLOW RATE MFR B TINIUS OLSEN 1 0

L5.12 GOTFFERT
L5.13 METERS, RHEOMETERS (DMS) B TA INSTRUMENTS 1 0 SS Justification Rec'd
L6.0 MICROSCOPES
L6.1 MICROSCOPES, FTIR B BRUKER 1 0
L6.1 PERKIN ELMER

L6.1 THERMO-NICOLET

L6.2 MICROSCOPES, LIGHT B LEICA 1 0

L6.2 ZEISS

L6.3 MICROSCOPES - LOW END B


THERMO AUTOMATION Equivalent is acceptable
L6.4 MICROSCOPES, SAMPLE PREPARATION INSTRUMENTS B 1 0
SYSTEMS upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.5 B LEICA 1 0
CRYO MICROTOME upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.6 B DIATOME 1 0
DIAMOND KNIVE- RIMMING upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.7 B DIATOME 1 0
DIAMOND KNIVES - POLISHING upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.8 B LECO 1 0
MOUNTING PRESS upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.9 B STRUERS 1 0
METALLOGRAPHY - POLISHING AND GRINDING upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS Equivalent is acceptable
L6.10 B STRUERS 1 0
METALLOGRAPHY - SECTIONING upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.11 B CRESSINGTON 1 0
FINE METAL DEPOSITION upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.12 B SPI 1 0
CARBON DEPOSITION upon Company Approval
MICROSCOPY, SAMPLE PREPARATION INSTRUMENTS - Equivalent is acceptable
L6.13 B FISONS 1 0
LOW TEMP ASHING upon Company Approval

L6.14 MICROSCOPES, SCANNING ELECTRON (SEM) B FEI 1 0

L6.14 JEOL
L6.14 PHILLIPS ANALYTICAL
L6 14
L6.14 TA INSTRUMENTS
L7.0 SPECTROMETERS
Standardization -
L7.1 SPECTROMETERS , FTIR- MID IR (General Applications) B BOMEM 1 0
Category B
L7.1 NICOLET
L7.1 PERKIN ELMER
L7.2 SPECTROMETERS , INDUCTIVELY COUPLES PLASMA (ICP) B PERKIN ELMER 1 0 SS Justification Rec'd
Equivalent is acceptable
L7.3 SPECTROMETERS , MASS (HELIUM LEAK DETECTOR) B THERMO ELECTRON 1 0
upon Company Approval
L7.4 SPECTROMETERS, NEAR IR B BOMEM 1 0 SS Justification Rec'd
SPECTROMETERS, NUCLEAR MAGNETIC RESONANCE
L7.5 B BRUKER 1 0 SS Justification Rec'd
SPECTROMETER (NMR)
L7.6 SPECTROPHOTOMETERS B HACH 1 0 SS Justification Rec'd
Equivalent is acceptable
L7.7 SPECTROPHOTOMETERS, AUTOMATED B SYSTEA 1 0
upon Company Approval
L7.8 SPECTROMETERS, UV VISIBLE DIODE ARRAY B AGILENT 1 0
L7.8 PERKIN ELMER
L7.8 WATERS ALLIANCE
L8.0 TITRATORS

L8.1 TITRATORS B BRINKMANN-METROHM 1 0

L8.1 METTLER-TOLEDO
TITRATORS, WATER ANALYZERS (Karl Fisher Scientific
L8.2 B BRINKMANN-METROHM 1 0
Titrators)
L8.2 METTLER-TOLEDO
L9.0 X-RAY
L9.1 X-RAY, FLUORESCENCE (BENCH TOP) B BRUKER 1 0 SS Justification Rec'd

L9.2 X-RAY, FLUORESCENCE (PROBLEM SOLVING) B BRUKER 1 0 SS Justification Rec'd

L9.3 X-RAY, DIFFRACTION B BRUKER 1 0 SS Justification Rec'd

L10.0 MISCELLANEOUS LABORATORY EQUIPMENT

L10.1 CAST FILM ANALYZERS B OCS 1 0 SS Justification Rec'd

Equivalent is acceptable
L10.2 DIE CUTTERS B FISHER SCIENTIFIC 1 0
upon Company Approval
Equivalent is acceptable
L10.3 DRYING OVEN B FISHER SCIENTIFIC 1 0
upon Company Approval
Equivalent is acceptable
L10.4 EVAPORATOR B ORGANIMATION 1 0
upon Company Approval
Equivalent is acceptable
L10.5 HARDNESS TESTER B ROCKWELL 1 0
upon Company Approval
L10.6 HDT/VICAT TESTER B TINIUS OLSEN 1 0 SS Justification Rec'd
L10.7 HYDRAULIC PRESS B CARVER 1 0 SS Justification Rec'd

Doc. No. A554-K-PRG-PU-LIS-DOC-009 Date: 29 July 2011


(Laboratory Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Ras Tanura Integrated Project (RTIP)

Program Supply Plan


Laboratory Equipment (Pending)

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Expediting Inspection Estimated Total Estimated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Purchasing Strategy Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix US$ Level Level Weight Volume Date Date (weeks) Time (weeks)
Requirements
Equipment

L10.8 INJECTION MOLDER B TOYO 1 0

L10.9 LABORATORY AUTOCLAVE B FISHER SCIENTIFIC 1 0

L10.9 PRIORCLAVE UK
L10.10 MICRO GC B AGILENT 1 0 SS Justification Rec'd
Equivalent is acceptable
L10.11 OIL TEST CENTRIFUGE B SETA 1 0
upon Company Approval
L10.12 PURGE AND TRAP B OL CORPORATION 1 0
L10.12 TEKMAR
L10.12 TELEDYNE
Standardization -
L10.13 RECIPROCATING SHAKER B EBERBACH 1 0
Category B
L10.13 FISHER SCIENTIFIC

L10.14 TENSILE STRENGTH APPARATUS (FLEX, COMPRESSION) B INSTRON 1 0 SS Justification Rec'd

L10.15 TENSILE TESTER B INSTRON 1 0

L10.15 MTS
L10.15 UNITED (SA)
Standardization -
L10.16 WATER BATH B BOEKEL 1 0
Category B
L10.16 FISHER SCIENTIFIC

L10.16 PRECISION

Equivalent is acceptable
L10.17 WATER PURIFIER B MILLIPORE 1 0
upon Company Approval

L10.18 CLOUD POINT TESTER B METTLER 1

L10.18 BRINKMAN
L10.19 CALORIMETER B PAAR INSTRUMENT 1 0 SS Justification Rec'd
Equivalent is acceptable
L10.20 CHEMILUMINISENCE NOX B ANTECH 1 0
upon Company Approval
L10.21 ATOMIC ABSORPTION SPECTROMETER B PERKIN ELMER 1 0 SS Justification Rec'd
L10.22 ANALYTICAL FERROGRAPHY B
Equivalent is acceptable
L10.23 MOISTURE ANALYZER (GAS) B AMETEK 1 0
upon Company Approval
Equivalent is acceptable
L10.24 GLOSS MEASUREMENT B FISHER SCIENTIFIC 1 0
upon Company Approval
L10.25 PARTICLE COUNTER B
L10.26 PARTICLE SIZE ANALYZER B
L10.27 RESPIROMETER B
L10.28 TOTAL CHLORIDE ANALYZER B COSA 1 0 SS Justification Rec'd
L10.29 TOTAL SULFUR ANALYZER B HOUSTON ATLAS 1 0 SS Justification Rec'd
L10.30 TOTAL NITROGEN ANALYZER B COSA 1 0
L10 31
L10.31 VISCOMETER B BROOKFIELD 1 0 SS Justification Rec'd
Rec d
Equivalent is acceptable
L10.32 MUFLE FURNACE B FISHER SCIENTIFC 1 0
upon Company Approval
Equivalent is acceptable
L10.33 CENTRIFUGE B FISHER SCIENTIFC 1 0
upon Company Approval
Equivalent is acceptable
L10.34 REFRIGERATORS B FISHER SCIENTIFC 1 0
upon Company Approval
Equivalent is acceptable
L10.35 ENVIRONMENTAL CHAMBERS B FISHER SCIENTIFIC 1 0
upon Company Approval
L10.36 HYDROGEN GENERATORS PROTON ENERGY 1 0 SS Justification Rec'd

L10.37 RDA RHEOMETRIC 1 0 SS Justification Rec'd

L10.38 MELT INDEXER TINUS OLSEN 1 0 SS Justification Rec'd

L10.39 GLASS WASHER MIELE 1 0 SS Justification Rec'd

L10.40 NUCLEAR MASS SPECTROMETRY BRUKER 1 0 SS Justification Rec'd

L10.41 CALORIMETER PAAR INSTRUMENTS 1 0 SS Justification Rec'd

L10.42 AT-LINE ALFA FILM ANALYZER OCS 1 0

L10.43 LC-EXACT MS 1 0

L10.44 LIGHT MICROSCOPE 1 0

L10.45 FILM TAPE ANALYZER GEOTTFERT RHEOTENS 1 0

L10.46 GEL CAMERA 1 0

L10.47 PSSD EQUIPMENT 1 0

L10.48
L10 48 PURICON DUST EQUIPMENT 1 0

L10.49 CROSS POLOR MICROSCOPE NIKON 1 0

L10.50 MICROSCOPE WITH CAMERA TO COUNT BAGS 1 0

L10.51 MLSS PROBE (MIXED LIQUOR SUSPENDED SOLIDS) 1 0

L10.52 MOISTURE ANALYZER 1 0

L10.53 D-MELT 1 0

L10.54 BLACK SPEC COUNTER OCS 1 0

L10.55 MOISTURE ANALYZER (COMPUTRAC VAPOR PRO) COMPUTRAC 1 0

L10.56 DIE FOR PUNCHING COUPONS FOR DENSITY ANALYSIS 1 0

L10.57 PELLETT INSPECTION TABLE 1 0

L10.58 HE LEAK CHECK DEVICE 1 0

Doc. No. A554-K-PRG-PU-LIS-DOC-009 Date: 29 July 2011


(Laboratory Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Ras Tanura Integrated Project (RTIP)

Program Supply Plan


Laboratory Equipment (Pending)

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Expediting Inspection Estimated Total Estimated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Purchasing Strategy Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix US$ Level Level Weight Volume Date Date (weeks) Time (weeks)
Requirements
Equipment

L10.59 JACK PALLET 1 0

L10.60 MOONEY VISCOMETERS MODEL #MV2000 1 0


MITUTOYO DIGIMATIC INDICATOR (MI (MELT INDEX)
L10.61 1 0
TRAVEL

MITUTOYO DIGIMATIC OUTSIDE MICROMETER AND


L10.62 1 0
STAND

L10.63 MITUTOYO ABSOLUTE DIGIMATIC CALIPER (4 PLACE) 1 0

L10.64 MITUTOYO DIGIMATIC HEAD (5 PLACE) 1 0

L10.65 IN-SITE EQUIPMENT - not defined yet 1 0

Doc. No. A554-K-PRG-PU-LIS-DOC-009 Date: 29 July 2011


(Laboratory Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Rev. 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Automation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Expediting Inspection Estimated Total Estimated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Purchasing Strategy Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix US$ Level Level Weight Volume Date Date (weeks) Time (weeks)
Requirements
Equipment
M1.0 SYSTEMS
COMPRESSOR CONTROLS
M1.1 COMPRESSOR ANTI-SURGE CONTROL E 2 2
CORPORATION (CCC)
WOODWARD GOVERNOR
M1.1
COMPANY
M1.1 ABB AUTOMATION
M1.1 INVENSYS (TRICONEX)
SYSTEM, TURBO MACHINERY CONTROL SYSTEMS COMPRESSOR CONTROLS
M1.2 E
(GOVERNORS) CORPORATION (CCC)
M1.2 INVENSYS (TRICONEX)

M1.2 WOODWARD GOVERNOR


COMPANY
M1.2 ABB AUTOMATION
SPEED SYSTEMS, OVERSPEED PROTECTION SYSTEMS - GE ENERGY (BENTLY
M1.3 E
CRITICAL NEVADA)
M1.3 INVENSYS (TRICONEX)
M1.3 WOODWARD
ROCKWELL AUTOMATION
M1.4 SYSTEM, PROGRAMMABLE LOGIC CONTROLLER (PLC) E (ALLEN BRADLEY) PLC-5
SERIES
SIEMENS SIMATIC S7-400
M1.4 SERIES
M2.0 SOFTWARE
PROCESS AUTOMATION
M2.1 MOC SOFTWARE E
SERVICES (PAS)
M2.1 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.1
PRODUCT
HONEYWELL STANDARD
M2.1
PRODUCT
EMERSON STANDARD
M2.1
PRODUCT
YOKOGAWA STANDARD
M2.1
PRODUCT
M2.2 ALMS SOFTWARE E MATRIKON
M2.2 PAS
M2.2 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.2
PRODUCT
HONEYWELL STANDARD
M2.2
PRODUCT
EMERSON STANDARD
M2.2
PRODUCT
YOKOGAWA STANDARD
M2.2
PRODUCT
M2.3 AMS SOFTWARE E PAS
M2.3 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.3
PRODUCT
HONEYWELL STANDARD
M2.3
PRODUCT
EMERSON STANDARD
M2.3
PRODUCT
YOKOGAWA STANDARD
M2.3
PRODUCT
M2.4 OPC SOFTWARE E MATRIKON
M2.4 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.4
PRODUCT
HONEYWELL STANDARD
M2.4
PRODUCT
EMERSON STANDARD
M2.4
PRODUCT
YOKOGAWA STANDARD
M2.4
PRODUCT
M2.5 CONTROLLER PERFORMANCE MONITORING SOFTWARE E MATRIKON
M2.5 EXPERTUNE
M2.5 PAS
M2.5 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.5
PRODUCT
HONEYWELL STANDARD
M2.5
PRODUCT
EMERSON STANDARD
M2.5
PRODUCT
YOKOGAWA STANDARD
M2.5
PRODUCT
M2.6 IPCS DOCUMENTATION SOFTWARE E PAS
M2.6 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.6
PRODUCT
HONEYWELL STANDARD
M2.6
PRODUCT
EMERSON STANDARD
M2.6
PRODUCT
YOKOGAWA STANDARD
M2.6
PRODUCT
M2.7 (ADVANCED) LOOPTUNING SOFTWARE E CONTROL SOFT
M2.7 EXPERTUNE
M2.7 PAS
M2.7 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.7
PRODUCT
HONEYWELL STANDARD
M2.7
PRODUCT
EMERSON STANDARD
M2.7
PRODUCT
YOKOGAWA STANDARD
M2.7
PRODUCT
M2.8 SIMULATION SOFTWARE E CAPE VPLINK
M2.8 ABB STANDARD PRODUCT
INVENSYS STANDARD
M2.8
PRODUCT

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Laboratory Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04
Ras Tanura Integrated Project (RTIP)
Program Supply Plan
Process Automation

Project No: Owner to COMPLETE


Project Name: FEED / PMC Contractor to COMPLETE
Last Revised: EPC Contractor to COMPLETE
Classification
Special
PAVL B= Bulk Item Tag Number / Estimate 1000 Expediting Inspection Estimated Total Estimated Total Planned Inquiry Planned PO Dwg Lead Time Delivery Lead
Pkg. No. Revision Equipment Description Tag- Type Quantity Material Size Model / Design Manufacturers Purchasing Strategy Negotiator Transportation Time Level Field Need Date Special Considerations
CODE E= Suffix US$ Level Level Weight Volume Date Date (weeks) Time (weeks)
Requirements
Equipment
HONEYWELL STANDARD
M2.8
PRODUCT
EMERSON STANDARD
M2.8
PRODUCT
YOKOGAWA STANDARD
M2.8 PRODUCT
M3.0 MISCELLANEOUS
M3.1 COLOR PRINTER E HP
M3.2 LAPTOP FOR PLC/FIELDBUS/ETC. (re)configuration E HP
M3.2 DELL
M3.2 LENOVO
M3.3 FURNITURE/FURNITURE MANUFACTURER E ABB STANDARD PRODUCT
INVENSYS STANDARD
M3.3
PRODUCT
HONEYWELL STANDARD
M3.3
PRODUCT
EMERSON STANDARD
M3.3
PRODUCT
YOKOGAWA STANDARD
M3.3
PRODUCT
M3.3 CERGO
M3.3 EVANS
M3 3
M3.3 KNURR
M3.3 EVOSITE

Date: 29 July 2011


Doc. No: A554-K-PRG-PU-LIS-DOC-009 (Laboratory Equipment) Contains Confidential Information of Both Dow and Saudi Aramco Revision: 04

S-ar putea să vă placă și